Actions for Central Agencies 2020

Central Agencies 2020

Premier and Cabinet
Treasury
Financial reporting
Internal controls and governance
Management and administration
Risk

This report analyses the results of our audits of the financial statements of the Treasury, Premier and Cabinet, Customer Service cluster agencies (central agencies), and the Legislature for the year ended 30 June 2020. The table below summarises our key observations.

1. Financial reporting

Audit opinions and timeliness of reporting

Unqualified audit opinions were issued on the 2019–20 financial statements of central agencies and the Legislature.

The audit opinion on the Social and Affordable Housing NSW Fund's compliance with the payment requirements of the Social and Affordable Housing NSW Fund Act 2016 was qualified.

All agencies met statutory deadlines for submitting
financial statements. 

Agencies were financially impacted by recent emergency events The NSW Government allocated $1.4 billion to provide small business support and bushfire recovery relief, support COVID-19 quarantine compliance management, recruit more staff to respond to increased customer demand, and meet additional COVID-19 cleaning requirements. Agencies spent $901 million (64 per cent of the allocated funding) for the financial year ended 30 June 2020. NSW Self Insurance Corporation reported an increase of $850 million in its liability for claims related to emergency events.
AASB 16 'Leases' resulted in significant changes to agencies' financial position The implementation of new accounting standards was challenging for many agencies. The New South Wales Government Telecommunications Authority was not well-prepared to implement AASB 16 'Leases' and had not completely assessed contracts that contained leases. This resulted in understatements of leased assets and liabilities by $56 million which were subsequently corrected.
Implementation of new revenue standards NSW Treasury did not adequately implement the new revenue standard AASB 1058 ‘Income of Not-for-Profit Entities’ for the Crown Entity. This resulted in understatements of $274 million in opening equity and $254 million to current year revenue, which have been corrected in the final financial statements.

2. Audit observations

Management letter findings and repeat issues Our 2019–20 audits identified nine high risk and 122 moderate risk issues across central agencies and the Legislature. The high risk issues were identified in the audits of:
  • Insurance and Care NSW
  • New South Wales Government Telecommunications Authority
  • Rental Bond Board
  • Independent Commission Against Corruption
  • NSW Treasury
  • Crown Entity
  • Department of Premier and Cabinet.

High risk findings include:

  • Insurance and Care NSW (icare) allocates service costs to the Workers Compensation Nominal Insurer, and the other schemes it supports. The documentation supporting cost allocations does not demonstrate how these allocations reflect actual costs. There is a risk of the Workers Compensation Nominal Insurer being overcharged.
  • New South Wales Government Telecommunications Authority's delay in capitalisation and valuation of material capital projects; and insufficient work performed to implement the new accounting standard AASB 16 ‘Leases’.
  • NSW Treasury's four-year plan to transition RailCorp to a for-profit State Owned Corporation called Transport Asset Holding Entity of New South Wales (TAHE) by 1 July 2019, remains to be implemented. On 1 July 2020, RailCorp converted to TAHE. A large portion of the planned arrangements are still to be implemented. As at the time of the audit, the TAHE operating model, Statement of Corporate Intent (SCI) and other key plans and commercial agreements were not finalised. In the absence of commercial arrangements with the public rail operators, there is a lack of evidence to demonstrate TAHE’s ability to create a commercial return in the long term. This matter has been included as a high risk finding in our management letter as there may be financial reporting implications to the State if TAHE does not generate a commercial return for its shareholders in line with the original intent. NSW Treasury and TAHE should ensure the commercial arrangements, operating model and SCI are finalised in 2020–21.

Of the 122 moderate risk issues, 36 per cent were repeat issues. The most common repeat issue related to weaknesses in controls over information technology user access administration, which increases the risk of inappropriate access to systems and records.

Grants administration for disaster relief Service NSW delivers grants responding to emergency events on behalf of other NSW Public Sector agencies. Since the first grant program commenced in January 2020, Service NSW processed approximately $791 million to NSW citizens and businesses impacted by emergency events for the financial year ended 30 June 2020. A performance audit of grants administration for disaster relief is planned for 2020–21. It will assess whether grants programs administered under the Small Business Support Fund were effectively designed and implemented to provide disaster relief.
Internal controls at GovConnect NSW service providers require enhancement

GovConnect NSW provides transactional and information technology services to central agencies. It engages an independent service auditor (service auditor) from the private sector to perform annual assurance reviews of controls at service providers, namely Infosys, Unisys and the Department of Customer Service (DCS). The service auditor issued:

  • unqualified opinions on information technology and business process controls at Infosys and Unisys, but there was an increase in control deficiencies identified in the user access controls at these service providers
  • a qualified opinion on DCS's information technology (IT) security monitoring controls because security tools were not implemented and monitored for the entire financial year. Responsibility for IT security monitoring transitioned from Unisys to DCS in 2019–20. These control deficiencies can increase the risk of fraud and inappropriate use of sensitive data.

These may impact on the ability of agencies to detect and respond to a cyber incident.

Recommendation:

We recommend DCS work with GovConnect service providers to resolve the identified control deficiencies as a matter of priority.

The NSW Public Sector's cyber security resilience needs to improve

The NSW Cyber Security Policy requires agencies to provide a maturity self-assessment against the Australian Cyber Security Centre (ACSC) Essential 8 to the head of the agency and Cyber Security NSW annually. Completed self-assessment returns highlighted limited progress in implementing the Essential 8.

Repeat recommendation:

Cyber Security NSW and NSW government agencies need to prioritise improvements to their cyber security resilience as a matter of urgency

Three Insurance and Care NSW (icare) entities had net asset deficiencies at 30 June 2020 The Workers Compensation Nominal Insurer, NSW Self Insurance Corporation and the Lifetime Care and Support Authority of NSW all had negative net assets at 30 June 2020. These icare entities did not hold sufficient assets to meet the estimated present value of all of their future payment obligations at 30 June 2020. The deterioration in net assets was largely due to increases in outstanding claims liabilities. Notwithstanding the overall net asset deficiencies, the financial statements for these entities were prepared on a going concern basis. This is because future payment obligations are not all due within the next 12 months. Settlement is instead expected to occur over years into the future, depending on the nature of the benefits provided by each scheme.
icare has not been able to demonstrate that its allocation of costs reflects the actual costs incurred by the Workers Compensation Nominal Insurer and other schemes

Costs are incurred by icare as the 'service entity' of the statutory scheme it administers, and then subsequently recovered from the schemes through 'service fees'. In the absence of documentation supported by robust supporting analysis, there is a risk of the schemes being overcharged, and the allocation of costs being in breach of legislative requirements.

Recommendation:

icare should ensure its approach to allocating service fees to the Workers Compensation Nominal Insurer and the other schemes it manages, is transparent and reflects actual costs.

icare did not comply with GIPA requirements icare did not comply with the Government Information (Public Access) Act 2009 (GIPA) contract disclosure requirements in 2019–20 and has not complied for several years. A total of 417 contracts were identified by management as not having been published on the NSW Government’s eTendering website. The final upload of these past contracts occurred on 20 August 2020.
Implementation of Machinery of Government (MoG) changes MoG changes impacted the governance and business processes of some agencies. Our audits identified and reported areas for improvement in the consolidation of corporate functions following MoG implementation processes at Infrastructure NSW and in the Customer Service cluster.

This report provides Parliament and other users of NSW Government central agencies' financial statements and the Legislature's financial statements with the results of our financial audits, observations, analyses, conclusions and recommendations.

Emergency events, such as bushfires, floods and the COVID-19 pandemic significantly impacted agencies in 2019–20. Our findings on nine agencies that were most impacted by recent emergency events are included throughout this report.

Refer to Appendix one for the names of all central agencies and Appendix four for the nine agencies most impacted by emergency events.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely. This chapter outlines our audit observations on the financial reporting of central agencies and the Legislature for 2020, including the financial implications from recent emergency events.

Section highlights

  • Unqualified audit opinions were issued on the 2019–20 financial statements of central agencies and the Legislature. All agencies met the statutory deadlines for submitting their financial statements.
  • The audit opinion on the Social and Affordable Housing NSW Fund's compliance with the payment requirements of the Social and Affordable Housing NSW Fund Act 2016 was qualified as a result of a payment made without a Treasurer's delegation.
  • Agencies were impacted by emergency events during 2019–20. This included additional grants to fund specific deliverables.
  • The implementation of new accounting standards was challenging for many agencies. The New South Wales Government Telecommunications Authority was not well-prepared to implement AASB 16 'Leases' and had not completely assessed contracts that contained leases. This resulted in understatements of leased assets and liabilities by $56 million which were subsequently corrected.
  • NSW Treasury did not adequately implement the new revenue standard AASB 1058 ‘Income of Not-for-Profit Entities’ for the Crown Entity. This resulted in understatements of $274 million in opening equity and $254 million to current year revenue in the financial statements. These misstatements were due to incorrect revenue calculations performed by the Transport agencies. The Crown Entity relies on information from Transport agencies as they are responsible for carrying out the State’s contractual obligations for Commonwealth funded transport projects. The extent of misstatements could have been reduced with more robust quality review processes in place by Treasury and Transport.

 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines:

  • our observations and insights from the financial statement audits of agencies in the central agencies and the Legislature
  • our assessment of how well agencies adapted their systems, policies, procedures and governance arrangements in response to recent emergencies.

Section highlights

  • The 2019–20 audits identified nine high risk and 122 moderate risk issues across the agencies. Of the 122 moderate risk issues, 44 (36 per cent) were repeat issues. The most common repeat issue relates to weaknesses in controls over information technology user access administration.
  • Service NSW delivers grants responding to emergency events on behalf of other NSW Public Sector agencies. Since the first grant program commenced in January 2020, Service NSW processed approximately $791 million to NSW citizens and businesses impacted by these emergency events for the financial year ended 30 June 2020.
  • GovConnect NSW engaged an independent auditor (the service auditor) from the private sector to evaluate the internal controls of its service providers. DCS's information technology security monitoring controls were qualified by the service auditor because security tools were not implemented and monitored for the entire financial year. These may impact on the ability of agencies to detect and respond to a cyber incident.
  • NSW Government agency self-assessment results show that the NSW Public Sector's cyber security resilience needs urgent attention.
  • The Workers Compensation Nominal Insurer, NSW Self Insurance Corporation and the Lifetime Care and Support Authority of NSW all had negative net assets at 30 June 2020. The financial statements for these entities continued to be prepared on a going concern basis as their liabilities are not all due for settlement within the next 12 months.
  • icare did not comply with the Government Information (Public Access) Act 2009 (GIPA) contract disclosure requirements in 2019–20, and has not complied for several years. A total of 417 contracts were identified by management as not having been published on the NSW Government’s eTendering website. The final upload of these past contracts occurred on 20 August 2020.
  • Machinery of Government (MoG) changes impacted the governance and business processes of affected agencies. Our audits identified and reported areas for improvement in the consolidation of corporate functions following MoG changes at Infrastructure NSW and in the Customer Service cluster.

 

Published

Actions for Health 2020

Health 2020

Health
Compliance
Financial reporting
Infrastructure
Internal controls and governance
Service delivery

This report analyses the results of our audits of financial statements of the Health cluster for the year ended 30 June 2020. The table below summarises our key observations.

1. Financial reporting

Financial reporting

Unqualified financial audit opinions

The financial statements of NSW Health and its 25 controlled entities received unqualified opinions.

The number of corrected and uncorrected misstatements increased from the prior year. Misstatements related predominantly to the implementation of new accounting standards, asset revaluations and accounting for new revenue streams to cover the cost of HSW Health’s response to the COVID-19 pandemic.

Qualified compliance audit opinion

We issued a qualified audit opinion for the Ministry of Health’s Annual Prudential Compliance Statement for aged care facilities operated by NSW Health. We identified 18 instances of material non-compliance with the Fees and Payments Principles 2014 (No. 2) (the Principles) in 2019–20 (30 in 2018–19).

Financial performance

NSW Health received an additional $3.3 billion in funding to cover costs associated with its response to the COVID-19 pandemic.

The impacts of the COVID-19 pandemic on the cluster were significant for health entities and included changes to operations, increased revenues, expenditure, assets and liabilities. Cancellation of elective surgery and decreased emergency department presentations meant that despite the pandemic, activity levels at many health entities decreased. Health Pathology and HealthShare were notable exceptions.

In the period to the 30 June 2020, NSW Health reported that over 900,000 COVID-19 tests were conducted. Health Pathology conducted over 500,000 of these tests. Health Pathology's surge requirements were enhanced through arrangements with 13 private sector providers. HealthShare purchased $864.2 million of personal protective equipment.

Overall, NSW Health recorded an operating surplus of $3.1 billion in 2019–20, an increase of $2.0 billion from 2018–19. As in previous years, the surplus largely resulted from additional revenue received to fund capital projects including the construction of new facilities, upgrades and redevelopments. In 2019–20 additional Commonwealth and State funding for the purchase and stockpiling of personal protective equipment also contributed to the operating surplus.

Overtime payments The Ambulance Service of NSW’s (NSW Ambulance) reduced their overtime payments to $79.7 million in 2019–20 ($83.1 million in 2018–19). Overtime payments in 2019–20 included $6.8 million related to the response to the 2019–20 bushfire season. NSW Ambulance overtime payments represent 16.8 per cent of total overtime payments in the cluster.

2. Audit observations

Internal control deficiencies

We identified more internal control deficiencies in 2019–20. The number of repeat issues from prior years also remains high.

NSW Health addressed 18 out of the 25 information system control deficiencies during the year.

Several key agreements lacked formal documentation. This included agreements between the Ministry and health entities, between health entities and agencies in other clusters and between the Ministry and health departments in other jurisdictions.

Infrastructure delivery NSW Health had 44 ongoing major capital projects at 30 June 2020 with a total revised budget of $12.3 billion. The revised total budget of $12.3 billion is $2.0 billion more than the original budget. NSW Health revises budgets when it combines project stages.

This report provides parliament and other users of the Health cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

The impacts of the COVID-19 pandemic on the cluster were significant and included changes to the operations of the health entities and increased revenue, expenditure, assets and liabilities.

As a part of this year's audits of health entities, we have considered:

  • financial implications of the COVID-19 emergency at both health entity and cluster levels
  • changes to agencies' operating models
  • agencies' access to technology and the maturity of systems and controls to prevent unauthorised and fraudulent access to data.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

The response to the COVID-19 pandemic primarily impacted the financial reporting of NSW Health through:

  • additional revenue from the State government in the form of grants and stimulus payments
  • additional revenue from the Commonwealth government under the National Partnership Agreement for COVID-19 to cover part of the cost of responding to the COVID-19 pandemic
  • increased expenses, largely due to increased payments to private health operators to maintain their viability during the COVID-19 pandemic and later to assist with public patient elective surgery waitlists and increased cleaning costs
  • increased purchases of personal protective equipment.

Chapter one outlines the impacts of NSW Health’s response to the COVID-19 pandemic. This chapter outlines our other audit observations related to the financial reporting of agencies in the Health cluster for 2020.

Section highlights

  • Unqualified audit opinions were issued for all health entities’ financial statements, although more misstatements were identified than last year.
  • NSW Health recorded an operating surplus of $3.1 billion, an increase of $2.0 billion from 2018–19. This is largely due to additional capital grants for new facilities, upgrades and redevelopments and additional Commonwealth and State funding for the purchase of personal protective equipment.
  • NSW Health’s expenses increased by 5.5 per cent in 2019–20 (7.0 per cent in 2018–19) despite the impact of the COVID-19 pandemic. The primary causes for the growth in expenses are increases in:
    • employee related expenses due to higher employee numbers, increased overtime and a 2.5 per cent award increase
    • payments to private health operators to maintain their viability during the COVID-19 pandemic and later to assist with public patient elective surgery waitlists
    • payments to private health operators due to the first full year of operation of the Northern Beaches hospital.
  • The Ambulance Service of NSW (NSW Ambulance) continued to report higher overtime payments than other health entities. However, despite the response to the 2019–20 bushfire season, their overtime payments were lower than last year. NSW Ambulance paid $79.7 million in overtime payments in 2019–20 ($83.1 million in 2018–19).
  • A qualified audit opinion was issued for the Ministry of Health’s Annual Prudential Compliance Statement for aged care facilities operated by NSW Health. There were 18 instances of material non-compliance with the Fees and Payments Principles 2014 (No. 2) (the Principles) in 2019–20 (30 in 2018–19)

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

The primary impact of the COVID-19 pandemic on the effectiveness of the internal controls of NSW Health and health entities relates to the effectiveness of controls implemented by HealthShare relating to the stocktake of personal protective equipment inventories. Inventory managed by HealthShare increased by 2,746 per cent during 2019–20. HealthShare’s inventory controls did not maintain pace with the sudden, significant increase.

The impacts of NSW Health’s response to the COVID-19 pandemic are outlined in chapter one. This chapter outlines other observations and insights from our financial statement audits of agencies in the Health cluster.

Section highlights

  • The number of internal control deficiencies has increased since 2018–19. More than a third of control deficiencies are repeat issues.
  • Control deficiencies that relate to managing employees’ leave and employee’s time recording continue to be difficult for entities to resolve, particularly during the ongoing response to the COVID-19 pandemic.
  • Several key agreements were undocumented. These included agreements between the Ministry and the health entities, between health entities, and between the Ministry and entities in other clusters and jurisdictions. These related to:
    • a loan arrangement between the Ministry and HealthShare for $319 million.
    • Northern Sydney Local Health District's use of land and buildings owned by the Graythwaite Charitable Trust
    • agreements for the treatment of New South Wales residents while they are interstate, and interstate residents receiving treatment while they are in New South Wales from Queensland, Victoria, South Australia and the ACT for both 2019–20 and 2018–19.
  • NSW Health reported that they completed nine major capital projects during 2019–20. As at 30 June 2020 there were 44 ongoing major capital health projects in NSW. The revised capital budget for these projects in total was $2.0 billion more than the original budget of $10.3 billion. NSW Health reported the budget revisions are largely the result of combining project stages.

Appendix one – List of 2020 recommendations 

Appendix two – Status of 2019 recommendations 

Appendix three – Financial data

Appendix four – Analysis of financial indicators 

Appendix five – Analysis of performance against budget

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Auditor-General’s Report to Parliament

Health 2020

11 December 2020

This corrigendum has been prepared to amend the following text within the Auditor-General’s Report to Parliament on Health 2020, dated 10 December 2020.

NSW Health emergency department treatment times

On page five the original text was as follows:

NSW Health also measures the percentage of patients whose clinical care in emergency departments is completed within four hours. The measure is used as an indicator of accessibility to public hospital services.

NSW Health aims to complete clinical care in the emergency department for 81 per cent of patients within four hours. In 2019–20 NSW Health reports it completed clinical care within four hours for 72.1 per cent of patients (a 7.3 per cent decrease from 2018–19).

At Western Sydney Local Health District, 59 per cent of patients were treated within the targeted timeframe. NSW Health attribute this to the profile of patients presenting in emergency departments and additional time taken processing COVID-19 patients to ensure staff safety.

The original text has now been changed to:

NSW Health also measures the percentage of patients with total time in the emergency department of four hours or less for each local health district. The measure is used as an indicator of accessibility to public hospital services.

Local Health Districts Target % (2019–20) Actual % (2019–20)
Central Coast 77.0 59.9
Far West 90.2 86.6
Hunter New England 81.0 72.5
Illawarra Shoalhaven 79.0 60.2
Mid North Coast 82.0 76.7
Murrumbidgee 85.3 81.9
Nepean Blue Mountains 79.0 65.5
Northern NSW 81.0 78.2
Northern Sydney 79.0 73.9
South Eastern Sydney 78.0 70.3
South Western Sydney 78.0 61.2
Southern NSW 85.0 83.0
Sydney 76.0 70.9
Sydney Children’s Hospitals Network 80.0 72.1
Western NSW 85.9 81.0
Western Sydney 78.0 59.0
St Vincent's Health Network* 75.0 65.4
* St Vincent’s Health Network Sydney (SVHNS) comprises of St Vincent’s Hospital Sydney Limited as the affiliated health organisation in respect of four recognised establishments under the Health Services Act 1997 (NSW) (Health Services Act). Under the Health Services Act, St Vincent’s Hospital Sydney Limited, is treated as a Network for the purposes of the National Health Reform Agreement in respect of the three recognised establishments: St Vincent’s Hospital, Darlinghurst; Sacred Heart Health Service, Darlinghurst; St Joseph’s Hospital, Auburn; and St Vincent's Correctional Health, Parklea.
Source: NSW Health (unaudited)

The above changes will be reflected in the version of the report published on the Audit Office website and should be considered the true and accurate version.

Published

Actions for Transport 2020

Transport 2020

Transport
Asset valuation
Cyber security
Financial reporting
Information technology
Infrastructure
Project management

1. Financial Reporting

Audit opinion Unmodified audit opinions issued for the financial statements of all Transport cluster entities.
Quality and timeliness of financial reporting All cluster agencies met the statutory deadlines for completing the early close and submitting the financial statements.

Transport cluster agencies continued to experience some challenges with accounting for land and infrastructure assets. The former Roads and Maritime Services and Sydney Metro recorded prior period corrections to property, plant and equipment balances.
Impact of COVID-19 on passenger revenue and patronage Total patronage and revenue for public transport decreased by approximately 18 per cent in 2019–20 due to COVID-19.

The Transport cluster received additional funding from NSW Treasury during the year to support the reduced revenue and additional costs incurred such as cleaning on all modes of public transport and additional staff to manage physical distancing.
Completion of the CBD and South East Light Rail The CBD and South East Light Rail project was completed and commenced operations in this financial year. At 30 June 2020, the total cost of the project related to the CBD and South East Light Rail was $3.3 billion. Of this total cost, $2.6 billion was recorded as assets, whilst $700 million was expensed.

2. Audit Observations

Internal control While internal controls issues raised in management letters in the Transport cluster have decreased compared to the prior year, control weaknesses continue to exist in access security for financial systems. We identified 56 management letter findings across the cluster and 43 per cent of all issues were repeat issues. The majority of the repeat issues relate to information technology controls around user access management.

There were three high risk issues identified - two related to financial reporting of assets and one for implementation of TAHE (see below).
Agency responses to emergency events Transport for NSW established the COVID-19 Taskforce in March 2020 to take responsibility for the overall response of planning and coordination for the Transport cluster. It also implemented the COVIDSafe Transport Plan which incorporates guidance on physical distancing, increasing services to support social distancing and cleaning.
RailCorp transition to TAHE On 1 July 2020, RailCorp was renamed Transport Asset Holding Entity of New South Wales (TAHE) and converted to a for-profit statutory State-Owned Corporation. TAHE is a commercial for-profit Public Trading Entity with the intent to provide a commercial return to its shareholders.

A plan was established by NSW Treasury to transition RailCorp to TAHE which covered the period 1 July 2015 to 1 July 2019. A large portion of the planned arrangements were not implemented by 1 July 2020. As at the time of this report, the TAHE operating model, Statement of Corporate Intent (SCI) and other key plans and commercial agreements are not finalised. The State Owned Corporations Act 1989 generally requires finalisation of an SCI three months after the commencement of each financial year. However, under the Transport Administration Act 1988, TAHE received an extension from the voting shareholders, the Treasurer and Minister for Finance and Small Business, to submit its first SCI by 31 December 2020. In accordance with the original plan, interim commercial access arrangements were supposed to be in place with RailCorp prior to commencement of TAHE.

Under the transitional arrangements, TAHE is continuing to operate in accordance with the asset and safety management plans of RailCorp. The final operating model is expected to include considerations of safety, operational, financial and fiscal risks. This should include a consideration of the potential conflicting objectives of a commercial return, and maintenance and safety measures.

This matter has been included as a high risk finding in our management letter due to the significance of the financial reporting impacts and business risks for TAHE.

Recommendation: TAHE management should:
  • establish an operating model in line with the original intent of a commercial return
  • finalise commercial agreements with the public rail operators
  • confirm forecast financial information to assess valuation of TAHE infrastructure
  • finalise asset and safety management plans.

Resolution of the above matters are critical as they may significantly impact the financial reporting arrangements for TAHE for 2020–21, in particular, accounting policies adopted as well as measurement principles of its significant infrastructure asset base.

Completeness and accuracy of contracts registers Across the Transport cluster, contracts and agreements are maintained by the transport agencies using disparate registers.

Recommendation (repeat): Transport agencies should continue to implement a process to centrally capture all contracts and agreements entered. This will ensure:
  • agencies are fully aware of contractual and other obligations
  • appropriate assessment of financial reporting implications
  • ongoing assessments of accounting standards, in particular AASB 16 ‘Leases’, AASB 15 'Revenue from Contract with Customers', AASB 1058 'Income of Not-for-Profit Entities' and new accounting standard AASB 1059 'Service Concession Arrangements: Grantors' are accurate and complete.

 

This report provides parliament and other users of the Transport cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations
  • the impact of emergencies and the pandemic.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Transport cluster for 2020, including any financial implications from the recent emergency events.

Section highlights

  • Total patronage and revenue for public transport decreased by approximately 18 per cent in 2019–20 due to COVID-19.
  • Unqualified audit opinions were issued on all Transport agencies' financial statements.
  • Transport cluster agencies continued to experience challenges with accounting of land and infrastructure assets.

 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our:

  • observations and insights from our financial statement audits of agencies in the Transport cluster
  • assessment of how well cluster agencies adapted their systems, policies and procedures, and governance arrangements in response to recent emergencies.

Section highlights

  • While there was a decrease in findings on internal controls across the Transport cluster, 43 per cent of all issues were repeat issues. Many repeat issues related to information technology controls around user access management.
  • RailCorp transitioned to TAHE on 1 July 2020. TAHE's operating model and commercial arrangements with public rail operators has not been finalised despite government original plans to be operating from 1 July 2019. TAHE management should finalise its operating model and commercial agreements with public rail operators as they may significantly impact the financial reporting arrangements for TAHE for 2020–21.
  • Completeness and accuracy of contracts registers remains an ongoing issue for the Transport cluster.

Appendix one – List of 2020 recommendations

Appendix two – Status of 2019, 2018 and 2017 recommendations

Appendix three – Management letter findings

Appendix four – Financial data

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for State Finances 2020

State Finances 2020

Education
Finance
Community Services
Health
Justice
Industry
Planning
Environment
Premier and Cabinet
Transport
Treasury
Whole of Government
Financial reporting

The Auditor-General for New South Wales, Margaret Crawford, released her report today on State Finances for the year ended 30 June 2020.

‘I am pleased to once again report that I issued an unmodified audit opinion on the State’s consolidated financial statements,’ the Auditor-General said.

The report acknowledges this has been a challenging year, with New South Wales impacted by natural disasters and the COVID-19 pandemic.

The State’s Budget Result, reported in the financial statements, was a deficit of $6.9 billion. This is different to the 2019-20 budget forecast surplus of $1.0 billion and is an outcome of the government’s significant response to bushfires and COVID-19.

The report summarises a number of audit and accounting matters arising from the audit of the Total State Sector Accounts, a sector that comprises 291 entities controlled by the NSW Government with total assets of $495 billion and total liabilities of $256 billion.

Read full report (PDF)

Our audit opinion on the State’s 2019–20 financial statements was unmodified

An unmodified audit opinion was issued on the State’s 2019–20 consolidated financial statements.

The State extended signing its financial statements by six weeks.

Natural disasters, the COVID-19 pandemic and other factors impacted the State’s 2019–20 reporting timetable. The State extended signing its financial statements by six weeks, compared with 2018–19.

All agencies were also given a two-week extension to prepare their financial statements compared with 2018–19. Further extensions beyond two weeks were subsequently approved for the following 11 agencies (7 in 2018–19) to submit completed financial statements for audit:

  • Department of Communities and Justice
  • Department of Customer Service
  • Department of Planning, Industry and Environment
  • Department of Regional NSW
  • Department of Transport
  • Environment Protection Authority
  • Infrastructure NSW
  • Lord Howe Island Board
  • NSW Crown Holiday Parks Land Manager
  • Service NSW
  • Water Administration Ministerial Corporation.

The extensions reflected that the COVID-19 pandemic impacted agencies’ work environments during the first six months of 2020. This was at a time when many were still implementing machinery of government changes and preparing to implement three significant new accounting standards:

  • AASB 15 Revenue from Contracts with Customers (issued December 2014, effective 1 July 2019)
  • AASB 16 Leases (issued February 2016, effective 1 July 2019)
  • AASB 1058 Income of Not-for-profit entities (issued December 2016, effective 1 July 2019).

These new accounting standards were issued some years before they became effective, to allow reporting entities sufficient time to prepare for implementation. Notwithstanding this, some agencies had not fully implemented the new accounting standards in time for early close procedures, and the unforeseen impact of COVID-19 further complicated the year-end financial reporting processes for the State and its agencies.

The graph below shows the number of reported errors exceeding $20 million over the past five years in agencies’ financial statements presented for audit.

In 2019–20, agency financial statements presented for audit contained 19 errors exceeding $20 million (six in 2018–19). The total value of these errors increased to $1.4 billion ($927 million in 2018–19).

The errors resulted from:

  • incorrectly applying Australian Accounting Standards and Treasury Policies
  • incorrect judgements and assumptions when valuing noncurrent physical assets and liabilities
  • incorrectly interpreting the accounting treatment for unspent stimulus funding.

Errors in agency financial statements exceeding $20m (2016–2020)

$4.1 billion in stimulus funding was allocated in 2019–20

The government implemented an economic stimulus package primarily to mitigate the impacts of the COVID-19 pandemic on New South Wales.

The COVID-19 pandemic and bushfires had a significant impact on the State’s finances, reducing its revenue and increasing its expenses especially in sectors directly responsible for responding to the COVID-19 pandemic, such as Health.

The government announced a $4.1 billion health and economic stimulus package in 2019–20. This primarily included:

  • $2.2 billion in health measures including purchases of essential medical equipment and increasing clinical health capacity (like intensive care spaces)
  • $1.0 billion in small business and land tax relief
  • $355 million in extra cleaning services and quarantine costs.

Cluster agencies had spent $3.0 billion (just under 75 per cent) of the COVID-19 stimulus package by 30 June 2020.

The Health cluster incurred most of this expenditure.

Total spend relating to bushfires was $1.3 billion in 2019–20.

The graph below shows the total allocation and spend by cluster to 30 June 2020.

Economic stimulus allocation and spend by cluster to 30 June 2020

Deficit of $6.9 billion compared with a budgeted surplus of $1.0 billion

An outcome of the government’s overall activity and policies is its net operating balance (Budget Result). This is the difference between the cost of general government service delivery and the revenue earned to fund these sectors.

The General Government Sector, which comprises 199 entities, generally provides goods and services funded centrally by the State.

The Non-General Government Sector, which comprises 92 government businesses, generally provides goods and services, such as water, electricity and financial services that consumers pay for directly.

The Budget Result for the 2019–20 financial year was a deficit of $6.9 billion. The original budget forecast, set before the COVID-19 pandemic and bushfires, was a $1.0 billion surplus. The main driver of the change in result was:

  • $1.3 billion of higher employee costs, mainly due to:
    • increased workers compensation claims
    • additional personnel required (mainly in the Health sector) to respond to the COVID-19 pandemic
  • $2.3 billion of higher operating expenses, mainly due to:
    • $828 million from first time recognition of a child abuse claim liability
    • $507 million from additional insurance claims from the NSW bushfires
    • $343 million from COVID-19 claims by agencies for loss of revenue.
  • $1.8 billion in higher grants and subsidy expenses, mainly due to:
    • small business grants
    • COVID-19 quarantine compliance measures
    • costs incurred in response to the 2019–20 bushfires, drought and disaster relief payments
    • third party-controlled assets that were subsequently transferred to councils and utility providers, mainly arising from construction of the CBD and South East Light Rail.

The deficit was further driven by:

  • $1.9 billion less taxation revenue, mainly resulting from:
    • $1.3 billion less in payroll tax due to relief measures introduced by the government as part of its COVID-19 economic stimulus
    • $424 million less in gambling and betting taxes, due to venue closures required by COVID-19 public health orders
  • $523 million less in dividends and income tax revenue from the Non-General Government Sector, due to lower dividends received from NSW Treasury Corporation and from the State’s other commercial government businesses
  • lower fines, regulatory fees and other revenue, due to a $305 million decrease in mining royalties, largely driven by lower coal prices.

Main drivers of the 2019–20 actual vs. budget variance

Revenues increased $209 million to $86.3 billion

In 2019–20, the State’s total revenues increased by $209 million to $86.3 billion, 0.2 per cent higher than in 2018–19. COVID-19 impacted taxation revenue, which fell by $1.1 billion and revenue from the sale of goods and services, which fell by $1.1 billion. These falls were offset by a $2.5 billion (7.7 per cent) increase in grants and subsidies from the Australian Government, mainly in the form of additional stimulus funding.

Taxation revenue fell 3.5 per cent

Taxation revenue fell by $1.1 billion, mainly due to a:

  • $861 million fall in payroll tax as a result of COVID-19 relief (reduced payroll tax payments for eligible small businesses)
  • $430 million fall in stamp duty collections, driven by lower than expected growth in the property market
  • $427 million decline in gambling and betting taxes, mainly due to venue closures driven by COVID-19 public health orders.

Stamp duties of $8.8 billion were the largest source of taxation revenue, $473 million higher than payroll tax, the second-largest source of taxation revenue.

Australian Government grants and subsidies

The State received $34.2 billion in grants and subsides which are mainly from the Australian Government, $2.4 billion more than in 2018–19.

The increase was driven by a $1.1 billion increase in Commonwealth Specific Purpose Payments to support the Health cluster respond to the COVID-19 pandemic. Commonwealth National Partnership Payments increased by a similar amount to provide the State with Natural Disaster relief.

Sales of goods and services

In 2019–20, sales of goods and services fell $1.1 billion. This was due to the COVID-19 pandemic reducing:

  • patronage and related transport passenger revenue
  • health billing activities with elective surgery being put on hold
Fines, regulatory fees and other revenues

Fines, regulatory fees and other revenues fell $505 million. This was mainly due to a $409 million decrease in mining royalties attributed to a drop in thermal coal prices during 2019–20.

Other dividends and distributions

Other dividends and distributions rose by $616 million due to higher distributions received from the State’s investments. This was due to an additional $1.3 billion held in the State’s investment portfolio compared with last year.

Expenses increased $8.2 billion to $96.0 billion

The State’s expenses increased 9.3 per cent compared with 2018–19. Most of the increase was due to higher employee expenses, other operating costs and grants and subsidies.

Employee expenses, including superannuation, increased 5.7 per cent to $42.6 billion.

Salaries and wages increased to $42.6 billion from $40.3 billion in 2018–19. This was mainly due to increases in staff numbers and a 2.5 per cent increase in pay rates across the sector. Salaries and wages for the Education and Health sectors increased by $659 million and $732 million in each sector respectively.

The Health sector employed an additional 2,763 full time staff in 2019–20. It also incurred more overtime in response to COVID-19. Education increased staff numbers by 4,866 full time equivalents and paid a one off 11 per cent pay rise to school administration staff in 2019–20. Historically, the government wages policy aims to limit growth in employee remuneration and other employee related costs to no more than 2.5 per cent per annum.

Operating expenses increased 8.7 per cent to $27.0 billion.

Operating expenses increased to $27.0 billion in 2019–20 ($24.8 billion in 2018–19) due to higher operating activities in Health. The higher level of activities and related costs is attributed to a full year of operations at the Northern Beaches Hospital (opened November 2018), and responding to COVID-19. The response to COVID-19 involved the State providing viability payments to private hospitals, higher visiting medical officer costs due to additional overtime hours and spending more on equipment to set up COVID-19 testing clinics.

Insurance claims increased by $2.0 billion. This was mainly due to NSW Self Insurance Corporation (SiCorp) recognising a liability for child abuse claims incurred but not reported for the first time, and claims for the 2019–20 bushfires, floods and COVID-19.

Health costs remain the State’s highest expense.

Total expenses of the State were $96 billion ($87.8 billion in 2018–19). Traditionally, the following clusters have the highest expenses as a percentage of total government expenses:

  • Health – 24.3 per cent (25.8 per cent in 2018–19)
  • Education – 17.6 per cent (19.3 per cent in 2018–19)
  • Transport - 12.8 per cent (12.6 per cent in 2018–19).

General public service expenses as a percentage of total State expenses is higher due to a $2.0 billion increase in SiCorp’s accrued claim expenses.

Other expenses increased due to additional grant funding by the State for drought relief and COVID-19 stimulus spend.

Health expenses increased by $632 million compared with 2018–19 but fell as a proportion of total State expenses.

Education expenses remained stable compared with last year due to savings in student transportation costs primarily driven by COVID-19. This led to a decrease in the proportion of the State’s costs relating to education activities.

Grants and subsidies increased $2.5 billion to $14.1 billion.

The increase in grants and subsidies was due to payments the State made to support businesses and local communities in the face of COVID-19 and bushfires. In addition, the State transferred CBD and South East Light Rail assets to councils and utility providers during 2019–20 as it no longer controlled these.

Depreciation expense increased $1.0 billion to $9.2 billion.

Depreciation increased to $9.2 billion from $8.0 billion in 2018–19. At 1 July 2019, the State implemented the new leases standard recognising a right of use (ROU) asset and related lease liability in its financial statements. The value of ROU assets are amortised over the term of the lease. This contributed to $980 million of the increase in 2019–20 depreciation expense. Last year, these costs were previously reported within other operating expenses.

Assets grew by $28.0 billion to $495 billion

The State’s assets primarily include physical assets such as land, buildings and infrastructure, and financial assets such as cash, and other financial instruments and equity investments. The value of total assets increased by $28.0 billion to $495 billion. This was a six per cent increase compared with 2018–19, mostly due to changes in asset carrying values.

Of the State’s $28.0 billion increase in asset values, $9.3 billion was due to a new accounting standard requirement for operating leases to be valued and recorded on balance sheet for the first time.

AASB 16 Leases requires entities recognise values for right-ofuse assets (ROU) for the first time. An ROU asset is a lessee’s right to use an asset, the value of which is amortised over the term of the lease. This standard came into effect from 1 July 2019.

Valuing the State’s physical assets

State’s physical assets valued at $365 billion.

The value of the State’s physical assets increased by $14.1 billion to $365 billion in 2019–20. The assets include land and buildings ($168 billion), infrastructure ($180 billion) and plant and equipment ($16.7 billion). A prior period error relating to the valuation of RMS infrastructure assets reduced the reported values by $1.0 billion from $352 billion to $351 billion at 30 June 2019.

The movement in physical asset values between years includes additions, disposals, depreciation and valuation adjustments. Other movements include reclassification of physical assets leased under finance leases to right of use assets upon adoption of AASB 16 Leases on 1 July 2019.

Movements in physical asset values

Liabilities increased $38.4 billion to $256 billion

The State borrowed additional funds in response to natural disasters and COVID-19.

The State’s borrowings rose by $33.9 billion to $113.8 billion at 30 June 2020. This accounted for most of the increase in the State’s total liabilities.

The value of TCorp bonds on issue increased by $25.2 billion to $97.0 billion to largely fund capital expenditure and costs associated with the bushfires, drought and COVID-19.

TCorp bonds are actively traded in financial markets and are guaranteed by the NSW Government.

Over 2019–20, TCorp continued to take advantage of lower interest rates, buying back short-term bonds and replacing them with longer dated debt. This lengthens the portfolio matching liabilities with the funding requirements for infrastructure assets.

With effect from 1 July 2019, AASB 16 Leases required the State to recognise liabilities for operating leases for the first time. This increased total lease liabilities from $5.3 billion at 30 June 2019 to $11.8 billion at 30 June 2020.

More than a third of the State’s liabilities relate to its employees. They include unfunded superannuation and employee benefits, such as long service and recreation leave.

Valuing these obligations involves complex estimation techniques and significant judgements. Small changes in assumptions and other variables, such as a lower discount rate, can materially impact the valuation of liability balances in the financial statements.

The State’s unfunded superannuation liability rose $300 million from $70.7 billion to $71.0 billion at 30 June 2020. This was mainly due to a lower discount rate of 0.87 per cent (1.32 per cent in 2018–19). The State’s unfunded superannuation liability represents the value of its obligations to past and present employees less the value of assets set aside to fund those obligations.

 

The State maintained its AAA credit rating

The object of the Fiscal Responsibility Act 2012 is to maintain the State’s AAA credit rating.

The government manages New South Wales’ finances in accordance with the Fiscal Responsibility Act 2012 (the Act).

The Act establishes the framework for fiscal responsibility and the strategy to maintain the State’s AAA credit rating and service delivery to the people of New South Wales.

The legislation sets out targets and principles for financial management to achieve this.

This year, the State’s credit rating from Standard & Poor’s changed from AAA/Stable to AAA/Negative. Moody’s Investors Service credit rating of Aaa/Stable did not change from the previous year.

The fiscal target for achieving this objective is that General Government annual expenditure growth should be lower than long term average revenue growth.

The State did not achieve its fiscal target of maintaining annual expenditure growth below the long-term revenue growth rate target of 5.6 per cent.

In 2019–20, General Government expenditure grew by 9.7 per cent (5.5 per cent in 2018–19).

Expenditure items that contributed most to the growth rate include:

  • recurrent grants and subsidies (20.4 per cent)
  • other operating expenses (9.5 per cent)
  • employee costs (including superannuation) (5.6 per cent)

Recurrent grant and subsidy expenses increased by $2.8 billion in 2019–20 mainly due to the COVID-19 and natural disaster payments. Other operating expenses increased mainly due to a $2.0 billion increase in SiCorp insurance claims. This included the $828 million provision for child abuse claims incurred but not reported. The bushfires and COVID-19 pandemic also increased the number and cost of claims in 2019–20.

Superannuation funding position since inception of the Act - AASB 1056 Valuation

Published

Actions for Health capital works

Health capital works

Health
Compliance
Infrastructure
Procurement
Project management

This report examines whether NSW Health effectively planned and delivered major capital works to meet the demand for health services in New South Wales.

The report found that NSW Health has substantially expanded health infrastructure across New South Wales since 2015. However, the program was driven by Local Health District priorities without assessment of the State’s broader and future‑focussed health requirements.

The report found that unclear decision making roles and responsibilities between Health Infrastructure and the Ministry of Health limited the ability of NSW Health to effectively test and analyse investment options.

Project delays and budget overruns on some major projects indicate that Health Infrastructure's project governance, risk assessment and management systems could be improved.

The Auditor‑General recommends that NSW Health ensure its capital projects offer the greatest value to New South Wales by establishing effective policy guidance and enhancing project governance and management systems.

Read full report (PDF)

Since 2011–12, NSW Health has aimed to improve its facilities and build 'future focused' infrastructure. The NSW Government’s 2015–16 election commitments established a four-year $5.0 billion capital program for NSW Health to build and upgrade more than 60 hospitals and health services. The 2019–20 State Budget committed a further $10.1 billion over four years for another 29 projects. This is the largest investment to date on health capital works in New South Wales.

Recent reviews of infrastructure have recognised that population and demographic growth will require a change in the delivery and composition of health infrastructure, including considering greater use of non-traditional, non-capital health service options and assets.

To ensure that expenditure on capital works represents the best value for money, NSW Health's business cases need to be robust and supported by evidence that demonstrates they are worthy investments. The NSW Process of Facility Planning has been the main framework guiding the detailed planning and development of NSW Health's capital works proposals. This framework was developed by the then NSW Department of Health in 2010. Its aim is to ensure investment proposals are supported by rigorous planning processes that address health service needs and provide value for money.

Infrastructure projects of the complexity and scale being delivered by NSW Health carry inherent risks. For example, unplanned cost escalations can potentially impact on the State’s finances. Unforeseen delays can also reduce the intended benefits. The growth in the State’s health capital spend and project profile, means its exposure to such risks has increased over time.

The objective of this audit was to assess the effectiveness of planning and delivery of major capital works to meet demand for health services in New South Wales. To address this objective, the audit examined whether:

  • the Ministry of Health has effective procedures for planning and prioritising investments in major health capital works
  • Health Infrastructure develops robust business cases for initiated major capital works that reliably inform government decision making
  • Health Infrastructure has effective project governance and management systems that support delivering projects on-time, within budget and achievement of intended benefits.

The audit focused on the Ministry of Health and Health Infrastructure – being the lead agencies within NSW Health responsible for prioritising, planning and delivering major health capital works across the State. The audit examined 13 business cases for eight discrete projects over a ten-year period.

Conclusion

NSW Health has substantially expanded health infrastructure across New South Wales since 2015. However, its planning and prioritisation processes were not assessed against a long-term statewide health infrastructure plan and lacked rigorous assessment against non-capital options creating a risk that they do not maximise value for New South Wales.

The scale of NSW Health's capital investment is significant and has grown substantially in recent years. The NSW Government’s election commitments in 2015–16 and 2019–20 collectively set out a $15.0 billion capital program to build and upgrade 89 hospitals and health services. NSW Health developed this infrastructure program in the absence of a statewide health infrastructure strategy and investment framework to focus its planning and decisions on the types of capital investments required to meet the long-term needs of the NSW health system.

Consequently, locally focused priorities of the State’s 17 Local Health Districts have been the primary drivers of NSW Health’s capital investments since 2015–16. Local Health District investment proposals for hospitals were developed without consideration of alternative health options such as community health service models, technology-driven eHealth care, or private sector options. Without rigorous assessment against a range of potential health service options, there is a risk that selected projects do not maximise value for New South Wales.

In recognition of the need for a statewide approach to infrastructure planning, the Ministry of Health recently developed a 20-year Health Infrastructure Strategy and prioritisation framework in 2019. The strategy was approved by the NSW Government in April 2020.

NSW Health's ability to effectively test and analyse its capital investment options has been compromised by unclear decision-making roles and responsibilities between its Health Infrastructure and the Ministry of Health agencies.

While both Health Infrastructure and the Ministry of Health have responsibilities for the assessment of business cases for proposed infrastructure projects, confusion about the roles of each agency at key steps compromised the efficacy of the process. Health Infrastructure and the Ministry of Health have differing views about which agency is responsible for testing business case inputs and conducting comprehensive options appraisals.

As a result of this confusion, Health Infrastructure and the Ministry of Health did not rigorously test Local Health District capital investment proposals against defined statewide health infrastructure investment priorities. The NSW Process of Facility Planning does not clarify the responsibilities of all parties in validating and prioritising Local Health District's Clinical Service Plans and progressing them to business cases.

NSW Health's infrastructure priorities are not sufficiently supported by transparent documentation of selection methodology and the rationale for decisions. Consequently, there is a risk that recommended options, whilst having some economic and health service merit, do not represent the greatest value.

Substantial delays and budget overruns on some major projects indicate that Health Infrastructure's project governance, risk assessment and management systems could be improved.

Health Infrastructure did not fully comply with NSW Government guidelines for developing business cases and making economic appraisals for proposed capital investments. These weaknesses, along with delays and budget overruns on some projects, demonstrate a need for Health Infrastructure to strengthen its project governance, management and quality control systems.

 

Over the period of review, NSW Government policies for business case development and submission have emphasised that effective governance arrangements are critical to a proposal's successful implementation.

NSW Health's Process of Facility Planning similarly highlights the importance of effective governance and project management for achieving good outcomes. It prescribes a general governance structure managed by Health Infrastructure that can be tailored to the planning and delivery of health infrastructure projects greater than $10.0 million.

Project challenges indicate opportunities for strengthening governance and project management

The three major hospital redevelopments examined in metropolitan, regional and rural areas had a combined Estimated Total Cost of more than $1.2 billion and comprised eight discrete projects and 13 separate business cases.

Almost all these projects experienced delivery challenges which impacted achievement of their original objectives and intended benefits. This is expected in complex and large-scale health infrastructure programs. However, in some projects the impacts were significant and resulted in substantial delays, unforeseen costs, and diversion of resources from other priority areas.

Our review of the selected case studies highlighted opportunities for enhancing governance and project management. Specifically, it indicates a need for improving transparency in the management of contingencies, risk management and assessments particularly relating to adverse site conditions and the selection of contractors. There is also a need to strengthen forward planning for options to address unfunded priorities within business cases that risk complicating the delivery of future project stages resulting in unforeseen costs and potentially avoidable budget overruns.

Need for increased transparency and accountability in the management of contingency funds

In February 2017, the Ministry's Capital Strategy Group approved the use of surplus funds of $13.76 million from Stage 1 of the Hornsby Ku-ring-gai Hospital Redevelopment for new works deemed needed to support Stage 2. Following this decision, Health Infrastructure finalised and submitted a business case addendum for Stage 1 to the Ministry in March 2017, addressing the new works comprising a two-storey building for medical imaging and paediatric floors. The business case addendum also addressed options to fit out and procure major medical imaging equipment. The Ministry approved the Stage 1 business case in July 2017, noting the Ministry's Capital Strategy Group had already approved the use of remaining Stage 1 funds to deliver the new works.

Stage 1 was completed in 2015, almost two years before the Stage 1 business case addendum was prepared in February 2017.

The Ministry's decision to approve the new works using $13.76 million of surplus Stage 1 funds did not comply with the NSW Treasury Circular TC 12/20. This policy establishes the Treasurer's approval must be sought and received before a new capital project with an Estimated Total Cost of $5.0 million or more can be approved by NSW Health. The Ministry therefore exceeded its delegated authority in making this decision, as it was not evident it had sought and received the Treasurer's approval prior to doing so.

Consequently, the surplus Stage 1 funds should not have been used by the Ministry to deliver new works in the circumstances. Instead, they should have been released from the Stage 1 project in accordance with established NSW Health procedures, and the Stage 1 Estimated Total Cost revised down accordingly. This did not occur, and NSW Health ultimately directed $11.0 million in surplus Stage 1 funds to the new works.

These circumstances indicate a need to strengthen transparency and accountability within NSW Health for the approval of new projects, and how contingency funds are used in the management of major health capital works. They also demonstrate the impact of weaknesses with options appraisal as the initial Stage 1 business case did not consider alternative options for addressing the initially unfunded works later covered by the Stage 1 business case addendum and ultimately funded from the Stage 1 contingency provision.

Weaknesses in service delivery planning resulted in unaccounted-for costs

In addition to proposing the above-noted new works, the 2017 Stage 1 Business Case Addendum for the Hornsby-Ku-ring-gai development sought to retrospectively address the estimated funding gap of around $14.0 million for the internal fit out, supply of major medical imaging equipment, and cost to operate the medical imaging service at Hornsby Ku-ring-gai Hospital also not addressed in the originally Stage 1 business case.

The Stage 1 business case addendum considered various procurement options to purchase and run the medical imaging services ranging from State operation purchase options to private operation purchase options.

It recommended outsourcing the operation and provision of equipment to the private sector based on estimated savings to the public sector initially of around $650,000 per annum reducing over time to $270,000. The Ministry endorsed this option in June 2017, but it did not ultimately proceed.

A July 2018 report to the Executive Steering Committee on the project shows NSW Health later decided to deliver operation of the medical imaging unit 'traditionally' with an updated estimate of the cost at approximately $16.4 million. The report also shows the Ministry supported the costs now being met by the Northern Sydney Local Health District.

This means the funding gap previously identified in the Stage 1 business case addendum for fitting out the medical imaging building and supply of major medical equipment would need to be met fully by the State, representing a $16.4 million cost overrun for the project.

Examined reports to the Executive Steering Committee show this was largely funded by the Northern Sydney Local Health District via the disposal of land realising approximately $15.0 million in proceeds.

This initially unforeseen cost, along with the additional $11.0 million for the new works approved under the Stage 1 business case addendum, were ultimately merged with the Stage 2 project initially approved in 2017–18 with an Estimated Total Cost of $200 million.

The extent of budget variation on the Hornsby Kur-ring-gai development has not been transparent

The 2019–20 State Budget provided an additional $65.0 million for a further Stage 2A to deliver additional built capacity to support outpatient services, enhanced allied health services, re-housed community health services and the delivery of prioritised clinical services unfunded as part of Stage 2. The funds were approved based on an Investment Decision Template (IDT) that examined two options in addition to the base case representing scoping alternatives to the preferred master planned capital solution.

However, we found the IDT showed around 23 per cent of the $65.0 million sought (i.e. $15.0 million) was to be allocated to fund the deficit in Stage 2, which had arisen as a result of project delays due to adverse site conditions. This was not discussed in the IDT.

The February 2020 report to the Executive Steering Committee shows a combined Stage 2 and 2A final forecast cost of $292.6 million against a potential budget of $290.7 million representing an overall deficit for the project of around 0.6 per cent.

However, this favourable final budget position does not transparently show the funding challenges experienced over the project's implementation to-date. The three major budget issues include:

  • inappropriate use of around $11.0 million in Stage 1 contingency for originally unfunded works contrary to Treasury policy
  • the additional $16.4 million cost unforeseen in the Stage 1 business case for delivering medical imaging services mostly funded through the sale of land
  • an additional $15.0 million from Stage 2A to cover the budget overrun in Stage 2 due to adverse site conditions.

The cumulative impact of these events is that Stages 1 and 2 of the Hornsby project cost approximately $42.4 million than it should have in the circumstances around 14 per cent more than what the revised combined Estimated Total Cost for both stages should have been after releasing the $11.0 million in surplus Stage 1 funds, with Stage 2 delayed by around 14 months.

Opportunity for strengthening risk management for adverse site conditions

Major construction projects often experience adverse site conditions which can be difficult to fully detect in advance. However, we found this was a common occurrence in the projects we examined sometimes with significant time and/or budget impacts indicating scope to enhance related risk and cost assessments. Specifically:

  • Hornsby Ku-ring-gai Hospital Redevelopment Stage 2: adverse site conditions during demolition works resulted in an 11-month delay for delivering the medical imaging unit and 14-month delay completing Stage 2 main works including need for additional $15.0 million in funds to cover the resultant budget deficit for the project.
  • Blacktown Mt Druitt Hospital Redevelopment Stage 2: adverse site conditions combined with project complexity delayed completion of the early works by approximately five months. This contributed to the delay in completing the main construction works which occurred around nine months later than planned in the business case.
  • Dubbo Health Service Redevelopment Stages 3 and 4: Health Infrastructure advised adverse site conditions including asbestos containing materials and ground conditions delayed works for the main building with completion forecast for March 2021, around 21 months later than planned in the final business case. This resulted in the need for additional $13.5 million to cover increased construction costs and risks, increasing the Stage 3 and 4 forecast final cost from $150 million to $163.5 million as at February 2020.

These examples indicate a risk the cumulative impact of adverse site conditions may be substantial when measured across both time and Health Infrastructure's full delivery program. They also point to potential for Health Infrastructure to achieve efficiencies and improved outcomes from strengthening its approach to assessing and mitigating the risks from adverse site conditions.

Limited due diligence with prospective contractors risks avoidable delays and costs

Main construction works on Stage 1 of the Dubbo Health Service Redevelopment were completed in October 2015, approximately 13 months later than planned in the final business case. Delays were mainly due to insolvency of the early works contractor resulting in their departure from the project. The ensuing 11-month delay in completing the early works significantly impacted the overall schedule and delivery of main construction works.

The insolvency event was significant as it affected nine separate Health Infrastructure projects – three of which had yet to reach practical completion. It also affected state-funded projects in other sectors. It resulted in the need for additional funding of $11.5 million that was provided in the 2014–15 State Budget increasing the total Stage 1 and 2 budget from $79.8 million to $91.3 million.

Health Infrastructure’s analysis of lessons learned shows it worked actively to mitigate the impacts of the insolvency event across all affected projects. However, it also indicates a risk the lessons were mainly focused on mitigating the impacts after an insolvency event occurred rather than on prevention.

Although Health Infrastructure initially commissioned a financial assessment of the now insolvent early works contractor before engagement, it did not detect any risks of the impending insolvency and instead concluded the contractor was in a strong financial position. However, the contractor became insolvent shortly after commencement approximately seven months later. This indicates a risk of weaknesses in the assessment performed that was not explicitly addressed by the lessons learned.

Delivery of the main construction works were further impacted by disputes with the main works contractor over the scope of works for the renal unit resulting in Health Infrastructure terminating the contract in November 2016 following lengthy negotiations over several months.

The scope of works relating to the renal unit were ultimately transferred to Stages 3 and 4 and were delivered in December 2019, around five years later than originally planned in the business case.

Health Infrastructure advised the delay was ultimately beneficial to the project because the refurbishment works for the renal unit, initially scheduled for Stages 1 and 2, would have been demolished to accommodate the new Western Cancer Centre proposed after Stages 1 and 2 and currently being delivered in parallel with Stages 3 and 4.

Health Infrastructure advised the actual cost of Stages 1 and 2 was $84.7 million against the budget of $91.3 million. The residual $6.6 million relates to the renal works not delivered during Stage 1 and 2 and transferred to Stage 3 and 4.

Health Infrastructure advised the contractual provisions for mitigating insolvency events 'in-flight' are limited highlighting the importance of proactive and effective due diligence prior to engaging contractors for significant construction projects.

Need for a quality framework linked to staff training and capability development

Health Infrastructure's 2017-20 Corporate Plan identifies the development of a quality framework to support delivery of future-focused outcomes as a key organisational priority. Related initiatives within the Corporate Plan describe a framework underpinned by a Quality Committee providing advice on:

  • records management, to meet the requirements of the State Records Act 1998
  • project assurance, to ensure future focused outcomes and enhance Health Infrastructure's Standards, Policies, Procedures and Guidelines, Templates and Design Guidance Notes
  • knowledge management and library services, to promote and leverage from project learnings.

Although Health Infrastructure has some elements of a quality framework it is not yet fully in place. Health Infrastructure advised it had yet to establish the quality framework and related committee described in its Corporate Plan due in part to its focus on responding to the growth of its capital program.

Health Infrastructure's Development and Innovation team has been active in supporting continuous improvement in knowledge and project management including development of business cases. Although useful, these initiatives have relied heavily on leveraging and disseminating insights from Gateway reviews and have not formed part of a systematic quality and continuous improvement framework.

The limited focus on the quality of business cases is reflected in internal performance monitoring and reporting which focuses mainly on tracking the delivery of projects against internal benchmarks, often revised from the baselines in the business case, and expenditure against cashflow targets. There is no evident internal monitoring and/or reporting to the Chief Executive and Board on defined quality metrics linked to business case development and staff capability.

Performance reporting on balanced scorecard metrics has similarly focused mainly on process rather than quality and has been inconsistent in recent years.

Appendix one – Response from agency

Appendix two – About the audit

Appendix three – Performance auditing

Appendix four – Ministry of Health planning tools and guidelines

Appendix five – Streamlined investment decision process for Health Capital Projects

Appendix six – Timeline of business cases and relevant policy guidelines

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #338 - released 12 August 2020

Published

Actions for CBD South East Sydney Light Rail: follow-up performance audit

CBD South East Sydney Light Rail: follow-up performance audit

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk
Service delivery

This is a follow-up to the Auditor-General's November 2016 report on the CBD South East Sydney Light Rail project. This follow-up report assessed whether Transport for NSW has updated and consolidated information about project costs and benefits.

The audit found that Transport for NSW has not consistently and accurately updated project costs, limiting the transparency of reporting to the public.

The Auditor-General reports that the total cost of the project will exceed $3.1 billion, which is above the revised cost of $2.9 billion published in November 2019. $153.84 million of additional costs are due to omitted costs for early enabling works, the small business assistance package and financing costs attributable to project delays.

The report makes four recommendations to Transport for NSW to publicly report on the final project cost, the updated expected project benefits, the benefits achieved in the first year of operations and the average weekly journey times.

Read full report (PDF)

The CBD and South East Light Rail is a 12 km light rail network for Sydney. It extends from Circular Quay along George Street to Central Station, through Surry Hills to Moore Park, then to Kensington and Kingsford via Anzac Parade and Randwick via Alison Road and High Street.

Transport for NSW (TfNSW) is responsible for planning, procuring and delivering the Central Business District and South East Light Rail (CSELR) project. In December 2014, TfNSW entered into a public private partnership with ALTRAC Light Rail as the operating company (OpCo) responsible for delivering, operating and maintaining the CSELR. OpCo engaged Alstom and Acciona, who together form its Design and Construct Contractor (D&C).

On 14 December 2019, passenger services started on the line between Circular Quay and Randwick. Passenger services on the line between Circular Quay and Kingsford commenced on 3 April 2020.

In November 2016, the Auditor-General published a performance audit report on the CSELR project. The audit found that TfNSW would deliver the CSELR at a higher cost with lower benefits than in the approved business case, and recommended that TfNSW update and consolidate information about project costs and benefits and ensure the information is readily accessible to the public.

In November 2018, the Public Accounts Committee (PAC) examined TfNSW's actions taken in response to our 2016 performance audit report on the CSELR project. The PAC recommended that the Auditor-General consider undertaking a follow-up audit on the CSELR project. The purpose of this follow-up performance audit is to assess whether TfNSW has effectively updated and consolidated information about project costs and benefits for the CSELR project.

Conclusion

Transport for NSW has not consistently and accurately updated CSLER project costs, limiting the transparency of reporting to the public. In line with the NSW Government Benefits Realisation Management Framework, TfNSW intends to measure benefits after the project is completed and has not updated the expected project benefits since April 2015.

Between February 2015 and December 2019, Transport for NSW (TfNSW) regularly updated capital expenditure costs for the CSELR in internal monthly financial performance and risk reports. These reports did not include all the costs incurred by TfNSW to manage and commission the CSELR project.

Omitted costs of $153.84 million for early enabling works, the small business assistance package and financing costs attributable to project delays will bring the current estimated total cost of the CSELR project to $3.147 billion.

From February 2015, TfNSW did not regularly provide the financial performance and risk reports to key CSELR project governance bodies. TfNSW publishes information on project costs and benefits on the Sydney Light Rail website. However, the information on project costs has not always been accurate or current.

TfNSW is working with OpCo partners to deliver the expected journey time benefits. A key benefit defined in the business plan was that bus services would be reduced owing to transfer of demand to the light rail - entailing a saving. However, TfNSW reports that the full expected benefit of changes to bus services will not be realised due to bus patronage increasing above forecasted levels.

Appendix one – Response from agency

Appendix two – Governance and reporting arrangements for the CSELR

Appendix three – 2018 CSELR governance changes

Appendix four – About the audit

Appendix five – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #335 - released 11 June 2020

Published

Actions for Health 2017

Health 2017

Health
Asset valuation
Compliance
Financial reporting
Fraud
Information technology
Internal controls and governance
Management and administration
Procurement
Project management

The following report highlights results of the financial audits of entities in the NSW health cluster. The report focuses on key observations and findings from the most recent audits of these entities.

The report also includes a range of findings on service delivery. Overall, NSW Health is achieving most of their targets. Some local health districts are continuing to experience increased demand for their services and are finding it more difficult to meet their targets. For example, three local health districts had not achieved some emergency department response time targets for three consecutive years.

1. Financial reporting and controls

Financial Reporting

All health cluster entities received unqualified audit opinions and the quality of financial reporting remains high across the cluster.

Early close procedures were largely completed and all financial statements were submitted by the deadlines.

Financial performance

Overall, NSW Health recorded an operating surplus of $407 million in 2016–17. Eleven local health districts/specialty networks recorded operating deficits in 2016–17, four more than 2015–16.

Expenses across NSW Health increased by 4.4 per cent in 2016–17 (6.0 per cent in 2015–16), lower than the expected long term annual expense growth rate.

Excess annual leave Managing excess annual leave is a continual challenge for NSW Health, with thirty–five per cent of the workforce having excess balances.
Overtime payments NSW Health entities are generally managing overtime well; however NSW Ambulance’s overtime payments, $74.6 million in 2016–17, remain significantly higher than other health entities.
Time and leave recording practices Unapproved employee timesheets continue to be a problem for health entities. Weak timesheet approval controls increase the risk of staff claiming and being paid for hours they have not worked. There is also an increased risk of high volumes of roster adjustments, manual pays, salary overpayments and leave not being recorded accurately.

2. Service Delivery

Service Agreements Most of the service agreements between the Secretary of NSW Health and health entities were signed earlier than prior years.
Performance monitoring Five NSW Health entities are not meeting the Ministry of Health’s performance expectations at 30 June 2017.
Emergency department performance Data provided by the Ministry indicates NSW Health, on average, met emergency department triage response time targets across all triage categories for the fourth consecutive year.
Ambulance response times Data provided by the Ministry shows NSW Ambulance response times for imminently life‑threatening incidents of 7.5 minutes in 2016–17 was within the Ministry’s target of 10.0 minutes.

Data provided by the Ministry indicates NSW Ambulance response times for potentially life‑threatening incidents did not improve in 2016–17. The median response time of 11.1 minutes in 2016–17 was similar to 2015–16 (11.0 minutes). This is despite the number of Priority 1 responses reducing by 4.3 per cent.
Unplanned hospital re-admissions Data provided by the Ministry shows eight local health districts achieved the Ministry of Health’s unplanned hospital re‑admissions target in 2016–17. The target is for local health districts to reduce re‑admission rates from the previous financial year.

This report sets out the results of the 30 June 2017 financial statement audits of Health cluster entities.

The report has been structured into two chapters focusing on:

  • Financial reporting and controls
  • Service delivery.

This chapter outlines audit observations, conclusions and recommendations related to financial reporting and internal controls of entities for 2016-17.

Observation Conclusion or recommendation

2.1 Quality of financial reporting

All cluster entities received unqualified audit opinions and misstatements identified in financial statements fell. The quality of financial reporting remains high across the cluster.

2.2 Timeliness of financial reporting

Early close procedures were largely completed and all financial statements were submitted by the deadlines. Health entities controlled by the Ministry of Health continued submitting their financial statements well ahead of the statutory deadlines.

2.4 Financial and sustainability analysis

NSW Health recorded an operating surplus of $407 million in 2016–17.



Eleven local health districts/specialty networks recorded operating deficits in 2016–17, four more than 2015–16.


Expenses across NSW Health increased by 4.4 per cent in 2016–17 (6.0 per cent in
2015–16).

The capital replacement ratio of local health districts/specialty networks ranged from 0.5 to 5.7 in 2016–17. Seven local health districts had capital replacement ratio higher than one.

The statewide operating surplus was $84 million higher than 2015–16. Net surpluses contribute to NSW Health’s ability to invest in new facilities, upgrades and redevelopments.

The 2016–17 financial results were once again impacted by the NSW Government initiative to improve cash management across the sector.

The expense growth rate for NSW Health is 1.6 percentage points lower than the expected long term annual expense growth rate.

Substantial ongoing investment in hospitals and other assets across NSW Health is evidenced by high capital replacement ratios for some health entities in 2016–17.

2.5 Performance against budget
Ten local health districts/specialty networks’ expense budget variance was outside performance expectations agreed with the Ministry at the beginning of 2016–17. The Ministry continues to manage performance across NSW Health to improve the accuracy of budgeting practices.
2.7 Human Resources    

Thirty-five per cent of NSW Health’s workforce have excess annual leave balances.

 

 

 

 

 

 

NSW Ambulance had the highest average sick leave rate in NSW Health of 85.2 hours per FTE in 2016–17 (78.7 hours in 2015–16). This was higher than the statewide average of 62.1 hours (62.0 hours in 2015–16).

NSW Ambulance’s overtime payments in 2016–17 totalled $74.6 million; $2.8 million more than 2015–16 and significantly higher than other health entities

Other NSW Health entities are generally managing overtime well.

 

Unapproved employee timesheets continue to be a problem for health entities. Weak timesheet approval controls increase the risk of staff claiming and being paid for hours they have not worked.

 

Managing excess annual leave is a continual challenge for health entities.

Recommendation: Health entities should further review the approach to managing excess annual leave in 2017–18. They should:

  • monitor current and projected leave balances to the end of the financial year on a monthly basis
  • agree formal leave plans with employees to reduce leave balances over an acceptable timeframe.


NSW Ambulance continues to face significant challenges in managing sick leave.

Recommendation: NSW Ambulance should further implement and monitor targeted human resource strategies to address the high rates of sick leave taken

Recommendation: NSW Ambulance should further review the effectiveness of its rostering practices to identify strategies to reduce excessive overtime payments.

Recommendation: Health entities should conduct a risk‑based review of time and leave recording practices to ensure control weaknesses are identified and fixed.

This chapter outlines our audit observations, conclusions and recommendations relating to service delivery for 2016–17.

Observation Conclusion or recommendation
3.1 Service agreements in NSW Health

Most of the service agreements between the Secretary of NSW Health and health entities were signed earlier than prior years.

Thirteen local health districts/specialty networks signed their service agreements by the 31 July 2017 due date. This is a significant improvement with only seven local health districts/specialty networks meeting the date in 2015–16.

Having service agreements signed as close as possible to the start of each year provides the Ministry and NSW Health entities with clarity around roles, responsibilities, performance measures, budgets, and service volumes and levels.
3.2 Performance of NSW Health entities
Five NSW Health entities were not meeting the Ministry’s performance expectations at 30 June 2017. The Ministry is managing the five entities in accordance with its performance review process.
3.4 Emergency department response times

Data provided by the Ministry indicates NSW Health again, on average, met emergency department triage response time targets across all triage categories for the fourth consecutive year.

The Ministry manages performance across NSW Health to ensure patients presenting at emergency departments receive care in a clinically appropriate timeframe.

Based on the Ministry’s data, local health districts/specialty networks are, on average, meeting triage targets despite increasing emergency department attendances.

The data shows eleven local health districts met all triage targets in 2016–17, compared to eight in
2015–16. 

3.5 Emergency treatment performance

The Ministry manages public patient access to emergency services in public hospitals.

It has an emergency treatment performance target of 81 per cent of patients leaving emergency departments within four hours.

Data provided by the Ministry indicates NSW Health maintained its overall emergency treatment performance in 2016–17, but did not achieve its target. The State average emergency treatment performance was 74.2 per cent (74.2 per cent in 2015–16).

Based on the Ministry’s data, only four local health districts achieved the target in 2016–17, five in
2015–16.

3.6 Ambulance response times
NSW Ambulance has a response time target of 10.0 minutes for imminently life‑threatening incidents in New South Wales. Data provided by the Ministry indicates NSW Ambulance response times for imminently life-threatening incidents of 7.5 minutes in 2016–17 was within the Ministry’s target.
 
3.7 Transfer of care
The Ministry has a target of 90 per cent for the number of ambulance arrivals within a 30 minute ‘transfer of care’ timeframe. Data provided by the Ministry indicates the rate of ambulance arrivals within a 30 minute 'transfer of care' timeframe improved from 87.6 per cent in
2015–16 to 91.7 per cent in 2016–17, exceeding the Ministry’s target.
3.8 Average length of stay in hospital
Based on the Ministry’s 2016–17 data, the average length of stay for acute episodes was 3.0 days. The average length of stay in New South Wales hospitals is lower than the national average of 3.2 days (in 2015–16). The Ministry’s data shows the average length of stay by patients for acute episodes has remained stable in New South Wales hospitals for four years. 
3.9 Elective surgery access performance
Data provided by the Ministry indicates NSW Health continues to manage waiting times for elective surgery in public hospitals. The Ministry’s data shows NSW Health improved on‑time admission of patients for elective surgery in 2016–17 despite a 1.8 per cent increase in admissions. While the result improved, only one of the three targets for elective surgery waiting times was met in 2016–17.
3.10 Unplanned hospital re-admissions

Data provided by the Ministry indicates NSW Health, on average, did not reduce the rate of unplanned hospital re‑admissions in 2016–17. The Ministry has a target of reducing unplanned hospital re‑admissions compared to the previous financial year.

Low re‑admission rates may indicate good patient management practices and post-discharge care.

The Ministry’s data shows eight local health district met the target to reduce the rate of re‑admissions compared to the previous financial year. The statewide average rate increased from 6.3 per cent to 6.4 per cent.
3.11 Post discharge care for acute mental health patients
NSW Health has a goal to increase community-based care to acute mental health patients after they are discharged. Continuity of care in the community can lead to reduced symptom severity, lower re‑admission rates, and improved quality of life. The Ministry’s 2016–17 data shows the statewide average for post discharge follow-up of acute mental health patients within seven days was 70.0 per cent (66.0 per cent in 2015–16). The statewide average improved and met the NSW Health target of 70 per cent. Nine local health districts exceeded the NSW Health target.
3.12 Mental health acute re-admissions
NSW Health has a goal to reduce acute public sector mental health re-admissions. High re‑admission rates may indicate deficiencies in inpatient treatment and follow up care. The Ministry’s data shows twelve local health districts did not achieve the NSW Health target of 13 per cent mental health acute re‑admissions in 2016–17.
3.13 Unplanned and emergency re‑presentations

NSW Health aims to reduce the number of unplanned and emergency re‑presentations to emergency departments.

The Ministry’s 2016–17 data shows the State average of emergency department re‑presentations decreased marginally from 5.0 per cent in 2015–16 to 4.9 per cent.

Patients attending rural emergency departments are more likely to re‑present within 48 hours of being discharged than those in regional or metropolitan emergency departments.
3.14 Healthcare associated infection
The national target for the rate of Staphylococcus aureus (golden staph) bloodstream infection is two cases per 10,000 bed days. Data provided by the Ministry indicates the rate of golden staph bloodstream infection in New South Wales hospitals continues to be well below the target and national benchmark at 0.72 cases per 10,000 bed days in 2016–17 (0.75 in 2015–16).
3.15 Patient experience and satisfaction

The Bureau of Health Information analyses and reports on the results of patient surveys.

The Bureau’s survey shows 65 per cent of adult admitted patients rated the care they received in hospital as ‘very good’ and 29 per cent rated it as ‘good’.

NSW Health recognises that patient surveys are an important feedback mechanism on the health care system that can only come from personal experiences.

Published

Actions for Central Agencies 2017

Central Agencies 2017

Finance
Premier and Cabinet
Asset valuation
Compliance
Financial reporting
Fraud
Information technology
Internal controls and governance
Project management

This report highlights the results of the financial audits of NSW Government central agencies. The report focuses on key observations and findings from the most recent financial statement audits of agencies in the Treasury, Premier and Cabinet, and Finance, Services and Innovation clusters.

The report includes a range of findings in respect to service delivery. One repeat finding is that while the Government regularly reports on the 12 Premier's priorities, there is no comprehensive reporting on the 18 State priorities. 

1. Financial reporting and controls

Audit Opinions Unqualified audit opinions were issued for all agencies' 30 June 2017 financial statements.
Early close Early close procedures continue to facilitate the timely preparation of financial statements and completion of audits, but agencies can make further improvement.
Deficient user administration access User access administration over financial systems remains an area of weakness. Agencies need to strengthen user access administration to critical systems.
Transitioning to outsourced service providers Transitioning of services to outsourced service providers can be improved. Outsourcing services can lead to better outcomes, which may include lower transaction costs and improved services, but it also introduces new risks.

2. Service delivery

Premier and State Priorities   A comprehensive report of performance against the 18 State Priorities is yet to be published. While some measures are publicly reported through agency annual reports or other sources, a comprehensive report of performance against the 18 State Priorities would ensure all State Priorities are publicly reported, provide a single and easily accessible source of reference and improve transparency.
ICT and digital government The Digital Government Strategy was released in May 2017. Targets will need to be set to assess and monitor progress against the Strategy.
Digital information security Not all agencies are complying with the NSW Government's information security policy. This increases the risk of noncompliance with legislation, information security breaches and difficulty restoring data or maintaining business continuity in the event of a disaster or disruption.
Property and asset utilisation Property NSW's performance reporting would be enhanced by developing and reporting on customer satisfaction, reporting against set targets and benchmarking cost of service to the private sector.

3. Government financial services

Prudential oversight
of NSW Government superannuation
funds  
Prudential oversight of SAS Trustee Corporation Pooled Fund and Parliamentary Contributory Superannuation Fund has not been prescribed. Structured and comprehensive prudential oversight of these funds remains important as they operate in a specialised, complex and continuously changing investment market sector, have over 106,000 members and manage investments in excess of $42.4 billion.
Green slip scheme affordability Currently, Green Slips in NSW are the most expensive in Australia. However, CTP reforms are expected to reduce the cost of Green Slips.

This report sets out the results of the 30 June 2017 financial statement audits of NSW Government's central agencies and their cluster agencies.

Central agencies play a key role in ensuring policy coordination, good administrative and people management practices and prudent fiscal management. The central agencies and their key responsibilities are set out below.

Confidence in public sector decision‑making and transparency is enhanced when financial reporting is accurate and timely. Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. This chapter outlines our audit observations, conclusions or recommendations related to financial reporting and controls of agencies for 2016–17.

Observation Conclusion or recommendation
2.1 Quality of financial reporting
Unqualified audit opinions were issued for all agency financial statements. The quality of financial reporting continues to remain strong across the clusters.
2.2 Timeliness of financial reporting
Most agencies complied with the statutory timeframes for completion of early close procedures and preparation and audit of financial statements. Early close procedures continue to facilitate the timely preparation of financial statements and completion of audits, but agencies can make further improvement.
2.3 Financial performance and sustainability
We assessed the performance of agencies listed in Appendix six against some key financial sustainability indicators. This highlighted two agencies with negative operating margins of more than ten per cent and one agency with a liquidity ratio of less than 0.5. These agencies have strategies in place to remain financially sustainability and manage their liquidity. Our analysis found that, overall, the agencies are not at high risk of sustainability concerns.
2.4 Internal Controls

User access administration over financial systems remains an area of weakness. Sixteen moderate risk and ten low risk issues related to user access administration across eight agencies were identified. 

Recommendation: Agencies should review user access administration to critical systems to ensure:

  • policies for user access creation, modification and deactivation are documented
  • approval is being obtained to establish, modify or delete user accounts
  • regular user access reviews are performed and highly privileged user account activity is logged and monitored
  • evidence of review is maintained.

Transitioning of services to outsourced service providers can be improved. Our 2016–17 audits identified one high risk issue relating to Property NSW's outsourcing of property and facility management services to the private sector.

While a high risk issue was identified in 2015–16 from the Department of Finance, Services and Innovation's outsourcing of transactional and information technology services to GovConnect there has been an improvement in GovConnect's internal control environment throughout
2016–17.

Outsourcing services can lead to better outcomes, which may include lower transaction costs and improved services, but it also introduces new risks. The transition needs to be carefully managed and requires thorough planning and effective project governance. This should be supported by oversight and direction from senior management and independent project assurance.
2.5 Human Resources    
The percentage of full‑time equivalent staff with annual leave greater than 30 days in the Finance, Services and Innovation, Premier and Cabinet and the Treasury clusters is 7.9 per cent, 17.1 per cent and 18.4 per cent respectively. Agencies have strategies in place to reduce annual leave balances that are greater than 30 days. The effectiveness of these strategies will need to be monitored to ensure they are helping to achieve the desired outcome.

This chapter outlines our audit observations, conclusions and recommendations relating to service delivery for 2016–17. 

Observation Conclusion or recommendation
3.1 Premier and State priorities

The Department of Premier and Cabinet monitors the achievement of targets and the implementation of initiatives to deliver the 12 Premier’s Priorities.

Responsible ministers and agencies manage the 18 State Priorities. A comprehensive report of performance against the 18 State Priorities is yet to be published.

While some measures are publicly reported through agency annual reports or other sources, a comprehensive report of performance against the 18 State Priorities would ensure all State Priorities are publicly reported, provide a single and easily accessible source of reference and improve transparency.
Where possible, independent sources are used to measure performance, however without independent assurance there is an increased risk that the target measures are inaccurate, not relevant or do not fairly represent actual performance.

Performance against the State Priority to make NSW the easiest state to start a business is not currently published.

A key aspect of making NSW the easiest state to start a business is making regulatory obligations easier to understand and implement.

Initiatives, such as easy to do business and red tape reduction are in place to help achieve this priority.

The regulatory policy framework is under review following an October 2016 performance audit on ‘Red tape reduction’ that found the regulatory burden of legislation had increased.
3.2 Financial management
Revenue NSW earned record crown revenue of $30.0 billion in 2016–17 to support the state's finances. Record crown revenue has been driven by the sustained increase in duties revenue, which has increased by 93.7 per cent over the last five years. This is a consequence of the continued strength in the property market over this time and large one off NSW Government business asset sales and leases.
3.3 ICT and digital government
The Digital Government Strategy (the Strategy) was released in May 2017 to build on reforms set out in previous ICT strategies. The Strategy’s priorities and enablers aim to support digital innovation. Targets and measures will need to be set to assess and monitor progress against the Strategy.
The Digital Information Security Policy (DISP) is a key tool that helps ensure a minimum set of information security controls are implemented across NSW Government agencies.

A review of 2016 annual reports found 15 agencies (13 in 2015) did not attest to compliance with the DISP and of the agencies that attested to compliance, 34 reported issues associated with their compliance.

The Strategy’s priorities and enablers aim to support digital innovation. Targets and measures will need to be set to assess and monitor progress against the Strategy.

Failure to comply with the DISP increases the risk of noncompliance with legislation, information security breaches and difficulty restoring data or maintaining business continuity in the event of a disaster or disruption.

3.4 Property and asset utilisation

Property NSW's performance reporting could be
improved. M2012-20 'Government Property NSW
and Government Property Principles' required
Property NSW to set key performance indicators
to measure property and asset utilisation
performance.
 

Property NSW's performance reporting would be enhanced by developing and reporting on customer satisfaction, reporting against set targets and benchmarking cost of service to the private sector.

This chapter outlines our audit observations, conclusions and recommendations specific to NSW Government agencies providing financial services.

Observation Conclusion or recommendation
4.1 Key issues

The SAS Trustee Corporation (STC) Pooled Fund and the Parliamentary Contributory Superannuation (PCS) Fund are not required to comply with the prudential and reporting standards issued by the Australian Prudential Regulation Authority (APRA). Amendments to relevant legislation allows the Minister for Finance, Services and Property to prescribe applicable prudential standards and audit requirements.

Structured and comprehensive prudential oversight of these funds remains important as they operate in a specialised, complex and continuously changing investment market sector, have over 106,000 members and manage investments of more than $42.4 billion.

Recommendation: The Treasury should liaise with
the respective Trustees to implement appropriate
prudential standards and oversight arrangements for
the exempt public sector superannuation funds.

Currently, Green Slips in NSW are the most expensive in Australia. Average premiums for Sydney Metropolitan vehicles increased by 10.4 per cent between 1 January 2016 and 31 December 2016.

CTP reforms are expected to reduce the cost of Green Slips. The State Insurance Regulatory Authority will need to ensure it has appropriate processes in place to track and report against the expected benefits.
4.2 Financial performance and sustainability
Net unfunded superannuation liabilities were $15.0 billion at 30 June 2017.

Under the Fiscal Responsibility Act 2012, the NSW Government’s target is to eliminate unfunded superannuation liabilities by 2030.
The superannuation funds’ strategic asset allocation and investment strategies are monitored and adjusted to help achieve a fully funded position by 2030.
The Home Warranty Scheme commenced in 2011. Over this time total premiums collected have not been sufficient to cover expected claim costs. Funding arrangements introduced during 2016–17 allow the Home Building Compensation Fund to apply to the Crown for reimbursement of unfunded realised losses from under-pricing of premiums.

Other reforms are planned to address the long term sustainability of the home building compensation scheme.
4.3 Investment performance
The NSW Government’s main superannuation funds have maintained the management expense ratio (MER) at consistent levels over the past two years. The Parliamentary Contributory Superannuation (PCS) Fund does not set an MER target. MER is an industry recognised ratio to measure the performance of funds and investment managers.

Recommendation: The Fund Secretary for the PCS Fund, in conjunction with the Trustee, should consider establishing an appropriate management expense ratio target to measure performance.

Published

Actions for State Finances 2017

State Finances 2017

Finance
Health
Industry
Justice
Local Government
Planning
Premier and Cabinet
Treasury
Universities
Whole of Government
Environment
Asset valuation
Financial reporting
Information technology
Internal controls and governance

Total State Sector Accounts received an unqualified audit opinion for the fifth consecutive year.

There was a $5.7 billion State budget surplus and continued investment in new infrastructure, in part funded by the long-term leases of Ausgrid and Endeavour Energy assets. This report also comments on key accounting matters, including the correction of some previously reported balances and the first time reporting of combined Cabinet members’ compensation in the Total State Sector Accounts.

Pursuant to the Public Finance and Audit Act 1983, I present my Report on State Finances 2017.

You will note that the format of this report has changed from previous years.

The intent of this change is to draw attention to the key matters that have been the focus of our audit and highlight significant factors that have contributed to the outcome.

First, it is pleasing to report once again that I issued a clear audit opinion on the State’s consolidated financial statements. This outcome demonstrates the Government’s continued focus on the quality of financial reporting across the NSW public sector.

High quality financial management and reporting are crucial to properly inform the public and build community confidence in our system of government.

The Treasury’s Financial Management Transformation program also aims to improve financial governance, budgeting and reporting arrangements across the sector. My Office is working collaboratively with The Treasury on reforms to reduce the burden of reporting, without weakening established safeguards.

The reforms should include measures to provide independent assurance of the budget process, of outcome reporting by agencies, and the power to “follow the dollar” given the increasing use of non-government organisations to deliver Government programs.

This Report also highlights another year of strong financial performance. The State’s budget result was a $5.7 billion surplus, and investment in new infrastructure has continued, in part funded by the long-term leases of Ausgrid and Endeavour Energy assets.

Finally, could I take this opportunity to thank the staff of The Treasury for the way they approached this audit. Our partnership is critical to ensuring NSW is an exemplar of quality financial management and reporting.

02_Margaret_signature.jpg

Margaret Crawford 
24 October 2017

A clear audit opinion on the State’s consolidated financial statements was issued.

Timely and accurate financial reporting is essential for informed decision making, effective management of public funds and enhancing public accountability.

This year’s clear audit opinion reflects the Government’s continued efforts to improve the quality of financial reporting across the NSW public sector.

Since the introduction of ‘early close procedures’ in 2011-12, the number of significant errors in financial statements of agencies has generally fallen largely due to identifying and resolving complex accounting issues early. Agencies’ 2016-17 financial statements submitted for audit contained nine errors exceeding $20 million. All errors were subsequently corrected in the individual agencies financial statements.

Agencies should continue to respond to key accounting issues as soon as they are identified. Where issues are identified, accounting position papers should be prepared for consideration by the Audit Office, their Audit and Risk Committee members, and when relevant, The Treasury.

The State addressed the following key accounting matters during 2016-17. 

The State recognised rail tunnels and earthworks valued at $8.5 billion.

Some rail tunnels and earthworks have never been valued by the State. These include the City Circle, the country rail network and other tunnels and earthworks built before the year 2000. Some of these tunnels and earthworks date back to the early 1900s.

For many years, the State did not account for these assets as they believed that their value could not be reliably measured. This year an independent valuer was engaged to perform a comprehensive valuation. The methodology used demonstrated
that the assets could have been reflected in the financial statements earlier.

The State recorded an additional $8.5 billion to correct the value of infrastructure assets at 1 July 2016.

Cabinet member’s compensation and related party transactions were reviewed.

Due to changes in Accounting Standards, the State had to consider 'related party information' in the financial statements. Previously this only applied to for-profit entities.

This year, requirements to report related party information extended to members of Cabinet, considered to be “key management personnel” of the State, as defined by Accounting Standards.

The Treasury implemented a process to assess and report Cabinet member’s compensation, and transactions between Cabinet members and/or their close family members, and government agencies.

Collectively, Cabinet members’ remuneration was $8.8 million, which was mainly salaries and allowances, and $3.5 million of non-monetary benefits such as security and drivers. The Treasury determined there were no other specific “related party” transactions or balances that required disclosure in the State’s financial statements.

Information system limitations continue at TAFE NSW.

TAFE NSW has experienced ongoing issues with its student administration system.

TAFE NSW has again implemented additional processes to verify the accuracy and completeness of revenue from sales of goods and services.

TAFE NSW expects to spend up to $89 million on a new information system to address these issues. Modules of the new student enrolment system are expected to be in place for the 2018 enrolment period.

Restatements relating to the General Government Sector's investment in the commercial sector.

The State corrected two previously reported balances relating to the General Government Sector’s investment in the commercial sector.

Accounting Standards require the General Government Sector to effectively store gains or losses related to its investment in the commercial sector in reserves until the investment is derecognised.

When these investments are disposed of, the cumulative gains and losses must be cleared and recognised in the operating result. However, the Government had previously cleared the cumulative gains and losses directly to Accumulated Funds within equity.

To comply with Accounting Standards, a total of $6 billion previously reported as a movement in equity  at 30 June 2016, has now been corrected to the operating result.

In addition, Accounting Standards only allow gains or losses on its investments to be stored in reserves. In past years, the State recognised all changes in the value of its investment in Available for Sale Reserves, including the capital contributed to establish the State’s investment. In 2016-17, a total of $23.4 billion of contributed capital was corrected to accumulated funds at 1 July 2015.

The State’s budget result was a $5.7 billion surplus, $2.0 billion higher than the budget estimate.

The Total State Sector comprises 310 entities controlled by the NSW Government.

Of the total, the General Government Sector comprises 215 entities that provide goods and services not directly paid for by consumers.

The non-General Government Sector comprises 95 Government businesses that provide goods and services such as water and electricity, or financial services.

A principal measure of a Government’s overall performance is its Net Operating Balance, or Budget Result. The Net Operating Balance reports the difference between the cost of General Government service delivery and the revenue earned to fund these sectors.

The State has recorded budget surpluses and exceeded the original budget result in nine of the last ten years.

The State maintained its AAA credit rating.

The object of the Act is to maintain the AAA credit rating.

NSW’s finances are managed in alignment with the Fiscal Responsibility Act 2012 (the Act).

The Act established the framework for fiscal responsibility and strategy needed to protect the State’s AAA credit rating and service delivery to the people of NSW.

The purpose of maintaining the AAA credit rating is to reduce the cost of, and ensure the broadest access to, borrowings.

A triple-A credit rating also helps maintain business and consumer confidence so economic activity and employment are sustained. The legislation sets out targets and principles for financial management to achieve this.

New South Wales has credit ratings of AAA/Negative from Standard & Poor’s and Aaa/Stable from Moody’s Investors Service.

The fiscal targets for achieving this objective are:

General Government expenditure growth is lower than long term revenue growth.

General Government expenditure growth was 4.2 per cent in 2016-17, below the long-term revenue growth of 5.6 per cent.

Eliminating unfunded superannuation liabilities by 2030.

The Act sets a target of eliminating unfunded defined benefit superannuation liabilities by 2030. The State’s net superannuation liability was $58.6 billion at 30 June 2017 ($71.2 billion at 30 June 2016).

The Government predicts the 2030 target will be achieved. The State’s funding plan is to contribute amounts escalated by five per cent each year so the schemes will be fully funded by 2030. In 2016-17, the State made employer contributions of $1.5 billion, which is largely consistent with contributions over the past five years.

The liability values in the graph below do not reflect the values recorded in the Total State Sector Accounts. For financial reporting purposes, Accounting Standards (AASB 119 Employee Benefits) require the State to discount its superannuation liability using the government bond rate (refer to page 10 of this report). 

The relevant government bond rate in the current economic climate is 2.62 per cent.

The State’s target for the unfunded superannuation liability is measured using AASB 1056 Superannuation Entities. This is because it adopts a measurement basis that reflects expected earnings on fund assets, which are currently between 5.9 and 7.4 per cent. Using these rates, the liability is $15.0 billion at 30 June 2017 ($16.1 billion at 30 June 2016). The unfunded liability is $2.4 billion less than when the Act was introduced.

The State’s assets grew by $31.6 billion during 2016-17 to $409 billion.

Valuing the State’s physical assets.

When we audit the financial statements, we focus on areas we consider as higher risk. These areas are often complex, and require the use of estimates and judgements.

The State has $307.2 billion of physical assets measured at fair value in accordance with Australian Accounting Standards. Fair value calculations are inherently complex and sensitive to assumptions and estimates, increasing the risk these assets are incorrectly valued.

In our audits, we assess the reasonableness and appropriateness of assumptions used in valuing physical assets. This includes obtaining an understanding of the valuation methodologies applied and judgements made. We also review the completeness of asset registers, and the mathematical accuracy of valuation models.

Net movements between years includes additions, disposals, depreciation and valuations. This year, valuations of physical assets added $16.2 billion to the State’s assets, comprising: 

  • Transport for NSW and Railcorp $8.5 billion

  • New South Wales Land and Housing Corporation $4.8 billion

  • Roads and Maritime Services $930 million

  • Crown Entity $400 million.    

The State’s financial assets increased $27.5 billion in 2016-17

The State’s financial assets have increased by 88 per cent over the past four years. In 2016-17, financial assets increased primarily due to proceeds from the sale of government assets and businesses.

The Government implemented reforms to better use the State’s financial assets. A key element was the creation of an Asset and Liability Committee (ALCO) to provide advice on ways to improve balance sheet management.

Since the creation of the ALCO, reforms include:

  • Establishment of the New South Wales Infrastructure Future Fund (NIFF). The net proceeds from the State’s asset recycling program are invested into the NIFF, which is managed by TCorp, with a balance of $14.6 billion by 30 June 2017. Funds raised are invested through the NIFF until the Government requires them for critical infrastructure projects that are part of the Restart NSW and Rebuilding NSW program of works. ALCO and TCorp provide advice on the NIFF’s performance and management

  • Establishment of the Social and Affordable Housing Fund ($1.1 billion at 30 June 2017). ALCO oversees the Fund to ensure an appropriate investment approach that will maintain funding certainty for new social and affordable housing stock

  • Cash and liquidity management reforms to centralise cash previously held by agencies in the Treasury Banking System. This reform is designed to ensure agencies have adequate levels of liquidity but with surplus funds invested centrally for better returns.

The State’s liabilities decreased by $13.1 billion during 2016-17 to $182 billion.

Valuing the State’s liabilities relies on an actuarial assessment.

Nearly half of the State’s liabilities relate to its employees. This includes unfunded superannuation, and employee benefits, such as long service and recreation leave.

Valuation of these obligations is subject to complex estimation techniques and significant judgements. Small changes in assumptions can materially impact the financial statements.

We address the risk associated with auditing these balances:

  • using actuarial specialists

  • testing controls around underlying employee data used in data models, and testing the accuracy of the calculations

  • evaluating assumptions applied in calculating employee entitlements such as the discount rate and the probability of long service leave vesting conditions being met.

The State’s superannuation obligations reduced by $12.6 billion in 2016-17.

The State’s $58.6 billion superannuation liability represents obligations for past and present employees, less the value of assets set aside to meet those obligations. The superannuation liability decreased from $71.2 billion to $58.6 billion, largely due to an increase in the discount rate from 1.99 per cent to 2.62 per cent. This alone reduced the liability by $9.2 billion

The State’s borrowings totalled $70.6 billion at 30 June 2017.

The State’s borrowings totalled $70.6 billion at 30 June 2017, $9.5 billion less than the previous year. This was largely due to the repayment of borrowings when the assets of Ausgrid and Endeavour Energy were leased to the private sector.

TCorp issues bonds to raise funds for NSW Government agencies. The bonds are actively traded in financial markets providing price transparency and liquidity to public sector borrowers and institutional investors. All TCorp bonds are guaranteed by the NSW Government.

The Government manages its debt liabilities through its balance sheet management strategy. The strategy extends to TCorp, which applies an active risk management strategy to the Government’s debt portfolio.

General Government Sector debt is being restructured by replacing shorter-term debt with longer-term debt. This lengthens the portfolio to better match liabilities with the funding requirements of infrastructure assets and reduces refinancing risks. It also allows the Government to take advantage of the low interest rate environment.

The State recorded revenue of $83.5 billion in  2016-17, an increase of $5.3 billion from 2015-16.

The State’s results are underpinned by revenue growth in taxation, fees and fines.

Taxation, fees, fines and other revenue comprises $30.5 billion of taxation ($28.7 billion in 2015-16) and $5.3 billion of fees, fines and other revenue ($4.6 billion).

Tax revenue for the Total State Sector increased by $1.8 billion, or 6.4 per cent compared to 2015-16, primarily due to:

  • one-off business asset sales and lease transactions, including $718 million in transfer duty from the Ausgrid and Endeavour Energy lease transactions

  • $385 million increase in payroll tax from growth in NSW employment and average employee compensation

  • a $426 million increase in land taxes.

Growth in stamp duty is expected to slow over the next 4 years.

General Government Sector stamp duties have increased from $6.2 billion in 2012-13 to $11.5 billion in 2016-17, an annual average growth rate of 16.5 per cent. The Government’s budget forecasts the growth in stamp duties to decline, to an average annual growth rate of 2.6 per cent between 2016-17 and 2020-21.

The State received Commonwealth grants and subsidies of $30.8 billion in 2016-17.

The State received $30.8 billion from the Commonwealth Government in 2016-17, $1.6 billion more than in 2015-16. This was primarily due to transaction based asset recycling grants of $1.0 billion and a $720 million increase in national land transport grants. This increase was offset by a $435 million decrease in General Purpose Grants, which mainly comprises New South Wales’ share of the Goods and Services Tax (GST). 

The State spent $79.4 billion in 2016-17 to deliver services to the community, an increase of $3.9 billion from 2015-16.

Overall expenses increased 5.2 per cent from last year. Most of the increase was due to higher employee costs and operating costs.

Total salaries and wages increased by 4.2 per cent from 2015-16.

Total salaries and wages increased to $30 billion from $28.8 billion in 2015-16. The Government wages policy aims to limit the growth in remuneration and other employee costs to no more than 2.5 per cent per annum.

Operating expenses increased by 12.4 per cent from 2015-16.

Within operating expenses, payments for supplies, services and other expenses increased, in part, due to the State:

  • reacquiring mining licenses worth $482 million and additional land remediation costs of $101 million

  • spending more on health including additional drug supplies relating to Hepatitis C.

State spend on transport and communications increased by 68.1 per cent since 2012-13.

While spending on health and education remain the largest functional areas provided by Government, expenditure on transport and communication increased, on average, by 13.9 per cent annually between 2012-13 and 2016-17. This increase reflects the Government’s investment in transport infrastructure such as the Sydney Metro and Westconnex. Over the same period, spending on health increased by $3.9 billion.

Expenditure on fuel and energy has decreased by an average of 44.7 per cent since 2012-13, reflecting the State’s leases of electricity network assets.

In 2011, the Government established Restart NSW to fund high priority infrastructure projects.

Restart NSW projects are primarily funded from the proceeds from the asset recycling program enabling Government to deliver new infrastructure investment.

Restart NSW provides funding for the delivery of Rebuilding NSW, which is the Government’s 10-year plan to invest $20 billion in new infrastructure.

The State finalised long-term leases of Ausgrid and Endeavour Energy assets.

In June 2017, the Government finalised its long-term lease of 50.4 per cent of Endeavour Energy. This transaction follows on from the long-term leases of TransGrid in December 2015 and 50.4 per cent of Ausgrid in December 2016. Net proceeds of $15.0 billion were paid into Restart NSW relating to these transactions.

The Government also finalised an arrangement for the private sector to provide land titling and registry services to the public for 35 years. The State, through Restart NSW, received an upfront payment of $2.6 billion from the new operator.

Restart NSW is funding $29.8 billion of new infrastructure.

The Government has detailed its plan to invest $20 billion into the Rebuilding NSW plan from Restart NSW.

At 30 June 2017, around $2.9 billion has already been spent on Rebuilding NSW projects from Restart NSW, with a further $9 billion included in the budget aggregates. The Government has also earmarked a further $8.1 billion in Restart NSW for future projects.

The most significant project is the Sydney Metro. The Government has committed $7.0 billion from Restart NSW to build a 30-kilometre metro line, linking Sydney Metro Northwest at Chatswood, through new stations in the lower North Shore, the Sydney CBD and southwest to Bankstown. At 30 June 2017, $2.4 billion has been spent on this project from Restart NSW.

Other significant projects funded by Restart NSW include a $1.8 billion contribution to WestConnex and reserved funding of $1 billion towards the State’s Major Stadia Network program.

The Treasury initiated the Financial Management Transformation (FMT) program with the aim of changing and improving financial governance, budgeting and reporting arrangements of the New South Wales public sector.

FMT aims to deliver better outcomes for the people of New South Wales and focuses on transparency and accountability for expenditure, and better value for money.

New Financial Management System

PRIME is the Information Technology (IT) solution component of the FMT program, replacing several historical systems. PRIME will provide both financial and performance information within one IT platform for all agencies in the NSW public sector.

It is expected to give Government more timely information to plan and deliver its policy priorities and the budget.

Independent assurance over the budget process would improve confidence in the reliability of the State’s financial information.

Published

Actions for Sydney Road Maintenance Contracts

Sydney Road Maintenance Contracts

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management

In November 2013, Roads and Maritime Services (RMS) outsourced the maintenance of State roads in the Sydney region south and west zones using an innovative contracting approach called the Stewardship Maintenance Contract (SMC). The SMC links risk to reward, and uses a performance framework where outcomes should drive improved performance over time.

RMS’ SMC contract management includes most elements of good practice, including governance and dispute resolution mechanisms. However, key elements are missing which reduces its effectiveness.

Roads and Maritime Services (RMS) is responsible for the Sydney region State roads network This includes over 2,800 kilometres of roads and associated road corridor infrastructure such as bridges, tunnels and drainage structures. RMS divides the network into three geographical areas: south, west and north zones.

In 1995, RMS first outsourced road corridor infrastructure maintenance for the north zone through a Performance Specified Maintenance Contract (PSMC). The current 10-year PSMC for the north zone will expire in October 2018. Prior to November 2013, RMS maintained roads in the south and west zones through its Road and Fleet Services unit. 

In November 2013, RMS outsourced road maintenance services for the south and west zones using Stewardship Maintenance Contracts (SMC). The contracts run for seven years with an option for a further three years at RMS’ discretion. RMS estimated that the annual cost of these contracts was around $240 million in total. In March 2018, the contract prices are due to be reset by negotiation to reflect the contractors’ experience with, and better information about, the road networks and routine maintenance requirements. 

The SMC model adopted stewardship principles to improve value for money. RMS defined stewardship principles as a broad set of values, attitudes and behaviours, required of the contractor to effectively manage the assets on behalf of RMS. The SMC also includes commercial principles, such as linking risk to reward, and a performance framework where outcomes drive performance.

This audit assessed whether RMS had effectively managed the outsourcing of road maintenance in the Sydney region south and west zones. In making this assessment, we answered the following questions:

  1. Did RMS justify the decision to adopt the SMC model?
  2. Do SMCs include key performance indicators (KPIs) and incentives which promote efficiency and effectiveness? 
  3. Does RMS collect high quality information on contractor performance and take action to correct performance deficiencies?
  4. Are the expected benefits being achieved?

Conclusion

RMS developed an innovative contracting approach with the SMC. RMS has realised some benefits in the first year, including savings, from outsourcing road maintenance in the Sydney region south and west zones using the SMC. However, RMS’ management of the SMC has key elements missing which reduces its effectiveness.

The SMC includes performance measures and incentives to drive efficiency and effectiveness improvements over time.  

RMS has established a contract management framework which includes most elements of good practice, including governance and dispute resolution mechanisms. However, it does not have procedures to guide its contract managers in managing specific provisions of the SMC. Consequently, RMS has not exercised several significant SMC requirements, such as having the contractor account for an efficiency dividend in its pricing at the start of each three-year works period. It also has not done enough to assure itself that the contractor provided performance and financial data are correct. This is important because the data is used to measure performance and calculate contractor payments.  

RMS assessed that it had achieved around 80 per cent of the expected cost benefit in the initial year of the SMC. However, it has not tracked its achievement of benefits since then.

The Stewardship Maintenance Contract

RMS justified adopting the SMC model and included KPIs to drive efficiency and effectiveness

The SMC model includes features that RMS had not previously used for road maintenance contracts. These included adopting stewardship principles and transferring price risk to the contractor over time as the contractor becomes familiar with the assets being maintained.

The SMC model meets RMS’ requirements for flexibility in pricing models, the need for collaboration in asset maintenance planning, promoting innovation and effective performance management.

RMS used many good practices to develop the SMC model, including:

  • preparing a robust business case comparing the SMC model to RMS maintaining the road network itself, as well as assessing whether two other contracting models
    (traditional and alliance) would meet its requirements
  • assessing experiences with similar arrangements in other jurisdictions and identifying elements that worked to get the best outcomes
  • developing a robust performance framework, which included a mix of efficiency and effectiveness KPIs that reflected NSW Government policy and RMS priorities
  • incorporating risk and reward incentives delivered through cost sharing arrangements which change as the contract matures
  • using a contract duration that supports RMS priorities and provides an incentive for better quality outcomes.

RMS uses data provided by the contractor to measure performance and calculate payments to the contractor. The SMC includes a specific sanction if RMS finds that the contractor provided incorrect performance data, but no specific sanction if the contractor provides incorrect financial data. If RMS finds that the contactor provided incorrect performance or financial data, RMS can only recover over-payments which may have been made using the incorrect data.  

To provide a stronger incentive for the contractor to ensure data it provides is accurate, RMS should consider whether to incorporate stronger sanctions when negotiating the commercial reset due in mid-2018 for south and west zones. RMS should also consider this for the new contract for the north zone when the current PSMC contract expires in October 2018.

RMS' contract management approach and benefits realization

RMS can improve the effectiveness of its oversight and management of the SMC

RMS does not have SMC specific contract procedures to guide its contract managers. Consequently, RMS has not exercised several significant SMC requirements, such as having the contractors account for an efficiency dividend in their pricing at the start of each three-year works period. Effective contract management should be supported by contract specific procedures, with explanations of, and allocation of responsibility for, the various interventions that RMS may be required to exercise in the SMC.

Performance and financial reporting under the SMC is based on a mix of RMS and contractor provided data. While there are a range of audits of contractor provided performance and financial data that RMS can conduct each year under the SMC, it does not have a schedule of audits it will conduct and when.  
During the first year of the SMC, RMS commissioned some limited audits of financial data. In the first three years of the SMC, RMS did not conduct any audits of performance data. Had there been SMC specific procedures in place, this would have reduced the risk of RMS not implementing a systematic audit program to give it reasonable assurance on the quality of the data that the contractor has provided. This is important because the data is used to measure performance and calculate contractor payments.

RMS has been aware of data quality issues since 2015. While RMS advised that it commenced addressing some data quality issues in response to a series of reviews conducted in 2015, a recent internal audit report indicates that RMS has not resolved the data quality issues.  

RMS achieved benefits in the first year, but has not tracked benefits since

As part of the business case, RMS agreed to implement a benefits realisation strategy, including a benefits tracking tool. RMS commenced tracking benefits, but did not establish a comparative baseline pre-SMC on non-financial benefits, and has not tracked benefits past year one.

In 2015, a benchmarking study commissioned by RMS found that it had achieved 80 per cent of the expected recurrent cost savings and other benefits, such as improved workplace safety, in the first full year of the SMC. However, there was no clear baseline to measure
non-financial performance. The study was qualified due to gaps in available data. The study also did not reconcile the actual one-off transition costs to the business case estimate.

During the course of the audit, RMS advised that it intends to repeat this type of study to determine whether it has achieved all expected benefits (and their value), and that it would use the results to inform its negotiation with the SMC contractors as part of the commercial reset due in mid-2018.

Roads and Maritime Services is responsible for the State Roads network in the Sydney region

Roads and Maritime Services (RMS) is responsible for the Sydney region State roads network. This includes over 2,800 kilometres of roads and associated road corridor infrastructure such as bridges, tunnels and drainage structures. The network is divided into three geographical areas: south, west and north zones. Prior to November 2013, RMS maintained roads in the Sydney region south and west zones through its Road and Fleet Services unit.  

In 1995, RMS first outsourced road corridor infrastructure maintenance for the north zone through a Performance Specified Maintenance Contract (PSMC). The current 10-year PSMC for the north zone will expire in October 2018. This contract is worth around $35 million per annum.  

NSW Government priorities and road maintenance

Efficient and effective road maintenance contributes to the following NSW Government priorities:

  • improving road travel reliability
  • ensuring on-time running of public transport
  • reducing road fatalities
  • improving government services
  • keeping our environment clean.

The NSW Commission of Audit recommended outsourcing the maintenance of State roads

The NSW Commission of Audit in its Final Report on Government Expenditure (May 2012) recommended contestability as an appropriate strategy to consider for improving road maintenance service delivery for State roads.  

The Commission benchmarked RMS’ road surface quality and cost per lane kilometre against those of Western Australia, Victoria, and Queensland. This showed that New South Wales lagged the other states on both these measures.  

Exhibit 1: Interjurisdictional comparison of road maintenance outcomes 2009–10
  WA VIC QLD NSW
Roads managed (lane kms) 52,659 50,510 71,353 80,348
Estimated spend ($/lane km) 5,000 4,500 6,000 7,000
Road quality measure (%) 99 99 94 91

Source: NSW Commission of Audit Final Report May 2012.

The Commission noted that RMS had conducted two independent reviews to examine the potential for extending road maintenance contestability. The Commission found that there was inadequate and inconclusive benchmarking to establish the efficiency of RMS’ Road and Fleet Services unit when compared to outsourcing. It recommended that RMS bring forward a proposal to conduct a competitive tender for the road maintenance of the Sydney region south zone road network to inform the feasibility of a progressive rollout of road maintenance contestability across other areas of the State. In August 2012, the NSW Government adopted the Commission’s recommendation.

The NSW Government introduced road maintenance contestability through Stewardship Maintenance Contracts

In April 2013, the NSW Government announced that it would introduce road maintenance contestability across the Sydney region, using a Stewardship Maintenance Contract (SMC) model to improve value for money. In doing so, it excluded RMS’ Road and Fleet Services unit from tendering.  

The SMC model is based on the following key commercial and performance principles set by RMS:

  • performance driven by outcomes
  • flexible and adaptable
  • transparent and measurable
  • linking risk to reward
  • continuous improvement
  • criteria for selection of, and transition to, different payment models.

The following key stewardship principles underpin the SMC’s broad set of values, attitudes and behaviours, which are required of the contractor to effectively manage the assets on behalf of RMS:

  • putting RMS’ customers (road users and the general public) first and being responsive to them
  • being responsible and accountable for the outcomes resulting from the management of the assets
  • managing the assets diligently, efficiently and effectively with limited direction from RMS
  • working collaboratively with RMS to deliver services that are tailored to meet RMS’ evolving needs
  • acting with integrity and transparency in performing the services
  • performing the services in the best interests of RMS and asset users.

Other key features of the SMC include:

  • service requirements which describe the scope of the services, and the standards the contractor must meet
  • a commercial framework which defines how payments are structured, how performance assessment will impact on payments and outlines the key commercial principles. SMCs primarily divide payments into two main mechanisms, these being the priced component (or fixed price) and the target cost calculated as follows:
    • fixed price – the contractor is paid a pre-agreed amount for specific services being provided, regardless of the actual costs incurred
    • target cost – RMS and the contractor agree on a target cost for a project, and any cost overruns or underruns are shared between them
  • a performance framework which provides mechanisms for assessing contractor performance. This includes a comprehensive listing of the key result areas (KRAs) and key performance indicators (KPIs) against which RMS measures the contractor’s performance. The framework also outlines the scoring methodology that RMS uses to determine whether the contractor’s bid margin (profit and overheads) is reduced due to less than satisfactory performance or whether a bonus is paid if a threshold performance score is exceeded.

Road maintenance under SMCs for Sydney region south and west zones commenced in November 2013

In November 2013, RMS awarded SMCs to the Leighton Boral Amey consortium, now named Ventia Boral Amey (VBA), for the south zone and the DownerMouchel (DM) consortium for the west zone. The contracts run for seven years with an option for a further three years at RMS’ discretion. In April 2014, full services commenced following a four-month transition period. RMS estimated that the annual cost of these contracts was around $240 million in total. In March 2018, the contract prices are due to be reset by negotiation to reflect the contractors’ experience with, and better information about, the road networks and routine maintenance requirements. 

  1. Roads and Maritime Services should consider whether to incorporate stronger sanctions in the Stewardship Maintenance Contract if the contractor provides incorrect performance or financial data to RMS, when:
     
    1. negotiating the commercial reset for the next works period with the Sydney region south and west zone contractors due in July 2018.
    2. finalising a new SMC contract for the Sydney region north zone, due to commence in October 2018.

Roads and Maritime Services should, by September 2017:

2.  Review its contract management framework for SMCs to ensure that all authorities and accountabilities of
     contract managers are clearly defined, including:

a) accountability and procedures for exercising all operational clauses in the SMC where RMS may opt to, or be required to intervene, or make a decision

b) authority to approve or initiate the interventions RMS is required to, or may, exercise under the SMC

c) the audits that RMS will conduct to systematically validate the performance and financial data that the SMC contractors provide

d) the accountabilities of RMS contract managers to systematically review audits and quality reviews that the SMC contractors must conduct to demonstrate compliance with their service plans

e) the accountabilities of RMS contract managers to check that the monthly and annual reports provided by SMC contractors do not contain errors, omissions or inaccuracies.

3.  Improve its management of benefits realisation by:

a) initiating a further benefits realisation review and record the benefits delivered against those
    estimated following the tender process, including the one-off transition costs

b) identify any benefits, including savings, not yet attained and develop strategies to address any short-falls

c) establish a tool to track the ongoing realisation of benefits.