Actions for Government assistance to industry

Government assistance to industry

Industry
Management and administration
Project management

Governments provide assistance to industry for a number of reasons, including facilitating economic growth, increase employment, support regional development, or grow priority industries.
 
This audit examined seven programs administered by the former Department of Trade and Investment, Regional Infrastructure and Services that provide at least $2 million per year in grants and subsidies to industry. This included the State Investment Attraction Scheme and Regional Industries Investment Fund.

 

Parliamentary reference - Report number #262 - released 17 December 2015

Published

Actions for Volume Ten 2015 Health

Volume Ten 2015 Health

Health
Information technology
Internal controls and governance
Project management
Risk

NSW Health, on average, met the emergency department triage response time targets across all triage categories in 2014-15 for the second consecutive year. However, fewer health entities met all triage targets in 2014-15, according to a report released by the New South Wales Acting Auditor-General, Tony Whitfield. 
 
NSW Health improved its emergency department treatment performance in 2014-15, but did not achieve its target of 81 per cent of patients being admitted, transferred or discharged within four hours of presenting. In 2014-15, the State average was 74.3 per cent compared to 73.9 per cent in 2013-14. Only five local health districts achieved the 81 per cent target in 2014-15.

Published

Actions for Volume Six 2015 Transport

Volume Six 2015 Transport

Transport
Information technology
Internal controls and governance
Project management
Risk

Public transport revenue decreased by 2.7 per cent despite a fare increase and increased patronage. Twenty-five per cent of all Opal trips (over 74 million) were free, including 47 per cent of trips on ferries, according to a report released today by the New South Wales Acting Auditor-General, Tony Whitfield. These trips were valued at $189 million.

Published

Actions for Albert 'Tibby' Cotter Walkway

Albert 'Tibby' Cotter Walkway

Transport
Internal controls and governance
Procurement
Project management

On 17 September 2015, the Acting Auditor-General of New South Wales, Tony Whitfield, released a report on the Albert ‘Tibby’ Cotter Walkway which crosses over Anzac Parade in Moore Park. The Walkway’s primary function is to cater for event patrons in the precinct. Moore Park is listed on the State Heritage Register and is an open space specifically established to cater for public recreation.
 
Roads and Maritime Services (RMS) delivered the Walkway to an extremely tight timeframe. It was operational for the 2015 Cricket World Cup at the Sydney Cricket Ground as promised by the government. However, the World Cup deadline added substantially to the total cost of the Walkway, which is projected to be $38 million.
 
Transport for NSW and RMS could not provide evidence of a compelling economic or financial argument to support the construction of the Walkway or for the tight deadline. Also, the processes they adopted to provide assurance of the project’s value for money were not adequate.

 

Parliamentary reference - Report number #260 - released 17 September 2015

Published

Actions for Sydney metropolitan bus contracts

Sydney metropolitan bus contracts

Transport
Internal controls and governance
Management and administration
Procurement
Project management
Service delivery

On 9 September 2015, the Acting Auditor-General of New South Wales, Tony Whitfield, released a report on Sydney Metropolitan Bus Service Contracts.
 
All scheduled bus services in the Sydney metropolitan area are provided under contracts with the public and private operators. The contracts allow Transport for NSW (TfNSW) to determine what bus services are provided and to whom. This audit assessed the effectiveness of TfNSW’s design and management of these contracts.
 
Bus services provided under the Sydney Metropolitan Bus Service Contracts have largely been effective and efficient. Operators are mostly meeting their key performance indicators. Customer satisfaction is better than under the previous contracts and improving, patronage is increasing, and the unit costs of providing services are now lower than under the previous contracts. 
 
However, punctuality remains a problem. Private operators are mostly starting their trips on time, but rarely meeting their mid and end-of-trip targets. State Transit Authority’s (STA) punctuality is improving but is worse than private operators, and other areas of performance are generally below private operators.
 
The current situation is a substantial improvement over what we found in our 2010 audit on the previous contracts.

 

Parliamentary reference - Report number #258 - released 9 September 2015

Published

Actions for Large construction projects

Large construction projects

Treasury
Transport
Health
Industry
Planning
Premier and Cabinet
Whole of Government
Compliance
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management

The independent assurance given to the NSW Government and sponsor agencies on the viability of large capital projects throughout their lifecycle is inadequate. Government policy is regularly not followed and not properly communicated to those responsible for implementing such policy.
 
This audit sought to test the effectiveness of the NSW capital project assurance system - which includes gateway reviews and reporting - but significant levels of non-compliance identified in our case studies prevented this. The NSW Commission of Audit also identified this issue in 2012. Gateway reviews are conducted by independent reviewers at key stages of a project’s life cycle and provide an independent assessment on a project’s readiness to proceed to the next stage.

 

Parliamentary reference - Report number #252 - released 7 May 2015

Published

Actions for Country towns water supply and sewerage program

Country towns water supply and sewerage program

Industry
Planning
Environment
Internal controls and governance
Management and administration
Project management
Service delivery

The Country Towns Water Supply and Sewerage Program has effectively promoted adoption of better management practices by local water utilities, but will not achieve its objective of eliminating the water supply and sewerage infrastructure backlog in urban areas of country NSW.
 
The $1.2 billion Program aims to help local water utilities provide appropriate, affordable, cost effective and well-managed water supply and sewerage services in the urban areas of country NSW. It has two broad elements:

  • promoting adoption of better practices 
  • providing financial assistance towards the capital cost of infrastructure backlog works.

 

Parliamentary reference - Report number #251 - released 4 May 2015

Published

Actions for Areas of focus from 2014

Areas of focus from 2014

Education
Community Services
Finance
Health
Industry
Justice
Local Government
Planning
Premier and Cabinet
Transport
Treasury
Universities
Whole of Government
Environment
Compliance
Financial reporting
Fraud
Information technology
Internal controls and governance
Procurement
Project management
Risk

The 2014 audits showed that the quality and timeliness of financial reporting have continued to improve. However, many agencies do not have financial sustainability indicators that provide early warning of management issues, such as an inability to meet financial obligations. Weaknesses were identified in information security, management of leave balances, asset management and internal controls.
 
Governance issues and gaps in performance information and reporting across the sector suggest Chief Financial Officers should have a stronger role and be more involved in strategy and risk management to maximise performance and add value.
 

Published

Actions for Vocational education and training reform

Vocational education and training reform

Education
Industry
Management and administration
Procurement
Project management
Service delivery
Workforce and capability

The Department’s framework for VET reform has the potential to effectively achieve the government’s immediate objectives for the reform, which are associated with meeting its commitments under the National Partnership Agreement for Skills Reform without spending more. We found that the government is addressing VET reform objectives in the following order of priority: no extra cost (budget neutrality), TAFE viability, quality VET, access to VET for regions and equity groups, more contestability, student choice. Overall, we conclude that a more balanced approach, by putting more emphasis on increased contestability and student choice, is more likely to maximise the public value for the government’s investment in VET.

 

Parliamentary reference - Report number #249 - released 29 January 2015

Published

Actions for The Millennium Train Project

The Millennium Train Project

Transport
Infrastructure
Procurement
Project management
Service delivery

State Rail has made significant improvements since the purchase of the Tangara. It improved measures necessary for handling contracts dealing with technically complex and innovative projects, although some other problems have been encountered, with new lessons to learn. The design and manufacture of new trains requires a significant investment in both time and cost. The Millennium Train has come at a considerably higher price than originally expected. And it is very late compared to the Government’s original announcements, as the development/design took longer than planned.

 

Parliamentary reference - Report number #112 - released 17 June 2003