Actions for WestConnex: Assurance to the Government

WestConnex: Assurance to the Government

Transport
Treasury
Premier and Cabinet
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk

This audit assesses the assurance provided to the NSW Government for the initial stages of the WestConnex project.

The audit examined the WestConnex project from concept development to the pre-tender phase for Stage 1A – M4 (Parramatta to Homebush Bay). It did not examine the merit of the project or whether it represented value-for-money.

This audit found a number of shortcomings with the governance of the WestConnex project during its early stages and makes recommendations on how to better govern the remainder of the project to minimise the risk of failure.

 

Parliamentary reference - Report number #247 - released 18 December 2014

Published

Actions for Managing Contaminated Sites

Managing Contaminated Sites

Planning
Industry
Environment
Compliance
Internal controls and governance
Management and administration
Project management
Regulation
Risk

NSW Government agencies with large landholdings need to better manage their contaminated sites.

When contaminated sites are reported to the Environmental Protection Authority (EPA) there are long delays in assessing the extent of contamination. The EPA also lacks the management controls to ensure that all significantly contaminated sites are actively monitored and key milestones for remediation are met.

 

Parliamentary reference - Report number #245 - released 10 July 2014

Published

Actions for Use of Purchasing Cards and Electronic Payment Methods

Use of Purchasing Cards and Electronic Payment Methods

Treasury
Compliance
Fraud
Procurement

NSW government agencies are not making sufficient use of purchasing cards and EFTs to pay for goods and services. There are potential savings in processing costs of around $22 per transaction from purchasing cards and over $7 when using EFTs instead of cheques.

 

Parliamentary reference - Report number #243 - released 5 June 2014

Published

Actions for Regional Road Funding - Block Grant and REPAIR Programs

Regional Road Funding - Block Grant and REPAIR Programs

Transport
Internal controls and governance
Management and administration
Project management
Risk

In 2013–14, Roads and Maritime Services (RMS) provided over $170 million to local councils through the Block Grant and REPAIR programs to spend on Regional Roads. Regional Roads are the link between State Roads and Local Roads.

 

Parliamentary reference - Report number #241 - released 8 May 2014

Published

Actions for Responding to Domestic and Family Violence

Responding to Domestic and Family Violence

Community Services
Justice
Health
Internal controls and governance
Management and administration
Service delivery

Organisations generally work together to improve the safety of victims when there is an overt and serious crisis, particularly where children are involved. There are no standard ways for victims and perpetrators to access help that might prevent ongoing violence and address underlying issues. This is particularly problematic where there are repeat victims and perpetrators, many of whom have complex mental health, drug and alcohol problems and are difficult to work with. New South Wales has trialled a number of projects to improve the way that organisations work together to support vulnerable people in particular communities.

 

Parliamentary reference - Report number #218 - released 8 November 2011

Published

Actions for Government expenditure and transport planning in relation to implementing Barangaroo

Government expenditure and transport planning in relation to implementing Barangaroo

Industry
Treasury
Transport
Compliance
Internal controls and governance
Management and administration
Project management
Service delivery

Barangaroo is an ambitious and significant development on Government-owned Sydney Harbour foreshore. Construction on the 22 hectare CBD site is expected to take 12 years to 2023. Developer contributions to Government of $1 billion are to provide for public domain and other Government development costs, including a six hectare Headland Park. When completed the precinct is to service an anticipated 26,000 workers and residents and up to 33,000 visitors a day. The Auditor-General concluded that while there was extensive transport planning and extensive documentation supporting Government financial forecasts, considerable risks remain for the implementation of the Barangaroo project. 

 

Parliamentary reference - Report number #214 - released 15 June 2011

Published

Actions for Purchasing Hospital Supplies: Follow-up of 2002 Performance Audit

Purchasing Hospital Supplies: Follow-up of 2002 Performance Audit

Health
Asset valuation
Financial reporting
Management and administration
Procurement
Service delivery

Periodically we review the extent to which agencies have changed their practices as a result of our audits. This gives Parliament and the public an update on the extent of progress made.

In this follow-up audit, we examine changes following our September 2002 report, to assess whether NSW Health has improved its buying of hospital supplies using electronic systems.

NSW Health spends over $1.3 billion on hospital supplies. It is the largest expenditure area after employee costs. Reform of this area has the potential to make significant savings that could be redirected to frontline services.

As part of our series of audits in the area of e-government, our previous audit looked closely at the extent to which technology was being used to deliver potentially major savings in purchasing hospital supplies. This is a key area of so-called “process re-engineering” in the “e” field, and NSW Health provided an ideal case study.

Whilst implementing large-scale e-procurement has many technical aspects, it is not chiefly a technical issue. The key requirements for success reside in effective change management, in particular being clear as to who has the authority to make change decisions and be held accountable.

This audit looks at NSW Health’s successes to date, and its frustrations and challenges in making further progress in this field. Many of the issues raised in this report may provide lessons for any agency that is seeking to drive a significant change program.

 

Parliamentary reference - Report number #145 - released 23 November 2005

Published

Actions for Oversight of State Owned Electricity Corporations

Oversight of State Owned Electricity Corporations

Treasury
Asset valuation
Financial reporting
Management and administration
Service delivery

Issues of corporate governance have long been a matter for concern in the private sector. Following recent corporate collapses and scandals, legislators and regulators in a number of countries have focused on strengthening governance in publicly traded corporations. Considerable attention has been given to setting clear expectations for the performance of boards and for the disclosure of information to various stakeholders.

Good governance is no less important in the public sector.

Indeed issues of oversight and accountability may be more complex in the public sector, particularly in government businesses. There are more stakeholders involved (portfolio Ministers, shareholder Ministers, Parliament and central agencies) and there are competing – and potentially conflicting - objectives (financial, social, environmental, etc).

Because of these potential conflicts, it is important that Boards understand what government expects of them. Some of these expectations reflect the government’s regulatory role in areas such as safety, pricing and ensuring consumers receive essential services. Some expectations reflect the government’s role as a business owner.

Having a clear separation of regulatory expectations from ownership expectations is essential if boards are to be accountable for their performance on both aspects. To assist in this separation, New South Wales (like many other jurisdictions) has adopted the concept of ‘shareholder Ministers’ – as distinct from the portfolio Minister – to exercise the ownership function.

This report looks more closely at a particular area - how the State conducts itself as the owner of the State owned electricity corporations. This is an important issue as the State’s (ie taxpayers’) equity in these businesses is worth over $9 billion. Managing the risks associated with continuing ownership of these businesses is an essential aspect of good governance.

Although the audit focuses on the State’s holdings in the electricity sector, its findings and recommendations have relevance for all State owned corporations.

 

Parliamentary reference - Report number #144 - released 19 October 2005

Published

Actions for Implementing Asset Management Reforms

Implementing Asset Management Reforms

Justice
Planning
Finance
Treasury
Asset valuation
Financial reporting
Infrastructure
Internal controls and governance
Management and administration
Project management

Hospitals, schools, public housing, roads, bridges, buses and trains are just some of the assets used by government in providing services to citizens.

The NSW Government’s asset base is impressive in size - with a value of around $167 billion and with government plans to spend around $8 billion acquiring or replacing assets in the current year. Another $2 billion is spent each year on maintenance.

Good asset management is very important to government; even a small efficiency gain in this area can provide significant returns. Good practice by those responsible for managing assets can improve reliability, extend asset life, save on maintenance costs and aid in identifying and disposing of unnecessary or non-performing assets.

Improving the NSW public sector’s approach to asset management has been on the reform agenda for at least a decade. Changes in practice have been accelerated more recently by integrating asset management policy with the budget process.

In this audit we examined NSW Treasury’s efforts to improve asset management practices in the public sector and the progress made by 3 agencies - the Department of Corrective Services, NSW Fire Brigades and the Powerhouse Museum - towards better managing their asset portfolios.

This report informs Parliament and the community on progress to date and what more needs to be done to ensure that agencies manage assets effectively and achieve best value.

 

Parliamentary reference - Report number #143 - released 12 October 2005

Published

Actions for Follow-up of Performance Audit: Bus Maintenance and Bus Contracts

Follow-up of Performance Audit: Bus Maintenance and Bus Contracts

Transport
Asset valuation
Compliance
Financial reporting
Infrastructure
Management and administration
Procurement
Project management
Service delivery
Workforce and capability

Periodically we review the extent to which agencies have implemented the recommendations they accepted from our earlier audits.

This gives Parliament and the public an update on the extent of progress made.

In this follow-up audit, we examine changes following our May 2002 report on how well the:

  • State Transit Authority maintained its buses
  • Ministry of Transport administered contracts for the provision of regular passenger bus services.

 

Parliamentary reference - Report number #138 - released 14 June 2005