Reports
Actions for Large construction projects
Large construction projects
The independent assurance given to the NSW Government and sponsor agencies on the viability of large capital projects throughout their lifecycle is inadequate. Government policy is regularly not followed and not properly communicated to those responsible for implementing such policy.
This audit sought to test the effectiveness of the NSW capital project assurance system - which includes gateway reviews and reporting - but significant levels of non-compliance identified in our case studies prevented this. The NSW Commission of Audit also identified this issue in 2012. Gateway reviews are conducted by independent reviewers at key stages of a project’s life cycle and provide an independent assessment on a project’s readiness to proceed to the next stage.
Parliamentary reference - Report number #252 - released 7 May 2015
Actions for Cost of Alcohol Abuse to the NSW Government
Cost of Alcohol Abuse to the NSW Government
The NSW Government does not estimate or report the total cost of alcohol abuse. The Audit Office of New South Wales’ sponsored research estimates it costs the government over $1 billion a year, or around $416 from each NSW household.
Parliamentary reference - Report number #235 - released 6 August 2013
Actions for The Cross City Tunnel Project
The Cross City Tunnel Project
In our opinion the Government’s ‘no net cost to government’ requirement was a legitimate (but not the only possible) basis for the tunnel bid process. The Government was entitled to decide that tunnel users meet the tunnel costs. Structuring the bid process on the basis of an upfront reimbursement of costs incurred (or to be incurred) by the Roads and Traffic Authority (RTA) was therefore appropriate.
In our opinion, however, the Government, Treasury and the RTA did not sufficiently consider the implications of an upfront payment involving more than simple project cost reimbursement (i.e. the ‘Business Consideration Fee’ component). In addition, the RTA was wrong to change the toll escalation factor late in 2002 to compensate the tunnel operator, Cross City Motorway Pty Ltd, for additional costs.
Parliamentary reference - Report number #152 - released 31 May 2006
Actions for Lease to Fox Studios Australia
Lease to Fox Studios Australia
The audit found that the process for the lease and development of the Showground site commenced on the basis that no Government moneys would be provided and no theme park activities would be allowed. However despite this a State Government subsidy of between $84.8m and $106.8m (in net present value terms) is to be provided for the development and the area of the Showground to be leased to Fox was extended to comprise 24.3 hectares of the 28.8 hectare site to allow Fox also to develop a family entertainment park.
The audit also found that the process commenced under the former Government were intended to ensure that no one party was placed above another however, the actual processes employed up to the General Election in March 1995 were so flawed as not to be relied upon to select a preferred proponent or to justify dispensing with a tender process.
Parliamentary reference - Report number #44 - released 8 December 1997