Reports
Actions for Volume Twelve 2015 Part Two Water
Volume Twelve 2015 Part Two Water
The distributions to the NSW Government increased from $690 million in 2013-14 to $1.0 billion in 2014-15. The increase was largely due to a higher dividend from Sydney Water Corporation.
Actions for Large construction projects
Large construction projects
The independent assurance given to the NSW Government and sponsor agencies on the viability of large capital projects throughout their lifecycle is inadequate. Government policy is regularly not followed and not properly communicated to those responsible for implementing such policy.
This audit sought to test the effectiveness of the NSW capital project assurance system - which includes gateway reviews and reporting - but significant levels of non-compliance identified in our case studies prevented this. The NSW Commission of Audit also identified this issue in 2012. Gateway reviews are conducted by independent reviewers at key stages of a project’s life cycle and provide an independent assessment on a project’s readiness to proceed to the next stage.
Parliamentary reference - Report number #252 - released 7 May 2015
Actions for Areas of focus from 2014
Areas of focus from 2014
Actions for Volume Twelve 2014 Health
Volume Twelve 2014 Health
The quality of financial statements in the health cluster continues to improve with significantly fewer misstatements. The financial statements of all cluster agencies received unqualified audit opinions. Health has maintained or bettered its emergency triage performance and the percentage of patients admitted for elective surgery within clinically appropriate timeframes has improved.
Actions for Volume Eleven 2014 Focusing on Planning and Environment
Volume Eleven 2014 Focusing on Planning and Environment
The quality of financial reporting in the planning and environment cluster continues to improve with fewer reported misstatements over the last two years. The financial statements of all agencies within this cluster received unqualified audit opinions, except for one small agency where the audit is incomplete. Many cluster agencies’ actual revenues, expenses, assets and liabilities varied from budget by more than five per cent, suggesting financial management and budgetary controls could be improved.
Actions for Volume Eight 2014 Focusing on Police and Justice (Law, Order and Emergency Services)
Volume Eight 2014 Focusing on Police and Justice (Law, Order and Emergency Services)
The quality of financial reporting in the cluster continues to improve with the number of reported misstatements identified during audit decreasing over the past five years. The audits resulted in unqualified audit opinions on the financial statements of all cluster agencies for the year ended 30 June 2014, with the exception of the State Emergency Service.
Actions for Volume Five 2014 Focusing on Electricity and Water
Volume Five 2014 Focusing on Electricity and Water
In 2013-14, the NSW Government electricity businesses generated $9 billion in revenue ($9.6 billion during 2012-13) and achieved a combined net profit after tax of $1.5 billion ($1.6 billion). The combined profit after tax for NSW Distributors was $1.2 billion in 2013-14 down from $1.3 billion in 2012-13. The Distributors’ revenues decreased by $205 million to $6.8 billion in 2013-14, largely due to lower consumption by customers associated with milder weather conditions, economic impacts, energy efficiency measures and an increase in the number of customers using solar energy.
Actions for Volume Four 2014 focusing on New South Wales State Finances
Volume Four 2014 focusing on New South Wales State Finances
For the second consecutive year, the General Government and Total State Sector Accounts received an unqualified auditor’s opinion following more than a decade of qualifications. The quality and timeliness of financial reporting across the NSW public sector has continued to improve. Compared to previous years, there were fewer errors in agencies’ 2013–14 financial statements submitted for audit and used for whole-of-government financial reporting.
Actions for Managing Contaminated Sites
Managing Contaminated Sites
NSW Government agencies with large landholdings need to better manage their contaminated sites.
When contaminated sites are reported to the Environmental Protection Authority (EPA) there are long delays in assessing the extent of contamination. The EPA also lacks the management controls to ensure that all significantly contaminated sites are actively monitored and key milestones for remediation are met.
Parliamentary reference - Report number #245 - released 10 July 2014
Actions for Volume One 2014 - Areas of focus from 2013
Volume One 2014 - Areas of focus from 2013
Today the Auditor-General of New South Wales, Grant Hehir, released his Volume One Report to Parliament for 2014. The observations included in this report are designed to inform readers of common findings from the 2013 financial and performance audits so agencies and audit committees can use them to identify issues that may be relevant to their organisations.