Refine search Expand filter

Reports

Published

Actions for Management of Historic Heritage in National Parks and Reserves

Management of Historic Heritage in National Parks and Reserves

Planning
Environment
Infrastructure
Management and administration

The National Parks and Wildlife Service is spreading its resources too thinly, running the risk that the heritage significance of important assets will eventually be lost.

 

Parliamentary reference - Report number #230 - released 29 May 2013

Published

Actions for Condition of State Roads

Condition of State Roads

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Service delivery

The Roads and Traffic Authority (RTA) has improved the overall surface condition of State Roads in the last decade. Country road surfaces are now generally much better. Ride quality has improved and cracking has been reduced. The RTA has also achieved a substantial reduction in the number of structurally deficient bridges over the same period. 

Despite a significant increase in the State’s contribution to maintenance since 1999-2000, the RTA has deferred road rebuilding projects. The RTA is rebuilding at less than half its long term target, and has not met this target at any time this decade. The RTA has not identified how it will address deferred rebuilding, although it advises it is developing a new road network management plan which will address this.

 

Parliamentary reference - Report number #157 - released 16 August 2006

Published

Actions for The Cross City Tunnel Project

The Cross City Tunnel Project

Transport
Treasury
Premier and Cabinet
Planning
Environment
Infrastructure
Management and administration
Procurement
Project management
Risk

In our opinion the Government’s ‘no net cost to government’ requirement was a legitimate (but not the only possible) basis for the tunnel bid process. The Government was entitled to decide that tunnel users meet the tunnel costs. Structuring the bid process on the basis of an upfront reimbursement of costs incurred (or to be incurred) by the Roads and Traffic Authority (RTA) was therefore appropriate.

In our opinion, however, the Government, Treasury and the RTA did not sufficiently consider the implications of an upfront payment involving more than simple project cost reimbursement (i.e. the ‘Business Consideration Fee’ component). In addition, the RTA was wrong to change the toll escalation factor late in 2002 to compensate the tunnel operator, Cross City Motorway Pty Ltd, for additional costs.

 

Parliamentary reference - Report number #152 - released 31 May 2006

Published

Actions for Agencies working together to improve services

Agencies working together to improve services

Premier and Cabinet
Treasury
Justice
Transport
Education
Internal controls and governance
Service delivery
Shared services and collaboration

In the cases we examined, we found that agencies working together can improve services or results. However, the changes were not always as great as anticipated or had not reached maximum potential. Establishing the right governance framework and accountability requirements between partners at the start of the project is critical to success. And joint responsibility requires new funding and reporting arrangements to be developed.

 

Parliamentary reference - Report number #149 - released 22 March 2006

Published

Actions for Management of road passenger transport regulation

Management of road passenger transport regulation

Transport
Management and administration
Regulation
Service delivery
Shared services and collaboration

The Audit Office is of the opinion that the Department’s levels of regulatory activity in respect of road passenger transport regulation may have exceeded optimum levels. The Department’s current focus on processing activity limits the Department in achieving all of its desired outcomes. The Audit Office considers that a change in the approach to undertaking and managing road passenger transport regulatory activities would achieve better outcomes for the community and a better use of resources within the Department.

The Audit Office believes that while there is scope to make some improvements from procedural changes, such changes would not be sufficient to generate significant improvements.

 

Parliamentary reference - Report number #75 - released 6 September 2000