Reports
Actions for Handback of the M4 Tollway
Handback of the M4 Tollway
This audit focuses on the M4 handback. It looks at whether the road will be in good condition when the State gets it back, and whether it will cope with the extra traffic after the toll is removed. These are critical issues for taxpayers and motorists. Taxpayers don’t want to be responsible for a large repair bill and motorists don’t want to be stuck in traffic jams. To ensure that future private sector partnerships (PPP) deal adequately with handb
Actions for Tackling Cancer with Radiotherapy
Tackling Cancer with Radiotherapy
Overall radiotherapy services are managed in a reasonably efficient and effective manner. Much is being done to further improve efficiency and effectiveness, and more can be done. While New South Wales has a number of well-established radiotherapy treatment centres, the high capital cost limits their availability in all hospitals. Some patients need to travel long distances and be away from their homes for up to seven weeks. The projected growth in deman
Actions for Grants Administration
Grants Administration
We found no significant difference in the funding of government and opposition electorates. However, more money was given to electorates that were safely held by the major parties. These seats received $1.29 for every dollar given to marginal and independent seats with government marginals getting the least. Electorates also receive different levels of funding according to which region they are in. Such variations may reflect valid agency objectives such
Actions for Waiting Times for Elective Surgery in Public Hospitals
Waiting Times for Elective Surgery in Public Hospitals
We recognise that managing waiting times is a difficult and complex task. Waiting times are influenced by many factors, some of which are outside the control of NSW Health. There are, however, steps which NSW Health could, and should, take to ensure that the processes to manage waiting times are efficient and effective. By all measures used by NSW Health, patients are waiting longer for elective treatment today than six or seven years ago. In March 2003
Actions for Dealing with Unlicensed and Unregistered Driving
Dealing with Unlicensed and Unregistered Driving
In our opinion there are inadequacies in the current arrangements for detecting unauthorised driving. For example better information is needed on the extent of unlicensed driving. This may require giving the NSW Police power to conduct random licence and registration checks. In addition, there are technological and legal constraints to the efficient and effective detection of unauthorised driving. Parliamentary reference - Report number #115&nbs
Actions for The Millennium Train Project
The Millennium Train Project
State Rail has made significant improvements since the purchase of the Tangara. It improved measures necessary for handling contracts dealing with technically complex and innovative projects, although some other problems have been encountered, with new lessons to learn. The design and manufacture of new trains requires a significant investment in both time and cost. The Millennium Train has come at a considerably higher price than originally expected. An
Actions for Delivering Services Online
Delivering Services Online
A staged, systematic and careful approach and extensive business re-engineering effort underpinned the Roads and Traffic Authority's (RTA) steady progress in providing customers with a range of reliable and secure online registration services. The RTA’s consistent and disciplined pursuit of new and challenging e-business opportunities is commendable. Parliamentary reference - Report number #111 - released 11 June 2003
Actions for Review of Eastern Distributor
Review of Eastern Distributor
Following a resolution of the Legislative Council, the Audit Office has undertaken a performance audit of the Eastern Distributor. For a number of reasons, The Audit Office is not in the position to determine “whether the proposed toll and concession period represents the best deal”. In part this is the result of time constraints which do not allow a careful analysis of many toll and concession options. Similarly, the audit does not answer “whether