Actions for Handback of the M4 Tollway

Handback of the M4 Tollway

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management

This audit focuses on the M4 handback. It looks at whether the road will be in good condition when the State gets it back, and whether it will cope with the extra traffic after the toll is removed. These are critical issues for taxpayers and motorists. Taxpayers don’t want to be responsible for a large repair bill and motorists don’t want to be stuck in traffic jams.

To ensure that future private sector partnerships (PPP) deal adequately with handback, we recommend that the Roads and Traffic Authority (RTA):

  • ensure deeds spell out an appropriate inspection and testing program to determine repairs required to bring roads up to a satisfactory condition at handback (p.11)
  • ensure deeds link condition standards and maintenance approaches to changing industry standards and approaches over the life of the PPP (p.11)
  • consider including in deeds a requirement that operators provide a performance bond or similar security over the cost of handback repairs (p.11)
  • review the lessons learnt from the M4 tollway handback and determine whether it should seek to negotiate changes to existing tollway deeds to better deal with handback, by June 2010 (p.11)

 

Parliamentary reference - Report number #193 - released 27 October 2009

Published

Actions for Government Licensing Project

Government Licensing Project

Finance
Information technology
Internal controls and governance
Management and administration
Project management
Shared services and collaboration

The Government Licensing Project (GLP) is standardising and simplifying processes of agencies which issue licences. However, it is currently running over the original anticipated completion date, exceeding the original budget and expected to produce savings less than originally planned.

 

Parliamentary reference - Report number #192 - released 7 October 2009

Published

Actions for Administering Domestic Waterfront Tenancies

Administering Domestic Waterfront Tenancies

Planning
Transport
Management and administration
Service delivery
Shared services and collaboration

The audit’s overall conclusion is that Lands and Maritime are broadly achieving outcomes consistent with the IPART report on administering domestic waterfront tenancies. But a lack of collaboration between the agencies is contributing to poor customer service. Inconsistencies with the IPART report recommendations and operational differences between the two agencies result in different rents and conditions for tenants in the two agencies. The differences are having a significant impact on customer service.

 

Parliamentary reference - Report number #191 - released 23 September 2009

Published

Actions for Helping Aboriginal Defendants through MERIT

Helping Aboriginal Defendants through MERIT

Justice
Health
Management and administration
Service delivery

The Magistrates Early Referral into Treatment program (MERIT) diverts adult defendants with drug problems from the local court into a drug treatment program. Recent studies of MERIT outcomes indicate that MERIT is a highly appropriate intervention program for Aboriginal defendants. It has improved the health of participants, including significant reduction in drug use and significant improvement in mental health. Better justice outcomes include lower rates of imprisonment and reduced rates of reoffending.

Overall, the ability to identify MERIT clients, the eligibility criteria, the location and the ability of MERIT teams to engage with Aboriginal defendants are key factors that limit MERIT’s capacity to treat Aboriginal defendants. MERIT needs to overcome these barriers. If MERIT is to be a truly mainstream program, it must adapt to meet the needs of all who should participate.

 

Parliamentary reference - Report number #189 - released 5 August 2009

Published

Actions for Tackling Cancer with Radiotherapy

Tackling Cancer with Radiotherapy

Health
Internal controls and governance
Management and administration
Procurement
Service delivery
Workforce and capability

Overall radiotherapy services are managed in a reasonably efficient and effective manner. Much is being done to further improve efficiency and effectiveness, and more can be done. While New South Wales has a number of well-established radiotherapy treatment centres, the high capital cost limits their availability in all hospitals. Some patients need to travel long distances and be away from their homes for up to seven weeks. The projected growth in demand for radiotherapy services will further challenge NSW Health and it needs to more clearly demonstrate how it will have the right facilities in the right place at the right time.

 

Parliamentary reference - Report number #188 - released 23 June 2009

Published

Actions for Relocating Agencies to Regional Areas

Relocating Agencies to Regional Areas

Premier and Cabinet
Internal controls and governance
Management and administration
Service delivery
Shared services and collaboration
Workforce and capability

Decisions to relocate government agencies to non-metropolitan areas are not made purely for cost reasons. They can also serve government policy objectives, such as promoting regional economic development.

Regardless of the policy objectives that may exist, I would expect that decisions on individual agency relocations would be based on sound business cases. Those business cases would show how the relocation achieves any relevant government objectives, what costs (or savings) would be involved, logistical considerations such as obtaining appropriate accommodation and staff, and any impacts on levels service to the public.

In my view, the existence of government policy objectives does not remove the need for individual decisions to be made in a transparent, rational and accountable manner. Responsible public servants should provide the appropriate information to government to allow it to judge how best to implement its policies.

 

Parliamentary reference - Report number #147 - released 14 December 2005

Published

Actions for Liverpool to Parramatta Bus Transitway

Liverpool to Parramatta Bus Transitway

Transport
Treasury
Infrastructure
Management and administration
Project management
Service delivery

Several of my recent audits have identified a need to improve our public transport system – both for the benefit of travellers and to assist in achieving better air quality.

Bus Transitways can provide a good public transport solution for lower density population areas, potentially at a relatively low capital cost. This audit examines the transitway running between Liverpool and Parramatta, the first of several planned for Sydney. This audit should contribute to a better understanding of the lessons learnt from this first project, and so to future transitways providing better value for money.

But this audit also raises broader issues.

It highlights the importance of accurately projecting the total cost of major infrastructure projects before governments lock in their decisions. It also highlights the need for sound decision-making processes when government agencies compete with the private sector. The principles and recommendations flowing from these issues are ones I would draw to the attention of all agencies, and to the Government.

 

Parliamentary reference - Report number #146 - released 5 December 2005

Published

Actions for Purchasing Hospital Supplies: Follow-up of 2002 Performance Audit

Purchasing Hospital Supplies: Follow-up of 2002 Performance Audit

Health
Asset valuation
Financial reporting
Management and administration
Procurement
Service delivery

Periodically we review the extent to which agencies have changed their practices as a result of our audits. This gives Parliament and the public an update on the extent of progress made.

In this follow-up audit, we examine changes following our September 2002 report, to assess whether NSW Health has improved its buying of hospital supplies using electronic systems.

NSW Health spends over $1.3 billion on hospital supplies. It is the largest expenditure area after employee costs. Reform of this area has the potential to make significant savings that could be redirected to frontline services.

As part of our series of audits in the area of e-government, our previous audit looked closely at the extent to which technology was being used to deliver potentially major savings in purchasing hospital supplies. This is a key area of so-called “process re-engineering” in the “e” field, and NSW Health provided an ideal case study.

Whilst implementing large-scale e-procurement has many technical aspects, it is not chiefly a technical issue. The key requirements for success reside in effective change management, in particular being clear as to who has the authority to make change decisions and be held accountable.

This audit looks at NSW Health’s successes to date, and its frustrations and challenges in making further progress in this field. Many of the issues raised in this report may provide lessons for any agency that is seeking to drive a significant change program.

 

Parliamentary reference - Report number #145 - released 23 November 2005

Published

Actions for Implementing Asset Management Reforms

Implementing Asset Management Reforms

Justice
Planning
Finance
Treasury
Asset valuation
Financial reporting
Infrastructure
Internal controls and governance
Management and administration
Project management

Hospitals, schools, public housing, roads, bridges, buses and trains are just some of the assets used by government in providing services to citizens.

The NSW Government’s asset base is impressive in size - with a value of around $167 billion and with government plans to spend around $8 billion acquiring or replacing assets in the current year. Another $2 billion is spent each year on maintenance.

Good asset management is very important to government; even a small efficiency gain in this area can provide significant returns. Good practice by those responsible for managing assets can improve reliability, extend asset life, save on maintenance costs and aid in identifying and disposing of unnecessary or non-performing assets.

Improving the NSW public sector’s approach to asset management has been on the reform agenda for at least a decade. Changes in practice have been accelerated more recently by integrating asset management policy with the budget process.

In this audit we examined NSW Treasury’s efforts to improve asset management practices in the public sector and the progress made by 3 agencies - the Department of Corrective Services, NSW Fire Brigades and the Powerhouse Museum - towards better managing their asset portfolios.

This report informs Parliament and the community on progress to date and what more needs to be done to ensure that agencies manage assets effectively and achieve best value.

 

Parliamentary reference - Report number #143 - released 12 October 2005

Published

Actions for In-year Monitoring of the State Budget

In-year Monitoring of the State Budget

Finance
Premier and Cabinet
Compliance
Financial reporting
Internal controls and governance
Management and administration

The annual Budget is one of the most important and visible statements about a government’s financial intentions.

Once a Budget is released, it is important to monitor variations from the projections it contains. This is done for two reasons -

  • first, to ensure that individual agencies are properly managing their budget allocations and that any genuine emerging need for additional funding is met.
  • second, to ensure that any changes to the State’s overall financial position are understood and corrective action is undertaken.

This audit dealt primarily with the second of these objectives.

Budget monitoring involves both agencies and Treasury working together to quickly identify factors that might impact the budget, to clearly understand the implications for their budget position and to take any remedial action needed.

Poor monitoring may reduce the confidence that stakeholders have in the government’s financial management. It may mean that government decisions made in- year or for the following budget (for example on tax measures or spending increases/savings) are based on an incorrect understanding of the State’s true financial position.

I hope that this Report provides some useful insights that will assist in better monitoring.

 