Actions for Government's acquisition of private property: Sydney Metro project

Government's acquisition of private property: Sydney Metro project

Transport
Planning
Whole of Government
Compliance
Infrastructure
Internal controls and governance
Project management
Risk

What the report is about

Sydney Metro is Australia’s largest public transport project. It requires the acquisition of many private properties, including residential and business properties.

This audit assessed the effectiveness of the acquisition of private properties for the Sydney Metro project. The audited agencies were Sydney Metro, the Department of Planning and Environment (Valuer General NSW) and Transport for NSW (the Centre for Property Acquisition).

The audit assessed agencies against the framework for property acquisitions in New South Wales. It did not re-perform the valuations done for individual properties that were acquired by Sydney Metro.

What we found

Acquisitions of private property for the Sydney Metro project were mostly effective in the sample of acquisitions we assessed. We found Sydney Metro:

  • complied with legislative and policy requirements for compensation and communication with people subject to property acquisitions
  • kept accurate records of its acquisitions and applied probity controls consistently
  • did not complete detailed plans or negotiation strategies for the high-risk and high-value acquisitions we reviewed
  • did not comply with legislative timelines for most compulsory acquisitions because of delays in receiving the required information from the Valuer General in these cases.

The Centre for Property Acquisition has overseen the implementation of reforms to residential acquisition processes, but its assessment of the effectiveness of these reforms has not been comprehensive.

What we recommended

The audit made four recommendations to the audited agencies to improve:

  • plans and strategies for the acquisition of high-risk and high-value properties
  • timeliness of issuing compensation determinations for compulsory acquisitions
  • data quality on the experience of people subject to property acquisitions.

The NSW Government has the power to acquire land that is owned or leased by individuals or businesses, if it is needed for a public purpose. The power arises from the Land Acquisition (Just Terms Compensation) Act 1991 (the Just Terms Act). Government agencies that have the power to compulsorily acquire private property are referred to as ‘acquiring authorities’. People who are subject to acquisitions are referred to as ‘affected parties’ and include property owners (business or residential), businesses with a commercial lease on a property, or individuals with residential tenancy leases. In recent years, the vast majority of acquisitions by the NSW Government have been for public transport or road projects.

Sydney Metro is a NSW Government agency with responsibility for building the Sydney Metro railway project. Sydney Metro is Australia’s largest public transport project. The project requires the acquisition of a large number of private properties. Sydney Metro has been one of the largest acquirers of private property in recent years, completing over 500 acquisitions between 2020 and mid-2022, with a total acquisition value of over $2 billion. Other agencies and statutory officers involved in the acquisition of property for the Sydney Metro project include:

  • the Department of Planning and Environment (DPE), which supports the minister responsible for the Just Terms Act. DPE also provides staff to the Valuer General of NSW
  • the Valuer General of NSW, an independent statutory officer that determines compensation in cases where the acquiring authority and the affected party cannot agree on compensation for property that has been acquired
  • Transport for NSW, which includes the Centre for Property Acquisition (CPA). The CPA does not have a direct role in acquiring properties, but its responsibilities include developing guidance for acquiring agencies and monitoring and reporting on their activities.

About this audit

The objective of this audit was to assess the effectiveness of acquisitions of private properties for Sydney Metro projects. The audit assessed agencies against the legislative and policy requirements in place for government acquisitions of private property in New South Wales. In line with the Audit Office's legislative mandate, the audit does not comment on the merits of the policy objectives reflected in the Just Terms Act.

The audit examined a sample of 20 property acquisitions. This was not a statistically representative sample. While our report provides comments on Sydney Metro’s overall acquisition processes, it does not provide assurance regarding the acquisitions that were not examined for this audit.

The audit did not re-perform the valuations done for individual properties that were acquired by Sydney Metro. Affected parties who disagree with the valuation of their property have the right to seek independent assessment of this via the Valuer General and the Land and Environment Court.

Conclusion

Acquisitions of property for the Sydney Metro project were mostly effective in the sample of acquisitions we assessed. Sydney Metro followed requirements for communication with affected parties. Compensation processes were conducted in compliance with legislative requirements, but compensation determinations for compulsory acquisitions were not completed within legislated time frames due to delays in receiving these from the Valuer General. Governance and probity processes were followed consistently, with some relatively minor exceptions. 

Sydney Metro has detailed guidelines for acquisitions that are based on relevant legislation and government policy. In the 20 acquisitions we assessed for this audit, these procedures were followed consistently. This included adhering to minimum timelines for negotiation periods, engaging independent valuers and other experts when needed, and complying with governance and probity processes.

Sydney Metro staff followed requirements for communication and support for residential acquisitions by assigning ‘personal managers’ and providing additional support to affected parties when needed. The Centre for Property Acquisition (CPA) has overseen reforms to the residential property acquisition process in recent years. These reforms include the introduction of the NSW Property Acquisition Standards and the use of personal managers, in addition to the existing acquisition managers, for residential acquisitions. However, the CPA has not assessed the impact of these changes on the experiences on people affected by property acquisitions.

Sydney Metro did not comply with the legislative requirement to provide a formal compensation notice to the affected party within 45 days of a compulsory acquisition starting in any of the eight relevant acquisitions in our sample. This was because Sydney Metro must wait for the Valuer General to complete a compensation determination before Sydney Metro can send the compensation notice, and the Valuer General did not do this within 45 days. We acknowledge that Sydney Metro does not have full control over this process, and that it has taken steps to mitigate the impact of delays on affected parties. 

This chapter presents our findings on Sydney Metro's acquisition of industrial and commercial properties. Industrial properties include construction businesses and manufacturing facilities. Commercial properties were mostly properties such as shopping centres and office towers. Many of these acquisitions involve businesses and properties that are relatively complex and have high values. This means the valuation process can require multiple experts and can be lengthy and contested. Adherence to governance and probity requirements is important for these acquisitions in order to demonstrate that the acquiring authority has achieved value for money.

This chapter presents our findings on Sydney Metro's acquisition of residential properties, which include apartments and houses, and small business leases, which mostly affected businesses in small shopping centres or arcades. Most of these acquisitions were lower value compared to industrial and commercial property acquisitions and did not require as much expert advice on complex technical issues. However, residential property acquisitions can be personally distressing for the affected parties and require staff from the acquiring authority to provide support and show empathy while ensuring legislative compliance and value for money.

Appendix one – Responses from agencies

Appendix two – About the audit 

Appendix three – Performance auditing 

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #375 - released 9 February 2023

Published

Actions for Design and implementation of the Transport Asset Holding Entity

Design and implementation of the Transport Asset Holding Entity

Transport
Treasury
Asset valuation
Financial reporting
Infrastructure
Procurement
Risk
Service delivery

What the report is about

The Transport Asset Holding Entity (TAHE) is the State's custodian of rail assets. It is a state owned corporation and commenced operating on 1 July 2020.

This audit assessed the effectiveness of NSW Government agencies' design and implementation of TAHE. We audited TAHE, Transport for NSW (TfNSW) and NSW Treasury.

Separate and related audits on TAHE are reported in 'State Finances 2022', 'State Finances 2021' and 'Transport and Infrastructure 2022' reports.

What we found

The design and implementation of TAHE, which spanned seven years, was not effective.

The process was not cohesive or transparent. It delivered an outcome that is unnecessarily complex in order to support an accounting treatment to meet the NSW Government's short-term Budget objectives, while creating an obligation for future governments.

The benefits of TAHE were claimed in the 2015–16 NSW Budget before the enabling legislation was passed by Parliament in 2017. This committed the agencies to implement a solution that justified the 2015–16 Budget impacts, regardless of any challenges that arose.

Rail safety arrangements were a priority throughout TAHE's design and implementation, and risks were raised and addressed.

Agencies relied heavily on consultants on matters related to the creation of TAHE, but failed to effectively manage these engagements. Agencies failed to ensure that consultancies delivered independent advice as an input to decision-making. A small number of firms were used repeatedly to provide advice on the same topic. The final cost of TAHE-related consultancies was $22.6 million compared to the initial estimated cost of $12.9 million.

What we recommended

We recommended that the audited agencies should:

  • improve accountability and transparency for major new fiscal transformation initiatives
  • ensure entities do not reflect the financial impact of significant initiatives in the Budget when there is uncertainty, or it creates perverse incentives
  • review record keeping practices, systems and policies to ensure compliance with the State Records Act 1998, and the NSW Government Information Classification, Labelling and Handling Guidelines
  • review procurement policies to ensure that consultant use complies with all NSW Government policy requirements.

The NSW Government established the Transport Asset Holding Entity (TAHE), a statutory State Owned Corporation (SOC), on 1 July 2020 to replace the former rail infrastructure owner – RailCorp. It is the State's custodian of rail network assets, including rail tracks and other infrastructure, rolling stock, land, train stations and facilities, retail space, and signal and power systems, within metropolitan and regional New South Wales. It is responsible for $2.8 billion of major capital projects in 2022–23.

TAHE was established under Part 2 of the Transport Administration Act 1988 and is governed by a decision-making board. The Treasurer and the Minister for Finance and Employee Relations are the Shareholding Ministers of TAHE, and they annually agree performance expectations articulated in a Statement of Corporate Intent.

Whereas TAHE is the custodian of rail assets, Sydney Trains and NSW Trains operate public rail services. TAHE does not have responsibility for the operation of the heavy rail network or train services, nor does it have network control functions. TAHE, Sydney Trains and NSW Trains are in the Transport and Infrastructure cluster in the public sector (formerly the Transport cluster and renamed in April 2022), which also includes Sydney Metro and Transport for NSW (TfNSW).

TfNSW leads the Transport and Infrastructure cluster. Its role is to set the strategic direction for transport across the State. This involves the shaping of planning, policy, strategy, regulation, resource allocation and other service and non-service delivery functions for all modes of transport.

TAHE's Operating Licence is granted by the Portfolio Minister and authorises the entity to perform the functions required to acquire, develop, finance, divest and hold assets, pursuant to the Transport Administration Act 1988. The Portfolio Minister also issues a Statement of Expectations which outlines the government’s expectation for the business for the next three to five years.

TAHE's original Portfolio Minister was the Minister for Transport who approved, on 30 June 2020, the issuing of an interim 12-month Operating Licence to enable TAHE to commence operating on 1 July 2020. The Portfolio Minister then granted TAHE's current Operating Licence in 2021. After TAHE requested a 12-month extension to its current Operating Licence, its next Operating Licence is due on 1 July 2024. The current Portfolio Minister is the Minister for Infrastructure, Cities and Active Transport.

About this audit

This audit assessed the effectiveness of NSW Government agencies' design and implementation of TAHE. In making this assessment, we considered whether: 

  • the process of designing and implementing TAHE was cohesive and transparent, and delivered an effective outcome
  • agencies' roles and responsibilities were clear in the planning of TAHE
  • agencies effectively identified and managed certain risks.

Conclusion

The design and implementation of TAHE was not effective. The process was not cohesive or transparent. It delivered an outcome that is unnecessarily complex in order to meet the NSW Government's short-term Budget objectives, while creating an obligation for future governments to sustain TAHE through continuing investment, and funding of the state owned rail operators. The ineffective process to design TAHE delivered a model that entails significant uncertainty as to whether the anticipated longer-term financial improvements to the Budget position can be achieved or sustained.

NSW Treasury and TfNSW had different objectives for TAHE

Up to June 2013, RailCorp had been the owner and operator of rail services and maintainer of the metropolitan rail network for almost a decade. It had been operating as a not-for-profit Public Non-Financial Corporation (PNFC).

In 2012, NSW Treasury (hereafter Treasury) decided there was a risk that the Australian Bureau of Statistics (ABS) would reclassify RailCorp to the General Government Sector (GGS), meaning depreciation expenses of approximately $870 million would be reflected in the GGS Budget. Treasury wanted to avoid this impact on the GGS Budget, and considered the establishment of a transport asset holding entity as a means to do so. Capital grants to RailCorp were being treated as an expense to the GGS Budget.

TfNSW also wanted an asset holding entity – but one that would be a non-trading ‘shell’ company with no staff that would hold and manage all public transport assets. TfNSW's concept envisaged the entity would have a structure that would enable future public transport reforms and strategic directions while ensuring vertical integration of operations between asset owners and the rail operators to maintain rail safety.

However, Treasury pursued its objective to improve the GGS Budget result, and sought to expand on TfNSW's 'shell' asset holding entity concept. Treasury wanted an entity that could generate a return on investment, as this meant that government investment in transport assets could be treated as equity investments, rather than a Budget expense, and in turn improve the GGS Budget position. As an example of the potential impact of creating this new entity, capital grants of $2.3 billion were paid to RailCorp in 2013–14. If Treasury's objective was met, grants of this significance would then be treated as an equity investment, rather than an expense in the GGS Budget.

In 2017, Treasury's preferred option was progressed through legislation, but both agencies' central objectives for the proposed asset holding entity would continue to prove difficult to reconcile. To achieve Treasury's objective to improve the Budget result, the entity would need to generate a return on investment (this is further discussed below). However, TfNSW expressed concerns that the prioritisation of rail safety, and the effective management of governance, regulation and operations would be more complex in an entity with commercial imperatives.

Asset holding entities are a common approach to the management of transport assets in Australia and internationally, and there are a range of approaches to how they are structured and used. Such structures should be driven by the goal of improved asset management. Ultimately, TfNSW's objectives could have been delivered through a simpler entity structure. However, reconciling TfNSW's objectives with Treasury's imperative to deliver and justify a Budget improvement in the short-term resulted in an overly lengthy process and an unnecessarily complex outcome that places an obligation on future governments to sustain. There is still significant uncertainty as to whether the short-term improvements to the Budget can continue to be realised in the longer-term.

The Budget benefits of TAHE were claimed before the entity was legislated, committing the agencies to deliver, regardless of the complexities that subsequently arose

The 2015–16 GGS Budget treated the government's investment in TAHE (still known at this time as RailCorp) as an equity contribution. This had the immediate impact of improving the Budget result by $1.8 billion per annum. However, the legislation to enable the establishment of TAHE had not yet been passed by Parliament, key elements of the operating model were still under development, and imminent changes in accounting standards had the potential to impact TAHE's financial model. The decision to book the benefits in the Budget early committed the involved agencies to implement a solution that justified the 2015–16 Budget impacts, irrespective of the challenges that arose. 

TAHE's financial structure requires circular government investment to work

For the NSW Government to continue to treat its investment in TAHE as an equity contribution, rather than an expense to the Budget, there must be a reasonable expectation that TAHE will generate a sufficient rate of return as required by the Government Finance Statistics (GFS) framework. In doing so, it needs to recover a revaluation loss created by a $20.3 billion reduction in the value of its assets which was incurred in its first full year of operation. This loss occurred as a result of a revaluation of TAHE's assets when RailCorp (a not-for profit entity) became TAHE (a for-profit commercial entity) – and is discussed further in the 'Key findings' below.

TAHE generates a small portion of its income from transactions with the private sector but, as noted in our report 'State Finances 2021', TAHE receives the majority of its revenue (more than 80%) from access and licence fee agreements with Sydney Trains and NSW Trains. Both of these entities are funded by grants (a Budget expense) to TfNSW from the GGS Budget.

Based on Treasury’s correspondence with the ABS in 2015, TAHE was initially expected to pay a return on equity of 7% in 2016–17. The assumption of a 7% return persisted through to 2018, after the legislation enabling the establishment of TAHE was passed by Parliament. However, when the initial access and licence fees were agreed on 1 July 2020, this figure had been revised to an expected rate of return of 1.5% excluding the revaluation loss. This was below the long-term inflation target and did not include the recovery of the revaluation loss – risking the government's ability to treat its investment in TAHE as an equity contribution. Importantly, as TAHE is primarily reliant on fees paid by the state owned rail operators that, in turn, are funded by the GGS Budget (as an expense), the decision to change the returns model from 7% to 1.5% would in its own right have had a positive impact on the GGS Budget. However, the decision to use a 1.5% return would ultimately be problematic as it made it difficult to treat the government's contributions to TAHE as an equity investment, as discussed below.

On 14 December 2021, to avoid a qualified audit opinion, the NSW Government made the decision to increase TAHE's expected rate of return to 2.5%, equal to the Reserve Bank’s long-term inflation target.

In 2021-22, TAHE needed to start charging rail operators higher access and licence fees in order to generate a return of 2.5%, so as to support the government's treatment of its investment in TAHE as an equity contribution in the GGS Budget. This meant the government needed to provide additional grant (expense) funding to the state owned rail operators so they could pay the increased access and licence fees to TAHE. Based on current projections, TAHE is not expected to recover the revaluation loss until 2046.

There remains a risk that TAHE will not be able to generate a sufficient return on the NSW Government's investment without relying on increased funding to state owned rail operators so that they can in turn pay the higher access and licence fees. TAHE's ability to generate returns on government investment from other sources are uncertain and may not be achievable or sustainable. Current modelling highlights that TAHE remains largely reliant, through to 2046, on increasing fees (which are assumed to increase at 2.5% per annum from 2031 onwards when the current 10 year contracts with rail operators expire) paid by the state owned rail operators that remain principally reliant on GGS Budget grants.

The process of designing and implementing TAHE was not transparent to independent scrutiny

Our report 'State Finances 2021' commented that Treasury did not always provide this Office with information relating to TAHE on a timely basis. Similarly, during this performance audit, there were also multiple instances where auditees were unable to provide documentation regarding key activities in the process to deliver TAHE. Agencies also applied higher sensitivity classifications to large tranches of documents than was justified or required by policy. Of particular concern is the incorrect classification of documents as Cabinet sensitive information. The incorrect or over-classification of documentation as Cabinet sensitive delayed this Office's ability to provide scrutiny or independent assurance.

There was a lack of clarity around the roles and responsibilities of governance structures set up to oversee the design and implementation of TAHE

From 2014, multiple workstreams and advisory committees were established to progress the design and implementation of TAHE. For some of these committees and workstreams, there is limited information on what they were tasked to do and what they achieved. Most had ceased meeting by 2018, before significant work needed to deliver TAHE was completed.

The lack of clarity around the roles and responsibilities of these governance structures reduced opportunities for TfNSW and Treasury to reconcile their differing objectives for TAHE, and resolve key questions earlier in the process.

There was a heavy reliance on consulting firms throughout the process to establish TAHE, and the management of consultant engagements failed to ensure that agencies received independent advice to support objective decision-making

In 2020, Treasury and TfNSW failed to prevent, identify, or adequately manage a conflict of interest when they engaged the same 'Big 4' consulting firm to work on separate TAHE-related projects. Both agencies used the firm's work to further their respective views with regard to the financial implications of TAHE's operating model. At this time those views were still unreconciled.

Treasury engaged the firm to provide a fiscal risk management strategy and advice on the impact of changes to accounting standards. TfNSW engaged the same firm to develop operating and financial models for TAHE, which raised concerns regarding the viability of TAHE. Disputes arose around the findings of these reports. Treasury disagreed with some of the outcomes of the work commissioned by TfNSW, relating to accounting treatment and fiscal advice.

The management of this conflict (real or perceived) was left to the 'Big 4' consulting firm when it was more appropriate for it to be managed by Treasury and TfNSW. If these agencies had communicated more effectively, used available governance structures consistently, and shared information openly about their use of the firm and the nature of their respective engagements, these disputes might have been avoided. This issue, coupled with deficiencies in procurement by both agencies, reflected and further perpetuated the lack of cohesion in the design and implementation of TAHE.

More broadly, over the period 2014 – 2021, 16 separate consulting firms were employed to work on 36 contracts, valued at over $22.56 million, relating to TAHE ranging from accounting and legal advice, project management, and the provision of administrative support and secretariat services.

Consultants are legitimately used by agencies to provide advice on how to achieve the outcomes determined by government, including advising agencies on the risks and challenges in achieving those outcomes. Similarly, consultants can provide expert knowledge in the service of achieving those outcomes and managing the risks. However, the heavy reliance on consulting firms during the design and implementation of TAHE heightened the risk that agencies were not receiving value for money, were outsourcing tasks that should be performed by the public service, and did not mitigate the risk that the advice received was not objective and impartial. The risk that the role of consultants could have been blurred between providing independent advice to government on options and facilitating a pre-determined outcome was not effectively treated or mitigated. This risk was amplified because a small number of firms were used repeatedly to provide advice on one topic. The effective procurement and management of consultants is an obligation of government agencies.

Appendix one – Responses from audited agencies, and Audit Office clarification of matters raised in the TAHE formal response 

Appendix two – Classification of government entities 

Appendix three – About the audit 

Appendix four – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #372 - released 24 January 2023

 

Published

Actions for Coordination of the response to COVID-19 (June to November 2021)

Coordination of the response to COVID-19 (June to November 2021)

Premier and Cabinet
Community Services
Health
Justice
Whole of Government
Internal controls and governance
Risk
Service delivery
Shared services and collaboration

What the report is about

This audit assessed the effectiveness of NSW Government agencies’ coordination of the response to COVID-19, with a focus on the Delta variant outbreak in the Dubbo and Fairfield Local Government Areas (LGA) between June and November 2021. We audited five agencies - the Department of Premier and Cabinet, NSW Health, the NSW Police Force, Resilience NSW and the Department of Customer Service.

The audit also considered relevant planning and preparation activities that occurred prior to June 2021 to examine how emergency management and public health responses learned from previous events.

What we found

Prior to Delta, agencies developed capability to respond to COVID-19 related challenges.

However, lessons learned from prior reviews of emergency management arrangements, and from other jurisdictions, had not been implemented when Delta emerged in June 2021. As a result, agencies were not as fully prepared as they could have been to respond to the additional challenges presented by Delta.

Gaps in emergency management plans affected agencies' ability to support individuals, families and businesses impacted by restrictions to movement and gathering such as stay-at-home orders. In LGAs of concern, modest delays of a few days had a significant impact on people, especially those most vulnerable.

On 23 July 2021, the NSW Government established a cross-government coordinating approach, the Delta Microstrategy, which complemented existing emergency management arrangements, improved coordination between NSW Government agencies and led to more effective local responses.

Where possible, advice provided to government was supported by cross-government consultation, up-to-date evidence and insights. Public Health Orders were updated as the response to Delta intensified or to address unintended consequences of previous orders. The frequency of changes hampered agencies' ability to effectively communicate changes to frontline staff and the community in a rapidly evolving situation.

The NSW Government could provide greater transparency and accountability over decisions to apply Public Health Orders during a pandemic.

What we recommended

The audit made seven recommendations intended to improve transparency, accountability and preparedness for future emergency events.

This audit assessed the effectiveness of NSW Government agencies’ coordination (focused on the Department of Premier and Cabinet, NSW Health, the NSW Police Force, Resilience NSW and the Department of Customer Service) of the COVID-19 response in selected Local Government Areas (Fairfield City Council and Dubbo Regional Council) between June and November 2021.

As noted in this report, Resilience NSW was responsible for the coordination of welfare services as part of the emergency management arrangements. On 16 December 2022, the NSW Government abolished Resilience NSW.

During the audited period, Resilience NSW was tasked with supporting the needs of communities subject to stay-at-home orders or stricter restrictions and it provided secretariat support to the State Emergency Management Committee (SEMC). The SEMC was, and remains, responsible for the coordination and oversight of emergency management policy and preparedness.

Our work for this performance audit was completed on 15 November 2022, when we issued the final report to the five audited agencies. While the audit report does not make specific recommendations to Resilience NSW, it does include five recommendations to the State Emergency Management Committee. On 8 December 2022, the then Commissioner of Resilience NSW provided a response to the final report, which we include as it is the formal response from the audited entity at the time the audit was conducted.

The community of New South Wales has experienced significant emergency events during the past three years. COVID-19 first emerged in New South Wales after bushfire and flooding emergencies in 2019–20. The pandemic is now into its third year, and there have been further extreme weather and flooding events during 2021 and 2022.

Lessons taken from the experience of these events are important to informing future responses and reducing future risks to the community from emergencies.

This audit focuses on the NSW Government's response to the COVID-19 pandemic, and in particular, the Delta variant (Delta) that occurred between June and November 2021. The response to the Delta represents six months of heightened challenges for the NSW Government.

Government responses to emergencies are guided by legislation. The State Emergency and Rescue Management Act 1989 (SERM Act) establishes emergency management arrangements in New South Wales and covers:

  • coordination at state, regional and local levels through emergency management committees
  • emergency management plans, supporting plans and functional areas including the State Emergency Management Plan (EMPLAN)
  • operations centres and controllers at state, regional and local levels.

This audit focuses on the activities of five agencies during the audit period:

  • The NSW Police Force led the emergency management response and was responsible for coordinating agencies across government in providing the tactical and operational elements that supported and enhanced the health response to the pandemic. The NSW Police Force also led the compliance response which enforced Public Health Orders and included household checks on those required to isolate at home after testing positive to COVID-19. In some parts of NSW, they were supported by the Australian Defence Force in this role.
  • NSW Health was responsible for leading the health response which coordinated all parts of the health system, initially to prevent, and then to manage, the pandemic.
  • Resilience NSW coordinated welfare services as part of the emergency management arrangements and provided secretariat support to the State Emergency Management Committee (SEMC). The SEMC is responsible for the coordination and oversight of emergency management policy and preparedness. Resilience NSW was also tasked with supporting the needs of communities subject to stay-at-home orders or stricter restrictions.
  • The Department of Customer Service (DCS) was responsible for the statewide strategic communications response.
  • The Department of Premier and Cabinet (DPC) held a key role in providing policy and legal services, as well as supporting the coordination of activity across a range of functional areas and decision-making by our State’s leaders.

This audit assessed the effectiveness of NSW Government agencies’ coordination (focused on the Department of Premier and Cabinet, NSW Health, the NSW Police Force, Resilience NSW and the Department of Customer Service) of the COVID-19 response in selected Local Government Areas (LGA) (Fairfield City Council and Dubbo Regional Council) after June 2021.

The audit investigated whether:

  • government decisions to apply LGA-specific Public Health Orders were supported by effective crisis management governance and planning frameworks
  • agencies effectively coordinated in the communication (and enforcement) of Public Health Orders.

While focusing on the coordination of NSW Government agencies’ response to the Delta variant in June through to November 2021, the audit also considered relevant planning and preparation activities that occurred prior to June 2021 to examine how emergency management and public health responses learned from previous events.

This audit does not assess the effectiveness of other specific COVID-19 responses such as business support. It refers to the preparedness, planning and delivery of these activities in the context of supporting communities in selected LGAs. NSW Health's contribution to the Australian COVID-19 vaccine rollout was also subject to a separate audit titled 'New South Wales COVID-19 vaccine rollout' tabled in NSW Parliament on 7 December 2022. 

This audit is part of a series of audits which have been completed, or are in progress, regarding the New South Wales COVID-19 emergency response. The Audit Office of New South Wales '2022–2025 Annual Work Program' details the ongoing focus our audits will have on providing assurance on the effectiveness of emergency responses.

In this document Aboriginal refers to the First Nations peoples of the land and waters now called Australia, and includes Aboriginal and Torres Strait Islander peoples.

Conclusion

Prior to June 2021, agencies worked effectively together to adapt and refine pre-existing emergency management arrangements to respond to COVID-19. However, lessons learned from prior reviews of emergency management arrangements, and from other jurisdictions, had not been implemented when Delta emerged in June 2021. As a result, agencies were not as fully prepared as they could have been to respond to the additional challenges presented by Delta.

In the period March 2020 to June 2021, the State's Emergency Management (EM) arrangements coordinated the New South Wales emergency response to COVID-19 with support from the Department of Premier and Cabinet (DPC) which led the cross-government COVID-19 Taskforce. NSW Government agencies enhanced the EM arrangements, which until then had typically been activated in response to natural disasters, to meet the specific circumstances of the pandemic.

However, the State Emergency Management Committee (SEMC), supported by Resilience NSW, did not address relevant recommendations arising from the 2020 Bushfires Inquiry before June 2021 and agencies did not always integrate lessons learned from other jurisdictions or scenario training exercises into emergency management plans or strategies before Delta. As a result, deficiencies in the EM arrangements, including representation of vulnerable communities on EM bodies, well-being support for multicultural communities in locked down environments and cross-agency information sharing, persisted when Delta emerged in June 2021.

It should be noted that for the purposes of this audit there is no benchmark, informed by precedent, that articulates what level of preparation would have been sufficient or proportionate. However, the steps required to address these gaps were reasonable and achievable, and the failure to do so meant that agencies were not as fully prepared as they could have been for the scale and escalation of Delta’s spread across the State.

The Delta Microstrategy complemented the EM arrangements to support greater coordination and agencies are working to improve their capability for future events

The Delta Microstrategy (the Microstrategy) led to innovations in information sharing and collaboration across the public service. Agencies involved in the response have completed, or are completing, reviews of their contribution to the response. That said, none of these reviews includes a focus on whole-of-government coordination.

On 23 July 2021, the NSW Government approved the establishment of the Microstrategy to respond to the additional challenges presented by Delta including the need to support communities most impacted by restrictions to movement and gathering in the LGAs of concern. An extensive range of government agencies were represented across eight Microstrategy workstreams, which coordinated with the existing EM arrangements to deliver targeted strategies to communities in high-risk locations and improve data and information sharing across government. This enhanced the public health, compliance, income and food support, communications and community engagement aspects of the response.

Agencies also leveraged learnings from early weeks of the Delta wave and were able to replicate those lessons in other locations. The use of pre-staging hubs in Fairfield to support food and personal hamper distribution was used a month later in Dubbo which acted as a central hub for more remote parts of the State.

Emergency management plans did not enable government to respond immediately to support vulnerable communities in high-risk LGAs or regional NSW

There are gaps in the emergency management plans relating to the support for individuals, families and businesses impacted by the stay-at-home orders and other restrictions to movement and gathering. These gaps affected agencies' ability to respond immediately when the need arose during Delta.

Emergency management plans and supporting instruments did not include provision for immediate relief for households, which meant arrangements for isolation income support and food security measures had to be designed in the early stages of Delta before it could be approved and deployed.

There were delays – sometimes only days, on occasion, weeks - in providing support to affected communities. In particular, there were delays to the provision of income support and in scaling up efforts to coordinate food and grocery hampers to households in isolation. In LGAs of concern, modest delays of a few days had a significant impact on people, especially those most vulnerable.

Although government issued stricter restrictions for workers in the Fairfield LGA on 14 July 2021, it only approved targeted income support for people in LGAs of concern on 16 August 2021.

Overall, agencies coordinated effectively to provide advice to government but there are opportunities to learn lessons to improve preparedness for future events

Agencies coordinated in providing advice to government. The advice was supported by timely public health information, although this was in the context of a pandemic, where data and information about the virus and its variants was changing regularly. However, agencies did not always consider the impact on key industries or supply chains when they provided advice to government, which meant that Public Health Orders would sometimes need to be corrected.

Public Health Orders were also updated as the response to Delta intensified or to address unintended consequences of previous orders. The frequency of changes hampered agencies' ability to effectively communicate changes to frontline staff and the community in a rapidly evolving situation.

The audit identified several occasions where there were delays, ranging from three to 21 days, between the provision of advice to government and subsequent decision-making (which we have not detailed due to the confidentiality of Cabinet deliberations). Agency officers advised of instances where they were not provided sufficient notice of changes to Public Health Orders to organise local infrastructure (such as traffic support for testing clinics) to support compliance with new requirements.

The COVID-19 pandemic arrived in Australia in late January 2020 as the bushfire and localised flooding emergencies were in their final stages. Between 2020 and mid-2021, agencies responded to the initial variants of COVID-19, managed a border closure with Victoria that lasted nearly four months and dealt with localised ‘flare-ups’ that required postcode-based restrictions on mobility in northern parts of Sydney and regional New South Wales. During this period, New South Wales had the opportunity to learn from events in Victoria which imposed strict restrictions on mobility across the State and the growing emergence of the Delta variant (Delta) across the Asia Pacific.

This section of the report assesses how emergency management and public health responses adapted to these lessons and determined preparedness for, and responses to, widespread community transmission of Delta in New South Wales.

The previous chapter discusses how agencies had refined the existing emergency management arrangements to suit the needs of a pandemic and describes some gaps that were not addressed. This chapter explores the first month of Delta (mid-June to mid-July 2021). It explores the areas where agencies were prepared and responses in place for the outbreak. It also discusses the impact of the gaps that were not addressed in the period prior to Delta and other issues that emerged.

NSW Health provided advice on the removal of restrictions based on up-to-date advice

The NSW Government discussed the gradual process for removing restrictions using the Doherty Institute modelling provided to National Cabinet on 10 August 2021. NSW Health highlighted the importance of maintaining a level of public health and safety measure bundles to further suppress case numbers. This was based on additional modelling from the Doherty Institute.

The Department of Regional NSW led discussion and planning around reopening with a range of proposal through August and September 2021. The Department of Premier and Cabinet and NSW Health jointly developed a paper to provide options on the restrictions when the State reached a level of 70% double dose vaccinations.

The roadmap to reopening was originally published on 9 September 2021. However, by 11 October 2021, the restrictions were relaxed when the 70% double dose threshold was reached to allow:

  • up to ten fully vaccinated visitors to a home (increased from five)
  • up to 30 fully vaccinated people attending outdoor gatherings (increased from 20)
  • weddings and funerals limits increased to 100 people (from 50)
  • the reopening of indoor pools for training, exercise and learning purposes only.

On the same day, the NSW Government announced further relaxation of restrictions once the 80% double dose threshold was reached. These restrictions were further relaxed on 8 November 2021. This included the removal of capacity restrictions to the number of visitors to a private residence, indoor pools to reopen for all purposes and density limits of one person for every two square metres, dancing allowed in nightclubs and 100% capacity in major stadia.

The NSW Government allowed workers in regional areas who received one vaccination dose to return to their workplace from 11 October 2021.

The Premier extended the date of easing of restrictions for unvaccinated people aged over 16 from 1 December to 15 December 2021.

Many agencies have undertaken reviews of their response to the Delta outbreak but a whole-of-government review has yet to be conducted

Various agencies and entities associated with the response to the Delta outbreak conducted after-action review processes. These processes assessed the achievements delivered, lessons learned and opportunities for improvement. However, a whole-of-government level review has not been conducted. This limits the New South Wales public service's ability to improve how it coordinates responses in future emergencies.

The agencies/entities that conducted reviews included:

  • South West Metropolitan region, Western NSW region, Fairfield Local Emergency Management Committee (LEMC), Dubbo Local Emergency Operations Controller (LEOCON), which were collated centrally by the State Emergency Operations Centre (SEOC)
  • Aboriginal Affairs NSW assessed representation and relevance of the emergency management arrangements for Aboriginal communities following the 2019 bushfires
  • Resilience NSW developed case studies to capture improved practice with regard to food security and supply chains
  • a community support and empowerment-focused after-action review undertaken by the Pillar 5 workstream of the Microstrategy.

Key lessons collated from the after-action reviews include:

  • the impact of variation in capability across agencies on the management of key aspects of the response including welfare support and logistics
  • issues with boundary differences between NSW Police Force regions, local government areas (LGA and local health districts (LHD) caused issues in delivering and coordinating services in an emergency situation 
  • the need to improve relationships between state and local Government outside of acute emergency responses to improve service delivery 
  • issues arising from impediments to information sharing between agencies and jurisdictions, such as:
    • timeliness and accuracy of data used to direct compliance activities
    • the impact of insufficient advance notice on changes to Public Health Orders
    • timely access to data across public sector agencies and other jurisdictions to inform decision-making, analysis and communications
    • gaps in data around ethnicity, geolocation of recent positive cases and infection/vaccination rates in Aboriginal communities.
  • the lack of Aboriginal community representation on many LEMCs
  • compared with the response to COVID-19 in 2020, improved coordination of communications with Culturally and Linguistically Diverse (CALD) populations with a reduction in overlapping messages and over-communication
  • improved attendance from agency representatives in LEMCs, and regional emergency operations centres (REOC) to improve interagency communications, planning, capability development and community engagement issues
  • deficiencies in succession planning and fatigue management practices
  • the potential for REOC Welfare/Well-being subgroups to be included as part of the wider efforts to community needs during emergencies.

NSW Health commenced a whole of system review of its COVID-19 response in May 2022. At the time of writing, the completion due date for the debrief is 7 November 2022. This debrief is expected to explore:

  • governance
  • engagement 
  • innovation and technology 
  • community impact 
  • workforce impact
  • system impact and performance.

NSW Health is also undertaking a parallel Intra-Action Review that is focused on the public health aspects of the response with finalisation estimated for the end of November 2022. At the time of completing this performance audit report, NSW Health had not finalised these reviews and, as a result, we cannot validate their findings against our own observations.

Recent inquiries are likely to impact the governance of emergency management in New South Wales

In March 2022, the NSW Government established an independent inquiry to examine and report on the causes of, preparedness for, response to and recovery from the 2022 floods. The Flood Inquiry report made 28 recommendations, which the NSW Government supported in full or in principle. Some of the recommendations relate directly to the governance and leadership of emergency management arrangements in New South Wales. 

The State Emergency Management Committee (SEMC) will likely be involved in, and impacted by, the recommendations arising from the Flood Inquiry with potential changes to its membership and reshaping of functional areas and agencies. At the same time, the SEMC may have a role in overseeing the changes that emerge from the SEOC consolidated after-action reviews. This can also extend to ensuring local and regional bodies have incorporated the required actions. There is a risk that the recommendations from the pandemic-based after-action reviews may not be considered due to the priority of action resulting from the Flood Inquiry.

Furthermore, there is potential for the SEMC to work with NSW Health during its system-wide review. Such an approach is likely to improve preparedness for future events.

Appendix one – Response from agencies

Appendix two – Chronology 2020–2021

Appendix three – About the audit

Appendix four – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #371 - released 20 December 2022

Published

Actions for Stronger Communities 2022

Stronger Communities 2022

Justice
Community Services
Asset valuation
Compliance
Cyber security
Financial reporting
Information technology
Internal controls and governance
Management and administration
Procurement
Project management
Risk

What the report is about

Results of the Stronger Communities cluster agencies' financial statement audits for the year ended 30 June 2022.

What we found

Unqualified audit opinions were issued on all completed 30 June 2022 financial statement audits. One audit is ongoing.

All 13 cluster agencies that have accommodation arrangements with Property NSW derecognised right-of-use assets and lease liabilities of $917 million and $1 billion respectively. The agencies also collectively recorded a gain on derecognition of $136 million.

The Department of Communities and Justice (the department) assumed the responsibility for delivery of the Process and Technology Harmonisation program from the Department of Customer Service. In 2021–22, the department incurred costs of $42.8 million in relation to the project, which remains ongoing.

The number of monetary misstatements identified during the audits decreased from 50 in 2020–21 to 48 in 2021–22.

What the key issues were

Six of the 15 cluster agencies required to submit 2021–22 mandatory early close procedures did not meet the statutory deadlines. One agency did not complete all mandatory procedures.

Five high-risk findings were identified in 2021–22. They related to deficiencies in:

  • user access administration at the department, NSW Rural Fire Service and New South Wales Aboriginal Land Council (NSWALC)
  • segregation of duties at the NSW Trustee and Guardian and NSWALC.

Recommendations were made to those agencies to address these control deficiencies.

This report provides Parliament and other users of the Stronger Communities cluster’s financial statements with the results of our audits, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Stronger Communities cluster (the cluster) for 2022.

Section highlights

  • Unqualified audit opinions were issued on all completed 30 June 2022 financial statement audits of cluster agencies, including the acquittal and compliance audits for the Legal Aid Commission of New South Wales and Crown Solicitor's Office. One audit is ongoing.

  • Reported corrected misstatements decreased from 30 in 2020–21 to 23 with a gross value of $187 million in 2021–22 ($101 million in 2020–21). Reported uncorrected misstatements increased from 20 in 2020–21 to 25 with a gross value of $92.3 million in 2021–22 ($107 million in 2020–21).

  • Six of the 15 cluster agencies required to submit 2021–22 early close financial statements and all other mandatory procedures did not meet the statutory deadlines. One agency did not complete all mandatory procedures.

  • All 13 cluster agencies that have accommodation arrangements with Property NSW accepted the changes in the Client Acceptance Letters, resulting in the derecognition of right-of-use assets and lease liabilities of $917 million and $1 billion respectively. The agencies also collectively recorded a gain on derecognition of $136 million.

  • The Department of Communities and Justice (the department) assumed the responsibility to deliver the Process and Technology Harmonisation program from the Department of Customer Service. In 2021–22, the department incurred costs of $42.8 million in relation to the project.

  • In 2021–22, the department continued to implement the International Financial Reporting Standards Interpretations Committee's agenda decision on 'Configuration or customisation costs in a cloud computing arrangement'. The department's review of the remaining arrangements, with a net book value of $233 million at 30 June 2021, resulted in the recognition as an expense (through accumulated funds at 1 July 2020) of previously capitalised intangible assets totalling $106 million.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our observations and insights from our financial statement audits of agencies in the Stronger Communities cluster.

Section highlights

  • The number of issues reported to management has decreased from 130 in 2020–21, to 110 in 2021–22, and 43% were repeat issues (51% in 2020–21). Many repeat issues related to information technology, governance and oversight controls, and non-compliance with key legislation and/or agency policies.

  • Five high-risk issues were identified in 2021–22, all of which are repeat issues and related to user access administration and segregation of duties.

  • Of the 24 newly identified moderate risk issues, 11 related to information technology. The rest related to governance and oversight controls and internal control deficiencies or improvements in payroll, asset management and other processes.

Appendix one – Misstatements in financial statements submitted for audit

Appendix two – Early close procedures

Appendix three – Timeliness of financial reporting

Appendix four – Financial data

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Health 2022

Health 2022

Health
Whole of Government
Asset valuation
Compliance
Cyber security
Financial reporting
Information technology
Infrastructure
Internal controls and governance
Management and administration
Procurement
Risk
Service delivery
Shared services and collaboration
Workforce and capability

What the report is about

Result of Health cluster (the cluster) agencies' financial statement audits for the year ended 30 June 2022.

What we found

Unmodified audit opinions were issued for the financial statements for all Health cluster agencies.

The COVID-19 pandemic continued to increase the complexity and number of accounting matters faced by the cluster. The total gross value of corrected misstatements in 2021–22 was $353.3 million, of which $186.7 million related to an increase in the impairment provision for Rapid Antigen Tests (RATs).

A qualified audit opinion was issued on the Annual Prudential Compliance Statement related to five residential aged care facilities. There were 20 instances (19 in 2020–21) of non-compliance with the prudential responsibilities within the Aged Care Act 1997.

What the key issues were

The total number of matters we reported to management across the cluster decreased from 116 in 2020–21 to 67 in 2021–22. Of the 67 issues raised, four were high risk (three in 2020-21) and 37 were moderate risk (57 in 2020–21). Nearly half of all control deficiencies reported in 2021–22 were repeat issues.

Three unresolved high-risk issues were:

  • COVID-19 inventories impairment – we continued to identify issues relating to management’s impairment model which relies on anticipated future consumption patterns. RATs had not been assessed for impairment.

  • Asset capitalisation threshold – management has not reviewed the appropriateness of the asset capitalisation threshold since 2006.

  • Forced-finalisation of HealthRoster time records – we continued to observe unapproved rosters being finalised by system administrators so payroll can be processed on time. 2.6 million time records were processed in this way in 2021–22.

What we recommended

  • COVID-19 inventories impairment – ensure consumption patterns are supported by relevant data and plans.

  • Assets capitalisation threshold – undertake further review of the appropriateness of applying a $10,000 threshold before capitalising expenditure on property, plant and equipment.

  • Forced-finalisation of HealthRoster time records – develop a methodology to quantify the potential monetary value of unapproved rosters being finalised.

This report provides Parliament and other users of Health cluster (the cluster) agencies' financial statements with the results of our audits, analysis, conclusions and recommendations in the following areas:

  • financial reporting

  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision-making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Health cluster (the cluster) for 2022.

Section highlights

  • Unqualified audit opinions were issued for all cluster agencies required to prepare general purpose financial statements.

  • The total gross value of corrected monetary misstatements for 2021–22 was $353.3 million, of which, $186.7 million related to an increase in the impairment provision for Rapid Antigen Tests.

  • A qualified audit opinion was issued on the ministry's Annual Prudential Compliance Statements.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision-making.

This chapter outlines our observations and insights from our financial statement audits of agencies in the cluster.

Section highlights

  • The total number of internal control deficiencies has decreased from 116 in 2020–21 to 67 in 2021–22. Of the 67 issues raised in 2021–22, four were high (2020–21: 3) and 37 were moderate (2020–21: 57); with nearly half of all control deficiencies reported in 2021–22 being repeat issues.

  • The following four issues were reported in 2021–22 as high risk:

    • impairment of COVID-19 inventories

    • inadequate review over the appropriateness of asset capitalisation threshold

    • forced-finalisation of HealthRoster time records

    • COVID-19 vaccination inventories – data quality issue at 31 March 2022.

  • Management of excessive leave balances and poor quality or lack of documentation supporting key agreements continued to be the key repeat issues observed in the 2021–22 financial reporting period.

Appendix one – Misstatements in financial statements submitted for audit

Appendix two – Early close procedures

Appendix three – Timeliness of financial reporting

Appendix four – Financial data

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for New South Wales COVID-19 vaccine rollout

New South Wales COVID-19 vaccine rollout

Health
Internal controls and governance
Management and administration
Project management
Risk
Service delivery

What the report is about

The Australian Government led and implemented the Australian COVID-19 vaccine rollout, with the support of state and territory governments. As part of the Australian Government's vaccine rollout, NSW Health launched its vaccination program on 22 February 2021, with responsibility for distributing and administering COVID-19 vaccine stock provided by the Australian Government.

This audit examined the period 1 January 2021 to 31 December 2021 and focused on NSW Health's contribution to the Australian Government led vaccine roll out in four Local Health Districts (LHDs), in particular the administration of two doses of vaccine to people aged 16 and over.

What we found

On 16 October 2021, NSW Health, in partnership with the Australian Government's vaccination program, achieved its first objective to fully vaccinate 80% of people in NSW aged 16 and over. Demand for the vaccine reduced in December 2021, and NSW Health did not reach its target of 95% fully vaccinated for people aged 16 and over until June 2022.

Despite challenges such as uncertain supply and changes to clinical advice affecting vaccine eligibility, NSW Health's overall delivery of vaccination services was effective and efficient.

During the audit period, NSW Health implemented effective strategies to allocate vaccines and reduce wastage to optimise the number of vaccines available.

NSW Health implemented its own booking system after it identified that the Australian Government's system would not manage bookings. There were problems with NSW Health's interim vaccine booking system, and NSW Health fully resolved these issues by September 2021.

As at 19 October 2022, vaccination rates for Aboriginal peoples and culturally and linguistically diverse people remained below the 95% target.

What we recommended

By June 2023, NSW Health should conduct a comprehensive review of the COVID-19 vaccine rollout and incorporate lessons learned into pandemic response plans.

The first three cases of COVID-19 in New South Wales were diagnosed in January 2020. By 30 June 2021, 128 people were being treated in hospital and one person was in intensive care. By the end of December 2021, 187,504 total cases and 663 deaths were reported in New South Wales. As at 27 October 2022, NSW Health reported more than three million total cases and 5,430 deaths.

The COVID-19 pandemic continues to have a significant impact on the people and the health sector of New South Wales. The Australian, state, territory, and local governments have directed significant resources towards health responses and economic recovery.

On 13 November 2020, National Cabinet (comprised of the Australian, state, and territory governments) endorsed the Australian COVID-19 Vaccination Policy. Australia's vaccination program was launched on 21 February 2021 with the goal of providing safe and effective vaccines to the people who most needed them as quickly as possible, to support the physical, mental and economic wellbeing of the nation.

The Australian Government led and implemented the Australian vaccine rollout, with the support of state and territory governments. As part of the Australian Government's vaccine rollout, NSW Health launched its vaccination program on 22 February 2021, with responsibility for distributing and administering COVID-19 vaccine stock provided by the Australian Government.

The overall objective of this audit was to assess the effectiveness and efficiency of NSW Health’s contribution to the Australian COVID-19 vaccine rollout. It is important to note that in New South Wales, primary care providers (GPs and pharmacies) and aged care providers administered the majority of vaccines. Primary care providers and aged care providers are the responsibility of the Australian Government.

The audit had a particular focus on whether NSW Health:

  • set clear vaccination targets underpinned and/or guided by evidence
  • managed the rollout of the vaccination program effectively and efficiently
  • managed demand of vaccines effectively and efficiently.

The audit examined the period 1 January 2021 to 31 December 2021 and focused on NSW Health's contribution to the Australian Government led vaccine rollout in four Local Health Districts (LHDs), in particular the administration of two doses of vaccine to people aged 16 and over. We did not audit the subsequent rollout for ages five to 15, or the booster rollout (third and fourth doses) as these activities mostly occurred outside the date of our review.

This audit also did not assess the Australian Government’s allocation of vaccine supplies to New South Wales because we do not audit the Australian Government's activities. On 17 August 2022, the Australian National Audit Office completed a performance audit which assessed the Australian Department of Health and Aged Care's effectiveness in the planning and implementation of Australia's COVID-19 vaccine rollout.

This audit is one of a series of audits that have been completed or are in progress regarding the New South Wales COVID-19 emergency response. This includes the planned performance audit ‘Coordination of the response to COVID-19 (June to November 2021)’, and financial audit assurance activities focusing on Local Health District processes and controls to manage the receipt, distribution and inventory management of vaccine stock. The Audit Office New South Wales '2022–25 Annual Work Program' details the ongoing focus our audits will have on providing assurance on the effectiveness of emergency responses.

Conclusion

By 12 December 2021, NSW Health had administered two doses of vaccines to one third of eligible people in New South Wales aged 16 and over – contributing significantly to the achievement of the NSW Government vaccination target of 80% fully vaccinated before 31 December 2021. Despite challenges such as uncertain supply and changes to clinical advice affecting vaccine eligibility, NSW Health's overall delivery of vaccination services was effective and efficient.

NSW Health implemented its own booking system after it identified that the Australian Government's system would not manage bookings. There were problems with NSW Health's interim vaccine booking system, and NSW Health fully resolved these issues by September 2021.

Vaccination levels in some vulnerable populations remain below the 95% double dose target currently in place. Access to quality data to regularly measure vaccination rates in some vulnerable populations remains an ongoing challenge for the NSW and Australian Governments. As a result, NSW Health is unable to fully ensure it has delivered on its shared responsibility with the Australian Government to vaccinate vulnerable people.

NSW Health managed challenges regarding the uncertain supply of vaccines from the Australian Government and filled gaps beyond its agreed responsibilities in the National Partnership on COVID-19 Response. During the Delta outbreak of the pandemic, NSW Health sought to achieve the best possible public health outcome from limited vaccine supply by opening up additional vaccination clinics in highly affected areas and redistributing vaccine supplies from areas with fewer cases to highly affected local government areas in south west Sydney.

During the audit period, NSW Health implemented effective strategies to allocate vaccines and reduce wastage to optimise the number of vaccines available. Our financial audit report, 'Health 2022', includes additional information on vaccine supply stock held by NSW Health.

NSW Health demonstrated agility by using a range of strategies to promote vaccination, including direct engagement with communities to develop culturally appropriate services such as pop-up clinics. NSW Heath recruited prominent community members, such as faith leaders, elders and sportspeople, to promote vaccination within their communities. However, at the date of this report, there are still vulnerable populations with vaccination rates lower than the current 95% double dose vaccination target. There is also a lack of regularly updated data for some cohorts which prevents NSW Health from accurately monitoring vaccination rates in some populations it has identified as vulnerable.

In March 2021, NSW Health identified that the booking system provided by the Australian Government was an online directory of vaccine clinics and would not manage bookings. To overcome this, NSW Health amended an internal-use system to be publicly facing. This solution was not user-friendly for staff or those seeking to make an appointment. Between June to September 2021, NSW Health progressively resolved booking system related issues, by developing and rolling out a new purpose-built booking solution for NSW Health vaccination clinics.

Appendix one – Response from agency

Appendix two – Australian audits on the vaccine rollouts

Appendix three – Committee members 

Appendix four – About the audit 

Appendix five – Performance auditing 

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #369 - released 7 December 2022

Published

Actions for Audit Insights 2018-2022

Audit Insights 2018-2022

Community Services
Education
Environment
Finance
Health
Industry
Justice
Local Government
Premier and Cabinet
Planning
Transport
Treasury
Universities
Whole of Government
Asset valuation
Cross-agency collaboration
Compliance
Cyber security
Financial reporting
Fraud
Information technology
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Regulation
Risk
Service delivery
Shared services and collaboration
Workforce and capability

What the report is about

In this report, we have analysed the key findings and recommendations from our audit reports over the past four years.

This analysis includes financial audits, performance audits, and compliance audits of state and local government entities that were tabled in NSW Parliament between July 2018 and February 2022.

The report is framed by recognition that the past four years have seen significant challenges and emergency events.

The scale of government responses to these events has been wide-ranging, involving emergency response coordination, service delivery, governance and policy.

The report is a resource to support public sector agencies and local government to improve future programs and activities.

What we found

Our analysis of findings and recommendations is structured around six key themes:

  • Integrity and transparency
  • Performance and monitoring
  • Governance and oversight
  • Cyber security and data
  • System planning for disruption
  • Resource management.

The report draws from this analysis to present recommendations for elements of good practice that government agencies should consider in relation to these themes. It also includes relevant examples from recent audit reports.

In this report we particularly call out threats to the integrity of government systems, processes and governance arrangements.

The report highlights the need for balanced advice to government on options and risks, for transparent documentation and reporting of directions and decisions, and for early and open sharing of information with integrity bodies and audit.

A number of the matters highlighted in this report are similar to those described in our previous Insights Report, (Performance Audit Insights: key findings from 2014–2018) specifically in relation to cyber and information security, to performance measurement, reporting and evaluation, and system and workforce planning and capability.

Fast facts

  • 72 audits included in the Audit Insights 2018–2022 analysis
  • 4 years of audits tabled by the Auditor-General for New South Wales
  • 6 key themes for Audit Insights 2018–2022.

picture of Margaret Crawford Auditor-General for New South Wales in black dress with city skyline as backgroundI am pleased to present the Audit Insights 2018–2022 report. This report describes key findings, trends and lessons learned from the last four years of audit. It seeks to inform the New South Wales Parliament of key risks identified and to provide insights and suggestions to the agencies we audit to improve performance across the public sector.

The report is framed by a very clear recognition that governments have been responding to significant events, in number, character and scale, over recent years. Further, it acknowledges that public servants at both state and council levels generally bring their best selves to work and diligently strive to deliver great outcomes for citizens and communities. The role of audit in this context is to provide necessary assurance over government spending, programs and services, and make suggestions for continuous improvement.

A number of the matters highlighted in this report are similar to those described in our previous Insights Report, (Performance Audit Insights: key findings from 2014–2018) specifically in relation to cyber and information security, to performance measurement, reporting and evaluation, and system and workforce planning and capability.

However, in this report we particularly call out threats to the integrity of government systems, processes and governance arrangements. We highlight the need for balanced advice to government on options and risks, for transparent documentation and reporting of directions and decisions, and for early and open sharing of information with integrity bodies and audit. Arguably, these considerations are never more important than in an increasingly complex environment and in the face of significant emergency events and they will be key areas of focus in our future audit program.

While we have acknowledged the challenges of the last few years have required rapid responses to address the short-term impacts of emergency events, there is much to be learned to improve future programs. I trust that the insights developed in this report provide a helpful resource to public sector agencies and local government across New South Wales. I would be pleased to receive any feedback you may wish to offer.

Margaret Crawford
Auditor-General for New South Wales

Integrity and transparency Performance and monitoring Governance and oversight Cyber security and data System planning Resource management
Insufficient documentation of decisions reduces the ability to identify, or rule out, misconduct or corruption. Failure to apply lessons learned risks mistakes being repeated and undermines future decisions on the use of public funds. The control environment should be risk-based and keep pace with changes in the quantum and diversity of agency work. Building effective cyber resilience requires leadership and committed executive management, along with dedicated resourcing to build improvements in cyber security and culture. Priorities to meet forecast demand should incorporate regular assessment of need and any emerging risks or trends. Absence of an overarching strategy to guide decision-making results in project-by-project decisions lacking coordination. Governments must weigh up the cost of reliance on consultants at the expense of internal capability, and actively manage contracts and conflicts of interest.
Government entities should report to the public at both system and project level for transparency and accountability. Government activities benefit from a clear statement of objectives and associated performance measures to support systematic monitoring and reporting on outcomes and impact. Management of risk should include mechanisms to escalate risks, and action plans to mitigate risks with effective controls. In implementing strategies to mitigate cyber risk, agencies must set target cyber maturity levels, and document their acceptance of cyber risks consistent with their risk appetite. Service planning should establish future service offerings and service levels relative to current capacity, address risks to avoid or mitigate disruption of business and service delivery, and coordinate across other relevant plans and stakeholders. Negotiations on outsourced services and major transactions must maintain focus on integrity and seeking value for public funds.
Entities must provide balanced advice to decision-makers on the benefits and risks of investments. Benefits realisation should identify responsibility for benefits management, set baselines and targets for benefits, review during delivery, and evaluate costs and benefits post-delivery. Active review of policies and procedures in line with current business activities supports more effective risk management. Governments hold repositories of valuable data and data capabilities that should be leveraged and shared across government and non-government entities to improve strategic planning and forecasting. Formal structures and systems to facilitate coordination between agencies is critical to more efficient allocation of resources and to facilitate a timely response to unexpected events. Transformation programs can be improved by resourcing a program management office.
Clear guidelines and transparency of decisions are critical in distributing grant funding. Quality assurance should underpin key inputs that support performance monitoring and accounting judgements. Governance arrangements can enable input into key decisions from both government and non-government partners, and those with direct experience of complex issues.     Workforce planning should consider service continuity and ensure that specialist and targeted roles can be resourced and allocated to meet community need.
Governments must ensure timely and complete provision of information to support governance, integrity and audit processes.          
Read more Read more Read more Read more Read more Read more

 

This report brings together a summary of key findings arising from NSW Audit Office reports tabled in the New South Wales Parliament between July 2018 and February 2022. This includes analysis of financial audits, performance audits, and compliance audits tabled over this period.

  • Financial audits provide an independent opinion on the financial statements of NSW Government entities, universities and councils and identify whether they comply with accounting standards, relevant laws, regulations, and government directions.
  • Performance audits determine whether government entities carry out their activities effectively, are doing so economically and efficiently, and in accordance with relevant laws. The activities examined by a performance audit may include a selected program or service, all or part of an entity, or more than one government entity. Performance audits can consider issues which affect the whole state and/or the local government sectors.
  • Compliance audits and other assurance reviews are audits that assess whether specific legislation, directions, and regulations have been adhered to.

This report follows our earlier edition titled 'Performance Audit Insights: key findings from 2014–2018'. That report sought to highlight issues and themes emerging from performance audit findings, and to share lessons common across government. In this report, we have analysed the key findings and recommendations from our reports over the past four years. The full list of reports is included in Appendix 1. The analysis included findings and recommendations from 58 performance audits, as well as selected financial and compliance reports tabled between July 2018 and February 2022. The number of recommendations and key findings made across different areas of activity and the top issues are summarised at Exhibit 1.

The past four years have seen unprecedented challenges and several emergency events, and the scale of government responses to these events has been wide-ranging involving emergency response coordination, service delivery, governance and policy. While these emergencies are having a significant impact today, they are also likely to continue to have an impact into the future. There is much to learn from the response to those events that will help the government sector to prepare for and respond to future disruption. The following chapters bring together our recommendations for core elements of good practice across a number of areas of government activity, along with relevant examples from recent audit reports.

This 'Audit Insights 2018–2022' report does not make comparative analysis of trends in public sector performance since our 2018 Insights report, but instead highlights areas where government continues to face challenges, as well as new issues that our audits have identified since our 2018 report. We will continue to use the findings of our Insights analysis to shape our future audit priorities, in line with our purpose to help Parliament hold government accountable for its use of public resources in New South Wales.

Appendix one – Included reports, 2018–2022

Appendix two – About this report

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Rail freight and Greater Sydney

Rail freight and Greater Sydney

Transport
Information technology
Infrastructure
Management and administration
Project management
Service delivery

What the report is about

The movement of freight contributes $66 billion annually to the NSW economy. Two thirds of all freight in NSW moves through Greater Sydney, and the volume of freight moving through Greater Sydney is expected to increase by 48 per cent by 2036.

This audit assessed the effectiveness of transport agencies in improving the use of rail freight capacity in Greater Sydney, and to meet current and future freight demand.

What we found

Transport agencies do not have strategies or targets in place to improve the efficiency or capacity of the metropolitan shared rail network for freight.

The transport agencies acknowledge that they do not have sufficient information to achieve the most efficient freight outcomes and they do not know how to use the shared rail network to maximise freight capacity without compromising passenger rail services.

The Freight and Ports Plan 2018-2023 contains one target for rail freight - to increase the use of rail at Port Botany to 28 per cent by 2021. However, Transport for NSW (TfNSW)'s data indicates this target will not be met.

Sydney Trains records data on train movements and collects some data on delays and incidents. TfNSW collects data for the construction of the Standard Working Timetable and third-party contracts.

However, a lack of clarity around what data is gathered and who has ownership of the data makes data sharing difficult and limits its analysis and reporting.

The Freight and Ports Plan 2018-2023 includes the goal of 'Reducing avoidable rail freight delays', but the transport agencies do not have any definition for an avoidable delay and, as a result, do not measure or report them.

TfNSW and Sydney Trains are appointed to manage and deliver the Transport Asset Holding Entity of New South Wales (TAHE)'s obligations to allow rail freight operators to use the shared rail network. There are no performance measures in rail freight operator contracts or inter-agency agreements. This limits transport agencies' ability to improve performance.

TfNSW’s Freight Branch is working on four freight-specific strategies; a review of the Plan, a freight rail strategy, a port efficiency strategy and a freight data strategy.

TfNSW has not yet determined the timeframes or intended outcomes of these strategies.

What we recommended

Transport agencies should:

  • commit, as part of the review of Future Transport 2056, to delivering the freight-specific strategies currently in development and develop whole-of-cluster accountability for this work including timeframes, specific targets and clear roles and responsibilities 
  • improve the collection and sharing of freight data
  • develop a plan to reduce avoidable freight delays
  • systematically collect data on the management of all delays involving and/or impacting rail-freight
  • develop and implement key performance indicators for the agreements between the transport agencies.

Fast facts    

  • 288 million tonnes of freight volume predicted to pass through Greater Sydney in 2036, up from 194 million in 2016 (an increase of 48%)

  • 54 trucks that can be replaced by one 600 m long port shuttle freight train    

  • 26,671 freight trains that passed through the metropolitan shared rail network between 1 July 2020 and 30 June 2021

The movement of freight contributes $66.0 billion annually to the New South Wales economy — or 13 per cent of the Gross State Product. Two thirds of all freight in New South Wales moves through Greater Sydney, and the volume of freight moving through Greater Sydney is expected to increase by 48 per cent by 2036. This increasing demand is driven by increasing population and economic growth.

The sequence of activities required to move goods from their point of origin to the eventual consumer (the supply chain) is what matters most to shippers and consumers. Road can provide a single-mode door-to-door service, whereas conveying goods by rail typically involves moving freight onto road at some point. In Greater Sydney, 80 per cent of all freight is moved on road. Freight often passes through intermodal terminals (IMTs) as it transitions from one mode of transport to the next.

In 2016, Transport for NSW (TfNSW) released Future Transport 2056 - the NSW Government's 40-year vision for transport in New South Wales, which is intended to guide investment over the longer term. In Future Transport 2056, TfNSW noted that New South Wales will struggle to meet increasing demand for freight movements unless rail plays a larger role in the movement of freight.

Sydney Trains manages the metropolitan shared rail network, which is made up of rail lines that are used by both passenger and freight trains. The Transport Administration Act 1988 requires that, for the purposes of network control and timetabling, NSW Government transport agencies give ‘reasonable priority’ to passenger trains on shared lines. As the Greater Sydney population and rail patronage continue to grow, so too will competition for access to the shared rail network. See Appendix two for details of the area encompassed by Greater Sydney.

Freight operators can also use dedicated rail freight lines operated by the Australian Rail Track Corporation (ARTC - an Australian Government statutory-owned corporation). As the metropolitan shared rail network connects with dedicated freight lines, freight operators often use both to complete a journey.

TfNSW, Sydney Trains and the Transport Asset Holding Entity (TAHE) work in conjunction with other rail infrastructure owners and private sector entities, including port operators, privately operated IMTs and freight-shipping companies. TfNSW and Sydney Trains are responsible for managing the movement of freight across the metropolitan shared rail network. TAHE is the owner of the rail infrastructure that makes up the metropolitan shared rail network. The NSW Government established TAHE, a NSW Government state-owned corporation, on 1 July 2020 to replace the former rail infrastructure owner - RailCorp. The Auditor-General for New South Wales has commenced a performance audit on TAHE which is expected to table in 2022.

On 1 July 2021, TAHE entered into new agreements with TfNSW and Sydney Trains to operate, manage and maintain the metropolitan shared rail network. Until 30 June 2021, and in accordance with TAHE's Implementation Deed, TAHE operated under the terms of RailCorp's existing arrangements and agreements.

This audit assessed the effectiveness of TfNSW, Sydney Trains and TAHE in improving the use of rail freight capacity in Greater Sydney, and to meet current and future freight demand.

The audit focused on:

  • the monitoring of access to shared rail lines
  • the management of avoidable delays of rail freight movements
  • steps to increase the use of rail freight capacity in Greater Sydney.

Conclusion

Transport agencies do not have clear strategies or targets in place to improve the freight efficiency or capacity of the metropolitan shared rail network. They also do not know how to make best use the rail network to achieve the efficient use of its rail freight capacity. These factors expose the risk that rail freight capacity will not meet anticipated increases in freight demand.

Future Transport 2056 notes that opportunities exist to shift more freight onto rail, and that making this change remains an important priority for the NSW Government. However, the transport agencies acknowledge that they do not have sufficient information to achieve the most efficient freight outcomes. In particular, transport agencies do not know how to use the shared rail network in a way that maximises freight capacity without compromising passenger rail services.

Neither Future Transport 2056 nor the Freight and Ports Plan 2018–2023 give any guidance on how transport agencies will improve the efficiency or capacity of the shared rail network. Other than a target for rail freight movements to and from Port Botany, which TfNSW's data indicates will not be met, there are no targets for improving rail freight capacity across the shared network. The lack of specific strategies, objectives and targets reduces accountability and makes it difficult for transport agencies to effectively improve the use of rail freight capacity in line with their commitment to do so.

Sydney Trains and Transport for NSW do not effectively use data to improve rail freight performance and capacity.

To drive performance improvement when planning for the future, transport agencies need good quality data on freight management and movements. Sydney Trains records data on train movements in real-time and collects some data on delays and incidents. TfNSW collects data for the construction of the Standard Working Timetable (SWTT) and third-party contracts. However, the different types of data gathered and the separation between the teams responsible mean that there is a lack of clarity around what data is gathered and who has ownership it. This lack of coordination prevents best use of the data to develop a single picture of how well the network is operating or how performance could be improved.

Sydney Trains' ability to evaluate the effectiveness of its incident and delay mitigation strategies is also limited by a lack of information on its management of rail-freight related delays or incidents. While Sydney Trains collects data on major incidents, it can only use this to conduct event-specific analysis on the causes of an incident, and to review the operational and management response. The use of complete and accurate incident data would assist to define, identify and reduce avoidable delays. Reducing avoidable delays is a goal of the Freight and Ports Plan 2018–2023. More complete data on all incidents would help TfNSW to have more effective performance discussions with rail freight operators to help improve performance.

TfNSW has started developing strategies to identify how it can use rail freight capacity to achieve efficient freight outcomes, but it has not committed to implementation timeframes for this work.

TfNSW’s Freight Branch has started work on four freight-specific strategies to improve freight efficiency: a review of the Plan, a freight rail strategy, a port efficiency strategy and a freight data strategy. However, none of these strategies will be fully developed before the end of 2022. TfNSW has not yet determined the implementation timeframes or intended outcomes of these strategies, although TfNSW reports that it is taking an iterative approach and some recommendations and initiatives will be developed during 2022. 

Appendix one - Response from agencies

Appendix two - The Greater Sydney region

Appendix three - TfNSW strategic projects 

Appendix four - Sydney Trains path priority principles 

Appendix five - Sydney Trains delay management

Appendix six - About the audit 

Appendix seven - Performance auditing
 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #357 - released (19 October 2021).

Published

Actions for Managing cyber risks

Managing cyber risks

Whole of Government
Transport
Cyber security
Information technology
Internal controls and governance
Procurement
Risk

What the report is about

This audit assessed how effectively Transport for NSW (TfNSW) and Sydney Trains identify and manage their cyber security risks.

The NSW Cyber Security Policy (CSP) sets out 25 mandatory requirements for agencies, including implementing the Australian Cyber Security Centre’s Essential 8 strategies to mitigate cyber security incidents, and identifying the agency’s most vital systems, their ‘crown jewels’. 

The audited agencies have requested that we do not disclose detail of the significant vulnerabilities detected during the audit, as these vulnerabilities are not yet remediated. We provided a detailed report to the agencies in December 2020 outlining significant issues identified in the audit. We have conceded to the agencies' request but it is disappointing that transparency to the Parliament and the public on issues that potentially directly affect them needs to be limited in this way.

What we found

TfNSW and Sydney Trains are not effectively managing their cyber security risks.

Both agencies have assessed their cyber security risks as unacceptably high and both agencies had not identified all of the risks we detected during this audit – some of which are significant.

Both agencies have cyber security plans in place that aim to address cyber security risks. TfNSW and Sydney Trains have combined this into the Transport Cyber Defence Rolling Program, part of the Cyber Defence Portfolio (CDP). 

However, neither agency has reached its target ratings for the CSP and the Essential 8 and maturity is low in relation to significant risks and vulnerabilities exposed.

Further, neither agency is fostering a culture where cyber security risk management is an important and valued aspect of decision-making.

TfNSW is not implementing cyber security training effectively across the cluster with only 7.2% of staff having completed basic cyber security training.

What we recommended

TfNSW and Sydney Trains should:

  • develop and implement a plan to uplift the Essential 8 controls to the agency's target state
  • as a matter of priority, address the vulnerabilities identified as part of this audit and previously described in a detailed Audit Office report provided to both agencies
  • ensure cyber security risk reporting to executives and the Audit and Risk Committee
  • collect supporting information for the CSP self assessments 
  • classify all information and systems according to importance and integrate this with the crown jewels identification process
  • require more rigorous analysis to re-prioritise CDP funding 
  • increase uptake of cyber security training.

TfNSW should assess the appropriateness of its target rating for each of the CSP mandatory requirements.

Department of Customer Service should:

  • clarify the requirement for the CSP reporting to apply to all systems
  • require agencies to report the target level of maturity for each mandatory requirement.

Fast facts

  • $42m Total value of the Transport Cyber Defence Rolling Program over three years.
  • 7.2% Percentage of staff across the Transport cluster who had completed introductory cyber security training

Response to requests by audited agencies to remove information from this report

In preparing this audit report, I have considered how best to balance the need to support public accountability and transparency with the need to avoid revealing information that could pose additional risk to agencies’ systems. This has involved an assessment of the appropriate level of detail to include in the report about the cyber security vulnerabilities identified in this audit.

In making this assessment, the audit team consulted with Transport for NSW (TfNSW), Sydney Trains, and Cyber Security NSW to identify content which could potentially pose a threat to the agencies’ cyber security.

In December 2020, my office also provided TfNSW and Sydney Trains with a detailed report of many of the significant vulnerabilities identified in this audit, to enable the agencies to address the cyber security risks identified. The detailed report was produced as a result of a 'red team' exercise, which was conducted with both agencies' knowledge and consent. The scope of this exercise reflected the significant input provided by both agencies. More information on this exercise is at page 12 of this report.

TfNSW and Sydney Trains have advised that in the six months from December 2020 and at the time of tabling this audit report, they have not yet remediated all the vulnerabilities identified. As a result, they, along with Cyber Security NSW, have requested that we not disclose all information contained in this audit report to reduce the likelihood of an attack on their systems and resulting harm to the community. I have conceded to this request because the vulnerabilities identified have not yet been remediated and leave the agencies exposed to significant risk.

It should be stressed that the risks identified in the detailed report exist due to the continued presence of these previously identified vulnerabilities, rather than due to their potential publication. The audited agencies, alone, are accountable for remediating these vulnerabilities and addressing the risks they pose.

It is disappointing that transparency to the Parliament and the public on issues that potentially directly affect them needs to be limited in this way.

That said, the conclusions drawn in this report are significant in terms of risk and remain valid, and the recommendations should be acted upon with urgency.

Cyber security risk is an increasing area of concern for governments in Australia and around the world. In recent years, there have been a number of high-profile cyber security attacks on government entities in Australia, including in New South Wales. Malicious cyber activity in Australia is increasing in frequency, scale, and sophistication. The Audit Office of New South Wales is responding to these risks with a program of audits in this area, which aim to identify the effectiveness of particular agencies in managing cyber risks, as well as their compliance with relevant policy.

Cyber Security NSW, part of the Department of Customer Service (DCS) releases and manages the NSW Cyber Security Policy (CSP). The CSP sets out 25 mandatory requirements for agencies, including making it mandatory for agencies to implement the Australian Cyber Security Centre Essential 8 Strategies to Mitigate Cyber Security Incidents (the Essential 8). The Essential 8 are key controls which serve as a baseline set of protections which agencies can put in place to make it more difficult for adversaries to compromise a system. Agencies are required to self-assess their maturity against the CSP and the Essential 8, and report that assessment to Cyber Security NSW annually.

The CSP makes agencies responsible for identifying and managing their cyber security risks. The CSP sets out responsibilities and governance regarding risk identification, including making agencies responsible for identifying their 'crown jewels', the agency's most valuable and operationally vital systems. Once these risks are identified, agencies are responsible for developing a cyber security plan to mitigate those risks.

This audit focussed on two agencies: Transport for NSW (TfNSW) and Sydney Trains. TfNSW is the lead agency for the Transport cluster and provides a number of IT services to the entire cluster, including Sydney Trains. This audit focussed on the activities of TfNSW's Transport IT function, which is responsible for providing cyber security across the cluster, as well as directly overseeing four of TfNSW's crown jewels. Sydney Trains is one of the agencies in the Transport cluster. While it receives some services from TfNSW, it is also responsible for implementing its own IT controls, as well as controls to protect its Operational Technology (OT) environment. This OT environment includes systems which are necessary for the operation and safety of the train network.

To test the mitigations in place and the effectiveness of controls, this audit involved a 'red team' simulated exercise. A red team involves authorised attackers seeking to achieve certain objectives within the target's environment. The red team simulated a determined external cyber threat actor seeking to gain access to TfNSW's systems. The red team also sought to test the physical security of some Sydney Trains' sites relevant to the agency's cyber security. The red team exercise was conducted with the knowledge of TfNSW and Sydney Trains.

This audit included the Department of Customer Service as an auditee, as they have ownership of the CSP through Cyber Security NSW. This audit did not examine the management of cyber risk in the Department of Customer Service.

This audit assessed how effectively selected agencies identify and manage their cyber security risks. The audit assessed this with the following criteria:

  • Are agencies effectively identifying and planning for their cyber security risks?
  • Are agencies effectively managing their cyber security risks?

Following this in-depth portfolio assessment, the Auditor-General for NSW will also table a report on NSW agencies' compliance with the CSP in the first quarter of 2021–22.

Conclusion

Transport for NSW and Sydney Trains are not effectively managing their cyber security risks. Significant weaknesses exist in their cyber security controls, and both agencies have assessed that their cyber risks are unacceptably high. Neither agency has reached its Essential 8 or Cyber Security Policy target levels. This low Essential 8 maturity exposes both agencies to significant risk. Both agencies are implementing cyber security plans to address identified cyber security risks.
This audit identified other weaknesses, such as low numbers of staff receiving basic cyber security awareness training. Cyber security training is important for building and supporting a cyber security culture. Not all of the weaknesses identified in this audit had previously been identified by the agencies, indicating that their cyber security risk identification is only partially effective.
Agency executives do not receive regular detailed information about cyber risks and how they are being managed, such as information on mitigations in place and the effectiveness of controls for cyber risk. As a result, neither agency is fostering a culture where cyber security risk management is an important and valued aspect of executive decision-making.
TfNSW and Sydney Trains are partially effective at identifying their cyber security risks and both agencies have cyber security plans in place

Both agencies regularly carry out risk assessments and have identified key cyber security risks, including risks that impact on the agencies' crown jewels. These risks have been incorporated into the overall enterprise risk process. However, neither agency regularly reports detailed cyber risk information to agency executives to adequately inform them about cyber risk. The Cyber Security Policy (CSP) requires agencies to foster a culture where cyber security risk management is an important and valued aspect of decision-making. By not informing agency executives in this way, TfNSW and Sydney Trains are not fulfilling this requirement.

Agencies' cyber security risk assessment processes are not sufficiently comprehensive to identify all potential risks. Not all of the weaknesses identified in this audit had previously been identified by the agencies.

To address identified cyber security risks, both agencies have received funding approval to implement cyber security plans. TfNSW first received approval for its cyber security plan in 2017. Sydney Trains received approval for its cyber security plan in February 2020. In 2020–21 TfNSW and Sydney Trains combined their plans into the Transport Cyber Defence Rolling Program business case valued at $42.0 million over three years. This is governed as part of a broader Cyber Defence Portfolio (CDP). The CDP largely takes a risk-based approach to annual funding. The Cyber Defence Portfolio Steering Committee and Board can re-allocate funds from an approved project to a different project. This re-allocation process could be improved by making it more risk-based.

TfNSW and Sydney Trains are not effectively managing their cyber security risks

Neither agency has fully mitigated its cyber security risks. These risks are significant. Neither TfNSW nor Sydney Trains have reduced their cyber risk to levels acceptable to the agencies. Both agencies have set a risk tolerance for cyber security risks, and the identified enterprise-level cyber security risks remain above this rating. Both agencies' self-attested maturity against the Essential 8 remains low in comparison to the agencies' target levels, and in relation to the significant risks and vulnerabilities that are exposed. Little progress was made against the Essential 8 in 2020.

Neither agency has reached its target levels of maturity for the CSP mandatory requirements. Not reaching the target rating of the CSP mandatory requirements risks information and systems being managed inconsistently or not in alignment with good governance principles. The Transport Cyber Defence Rolling Program has a KPI to achieve a target rating of three for all CSP requirements where business appropriate. TfNSW considers this target rating to be its target for all the CSP requirements. However TfNSW has not undertaken analysis to determine whether this target is appropriate to its business.

The CSP makes agencies accountable for the cyber risks of their ICT service providers. While both agencies usually included their cyber security expectations in contracts with third-party suppliers, neither agency was routinely conducting audits to ensure that these expectations were being met.

The CSP requires agencies to make staff aware of cyber security risks and deliver cyber security training. TfNSW is responsible for delivering cyber security training across the Transport cluster, including in Sydney Trains. TfNSW was not effectively delivering cyber security training across the cluster because training was not mandatory for all staff at the time of the audit and completion rates among those staff assigned the training was low. As such, only 7.2 per cent of staff across the Transport cluster had completed introductory cyber security training as at January 2021.

Agencies have assessed their cyber risks as being above acceptable levels

An agency's risk tolerance is the amount of risk which the agency will accept or tolerate without developing further strategies to modify the level of risk. Risks that are within an agency's risk tolerance may not require further mitigation and may be deemed acceptable, while risks which are above the agency's risk tolerance likely require further mitigation before they become acceptable to the agency.

Both agencies have defined their risk tolerance and have identified risks which are above this level, indicating that they are unacceptable to the agency. TfNSW has defined 'very high' risks as generally intolerable and 'high' risks as undesirable. Its risk tolerance is 'medium'. Sydney Trains has four classifications of risk: A, B, C and D. A and B risks are deemed 'unacceptable' and 'undesirable' respectively, while C risks are considered 'tolerable'. This aligns with the TfNSW definition of a medium risk tolerance.

Transport IT reported five enterprise-level cyber security risks through its enterprise risk reporting tool in September 2020, all of which relate to cyber security or have causes relating to cyber security. These risks are in aggregate form, rather than relating to specific vulnerabilities. At the time of the audit, one of these risks was rated as very high and the other four rated as high. At this time, Transport IT had identified a further seven divisional-level risks which were above the agency’s risk tolerance.

Similarly, Sydney Trains has identified one main cyber security risk in its IT enterprise-level risk register and another with a potential cyber cause. Both of these IT risks are deemed to have a residual risk of ‘unacceptable’.

Similarly, two cyber-related OT risks have been determined to be above the agency's risk tolerance. One risk is rated as 'unacceptable'. Another risk, while not entirely cyber rated, is rated 'undesirable' and is deemed to have some causes which may stem from a cyber-attack.

Agencies have assessed their current cyber risk mitigations as requiring improvement

In addition to the risk ratings stated above, at the time of the audit neither agency believed that its controls were operating effectively. Transport IT had rated the control environments for its cyber security enterprise risks as 'requires improvement'. Mitigations were listed in the risk register for these risks but, in some cases, they were unlikely to reduce the risk to the target state or by the target date. For example, one risk had actions listed as 'under review' and no further treatment actions listed, but a due date of July 2021, while another risk was being treated by the CDP with a due date of July 2021. The CDP identified in May 2020 that while the average risk identified as part of that program will be reduced to a medium level by this date, ten high risks will still remain. Given the delays in the program, this number may be higher. As such, it seems unlikely that the enterprise risk will be reduced to below a 'high' level by July 2021.

Sydney Trains’ IT and OT risk registers cross-reference controls and mitigations against the causes and consequences. The IT cyber security risk identified in the register had causes with no mitigations designed for them. Further, some of these causes did not have future mitigations designed for them. This risk also had controls in place which are identified as partially effective. For the unacceptable OT risk noted above, while there was a control designed for each of the potential causes, Sydney Trains had identified all of the controls in place as either partially effective or ineffective. This indicates that Sydney Trains was not effectively mitigating the causes of its cyber risks and, even where it had designed controls or mitigations, these were not always implemented to fully mitigate the cause of the risk.

Additional information on gaps in cyber mitigations which were exposed in the course of this audit has been detailed to both agencies. The Foreword of this report provides information about why this detail is not included here.

Essential 8 maturity is low across TfNSW and Sydney Trains and little progress was made in 2020

CSP mandatory requirement 3.2 states that agencies must implement the ACSC Essential 8. Agencies must also rate themselves against each of the Essential 8 on a maturity scale from zero to three and report this to Cyber Security NSW. A full list of the Essential 8 can be found in Exhibit 1. Both agencies have a low level of maturity against the Essential 8 not just in comparison to the targets they have set, but also in relation to the risks and vulnerabilities exposed. Both agencies have set target maturity ratings for the Essential 8 but none of the Essential 8 ratings across either agency are currently implemented to this level. Having a low level of Essential 8 maturity exposes both agencies to significant risks and vulnerabilities. Little progress was made between the 2019 and 2020 attestation periods.

Transport IT has set a target rating of three across all of the Essential 8. Sydney Trains has set a target rating of three for its IT systems. Sydney Trains had an interim target of two for its OT systems in 2020 and advised that this has since increased to three. It should be noted that not all the Essential 8 are applicable to OT systems.

None of the Essential 8 ratings across either agency are currently implemented to the target levels. Given that the Essential 8 provide the controls which are most commonly able to deter cyber-attacks, having maturity at a low level potentially exposes agencies to a cyber security attack.

Some work is underway across both TfNSW and Sydney Trains to improve the Essential 8 control ratings. The CDP provided some resources to the Essential 8 over 2019–20, with uplift focusing on specific systems. The CDP work in 2019 and 2020 relevant to the Essential 8 largely focussed on determining the current state of the Essential 8 and creating a target state roadmap. As a result, there was little improvement between the 2019 and 2020 attestation periods. The CDP has a workstream for the Essential 8 in its FY 2020–21 funding allocation, however as noted above in Exhibit 6 this was delayed as resources were redeployed to Project La Brea. Regardless, work on some specific aspects of the Essential 8 remain part of the 2020–21 CDP allocation, with workstreams allocated to improving three of the Essential 8. In addition, some work from Project La Brea should lead to an improvement in the Essential 8.

Sydney Trains' Cyber Uplift Program included a workstream which had in scope the uplift in the Essential 8 in IT. There were also other workstreams which aimed to improve some of the Essential 8 for OT systems. Work is also ongoing as part of the CDP to uplift these scores in Sydney Trains.

TfNSW and Sydney Trains have not reached their target maturity across the CSP mandatory requirements and TfNSW has not evaluated its cluster-wide target to ensure it is appropriate

Cyber Security NSW allows each agency to determine its target level of maturity for the first 20 CSP mandatory requirements. Agencies can tailor their target levels to their risk profile. Not reaching the target rating of the CSP mandatory requirements risks information and systems being managed inconsistently or not in alignment with good governance principles.

Sydney Trains has set its target level of maturity for IT and OT. All of Sydney Trains' target maturity levels are at least a three (defined), with a target of four (quantitatively managed) for many of the mandatory requirements. While Cyber Security NSW does not currently mandate a minimum level of maturity, in 2019 there was a requirement for each agency to target a minimum level of three.

Sydney Trains has not met its target ratings across the mandatory requirements.

The Transport Cyber Defence Rolling Program has a program KPI to ensure that the entire cluster reaches a minimum maturity level of three against all the CSP requirements by 2023. TfNSW has not reviewed its CSP mandatory requirement targets to determine if a three is desirable for all requirements or if a higher target level may be more appropriate. It is important for senior management to set cyber security objectives as a demonstration of leadership and a commitment to cyber security.

TfNSW has not met its target ratings across the mandatory requirements for its Group IT ISMS, which was the focus of this audit.

Both agencies claimed progress in their implementation of the mandatory requirements between 2019 and 2020. The audit did not seek to verify the self-assessed results from either agency.

Both agencies operate ISMS in line with the CSP

CSP mandatory requirement 3.1 requires agencies to implement an Information Security Management System (ISMS) or Cyber Security Framework (CSF), with scope at least covering systems identified as the agency's ‘crown jewels’. The ISMS or CSF should be compliant with, or modelled on, one or more recognised IT or OT standard. As noted in the introduction, an ISMS ‘consists of the policies, procedures, guidelines, and associated resources and activities, collectively managed by an organisation, in the pursuit of protecting its information assets.’ Both agencies operate an ISMS compliant with the CSP requirement.

As noted in the introduction, TfNSW operates four ISMS. The Transport IT ISMS is certified against ISO27001, the most common standard for ISMS certification. Three of TfNSW’s six crown jewels are managed within this ISMS. The other ISMS are not certified to relevant standards, though TfNSW claims that they align with relevant controls. This is sufficient for the purposes of the CSP.

Sydney Trains operates two ISMS, one for IT and another for OT. Neither of these are certified to relevant ISMS Standards, however there have been conformance reviews of both IT and OT with relevant standards. These ISMS cover all crown jewels in the agency.

There are currently 11 ISMS in operation across the Transport cluster. TfNSW has proposed moving towards a holistic approach to these ISMS, with the CDP Board responsible for governing the available security controls and directing agency IT and OT teams to implement these.

Agencies are not routinely conducting audits of third-party suppliers to ensure compliance with contractual obligations

CSP mandatory requirement 1.5 makes agencies accountable for the cyber risks of their ICT service providers and ensuring that providers comply with the CSP and any other relevant agency security policies. The ACSC has provided advice on what organisations should do when managing third party suppliers of ICT. The ACSC advises that organisations should use contracts to define cyber security expectations and seek assurance to ensure that these contract expectations are being met. While both agencies usually include specific cyber security expectations in contracts, neither is routinely seeking assurance that these expectations are being met.

The NSW Government has mandated the use of the 'Core& One' contract template for low-value IT procurements and the Procure IT contract template for high-value IT procurements. Both of these contracts contain space for the procuring agency to include cyber security controls for the contractor to implement. The Procure IT contract template also includes a right-to-audit clause which allows agencies to receive assurance around the implementation of these controls. TfNSW and Sydney Trains used the mandated contracts for relevant contracts examined as part of this audit.

TfNSW included security controls in all the contracts examined as part of this audit. Compliance with ISO27001 was the most commonly stated security expectation. Of the contracts examined as part of this audit, only one contract did not have a right-to-audit clause. This contract was signed in October 2016. While these clauses are in place, TfNSW rarely conducted these audits on its third-party providers. Of the eight TfNSW contracts examined in detail, only two of these had been audited to confirm compliance with the stated security controls.

Sydney Trains included security controls in all but one of the contracts examined as part of this audit. Sydney Trains did not require contractors to be compliant with ISO27001, but only required compliance with whole-of-government policies. Sydney Trains does not routinely conduct audits of its third-party suppliers, however it did conduct deep-dive risk analyses of its top ten highest risk IT suppliers. This involved a detailed review of both the suppliers' security posture and also the contract underpinning the relationship with the supplier.

The CDP funding for 2020–21 includes a workstream for strategic third-party contract remediation. This funding is to conduct some foundational work which will allow the CDP to make further improvements in future years. While this funding will not address gaps in contract requirements or management across all contracts, this workstream aims to reduce the risks posed by strategic suppliers covering critical assets. Similarly, work is currently underway as part of the CDP to conduct OT risk assessments for key suppliers to Sydney Trains in a similar way to the work undertaken for IT suppliers.

Sydney Trains has risk assessed its third-party suppliers but TfNSW has not done so

It is important to conduct a risk assessment of suppliers to identify high-risk contractors. This allows agencies to identify those contractors who may require additional controls stated in the contract, those who require additional oversight, and also where auditing resources are best targeted.

Sydney Trains has risk assessed all its IT suppliers and, as noted above, has conducted a deep-dive risk analysis of its top ten highest risk suppliers. TfNSW has not undertaken similar analysis of its key suppliers, however it has identified risks attached to each of its strategic suppliers and has documented these. As a result of not risk assessing its suppliers, TfNSW cannot take a targeted approach to its contract management.

TfNSW demonstrated poor records handling relating to the contracts examined as part of this audit

TfNSW was not able to locate one of the contracts requested as part of the audit's sample. Other documentation, such as contract management plans, could not be located for many of the other contracts requested as part of this audit. These poor document handling practices limits TfNSW's ability to effectively oversee service providers and ensure that they are implementing agreed controls. It also limits public transparency on the effectiveness of these controls.

The Transport cluster is not effectively implementing cyber security awareness training

Agencies are responsible for implementing regular cyber security education for all employees and contractors under mandatory requirement 2.1 in the CSP. TfNSW is responsible for delivering this training to the whole Transport cluster, including Sydney Trains. The Transport cluster has basic cyber awareness training available for all staff. TfNSW also offers additional training provided by Cyber Security NSW targeted at executives and executive assistants. While TfNSW has training available to staff, it is not delivering this effectively. TfNSW does not make training mandatory for most staff nor does it require staff to repeat training regularly. Even among those staff who have been assigned the training, completion rates are low, meaning that delivery is not effectively monitored. Cyber security training is important for building and supporting a cyber security culture.

TfNSW is responsible for creating and rolling out all forms of training to agencies within the Transport cluster. Both TfNSW and Sydney Trains have the same mandatory cyber awareness training that is automatically assigned to new starters. At the time of the audit, this training was not mandatory for ongoing staff. TfNSW does make additional cyber security training available to staff who can choose to undertake the training themselves, or can be assigned the training by their manager. All TfNSW cyber security training is delivered via online modules and it is the responsibility of managers to ensure that it is completed.

Cyber security training completion rates for both TfNSW and Sydney Trains are low. Only 13.5 per cent of staff across the Transport cluster had been assigned the Cyber Safety for New Starters training as of January 2021. Although this course is mandatory for new starters, only 53 per cent of staff assigned the Cyber Safety for New Starters training module had completed the course by January 2021. As a result, only 7.2 per cent of staff across the entire Transport cluster had completed this training at that time. In Sydney Trains, less than one per cent of staff had completed this training as at January 2021 and a further 7.6 per cent of staff have completed the 'Cyber Security: Beyond the Basics' training. These low completion rates indicate that TfNSW is not effectively rolling out cyber security training across the cluster.

In October 2020, the Department of Customer Service released 'DCS-2020-05 Cyber Security NSW Directive - Practice Requirement for NSW Government', which made annual cyber security training mandatory for all staff from 2021. In line with this requirement, TfNSW has advised that it will be gradually implementing mandatory annual training from July 2021 for all staff.

The Transport cluster undertakes activities to build a cyber-aware culture in accordance with the CSP, but awareness remains low

Increasing staff awareness of cyber security risks and maintaining a cyber secure culture are both mandatory requirements of the CSP. While TfNSW does undertake some activities to build a cyber aware culture, awareness of cyber security risks remains low. This can be demonstrated by the low training rates outlined above, and the 'Spot the Scammer' exercise, described in Exhibit 7. TfNSW is responsible for delivering these awareness raising activities across the cluster.

TfNSW frequently communicates with staff across the Transport cluster about various cyber security risks through multiple avenues. Both agencies use the intranet, emails and other awareness raising activities to highlight the importance for staff to be aware of the seriousness of cyber risks. Advice given on the intranet includes tips for spotting scammers on mobile phones, promoting the cluster-wide training courses, as well as various advice that staff could use when dealing with cyber risks in the workplace.

In addition to these awareness raising activities, TfNSW has also undertaken a cluster-wide phishing email exercise called 'Spot the Scammer'. This is outlined in Exhibit 7. This exercise was carried out in 2019 and 2020 and allowed the Transport cluster to measure the degree to which staff were able to identify phishing emails. As can be seen in Exhibit 7, the results of this exercise indicate that staff awareness of phishing emails remains low.

Exhibit 7 - Spot the Scammer exercise
In both 2019 and 2020, TfNSW performed a ‘Spot the Scammer’ exercise in which they sent out over 25,000 emails to staff based on a real phishing attack in order to measure awareness and response. The exercise tested staff 'click through rate', the percentage of staff who clicked on the fake phishing link. In 2019, these results were then compared to industry benchmarks, with over a 20 per cent click through rate being considered 'very high'. Both TfNSW and Sydney Trains were considered to have a ‘very high’ click through rate in comparison to these benchmarks in both 2019 and 2020. This indicates that staff awareness of phishing emails was low. The click through rate for TfNSW was 24 per cent in 2020, an increase from 22 per cent in 2019. For Sydney Trains, the click through rate in 2020 was 32 per cent, which was a decrease from 40 per cent in 2019.
Source: Audit Office analysis of TfNSW documents.

Appendix one – Response from agencies

Appendix two – Cyber Security Policy mandatory requirements

Appendix three – About the audit

Appendix four – Performance auditing

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #353 - released (13 July 2021).

Published

Actions for WestConnex: changes since 2014

WestConnex: changes since 2014

Transport
Compliance
Infrastructure
Internal controls and governance
Management and administration
Project management
Risk

What the report is about

The report examined whether Transport for NSW (TfNSW) and Infrastructure NSW (INSW) effectively assessed and justified major scope changes to the WestConnex project since 2014.

What we found

NSW Government decisions to fund WestConnex-related projects outside WestConnex's $16.812 billion budget have reduced transparency and understate the full cost of WestConnex.

The NSW Government's decision to separate Sydney Gateway from WestConnex has reduced transparency over the cost of the road component of Sydney Gateway. $1.76 billion of the cost to complete Sydney Gateway is funded outside the WestConnex budget.

Network integration costs, currently estimated at $2.3 billion, are also funded outside the WestConnex budget. Many of these costs are directly attributable to WestConnex and ought to be included in the reported budget.

The Parramatta Road Urban Amenity Improvement Program, costing $198 million, should also be included as part of the WestConnex reported budget.

Decisions to exclude or remove these elements from WestConnex without justification have seen $4.26 billion of projects funded outside the $16.8 billion budget.

Positively, robust analysis was used to develop and incorporate design improvements into the 2015 WestConnex Updated Strategic Business Case.

The separate components of WestConnex underwent all required assurance reviews. However, the NSW Government's assurance framework does not require ongoing ‘whole-of-program’ assurance for large and complex projects like WestConnex. The absence of a holistic review of WestConnex allows for some costs and benefits to avoid scrutiny.

What we recommended

TfNSW should:

  • review the impact of scope changes on project objectives, costs and benefits for complex infrastructure projects
  • ensure that estimated costs and benefits of works which are reasonably required to meet consent conditions are included in business cases for complex large infrastructure projects
  • establish centralised and project specific record keeping for major infrastructure projects.

Infrastructure NSW should provide transparent whole of program assurance on total costs and benefits when complex projects are split into sub-projects.

Government should consider enhancing public transparency of existing infrastructure assurance processes by requiring that large complex infrastructure programs undergo periodic review at a whole-of-program level.

Fast facts

  • $16.812b 2015 WestConnex business case budget
  • $2.3b current estimated cost of network integration works to enable WestConnex, funded outside the WestConnex budget
  • $1.76b cost to complete Sydney Gateway to enable WestConnex and also funded outside the WestConnex budget
  • $198m Parramatta Road Urban Amenity Improvement Program, originally part of WestConnex but now funded outside the WestConnex budget

WestConnex

WestConnex is a 33 km motorway network that will link the western and south‑western suburbs with the Sydney CBD and the Airport and Port Botany precinct. It will also connect with proposed future motorway links to the north shore, northern beaches, and southern Sydney. The project is being delivered in three stages, with completion scheduled for 2023.

When first conceived by Infrastructure NSW (INSW) in 2012, WestConnex was described as a single integrated concept. In August 2013, government approved a business case for an integrated concept of WestConnex, with an estimated cost of $14.881 billion (in nominal outturn costs). Transport for NSW (TfNSW) is the government agency (sponsor agency) accountable for the delivery of WestConnex in accordance with the business case. In August 2014, the NSW Government established the Sydney Motorway Corporation to fund, deliver and operate WestConnex.

In November 2015, the NSW Government publicly released an updated WestConnex business case with greater detail and design enhancements, which increased the estimated cost to $16.812 billion.

Subsequent to this update, further changes were made to the design, including realignment of the M4 to M5 Link connection to the Western Harbour Tunnel project, an expanded interchange at Rozelle, the deletion of the Camperdown Intersection, and the addition of the Iron Cove Link. The reported budget for WestConnex was not changed as a result of these design updates.

To fund WestConnex, Sydney Motorway Corporation consolidated a concessional loan of $2 billion from the Australian Government, private sector debt and equity funding from the State. The Australian Government also provided a $1.5 billion contribution to the State to partially fund construction of WestConnex.

In August 2018, the NSW Government sold 51 per cent of its stake in Sydney Motorway Corporation for $9.26 billion. At the time of writing, the NSW Government is in the process of selling its remaining 49 per cent stake of Sydney Motorway Corporation.

About this audit

In the course of delivering a complex major infrastructure project, it is reasonable to expect changes to the original design and scope. Changes may occur as the design moves from a high‑level concept to a detailed design for project delivery, as new risks or issues are identified, as demands change, or as other interdependent projects are approved. Changes can also occur in response to potential cost or delivery overruns which arise as a result of planning deficiencies. Where design and scope changes significantly change the project costs and/or expected benefits, the justification for these changes should be robust and transparent.

Following our 2014 performance audit, 'WestConnex: Assurance to the government', the NSW Government established the Infrastructure Investor Assurance Framework (IIAF) to improve accountability and transparency over major projects that are developed, procured, or delivered by government agencies. Under the framework, TfNSW, as project sponsor, is responsible for ensuring the WestConnex project meets all IIAF requirements. These include ensuring the project remains strategically aligned and viable, and benefits are on track. INSW is responsible for coordinating the assurance review process and reporting directly to NSW Cabinet on project delivery against time, budget and risks to project delivery.

The objective of this performance audit is to assess whether TfNSW and INSW effectively assessed and justified major scope changes to the WestConnex project since 2014.

 

Conclusion

Government decisions to separate WestConnex related projects and deliver them outside WestConnex's 2015 business case budget of $16.812 billion has understated the total cost of WestConnex achieving its objectives. The rationale for separating these elements from the WestConnex project scope has not been transparent. Together, these projects represent costs of $4.26 billion funded outside the $16.812 billion WestConnex budget.

Since 2015, the NSW Government has removed several projects from the scope described in the 2015 WestConnex business case, and funded them separately:
  • In mid‑2017, the Sydney Gateway became a separate project outside WestConnex. This project, estimated in 2015 to cost $800 million, now has an estimated cost of $2.56 billion. The project remains partly funded by an $800 million contribution from the $16.812 billion WestConnex budget, with $1.76 billion funded outside the WestConnex budget.
  • In late 2018, the Parramatta Road Urban Amenity Improvement Program became a separate project outside the 2015 WestConnex budget. This project was part of the 2015 WestConnex Business Case and is intended to create urban renewal opportunities around Paramatta Road. It is estimated to cost $198 million.

Work required to integrate WestConnex with existing roads ('network integration') was funded outside the $16.812 billion budget for the November 2015 WestConnex business case. TfNSW is obliged to deliver network integration works to meet the conditions of planning approval for WestConnex. As such, these costs should be included in the WestConnex budget. The current estimated cost of these network integration works is $2.3 billion.

The rationale to exclude or remove each of these elements from the WestConnex project scope has not been transparent, nor supported by robust analysis and justification. These elements are required for WestConnex to achieve its objectives. The additional project costs will also deliver additional benefits not included in the 2015 WestConnex business case. Removing them understates the total cost of achieving the objectives set out in the 2013 and 2015 WestConnex business cases.

WestConnex's complex financing arrangements further reduce transparency on costs.

Transparency over the total cost of WestConnex – including elements funded from other project budgets – is further limited by the project's complex financing arrangements.

Prior to 2018, the Audit Office provided assurance on costs borne and levied by Sydney Motorway Corporation and its controlled entities. Since the NSW Government sold its majority stake in WestConnex in August 2018, the Auditor‑General no longer has the mandate to provide this assurance. Considering this, and the lack of transparency on the cost of projects removed from the WestConnex project scope, there is no transparent or comprehensive view of the total cost to deliver WestConnex – nor of how these cost would be offset by the sale of the government's remaining stake.

There is no 'whole‑of‑program' assurance over the WestConnex program of works. This limits transparency and confidence that WestConnex will meet intended objectives within its budget.

After INSW conducted a gateway review of a draft of the 2015 WestConnex Business Case under the IIAF, the project was broken up into separate components to support staged delivery. Each of these projects, including the Sydney Gateway, as well as the Network Integration Program, underwent the required assurance reviews under the IIAF. INSW also provided monthly progress updates to government. These individual projects are, in themselves, significant in scale and complexity. Addressing them as discrete components for the purposes of the assurance review process is justified and there is no requirement under the IIAF to holistically review projects which together deliver final benefits of the WestConnex program. However, whole‑of‑program review would improve transparency over total costs and benefits.

In 2016, TfNSW revised the design of the M4‑M5 Link and Rozelle to address traffic and integration issues.

TfNSW identified that the concept designs used for the M4‑M5 Link and Rozelle Interchange in the 2015 WestConnex Business Case would not integrate well with surface roads, including the proposed Bays Precinct, and would result in increased traffic on Victoria Road and the ANZAC Bridge. Following a comprehensive review conducted in mid‑2016, TfNSW refined the design of the M4‑M5 Link and Rozelle Interchange to address these limitations without increasing the cost of delivery. TfNSW documented the rationale for the design changes, including how the changes improved on the original design to increase capacity, improve traffic conditions and create more open space.

1. Key findings

Government decisions to fund WestConnex related projects outside of WestConnex's $16.812 billion reported budget have reduced transparency over costs and understate the full cost of WestConnex

In 2015, the work required to integrate WestConnex with existing roads ('network integration') was funded as a separate project with an estimated cost of $1.534 billion outside the 2015 WestConnex budget of $16.812 billion. TfNSW then created the Network Integration Program to respond to the conditions of planning approval for WestConnex. The current estimated cost to deliver all network integration works is $2.3 billion.

Since the 2015 WestConnex Business Case, the NSW Government has removed several elements from the scope of WestConnex and funded them as separate projects, while keeping the published WestConnex budget at an estimated $16.812 billion. Projects removed include:

  • Sydney Gateway, currently costed at $2.56 billion (with an $800 million contribution from WestConnex)
  • Parramatta Road Urban Amenity Improvement Program, costed at $198 million in late 2018 and funded though new funding to the Greater Sydney Commission.

Together, these projects represent costs of $4.26 billion that are not included in the WestConnex budget, but are required for WestConnex to achieve the objectives of the 2013 and 2015 WestConnex Business Cases. The costs of these elements in supporting the objectives of WestConnex is not tracked centrally, and there is no single point of oversight over them. Exhibit 1 compares total WestConnex forecast costs (including related projects) between November 2015 and April 2021.

 

November 2015
($ million)

April 2021
($ million)
WestConnex
Stage 1
Stage 1A (M4 Widening) 497 517
Stage 1B (M4 East) 3,802 3,782
Total 4,299 4,299
Stage 2
King Georges Road Interchange 131 131
New M5 4,335 4,335
Sydney Gateway Contribution 800 800
Total 5,266 5,266
Stage 3
M4‑M5 Link and Rozelle Interchange 7,049 7,049
Urban renewal (Parramatta Road) 198 ‑‑
Urban renewal (Rozelle) ‑‑ 198
Total 7,247 7,247
Total reportable WestConnex 16,812 16,812

Exhibit 1: WestConnex and related projects forecast costs
  November 2015
($ million)
April 2021
($ million)
Related projects
Network integration 1,534 2,300
Urban renewal (Parramatta Road) ‑‑ 198
Sydney Gateway Road Component ‑‑ 1,760
Total 1,534 4,258

Source: AO research.

Many network integration costs are directly attributable to WestConnex and ought to be included in the reported budget for WestConnex

Prior to 2015, the scope of WestConnex included enabling works needed before or during construction, as well as funding for future works to address any adverse traffic outcomes created by WestConnex which become apparent after its opening. These works are also known as network integration works.

When government approved the 2015 WestConnex Business Case, it noted that the project would require $1.534 billion for network integration works to address the impacts of WestConnex on the road network. However, the WestConnex project budget of $16.812 billion did not include funding for network integration works. Instead, Roads and Maritime Services (RMS, now TfNSW) was to fund network integration through its normal budget allocation.

It is important to recognise these costs as part of the total WestConnex project cost because:

  • TfNSW created the Network Integration Program to respond to network traffic and transport elements of the planning conditions of approval for WestConnex granted by the then NSW Department of Planning and Environment under the Environment, Planning and Assessment Act 1979.
  • NSW Treasury guidelines for business cases note that accurate cost estimates include assessment of the financial impact of meeting the conditions of planning approval.
  • Travel time and vehicle operating cost benefits attributed to the WestConnex project in the 2015 WestConnex Business Case assume that some network integration works, then costed at $373 million, were in place.

Refer to Appendix two for more detail on network integration works.

Some of the projects in the WestConnex Network Integration Program provide community and place benefits, such as parklands and cycleways. These benefits have not been attributed to WestConnex. Additionally, some network integration works are likely to deliver additional traffic related benefits to WestConnex. As the Network Integration Program’s primary purpose is to meet the conditions of planning approval for WestConnex, TfNSW should attribute all the costs and benefits of the program to WestConnex.

To September 2021, the total funded cost of the Network Integration Program is approximately $2.077 billion. TfNSW estimates that it will need a further $222 million to complete all expected network integration works.

The NSW Government's decision to separate Sydney Gateway from WestConnex has reduced transparency and accountability for TfNSW's underestimation of the cost of the road component of Sydney Gateway

Sydney Gateway is a high‑capacity connection between the new St Peters Interchange and the Sydney Airport and Port Botany precinct. It includes a road and rail components. The road component was included in the scope of WestConnex in the 2015 WestConnex Business Case. The November 2015 design, which TfNSW costed at $800 million, involved separate roadways from the St Peters Interchange to the International terminal, and to the domestic terminals and Mascot airport precinct.

By October 2016, TfNSW was aware that the $800 million budget for Sydney Gateway was insufficient and revised the forecast cost for the road component to $1.8 billion. The original cost estimate did not sufficiently consider the cost of:

  • constructing a complex design adjacent to the airport precinct
  • obtaining access to land required for the project
  • managing environmental contamination.

On 9 August 2017, the then Minister for WestConnex announced that the Sydney Gateway project was not part of WestConnex.

The 2015 WestConnex Business Case notes that material changes to the WestConnex budget, funding, scope, or timeframe are subject to Cabinet approval processes. It states that, when seeking approval for material changes, the portfolio Minister will make a submission to the relevant Cabinet Committee. Changes in project scope required the approval of the then Cabinet Committee on Infrastructure and should have been endorsed by the WestConnex Interdepartmental Steering Committee.

TfNSW and the NSW Department of Premier and Cabinet (DPC) assert that there is no documentation to support the government’s decision to separate Sydney Gateway from the WestConnex Program, or the WestConnex Interdepartmental Steering Committee's endorsement of a submission to Cabinet seeking approval for the separation.

The established governance processes for major scope changes were not followed in this instance. The lack of transparency regarding government's decision to separate Sydney Gateway from WestConnex also reduces visibility of TfNSW's underestimation of the cost of delivering the road component of Sydney Gateway.

The November 2018 Final Business Case for Sydney Gateway, which was approved by the government, included an estimate of $2.45 billion (nominal outturn cost) for the road component. This estimate included an $800 million contribution from WestConnex. A more recent estimate (late 2020) for this project is $2.56 billion (nominal outturn cost).

The Parramatta Road Urban Amenity Improvement Program should be included as part of the WestConnex budget

A specific objective of the 2015 WestConnex Business Case was the creation of opportunities for urban renewal along and around Parramatta Road. The business case included an allocation of $198 million in the $16.812 billion WestConnex budget for the Parramatta Road Urban Amenity Improvement program, designed to implement aspects of the objective. In November 2018, the NSW Government removed the Parramatta Road Urban Amenity Improvement Program from the WestConnex program of works and reallocated the $198 million (inside the $16.812 billion WestConnex budget) for urban renewal works around the Rozelle Interchange. As part of this decision, government approved new funding of $198 million to the Greater Sydney Commission for the urban amenity program, outside the $16.812 billion WestConnex budget. This understates the cost of WestConnex meeting its objectives by $198 million.

There is no requirement for ongoing ‘whole‑of‑program’ assurance of the WestConnex program of works, including related projects

In August 2015, INSW conducted its first Gateway Review of WestConnex as a program consisting of composite projects. Following that review, TfNSW registered each of the components of WestConnex with INSW as individual projects, rather than keeping WestConnex registered as a program or mega‑project. This is not inconsistent with the IIAF and all WestConnex related projects, including Sydney Gateway and the Network Integration Program, have undergone independent assurance reviews as individual projects under the IIAF.

Once a program like WestConnex is broken down into its composite parts, there is no requirement for the sponsor agency (TfNSW) or INSW to provide independent assurance on the program as a whole until it is completed. This is then done as part of the Gateway review for benefits realisation, which examines whether project benefits are being measured and meet expectations. These individual projects are, in themselves, significant in scale and complexity. While addressing them as discrete components for the purposes of the assurance review process can be justified, the absence of strategic, holistic reviews of WestConnex allows for total costs and benefits to become opaque and avoid scrutiny. Programs of this scale require greater ongoing transparency on total costs and benefits in order to ensure confidence they will meet intended objectives within budget.

There is a lack of public transparency on the total costs and benefits of the WestConnex project

Prior to 2018, the Audit Office provided assurance on costs borne and levied by Sydney Motorway Corporation and its controlled entities. Since the NSW Government sold 51 per cent of its stake in WestConnex in August 2018, the Auditor‑General no longer has the mandate to provide this assurance. The Audit Office is also unable to provide any assurance regarding the performance of tolling concessions.

This means that the total costs of WestConnex, including those levied on road users through tolling, are not reported alongside the full cost of delivering the project. This information, and independent assurance over that information, would provide transparency and context to the outcome of government's sale of its interest in WestConnex.

To enhance the transparency of existing infrastructure assurance processes, government could consider requiring large and complex infrastructure programs to undergo periodic review at a whole‑of‑program level. This could take the form of annual reports to Parliament on the total costs and benefits of selected large and complex projects by the responsible agency. The reports could include an assessment of the cost to government and cost to the community of funding and financing. Independent assurance of the agency report would provide Parliament with greater confidence that infrastructure is delivered economically and providing value for money for the people of NSW.

The Australian National Audit Office provides similar assurance on selected Department of Defence acquisition projects as part of its annual Major Projects Report.

Design enhancements included in the 2015 WestConnex Updated Strategic Business Case were supported by robust analysis

The 2015 WestConnex Business Case contained more detail than the 2013 WestConnex business case. Design enhancements were made as a result of modelling analysis conducted over the two years since the 2013 business case. Enhancements included a full underground link between Kingsgrove and St Peters as part of the New M5 and re‑alignment of the M4‑M5 link tunnel (Stage 3) to include the Rozelle Interchange. The Rozelle Interchange will provide a direct connection to the Anzac Bridge and Victoria Road, and will enable a connection to the proposed Western Harbour Tunnel and Beaches Link. A map and description of these elements can be found at Exhibits 2 and 3 of this report.

In 2016, TfNSW revised the design of the M4‑M5 Link and Rozelle to address traffic and integration issues

As part of preparing the 2015 WestConnex Business Case, TfNSW prepared a Project Definition and Delivery Report (PDDR) for the M4‑M5 Link. This report describes the scope of the project, including a high‑level concept design. TfNSW identified limitations with the proposed design of the M4‑M5 in the PDDR, which it would need to address as the project moved to a detailed design stage. In particular, these limitations included:

  • poor integration with the Bays Precinct masterplan
  • traffic capacity constraints on Victoria Road and Anzac Bridge
  • construction complexity.

Following a comprehensive review in mid‑2016, TfNSW changed the design of the M4‑M5 Link and Rozelle Interchange to address these limitations. These changes included:

  • deletion of the Camperdown intersection to improve traffic conditions on Parramatta Road
  • a fully underground and larger Rozelle Interchange with 10‑hectare dedicated parklands
  • a toll‑free tunnel link from Iron Cove Bridge to Anzac Bridge
  • increasing the lanes in the dual tunnels from three to four each way.

TfNSW documented, but did not publish, the rationale for the design changes, including how the changes addressed the limitations of the previous design while providing increased community benefit through the creation of open space. TfNSW undertook cost comparison studies which estimated that these changes would have a neutral impact on the estimated project cost while achieving the same or improved benefits.

TfNSW's record‑keeping systems for large infrastructure investments negatively impact accountability and transparency

In response to our formal requests for relevant information, made during the conduct of this audit, TfNSW advised that complete and valid records of key decision‑making processes, analysis and advice were unavailable. Additionally, TfNSW often provided information that was incomplete or unverifiable (for instance, unsigned briefing notes). This is not consistent with accepted governance practices and does not comply with the requirements of the State Records Act 1998.

We also requested that TfNSW provide a list of relevant documents held by the Sydney Motorway Corporation (SMC). While TfNSW acknowledged that SMC may hold material relevant to the audit, TfNSW did not have a list or description of these documents. As SMC is now a majority privately held entity, both the Audit Office and TfNSW have limited power to require SMC to provide documentation.

The delivery timeframe for large and complex infrastructure projects such as WestConnex frequently exceeds five years, and some projects can take over a decade to deliver. These projects represent a significant investment of public resources and government agencies should expect independent review and assurance activities such as performance audits. The establishment of dedicated record keeping facilities for major infrastructure projects, such as data rooms, would improve transparency and accountability. This would ensure that the use of public resources is fully auditable in line with public expectations and the requirements of the Government Sector Finance Act 2018, the State Records Act 1998 and the Public Finance and Audit Act 1983.

2. Recommendations

By December 2021, TfNSW should:

1. review the impact of scope changes on project objectives, costs and benefits for complex infrastructure projects

2. when preparing business cases for complex large infrastructure projects, ensure that the estimated costs and benefits of works which are reasonably expected to meet consent conditions are included in the overall project cost and its benefits (as per Treasury guidelines)

3. establish and maintain centralised and project‑specific record keeping, including through dedicated project data rooms, to ensure major infrastructure projects can readily be subject to external oversight and assurance.

By June 2022, INSW should:

4. provide transparent whole‑of‑program assurance on total costs and benefits throughout the project life‑cycle when complex projects are split into sub‑projects.

By June 2022, NSW Government should:

5. consider enhancing the public transparency of existing infrastructure assurance processes by requiring that large complex infrastructure programs undergo periodic review at a whole‑of‑program level. This could take the form of reports to Parliament on the total costs and benefits on selected large and complex projects by the responsible agency, including cost to government and cost to community of funding and financing, as well as an accompanying independent assessment of the agency report.

Following our 2014 performance audit report 'WestConnex: Assurance to the government', the NSW Government established the Infrastructure Investor Assurance Framework (IIAF). INSW is responsible for the development, implementation and administration of the IIAF. The assurance framework involves gateway reviews, health checks, deep dive reviews, and project monitoring and reporting at various stages in the lifecycle of a project. The main aims of the IIAF are to help ensure major infrastructure projects are delivered on time and on budget, and to ensure that reports are regularly monitored by the Cabinet of the NSW Government. The IIAF gateway review process is compulsory for all significant investments and expenditure under the NSW Treasury Gateway Policy.

In accordance with the IIAF, INSW is responsible for the following:

  • providing a dedicated Assurance Team including Gateway Review Managers to coordinate Reviews
  • determining appropriate expert reviewers, and manages scheduling, commissioning and administration of Assurance Review reports. Infrastructure NSW is independent of the Expert Review Team
  • monitoring Tier 1 – High Profile/High Risk projects, Tier 2 and Tier 3 (if required) project performance through independent Assurance Reviews
  • providing independent analysis and advice on key risks and any corrective actions recommended for Tier 1 – High Profile/High Risk, Tier 2 and Tier 3 projects
  • escalating projects to Infrastructure Investor Assurance Committee (IIAC) and Cabinet where projects present ‘red flag issues’ and where corrective action is needed
  • working with delivery agencies to register all capital projects with an estimated cost greater than $10.0 million and ensures they are risk profiled and assigned a risk‑based project tier with an endorsed IIAF Project Registration report
  • preparing forward looking annual Cluster Assurance Plans
  • maintaining and continuously improves the IIAF process
  • reporting to the IIAC, Cabinet and Infrastructure NSW Board
  • regularly report to NSW Treasury on the performance of the IIAF.

In relation to WestConnex, TfNSW is the sponsor agency responsible for meeting relevant IIAF requirements, including:

  • registering and risk profiling projects
  • IIAF gateway, health check, and deep dive assurance reviews
  • regular reporting.

Under the IIAF, it is mandatory for all capital projects valued over $10.0 million to be registered with INSW. Capital projects can be registered either as a program (comprising of a group of related projects or activities) or as a project (which may or may not be part of a program).

According to the IIAF, programs tend to have a lifespan of several years and aim to deliver outcomes and benefits related to an organisation's strategic objectives. Projects tend to have a shorter lifespan, and deal with outputs. Projects can, however, be grouped under a single program if they are similar in nature or if they are aimed at collectively achieving a strategic objective. Complex projects can be delivered in multiple stages, under different contracts, and across different time periods.

The last assurance review of the entire WestConnex program of works as a whole was in 2015

INSW conducted the first IIAF gateway review of WestConnex in August 2015. TfNSW developed a draft WestConnex Updated Strategic Business Case to consolidate the latest analysis on WestConnex, and to confirm that the project remained fit for purpose, economically viable, and financially deliverable. The review followed a recommendation in our 2014 performance audit report that business cases be thoroughly revisited.

During September 2015, INSW conducted additional informal reviews to identify strategic risks associated with public release of the WestConnex business case. Subsequently, INSW gave the Premier of NSW its views on the draft business case, including the following points:

  • The $398 million budget for Sydney Gateway was insufficient to meet the benefits claimed in the business case for a ‘functional’ connection to Sydney Airport and Port Botany. INSW studies indicate a future‑proof solution would require a minimum spend of $755 million.
  • Enabling works for WestConnex estimated at $1.534 billion were excluded from the cost of WestConnex. Significant work remained for RMS to identify mitigation measures to address planning approvals and network performance issues.
  • Enabling works (a Southern Connector), an access ramp and surface road improvements within St Peters were excluded from the draft 2015 business case despite their inclusion in the WestConnex scope in the 2014–15 State Budget.
  • The overall cost of works not funded within the WestConnex budget ranged from $2.011 billion to $2.196 billion. This included the enabling works, access ramp and surface road improvements and the shortfall for Sydney Gateway.

All WestConnex related projects, including Sydney Gateway have undergone independent assurance reviews under the IIAF

Since INSW submitted the first WestConnex progress update report to Cabinet in June 2015, INSW has been reporting monthly on the different stages of the WestConnex Program, including Sydney Gateway, as the projects were registered with INSW as High‑Profile, High‑Risk projects. Separate reporting enabled INSW to report and review each stage with more detailed scrutiny, compared to the reporting and reviewing at a program level.

WestConnex Stage 2 (New M5) underwent both mandatory and non‑mandatory reviews at key points in the project lifecycle. Three mandatory gateway reviews – at Gate 2 (Final business case), Gate 3 (Readiness for market), and Gate 4 (Tender evaluation) – were conducted by TfNSW before the introduction of IIAF. Four non‑mandatory health check reviews and one non‑mandatory deep dive review were conducted after the introduction of the IIAF managed by INSW.

Similarly, WestConnex Stage 3 projects – M4‑M5 link, M4‑M5 Tunnels, and Rozelle Interchange – also underwent mandatory and non‑mandatory reviews at key points in their lifecycle under IIAF.

The M4‑M5 Link had two mandatory gateway reviews and one non‑mandatory health check review under IIAF. These reviews were conducted before Stage 3 was split into two stages, due to major design changes to the Rozelle Interchange and the M4‑M5 tunnels.

The M4‑M5 tunnels had two mandatory gateway reviews (at Gates 3 and 4), one non‑mandatory health check review, and one non‑mandatory deep dive review under IIAF.

Rozelle Interchange also underwent three mandatory gateway reviews at Gate 3 (part 1), Gate 3 (part 2), and Gate 4, two non‑mandatory health check reviews, and one non‑mandatory deep dive review under IIAF.

Since mid‑2017, the Sydney Gateway project has undergone required independent assurance reviews, as well as a number of optional assurance reviews

In November 2016, INSW conducted a mandatory Gate 1 gateway review on a strategic business case for the Sydney Gateway Project. TfNSW did not proceed with this business case. Following the separation of Sydney Gateway from WestConnex in mid‑2017, TfNSW developed a new business case for Sydney Gateway. It has undergone the required Gate 1, Gate 2, and Gate 3 gateway reviews, as well as two non‑mandatory health check reviews, and three non‑mandatory deep dive reviews under IIAF.

Network integration works have undergone all IIAF required assurance reviews

TfNSW completed a strategic business case for the Network Integration Program in August 2020, and INSW completed a gateway review in November 2020. This is despite network integration projects starting as early as 2015, with $645 million having been spent by June 2020. The strategic business case included a prioritisation process for completing remaining works in the program. Prior to November 2020, TfNSW registered individual network integration projects with INSW, and these projects have undergone gateway reviews where required.

The Network Integration Program strategic business case does not include Rozelle interchange network integration works ($353 million) and additional network integration works to settle a contractor claim adjacent to St Peters Interchange ($190 million). These were excluded from the business case on the basis they had already been approved by government, and as such were not subject to the prioritisation elements of the business case. TfNSW has not developed separate business cases for these works, although the scope of the St Peters Interchange works was developed through a negotiated process.

TfNSW did not prepare business cases for some network integration works which have commenced, including the $323 million Campbell Road/Euston Road works

Prior to its development of the August 2020 strategic business case, TfNSW did not prepare business cases for many network integration works that have commenced, and in some instances were completed, before 2019. Significantly, TfNSW did not prepare a business case for the Campbell Road/Euston Road works, which cost $323 million and have been completed.

In 2016, TfNSW’s Business Case Policy requires the creation of business cases for capital projects costing over $1.0 million. At the time of writing this report, TfNSW’s draft policy requires full business cases for capital projects costing $10.0 million or more.

There is no requirement for ongoing ‘whole‑of‑program’ assurance of the WestConnex program of works, including related projects

INSW conducted its first gateway review of WestConnex (as a program, which consisted of composite projects) in August 2015. Following that review, TfNSW registered each of the components of WestConnex with INSW as individual projects, rather than keeping WestConnex registered as a program or complex project. The IIAF allows this to occur.

Separate registration enabled INSW to report and review each stage with more scrutiny compared to whole‑of‑program level review.

Such an approach has merit, considering the individual stages (and components of these stages) are multi‑million dollar works in their own right. Each project has its own timing for gateway reviews at stages such as 'Readiness for Market' and 'Tender Evaluation'.

Once a program such as WestConnex is broken down into its composite parts, there is no requirement for the sponsor agency (TfNSW) or INSW to conduct independent assurance on the program of works as a whole until the whole program is completed as part of the Benefits Realisation (Gate 6) gateway review. The absence of strategic, holistic reviews of projects of the scale and complexity such as WestConnex during their delivery allows for total costs and benefits to become opaque and avoid scrutiny. Projects of this scale require greater ongoing transparency on total costs and benefits in order to ensure confidence they will meet intended objectives within budget.

INSW has advised us that it has prepared a proposal to expand its assurance function to include whole‑of‑program review of inter‑related infrastructure projects.

Appendix one – Responses from agencies

Appendix two – Network integration works

Appendix three – About the audit

Appendix four – Performance auditing

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #351 - released (17 June 2021).