The Auditor‑General for New South Wales, Margaret Crawford, released a report today examining procurement management in Local Government.

The audit assessed the effectiveness of procurement management practices in six councils. All six councils had procurement management policies that were consistent with legislative requirements, but the audit found compliance gaps in some councils. The audit also identified opportunities for councils to address risks to transparency and accountability, and to ensure value for money is achieved when undertaking procurement.

The Auditor‑General recommended that the Department of Planning, Industry and Environment review the Local Government (General) Regulation 2005 and publish updated and more comprehensive guidance on procurement management for the Local Government sector. The report also generated insights for the Local Government sector on opportunities to strengthen procurement practices.

Effective procurement is important in ensuring councils achieve their objectives, demonstrate value for money and deliver benefits to the community when purchasing goods and services. Procurement also comes with risks and challenges in ensuring the purchased goods and services deliver to expectations. The risks of fraud and conflicts of interest also need to be mitigated.

The legislative requirements related to procurement in the Local Government sector are focused on sourcing and assessing tender offers. These requirements are included in the Local Government Act 1993 (the Act), the Local Government Amendment Act 2019 (the Amendment), the Local Government (General) Regulation 2005 (the Regulation), the Tendering Guidelines for NSW Local Government 2009 (the Tendering Guidelines), the Government Information (Public Access) Act 2009 (the GIPA Act) and the State Records Act 1998.

General requirements and guidance relevant to councils are also available in the Model Code of Conduct for Local Councils in NSW 2018 (the Model Code), the NSW Government Procurement Policy Framework 2019 and in publications by the Independent Commission Against Corruption (ICAC).1

Individual councils have developed their own procurement policies and procedures to expand on the legislative requirements. Understandably, these vary to reflect each council’s location, size and procurement needs. Nevertheless, the general principles of effective procurement management (such as transparency and accountability) and risk-mitigating practices (such as segregation of duties and the provision of training) are relevant to all councils.

The Audit Office of New South Wales Report on Local Government 2018 provided a sector-wide summary of aspects of procurement management in Local Government (see Section 2.1 of this report). This audit builds on this state-wide view by examining in detail the effectiveness of procurement management practices in six councils. This report also provides insights on opportunities to strengthen procurement management in the sector.

The selected councils for this audit were Cumberland City Council, Georges River Council, Lockhart Shire Council, Tweed Shire Council, Waverley Council and Wollongong City Council. They were selected to provide a mix of councils of different geographical classifications, sizes, priorities and levels of resourcing.

Conclusion

All six councils had procurement management policies and procedures that were consistent with the legislative requirements for sourcing and assessing tender offers. Their policies and procedures also extended beyond the legislative requirements to cover key aspects of procurement, from planning to completion. In terms of how these policies were applied in practice, the six councils were mostly compliant with legislative requirements and their own policies and procedures, but we found some gaps in compliance in some councils and made specific recommendations on closing these gaps.

There were also opportunities for councils to improve procurement management to mitigate risks to transparency, accountability and value for money. Common gaps in the councils’ procurement management approaches included not requiring procurement needs to be documented at the planning stage, not providing adequate staff training on procurement, not requiring procurement outcomes to be evaluated, and having discrepancies in contract values between contract registers and annual reports. These gaps expose risks to councils’ ability to demonstrate their procurements are justified, well managed, delivering to expectations, and achieving value for money. Chapter three of this report provides insights for the audited councils and the Local Government sector on ways to address these risks

Recommendations

  1. By June 2022, the Department of Planning, Industry and Environment should:
    1. publish comprehensive and updated guidance on effective procurement practices – including electronic tender submissions and procurements below the tender threshold
    2. review and update the Local Government (General) Regulation 2005 to reflect the increasing use of electronic tender submissions rather than paper copies.
  2. By December 2021, the six audited councils should consider the opportunities to improve procurement management in line with the improvement areas outlined in chapter three of this report.
  3. Cumberland City Council should immediately:
    1. ensure contract values are consistent between the contract register and the annual report
    2. introduce procedures to ensure supplier performance reviews are conducted as per the council’s policy
  4. Georges River Council should immediately:
    1. ensure contract values are consistent between the contract register and the annual report
    2. introduce procedures to ensure all the steps up to the awarding of a contract are documented as per the council’s policy
    3. introduce procedures to ensure outcome evaluations are conducted as per the council’s policy.
  5. Lockhart Shire Council should immediately:
    1. include additional information in the council’s contract register to ensure compliance with Section 29(b), (f), (g), (h) and (i) of the GIPA Act
    2. ensure contract values are consistent between the contract register and the annual report.
  6. Waverley Council should immediately ensure contracts are disclosed in the annual report as per Section 217(1)(a2) of the Regulation.

(1) The relevant ICAC publications include: Corruption Risks in NSW Government Procurement – The Management Challenge (2011), Corruption Risks in NSW Government Procurement – Suppliers’ Perception of Corruption (2011) and Corruption Risks in NSW Government Procurement – Recommendations to Government (2011).

While all six councils had procurement policies in place and were generally compliant with legislative requirements, this report has identified common gaps in processes and practices that expose risks to transparency, accountability and value for money.

This section discusses how councils can mitigate risks and ensure the best outcomes are achieved from their procurements.

Documented justification of procurement needs

The ICAC notes that determining what goods and services an agency requires is the first step of procurement, and the scope for corruption in how need is determined is significant. Without documenting how procurement needs have been justified, councils cannot demonstrate that they fulfill business needs, nor how the procurements may link to the councils’ strategic plans to deliver to the community.

This audit found that none of the six councils’ policies required them to document justification of procurement needs, and none did so consistently in practice. Councils can address this gap by building into their procurement planning process a requirement for staff to document the justification of procurement needs. For higher value procurements, this could be extended to include analysis of options, an assessment of risks and defining intended outcomes. Similarly, clearly establishing and documenting how relevant procurements relate to a council’s community strategic plans or operational plans helps ensure transparency.

Although a formal business case may not be required for many procurements (for example, low-value procurements or routine replacements), some form of documented justification for the expenditure should still be kept on record to demonstrate that the procurement relates to business purposes and is needed.

Segregation of duties

Segregation of duties is an effective control for reducing risks of error, fraud and corruption in procurement. It works on the principle that one person should not have end-to-end control of a procurement. Effective segregation of duties also often involves managerial or independent oversight that is built into the process. Four of the audited councils (Cumberland City Council, Georges River Council, Lockhart Shire Council and Wollongong City Council) appropriately addressed segregation of duties in their procurement frameworks. For example:

  • All procurements in Cumberland City Council required a delegated officer’s approval before commencing, and the requisitioning department is responsible for ensuring the completion of the goods, works or services associated with each contract. For contracts over $50,000, a specific ‘Authority to Procure’ form had to be completed by the requesting staff, signed by an approver and then forwarded to the procurement team.

  • Reflecting its small size, all procurements in Lockhart Shire Council were managed by one senior staff member. Nevertheless, this staff member had to bring contract management plans to the rest of the Executive Leadership Team for review and discussion, with large contracts such as those above the tender threshold referred to Council for approval.

The ICAC notes that segregation of duties helps to control discretion, which has particular risk implications for some types of procurement.This includes those involving low-value and high-volume transactions, restricted tenders, long-standing procurements and ‘pet projects’ (projects advocated by individual staff members). In cases where corruption risks are low, ICAC notes that monitoring staff’s involvement in procurement may be a cost-effective alternative to total segregation of duties.

Assessment of supplier performance

Councils need to monitor and assess supplier performance to ensure suppliers deliver the goods and services as agreed. The audit found that all six councils consistently monitored progress in capital works and for externally funded projects. Contract monitoring in these cases included ensuring timelines, funding, and legislative requirements were met. This is positive, as capital works made up the bulk of procurements (in terms of volume) in all of the audited councils.

That said, in all six councils, the level of scrutiny was lower for other types of procurements, and there is scope for improvement. For instance, the approach to monitoring capital works or externally funded projects could be replicated across other procurements of a similar nature and value. Conducting assessments and keeping records of supplier performance on all procurements does not need to be onerous, but instead provides useful information to inform future decision-making—including by helping ensure supplier pricing remains competitive, and avoiding re-engaging underperforming suppliers.

The NSW Government Procurement Policy Framework requires that NSW Government agencies establish systems and processes jointly with the suppliers to ensure compliance with contract terms and performance requirements. It also advises that agencies should drive continuous improvement and encourage innovation in coordination with suppliers and key stakeholders.

Centralised contract register

Centrally registering a contract provides improved transparency of procurement activities and facilitates monitoring and compliance checks. While councils are already required to maintain a contract register for all contracts above the reporting threshold (as per the GIPA Act), given the threshold is set at a relatively high benchmark ($150,000), there is merit in councils extending the practice to procurements below the reporting threshold. A central and comprehensive register of contracts helps avoid duplication of procurements and re-contracting of underperforming suppliers.

Three of the audited councils (Georges River Council, Tweed Shire Council and Wollongong City Council) had contract register policies that applied to procurements below the reporting threshold during the audited period. For example, Georges River Council required contracts valued at $10,000 or above to be registered with the procurement team, and Tweed Shire Council had a threshold of $50,000.

Evaluation of community outcomes and value for money

Councils may be progressing procurements to fulfill their strategic and business plans, or using them to fulfill commitments to the community. In these instances, outcomes evaluation is an important way to demonstrate to the community that the intended benefits and value for money have been delivered.

Five of the six audited councils did not require evaluations of community outcomes and value for money. While Georges River Council required contracts valued at $50,000 or more to be monitored, evaluated and reported on at least annually throughout the contract and also at its conclusion, in the procurements we examined the only ‘outcome evaluations’ that the council had conducted were community surveys that did not refer to individual procurements. Councils can miss opportunities to understand the impact of their work on the local community if evaluations of procurement outcomes are not completed. Evaluation findings are also valuable in guiding future resource allocation decisions.

Value for money in the procurement of goods and services is more than just having the specified goods delivered or services carried out. The NSW Government Procurement Policy Framework requires that state government agencies track and report benefits to demonstrate how value for money is being delivered. The framework notes that value for money is not necessarily the lowest price, nor the highest quality good or service, but requires a balanced assessment of a range of financial and non-financial factors, such as: quality, cost, fitness for purpose, capability, capacity, risk, total cost of ownership or other relevant factors.

Procurement training

Effective procurement management relies on the capability of staff involved in various stages of the process. Guidance can be provided through training, which is an important element of any procurement management framework. It ensures that staff members are aware of the councils' policies and procedures. If structured appropriately and provided in a timely manner, training can help to standardise practices, ensure compliance, reduce chances of error, and mitigate risks of fraud or corruption.

The ICAC notes that effective procurement management depends on the competence of staff undertaking procurements and the competence of those who oversee procurement activities. As the public sector is characterised by varying levels of procurement expertise, the ICAC notes that the sector would benefit from a structured approach to training and the application of minimum standards.3

At the time of this audit, only Wollongong City Council addressed staff training requirements in its procurement management framework. Exhibit 8 details its approach.

Exhibit 8: Wollongong City Council's approach to training
  • Wollongong City Council has a suite of procurement training available for staff, administered by a dedicated staff member who also monitors attendance and training needs
  • Staff must complete training before they can take part in a procurement or be a member of a tender assessment panel, and the council keeps a list of all accredited staff members.
  • Staff cannot access procurement files on the council's electronic records management system until they have received training and have been approved for access by the trainer.
  • Staff must be trained before they can receive a financial delegation.

Source: Audit Office of New South Wales analysis of Wollongong City Council's procurement policies and procedures 2020.
 

Two of the audited councils have now also introduced procurement training:

  • Georges River Council implemented online training, which is mandatory for new staff and serves as refresher training for existing staff. The council also provides in-person training for selected staff (covering contract management, contract specification writing and contractor relationship management) and has developed quick reference cards for all staff to increase awareness of the council's procurement processes.
  • Tweed Shire Council implemented mandatory online training for all staff members. The training covers the council's procurement policy and protocol as well as relevant legislation. It is linked to relevant council documents such as the Procurement Toolkit on the council's intranet, and includes a quiz for which training participants must score at least 80 per cent to have the training marked as completed.
(2) ICAC (2011) Corruption Risks in NSW Government Procurement – The Management Challenge.
(3) ICAC (2011) Corruption Risks in NSW Government Procurement – Recommendations to Government.

Appendix one – Responses from councils and the Department of Planning, Industry and Environment

Appendix two – Councils’ procurement contracts

Appendix three – About the audit

Appendix four – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #345 - released 17 December 2020

Published

Actions for Transport 2020

Transport 2020

Transport
Asset valuation
Cyber security
Financial reporting
Information technology
Infrastructure
Project management

1. Financial Reporting

Audit opinion Unmodified audit opinions issued for the financial statements of all Transport cluster entities.
Quality and timeliness of financial reporting All cluster agencies met the statutory deadlines for completing the early close and submitting the financial statements.

Transport cluster agencies continued to experience some challenges with accounting for land and infrastructure assets. The former Roads and Maritime Services and Sydney Metro recorded prior period corrections to property, plant and equipment balances.
Impact of COVID-19 on passenger revenue and patronage Total patronage and revenue for public transport decreased by approximately 18 per cent in 2019–20 due to COVID-19.

The Transport cluster received additional funding from NSW Treasury during the year to support the reduced revenue and additional costs incurred such as cleaning on all modes of public transport and additional staff to manage physical distancing.
Completion of the CBD and South East Light Rail The CBD and South East Light Rail project was completed and commenced operations in this financial year. At 30 June 2020, the total cost of the project related to the CBD and South East Light Rail was $3.3 billion. Of this total cost, $2.6 billion was recorded as assets, whilst $700 million was expensed.

2. Audit Observations

Internal control While internal controls issues raised in management letters in the Transport cluster have decreased compared to the prior year, control weaknesses continue to exist in access security for financial systems. We identified 56 management letter findings across the cluster and 43 per cent of all issues were repeat issues. The majority of the repeat issues relate to information technology controls around user access management.

There were three high risk issues identified - two related to financial reporting of assets and one for implementation of TAHE (see below).
Agency responses to emergency events Transport for NSW established the COVID-19 Taskforce in March 2020 to take responsibility for the overall response of planning and coordination for the Transport cluster. It also implemented the COVIDSafe Transport Plan which incorporates guidance on physical distancing, increasing services to support social distancing and cleaning.
RailCorp transition to TAHE On 1 July 2020, RailCorp was renamed Transport Asset Holding Entity of New South Wales (TAHE) and converted to a for-profit statutory State-Owned Corporation. TAHE is a commercial for-profit Public Trading Entity with the intent to provide a commercial return to its shareholders.

A plan was established by NSW Treasury to transition RailCorp to TAHE which covered the period 1 July 2015 to 1 July 2019. A large portion of the planned arrangements were not implemented by 1 July 2020. As at the time of this report, the TAHE operating model, Statement of Corporate Intent (SCI) and other key plans and commercial agreements are not finalised. The State Owned Corporations Act 1989 generally requires finalisation of an SCI three months after the commencement of each financial year. However, under the Transport Administration Act 1988, TAHE received an extension from the voting shareholders, the Treasurer and Minister for Finance and Small Business, to submit its first SCI by 31 December 2020. In accordance with the original plan, interim commercial access arrangements were supposed to be in place with RailCorp prior to commencement of TAHE.

Under the transitional arrangements, TAHE is continuing to operate in accordance with the asset and safety management plans of RailCorp. The final operating model is expected to include considerations of safety, operational, financial and fiscal risks. This should include a consideration of the potential conflicting objectives of a commercial return, and maintenance and safety measures.

This matter has been included as a high risk finding in our management letter due to the significance of the financial reporting impacts and business risks for TAHE.

Recommendation: TAHE management should:
  • establish an operating model in line with the original intent of a commercial return
  • finalise commercial agreements with the public rail operators
  • confirm forecast financial information to assess valuation of TAHE infrastructure
  • finalise asset and safety management plans.

Resolution of the above matters are critical as they may significantly impact the financial reporting arrangements for TAHE for 2020–21, in particular, accounting policies adopted as well as measurement principles of its significant infrastructure asset base.

Completeness and accuracy of contracts registers Across the Transport cluster, contracts and agreements are maintained by the transport agencies using disparate registers.

Recommendation (repeat): Transport agencies should continue to implement a process to centrally capture all contracts and agreements entered. This will ensure:
  • agencies are fully aware of contractual and other obligations
  • appropriate assessment of financial reporting implications
  • ongoing assessments of accounting standards, in particular AASB 16 ‘Leases’, AASB 15 'Revenue from Contract with Customers', AASB 1058 'Income of Not-for-Profit Entities' and new accounting standard AASB 1059 'Service Concession Arrangements: Grantors' are accurate and complete.

 

This report provides parliament and other users of the Transport cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations
  • the impact of emergencies and the pandemic.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Transport cluster for 2020, including any financial implications from the recent emergency events.

Section highlights

  • Total patronage and revenue for public transport decreased by approximately 18 per cent in 2019–20 due to COVID-19.
  • Unqualified audit opinions were issued on all Transport agencies' financial statements.
  • Transport cluster agencies continued to experience challenges with accounting of land and infrastructure assets.

 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our:

  • observations and insights from our financial statement audits of agencies in the Transport cluster
  • assessment of how well cluster agencies adapted their systems, policies and procedures, and governance arrangements in response to recent emergencies.

Section highlights

  • While there was a decrease in findings on internal controls across the Transport cluster, 43 per cent of all issues were repeat issues. Many repeat issues related to information technology controls around user access management.
  • RailCorp transitioned to TAHE on 1 July 2020. TAHE's operating model and commercial arrangements with public rail operators has not been finalised despite government original plans to be operating from 1 July 2019. TAHE management should finalise its operating model and commercial agreements with public rail operators as they may significantly impact the financial reporting arrangements for TAHE for 2020–21.
  • Completeness and accuracy of contracts registers remains an ongoing issue for the Transport cluster.

Appendix one – List of 2020 recommendations

Appendix two – Status of 2019, 2018 and 2017 recommendations

Appendix three – Management letter findings

Appendix four – Financial data

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Internal controls and governance 2020

Internal controls and governance 2020

Education
Environment
Community Services
Finance
Health
Industry
Justice
Premier and Cabinet
Transport
Treasury
Compliance
Cyber security
Information technology
Internal controls and governance
Management and administration
Procurement

The Auditor-General for New South Wales, Margaret Crawford today released her report on the findings and recommendations from the 2019–20 financial audits that relate to internal controls and governance at 40 of the largest agencies in the NSW public sector.

The bushfire and flood emergencies and the COVID‑19 pandemic continue to have a significant impact on the people and public sector of New South Wales. The scale of the government response to these events has been significant. The report focuses on the effectiveness of internal controls and governance processes, including relevant agencies’ response to the emergencies. In particular, the report focuses on:

  • financial and information technology controls
  • business continuity and disaster recovery planning arrangements
  • procurement, including emergency procurement
  • delegations that support timely and effective decision-making.

Due to the ongoing impact of COVID‑19 agencies have not yet returned to a business‑as‑usual environment. ‘Agencies will need to assess their response to the recent emergencies and update their business continuity, disaster recovery and other business resilience frameworks to reflect the lessons learnt from these events’ the Auditor-General said.

The report noted that special procurement provisions were put in place to allow agencies to better respond to the COVID-19 pandemic. The Auditor-General recommended agencies update their procurement policies to reflect the current requirements of the NSW Procurement Framework and the emergency procurement requirements.

Read the PDF report

This report analyses the internal controls and governance of 40 of the largest agencies in the NSW public sector for the year ended 30 June 2020. These 40 agencies constitute an estimated 85 per cent of total expenditure for all NSW public sector agencies.

1. Internal control trends
New, repeat and high risk findings

Internal control deficiencies increased by 13 per cent compared to last year. This is predominately due to a seven per cent increase in new internal control deficiencies and 24 per cent increase in repeat internal control deficiencies. There were ten high risk findings compared to four last year.

The recent emergencies have consumed agency time and resources and may have contributed to the increase in internal control deficiencies, particularly repeat deficiencies.

Agencies should:

  • prioritise addressing high-risk findings
  • address repeat internal control deficiencies by re-setting action plans and timeframes and monitoring the implementation status of recommendations.
Common findings

A number of findings remain common across multiple agencies over the last four years, including:

  • out of date or missing policies to guide appropriate decisions
  • poor record keeping and document retention
  • incomplete or inaccurate centralised registers or gaps in these registers.
2. Information technology controls
IT general controls

We found deficiencies in information security controls over key financial systems including:

  • user access administration deficiencies relating to inadequate oversight of the granting, review and removal of user access at 53 per cent of agencies
  • privileged users were not appropriately monitored at 43 per cent of agencies
  • deficient password controls that did not align to the agency's own password policies at 25 per cent of agencies.

The deficiencies above increase the risk of non-compliance with the NSW Cyber Security Policy, which requires agencies to have processes in place to manage user access, including privileged user access to sensitive information or systems and remove that access once it is not required or employment is terminated.

3. Business continuity and disaster recovery planning
Assessing risks to business continuity and Scenario testing

The response to the recent emergencies and the COVID-19 pandemic has encompassed a wide range of activities, including policy setting, on-going service delivery, safety and availability of staff, availability of IT and other systems and financial management. Agencies were required to activate their business continuity plans in response, and with the continued impact of COVID-19 have not yet returned to a business-as-usual environment.

Our audits focused on the preparedness of agency business continuity and disaster recovery planning arrangements prior to the onset of the COVID-19 pandemic.

We identified deficiencies in agency business continuity and disaster recovery planning arrangements. Twenty-three per cent of agencies had not conducted a business impact analysis (BIA) to identify critical business functions and determine business continuity priorities. Agencies can also improve the content of their BIA. For example, ten per cent of agencies' BIAs did not include recovery time objectives and six per cent of agencies did not identify key IT systems that support critical business functions. Scenario testing improves the effectiveness with which a live crisis is handled, but 40 per cent of agencies had not conducted a business continuity scenario testing exercise in the period from 1 January 2019 to 31 December 2019. There were also opportunities to improve the effectiveness of scenario testing exercises by:

  • involving key dependent or inter-dependent third parties who support or deliver critical business functions
  • testing one or more high impact scenarios identified in their business continuity plan
  • preparing a formalpost-exercise report documenting the outcome of their scenario testing.

Agencies have responded to the recent emergencies but addressing deficiencies will ensure agencies have adequate safeguards in their processes to again respond in the future, if required.

During 2020–21 we plan to conduct a performance audit on 'Business continuity and disaster recovery planning'. This audit will consider the effectiveness of agency business continuity planning arrangements to maintain business continuity through the recent emergencies and/or COVID-19 pandemic and return to a business-as-usual environment. We also plan to conduct a performance audit on whole-of-government 'Coordination of emergency responses'.

Responding to disruptions

We found agencies' governance functions could have been better informed about responses to disruptive incidents that had activated a business continuity or disaster recovery response between 1 January 2019 to 31 December 2019. For instance:

in 89 per cent of instances where a business continuity response was activated, a post-incident review had been performed. In 82 per cent of these instances, the outcomes were reported to a relevant governance or executive management committee

in 95 per cent of instances where a disaster recovery response was activated, a post incident review had been performed. In 86 per cent of these instances, the outcomes were reported to a relevant governance committee or executive management committee.

Examples of recorded incidents included extensive air quality issues and power outages due to bushfires, system and network outages, and infected and hijacked servers.

Agencies should assess their response to the recent emergencies and the COVID-19 pandemic and update business continuity, disaster recovery and other business resilience frameworks to incorporate lessons learned. Agencies should report to those charged with governance on the results and planned actions.

Management review and oversight Eighty-two per cent and 86 per cent of agencies report to their audit and risk committees (ARC) on their business continuity and disaster recovery planning arrangements, respectively. Only 18 per cent and five per cent of ARCs are briefed on the results of respective scenario testing. Briefing ARCs on the results of scenario testing exercises helps inform their decisions about whether sound and effective business continuity and disaster recovery arrangements have been established.
4. Procurement, including emergency procurement
Policy framework

Agency procurement policies did not capture the requirements of several key NSW Procurement Board Directions (the Directions), increasing the risk of non-compliance with the Directions. We noted: 

  • 67 per cent of agencies did specify that procurement above $650,000 must be open to market unless exempt or procured through an existing Whole of Government Scheme or contract
  • 36 per cent of agencies did specify that procurements above $500,000 payable in foreign currencies must be hedged
  • 69 per cent of agencies' policies did specify that the agency head or cluster CFO must authorise the engagement of consultants where the engagement of the supplier does not comply with the standard commercial framework.

Recommendation: Agencies should review their procurement policies and guidelines to ensure they capture the key requirements of the NSW Government Procurement Policy Framework, including NSW Procurement Board Directions.

Managing contracts

Eighty-eight per cent of agencies maintain a central contract register to record all details of contracts above $150,000, which is a requirement of GIPA legislation. Of the agencies that maintained registers, 13 per cent did not capture all contracts and eight per cent did not include all relevant contract details.

Sixteen per cent of agencies did not periodically review their contract register. Timely review increases compliance with GIPA legislation, and enhances the effectiveness with which procurement business units monitor contract end dates, contract extensions and commence new procurement.

Training and support

Ninety-three per cent of agencies provide training to staff involved in procurement processes, and a further 77 per cent of agencies provide this training on an on-going basis. Of the seven per cent of agencies that had not provided training to staff, we noted gaps in aspects of their procurement activity, including:

  • not conducting value for money assessments prior to renewing or extending the contract with their existing supplier
  • not obtaining approval from a delegated authority to commence the procurement process
  • procurement documentation not specifying certain key details such as the conditions for participation including any financial guarantees and dates for the delivery of goods or supply of services.

Training on procurement activities ensures there is effective management of procurement processes to support operational requirements, and compliance with procurement directions.

Procurement activities While agencies had implemented controls for tender activities above $650,000, 43 per cent of unaccredited agencies did not comply with the NSW Procurement Policy Framework because they had not had their procurement endorsed by an accredited agency within the cluster or by NSW Procurement. This endorsement aims to ensure the procurement is properly planned to deliver a value for money outcome before it commences.
Emergency procurement

As at 30 June 2020, agencies within the scope of this report reported conducting 32,239 emergency procurements with a total contract value of $316,908,485. Emergency procurement activities included the purchase of COVID-19 cleaning and hygiene supplies.

The government, through NSW Procurement released the 'COVID-19 Emergency procurement procedure', which relaxed procurement requirements to allow agencies to make COVID-19 emergency procurements. Our review against the emergency procurement measures found most agencies complied with requirements. For example:

  • 95 per cent of agencies documented an assessment of the need for the emergency procurement for the good and/or service
  • 86 per cent of agencies obtained authorisation of the emergency procurement by the agency head or the nominated employee under Public Works and Procurement Regulation 2019
  • 76 per cent of agencies reported the emergency procurement to the NSW Procurement Board.

Complying with the procedure helps to ensure government resources are being efficiently, effectively, economically and in accordance with the law.

Recommendation: Agency procurement frameworks should be reviewed and updated so they can respond effectively to emergency situations that may arise in the future. This includes:

  • updating procurement policies and guidelines to define an emergency situation, specify who can approve emergency procurement and capture other key requirements
  • using standard templates and documentation to prompt users to capture key requirements, such as needs analysis, supplier selection criteria, price assessment criteria, licence and insurance checks
  • having processes for reporting on emergency procurements to those charged with governance and NSW Procurement.
5. Delegations
Instruments of delegation

We found that agencies have established financial and human resources delegations, but some had not revisited their delegation manuals following the legislative and machinery of government changes. For those agencies impacted by machinery of government changes we noted:

  • 16 per cent of agencies had not updated their financial delegations to reflect the changes
  • 16 per cent of agencies did not update their human resources delegations to reflect the changes.

Delegations manuals are not always complete; 16 per cent of agencies had no delegation for writing off bad debts and 26 per cent of agencies had no delegation for writing off capital assets.

Recommendation: Agencies should ensure their financial and human resources delegation manuals contain regular set review dates and are updated to reflect the Government Sector Finance Act 2018, machinery of government changes and their current organisational structure and roles and responsibilities.

Compliance with delegations

Agencies did not understand or correctly apply the requirements of the Government Sector Finance Act 2018 (GSF Act), resulting in non-compliance with the Act. We found that 18 per cent of agencies spent deemed appropriations without obtaining an authorised delegation from the relevant Minister(s), as required by sections 4.6(1) and 5.5(3) of the GSF Act.

Further detail on this issue will be included in our Auditor-General's Reports to Parliament on Central Agencies, Education, Health and Stronger Communities, which will be tabled throughout December 2020.

Recommendation: Agencies should review financial and human resources delegations to ensure they capture all key functions of laws and regulations, and clearly specify the relevant power or function being conferred on the officer.

6. Status of 2019 recommendations
Progress implementing last year's recommendations

Recommendations were made last year to improve transparency over reporting on gifts and benefits and improve the visibility management and those charged with governance had over actions taken to address conflicts of interest that may arise. This year, we continue to note:

  • 38 per cent of agencies have not updated their gifts and benefits register to include all the key fields required under the minimum standards set by the Public Service Commission
  • 56 per cent of agencies have not provided training to staff and 63 per cent of agencies have not implemented an annual attestation process for senior management
  • 97 per cent of agencies have not published their gifts and benefits register on their website and 41 per cent of agencies are not reporting on trends in the gifts and benefits register to those charged with governance.

While we acknowledge the significance of the recent emergencies, which have consumed agency time and resources, we note limited progress has been made implementing these recommendations. Further detail on the status of implementing all recommendations is in Appendix 2.

Recommendation: Agencies should re-visit the recommendations made in last year's report on internal controls and governance and action these recommendations.

Internal controls are processes, policies and procedures that help agencies to:

  • operate effectively and efficiently
  • produce reliable financial reports
  • comply with laws and regulations
  • support ethical government.

This chapter outlines the overall trends for agency controls and governance issues, including the number of audit findings, the degree of risk those deficiencies pose to the agency, and a summary of the most common deficiencies we found across agencies. The rest of this report presents this year’s controls and governance findings in more detail.

Section highlights

We identified ten high risk findings, compared to four last year with two findings repeated from the previous year. There was an overall increase of 13 per cent in the number of internal control deficiencies compared to last year due to a seven per cent increase in new internal control deficiencies, and a 24 per cent increase in repeat internal control deficiencies. The recent emergencies have consumed agency time and resources and may have contributed to the increase in internal control deficiencies, particularly repeat deficiencies.

We identified a number of findings that remain common across multiple agencies over the last four years. Some of these findings related to areas that are fundamental to good internal control environments and effective organisational governance. Examples include:

  • out of date or missing policies to guide appropriate decisions
  • poor record keeping and document retention
  • incomplete or inaccurate centralised registers, or gaps in these registers.

Policies, procedures and internal controls should be properly designed, be appropriate for the current organisational structure and its business activities, and work effectively.

This chapter outlines our audit observations, conclusions and recommendations, arising from our review of agency controls to manage key financial systems.

Section highlights

Government agencies’ financial reporting is heavily reliant on information technology (IT). We continue to see a high number of deficiencies related to IT general controls, particularly those related to user access administration. These controls are key in adequately protecting IT systems from inappropriate access and misuse.

IT is also important to the delivery of agency services. These systems often provide the data to help monitor the efficiency and effectiveness of agency processes and services they deliver. Our financial audits do not review all agency IT systems. For example, IT systems used to support agency service delivery are generally outside the scope of our financial audit. However, agencies should also consider the relevance of our findings to these systems.

Agencies need to continue to focus on assessing the risks of inappropriate access and misuse and the implementation of controls to adequately protect their systems, focussing on the processes in place to grant, remove and monitor user access, particularly privileged user access.

 

This chapter outlines our audit observations, conclusions and recommendations, arising from our review of agency business continuity and disaster recovery planning arrangements.

Section highlights

We identified deficiencies in agency business continuity and disaster recovery planning arrangements and opportunities for agencies to enhance their business continuity management and disaster recovery planning arrangements. This will better prepare them to respond to a disruption to their critical functions, resulting from an emergency or other serious event. Twenty-three per cent of agencies had not conducted a business impact analysis (BIA) to identify critical business functions and determine business continuity priorities and 40 per cent of agencies had not conducted a business continuity scenario testing exercise in the period from 1 January 2019 to 31 December 2019. Scenario testing improves the effectiveness with which a live crisis is handled.

This section focusses on the preparedness of agency business continuity and disaster recovery planning arrangements prior to the onset of the COVID-19 pandemic. While agencies have responded to the recent emergencies, proactively addressing deficiencies will ensure agencies have adequate safeguards in their processes to again respond in the future, if required.

During 2020–21 we plan to conduct a performance audit on 'Business continuity and disaster recovery planning'. This audit will consider the effectiveness of agency business continuity planning arrangements to maintain business continuity through the recent emergencies and/or COVID-19 pandemic and return to a business-as-usual environment. We also plan to conduct a performance audit on whole-of-government 'Coordination of emergency responses'.

 

This chapter outlines our audit observations, conclusions and recommendations, arising from our review of procurement agency procurement policies and procurement activity.

Section highlights

We found agencies have procurement policies in place to manage procurement activity, but the content of these policies was not sufficiently detailed to ensure compliance with NSW Procurement Board Directions (the Directions). The Directions aim to ensure procurement activity achieves value for money and meets the principles of probity and fairness.

Agencies have generally implemented controls over their procurement process. In relation to emergency procurement activity, agencies reported conducting 32,239 emergency procurements with a total contract value of $316,908,485 up to 30 June 2020. Our review of emergency procurement activity conducted during 2019–20 identified areas where some agencies did not fully comply with the 'COVID-19 Emergency procurement procedure'.

We also found not all agencies are maintaining complete and accurate contract registers. This not only increases the risk of non-compliance with GIPA legislation, but also limits the effectiveness of procurement business units to monitor contract end dates, contract extensions and commence new procurement in a timely manner. We noted instances where agencies renewed or extended contracts without going through a competitive tender process during the year.

 

This chapter outlines our audit observations, conclusions and recommendations, arising from our review of agency compliance with financial and human resources delegations.

Section highlights
We found that agencies are not always regularly reviewing and updating their financial and human resources delegations when there are changes to legislation or other organisational changes within the agency or from machinery of government changes. For example, agencies did not understand or correctly apply the requirements of the GSF Act, resulting in non-compliance with the Act. We found that 18 per cent of agencies spent deemed appropriations without obtaining an authorised delegation from the relevant Minister(s), as required by sections 4.6(1) and 5.5(3) of the GSF Act.
In order for agencies to operate efficiently, make necessary expenditure and human resource decisions quickly and lawfully, particularly in emergency situations, it is important that delegations are kept up to date, provide clear authority to decision makers and are widely communicated.

Appendix one – List of 2020 recommendations 

Appendix two – Status of 2019 recommendations

Appendix three – Cluster agencies

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Credit card management in Local Government

Credit card management in Local Government

Local Government
Internal controls and governance
Management and administration
Procurement
Risk

The Auditor-General for New South Wales, Margaret Crawford, released a report today examining credit card management in Local Government.

The audit was in response to a letter from the then Minister for Local Government in November 2018. The audit assessed the effectiveness of credit card management practices in six councils, including in the areas of policies, procedures, compliance and monitoring.

The audit found that all six councils had gaps in their credit card policies and procedures. The Auditor-General recommended that the Department of Planning, Industry and Environment publish guidelines on credit card management for the Local Government sector. The report also generated insights for the Local Government sector with respect to credit card management.

Read full report (PDF)

In 2018–19, all councils responding to an Audit Office survey (representing over 90 per cent of the sector) indicated they issued credit cards to staff members to make work-related purchases. As there are no sector-wide requirements or policies for credit card use and management in Local Government, councils have developed their credit card management frameworks to suit their own needs. The quality of credit card policies and procedures may therefore vary across the sector.

Credit cards are an efficient means of payment, especially for low-value purchases. Compared to the use of petty cash, credit card transactions provide better transparency and accountability for expenditure. By using credit cards, councils only need to make one payment each month, which can reduce the time spent on paying separate vendors, as in the case of purchase orders.

This audit assessed the effectiveness of credit card management practices in six councils: Dubbo Regional Council, Junee Shire Council, Lane Cove Council, Nambucca Valley Council, Penrith City Council and Shellharbour City Council. The councils selected represent a mix of rural, regional and metropolitan councils. They were also among the top ten users of credit cards within their geographical classification, in terms of the number of credit cards issued or the number of transactions per credit card.

This audit referenced the NSW Treasury's Policy and Guidelines Paper TPP17–09 'Use and Management of NSW Government Purchasing Cards', as its principles and recommendations for NSW Government agencies are relevant for councils.

The Audit Office of New South Wales Report on Local Government 2019 provided a high-level overview of credit card management across the sector. While over 90 per cent of councils reported that they had a credit card policy and a credit card acquittal process, the quality of these policies and procedures may vary across the sector as there is no standardised or recommended approach to credit card management for Local Government. This audit complements the Report on Local Government 2019 by providing a detailed discussion of the effectiveness of credit card management practices in councils.

Audit conclusion

All six audited councils had important gaps in their credit card policies and procedures. Their reconciliation of credit card transactions needs to be enhanced to enable detection of potential misuse or fraud.
 
The audit found important gaps in each of the six audited councils' credit card management practices. Their policies and procedures covered the essential aspects of credit card use and management, but a lack of coverage or clarity in some areas could lead to inconsistent and inappropriate use of credit cards. These areas included: eligibility to hold a credit card, aligning credit card limits with financial delegations, and the reconciliation procedures.
 
While all six councils conducted reconciliations of credit card transactions, the processes need to be enhanced to enable detection of potential misuse or fraud. Reconciliations had focused solely on verifying receipts, and did not require evidence of business-related purposes, even for transactions such as alcohol purchases or spending at entertainment venues. Five of the six councils also did not include compliance checks in their reconciliation process, such as checking that purchases were not for restricted items.
 
The level of senior management involvement in monitoring credit card use varied across the six councils. Three of the six councils did not generate regular reports for management oversight. Five of the six councils had no plans for internal audits or targeted reviews of credit card management and use.

Council staff provided with a credit card can purchase from a wide range of businesses, including online transactions with overseas vendors. However, councils may limit the types of purchases that staff can make through their policies and procedures or by setting controls that block certain transaction types such as cash advances. To examine credit card usage, the audit obtained credit card transaction data from 1 July 2016 to 30 June 2019 for the six councils in this review. The data included:

  • transaction date
  • amount
  • merchant category code (MCC)
  • merchant name.

The audit analysed the number and value of transactions by each council, and the types of purchases made using credit cards.

The existence of a documented approach to managing credit cards ensures transparency and consistency of use within the council. A credit card management framework that contains preventative and detective controls can also minimise risks of fraud, misuse and wastage.

There is no prescribed credit card management framework for Local Government, but typical components of a credit card management framework include:

  • policies and procedures
  • guidance for staff
  • monitoring and reporting.

With no detailed guidance notes similar to those in TPP17–09 for NSW Government, councils have developed their own credit card management framework based on their size, structure, resources and intended credit card usage. For instance, the size of a council has implications for the number of credit cards issued, which in turn influences the arrangements for training and guidance provided to cardholders and approvers.

The intended level of credit card usage may determine whether a council adopts a manual or electronic credit card management system and councils should identify the system that best meets their needs. For instance, a council with few credit cards may not be able to justify investment in an electronic system. On the other hand, a manual system may only be viable for councils with a low number of credit cards and a low number of transactions.

Among the six councils audited, the three councils with fewer cards and a lower number of transactions had a manual credit card management system, while the three councils with more cards and a higher number of transactions used an electronic system.

Exhibit 10 summarises the six councils' policies on use of credit cards.

Exhibit 10: Overview of the six councils' policies on credit card use
Council Audit Office classification Number of staff (full-time equivalent) Number of credit cards issued (current at August 2019) Policy on credit card use
Dubbo Regional Council Regional 453 77 Purchase cards are used for official council business up to $5,000 and the policy allows cardholders to delegate the use of their purchase cards to other staff members.
Junee Shire Council Rural 71 1 Corporate credit cards are for council business activities and minor purchases where a purchase order is not accepted. Items that can be purchased via a purchase order should not be purchased on a corporate credit card.
Lane Cove Council Metropolitan 192 6 Corporate credit cards are for official council business, but should not be used when there is an alternative form of payment that aligns with the council's purchasing process.
Nambucca Valley Council Rural 110 37 Purchase cards are used for the payment of goods and services associated with council businesses.
Penrith City Council Metropolitan 1,031 167 Purchase cards are used for ‘low value and low risk procurement of goods and services’, while corporate cards are held by senior staff for ‘non-routine low value work related purchases’.
Shellharbour City Council Regional 372 65 Credit cards are for purchases up to $9,999 and the preferred payment method for transactions under $1,000.
Source: Audit Office of New South Wales analysis of council credit card registers, policies and procedures 2020; staff numbers from Office of Local Government's 'Your Council' website, except for Junee Shire Council which comes from their Workforce Plan 2020–24.

While it is important for councils to have an established credit card management framework, it is equally important that they ensure compliance in practice. This chapter examines councils' credit card management practices – how well staff members were complying with policies and procedures, and how effective their credit card controls were. The chapter is structured to cover:

  • preventative controls (embedded in the issuance, use and cancellation of cards) that prevent fraud and misuse
  • detective controls (embedded in reconciliation and record keeping) that assist in detecting fraud and misuse.

Where ineffective credit card management practices are identified, councils should reflect on whether they need to more closely monitor compliance, or whether there are fundamental deficiencies in their policies and procedures that need to be refined.

Dubbo Regional Council had gaps in its credit card policy and procedures. It allowed cardholders to share their credit card with other staff members, which complicated credit card management, increased the risk of misuse and fraud, and breached its agreement with the credit card issuer. The council's reconciliation of credit card transactions needs to be enhanced to ensure it can review compliance with policy and detect potential misuse or fraud.

Dubbo Regional Council had 77 credit cards at the time of the audit. The council's policy on credit card sharing violated its agreement with the card issuer that each credit card should be for the respective cardholder's use only. Credit card sharing also increases the risk of misuse and fraud.

The council's credit card policy and procedures lacked clarity in several areas. The eligibility criteria were broad and there was a risk of inconsistency in granting approvals, especially since the council gave approval delegations to multiple senior staff members. The policy and procedures also lacked guidance on the reconciliation of the general manager's credit card and the management of Cabcharge.

The audit identified gaps in the council's credit card management practices. While the council had a clear policy on financial delegations, there was no evidence that credit card limits were monitored in line with financial delegations. The credit card register contained inaccurate information, and the council was also unable to provide records of certain transactions requested for review by the audit.

The council's credit card reconciliation process needs to be enhanced to enable detection of potential misuse or fraud. It did not include compliance checks or reviewing the business-related purpose of transactions. Purchases of restricted items such as fuel, meals and entertainment were not accompanied by evidence of need or exemption. Travel expenses were not checked against travel pre-approval forms. The audit also identified instances of split transactions. The council provided no evidence of the finance team's involvement in the reconciliation of credit card transactions.

Senior management oversight of credit card use was lacking, as the council did not produce reports on credit card use. There was also no evidence that the internal auditor had undertaken monitoring activities as required in the credit card policy.

Recommendations

Dubbo Regional Council should immediately:

1. amend its credit card policy to prevent cardholders from sharing their credit card with other staff.

By December 2020, Dubbo Regional Council should:

2. clarify in the credit card policy and procedures:

  • eligibility criteria for a credit card
  • reconciliation arrangements for the general manager’s credit card
  • Cabcharge management policy and procedures

3. ensure that credit card management practices include:

  • monitoring credit card limits in line with financial delegations
  • considering the use of credit card blocks
  • keeping the credit card register are up-to-date, accurate and complete
  • maintaining complete and accurate records

4. ensure reconciliation involves:

  • scrutinising business-related purposes and incident details of transactions
  • keeping a record of the finance team's review of transactions
  • reviewing transactions against travel pre-approval forms (where applicable)
  • recording vehicle details and mileage when credit cards are used in place of fuel cards
  • checking that there are no split transactions

5. ensure there is ongoing senior management oversight of credit card use

6. ensure the internal auditor undertakes monitoring activities as specified in the credit card policy.

 

Junee Shire Council had gaps in its credit card policy and procedures. The council's reconciliation of credit card transactions needs to be enhanced to ensure it can review compliance with policy and detect potential misuse or fraud.

Junee Shire Council had only one credit card, held by the general manager, at the time of the audit. Staff members could seek approval from the general manager to purchase using the credit card. This raises concerns of credit card sharing, which would be a violation of the council's agreement with its credit card issuer. Credit card sharing also increases the risk of misuse and fraud.

The council had fuel cards and store cards for use by staff members. However, its credit card policy and procedures did not cover the management of these types of cards. The lack of documented rules and guidance increases the risk of misuse and fraud.

The audit identified other gaps in the council's credit card management practices:

  • the credit card limit was not monitored in line with financial delegation
  • there was a lack of targeted guidance for the approver (the mayor) in reconciliation
  • the council was unable to provide records of certain transactions requested for review by the audit
  • the council did not review its credit card policy according to schedule.

The council's credit card reconciliation process needs to be enhanced to enable detection of potential misuse or fraud. It did not include reviewing the business-related purpose of transactions. The council also provided no evidence of the finance team's involvement in the reconciliation of credit card transactions.

As the cardholder, the general manager reviewed all transactions every month. As the approver, the mayor (or deputy mayor) had to sign off on these transactions. Hence, there was sufficient management oversight of the council's credit card use. However, there was a lack of periodic review of the council's credit card use, as it was not included in the council's forward program of internal audits.

Recommendations

Junee Shire Council should immediately:

1. amend its credit card policy to prevent cardholders from sharing their credit card with other staff.

By December 2020, Junee Shire Council should:

2. clarify in the credit card policy and procedures:

  • fuel card management policy and procedures
  • store card management policy and procedures

3. ensure that credit card management practices include:

  • monitoring credit card limits in line with financial delegations
  • considering the use of credit card blocks
  • providing approvers with targeted guidance
  • maintaining complete and accurate records

4. ensure reconciliation involves:

  • scrutinising business-related purposes and incident details of transactions
  • keeping a record of the finance team's review of transactions
  • checking travel pre-approval forms (where applicable)
  • recording vehicle details and mileage when credit cards are used in place of fuel cards
  • checking that there are no split transactions

5. develop a plan for periodic reviews (e.g. internal audit) of credit card use and management

6. ensure its credit card policy and procedures are reviewed according to schedule.

 

Lane Cove Council had gaps in its credit card policy and procedures. The council's reconciliation of credit card transactions needs to be enhanced to ensure it can review compliance with policy and detect potential misuse or fraud.

Lane Cove Council had six credit cards, held by the most senior staff members, at the time of the audit. During our interviews, cardholders advised that they had shared their credit card with reporting staff. Credit card sharing is a violation of the council's agreement with its credit card issuer, and it also increases the risk of misuse and fraud.

The council's credit card policy lacked clarity in several areas. While the general manager had delegation to authorise the issue of credit cards, the policy did not specify any eligibility criteria. The policy and procedures also lacked guidance on the reconciliation of the general manager's credit card and the management of fuel cards and store cards.

The audit identified gaps in the council's credit card management practices. There was no evidence that credit card limits were monitored in line with financial delegations. The credit card register contained inaccurate information, and the council was also unable to provide records of certain transactions requested for review by the audit.

The council's credit card reconciliation process needs to be enhanced to enable detection of potential misuse or fraud. The process also did not include compliance checks or reviewing the business-related purpose of transactions. Purchases of restricted items such as fuel and fine payments were not accompanied by adequate justification. There was a lack of targeted guidance for approvers in reconciliation, and the council only evidenced the finance team's involvement in an administrative capacity (i.e. entering data into the journals).

Senior management oversight of credit card use was lacking. Although the credit card policy referred to management reporting, the council had not been producing such reports at the time of the audit. Management reporting was implemented in December 2019 following our discussions. There was a lack of periodic review of the council's credit card use, as it was not included in the council's forward program of internal audits.

The council has adopted a new Management Directive in January 2020, which has clarified the eligibility criteria for credit cards.

Recommendations

Lane Cove Council should immediately:

1. amend its credit card policy to prevent cardholders from sharing their credit card with other staff.

By December 2020, Lane Cove Council should:

2. clarify in the credit card policy and procedures:

  • reconciliation arrangements for the general manager’s credit card
  • fuel card management policy and procedures
  • store card management policy and procedures

3. ensure that credit card management practices include:

  • monitoring credit card limits in line with financial delegations
  • considering the use of credit card blocks
  • providing approvers with targeted guidance
  • keeping the credit card register up-to-date, accurate and complete
  • maintaining complete and accurate records

4. ensure reconciliation involves:

  • scrutinising business-related purposes and incident details of transactions
  • keeping a record of the finance team's review of transactions
  • checking travel pre-approval forms (where applicable)
  • recording vehicle details and mileage when credit cards are used in place of fuel cards

5. develop a plan for periodic reviews (e.g. internal audit) of credit card use and management.

 

Nambucca Valley Council had gaps in its credit card policy and procedures. The council's reconciliation of credit card transactions needs to be enhanced to ensure it can review compliance with policy and detect potential misuse or fraud.

Nambucca Valley Council had 37 credit cards at the time of the audit. During our interviews, cardholders described instances of credit card sharing within the council. Credit card sharing is a violation of the council's agreement with its credit card issuer, and it also increases the risk of misuse and fraud.

The council's credit card policy lacked clarity in several areas. While the general manager had delegation to authorise the issue of credit cards, the policy did not specify any eligibility criteria. The policy and procedures lacked guidance on the management of fuel cards, store cards and Cabcharge. The policy also lacked coverage of the reconciliation arrangements for the general manager's credit card as the general manager did not hold a credit card. While the policy did not preclude the mayor and the general manager from holding a credit card, both opted not to do so.

The audit identified gaps in the council's credit card management practices. There was no evidence that credit card limits were monitored in line with financial delegations. The credit card register contained inaccurate information, and there was insufficient control in handling staff departures, as the audit identified one incident where a credit card was returned after the staff member's last day.

The council's credit card reconciliation process needs to be enhanced to enable detection of potential misuse or fraud. The process also did not include adequate compliance checks or reviewing the business-related purpose of transactions. Purchases of restricted items such as fuel and the use of third-party travel websites were not accompanied by adequate justification. Travel expenses were not checked against travel pre-approval forms. The audit also identified instances of split transactions.

Senior management oversight of credit card use was insufficient, as the council had been producing reports for only one manager for his department at the time of the audit. Management reporting for the Chief Finance Officer was implemented following our discussions. There was a lack of periodic review of the council's credit card use, as it was not included in the council's forward program of internal audits.

The audit acknowledges that the council had revised its credit card procedures following our discussions to address our preliminary findings. The council has also set additional credit card blocks in response to this audit. The recommendations below contain only the outstanding items.

Recommendations

Nambucca Valley Council should immediately:

1. ensure cardholders stop sharing their credit card with other staff.

By December 2020, Nambucca Valley Council should:

2. clarify in the credit card policy and procedures:

  • reconciliation arrangements for the general manager’s credit card (should the policy continue to allow the general manager to have one)
  • fuel card management policy and procedures

3. ensure that credit card management practices include:

  • monitoring credit card limits in line with financial delegations
  • keeping the credit card register up-to-date, accurate and complete

4. ensure reconciliation involves:

  • scrutinising business-related purposes and incident details of transactions
  • checking travel pre-approval forms (where applicable)
  • recording vehicle details and mileage when credit cards are used in place of fuel cards
  • checking that there are no split transactions

5. develop a plan for periodic reviews (e.g. internal audit) of credit card use and management.

 

Penrith City Council had gaps in its credit card policy and procedures. The council's reconciliation of credit card transactions needs to be enhanced to ensure it can review compliance with policy and detect potential misuse or fraud.

Penrith City Council had 167 credit cards at the time of the audit. During our interviews, cardholders described instances of credit card sharing within the council. Credit card sharing is a violation of the council's agreement with its credit card issuer, and it also increases the risk of misuse and fraud.

The audit identified gaps in the council's credit card policy and procedures. There was no documented arrangement for the reconciliation of the general manager's credit card. There was also no guidance on the management of Cabcharge. The credit card register contained inaccurate information, and the council was also unable to provide records of certain transactions requested for review by the audit.

The council's credit card reconciliation process needs to be enhanced to enable detection of potential misuse or fraud. The process did not include adequate compliance checks or reviewing the business-related purpose of transactions. The council's policy required prior approval for conferences, accommodation or meal expenses. However, there was no evidence that such approvals were checked during credit card reconciliation. The audit also identified instances of split transactions.

The council implemented monthly reporting for managers in July 2019.

There was a lack of periodic review of the council's credit card use, as it was not included in the council's forward program of internal audits.

Recommendations

Penrith City Council should immediately:

1. ensure cardholders stop sharing their credit card with other staff.

By December 2020, Penrith City Council should:

2. clarify in the credit card policy and procedures

  • reconciliation arrangements for the general manager’s credit card
  • Cabcharge management policy and procedures

3. ensure that credit card management practices include:

  • considering the use of credit card blocks
  • keeping the credit card register up-to-date, accurate and complete
  • maintaining complete and accurate records

4. ensure reconciliation involves:

  • scrutinising business-related purposes and incident details of transactions
  • keeping a record of the finance team's review of transactions
  • checking travel pre-approval forms (where applicable)
  • recording vehicle details and mileage when credit cards are used in place of fuel cards
  • checking that there are no split transactions

5. develop a plan for periodic reviews (e.g. internal audit) of credit card use and management.

 

Shellharbour City Council had gaps in its credit card policy and procedures. The council's reconciliation of credit card transactions needs to be enhanced to ensure it can review compliance with policy and detect potential misuse or fraud.

Shellharbour City Council had 65 credit cards at the time of the audit. During our interviews, cardholders described instances of credit card sharing within the council. Credit card sharing is a violation of the council's agreement with its credit card issuer, and it also increases the risk of misuse and fraud.

The council's credit card policy lacked clarity in several areas. While the general manager had delegation to authorise the issue of credit cards, the policy did not specify any eligibility criteria. The council did not align credit card limits with financial delegations, and while blocking codes were used, there was no explanation in the policy or procedures. Although the mayor and general manager's credit card transactions were reviewed during the council's monthly Executive Leadership Team meetings, the policy and procedures lacked guidance on the reconciliation of their credit cards. The council also did not have sufficiently detailed documentation for the management of fuel cards.

The audit identified gaps in the council's credit card management practices:

  • The council's training material had not been updated following the review of its credit card policy and procedures.
  • The credit card register contained inaccurate information.
  • The council was unable to provide records of certain transactions requested for review by the audit.
  • The council did not review its credit card policy according to schedule.

The council's credit card reconciliation process needs to be enhanced to enable detection of potential misuse or fraud. The process did not include compliance checks or reviewing the business-related purpose of transactions. Purchases of restricted items, such as fuel and fine payments, were not accompanied by adequate justification. The audit identified instances of split transactions, and travel or conference approval forms were also not checked during reconciliation. There was a lack of targeted guidance for approvers in reconciliation, and the council also provided no evidence of the finance team's involvement in the reconciliation of credit card transactions.

The council's Executive Leadership Team was involved in the monthly review of credit card transactions, hence there was management oversight of credit card use. However, there was a lack of periodic review of the council's credit card use, as it was not included in the council's forward program of internal audits.

Recommendations

Shellharbour City Council should immediately:

1. ensure cardholders stop sharing their credit card with other staff.

By December 2020, Shellharbour City Council should:

2. clarify in the credit card policy and procedures:

  • eligibility criteria for a credit card
  • the use of blocking codes
  • reconciliation arrangements for the general manager’s credit card
  • fuel card management policy and procedures (with more details)

3. ensure that credit card management practices include:

  • monitoring credit card limits in line with financial delegations
  • providing approvers with targeted guidance
  • keeping the credit card register up-to-date, accurate and complete
  • maintaining complete and accurate records
  • updating the training material to reflect the latest policy and procedures

4. ensure reconciliation involves:

  • scrutinising business-related purposes and incident details of transactions
  • keeping a record of the finance team's review of transactions
  • checking travel pre-approval forms (where applicable)
  • recording vehicle details and mileage when credit cards are used in place of fuel cards
  • ensuring no split transactions

5. develop a plan for periodic reviews (e.g. internal audit) of credit card use and management

6. ensure its credit card policy and procedures are reviewed according to schedule.

Appendix one – Responses from councils and the Department of Planning, Industry and Environment

Appendix two – About the audit

Appendix three – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #340 - released 3 September 2020

Published

Actions for Health capital works

Health capital works

Health
Compliance
Infrastructure
Procurement
Project management

This report examines whether NSW Health effectively planned and delivered major capital works to meet the demand for health services in New South Wales.

The report found that NSW Health has substantially expanded health infrastructure across New South Wales since 2015. However, the program was driven by Local Health District priorities without assessment of the State’s broader and future‑focussed health requirements.

The report found that unclear decision making roles and responsibilities between Health Infrastructure and the Ministry of Health limited the ability of NSW Health to effectively test and analyse investment options.

Project delays and budget overruns on some major projects indicate that Health Infrastructure's project governance, risk assessment and management systems could be improved.

The Auditor‑General recommends that NSW Health ensure its capital projects offer the greatest value to New South Wales by establishing effective policy guidance and enhancing project governance and management systems.

Read full report (PDF)

Since 2011–12, NSW Health has aimed to improve its facilities and build 'future focused' infrastructure. The NSW Government’s 2015–16 election commitments established a four-year $5.0 billion capital program for NSW Health to build and upgrade more than 60 hospitals and health services. The 2019–20 State Budget committed a further $10.1 billion over four years for another 29 projects. This is the largest investment to date on health capital works in New South Wales.

Recent reviews of infrastructure have recognised that population and demographic growth will require a change in the delivery and composition of health infrastructure, including considering greater use of non-traditional, non-capital health service options and assets.

To ensure that expenditure on capital works represents the best value for money, NSW Health's business cases need to be robust and supported by evidence that demonstrates they are worthy investments. The NSW Process of Facility Planning has been the main framework guiding the detailed planning and development of NSW Health's capital works proposals. This framework was developed by the then NSW Department of Health in 2010. Its aim is to ensure investment proposals are supported by rigorous planning processes that address health service needs and provide value for money.

Infrastructure projects of the complexity and scale being delivered by NSW Health carry inherent risks. For example, unplanned cost escalations can potentially impact on the State’s finances. Unforeseen delays can also reduce the intended benefits. The growth in the State’s health capital spend and project profile, means its exposure to such risks has increased over time.

The objective of this audit was to assess the effectiveness of planning and delivery of major capital works to meet demand for health services in New South Wales. To address this objective, the audit examined whether:

  • the Ministry of Health has effective procedures for planning and prioritising investments in major health capital works
  • Health Infrastructure develops robust business cases for initiated major capital works that reliably inform government decision making
  • Health Infrastructure has effective project governance and management systems that support delivering projects on-time, within budget and achievement of intended benefits.

The audit focused on the Ministry of Health and Health Infrastructure – being the lead agencies within NSW Health responsible for prioritising, planning and delivering major health capital works across the State. The audit examined 13 business cases for eight discrete projects over a ten-year period.

Conclusion

NSW Health has substantially expanded health infrastructure across New South Wales since 2015. However, its planning and prioritisation processes were not assessed against a long-term statewide health infrastructure plan and lacked rigorous assessment against non-capital options creating a risk that they do not maximise value for New South Wales.

The scale of NSW Health's capital investment is significant and has grown substantially in recent years. The NSW Government’s election commitments in 2015–16 and 2019–20 collectively set out a $15.0 billion capital program to build and upgrade 89 hospitals and health services. NSW Health developed this infrastructure program in the absence of a statewide health infrastructure strategy and investment framework to focus its planning and decisions on the types of capital investments required to meet the long-term needs of the NSW health system.

Consequently, locally focused priorities of the State’s 17 Local Health Districts have been the primary drivers of NSW Health’s capital investments since 2015–16. Local Health District investment proposals for hospitals were developed without consideration of alternative health options such as community health service models, technology-driven eHealth care, or private sector options. Without rigorous assessment against a range of potential health service options, there is a risk that selected projects do not maximise value for New South Wales.

In recognition of the need for a statewide approach to infrastructure planning, the Ministry of Health recently developed a 20-year Health Infrastructure Strategy and prioritisation framework in 2019. The strategy was approved by the NSW Government in April 2020.

NSW Health's ability to effectively test and analyse its capital investment options has been compromised by unclear decision-making roles and responsibilities between its Health Infrastructure and the Ministry of Health agencies.

While both Health Infrastructure and the Ministry of Health have responsibilities for the assessment of business cases for proposed infrastructure projects, confusion about the roles of each agency at key steps compromised the efficacy of the process. Health Infrastructure and the Ministry of Health have differing views about which agency is responsible for testing business case inputs and conducting comprehensive options appraisals.

As a result of this confusion, Health Infrastructure and the Ministry of Health did not rigorously test Local Health District capital investment proposals against defined statewide health infrastructure investment priorities. The NSW Process of Facility Planning does not clarify the responsibilities of all parties in validating and prioritising Local Health District's Clinical Service Plans and progressing them to business cases.

NSW Health's infrastructure priorities are not sufficiently supported by transparent documentation of selection methodology and the rationale for decisions. Consequently, there is a risk that recommended options, whilst having some economic and health service merit, do not represent the greatest value.

Substantial delays and budget overruns on some major projects indicate that Health Infrastructure's project governance, risk assessment and management systems could be improved.

Health Infrastructure did not fully comply with NSW Government guidelines for developing business cases and making economic appraisals for proposed capital investments. These weaknesses, along with delays and budget overruns on some projects, demonstrate a need for Health Infrastructure to strengthen its project governance, management and quality control systems.

 

Over the period of review, NSW Government policies for business case development and submission have emphasised that effective governance arrangements are critical to a proposal's successful implementation.

NSW Health's Process of Facility Planning similarly highlights the importance of effective governance and project management for achieving good outcomes. It prescribes a general governance structure managed by Health Infrastructure that can be tailored to the planning and delivery of health infrastructure projects greater than $10.0 million.

Project challenges indicate opportunities for strengthening governance and project management

The three major hospital redevelopments examined in metropolitan, regional and rural areas had a combined Estimated Total Cost of more than $1.2 billion and comprised eight discrete projects and 13 separate business cases.

Almost all these projects experienced delivery challenges which impacted achievement of their original objectives and intended benefits. This is expected in complex and large-scale health infrastructure programs. However, in some projects the impacts were significant and resulted in substantial delays, unforeseen costs, and diversion of resources from other priority areas.

Our review of the selected case studies highlighted opportunities for enhancing governance and project management. Specifically, it indicates a need for improving transparency in the management of contingencies, risk management and assessments particularly relating to adverse site conditions and the selection of contractors. There is also a need to strengthen forward planning for options to address unfunded priorities within business cases that risk complicating the delivery of future project stages resulting in unforeseen costs and potentially avoidable budget overruns.

Need for increased transparency and accountability in the management of contingency funds

In February 2017, the Ministry's Capital Strategy Group approved the use of surplus funds of $13.76 million from Stage 1 of the Hornsby Ku-ring-gai Hospital Redevelopment for new works deemed needed to support Stage 2. Following this decision, Health Infrastructure finalised and submitted a business case addendum for Stage 1 to the Ministry in March 2017, addressing the new works comprising a two-storey building for medical imaging and paediatric floors. The business case addendum also addressed options to fit out and procure major medical imaging equipment. The Ministry approved the Stage 1 business case in July 2017, noting the Ministry's Capital Strategy Group had already approved the use of remaining Stage 1 funds to deliver the new works.

Stage 1 was completed in 2015, almost two years before the Stage 1 business case addendum was prepared in February 2017.

The Ministry's decision to approve the new works using $13.76 million of surplus Stage 1 funds did not comply with the NSW Treasury Circular TC 12/20. This policy establishes the Treasurer's approval must be sought and received before a new capital project with an Estimated Total Cost of $5.0 million or more can be approved by NSW Health. The Ministry therefore exceeded its delegated authority in making this decision, as it was not evident it had sought and received the Treasurer's approval prior to doing so.

Consequently, the surplus Stage 1 funds should not have been used by the Ministry to deliver new works in the circumstances. Instead, they should have been released from the Stage 1 project in accordance with established NSW Health procedures, and the Stage 1 Estimated Total Cost revised down accordingly. This did not occur, and NSW Health ultimately directed $11.0 million in surplus Stage 1 funds to the new works.

These circumstances indicate a need to strengthen transparency and accountability within NSW Health for the approval of new projects, and how contingency funds are used in the management of major health capital works. They also demonstrate the impact of weaknesses with options appraisal as the initial Stage 1 business case did not consider alternative options for addressing the initially unfunded works later covered by the Stage 1 business case addendum and ultimately funded from the Stage 1 contingency provision.

Weaknesses in service delivery planning resulted in unaccounted-for costs

In addition to proposing the above-noted new works, the 2017 Stage 1 Business Case Addendum for the Hornsby-Ku-ring-gai development sought to retrospectively address the estimated funding gap of around $14.0 million for the internal fit out, supply of major medical imaging equipment, and cost to operate the medical imaging service at Hornsby Ku-ring-gai Hospital also not addressed in the originally Stage 1 business case.

The Stage 1 business case addendum considered various procurement options to purchase and run the medical imaging services ranging from State operation purchase options to private operation purchase options.

It recommended outsourcing the operation and provision of equipment to the private sector based on estimated savings to the public sector initially of around $650,000 per annum reducing over time to $270,000. The Ministry endorsed this option in June 2017, but it did not ultimately proceed.

A July 2018 report to the Executive Steering Committee on the project shows NSW Health later decided to deliver operation of the medical imaging unit 'traditionally' with an updated estimate of the cost at approximately $16.4 million. The report also shows the Ministry supported the costs now being met by the Northern Sydney Local Health District.

This means the funding gap previously identified in the Stage 1 business case addendum for fitting out the medical imaging building and supply of major medical equipment would need to be met fully by the State, representing a $16.4 million cost overrun for the project.

Examined reports to the Executive Steering Committee show this was largely funded by the Northern Sydney Local Health District via the disposal of land realising approximately $15.0 million in proceeds.

This initially unforeseen cost, along with the additional $11.0 million for the new works approved under the Stage 1 business case addendum, were ultimately merged with the Stage 2 project initially approved in 2017–18 with an Estimated Total Cost of $200 million.

The extent of budget variation on the Hornsby Kur-ring-gai development has not been transparent

The 2019–20 State Budget provided an additional $65.0 million for a further Stage 2A to deliver additional built capacity to support outpatient services, enhanced allied health services, re-housed community health services and the delivery of prioritised clinical services unfunded as part of Stage 2. The funds were approved based on an Investment Decision Template (IDT) that examined two options in addition to the base case representing scoping alternatives to the preferred master planned capital solution.

However, we found the IDT showed around 23 per cent of the $65.0 million sought (i.e. $15.0 million) was to be allocated to fund the deficit in Stage 2, which had arisen as a result of project delays due to adverse site conditions. This was not discussed in the IDT.

The February 2020 report to the Executive Steering Committee shows a combined Stage 2 and 2A final forecast cost of $292.6 million against a potential budget of $290.7 million representing an overall deficit for the project of around 0.6 per cent.

However, this favourable final budget position does not transparently show the funding challenges experienced over the project's implementation to-date. The three major budget issues include:

  • inappropriate use of around $11.0 million in Stage 1 contingency for originally unfunded works contrary to Treasury policy
  • the additional $16.4 million cost unforeseen in the Stage 1 business case for delivering medical imaging services mostly funded through the sale of land
  • an additional $15.0 million from Stage 2A to cover the budget overrun in Stage 2 due to adverse site conditions.

The cumulative impact of these events is that Stages 1 and 2 of the Hornsby project cost approximately $42.4 million than it should have in the circumstances around 14 per cent more than what the revised combined Estimated Total Cost for both stages should have been after releasing the $11.0 million in surplus Stage 1 funds, with Stage 2 delayed by around 14 months.

Opportunity for strengthening risk management for adverse site conditions

Major construction projects often experience adverse site conditions which can be difficult to fully detect in advance. However, we found this was a common occurrence in the projects we examined sometimes with significant time and/or budget impacts indicating scope to enhance related risk and cost assessments. Specifically:

  • Hornsby Ku-ring-gai Hospital Redevelopment Stage 2: adverse site conditions during demolition works resulted in an 11-month delay for delivering the medical imaging unit and 14-month delay completing Stage 2 main works including need for additional $15.0 million in funds to cover the resultant budget deficit for the project.
  • Blacktown Mt Druitt Hospital Redevelopment Stage 2: adverse site conditions combined with project complexity delayed completion of the early works by approximately five months. This contributed to the delay in completing the main construction works which occurred around nine months later than planned in the business case.
  • Dubbo Health Service Redevelopment Stages 3 and 4: Health Infrastructure advised adverse site conditions including asbestos containing materials and ground conditions delayed works for the main building with completion forecast for March 2021, around 21 months later than planned in the final business case. This resulted in the need for additional $13.5 million to cover increased construction costs and risks, increasing the Stage 3 and 4 forecast final cost from $150 million to $163.5 million as at February 2020.

These examples indicate a risk the cumulative impact of adverse site conditions may be substantial when measured across both time and Health Infrastructure's full delivery program. They also point to potential for Health Infrastructure to achieve efficiencies and improved outcomes from strengthening its approach to assessing and mitigating the risks from adverse site conditions.

Limited due diligence with prospective contractors risks avoidable delays and costs

Main construction works on Stage 1 of the Dubbo Health Service Redevelopment were completed in October 2015, approximately 13 months later than planned in the final business case. Delays were mainly due to insolvency of the early works contractor resulting in their departure from the project. The ensuing 11-month delay in completing the early works significantly impacted the overall schedule and delivery of main construction works.

The insolvency event was significant as it affected nine separate Health Infrastructure projects – three of which had yet to reach practical completion. It also affected state-funded projects in other sectors. It resulted in the need for additional funding of $11.5 million that was provided in the 2014–15 State Budget increasing the total Stage 1 and 2 budget from $79.8 million to $91.3 million.

Health Infrastructure’s analysis of lessons learned shows it worked actively to mitigate the impacts of the insolvency event across all affected projects. However, it also indicates a risk the lessons were mainly focused on mitigating the impacts after an insolvency event occurred rather than on prevention.

Although Health Infrastructure initially commissioned a financial assessment of the now insolvent early works contractor before engagement, it did not detect any risks of the impending insolvency and instead concluded the contractor was in a strong financial position. However, the contractor became insolvent shortly after commencement approximately seven months later. This indicates a risk of weaknesses in the assessment performed that was not explicitly addressed by the lessons learned.

Delivery of the main construction works were further impacted by disputes with the main works contractor over the scope of works for the renal unit resulting in Health Infrastructure terminating the contract in November 2016 following lengthy negotiations over several months.

The scope of works relating to the renal unit were ultimately transferred to Stages 3 and 4 and were delivered in December 2019, around five years later than originally planned in the business case.

Health Infrastructure advised the delay was ultimately beneficial to the project because the refurbishment works for the renal unit, initially scheduled for Stages 1 and 2, would have been demolished to accommodate the new Western Cancer Centre proposed after Stages 1 and 2 and currently being delivered in parallel with Stages 3 and 4.

Health Infrastructure advised the actual cost of Stages 1 and 2 was $84.7 million against the budget of $91.3 million. The residual $6.6 million relates to the renal works not delivered during Stage 1 and 2 and transferred to Stage 3 and 4.

Health Infrastructure advised the contractual provisions for mitigating insolvency events 'in-flight' are limited highlighting the importance of proactive and effective due diligence prior to engaging contractors for significant construction projects.

Need for a quality framework linked to staff training and capability development

Health Infrastructure's 2017-20 Corporate Plan identifies the development of a quality framework to support delivery of future-focused outcomes as a key organisational priority. Related initiatives within the Corporate Plan describe a framework underpinned by a Quality Committee providing advice on:

  • records management, to meet the requirements of the State Records Act 1998
  • project assurance, to ensure future focused outcomes and enhance Health Infrastructure's Standards, Policies, Procedures and Guidelines, Templates and Design Guidance Notes
  • knowledge management and library services, to promote and leverage from project learnings.

Although Health Infrastructure has some elements of a quality framework it is not yet fully in place. Health Infrastructure advised it had yet to establish the quality framework and related committee described in its Corporate Plan due in part to its focus on responding to the growth of its capital program.

Health Infrastructure's Development and Innovation team has been active in supporting continuous improvement in knowledge and project management including development of business cases. Although useful, these initiatives have relied heavily on leveraging and disseminating insights from Gateway reviews and have not formed part of a systematic quality and continuous improvement framework.

The limited focus on the quality of business cases is reflected in internal performance monitoring and reporting which focuses mainly on tracking the delivery of projects against internal benchmarks, often revised from the baselines in the business case, and expenditure against cashflow targets. There is no evident internal monitoring and/or reporting to the Chief Executive and Board on defined quality metrics linked to business case development and staff capability.

Performance reporting on balanced scorecard metrics has similarly focused mainly on process rather than quality and has been inconsistent in recent years.

Appendix one – Response from agency

Appendix two – About the audit

Appendix three – Performance auditing

Appendix four – Ministry of Health planning tools and guidelines

Appendix five – Streamlined investment decision process for Health Capital Projects

Appendix six – Timeline of business cases and relevant policy guidelines

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #338 - released 12 August 2020

Published

Actions for Their Futures Matter

Their Futures Matter

Justice
Community Services
Education
Health
Whole of Government
Cross-agency collaboration
Internal controls and governance
Management and administration
Project management

The Auditor-General for New South Wales, Margaret Crawford, released a report today examining whether the Department of Communities and Justice had effective governance and partnership arrangements in place to deliver ‘Their Futures Matter’.

Their Futures Matter was intended to place vulnerable children and families at the heart of services, and direct investment to where funding and programs deliver the greatest social and economic benefits. It was a four-year whole-of-government reform in response to the 2015 Tune Review of out-of-home care.

The Auditor-General found that while important foundations were put in place, and new programs trialled, the key objective to establish an evidence-based whole-of-government early intervention approach for vulnerable children and families in NSW was not achieved.

Governance and cross-agency partnership arrangements to deliver Their Futures Matter were found to be ineffective. 'Their Futures Matter lacked mechanisms to secure cross portfolio buy‑in and did not have authority to drive reprioritisation of government investment', the Auditor-General said.

At the reform’s close, the majority of around $380 million in investment funding remains tied to existing agency programs, with limited evidence of their comparative effectiveness or alignment with Their Futures Matter policy objectives. The reform concluded on 30 June 2020 without a strategy or plan in place to achieve its intent.

The Auditor-General made four recommendations to the Department of Communities and Justice, aimed at improving implementation of outstanding objectives, revising governance arrangements, and utilising the new human services data set to address the intent of the reform. However, these recommendations respond only in part to the findings of the audit.

According to the Auditor-General, ‘Cross-portfolio leadership and action is required to ensure a whole-of-government response to delivering the objectives of Their Futures Matter to improve outcomes for vulnerable children, young people and their families in New South Wales.’

Read full report (PDF)

In 2016, the NSW Government launched 'Their Futures Matter' (TFM) - a whole-of-government reform aimed at delivering improved outcomes for vulnerable children, young people and their families. TFM was the government's key response to the 2015 Independent Review of Out of Home Care in New South Wales (known as 'the Tune Review').

The Tune Review found that, despite previous child protection reforms, the out of home care system was ineffective and unsustainable. It highlighted that the system was not client-centred and was failing to improve the long-term outcomes for vulnerable children and families. The review found that the greatest proportion of relevant expenditure was made in out of home care service delivery rather than in evidence-based early intervention strategies to support children and families when vulnerabilities first become evident to government services (such as missed school days or presentations to health services).

The then Department of Family and Community Services (FACS) designed the TFM reform initiatives, in consultation with central and human services agencies. A cross-agency board, senior officers group, and a new unit in the FACS cluster were established to drive the implementation of TFM. In the 2016–17 Budget, the government allocated $190 million over four years (2016–17 to 2019–20) to the reform. This resourced the design and commissioning of evidence-based pilots, data analytics work, staffing for the implementation unit and secretariat support for the board and cross-agency collaboration.

As part of the TFM reform, the Department of Premier and Cabinet, NSW Treasury and partnering agencies (NSW Health, Department of Education and Department of Justice) identified various existing programs that targeted vulnerable children and families (such as the preceding whole-of-government ‘Keep Them Safe’ reform coming to an end in June 2020). Funding for these programs, totalling $381 million in 2019–20, was combined to form a nominal ‘investment pool’. The government intended that the TFM Implementation Board would use this pool to direct and prioritise resource allocation to evidence-based interventions for vulnerable children and families in NSW.

This audit assessed whether TFM had effective governance and partnership arrangements in place to enable an evidence-based early intervention investment approach for vulnerable children and families in NSW. We addressed the audit objective with the following audit questions:

  • Was the TFM reform driven by effective governance arrangements?
  • Was the TFM reform supported by effective cross-agency collaboration?
  • Has the TFM reform generated an evidence base to inform a cross-agency investment approach in the future?

The audit did not seek to assess the outcomes for children, young people and families achieved by TFM programs and projects.

Conclusion

The governance and cross-agency partnership arrangements used to deliver the Their Futures Matter reform were ineffective. Important foundations were put in place, and new programs trialled over the reform's four years. However, an evidence-based whole-of-government early intervention approach for vulnerable children and families in NSW − the key objective of the reform − was not established. The reform concluded in June 2020 without a strategy or plan in place to achieve its intent.

The governance arrangements established for the Their Futures Matter (TFM) reform did not provide sufficient independence, authority and cross-agency clout to deliver on the reform’s intent. This hindered delivery of the reform's key elements, particularly the redirection of funding to evidence-based earlier intervention supports, and limited the impact that TFM could have on driving system change.

TFM increased focus on the contribution that other agencies outside of the former Family and Community Services portfolio could make in responding to the needs of vulnerable children and families, and in reducing the demand costs of related government service delivery. Despite being a whole-of-government reform, TFM lacked mechanisms to secure cross-portfolio buy-in and lacked the powers to drive reprioritisation of government investment in evidence-based and earlier intervention supports across agencies. At the reform’s close, the majority of the reform's investment pool funding remained tied to existing agency programs, with limited evidence of their comparative effectiveness or alignment with Their Futures Matter policy objectives.

TFM began building an evidence base about ‘what works’, including piloting programs and creating a new dataset to identify risk factors for vulnerability and future costs to government. However, this evidence base does not yet comprehensively map how existing services meet needs, identify system duplications or gaps, nor demonstrate which government funded supports and interventions are most effective to make a difference to life outcomes for vulnerable children and families in NSW.
Despite these issues, the need, intent and vision for Their Futures Matter remains relevant and urgent, as issues identified in the Tune Review remain pertinent.

Their Futures Matter (TFM) is a whole-of-government reform to deliver improved outcomes for vulnerable children, young people and their families.

Supported by a cross-agency TFM Board, and the TFM Unit in the then Department of Family and Community Services (FACS), the reform aimed to develop whole-of-government evidence-based early intervention investment approaches for vulnerable children and families in NSW.

Governance refers to the structures, systems and practices that an organisation has in place to:

  • assign decision-making authorities and establish the organisation's strategic direction
  • oversee the delivery of its services, the implementation of its policies, and the monitoring and mitigation of its key risks
  • report on its performance in achieving intended results, and drive ongoing improvements.

We examined whether the TFM reform was driven by effective governance arrangements and cross-agency collaboration.

The reform agenda and timeframe set down for Their Futures Matter (TFM) were ambitious. This chapter assesses whether the TFM Board and TFM Unit had the capability, capacity and clout within government to deliver the reform agenda.

Creating a robust evidence base was important for Their Futures Matter, in order to:

  • identify effective intervention strategies to improve supports and outcomes for vulnerable children and families
  • make efficient use of taxpayer money to assist the maximum number of vulnerable children and families
  • inform the investment-based approach for future funding allocation.

This chapter assesses whether the TFM reform has developed an evidence base to inform cross-agency investment decisions.

Appendix one – Response from agency

Appendix two – TFM governance entities

Appendix three – TFM Human Services Data Set

Appendix four – TFM pilot programs

Appendix five – About the audit

Appendix six – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #337 - released 24 July 2020

Published

Actions for CBD South East Sydney Light Rail: follow-up performance audit

CBD South East Sydney Light Rail: follow-up performance audit

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk
Service delivery

This is a follow-up to the Auditor-General's November 2016 report on the CBD South East Sydney Light Rail project. This follow-up report assessed whether Transport for NSW has updated and consolidated information about project costs and benefits.

The audit found that Transport for NSW has not consistently and accurately updated project costs, limiting the transparency of reporting to the public.

The Auditor-General reports that the total cost of the project will exceed $3.1 billion, which is above the revised cost of $2.9 billion published in November 2019. $153.84 million of additional costs are due to omitted costs for early enabling works, the small business assistance package and financing costs attributable to project delays.

The report makes four recommendations to Transport for NSW to publicly report on the final project cost, the updated expected project benefits, the benefits achieved in the first year of operations and the average weekly journey times.

Read full report (PDF)

The CBD and South East Light Rail is a 12 km light rail network for Sydney. It extends from Circular Quay along George Street to Central Station, through Surry Hills to Moore Park, then to Kensington and Kingsford via Anzac Parade and Randwick via Alison Road and High Street.

Transport for NSW (TfNSW) is responsible for planning, procuring and delivering the Central Business District and South East Light Rail (CSELR) project. In December 2014, TfNSW entered into a public private partnership with ALTRAC Light Rail as the operating company (OpCo) responsible for delivering, operating and maintaining the CSELR. OpCo engaged Alstom and Acciona, who together form its Design and Construct Contractor (D&C).

On 14 December 2019, passenger services started on the line between Circular Quay and Randwick. Passenger services on the line between Circular Quay and Kingsford commenced on 3 April 2020.

In November 2016, the Auditor-General published a performance audit report on the CSELR project. The audit found that TfNSW would deliver the CSELR at a higher cost with lower benefits than in the approved business case, and recommended that TfNSW update and consolidate information about project costs and benefits and ensure the information is readily accessible to the public.

In November 2018, the Public Accounts Committee (PAC) examined TfNSW's actions taken in response to our 2016 performance audit report on the CSELR project. The PAC recommended that the Auditor-General consider undertaking a follow-up audit on the CSELR project. The purpose of this follow-up performance audit is to assess whether TfNSW has effectively updated and consolidated information about project costs and benefits for the CSELR project.

Conclusion

Transport for NSW has not consistently and accurately updated CSLER project costs, limiting the transparency of reporting to the public. In line with the NSW Government Benefits Realisation Management Framework, TfNSW intends to measure benefits after the project is completed and has not updated the expected project benefits since April 2015.

Between February 2015 and December 2019, Transport for NSW (TfNSW) regularly updated capital expenditure costs for the CSELR in internal monthly financial performance and risk reports. These reports did not include all the costs incurred by TfNSW to manage and commission the CSELR project.

Omitted costs of $153.84 million for early enabling works, the small business assistance package and financing costs attributable to project delays will bring the current estimated total cost of the CSELR project to $3.147 billion.

From February 2015, TfNSW did not regularly provide the financial performance and risk reports to key CSELR project governance bodies. TfNSW publishes information on project costs and benefits on the Sydney Light Rail website. However, the information on project costs has not always been accurate or current.

TfNSW is working with OpCo partners to deliver the expected journey time benefits. A key benefit defined in the business plan was that bus services would be reduced owing to transfer of demand to the light rail - entailing a saving. However, TfNSW reports that the full expected benefit of changes to bus services will not be realised due to bus patronage increasing above forecasted levels.

Appendix one – Response from agency

Appendix two – Governance and reporting arrangements for the CSELR

Appendix three – 2018 CSELR governance changes

Appendix four – About the audit

Appendix five – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #335 - released 11 June 2020

Published

Actions for Destination NSW's support for major events

Destination NSW's support for major events

Treasury
Financial reporting
Management and administration
Procurement
Project management
Service delivery

This report focuses on whether Destination NSW (DNSW) can demonstrate that its support for major events achieves value for money.

The audit found that DNSW’s processes for assessing and evaluating the major events it funds are mostly effective, but its public reporting does not provide enough transparency.

DNSW provides clear information to event organisers seeking funding and has a comprehensive methodology for conducting detailed event assessments. However, the reasons for decisions to progress events from the initial assessment to the detailed assessment stage are not documented in sufficient detail.

DNSW does not publish detailed information about the events it funds or the outcomes of these events. This means that members of the public are unable to see whether its activities achieve value for money. However, DNSW’s internal reporting to its key decision‑makers, including the CEO, the Board and the Minister is appropriate.

The Auditor-General made four recommendations to DNSW, aimed at improving the transparency of its activities, improving the documentation of decisions and certain compliance matters, and streamlining its approach to assessing and evaluating events that receive smaller amounts of funding.

Read full report (PDF)

Destination NSW (DNSW) provides funding to attract a range of major events to New South Wales, including high-profile professional sports matches and tournaments, musicals, art and museum exhibitions, and participation-focused events such as festivals and sports events that members of the public can enter. The NSW Government's rationale for providing funding is to encourage event organisers to hold events in New South Wales, and to ensure that events held in New South Wales maximise the potential for attracting overseas and interstate visitors.

This audit assessed whether DNSW can demonstrate that its support for major events achieves value for money. In making this assessment, the audit examined whether:

  • DNSW effectively assesses proposals to support major events
  • DNSW effectively evaluates the impact of its support for major events.

This audit focused on DNSW's work to attract major events to New South Wales. It did not assess DNSW's tourism promotion or development work, which includes developing tourism strategies, marketing and advertising campaigns, national and international partnerships, and regional programs.

Conclusion

Destination NSW's processes for assessing event applications and evaluating its support for major events are mostly effective. DNSW's internal systems allow it to know whether its decisions are achieving value for money. Its public reporting does not provide enough information about its activities and their outcomes, although it is consistent with that of equivalent organisations in other Australian jurisdictions.

DNSW's process for assessing applications for funding from organisers of major events is mostly effective. Clear information is provided to event organisers seeking funding, and DNSW has a comprehensive methodology for conducting detailed event assessments. However, the reasons for decisions to progress events from the initial assessment to the detailed assessment stage are not documented in sufficient detail.

DNSW has a framework for disclosure and monitoring staff conflicts of interest. However, its forms for staff to disclose conflicts of interest on specific events they are working on are ambiguous. DNSW's management of gifts and benefits broadly complies with the minimum standards set by the Public Service Commission, but there are some gaps in its implementation of these.

DNSW conducts an evaluation of each major event it supports. DNSW articulates expected outcomes in contracts with event organisers and uses a sound methodology to evaluate events. Internal reporting to its key decision-makers, including the CEO, the Board and the Minister is appropriate. However, DNSW does not publish detailed information about the events it funds or the outcomes of these events. This means that members of the public are unable to see whether its activities achieve value for money.

Appendix one – Response from Destination NSW

Appendix two – About the audit 

Appendix three – Performance auditing

 

Copyright Notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #332 - released 9 April 2020.

Published

Actions for Report on Local Government 2019

Report on Local Government 2019

Local Government
Asset valuation
Cyber security
Financial reporting
Information technology
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Service delivery
Shared services and collaboration
Workforce and capability

I am pleased to present my third report to the Parliament on the 2019 audits of local government councils in New South Wales.

This report notes that unqualified audit opinions were issued on the 2018–19 financial statements of 134 councils and 11 joint organisations. The opinion for one council was disclaimed and three audits are yet to complete.

The report also highlights improvements I have seen in financial reporting and governance arrangements across councils. Fewer errors were identified. More councils have audit, risk and improvement committees and internal audit functions. Risk management practices, including fraud control systems, have also improved.

These are very pleasing indicators of the gradual strengthening of governance and financial oversight of the sector. I want to acknowledge the investment councils have made in working with the Audit Office to improve consistency of practice and accountability generally.

Of course there is more work to do, particularly to prepare for new accounting standards and to strengthen controls over information technology and cyber security management. Asset management practices can also be improved. This report provides some guidance to council on these matters and we will continue to partner with the Office of Local Government in the Department of Planning, Industry and Environment to support good practice.

Margaret Crawford

Auditor-General
5 March 2020

This report focuses on key observations and findings from the 2018–19 financial audits of councils and joint organisations.

Unqualified audit opinions were issued on the financial statements for 134 councils and 11 joint organisations. The audit opinion for Bayside’s 2017–18 and 2018–19 financial statements were disclaimed. Three audits are still in progress and will be included in next year’s report.

The report highlights a number of areas where there has been improvement. There was a reduction in errors identified in council financial statements and high risk issues reported in audit management letters. More councils have audit, risk and improvement committees and internal audit functions. Risk management practices and fraud control systems have also improved.

The report also found that councils could do more to be better prepared for the new accounting standards, asset management practices could be strengthened, and information technology controls and cyber security management could be improved.

The Auditor-General recommended that the Office of Local Government within the Department of Planning, Industry and Environment develop a cyber security policy by 30 June 2021 to ensure a consistent response to cyber security risks across councils.

Read the PDF Report

Financial reporting is an important element of good governance. Confidence in and transparency of public sector decision making is enhanced when financial reporting is accurate and timely. Strong financial performance provides the platform for councils to deliver services and respond to community needs.

This chapter outlines our audit observations on the financial reporting and performance of councils and joint organisations.

Section highlights
  • There was a reduction in the number and dollar value of errors identified in councils' financial statements.
  • We continue to identify prior period errors, which are predominantly asset-related.
  • Unqualified audit opinions were issued for 99 per cent of completed audits for councils and joint organisations.
  • Three audits remain outstanding, with the outcomes to be reported in next year's Report to Parliament.
  • Seventy-nine per cent of councils and joint organisations lodged their financial reports by 31 October 2019.
  • Councils that performed some early reporting procedures achieved better outcomes in terms of the quality and timeliness of financial reporting.
  • Councils are at various levels of preparedness to implement the new accounting standards for the 2019–20 financial year. Some have made the necessary modifications to systems and processes, but others are still assessing impacts.
  • Most councils met the prescribed benchmarks for the liquidity and working capital performance measures over the past three years.
  • More councils reported negative operating performance compared with the prior year, meaning their operating expenditure exceeded their operating revenue.

Strong governance systems and internal controls help councils to operate effectively and efficiently, produce reliable financial reports, comply with laws and regulations and support ethical government.

This chapter outlines the overall trends related to governance and internal control issues across councils and joint organisations for 2018–19.

Section highlights
  • While the total number of issues reported in our management letters increased compared with the prior year, the total number of high risk issues have decreased. Of the high-risk issues, 41 per cent were deficiencies in information technology controls.
  • More councils have established audit, risk and improvement committees and internal audit functions.
  • Councils have improved risk management practices, with over 75 per cent of councils now having a risk management policy and register.
  • While most councils have policies and processes to manage gifts and benefits, we identified some instances of non-compliance with the Model Code of Conduct.
  • Most councils have policies and processes to manage the use of credit cards.
  • Councils can strengthen policies and practices for managing fraud controls and legislative compliance.
  • There are further opportunities for councils to improve internal controls over revenue, purchasing, payroll, cash, financial accounting and governance processes.

Councils rely on information technology (IT) to deliver services and manage information. While IT delivers considerable benefits, it also presents risks that council needs to address.

In prior years, we reported that councils need to improve IT governance and controls to manage key financial systems. This chapter outlines the progress made by councils in the management of key IT risks and controls, with an added focus on cyber security.

Section highlights
  • We continue to report deficiencies in information technology controls, particularly around user access management. These controls are key to ensuring IT systems are protected from inappropriate access and misuse.
  • Many councils do not have IT policies and procedures and others do not identify, monitor or report on IT risks.
  • Cyber security management requires improvement, with some basic elements of governance not yet in place for many councils.

Councils are responsible for managing a significant range of assets to deliver services on behalf of the community.

This chapter outlines our asset management observations across councils and joint organisations.

Section highlights
  • There was an increase in the total number of issues reported in our management letters for asset management processes.
  • There were less high-risk issues reported compared to the previous year.
  • We continue to identify discrepancies between the council's Crown land asset records and the Crown Land Information Database (CLID) managed by the former Department of Industry (DOI).
  • Inconsistent practices remain across the Local Government sector in accounting for landfill sites.

Appendix one – Response from the Office of Local Government within the Department of Planning, Industry and Environment

Appendix two – Status of 2018 recommendations

Appendix three – Status of audits 

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Newcastle Urban Transformation and Transport Program

Newcastle Urban Transformation and Transport Program

Transport
Planning
Compliance
Infrastructure
Management and administration
Procurement
Project management

The urban renewal projects on former railway land in the Newcastle city centre are well targeted to support the objectives of the Newcastle Urban Transformation and Transport Program (the Program), according to a report released today by the Auditor-General for New South Wales, Margaret Crawford. The planned uses of the former railway land achieve a balance between the economic and social objectives of the Program at a reasonable cost to the government. However, the evidence that the cost of the light rail will be justified by its contribution to the Program is not convincing.

The Newcastle Urban Transformation and Transport Program (the Program) is an urban renewal and transport program in the Newcastle city centre. The Hunter and Central Coast Development Corporation (HCCDC) has led the Program since 2017. UrbanGrowth NSW led the Program from 2014 until 2017. Transport for NSW has been responsible for delivering the transport parts of the Program since the Program commenced. All references to HCCDC in this report relate to both HCCDC and its predecessor, the Hunter Development Corporation. All references to UrbanGrowth NSW in this report relate only to its Newcastle office from 2014 to 2017.

This audit had two objectives:

  1. To assess the economy of the approach chosen to achieve the objectives of the Program.
  2. To assess the effectiveness of the consultation and oversight of the Program.

We addressed the audit objectives by answering the following questions:

a) Was the decision to build light rail an economical option for achieving Program objectives?
b) Has the best value been obtained for the use of the former railway land?
c) Was good practice used in consultation on key Program decisions?
d) Did governance arrangements support delivery of the program?

Conclusion
1. The urban renewal projects on the former railway land are well targeted to support the objectives of the Program. However, there is insufficient evidence that the cost of the light rail will be justified by its contribution to Program objectives.

The planned uses of the former railway land achieve a balance between the economic and social objectives of the Program at a reasonable cost to the Government. HCCDC, and previously UrbanGrowth NSW, identified and considered options for land use that would best meet Program objectives. Required probity processes were followed for developments that involved financial transactions. Our audit did not assess the achievement of these objectives because none of the projects have been completed yet.

Analysis presented in the Program business case and other planning documents showed that the light rail would have small transport benefits and was expected to make a modest contribution to broader Program objectives. Analysis in the Program business case argued that despite this, the light rail was justified because it would attract investment and promote economic development around the route. The Program business case referred to several international examples to support this argument, but did not make a convincing case that these examples were comparable to the proposed light rail in Newcastle.

The audited agencies argue that the contribution of light rail cannot be assessed separately because it is a part of a broader Program. The cost of the light rail makes up around 53 per cent of the total Program funding. Given the cost of the light rail, agencies need to be able to demonstrate that this investment provides value for money by making a measurable contribution to the Program objectives.

2. Consultation and oversight were mostly effective during the implementation stages of the Program. There were weaknesses in both areas in the planning stages.

Consultations about the urban renewal activities from around 2015 onward followed good practice standards. These consultations were based on an internationally accepted framework and met their stated objectives. Community consultations on the decision to close the train line were held in 2006 and 2009. However, the final decision in 2012 was made without a specific community consultation. There was no community consultation on the decision to build a light rail.

The governance arrangements that were in place during the planning stages of the Program did not provide effective oversight. This meant there was not a single agreed set of Program objectives until 2016 and roles and responsibilities for the Program were not clear. Leadership and oversight improved during the implementation phase of the Program. Roles and responsibilities were clarified and a multi-agency steering committee was established to resolve issues that needed multi-agency coordination.
The light rail is not justified by conventional cost-benefit analysis and there is insufficient evidence that the indirect contribution of light rail to achieving the economic development objectives of the Program will justify the cost.
Analysis presented in Program business cases and other planning documents showed that the light rail would have small transport benefits and was expected to make a modest contribution to broader Program objectives. Analysis in the Program business case argued that despite this, the light rail was justified because it would attract investment and promote economic development around the route. The Program business case referred to several international examples to support this argument, but did not make a convincing case that these examples were comparable to the proposed light rail in Newcastle.
The business case analysis of the benefits and costs of light rail was prepared after the decision to build light rail had been made and announced. Our previous reports, and recent reports by others, have emphasised the importance of completing thorough analysis before announcing infrastructure projects. Some advice provided after the initial light rail decision was announced was overly optimistic. It included benefits that cannot reasonably be attributed to light rail and underestimated the scope and cost of the project.
The audited agencies argue that the contribution of light rail cannot be assessed separately because it is part of a broader Program. The cost of the light rail makes up around 53 per cent of the total Program funding. Given the high cost of the light rail, we believe agencies need to be able to demonstrate that this investment provides value for money by making a measurable contribution to the Program objectives.

Recommendations
For future infrastructure programs, NSW Government agencies should support economical decision-making on infrastructure projects by:
  • providing balanced advice to decision makers on the benefits and risks of large infrastructure investments at all stages of the decision-making process
  • providing scope and cost estimates that are as accurate and complete as possible when initial funding decisions are being made
  • making business cases available to the public.​​​​​​
The planned uses of the former railway land achieve a balance between the economic and social objectives of the Program at a reasonable cost to the government.

The planned uses of the former railway land align with the objectives of encouraging people to visit and live in the city centre, creating attractive public spaces, and supporting growth in employment in the city. The transport benefits of the activities are less clear, because the light rail is the major transport project and this will not make significant improvements to transport in Newcastle.

The processes used for selling and leasing parts of the former railway land followed industry standards. Options for the former railway land were identified and assessed systematically. Competitive processes were used for most transactions and the required assessment and approval processes were followed. The sale of land to the University of Newcastle did not use a competitive process, but required processes for direct negotiations were followed.

Recommendation
By March 2019, the Hunter and Central Coast Development Corporation should:
  • work with relevant stakeholders to explore options for increasing the focus on the heritage objective of the Program in projects on the former railway land. This could include projects that recognise the cultural and industrial heritage of Newcastle.
Consultations about the urban renewal activities followed good practice standards, but consultation on transport decisions for the Program did not.

Consultations focusing on urban renewal options for the Program included a range of stakeholders and provided opportunities for input into decisions about the use of the former railway land. These consultations received mostly positive feedback from participants. Changes and additions were made to the objectives of the Program and specific projects in response to feedback received. 

There had been several decades of debate about the potential closure of the train line, including community consultations in 2006 and 2009. However, the final decision to close the train line was made and announced in 2012 without a specific community consultation. HCCDC states that consultation with industry and business representatives constitutes community consultation because industry representatives are also members of the community. This does not meet good practice standards because it is not a representative sample of the community.

There was no community consultation on the decision to build a light rail. There were subsequent opportunities for members of the community to comment on the implementation options, but the decision to build it had already been made. A community and industry consultation was held on which route the light rail should use, but the results of this were not made public. 

Recommendation
For future infrastructure programs, NSW Government agencies should consult with a wide range of stakeholders before major decisions are made and announced, and report publicly on the results and outcomes of consultations. 

The governance arrangements that were in place during the planning stages of the Program did not provide effective oversight. Project leadership and oversight improved during the implementation phase of the Program.

Multi-agency coordination and oversight were ineffective during the planning stages of the Program. Examples include: multiple versions of Program objectives being in circulation; unclear reporting lines for project management groups; and poor role definition for the initial advisory board. Program ownership was clarified in mid-2016 with the appointment of a new Program Director with clear accountability for the delivery of the Program. This was supported by the creation of a multi-agency steering committee that was more effective than previous oversight bodies.

The limitations that existed in multi-agency coordination and oversight had some negative consequences in important aspects of project management for the Program. This included whole-of-government benefits management and the coordination of work to mitigate impacts of the Program on small businesses.

Recommendations
For future infrastructure programs, NSW Government agencies should: 

  • develop and implement a benefits management approach from the beginning of a program to ensure responsibility for defining benefits and measuring their achievement is clear
  • establish whole-of-government oversight early in the program to guide major decisions. This should include:
    • agreeing on objectives and ensuring all agencies understand these
    • clearly defining roles and responsibilities for all agencies
    • establishing whole-of-government coordination for the assessment and mitigation of the impact of major construction projects on businesses and the community.

By March 2019, the Hunter and Central Coast Development Corporation should update and implement the Program Benefits Realisation Plan. This should include:

  • setting measurable targets for the desired benefits
  • clearly allocating ownership for achieving the desired benefits
  • monitoring progress toward achieving the desired benefits and reporting publicly on the results.

Appendix one - Response from agencies    

Appendix two - About the audit

Appendix three - Performance auditing

 

Parliamentary reference - Report number #310 - released 12 December 2018