Reports
Actions for WestConnex: Assurance to the Government
WestConnex: Assurance to the Government
This audit assesses the assurance provided to the NSW Government for the initial stages of the WestConnex project.
The audit examined the WestConnex project from concept development to the pre-tender phase for Stage 1A – M4 (Parramatta to Homebush Bay). It did not examine the merit of the project or whether it represented value-for-money.
This audit found a number of shortcomings with the governance of the WestConnex project during its early stages and makes recommendations on how to better govern the remainder of the project to minimise the risk of failure.
Parliamentary reference - Report number #247 - released 18 December 2014
Actions for Use of Purchasing Cards and Electronic Payment Methods
Use of Purchasing Cards and Electronic Payment Methods
NSW government agencies are not making sufficient use of purchasing cards and EFTs to pay for goods and services. There are potential savings in processing costs of around $22 per transaction from purchasing cards and over $7 when using EFTs instead of cheques.
Parliamentary reference - Report number #243 - released 5 June 2014
Actions for Regional Road Funding - Block Grant and REPAIR Programs
Regional Road Funding - Block Grant and REPAIR Programs
In 2013–14, Roads and Maritime Services (RMS) provided over $170 million to local councils through the Block Grant and REPAIR programs to spend on Regional Roads. Regional Roads are the link between State Roads and Local Roads.
Parliamentary reference - Report number #241 - released 8 May 2014
Actions for Visiting medical officers and staff specialists
Visiting medical officers and staff specialists
We found that hospitals are generally able to deploy their VMOs and staff specialists to be at the place and time required. However, a hospital’s ability to manage supply and demand at a local level is limited. This limitation will become more critical with the current national health reforms when public hospital funding will depend on their ability to set and meet activity targets and priorities. NSW Health cannot be sure that all payments made to VMOs are for agreed and delivered services. Across the hospitals visited we found limited checking of VMO claims for payment, limited quality information on staff specialist activities and limited hospital-level analysis of trends or inconsistencies in activities and treatments.
Parliamentary reference - Report number #219 - released 14 December 2011
Actions for Responding to Domestic and Family Violence
Responding to Domestic and Family Violence
Organisations generally work together to improve the safety of victims when there is an overt and serious crisis, particularly where children are involved. There are no standard ways for victims and perpetrators to access help that might prevent ongoing violence and address underlying issues. This is particularly problematic where there are repeat victims and perpetrators, many of whom have complex mental health, drug and alcohol problems and are difficult to work with. New South Wales has trialled a number of projects to improve the way that organisations work together to support vulnerable people in particular communities.
Parliamentary reference - Report number #218 - released 8 November 2011
Actions for Government expenditure and transport planning in relation to implementing Barangaroo
Government expenditure and transport planning in relation to implementing Barangaroo
Barangaroo is an ambitious and significant development on Government-owned Sydney Harbour foreshore. Construction on the 22 hectare CBD site is expected to take 12 years to 2023. Developer contributions to Government of $1 billion are to provide for public domain and other Government development costs, including a six hectare Headland Park. When completed the precinct is to service an anticipated 26,000 workers and residents and up to 33,000 visitors a day. The Auditor-General concluded that while there was extensive transport planning and extensive documentation supporting Government financial forecasts, considerable risks remain for the implementation of the Barangaroo project.
Parliamentary reference - Report number #214 - released 15 June 2011