Reports
Actions for Volume Five 2011 focus on Superannuation, Compensation and Housing
Volume Five 2011 focus on Superannuation, Compensation and Housing
The audits of the New South Wales Government controlled superannuation entities financial statements for the year ended 30 June 2011 resulted in unmodified audit opinions within the Independent Auditor’s Reports. Findings show that Treasury should review the structure and number of public sector superannuation funds and consider whether efficiencies and cost savings could be achieved through consolidation.
Actions for Volume One 2011
Volume One 2011
The level of non compliance with the requirements of this Premier’s Memorandum is concerning, particularly considering the NSW Procurement Reforms were effective since 2006. The implementation strategy for procurement reform was announced as early as 2001. We recommend the governing bodies of agencies and management review, not only the processes their agencies have in place to comply with procurement reforms and requirements, but also more broadly how agencies identify and comply with laws, regulations, Treasury policy pronouncements, Premier’s memoranda and other obligations.
Actions for Volume Six 2010 focus on Human Services and Technology
Volume Six 2010 focus on Human Services and Technology
The report includes comments on his financial audits of NSW Government human services and technology agencies. The audits of these agencies’ financial reports for the year ended 30 June 2010 each resulted in an unqualified Independent Auditor’s Report. The number of supported accommodation places for people with a disability has increased by 517 during 2009-10.
Actions for The Cross City Tunnel Project
The Cross City Tunnel Project
In our opinion the Government’s ‘no net cost to government’ requirement was a legitimate (but not the only possible) basis for the tunnel bid process. The Government was entitled to decide that tunnel users meet the tunnel costs. Structuring the bid process on the basis of an upfront reimbursement of costs incurred (or to be incurred) by the Roads and Traffic Authority (RTA) was therefore appropriate.
In our opinion, however, the Government, Treasury and the RTA did not sufficiently consider the implications of an upfront payment involving more than simple project cost reimbursement (i.e. the ‘Business Consideration Fee’ component). In addition, the RTA was wrong to change the toll escalation factor late in 2002 to compensate the tunnel operator, Cross City Motorway Pty Ltd, for additional costs.
Parliamentary reference - Report number #152 - released 31 May 2006