Actions for WestConnex: Assurance to the Government

WestConnex: Assurance to the Government

Transport
Treasury
Premier and Cabinet
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk

This audit assesses the assurance provided to the NSW Government for the initial stages of the WestConnex project.

The audit examined the WestConnex project from concept development to the pre-tender phase for Stage 1A – M4 (Parramatta to Homebush Bay). It did not examine the merit of the project or whether it represented value-for-money.

This audit found a number of shortcomings with the governance of the WestConnex project during its early stages and makes recommendations on how to better govern the remainder of the project to minimise the risk of failure.

 

Parliamentary reference - Report number #247 - released 18 December 2014

Published

Actions for Managing Contaminated Sites

Managing Contaminated Sites

Planning
Industry
Environment
Compliance
Internal controls and governance
Management and administration
Project management
Regulation
Risk

NSW Government agencies with large landholdings need to better manage their contaminated sites.

When contaminated sites are reported to the Environmental Protection Authority (EPA) there are long delays in assessing the extent of contamination. The EPA also lacks the management controls to ensure that all significantly contaminated sites are actively monitored and key milestones for remediation are met.

 

Parliamentary reference - Report number #245 - released 10 July 2014

Published

Actions for Volume Eight 2011 Focus on Transport and Ports

Volume Eight 2011 Focus on Transport and Ports

Transport
Industry
Asset valuation
Financial reporting
Fraud
Information technology
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Workforce and capability

The report includes comments on financial audits of government agencies in the Transport and Ports sectors. The audit of corporations’ financial statements for the year ended 30 June 2011 resulted in unmodified audit opinions within the Independent Auditor’s Reports. A key recommendation from the report is that Sydney Ports Corporation should continue working with other government authorities and industry stakeholders to improve the effectiveness of program initiatives for increasing container freight movements by rail. The Corporation should review the underlying causes hindering growth in the rail mode and develop and implement strategies to address the unfavourable trend.

Published

Actions for Solar Bonus Scheme

Solar Bonus Scheme

Premier and Cabinet
Compliance
Infrastructure
Management and administration
Project management
Regulation
Risk
Service delivery

A NSW Auditor General’s Report has found that the NSW Government and its agencies grossly underestimated the cost and number of people that would install systems under the Solar Bonus Scheme.

By October 2010, the estimated cost of the Scheme, if it continued the way it was going, would have reached $3.988 billion. More than ten times the original estimate of $362 million. In response to the increased cost, the gross tariff for new applicants was reduced from 60 to 20 cents reducing the estimated cost to $1.954 billion.

It was a statutory requirement that when 50 mega watts of installed capacity was reached, the Government would review the Scheme. By the time the review was completed the installed capacity had reached 101 mega watts.

Published

Actions for Improving road safety: Young drivers

Improving road safety: Young drivers

Transport
Finance
Project management
Regulation
Service delivery

The audit concluded that the RTA’s licence testing and regulation has been generally effective in ensuring the safety of young drivers. There has been a significant reduction in crash and fatality rates involving young drivers over the last decade, more so than for drivers 26 years and older. This has coincided with the introduction by the RTA of an enhanced GLS. International and national research has demonstrated graduated licensing systems to be effective in reducing crashes and saving lives. Despite these improvements, young drivers are more likely to be involved in fatal crashes than other drivers.

 

Parliamentary reference - Report number #217 - released 19 October 2011

Published

Actions for Prequalification Scheme: Performance and Management Services

Prequalification Scheme: Performance and Management Services

Premier and Cabinet
Finance
Compliance
Internal controls and governance
Management and administration
Regulation
Risk
Workforce and capability

There have been tangible improvements in the time it takes NSW Government agencies to engage consultants through the Government’s Prequalification Scheme. The Scheme was introduced in February 2008 to improve agencies’ procurement of consultants. More than 300 service providers have been prequalified and over $300 million worth of consultancy services have been provided. Ideally agencies should know what assignments each consultant has won, for what services, what their rates are and how well they have performed. Agencies should then be free to contact other agencies before engaging a consultant.

 

Parliamentary reference - Report number #216 - released 28 September 2011

Published

Actions for Improving Road Safety: Speed Cameras

Improving Road Safety: Speed Cameras

Transport
Project management
Regulation

We found that fixed speed cameras were generally located in areas with high road safety risk. Likewise, safety cameras that enforced speed limits were initially placed at high risk sites. However as all safety cameras will now enforce speed, RTA no longer uses evidence of a speeding problem to select these sites. Overall, total crashes and injuries each fell 26 per cent, and fatalities fell by more than two-thirds, in the three years after the installation of fixed speed camera. Long term trends show that these reductions have been maintained, the average number of speeding fines per fixed and safety cameras declines over time and fixed and safety speed cameras were located in areas with high road safety risk.

 

Parliamentary reference - Report number #215 - released 27 July 2011

Published

Actions for Condition of State Roads

Condition of State Roads

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Service delivery

The Roads and Traffic Authority (RTA) has improved the overall surface condition of State Roads in the last decade. Country road surfaces are now generally much better. Ride quality has improved and cracking has been reduced. The RTA has also achieved a substantial reduction in the number of structurally deficient bridges over the same period. 

Despite a significant increase in the State’s contribution to maintenance since 1999-2000, the RTA has deferred road rebuilding projects. The RTA is rebuilding at less than half its long term target, and has not met this target at any time this decade. The RTA has not identified how it will address deferred rebuilding, although it advises it is developing a new road network management plan which will address this.

 

Parliamentary reference - Report number #157 - released 16 August 2006

Published

Actions for The Cross City Tunnel Project

The Cross City Tunnel Project

Transport
Treasury
Premier and Cabinet
Planning
Environment
Infrastructure
Management and administration
Procurement
Project management
Risk

In our opinion the Government’s ‘no net cost to government’ requirement was a legitimate (but not the only possible) basis for the tunnel bid process. The Government was entitled to decide that tunnel users meet the tunnel costs. Structuring the bid process on the basis of an upfront reimbursement of costs incurred (or to be incurred) by the Roads and Traffic Authority (RTA) was therefore appropriate.

In our opinion, however, the Government, Treasury and the RTA did not sufficiently consider the implications of an upfront payment involving more than simple project cost reimbursement (i.e. the ‘Business Consideration Fee’ component). In addition, the RTA was wrong to change the toll escalation factor late in 2002 to compensate the tunnel operator, Cross City Motorway Pty Ltd, for additional costs.

 

Parliamentary reference - Report number #152 - released 31 May 2006