Actions for Volume Eight 2011 Focus on Transport and Ports
Volume Eight 2011 Focus on Transport and Ports
The report includes comments on financial audits of government agencies in the Transport and Ports sectors. The audit of corporations’ financial statements for the year ended 30 June 2011 resulted in unmodified audit opinions within the Independent Auditor’s Reports. A key recommendation from the report is that Sydney Ports Corporation should continue working with other government authorities and industry stakeholders to improve the effectiveness of program initiatives for increasing container freight movements by rail. The Corporation should review the underlying causes hindering growth in the rail mode and develop and implement strategies to address the unfavourable trend.
Actions for Solar Bonus Scheme
Solar Bonus Scheme
A NSW Auditor General’s Report has found that the NSW Government and its agencies grossly underestimated the cost and number of people that would install systems under the Solar Bonus Scheme.
By October 2010, the estimated cost of the Scheme, if it continued the way it was going, would have reached $3.988 billion. More than ten times the original estimate of $362 million. In response to the increased cost, the gross tariff for new applicants was reduced from 60 to 20 cents reducing the estimated cost to $1.954 billion.
It was a statutory requirement that when 50 mega watts of installed capacity was reached, the Government would review the Scheme. By the time the review was completed the installed capacity had reached 101 mega watts.
Actions for Prequalification Scheme: Performance and Management Services
Prequalification Scheme: Performance and Management Services
There have been tangible improvements in the time it takes NSW Government agencies to engage consultants through the Government’s Prequalification Scheme. The Scheme was introduced in February 2008 to improve agencies’ procurement of consultants. More than 300 service providers have been prequalified and over $300 million worth of consultancy services have been provided. Ideally agencies should know what assignments each consultant has won, for what services, what their rates are and how well they have performed. Agencies should then be free to contact other agencies before engaging a consultant.
Parliamentary reference - Report number #216 - released 28 September 2011
Actions for Transport of Dangerous Goods
Transport of Dangerous Goods
Dangerous goods make up 10-15% of domestic freight and have potential to harm people, property and the environment. They include substances such as explosives, flammable liquids and gases, and oxidising agents. However, Government inspection programs were limited. The Office of Environment and Heritage carried out very few checks in the four years up to 2010, with no inspections made in the metropolitan area. This is despite Port Botany handling around 50,000 containers of dangerous goods per year. Statewide, only 303 inspections were made in 2009/10 and only 20 in 2008/09.
Parliamentary reference - Report number #212 - released 10 May 2011
Actions for Volume One 2011
Volume One 2011
The level of non compliance with the requirements of this Premier’s Memorandum is concerning, particularly considering the NSW Procurement Reforms were effective since 2006. The implementation strategy for procurement reform was announced as early as 2001. We recommend the governing bodies of agencies and management review, not only the processes their agencies have in place to comply with procurement reforms and requirements, but also more broadly how agencies identify and comply with laws, regulations, Treasury policy pronouncements, Premier’s memoranda and other obligations.
Actions for Volume Nine 2010 focus on Transport, Planning and Industry
Volume Nine 2010 focus on Transport, Planning and Industry
The report includes comments on his financial audits of NSW Government transport, planning and industry agencies for 2009-10. A key recommendation from the report is that the New South Wales Government identify lessons learnt from the metro experience and ensure that future decision processes are developed to ensure the State never again expends such a large amount of scarce transport funding dollars and valuable time on a project that does not proceed.
Actions for Volume Five 2010 focus on Public Financing Enterprises
Volume Five 2010 focus on Public Financing Enterprises
The report includes comments on NSW Treasury and agencies in the finance and superannuation sectors. The New South Wales public sector superannuation funds’ investments were $42.2 billion at 30 June 2010, up from $38.5 billion in 2009. Investment returns reached 14.5 per cent in 2009-10. This is a significant improvement on the investment returns of up to negative 18.4 per cent at the peak of the global financial crisis in 2008.
Actions for Condition of State Roads
Condition of State Roads
The Roads and Traffic Authority (RTA) has improved the overall surface condition of State Roads in the last decade. Country road surfaces are now generally much better. Ride quality has improved and cracking has been reduced. The RTA has also achieved a substantial reduction in the number of structurally deficient bridges over the same period.
Despite a significant increase in the State’s contribution to maintenance since 1999-2000, the RTA has deferred road rebuilding projects. The RTA is rebuilding at less than half its long term target, and has not met this target at any time this decade. The RTA has not identified how it will address deferred rebuilding, although it advises it is developing a new road network management plan which will address this.
Parliamentary reference - Report number #157 - released 16 August 2006
Actions for The Cross City Tunnel Project
The Cross City Tunnel Project
In our opinion the Government’s ‘no net cost to government’ requirement was a legitimate (but not the only possible) basis for the tunnel bid process. The Government was entitled to decide that tunnel users meet the tunnel costs. Structuring the bid process on the basis of an upfront reimbursement of costs incurred (or to be incurred) by the Roads and Traffic Authority (RTA) was therefore appropriate.
In our opinion, however, the Government, Treasury and the RTA did not sufficiently consider the implications of an upfront payment involving more than simple project cost reimbursement (i.e. the ‘Business Consideration Fee’ component). In addition, the RTA was wrong to change the toll escalation factor late in 2002 to compensate the tunnel operator, Cross City Motorway Pty Ltd, for additional costs.
Parliamentary reference - Report number #152 - released 31 May 2006