Actions for Handback of the M4 Tollway

Handback of the M4 Tollway

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management

This audit focuses on the M4 handback. It looks at whether the road will be in good condition when the State gets it back, and whether it will cope with the extra traffic after the toll is removed. These are critical issues for taxpayers and motorists. Taxpayers don’t want to be responsible for a large repair bill and motorists don’t want to be stuck in traffic jams.

To ensure that future private sector partnerships (PPP) deal adequately with handback, we recommend that the Roads and Traffic Authority (RTA):

  • ensure deeds spell out an appropriate inspection and testing program to determine repairs required to bring roads up to a satisfactory condition at handback (p.11)
  • ensure deeds link condition standards and maintenance approaches to changing industry standards and approaches over the life of the PPP (p.11)
  • consider including in deeds a requirement that operators provide a performance bond or similar security over the cost of handback repairs (p.11)
  • review the lessons learnt from the M4 tollway handback and determine whether it should seek to negotiate changes to existing tollway deeds to better deal with handback, by June 2010 (p.11)

 

Parliamentary reference - Report number #193 - released 27 October 2009

Published

Actions for Tackling Cancer with Radiotherapy

Tackling Cancer with Radiotherapy

Health
Internal controls and governance
Management and administration
Procurement
Service delivery
Workforce and capability

Overall radiotherapy services are managed in a reasonably efficient and effective manner. Much is being done to further improve efficiency and effectiveness, and more can be done. While New South Wales has a number of well-established radiotherapy treatment centres, the high capital cost limits their availability in all hospitals. Some patients need to travel long distances and be away from their homes for up to seven weeks. The projected growth in demand for radiotherapy services will further challenge NSW Health and it needs to more clearly demonstrate how it will have the right facilities in the right place at the right time.

 

Parliamentary reference - Report number #188 - released 23 June 2009

Published

Actions for Grants Administration

Grants Administration

Premier and Cabinet
Treasury
Health
Community Services
Planning
Compliance
Internal controls and governance
Management and administration
Procurement
Risk

We found no significant difference in the funding of government and opposition electorates. However, more money was given to electorates that were safely held by the major parties. These seats received $1.29 for every dollar given to marginal and independent seats with government marginals getting the least. Electorates also receive different levels of funding according to which region they are in. Such variations may reflect valid agency objectives such as meeting State Plan targets or addressing socio-economic disadvantage.

But while agencies publish who gets what, they do not adequately evaluate or explain what grant programs have achieved. As a result, there is a risk that New South Wales may not get the best value for its spending. We recommend that agencies regularly evaluate their grant programs and publish the results.

 

Parliamentary reference - Report number #186 - released 6 May 2009

Published

Actions for Purchasing Hospital Supplies: Follow-up of 2002 Performance Audit

Purchasing Hospital Supplies: Follow-up of 2002 Performance Audit

Health
Asset valuation
Financial reporting
Management and administration
Procurement
Service delivery

Periodically we review the extent to which agencies have changed their practices as a result of our audits. This gives Parliament and the public an update on the extent of progress made.

In this follow-up audit, we examine changes following our September 2002 report, to assess whether NSW Health has improved its buying of hospital supplies using electronic systems.

NSW Health spends over $1.3 billion on hospital supplies. It is the largest expenditure area after employee costs. Reform of this area has the potential to make significant savings that could be redirected to frontline services.

As part of our series of audits in the area of e-government, our previous audit looked closely at the extent to which technology was being used to deliver potentially major savings in purchasing hospital supplies. This is a key area of so-called “process re-engineering” in the “e” field, and NSW Health provided an ideal case study.

Whilst implementing large-scale e-procurement has many technical aspects, it is not chiefly a technical issue. The key requirements for success reside in effective change management, in particular being clear as to who has the authority to make change decisions and be held accountable.

This audit looks at NSW Health’s successes to date, and its frustrations and challenges in making further progress in this field. Many of the issues raised in this report may provide lessons for any agency that is seeking to drive a significant change program.

 

Parliamentary reference - Report number #145 - released 23 November 2005

Published

Actions for Managing Disruptions to Cityrail Passenger Services

Managing Disruptions to Cityrail Passenger Services

Transport
Management and administration
Service delivery
Workforce and capability

About one in every twelve Sydney people travels by train each weekday.

Unplanned disruptions to services are inevitable, even on the best-run railways.

Because of the complexities of Sydney’s rail network, a single event can disrupt many services.

From a passenger’s perspective, three issues are important –

  • how quickly the disruption is fixed (“When will my train arrive?”)
  • the accuracy of information provided about the disruption (“Should I change my travel/meeting/other arrangements?”)
  • how often the disruptions occur (“Should I give up on rail travel?”).

In this audit, we looked at how well RailCorp responds when there are routine disruptions to its CityRail passenger services. We focused on how RailCorp manages passenger journeys and informs passengers.

This report informs Parliament and the community about the limitations of the current system, and what more needs to be done in order to minimise the impact of disruptions on passengers.

It should also help passengers judge the extent to which they can rely on the information they receive, and to better understand some of the obstacles faced by staff.

 

Parliamentary reference - Report number #139 - released 22 June 2005

Published

Actions for Follow-up of Performance Audit: Bus Maintenance and Bus Contracts

Follow-up of Performance Audit: Bus Maintenance and Bus Contracts

Transport
Asset valuation
Compliance
Financial reporting
Infrastructure
Management and administration
Procurement
Project management
Service delivery
Workforce and capability

Periodically we review the extent to which agencies have implemented the recommendations they accepted from our earlier audits.

This gives Parliament and the public an update on the extent of progress made.

In this follow-up audit, we examine changes following our May 2002 report on how well the:

  • State Transit Authority maintained its buses
  • Ministry of Transport administered contracts for the provision of regular passenger bus services.

 

Parliamentary reference - Report number #138 - released 14 June 2005

Published

Actions for Emergency Mental Health Services

Emergency Mental Health Services

Health
Management and administration
Service delivery
Shared services and collaboration
Workforce and capability

It is estimated that one in five people will be affected at some stage by a mental health problem or illness. The increasing prevalence of mental illness means that at some point in time most of us will either be affected or we will know of someone who is.

Although most people with mental illness can be treated in the community, at times some may require emergency treatment or admission to hospital for shortterm intensive therapy.

Not only are more mental health patients presenting to an emergency department for treatment than ever before, they are reportedly sicker and a greater number require admission to a hospital bed for further treatment. And, because of its very nature, those suffering from acute mental illness may not understand what is wrong or be able to communicate their problems clearly.

This makes access to emergency mental health services a significant issue for government that requires continuing attention.

The focus of this report is on the provision of 24-hour crisis services to adults. Emergency mental health services play a vital role in providing timely and appropriate care. Without proper treatment the severity of the illness may escalate, increasing the risk of self-harm or harm to others.

There have been many changes to mental health services over the last decade to deal with increasing demand. Much has been done to improve access to, and the quality of emergency services through significant increases in funding, the opening of new beds and the employment of more mental health staff.

Yet recent reviews have highlighted problems with accessing mental health beds and inadequate levels of psychiatric support in rural areas.

I believe that our report will provide valuable assistance to area health services on alternative models of emergency mental health care that better manage patient risk and further improve service quality.

 

Parliamentary reference - Report number #136 - released 26 May 2005

Published

Actions for The Millennium Train Project

The Millennium Train Project

Transport
Infrastructure
Procurement
Project management
Service delivery

State Rail has made significant improvements since the purchase of the Tangara. It improved measures necessary for handling contracts dealing with technically complex and innovative projects, although some other problems have been encountered, with new lessons to learn. The design and manufacture of new trains requires a significant investment in both time and cost. The Millennium Train has come at a considerably higher price than originally expected. And it is very late compared to the Government’s original announcements, as the development/design took longer than planned.

 

Parliamentary reference - Report number #112 - released 17 June 2003

Published

Actions for Review of Eastern Distributor

Review of Eastern Distributor

Transport
Infrastructure
Procurement
Project management

Following a resolution of the Legislative Council, the Audit Office has undertaken a performance audit of the Eastern Distributor. For a number of reasons, The Audit Office is not in the position to determine “whether the proposed toll and concession period represents the best deal”. In part this is the result of time constraints which do not allow a careful analysis of many toll and concession options. Similarly, the audit does not answer “whether the current proposal represents the best environmental outcome”. But each of these issues (toll and concession and environmental consequences) is discussed in the audit report.

The Audit Office recommends that the Roads and Traffic Authority (RTA), for any further major project of this type, ensures that it establishes a process which allows all decision makers to have a thorough understanding of the reasonableness of the proponents’ offers and their implications for the State and for the public. The Audit Office also recommends that the RTA should at the outset consult with TCorp in respect of each major project put to tender.

 

Parliamentary reference - Report number #42 - released 31 July 1997