Reports
Actions for CBD and South East Light Rail Project
CBD and South East Light Rail Project
Transport for NSW did not effectively plan and procure the CBD and South East Light Rail (CSELR) project to achieve best value for money according to a report released today by NSW Auditor-General, Margaret Crawford.
Transport for NSW is on track to deliver the project, but it will come at a higher cost with lower benefits than in the approved business case.
Parliamentary reference - Report number #278 - released 30 November 2016
Actions for Implementation of the NSW Government’s program evaluation initiative
Implementation of the NSW Government’s program evaluation initiative
The NSW Government’s ‘program evaluation initiative’, introduced to assess whether service delivery programs achieve expected outcomes and value for money, is largely ineffective according to a report released today by NSW Auditor-General, Margaret Crawford.
Government services, in areas such as public order and safety, health and education, are delivered by agencies through a variety of programs. In 2016–17, the NSW Government estimates that it will spend over $73 billion on programs to deliver services.
Parliamentary reference - Report number #277 - released 3 November 2016
Actions for Red tape reduction
Red tape reduction
Overall, NSW Government initiatives and processes to prevent and reduce red tape were not effective, according to a report released today by the NSW Auditor-General.
In 2015, the Government reported that its red tape reduction initiatives, implemented between 2011 and 2015, had resulted in $896 million in savings. While these initiatives resulted in some savings, the total value of savings is unknown because estimates for some initiatives were based on unverified assumptions, cost transfers or unrealised projections.
Parliamentary reference - Report number #272 - released 25 August 2016
Actions for Northside Storage Tunnel Project
Northside Storage Tunnel Project
The Northside Storage Tunnel was the first major public sector construction project using an alliance approach. In our opinion, the outcome of the project suggests that an alliance approach, when applied to a suitable project and managed appropriately, can support positive project outcomes. And in many respects the Alliance worked well. There are, however, a number of issues that we believe need to be addressed for future alliances.
Parliamentary reference - Report number #113 - released 24 July 2003
Actions for The Millennium Train Project
The Millennium Train Project
State Rail has made significant improvements since the purchase of the Tangara. It improved measures necessary for handling contracts dealing with technically complex and innovative projects, although some other problems have been encountered, with new lessons to learn. The design and manufacture of new trains requires a significant investment in both time and cost. The Millennium Train has come at a considerably higher price than originally expected. And it is very late compared to the Government’s original announcements, as the development/design took longer than planned.
Parliamentary reference - Report number #112 - released 17 June 2003