Actions for Effectiveness of SafeWork NSW in exercising its compliance functions

Effectiveness of SafeWork NSW in exercising its compliance functions

Finance
Industry
Health
Compliance
Internal controls and governance
Management and administration
Procurement
Project management
Regulation
Risk

What this report is about 

This report assesses how effectively SafeWork NSW, a part of the Department of Customer Service (DCS), has performed its regulatory compliance functions for work health and safety in New South Wales. 

The report includes a case study examining SafeWork NSW's management of a project to develop a realtime monitoring device for airborne silica in workplaces. 

Findings 

There is limited transparency about SafeWork NSW's effectiveness as a regulator. The limited performance information that is available is either subsumed within DCS reporting (or other sources) and is focused on activity, not outcomes. 

As a work health and safety (WHS) regulator, SafeWork NSW lacks an effective strategic and data-driven approach to respond to emerging WHS risks. 

It was slow to respond to the risk of respirable crystalline silica in manufactured stone. 

SafeWork NSW is constrained by an information management system that is over 20 years old and has passed its effective useful life. 

While it has invested effort into ensuring consistent regulatory decisions, SafeWork NSW needs to maintain a focus on this objective, including by ensuring that there is a comprehensive approach to quality assurance. 

SafeWork NSW's engagement of a commercial partner to develop a real-time silica monitoring device did not comply with key procurement obligations. 

There was ineffective governance and process to address important concerns about the accuracy of the real-time silica monitoring device. 

As such, SafeWork NSW did not adequately manage potential WHS risks. 

Recommendations 

The report recommended that DCS should: 

  • ensure there is an independent investigation into the procurement of the research partner for the real-time silica detector 
  • embed a formal process to review and set its annual regulatory priorities 
  • publish a consolidated performance report 
  • set long-term priorities, including for workforce planning and technology uplift 
  • improve its use of data, and start work to replace its existing complaints handling system 
  • review its risk culture and its risk management framework 
  • review the quality assurance measures that support consistent regulatory decisions

 

Read the PDF report.

Parliamentary reference - Report number #390 - released 27 February 2024
 

Published

Actions for Flood housing response

Flood housing response

Planning
Whole of Government
Community Services
Premier and Cabinet
Internal controls and governance
Management and administration
Procurement
Project management
Risk
Service delivery
Shared services and collaboration

What this report is about

Extreme rainfall across eastern Australia in 2021 and 2022 led to a series of major flood events in New South Wales.

This audit assessed how effectively the NSW Government provided emergency accommodation and temporary housing in response to the early 2022 Northern Rivers and late 2022 Central West flood events.

Responsible agencies included in this audit were the Department of Communities and Justice, NSW Reconstruction Authority, the former Department of Planning and Environment, the Department of Regional NSW and the Premier’s Department.

Findings

The Department of Communities and Justice rapidly provided emergency accommodation to displaced persons immediately following these flood events.

There was no plan in place to guide a temporary housing response and agencies did not have agency-level plans for implementing their responsibilities.

The NSW Government rapidly procured and constructed temporary housing villages. However, the amount of temporary housing provided did not meet the demand.

There is an extensive waitlist for temporary housing and the remaining demand in the Northern Rivers is unlikely to be met. The NSW Reconstruction Authority has not reviewed this list to confirm its accuracy.

Demobilisation plans for the temporary housing villages have been developed, but there are no long-term plans in place for the transition of tenants out of the temporary housing.

Agencies are in the process of evaluating the provision of emergency accommodation and temporary housing.

The findings from the 2022 State-wide lessons process largely relate to response activities.

Audit recommendations

The NSW Reconstruction Authority should:

  • Develop a plan for the provision of temporary housing.
  • Review the temporary housing waitlist.
  • Determine a timeline for demobilising the temporary housing villages.
  • Develop a strategy to manage the transition of people into long-term accommodation.
  • Develop a process for state-wide recovery lessons learned.

All audited agencies should:

  • Finalise evaluations of their role in the provision of emergency accommodation and temporary housing.
  • Develop internal plans for implementing their roles under state-wide plans.

Read the PDF report

Parliamentary reference - Report number #389 - released 22 February 2024

Published

Actions for Driver vehicle system

Driver vehicle system

Transport
Finance
Cyber security
Information technology
Internal controls and governance
Project management
Service delivery

What this report is about

Transport for NSW (TfNSW) uses the Driver vehicle System (DRIVES) to support its regulatory functions. The system covers over 6.2 million driver licences and over seven million vehicle registrations.

DRIVES first went live in 1991 and has been significantly extended and updated since, though is still based around the same core system. The system is at end of life but has become an important service for Service NSW and the NSW Police Force.

DRIVES now includes some services to other parts of government and non-government entities which have little or no connection to transport. There are 141 users of DRIVES in total, including commercial insurers, national regulators, and individual citizens.

This audit assessed whether TfNSW is effectively managing DRIVES and planning to transition it to a modernised system.

Audit findings

TfNSW has not effectively planned the replacement of DRIVES.

It is now working on its third business case for a replacement system but has failed to learn lessons from its past attempts.

In the meantime, TfNSW has not taken a strategic approach to managing DRIVES’ growth.

TfNSW has been slow to reduce the risk of misuse of personal information held in DRIVES. With its delivery partner Service NSW, TfNSW has also been slow to develop and implement automatic monitoring of access.

TfNSW uses recognised processes for managing most aspects of DRIVES, but has not kept the system consistently available for users. TfNSW has lacked accurate service availability information since June 2022, when it changed its technology support provider.

TfNSW needs to significantly prioritise cyber security improvements to DRIVES. TfNSW is seeking to lift DRIVES’ cyber defences, but it will not achieve its stated target safeguard level until December 2025.

Even then, one of the target safeguards will not be achieved in full until DRIVES is modernised.

Audit recommendations

TfNSW should:

  • implement a service management framework including insight into the views of DRIVES users, and ensuring users can influence the service
  • ensure it can accurately and cost effectively calculate when DRIVES is unavailable due to unplanned downtime
  • ensure implementation of a capability to automatically detect anomalous patterns of access to DRIVES
  • ensure that DRIVES has appropriate cyber security and resilience safeguards in place as a matter of priority
  • develop a clear statement of the future role in whole of government service delivery for the system
  • resolve key issues currently faced by the DRIVES replacement program including by:
    • clearly setting out a strategy and design for the replacement
    • preparing a specific business case for replacement.

Read the PDF report

Parliamentary reference - Report number #388 - released 20 February 2024

Published

Actions for Management of the Critical Communications Enhancement Program

Management of the Critical Communications Enhancement Program

Finance
Health
Justice
Whole of Government
Cyber security
Information technology
Infrastructure
Internal controls and governance
Project management
Risk
Service delivery
Shared services and collaboration

What the report is about

Effective radio communications are crucial to NSW's emergency services organisations.

The Critical Communications Enhancement Program (CCEP) aims to deliver an enhanced public safety radio network to serve the five emergency services organisations (ESOs), as well as a range of other users.

This report assesses whether the NSW Telco Authority is effectively managing the CCEP.

What we found

Where it has already been delivered (about 50% of the state), the enhanced network meets most of the requirements of ESOs.

The CCEP will provide additional infrastructure for public safety radio coverage in existing buildings agreed to with ESOs. However, radio coverage inside buildings constructed after the CCEP concludes will be at risk because building and fire regulations do not address the need for in-building public safety radio coverage.

Around 98% of radios connected to the network can be authenticated to protect against cloning, though only 42% are.

The NSW Telco Authority has not settled with ESOs on how call encryption will be used across the network. This creates the risk that radio interoperability between ESOs will not be maximised.

When completed, the public safety radio network will be the only mission critical radio network for ESOs. It is unclear whether governance for the ongoing running of the network will allow ESOs to participate in future network operational decisions.

The current estimated capital cost for the NSW Telco Authority to complete the CCEP is $1.293 billion. This is up from an estimated cost of $400 million in 2016. The estimated capital cost was not publicly disclosed until $1.325 billion was shown in the 2021–22 NSW Budget Papers.

We estimate that the full cost to government, including costs to the ESOs, of implementing the enhanced network is likely to exceed $2 billion.

We made recommendations about

  • The governance of the enhanced Public Safety Network (PSN) to support agency relationships.
  • The need to finalise a Traffic Mitigation Plan for when the network is congested.
  • The need to provide advice to the NSW Government about the regulatory gap for ensuring adequate network reach in future buildings.
  • The need to clarify how encryption and interoperability will work on the enhanced network.
  • The need for the NSW Telco Authority to comply with its policy on Infrastructure Capacity Reservation.
  • Expediting measures to protect against the risk of cloning by unauthenticated radios.

Public safety radio networks are critical for operational communications among Emergency Services Organisations (ESOs), which in New South Wales include:

  • NSW Ambulance
  • Fire and Rescue NSW
  • NSW Police Force
  • NSW Rural Fire Service
  • NSW State Emergency Service.1

Since 1993, these five ESOs have had access to a NSW Government owned and operated radio communications network, the Public Safety Network (PSN), to support their operational communications. Around 60 to 70 other entities also have access to this network, including other NSW government entities, Commonwealth government entities, local councils, community organisations, and utility companies.

Pursuant to the Government Telecommunications Act 2018 ('the Act'), the New South Wales Government Telecommunications Authority ('NSW Telco Authority') is responsible for the establishment, control, management, maintenance and operation of the PSN.2

Separate to the PSN, all ESOs and other government entities have historically maintained their own radio communication capabilities and networks. Accordingly, the PSN has been a supplementary source of operational radio communications for these entities.

These other radio networks maintained by ESOs and other entities are of varying size and capability, with many ageing and nearing their end-of-life. There was generally little or no interoperability between networks, infrastructure was often co-located and duplicative, and there were large gaps in geographic coverage.

In 2016, the NSW Telco Authority received dedicated NSW Government funding to commence the Critical Communications Enhancement Program (CCEP).

According to NSW Telco Authority's 2021–22 annual report, the CCEP is a transformation program for operational communications for NSW government agencies. The CCEP '…aims to deliver greater access to public safety standard radio communications for the State’s first responders and essential service agencies'. The objective of CCEP is to consolidate the large number of separate radio networks that are owned and operated by various NSW government entities and to enhance the state’s existing shared PSN. The program also aims to deliver increased PSN coverage throughout New South Wales.

The former NSW Government intended that as the enhanced PSN was progressively rolled-out across NSW, ESOs would migrate their radio communications to the enhanced network, before closing and decommissioning their own networks.

About this Audit

This audit assessed whether the CCEP is being effectively managed by the NSW Telco Authority to deliver an enhanced PSN that meets ESOs' requirements for operational communications.

We addressed the audit objective by answering the following two questions:

  1. Have agreed ESO user requirements for the enhanced PSN been met under day-to-day and emergency operational conditions?
  2. Has there been adequate transparency to the NSW Government and other stakeholders regarding whole-of-government costs related to the CCEP?

In answering the first question, we also considered how the agreed user requirements were determined. This included whether they were supported by evidence, whether they were sufficient to meet the intent of the CCEP (including in considering any role for new or alternative technologies), and whether they met any relevant technical standards and compliance obligations (including for cyber security resilience).

While other NSW government agencies and entities use the PSN, we focused on the experience of the five primary ESOs because these will be the largest users of the enhanced PSN.

Both the cost and time required to complete the CCEP roll-out have increased since 2016. While it was originally intended to be completed in 2020, this is now forecast to be 2027. Infrastructure NSW has previously assessed the reasons for the increases in time and cost. A summary of the findings made by Infrastructure NSW is presented in Chapter 1 of this report. Accordingly, as these matters had already been assessed, we did not re-examine them in this performance audit.

The auditee for this performance audit is the NSW Telco Authority, which is a statutory authority within the Department of Customer Service portfolio.

In addition to being responsible for the operation of the PSN, section 5 of the Act also prescribes that the NSW Telco Authority is:

  • to identify, develop and deliver upgrades and enhancements to the government telecommunications network to improve operational communications for government sector agencies
  • to develop policies, standards and guidelines for operational communications using telecommunications networks.

The NSW Telco Authority Advisory Board is established under section 10 of the Act. The role of the board is to advise the NSW Telco Authority and the minister on any matter relating to the telecommunications requirements of government sector agencies and on any other matter relating to the functions of the Authority. As of 2 June 2023, the responsible minister is the Minister for Customer Service and Digital Government.

The five identified ESOs are critical stakeholders of the CCEP and therefore they were consulted during this audit. However, the ESOs were not auditees for this performance audit.

Conclusion

In areas of New South Wales where the enhanced Public Safety Network has been implemented under the Critical Communications Enhancement Program, the NSW Telco Authority has delivered a radio network that meets most of the agreed requirements of Emergency Services Organisations for routine and emergency operations.
In April 2023, the enhanced Public Safety Network (PSN) was approximately 50% completed. In areas where it is used by Emergency Services Organisations (ESOs), the PSN generally meets agreed user requirements. This is demonstrated through extensive performance monitoring and reporting, which shows that agreed performance standards are generally achieved. Reviews by the NSW Government and the NSW Telco Authority found that the PSN performed effectively during major flood events in 2021 and 2022.

Where it is completed, PSN coverage is generally equal to or better than each ESO's individual pre-existing coverage. The NSW Telco Authority has a dedicated work program to address localised coverage gaps (or 'blackspots') in those areas where coverage has otherwise been substantively delivered. Available call capacity on the network far exceeds demand in everyday use. Any operational issues that may occur with the PSN are transparent to ESOs in real time.

The NSW Telco Authority consulted extensively with ESOs on requirements for the enhanced PSN, with relatively few ESO requirements not being included in the specifications for the enhanced PSN. Lessons from previous events, including the 2019–20 summer bushfires, have informed the design and implementation of the enhanced PSN (such as the need to ensure adequate backup power supply to inaccessible sites). The network is based on the Project 25 technical standards for mission-critical radio communications, which is widely-accepted in the public safety radio community throughout Australia and internationally.

There is no mechanism to ensure adequate radio coverage within new building infrastructure after the CCEP concludes, but the NSW Telco Authority and ESOs have agreed an approach to prioritise existing in-building sites for coverage for the duration of the CCEP.
The extent to which the PSN works within buildings and other built structures (such as railway tunnels) is of crucial importance to ESOs, especially the NSW Police Force, NSW Ambulance, and Fire and Rescue NSW. This is because a large proportion of their operational communications occurs within buildings.

There is no mechanism to ensure the adequacy of future in-building coverage for the PSN in new or refurbished buildings after the CCEP concludes. Planning, building, and fire regulations are silent on this issue. We note there are examples in the United States of how in-building coverage for public safety radio networks can be incorporated into building or fire safety codes.

In regard to existing buildings, it is not possible to know whether a building requires its own in-building PSN infrastructure until nearby outside radio sites, including towers and antennae, have been commissioned into the network. Only then can it be determined whether their radio transmissions are capable of penetrating inside nearby buildings. Accordingly, much of this work for in-building coverage cannot be done until outside radio sites are finished and operating.

In March 2023, the NSW Telco Authority and ESOs agreed on a list of 906 mandatory and 7,086

non-mandatory sites for in-building PSN coverage. Most of these sites will likely be able to receive radio coverage via external antennae and towers, however this cannot be confirmed until those nearby external PSN sites are completed. The parties also agreed on an approach to prioritising those sites where coverage is needed but not provided by antennae and towers. Available funding will likely only extend to ensuring coverage in sites deemed mandatory, which is nonetheless expected to meet the overall benchmark of achieving 'same or better' coverage than what ESOs had previously.

There is a risk that radio interoperability between ESOs will not be maximised because the NSW Telco Authority has not settled with ESOs how encryption will be used across the enhanced PSN.
End-to-end encryption of radio transmissions is a security feature that prevents radio transmissions being intercepted or listened to by people who are not meant to. The ability of the PSN to provide end-to-end encryption of operational communications is of critical importance to the two largest prospective users of the PSN: the NSW Police Force and NSW Ambulance. Given that encryption excludes other parties that do not have the requisite encryption keys, its use creates an obstacle to achieving a key intended benefit of the CCEP, that is a more interoperable PSN, where first responders are better able to communicate with other ESOs.

Further planning and collaboration between PSN participants are necessary to consider how these dual benefits can be achieved, including in what operational circumstances encrypted interoperability is necessary or appropriate.

The capital cost to the NSW Telco Authority of the CCEP, originally estimated at $400 million in 2016, was not made public until the 2021–22 NSW Budget disclosed an estimate of $1.325 billon.
The estimated capital cost to complete all stages of the CCEP increased over time. This increasing cost was progressively disclosed to the NSW Government through Cabinet processes between 2015–16 and 2021–22.

In 2016, the full capital cost to the NSW Telco Authority of completing the CCEP was estimated to be $400 million. This estimated cost was not publicly disclosed, nor were subsequent increases, until the cost of $1.325 billion was publicly disclosed in the 2021–22 NSW Budget (revised down in the 2022–23 NSW Budget to $1.293 billion).

There has been no transparency about the whole-of-government cost of implementing the enhanced PSN through the CCEP.
In addition to the capital costs incurred directly by the NSW Telco Authority for the CCEP, ESOs have incurred costs to maintain their own networks due to the delay in implementing the CCEP. The ESOs will continue to incur these costs until they are able to fully migrate to the enhanced PSN, which is expected to be in 2027. These costs have not been tracked or reported as part of transparently accounting for the whole-of-government cost of the enhanced PSN. This is despite Infrastructure NSW in 2019 recommending to the NSW Telco Authority that it conduct a stocktake of such costs so that a whole-of-government cost impact is available to the NSW Government.

1 The definition of 'emergency services organisation' is set out in the State Emergency and Rescue Management Act 1989 (NSW). In addition to the five ESOs discussed in this report, the definition also includes: Surf Life Saving New South Wales; New South Wales Volunteer Rescue Association Inc; Volunteer Marine Rescue NSW; an agency that manages or controls an accredited rescue unit; and a non-government agency that is prescribed by the regulations for the purposes of this definition.
2 Section 15(1) of the Government Telecommunications Act 2018 (NSW).

The NSW Telco Authority established and tracked its own costs for the CCEP

Over the course of the program from 2016, the NSW Telco Authority prepared a series of business cases and program reviews that estimated its cost of implementing the program in full, including those shown in Exhibit 6 below.

Exhibit 6: Estimated costs to fully implement the CCEP
Source Capital cost ($ million) Operating cost
($ million)
Completion date
March 2016 business case 400 37.3 2020
November 2017 internal review 476.7 41.7 2022
March 2020 business case 950–1,050 -- 2025
October 2020 business case 1,263.1 56.1 2026

Source: CCEP business cases as identified.

In response to the 2016 CCEP business case, the then NSW Government approved the NSW Telco Authority implementing the CCEP in full, with funding provided in stages. The NSW Telco Authority tracked its costs against approved funding, with monthly reports provided to the multi-agency Program Steering Committee

Throughout the program, the NSW Government was informed of increasing costs being incurred by the NSW Telco Authority for the CCEP

The various business cases, program updates, and program reviews prepared by the NSW Telco Authority were provided to the NSW Government through the required Cabinet process when seeking approval for the program proceeding and requests for both capital and operational funding. These provided clear indication of the changing overall cost of the CCEP to the NSW Telco Authority, as well as the delays that were being experienced.

There was no transparency to the Parliament and community about changes in the capital cost of the CCEP until the 2021–22 NSW Budget

As the business cases for the CCEP were not publicly available, the only sources of information about capital cost were NSW Budget papers and media releases. The information provided in the annual Budget papers prior to the 2021–22 NSW Budget provided no visibility of the estimated full capital cost to complete all stages of the CCEP. As shown in Exhibit 7 below, this information was fragmented and complex.

Media releases about the progress of the CCEP did not provide the estimated total cost to the NSW Telco Authority of $1.325 billion to complete all stages of the CCEP until June 2021. Prior to this date, media releases only provided funding for the initial stages of the program or for the stages subject to a funding announcement.

Even during the September 2019 and March 2020 Parliamentary Estimate Committee hearings where the costings and delays to the CCEP were raised, the estimated full cost of the CCEP was not revealed.

Exhibit 7: CCEP funding in NSW Budget papers from 2015–16 to 2022–23
Financial year Type of major work Description of expenditure Forecast estimate to complete ($ million) Estimated duration
2015–16 New work Infrastructure Rationalisation Program: Planning and Pilot 18.3 2015–16
2016–17 Work in progress CCEP Planning and Pilot 18.3 2015–17
New work CCEP 45 2016–17
2017–18 New work CCEP 190.75 2017–21
2018–19 Work in progress CCEP North Coast and State-wide Detailed Design 190.75 2017–21
New work CCEP Greater Metropolitan Area 236 2018–22
2019–20 Work in progress CCEP 426.9 2018–22
2020–21 Work in progress CCEP 664.8 2018–22
2021–22 Work in progress CCEP 1,325 2018–26
2022–23 Work in progress CCEP 1,292.8 2018–26

Source: NSW Treasury, Annual State Budget Papers.

The original business case for the CCEP included estimated ESO costs, though these costs were not tracked throughout the program

Estimates for ESO costs for operating and maintaining their own radio networks over the four years from 2016–17 were included in the original March 2016 business case. They included $75.2 million for capital expenditure and $95 million for one-off operating costs. These costs, as well as costs incurred by ESOs due to the delay in the program, were not subsequently tracked by the NSW Telco Authority.

In January 2017, Infrastructure NSW reviewed the CCEP business case of March 2016. In this review, Infrastructure NSW recommended that the NSW Telco Authority identify combined and apportioned costs and cashflow for all ESOs over the CCEP funding period reflecting all associated costs to deliver the CCEP. These to include additional incidental capital costs accruing to ESOs, transition and migration to the new network and the cost (capital and operational) of maintaining existing networks. This recommendation was implemented in the November 2017 program review, with ESO capital costs estimated as $183 million.

In 2019, Infrastructure NSW conducted a Deep Dive Review on the progress of the CCEP. In this review, Infrastructure NSW made what it described as a 'critical recommendation' that the NSW Telco Authority:

…coordinate a stocktake of the costs of operational bridging solutions implemented by PSAs [ESOs] as a result of the 18-month delay, so that a whole-of-government cost impact is available to the NSW Government.  

It should be noted that the delay to CCEP completion now is seven years and that further ‘operational bridging solutions’ have been needed by the ESOs.

'Stay Safe and Keep Operational' costs incurred by ESOs will be significantly higher than originally estimated

Stay Safe and Keep Operational (SSKO) funding was established to provide funding to ESOs to maintain their legacy networks while the CCEP was refreshing and enhancing the PSN. This recognised that much of the network infrastructure relied on by ESOs had reached – or was reaching – obsolescence and would either require extensive maintenance or replacement before the PSN was available for ESOs to migrate to it. ESOs may apply to NSW Treasury for SSKO funding, with their specific proposals being reviewed (and endorsed, where appropriate) by the NSW Telco Authority. Accordingly, SSKO expenditure does not fall within the CCEP budget allocation.

As shown in the table below, extracted from the March 2016 CCEP business case, the total expected cost for SSKO purposes over the course of the CCEP was originally $40 million, assuming the enhanced PSN would be fully available by 2020.

Exhibit 8: Stay Safe and Keep Operational forecast costs, 2017 to 2020
Year 2017 2018 2019 2020 Total
SSKO forecast ($ million) 12.5 15 10 2.5 40

Source: March 2016 CCEP business case.

In October 2022, the expected completion date for the CCEP was re-baselined to August 2027. Accordingly, ESOs will be required to continue to maintain their radio networks using legacy equipment for seven years longer than the original 2020 forecast. This will likely become progressively more expensive and require additional SSKO funding. For example, NSW Telco Authority endorsed SSKO bids for 2022–23 exceeded $35 million for that year alone.

Compared to the original forecast made in the March 2016 CCEP business case of $40 million, we found ESOs had estimated SSKO spending to 2027 will be $292.5 million.

A refresh of paging network used by ESOs and the decommissioning of redundant sites were both removed from the original 2016 scope of the CCEP

Paging

A paging network is considered an important user requirement by the Fire and Rescue NSW, NSW Rural Fire Service, and NSW State Emergency Service. The 2016 CCEP business case included a paging network refresh within the program scope of works. This was reiterated in the November 2017 internal review of the program. These documents did not estimate a cost for this refresh. The March 2020 and October 2020 business cases excluded paging from the program scope. The audit is unable to identify when, why or by whom the decision was made to remove paging from the program scope, something that was also not well communicated to the affected ESOs.

In 2021, after representations from the affected ESOs, the NSW Telco Authority prepared a separate business case for a refresh of the paging network at an estimated capital cost of $60.31 million. This program was subsequently approved by the NSW Government and included in the 2022–23 NSW Budget.

In determining an estimated full whole-of-government cost of delivering the enhanced PSN, we have included the budgeted cost of the paging network refresh on the basis that:

  • it was expressly included in the original approved March 2016 business case
  • the capability is deemed essential to the needs of three ESOs.

Decommissioning costs

The 2016 CCEP business case included cost estimates for decommissioning surplus sites (whether ‘old’ GRN sites or sites belonging to ESOs’ own networks). These estimates were provided for both the NSW Telco Authority ($38 million) and for the ESOs ($55 million). However, while these estimates were described, they were not included as part of the NSW Telco Authority's estimated capital cost ($400 million) or (more relevantly) operating cost ($37.3 million) for the CCEP. This is despite decommissioning being included as one of eight planned activities for the rollout of the program.

In the October 2020 business case, an estimate of $201 million was included for decommissioning agency networks based on a model whereby:

  • funding would be coordinated by the NSW Telco Authority
  • scheduling and reporting through an inter-agency working group and
  • where appropriate, agencies would be appointed as the most appropriate decommissioning party.

This estimated cost is not included in the CCEP budget.

In determining an estimated full whole-of-government cost of the enhanced PSN, we have included the estimated cost of decommissioning on the basis that:

  • decommissioning was included in the 2016 CCEP business case as one of eight 'planned activities for the rollout of the program'
  • effective decommissioning of surplus sites and equipment (including as described in the business case as incorporating asset decommissioning, asset re-use, and site make-good) is an inherent part of the program management for an enhanced PSN
  • costs incurred in decommissioning are entirely a consequence of the CCEP program.

The estimated minimum cost of building an enhanced PSN consistent with the original proposal is over $2 billion

We have derived two estimated minimum whole-of-government costs for delivering an enhanced PSN. These are:

  • $2.04 billion when calculated from NSW Telco Authority data – shown as estimate A in Exhibit 9 below.
  • $2.26 billion when calculated from ESO supplied data – shown as estimate B in Exhibit 9.

Both totals include:

  • budgeted amounts for both CCEP capital expenditure ($1,292.8 million) and operating expenditure ($139 million)
  • the NSW Telco Authority's 2020 estimated cost for decommissioning ($201 million)
  • the NSW Telco Authority's approved funding for paging refresh ($60.3 million).

The two estimated totals primarily vary around the capital expenditure of ESOs (particularly SSKO funding). To determine these costs, we used ESO provided actual SSKO costs to date, as well as their estimates for maintaining their legacy radio networks through to 2027.

The equivalent cost estimates from the NSW Telco Authority were sourced from the November 2017 internal review and the October 2020 business case for CCEP. It should be noted that the amounts for both estimates are not audited, or verified, but do provide an indication of how whole-of-government costs have grown over the course of the program.

The increase in and reasons for the increase in total CCEP costs (capital and one-off operating) incurred or forecast by the NSW Telco Authority (from $437.3 million in 2016 to $1,431.8 million in 2022) have been provided to the NSW Government through various business cases and reviews prepared by the NSW Telco Authority, as well as by reviews conducted by Infrastructure NSW as part of its project assurance responsibilities.

However, the growth in ESO costs and other consequential costs, such as paging and decommissioning, from around $263 million in the 2016 CCEP business case to between $600 million and $800 million, has to a large degree remained invisible and unexplained to the NSW Government and other stakeholders

Exhibit 9: Estimated whole-of-government costs of the enhanced PSN
  Estimated whole-of-government cost, over time
Cost type 20161 20172 20203 2023–Estimate A4 2023–Estimate B5
$ million $ million $ million $ million $ million
CCEP capital expenditure 400a 476.7b 1,263.1c 1,292.8d 1,292.8d
CCEP operating expenditure 37.3a 41.7b 41.5e 139d 139d
CCEP total 437.3 518.4 1,304.6 1,431.8 1,431.8
ESO capital expenditure 75.2a,f 183b,e 75.4e 258.4g 292.5
ESO one-off operating expenditure 93a n.a.l 86.5e 86.5h 273
ESO total 168.2 183 161.9 344.9 565.5
Paging n.a.i n.a.i n.a.j 60.3k 60.3k
Decommissioning 93 n.a.l 201.0 201h 201
Paging and decommissioning total 93 n.a. 201 261.3 261.3
Whole-of-government total 698.5 701.4 1,667.5 2,038 2,258.6

Notes:
  1. Financial year 2016 to Financial year 2020.
  2. Financial year 2016 to Financial year 2021.
  3. Financial year 2016 to Financial year 2025.
  4. Financial year 2016 to Financial year 2026.
  5. Financial year 2022 to Financial year 2025.
  6. Stay Safe and Keep Operational (SSKO) costs plus terminals costs.
  7. November 2017 internal review and October 2020 Business case.
  8. October 2020 Business case.
  9. Included in CCEP capital expenditure at that time.
  10. By 2020, a refresh of the paging network had been removed from the CCEP scope.
  11. A separate business case for a refresh of the paging network was approved by government in 2022.
  12. Figure not included in the source document.
Sources:
  1. March 2016 CCEP business case.
  2. November 2017 Internal Review conducted by the NSW Telco Authority.
  3. October 2020 CCEP business case.
  4. Derived from business cases, with ESO costs drawn from NSW Telco Authority data.
  5. Derived from business cases, with ESO costs based on data provided to the Audit Office of New South Wales by each of the five ESOs.

Appendix one – Response from agency

Appendix two – Trunked public safety radio networks

Appendix three – About the audit

Appendix four – Performance auditing

 

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #383 - released 23 June 2023

 

Published

Actions for Government advertising 2021–22

Government advertising 2021–22

Finance
Education
Whole of Government
Compliance
Management and administration
Procurement

What the report is about

The Government Advertising Act 2011 requires the Auditor-General to undertake a performance audit on government advertising activities each financial year.

This audit examined whether TAFE NSW's annual advertising campaign in 2021–22:

  1. was carried out effectively, economically, and efficiently
  2. complied with regulatory requirements and the Government Advertising Guidelines.

What we found

TAFE NSW complied with Section 6 of the Act, prohibiting political content.

It also complied with most other advertising requirements.
 
An important exception was that the Managing Director certified that the campaign complied with regulatory requirements and was an efficient and cost-effective means of achieving its public purpose, before a cost-benefit analysis (CBA) was completed.

We have found issues with agencies complying with CBA requirements in previous government advertising audits. This includes the failure to complete them before signing compliance certificates.

The policy owner, the Department of Customer Service (DCS), does not consider oversight of CBAs to be within the scope of their peer review process.  

TAFE NSW evaluated this advertising campaign by surveying a population significantly broader than the target audience. As such, survey results may not accurately reflect the views of the intended audience.

What we recommended

By 30 June 2023, TAFE NSW should:

  1. implement processes that ensure:
    1. CBAs are completed before the launch of campaigns over $1 million
    2. compliance certificates are completed only after all regulatory requirements are met
  2. consider adding to its current evaluation methods by surveying a population which closely reflects the age profile of its intended target audience.

By June 2023, DCS should:

  1. improve whole‑of‑government reporting and monitoring processes to provide the NSW Government with a central view of compliance, including the completion of CBAs by agencies.

The Government Advertising Act 2011 (the Act) sets out requirements that must be followed by a government agency when it carries out a government advertising campaign. The requirements include an explicit prohibition on political advertising, as well as a need to complete a peer review and cost-benefit analysis before the campaign commences. The accompanying Government Advertising Regulation 2018 (the Regulation) and Government Advertising Guidelines (the Guidelines) address further matters of detail.

The Act also requires the Auditor-General to conduct a performance audit on the activities of one or more government agencies in relation to government advertising campaigns in each financial year. The performance audit must assess whether a government agency (or agencies) has carried out activities in relation to government advertising campaigns in an effective, economical and efficient manner. It also assesses compliance with the Act, the Regulation, other laws and the Guidelines.

This audit examined TAFE NSW's advertising campaign for the 2021–22 financial year. TAFE NSW is the NSW Government's public provider of vocational education and training. TAFE NSW carries out an advertising campaign every year. In 2021–22, it spent $15.16 million on developing and implementing advertising. TAFE NSW used channels such as television, radio, internet and social media, press, and out of home advertising in public settings such as bus stops. The advertising aimed to increase the percentage of people considering TAFE NSW for training or education, grow the percentage of people who consider TAFE NSW to be the preferred education provider in NSW, and maintain the proportion of people who are aware of TAFE NSW more generally.

There are a range of private service providers helping to deliver vocational education and training in NSW.

Conclusion

TAFE NSW’s advertising campaign for 2021–22 was for an allowed purpose under the Act and did not include political advertising. TAFE NSW complied with most of the requirements set out in the Act, the Regulation, and the Guidelines, but it failed to complete a cost-benefit analysis for the campaign or provide sufficient support for the compliance certificate signed by TAFE NSW's Managing Director.

TAFE NSW complied with the requirement to complete a peer review of its campaign, but it did not meet the requirement to complete a cost-benefit analysis, either before it launched the campaign or during its implementation throughout 2021–22. Some of TAFE NSW's advertising did not meet the requirement for statements to be clearly supported by evidence.

The Act requires the head of an agency to sign a compliance certificate stating that, among other things, the campaign complies with the Act, the Regulation, and the Guidelines, and that the campaign is an efficient and cost-effective means of achieving the public purpose. TAFE NSW's Managing Director signed a compliance certificate in May 2021. However, TAFE NSW had not prepared a cost-benefit analysis as required under the Act and therefore TAFE NSW's Managing Director could not validly sign the compliance certificate. TAFE NSW did not subsequently complete a cost-benefit analysis during the campaign.

The campaign achieved many of its objectives and other performance measures and is likely to have been impactful. It is also likely that TAFE NSW’s advertising campaign in 2021–22 represented economical, efficient, and effective spend. However, the lack of a cost-benefit analysis meant that this could not be confidently demonstrated by TAFE NSW.

TAFE NSW used internal resources to create its advertising content, such as videos, radio scripts and press advertising, and relied upon a specialist partner to arrange and place its media in the appropriate advertising channel. TAFE NSW also adjusted the advertising campaign in response to performance data and in response to changes in the educational and advertising marketplaces.

TAFE NSW evaluated the impact of its advertising and tracked its brand performance using a survey which reflected the New South Wales general population aged between 16 and 60. However, this evaluation did not match TAFE NSW's advertising spend as TAFE NSW directed significantly more of its campaign budget to influencing younger people in this cohort.

This part of the report sets out key aspects of TAFE NSW's compliance with the government advertising regulatory framework. It considers whether TAFE NSW complied with the:

  • Government Advertising Act 2011
  • Government Advertising Regulation 2018
  • NSW Government Advertising Guidelines 2012 and other relevant policy.

This part of the report considers whether TAFE NSW's advertising program for 2021–22 was carried out in an effective, efficient, and economical manner.

Appendix one – Responses from agencies

Appendix two – About the campaign

Appendix three – About the audit

Appendix four – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #377 - released 28 February 2023

Published

Actions for Government's acquisition of private property: Sydney Metro project

Government's acquisition of private property: Sydney Metro project

Transport
Planning
Whole of Government
Compliance
Infrastructure
Internal controls and governance
Project management
Risk

What the report is about

Sydney Metro is Australia’s largest public transport project. It requires the acquisition of many private properties, including residential and business properties.

This audit assessed the effectiveness of the acquisition of private properties for the Sydney Metro project. The audited agencies were Sydney Metro, the Department of Planning and Environment (Valuer General NSW) and Transport for NSW (the Centre for Property Acquisition).

The audit assessed agencies against the framework for property acquisitions in New South Wales. It did not re-perform the valuations done for individual properties that were acquired by Sydney Metro.

What we found

Acquisitions of private property for the Sydney Metro project were mostly effective in the sample of acquisitions we assessed. We found Sydney Metro:

  • complied with legislative and policy requirements for compensation and communication with people subject to property acquisitions
  • kept accurate records of its acquisitions and applied probity controls consistently
  • did not complete detailed plans or negotiation strategies for the high-risk and high-value acquisitions we reviewed
  • did not comply with legislative timelines for most compulsory acquisitions because of delays in receiving the required information from the Valuer General in these cases.

The Centre for Property Acquisition has overseen the implementation of reforms to residential acquisition processes, but its assessment of the effectiveness of these reforms has not been comprehensive.

What we recommended

The audit made four recommendations to the audited agencies to improve:

  • plans and strategies for the acquisition of high-risk and high-value properties
  • timeliness of issuing compensation determinations for compulsory acquisitions
  • data quality on the experience of people subject to property acquisitions.

The NSW Government has the power to acquire land that is owned or leased by individuals or businesses, if it is needed for a public purpose. The power arises from the Land Acquisition (Just Terms Compensation) Act 1991 (the Just Terms Act). Government agencies that have the power to compulsorily acquire private property are referred to as ‘acquiring authorities’. People who are subject to acquisitions are referred to as ‘affected parties’ and include property owners (business or residential), businesses with a commercial lease on a property, or individuals with residential tenancy leases. In recent years, the vast majority of acquisitions by the NSW Government have been for public transport or road projects.

Sydney Metro is a NSW Government agency with responsibility for building the Sydney Metro railway project. Sydney Metro is Australia’s largest public transport project. The project requires the acquisition of a large number of private properties. Sydney Metro has been one of the largest acquirers of private property in recent years, completing over 500 acquisitions between 2020 and mid-2022, with a total acquisition value of over $2 billion. Other agencies and statutory officers involved in the acquisition of property for the Sydney Metro project include:

  • the Department of Planning and Environment (DPE), which supports the minister responsible for the Just Terms Act. DPE also provides staff to the Valuer General of NSW
  • the Valuer General of NSW, an independent statutory officer that determines compensation in cases where the acquiring authority and the affected party cannot agree on compensation for property that has been acquired
  • Transport for NSW, which includes the Centre for Property Acquisition (CPA). The CPA does not have a direct role in acquiring properties, but its responsibilities include developing guidance for acquiring agencies and monitoring and reporting on their activities.

About this audit

The objective of this audit was to assess the effectiveness of acquisitions of private properties for Sydney Metro projects. The audit assessed agencies against the legislative and policy requirements in place for government acquisitions of private property in New South Wales. In line with the Audit Office's legislative mandate, the audit does not comment on the merits of the policy objectives reflected in the Just Terms Act.

The audit examined a sample of 20 property acquisitions. This was not a statistically representative sample. While our report provides comments on Sydney Metro’s overall acquisition processes, it does not provide assurance regarding the acquisitions that were not examined for this audit.

The audit did not re-perform the valuations done for individual properties that were acquired by Sydney Metro. Affected parties who disagree with the valuation of their property have the right to seek independent assessment of this via the Valuer General and the Land and Environment Court.

Conclusion

Acquisitions of property for the Sydney Metro project were mostly effective in the sample of acquisitions we assessed. Sydney Metro followed requirements for communication with affected parties. Compensation processes were conducted in compliance with legislative requirements, but compensation determinations for compulsory acquisitions were not completed within legislated time frames due to delays in receiving these from the Valuer General. Governance and probity processes were followed consistently, with some relatively minor exceptions. 

Sydney Metro has detailed guidelines for acquisitions that are based on relevant legislation and government policy. In the 20 acquisitions we assessed for this audit, these procedures were followed consistently. This included adhering to minimum timelines for negotiation periods, engaging independent valuers and other experts when needed, and complying with governance and probity processes.

Sydney Metro staff followed requirements for communication and support for residential acquisitions by assigning ‘personal managers’ and providing additional support to affected parties when needed. The Centre for Property Acquisition (CPA) has overseen reforms to the residential property acquisition process in recent years. These reforms include the introduction of the NSW Property Acquisition Standards and the use of personal managers, in addition to the existing acquisition managers, for residential acquisitions. However, the CPA has not assessed the impact of these changes on the experiences on people affected by property acquisitions.

Sydney Metro did not comply with the legislative requirement to provide a formal compensation notice to the affected party within 45 days of a compulsory acquisition starting in any of the eight relevant acquisitions in our sample. This was because Sydney Metro must wait for the Valuer General to complete a compensation determination before Sydney Metro can send the compensation notice, and the Valuer General did not do this within 45 days. We acknowledge that Sydney Metro does not have full control over this process, and that it has taken steps to mitigate the impact of delays on affected parties. 

This chapter presents our findings on Sydney Metro's acquisition of industrial and commercial properties. Industrial properties include construction businesses and manufacturing facilities. Commercial properties were mostly properties such as shopping centres and office towers. Many of these acquisitions involve businesses and properties that are relatively complex and have high values. This means the valuation process can require multiple experts and can be lengthy and contested. Adherence to governance and probity requirements is important for these acquisitions in order to demonstrate that the acquiring authority has achieved value for money.

This chapter presents our findings on Sydney Metro's acquisition of residential properties, which include apartments and houses, and small business leases, which mostly affected businesses in small shopping centres or arcades. Most of these acquisitions were lower value compared to industrial and commercial property acquisitions and did not require as much expert advice on complex technical issues. However, residential property acquisitions can be personally distressing for the affected parties and require staff from the acquiring authority to provide support and show empathy while ensuring legislative compliance and value for money.

Appendix one – Responses from agencies

Appendix two – About the audit 

Appendix three – Performance auditing 

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #375 - released 9 February 2023

Published

Actions for Design and implementation of the Transport Asset Holding Entity

Design and implementation of the Transport Asset Holding Entity

Transport
Treasury
Asset valuation
Financial reporting
Infrastructure
Procurement
Risk
Service delivery

What the report is about

The Transport Asset Holding Entity (TAHE) is the State's custodian of rail assets. It is a state owned corporation and commenced operating on 1 July 2020.

This audit assessed the effectiveness of NSW Government agencies' design and implementation of TAHE. We audited TAHE, Transport for NSW (TfNSW) and NSW Treasury.

Separate and related audits on TAHE are reported in 'State Finances 2022', 'State Finances 2021' and 'Transport and Infrastructure 2022' reports.

What we found

The design and implementation of TAHE, which spanned seven years, was not effective.

The process was not cohesive or transparent. It delivered an outcome that is unnecessarily complex in order to support an accounting treatment to meet the NSW Government's short-term Budget objectives, while creating an obligation for future governments.

The benefits of TAHE were claimed in the 2015–16 NSW Budget before the enabling legislation was passed by Parliament in 2017. This committed the agencies to implement a solution that justified the 2015–16 Budget impacts, regardless of any challenges that arose.

Rail safety arrangements were a priority throughout TAHE's design and implementation, and risks were raised and addressed.

Agencies relied heavily on consultants on matters related to the creation of TAHE, but failed to effectively manage these engagements. Agencies failed to ensure that consultancies delivered independent advice as an input to decision-making. A small number of firms were used repeatedly to provide advice on the same topic. The final cost of TAHE-related consultancies was $22.6 million compared to the initial estimated cost of $12.9 million.

What we recommended

We recommended that the audited agencies should:

  • improve accountability and transparency for major new fiscal transformation initiatives
  • ensure entities do not reflect the financial impact of significant initiatives in the Budget when there is uncertainty, or it creates perverse incentives
  • review record keeping practices, systems and policies to ensure compliance with the State Records Act 1998, and the NSW Government Information Classification, Labelling and Handling Guidelines
  • review procurement policies to ensure that consultant use complies with all NSW Government policy requirements.

The NSW Government established the Transport Asset Holding Entity (TAHE), a statutory State Owned Corporation (SOC), on 1 July 2020 to replace the former rail infrastructure owner – RailCorp. It is the State's custodian of rail network assets, including rail tracks and other infrastructure, rolling stock, land, train stations and facilities, retail space, and signal and power systems, within metropolitan and regional New South Wales. It is responsible for $2.8 billion of major capital projects in 2022–23.

TAHE was established under Part 2 of the Transport Administration Act 1988 and is governed by a decision-making board. The Treasurer and the Minister for Finance and Employee Relations are the Shareholding Ministers of TAHE, and they annually agree performance expectations articulated in a Statement of Corporate Intent.

Whereas TAHE is the custodian of rail assets, Sydney Trains and NSW Trains operate public rail services. TAHE does not have responsibility for the operation of the heavy rail network or train services, nor does it have network control functions. TAHE, Sydney Trains and NSW Trains are in the Transport and Infrastructure cluster in the public sector (formerly the Transport cluster and renamed in April 2022), which also includes Sydney Metro and Transport for NSW (TfNSW).

TfNSW leads the Transport and Infrastructure cluster. Its role is to set the strategic direction for transport across the State. This involves the shaping of planning, policy, strategy, regulation, resource allocation and other service and non-service delivery functions for all modes of transport.

TAHE's Operating Licence is granted by the Portfolio Minister and authorises the entity to perform the functions required to acquire, develop, finance, divest and hold assets, pursuant to the Transport Administration Act 1988. The Portfolio Minister also issues a Statement of Expectations which outlines the government’s expectation for the business for the next three to five years.

TAHE's original Portfolio Minister was the Minister for Transport who approved, on 30 June 2020, the issuing of an interim 12-month Operating Licence to enable TAHE to commence operating on 1 July 2020. The Portfolio Minister then granted TAHE's current Operating Licence in 2021. After TAHE requested a 12-month extension to its current Operating Licence, its next Operating Licence is due on 1 July 2024. The current Portfolio Minister is the Minister for Infrastructure, Cities and Active Transport.

About this audit

This audit assessed the effectiveness of NSW Government agencies' design and implementation of TAHE. In making this assessment, we considered whether: 

  • the process of designing and implementing TAHE was cohesive and transparent, and delivered an effective outcome
  • agencies' roles and responsibilities were clear in the planning of TAHE
  • agencies effectively identified and managed certain risks.

Conclusion

The design and implementation of TAHE was not effective. The process was not cohesive or transparent. It delivered an outcome that is unnecessarily complex in order to meet the NSW Government's short-term Budget objectives, while creating an obligation for future governments to sustain TAHE through continuing investment, and funding of the state owned rail operators. The ineffective process to design TAHE delivered a model that entails significant uncertainty as to whether the anticipated longer-term financial improvements to the Budget position can be achieved or sustained.

NSW Treasury and TfNSW had different objectives for TAHE

Up to June 2013, RailCorp had been the owner and operator of rail services and maintainer of the metropolitan rail network for almost a decade. It had been operating as a not-for-profit Public Non-Financial Corporation (PNFC).

In 2012, NSW Treasury (hereafter Treasury) decided there was a risk that the Australian Bureau of Statistics (ABS) would reclassify RailCorp to the General Government Sector (GGS), meaning depreciation expenses of approximately $870 million would be reflected in the GGS Budget. Treasury wanted to avoid this impact on the GGS Budget, and considered the establishment of a transport asset holding entity as a means to do so. Capital grants to RailCorp were being treated as an expense to the GGS Budget.

TfNSW also wanted an asset holding entity – but one that would be a non-trading ‘shell’ company with no staff that would hold and manage all public transport assets. TfNSW's concept envisaged the entity would have a structure that would enable future public transport reforms and strategic directions while ensuring vertical integration of operations between asset owners and the rail operators to maintain rail safety.

However, Treasury pursued its objective to improve the GGS Budget result, and sought to expand on TfNSW's 'shell' asset holding entity concept. Treasury wanted an entity that could generate a return on investment, as this meant that government investment in transport assets could be treated as equity investments, rather than a Budget expense, and in turn improve the GGS Budget position. As an example of the potential impact of creating this new entity, capital grants of $2.3 billion were paid to RailCorp in 2013–14. If Treasury's objective was met, grants of this significance would then be treated as an equity investment, rather than an expense in the GGS Budget.

In 2017, Treasury's preferred option was progressed through legislation, but both agencies' central objectives for the proposed asset holding entity would continue to prove difficult to reconcile. To achieve Treasury's objective to improve the Budget result, the entity would need to generate a return on investment (this is further discussed below). However, TfNSW expressed concerns that the prioritisation of rail safety, and the effective management of governance, regulation and operations would be more complex in an entity with commercial imperatives.

Asset holding entities are a common approach to the management of transport assets in Australia and internationally, and there are a range of approaches to how they are structured and used. Such structures should be driven by the goal of improved asset management. Ultimately, TfNSW's objectives could have been delivered through a simpler entity structure. However, reconciling TfNSW's objectives with Treasury's imperative to deliver and justify a Budget improvement in the short-term resulted in an overly lengthy process and an unnecessarily complex outcome that places an obligation on future governments to sustain. There is still significant uncertainty as to whether the short-term improvements to the Budget can continue to be realised in the longer-term.

The Budget benefits of TAHE were claimed before the entity was legislated, committing the agencies to deliver, regardless of the complexities that subsequently arose

The 2015–16 GGS Budget treated the government's investment in TAHE (still known at this time as RailCorp) as an equity contribution. This had the immediate impact of improving the Budget result by $1.8 billion per annum. However, the legislation to enable the establishment of TAHE had not yet been passed by Parliament, key elements of the operating model were still under development, and imminent changes in accounting standards had the potential to impact TAHE's financial model. The decision to book the benefits in the Budget early committed the involved agencies to implement a solution that justified the 2015–16 Budget impacts, irrespective of the challenges that arose. 

TAHE's financial structure requires circular government investment to work

For the NSW Government to continue to treat its investment in TAHE as an equity contribution, rather than an expense to the Budget, there must be a reasonable expectation that TAHE will generate a sufficient rate of return as required by the Government Finance Statistics (GFS) framework. In doing so, it needs to recover a revaluation loss created by a $20.3 billion reduction in the value of its assets which was incurred in its first full year of operation. This loss occurred as a result of a revaluation of TAHE's assets when RailCorp (a not-for profit entity) became TAHE (a for-profit commercial entity) – and is discussed further in the 'Key findings' below.

TAHE generates a small portion of its income from transactions with the private sector but, as noted in our report 'State Finances 2021', TAHE receives the majority of its revenue (more than 80%) from access and licence fee agreements with Sydney Trains and NSW Trains. Both of these entities are funded by grants (a Budget expense) to TfNSW from the GGS Budget.

Based on Treasury’s correspondence with the ABS in 2015, TAHE was initially expected to pay a return on equity of 7% in 2016–17. The assumption of a 7% return persisted through to 2018, after the legislation enabling the establishment of TAHE was passed by Parliament. However, when the initial access and licence fees were agreed on 1 July 2020, this figure had been revised to an expected rate of return of 1.5% excluding the revaluation loss. This was below the long-term inflation target and did not include the recovery of the revaluation loss – risking the government's ability to treat its investment in TAHE as an equity contribution. Importantly, as TAHE is primarily reliant on fees paid by the state owned rail operators that, in turn, are funded by the GGS Budget (as an expense), the decision to change the returns model from 7% to 1.5% would in its own right have had a positive impact on the GGS Budget. However, the decision to use a 1.5% return would ultimately be problematic as it made it difficult to treat the government's contributions to TAHE as an equity investment, as discussed below.

On 14 December 2021, to avoid a qualified audit opinion, the NSW Government made the decision to increase TAHE's expected rate of return to 2.5%, equal to the Reserve Bank’s long-term inflation target.

In 2021-22, TAHE needed to start charging rail operators higher access and licence fees in order to generate a return of 2.5%, so as to support the government's treatment of its investment in TAHE as an equity contribution in the GGS Budget. This meant the government needed to provide additional grant (expense) funding to the state owned rail operators so they could pay the increased access and licence fees to TAHE. Based on current projections, TAHE is not expected to recover the revaluation loss until 2046.

There remains a risk that TAHE will not be able to generate a sufficient return on the NSW Government's investment without relying on increased funding to state owned rail operators so that they can in turn pay the higher access and licence fees. TAHE's ability to generate returns on government investment from other sources are uncertain and may not be achievable or sustainable. Current modelling highlights that TAHE remains largely reliant, through to 2046, on increasing fees (which are assumed to increase at 2.5% per annum from 2031 onwards when the current 10 year contracts with rail operators expire) paid by the state owned rail operators that remain principally reliant on GGS Budget grants.

The process of designing and implementing TAHE was not transparent to independent scrutiny

Our report 'State Finances 2021' commented that Treasury did not always provide this Office with information relating to TAHE on a timely basis. Similarly, during this performance audit, there were also multiple instances where auditees were unable to provide documentation regarding key activities in the process to deliver TAHE. Agencies also applied higher sensitivity classifications to large tranches of documents than was justified or required by policy. Of particular concern is the incorrect classification of documents as Cabinet sensitive information. The incorrect or over-classification of documentation as Cabinet sensitive delayed this Office's ability to provide scrutiny or independent assurance.

There was a lack of clarity around the roles and responsibilities of governance structures set up to oversee the design and implementation of TAHE

From 2014, multiple workstreams and advisory committees were established to progress the design and implementation of TAHE. For some of these committees and workstreams, there is limited information on what they were tasked to do and what they achieved. Most had ceased meeting by 2018, before significant work needed to deliver TAHE was completed.

The lack of clarity around the roles and responsibilities of these governance structures reduced opportunities for TfNSW and Treasury to reconcile their differing objectives for TAHE, and resolve key questions earlier in the process.

There was a heavy reliance on consulting firms throughout the process to establish TAHE, and the management of consultant engagements failed to ensure that agencies received independent advice to support objective decision-making

In 2020, Treasury and TfNSW failed to prevent, identify, or adequately manage a conflict of interest when they engaged the same 'Big 4' consulting firm to work on separate TAHE-related projects. Both agencies used the firm's work to further their respective views with regard to the financial implications of TAHE's operating model. At this time those views were still unreconciled.

Treasury engaged the firm to provide a fiscal risk management strategy and advice on the impact of changes to accounting standards. TfNSW engaged the same firm to develop operating and financial models for TAHE, which raised concerns regarding the viability of TAHE. Disputes arose around the findings of these reports. Treasury disagreed with some of the outcomes of the work commissioned by TfNSW, relating to accounting treatment and fiscal advice.

The management of this conflict (real or perceived) was left to the 'Big 4' consulting firm when it was more appropriate for it to be managed by Treasury and TfNSW. If these agencies had communicated more effectively, used available governance structures consistently, and shared information openly about their use of the firm and the nature of their respective engagements, these disputes might have been avoided. This issue, coupled with deficiencies in procurement by both agencies, reflected and further perpetuated the lack of cohesion in the design and implementation of TAHE.

More broadly, over the period 2014 – 2021, 16 separate consulting firms were employed to work on 36 contracts, valued at over $22.56 million, relating to TAHE ranging from accounting and legal advice, project management, and the provision of administrative support and secretariat services.

Consultants are legitimately used by agencies to provide advice on how to achieve the outcomes determined by government, including advising agencies on the risks and challenges in achieving those outcomes. Similarly, consultants can provide expert knowledge in the service of achieving those outcomes and managing the risks. However, the heavy reliance on consulting firms during the design and implementation of TAHE heightened the risk that agencies were not receiving value for money, were outsourcing tasks that should be performed by the public service, and did not mitigate the risk that the advice received was not objective and impartial. The risk that the role of consultants could have been blurred between providing independent advice to government on options and facilitating a pre-determined outcome was not effectively treated or mitigated. This risk was amplified because a small number of firms were used repeatedly to provide advice on one topic. The effective procurement and management of consultants is an obligation of government agencies.

Appendix one – Responses from audited agencies, and Audit Office clarification of matters raised in the TAHE formal response 

Appendix two – Classification of government entities 

Appendix three – About the audit 

Appendix four – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #372 - released 24 January 2023

 

Published

Actions for Coordination of the response to COVID-19 (June to November 2021)

Coordination of the response to COVID-19 (June to November 2021)

Premier and Cabinet
Community Services
Health
Justice
Whole of Government
Internal controls and governance
Risk
Service delivery
Shared services and collaboration

What the report is about

This audit assessed the effectiveness of NSW Government agencies’ coordination of the response to COVID-19, with a focus on the Delta variant outbreak in the Dubbo and Fairfield Local Government Areas (LGA) between June and November 2021. We audited five agencies - the Department of Premier and Cabinet, NSW Health, the NSW Police Force, Resilience NSW and the Department of Customer Service.

The audit also considered relevant planning and preparation activities that occurred prior to June 2021 to examine how emergency management and public health responses learned from previous events.

What we found

Prior to Delta, agencies developed capability to respond to COVID-19 related challenges.

However, lessons learned from prior reviews of emergency management arrangements, and from other jurisdictions, had not been implemented when Delta emerged in June 2021. As a result, agencies were not as fully prepared as they could have been to respond to the additional challenges presented by Delta.

Gaps in emergency management plans affected agencies' ability to support individuals, families and businesses impacted by restrictions to movement and gathering such as stay-at-home orders. In LGAs of concern, modest delays of a few days had a significant impact on people, especially those most vulnerable.

On 23 July 2021, the NSW Government established a cross-government coordinating approach, the Delta Microstrategy, which complemented existing emergency management arrangements, improved coordination between NSW Government agencies and led to more effective local responses.

Where possible, advice provided to government was supported by cross-government consultation, up-to-date evidence and insights. Public Health Orders were updated as the response to Delta intensified or to address unintended consequences of previous orders. The frequency of changes hampered agencies' ability to effectively communicate changes to frontline staff and the community in a rapidly evolving situation.

The NSW Government could provide greater transparency and accountability over decisions to apply Public Health Orders during a pandemic.

What we recommended

The audit made seven recommendations intended to improve transparency, accountability and preparedness for future emergency events.

This audit assessed the effectiveness of NSW Government agencies’ coordination (focused on the Department of Premier and Cabinet, NSW Health, the NSW Police Force, Resilience NSW and the Department of Customer Service) of the COVID-19 response in selected Local Government Areas (Fairfield City Council and Dubbo Regional Council) between June and November 2021.

As noted in this report, Resilience NSW was responsible for the coordination of welfare services as part of the emergency management arrangements. On 16 December 2022, the NSW Government abolished Resilience NSW.

During the audited period, Resilience NSW was tasked with supporting the needs of communities subject to stay-at-home orders or stricter restrictions and it provided secretariat support to the State Emergency Management Committee (SEMC). The SEMC was, and remains, responsible for the coordination and oversight of emergency management policy and preparedness.

Our work for this performance audit was completed on 15 November 2022, when we issued the final report to the five audited agencies. While the audit report does not make specific recommendations to Resilience NSW, it does include five recommendations to the State Emergency Management Committee. On 8 December 2022, the then Commissioner of Resilience NSW provided a response to the final report, which we include as it is the formal response from the audited entity at the time the audit was conducted.

The community of New South Wales has experienced significant emergency events during the past three years. COVID-19 first emerged in New South Wales after bushfire and flooding emergencies in 2019–20. The pandemic is now into its third year, and there have been further extreme weather and flooding events during 2021 and 2022.

Lessons taken from the experience of these events are important to informing future responses and reducing future risks to the community from emergencies.

This audit focuses on the NSW Government's response to the COVID-19 pandemic, and in particular, the Delta variant (Delta) that occurred between June and November 2021. The response to the Delta represents six months of heightened challenges for the NSW Government.

Government responses to emergencies are guided by legislation. The State Emergency and Rescue Management Act 1989 (SERM Act) establishes emergency management arrangements in New South Wales and covers:

  • coordination at state, regional and local levels through emergency management committees
  • emergency management plans, supporting plans and functional areas including the State Emergency Management Plan (EMPLAN)
  • operations centres and controllers at state, regional and local levels.

This audit focuses on the activities of five agencies during the audit period:

  • The NSW Police Force led the emergency management response and was responsible for coordinating agencies across government in providing the tactical and operational elements that supported and enhanced the health response to the pandemic. The NSW Police Force also led the compliance response which enforced Public Health Orders and included household checks on those required to isolate at home after testing positive to COVID-19. In some parts of NSW, they were supported by the Australian Defence Force in this role.
  • NSW Health was responsible for leading the health response which coordinated all parts of the health system, initially to prevent, and then to manage, the pandemic.
  • Resilience NSW coordinated welfare services as part of the emergency management arrangements and provided secretariat support to the State Emergency Management Committee (SEMC). The SEMC is responsible for the coordination and oversight of emergency management policy and preparedness. Resilience NSW was also tasked with supporting the needs of communities subject to stay-at-home orders or stricter restrictions.
  • The Department of Customer Service (DCS) was responsible for the statewide strategic communications response.
  • The Department of Premier and Cabinet (DPC) held a key role in providing policy and legal services, as well as supporting the coordination of activity across a range of functional areas and decision-making by our State’s leaders.

This audit assessed the effectiveness of NSW Government agencies’ coordination (focused on the Department of Premier and Cabinet, NSW Health, the NSW Police Force, Resilience NSW and the Department of Customer Service) of the COVID-19 response in selected Local Government Areas (LGA) (Fairfield City Council and Dubbo Regional Council) after June 2021.

The audit investigated whether:

  • government decisions to apply LGA-specific Public Health Orders were supported by effective crisis management governance and planning frameworks
  • agencies effectively coordinated in the communication (and enforcement) of Public Health Orders.

While focusing on the coordination of NSW Government agencies’ response to the Delta variant in June through to November 2021, the audit also considered relevant planning and preparation activities that occurred prior to June 2021 to examine how emergency management and public health responses learned from previous events.

This audit does not assess the effectiveness of other specific COVID-19 responses such as business support. It refers to the preparedness, planning and delivery of these activities in the context of supporting communities in selected LGAs. NSW Health's contribution to the Australian COVID-19 vaccine rollout was also subject to a separate audit titled 'New South Wales COVID-19 vaccine rollout' tabled in NSW Parliament on 7 December 2022. 

This audit is part of a series of audits which have been completed, or are in progress, regarding the New South Wales COVID-19 emergency response. The Audit Office of New South Wales '2022–2025 Annual Work Program' details the ongoing focus our audits will have on providing assurance on the effectiveness of emergency responses.

In this document Aboriginal refers to the First Nations peoples of the land and waters now called Australia, and includes Aboriginal and Torres Strait Islander peoples.

Conclusion

Prior to June 2021, agencies worked effectively together to adapt and refine pre-existing emergency management arrangements to respond to COVID-19. However, lessons learned from prior reviews of emergency management arrangements, and from other jurisdictions, had not been implemented when Delta emerged in June 2021. As a result, agencies were not as fully prepared as they could have been to respond to the additional challenges presented by Delta.

In the period March 2020 to June 2021, the State's Emergency Management (EM) arrangements coordinated the New South Wales emergency response to COVID-19 with support from the Department of Premier and Cabinet (DPC) which led the cross-government COVID-19 Taskforce. NSW Government agencies enhanced the EM arrangements, which until then had typically been activated in response to natural disasters, to meet the specific circumstances of the pandemic.

However, the State Emergency Management Committee (SEMC), supported by Resilience NSW, did not address relevant recommendations arising from the 2020 Bushfires Inquiry before June 2021 and agencies did not always integrate lessons learned from other jurisdictions or scenario training exercises into emergency management plans or strategies before Delta. As a result, deficiencies in the EM arrangements, including representation of vulnerable communities on EM bodies, well-being support for multicultural communities in locked down environments and cross-agency information sharing, persisted when Delta emerged in June 2021.

It should be noted that for the purposes of this audit there is no benchmark, informed by precedent, that articulates what level of preparation would have been sufficient or proportionate. However, the steps required to address these gaps were reasonable and achievable, and the failure to do so meant that agencies were not as fully prepared as they could have been for the scale and escalation of Delta’s spread across the State.

The Delta Microstrategy complemented the EM arrangements to support greater coordination and agencies are working to improve their capability for future events

The Delta Microstrategy (the Microstrategy) led to innovations in information sharing and collaboration across the public service. Agencies involved in the response have completed, or are completing, reviews of their contribution to the response. That said, none of these reviews includes a focus on whole-of-government coordination.

On 23 July 2021, the NSW Government approved the establishment of the Microstrategy to respond to the additional challenges presented by Delta including the need to support communities most impacted by restrictions to movement and gathering in the LGAs of concern. An extensive range of government agencies were represented across eight Microstrategy workstreams, which coordinated with the existing EM arrangements to deliver targeted strategies to communities in high-risk locations and improve data and information sharing across government. This enhanced the public health, compliance, income and food support, communications and community engagement aspects of the response.

Agencies also leveraged learnings from early weeks of the Delta wave and were able to replicate those lessons in other locations. The use of pre-staging hubs in Fairfield to support food and personal hamper distribution was used a month later in Dubbo which acted as a central hub for more remote parts of the State.

Emergency management plans did not enable government to respond immediately to support vulnerable communities in high-risk LGAs or regional NSW

There are gaps in the emergency management plans relating to the support for individuals, families and businesses impacted by the stay-at-home orders and other restrictions to movement and gathering. These gaps affected agencies' ability to respond immediately when the need arose during Delta.

Emergency management plans and supporting instruments did not include provision for immediate relief for households, which meant arrangements for isolation income support and food security measures had to be designed in the early stages of Delta before it could be approved and deployed.

There were delays – sometimes only days, on occasion, weeks - in providing support to affected communities. In particular, there were delays to the provision of income support and in scaling up efforts to coordinate food and grocery hampers to households in isolation. In LGAs of concern, modest delays of a few days had a significant impact on people, especially those most vulnerable.

Although government issued stricter restrictions for workers in the Fairfield LGA on 14 July 2021, it only approved targeted income support for people in LGAs of concern on 16 August 2021.

Overall, agencies coordinated effectively to provide advice to government but there are opportunities to learn lessons to improve preparedness for future events

Agencies coordinated in providing advice to government. The advice was supported by timely public health information, although this was in the context of a pandemic, where data and information about the virus and its variants was changing regularly. However, agencies did not always consider the impact on key industries or supply chains when they provided advice to government, which meant that Public Health Orders would sometimes need to be corrected.

Public Health Orders were also updated as the response to Delta intensified or to address unintended consequences of previous orders. The frequency of changes hampered agencies' ability to effectively communicate changes to frontline staff and the community in a rapidly evolving situation.

The audit identified several occasions where there were delays, ranging from three to 21 days, between the provision of advice to government and subsequent decision-making (which we have not detailed due to the confidentiality of Cabinet deliberations). Agency officers advised of instances where they were not provided sufficient notice of changes to Public Health Orders to organise local infrastructure (such as traffic support for testing clinics) to support compliance with new requirements.

The COVID-19 pandemic arrived in Australia in late January 2020 as the bushfire and localised flooding emergencies were in their final stages. Between 2020 and mid-2021, agencies responded to the initial variants of COVID-19, managed a border closure with Victoria that lasted nearly four months and dealt with localised ‘flare-ups’ that required postcode-based restrictions on mobility in northern parts of Sydney and regional New South Wales. During this period, New South Wales had the opportunity to learn from events in Victoria which imposed strict restrictions on mobility across the State and the growing emergence of the Delta variant (Delta) across the Asia Pacific.

This section of the report assesses how emergency management and public health responses adapted to these lessons and determined preparedness for, and responses to, widespread community transmission of Delta in New South Wales.

The previous chapter discusses how agencies had refined the existing emergency management arrangements to suit the needs of a pandemic and describes some gaps that were not addressed. This chapter explores the first month of Delta (mid-June to mid-July 2021). It explores the areas where agencies were prepared and responses in place for the outbreak. It also discusses the impact of the gaps that were not addressed in the period prior to Delta and other issues that emerged.

NSW Health provided advice on the removal of restrictions based on up-to-date advice

The NSW Government discussed the gradual process for removing restrictions using the Doherty Institute modelling provided to National Cabinet on 10 August 2021. NSW Health highlighted the importance of maintaining a level of public health and safety measure bundles to further suppress case numbers. This was based on additional modelling from the Doherty Institute.

The Department of Regional NSW led discussion and planning around reopening with a range of proposal through August and September 2021. The Department of Premier and Cabinet and NSW Health jointly developed a paper to provide options on the restrictions when the State reached a level of 70% double dose vaccinations.

The roadmap to reopening was originally published on 9 September 2021. However, by 11 October 2021, the restrictions were relaxed when the 70% double dose threshold was reached to allow:

  • up to ten fully vaccinated visitors to a home (increased from five)
  • up to 30 fully vaccinated people attending outdoor gatherings (increased from 20)
  • weddings and funerals limits increased to 100 people (from 50)
  • the reopening of indoor pools for training, exercise and learning purposes only.

On the same day, the NSW Government announced further relaxation of restrictions once the 80% double dose threshold was reached. These restrictions were further relaxed on 8 November 2021. This included the removal of capacity restrictions to the number of visitors to a private residence, indoor pools to reopen for all purposes and density limits of one person for every two square metres, dancing allowed in nightclubs and 100% capacity in major stadia.

The NSW Government allowed workers in regional areas who received one vaccination dose to return to their workplace from 11 October 2021.

The Premier extended the date of easing of restrictions for unvaccinated people aged over 16 from 1 December to 15 December 2021.

Many agencies have undertaken reviews of their response to the Delta outbreak but a whole-of-government review has yet to be conducted

Various agencies and entities associated with the response to the Delta outbreak conducted after-action review processes. These processes assessed the achievements delivered, lessons learned and opportunities for improvement. However, a whole-of-government level review has not been conducted. This limits the New South Wales public service's ability to improve how it coordinates responses in future emergencies.

The agencies/entities that conducted reviews included:

  • South West Metropolitan region, Western NSW region, Fairfield Local Emergency Management Committee (LEMC), Dubbo Local Emergency Operations Controller (LEOCON), which were collated centrally by the State Emergency Operations Centre (SEOC)
  • Aboriginal Affairs NSW assessed representation and relevance of the emergency management arrangements for Aboriginal communities following the 2019 bushfires
  • Resilience NSW developed case studies to capture improved practice with regard to food security and supply chains
  • a community support and empowerment-focused after-action review undertaken by the Pillar 5 workstream of the Microstrategy.

Key lessons collated from the after-action reviews include:

  • the impact of variation in capability across agencies on the management of key aspects of the response including welfare support and logistics
  • issues with boundary differences between NSW Police Force regions, local government areas (LGA and local health districts (LHD) caused issues in delivering and coordinating services in an emergency situation 
  • the need to improve relationships between state and local Government outside of acute emergency responses to improve service delivery 
  • issues arising from impediments to information sharing between agencies and jurisdictions, such as:
    • timeliness and accuracy of data used to direct compliance activities
    • the impact of insufficient advance notice on changes to Public Health Orders
    • timely access to data across public sector agencies and other jurisdictions to inform decision-making, analysis and communications
    • gaps in data around ethnicity, geolocation of recent positive cases and infection/vaccination rates in Aboriginal communities.
  • the lack of Aboriginal community representation on many LEMCs
  • compared with the response to COVID-19 in 2020, improved coordination of communications with Culturally and Linguistically Diverse (CALD) populations with a reduction in overlapping messages and over-communication
  • improved attendance from agency representatives in LEMCs, and regional emergency operations centres (REOC) to improve interagency communications, planning, capability development and community engagement issues
  • deficiencies in succession planning and fatigue management practices
  • the potential for REOC Welfare/Well-being subgroups to be included as part of the wider efforts to community needs during emergencies.

NSW Health commenced a whole of system review of its COVID-19 response in May 2022. At the time of writing, the completion due date for the debrief is 7 November 2022. This debrief is expected to explore:

  • governance
  • engagement 
  • innovation and technology 
  • community impact 
  • workforce impact
  • system impact and performance.

NSW Health is also undertaking a parallel Intra-Action Review that is focused on the public health aspects of the response with finalisation estimated for the end of November 2022. At the time of completing this performance audit report, NSW Health had not finalised these reviews and, as a result, we cannot validate their findings against our own observations.

Recent inquiries are likely to impact the governance of emergency management in New South Wales

In March 2022, the NSW Government established an independent inquiry to examine and report on the causes of, preparedness for, response to and recovery from the 2022 floods. The Flood Inquiry report made 28 recommendations, which the NSW Government supported in full or in principle. Some of the recommendations relate directly to the governance and leadership of emergency management arrangements in New South Wales. 

The State Emergency Management Committee (SEMC) will likely be involved in, and impacted by, the recommendations arising from the Flood Inquiry with potential changes to its membership and reshaping of functional areas and agencies. At the same time, the SEMC may have a role in overseeing the changes that emerge from the SEOC consolidated after-action reviews. This can also extend to ensuring local and regional bodies have incorporated the required actions. There is a risk that the recommendations from the pandemic-based after-action reviews may not be considered due to the priority of action resulting from the Flood Inquiry.

Furthermore, there is potential for the SEMC to work with NSW Health during its system-wide review. Such an approach is likely to improve preparedness for future events.

Appendix one – Response from agencies

Appendix two – Chronology 2020–2021

Appendix three – About the audit

Appendix four – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #371 - released 20 December 2022

Published

Actions for New South Wales COVID-19 vaccine rollout

New South Wales COVID-19 vaccine rollout

Health
Internal controls and governance
Management and administration
Project management
Risk
Service delivery

What the report is about

The Australian Government led and implemented the Australian COVID-19 vaccine rollout, with the support of state and territory governments. As part of the Australian Government's vaccine rollout, NSW Health launched its vaccination program on 22 February 2021, with responsibility for distributing and administering COVID-19 vaccine stock provided by the Australian Government.

This audit examined the period 1 January 2021 to 31 December 2021 and focused on NSW Health's contribution to the Australian Government led vaccine roll out in four Local Health Districts (LHDs), in particular the administration of two doses of vaccine to people aged 16 and over.

What we found

On 16 October 2021, NSW Health, in partnership with the Australian Government's vaccination program, achieved its first objective to fully vaccinate 80% of people in NSW aged 16 and over. Demand for the vaccine reduced in December 2021, and NSW Health did not reach its target of 95% fully vaccinated for people aged 16 and over until June 2022.

Despite challenges such as uncertain supply and changes to clinical advice affecting vaccine eligibility, NSW Health's overall delivery of vaccination services was effective and efficient.

During the audit period, NSW Health implemented effective strategies to allocate vaccines and reduce wastage to optimise the number of vaccines available.

NSW Health implemented its own booking system after it identified that the Australian Government's system would not manage bookings. There were problems with NSW Health's interim vaccine booking system, and NSW Health fully resolved these issues by September 2021.

As at 19 October 2022, vaccination rates for Aboriginal peoples and culturally and linguistically diverse people remained below the 95% target.

What we recommended

By June 2023, NSW Health should conduct a comprehensive review of the COVID-19 vaccine rollout and incorporate lessons learned into pandemic response plans.

The first three cases of COVID-19 in New South Wales were diagnosed in January 2020. By 30 June 2021, 128 people were being treated in hospital and one person was in intensive care. By the end of December 2021, 187,504 total cases and 663 deaths were reported in New South Wales. As at 27 October 2022, NSW Health reported more than three million total cases and 5,430 deaths.

The COVID-19 pandemic continues to have a significant impact on the people and the health sector of New South Wales. The Australian, state, territory, and local governments have directed significant resources towards health responses and economic recovery.

On 13 November 2020, National Cabinet (comprised of the Australian, state, and territory governments) endorsed the Australian COVID-19 Vaccination Policy. Australia's vaccination program was launched on 21 February 2021 with the goal of providing safe and effective vaccines to the people who most needed them as quickly as possible, to support the physical, mental and economic wellbeing of the nation.

The Australian Government led and implemented the Australian vaccine rollout, with the support of state and territory governments. As part of the Australian Government's vaccine rollout, NSW Health launched its vaccination program on 22 February 2021, with responsibility for distributing and administering COVID-19 vaccine stock provided by the Australian Government.

The overall objective of this audit was to assess the effectiveness and efficiency of NSW Health’s contribution to the Australian COVID-19 vaccine rollout. It is important to note that in New South Wales, primary care providers (GPs and pharmacies) and aged care providers administered the majority of vaccines. Primary care providers and aged care providers are the responsibility of the Australian Government.

The audit had a particular focus on whether NSW Health:

  • set clear vaccination targets underpinned and/or guided by evidence
  • managed the rollout of the vaccination program effectively and efficiently
  • managed demand of vaccines effectively and efficiently.

The audit examined the period 1 January 2021 to 31 December 2021 and focused on NSW Health's contribution to the Australian Government led vaccine rollout in four Local Health Districts (LHDs), in particular the administration of two doses of vaccine to people aged 16 and over. We did not audit the subsequent rollout for ages five to 15, or the booster rollout (third and fourth doses) as these activities mostly occurred outside the date of our review.

This audit also did not assess the Australian Government’s allocation of vaccine supplies to New South Wales because we do not audit the Australian Government's activities. On 17 August 2022, the Australian National Audit Office completed a performance audit which assessed the Australian Department of Health and Aged Care's effectiveness in the planning and implementation of Australia's COVID-19 vaccine rollout.

This audit is one of a series of audits that have been completed or are in progress regarding the New South Wales COVID-19 emergency response. This includes the planned performance audit ‘Coordination of the response to COVID-19 (June to November 2021)’, and financial audit assurance activities focusing on Local Health District processes and controls to manage the receipt, distribution and inventory management of vaccine stock. The Audit Office New South Wales '2022–25 Annual Work Program' details the ongoing focus our audits will have on providing assurance on the effectiveness of emergency responses.

Conclusion

By 12 December 2021, NSW Health had administered two doses of vaccines to one third of eligible people in New South Wales aged 16 and over – contributing significantly to the achievement of the NSW Government vaccination target of 80% fully vaccinated before 31 December 2021. Despite challenges such as uncertain supply and changes to clinical advice affecting vaccine eligibility, NSW Health's overall delivery of vaccination services was effective and efficient.

NSW Health implemented its own booking system after it identified that the Australian Government's system would not manage bookings. There were problems with NSW Health's interim vaccine booking system, and NSW Health fully resolved these issues by September 2021.

Vaccination levels in some vulnerable populations remain below the 95% double dose target currently in place. Access to quality data to regularly measure vaccination rates in some vulnerable populations remains an ongoing challenge for the NSW and Australian Governments. As a result, NSW Health is unable to fully ensure it has delivered on its shared responsibility with the Australian Government to vaccinate vulnerable people.

NSW Health managed challenges regarding the uncertain supply of vaccines from the Australian Government and filled gaps beyond its agreed responsibilities in the National Partnership on COVID-19 Response. During the Delta outbreak of the pandemic, NSW Health sought to achieve the best possible public health outcome from limited vaccine supply by opening up additional vaccination clinics in highly affected areas and redistributing vaccine supplies from areas with fewer cases to highly affected local government areas in south west Sydney.

During the audit period, NSW Health implemented effective strategies to allocate vaccines and reduce wastage to optimise the number of vaccines available. Our financial audit report, 'Health 2022', includes additional information on vaccine supply stock held by NSW Health.

NSW Health demonstrated agility by using a range of strategies to promote vaccination, including direct engagement with communities to develop culturally appropriate services such as pop-up clinics. NSW Heath recruited prominent community members, such as faith leaders, elders and sportspeople, to promote vaccination within their communities. However, at the date of this report, there are still vulnerable populations with vaccination rates lower than the current 95% double dose vaccination target. There is also a lack of regularly updated data for some cohorts which prevents NSW Health from accurately monitoring vaccination rates in some populations it has identified as vulnerable.

In March 2021, NSW Health identified that the booking system provided by the Australian Government was an online directory of vaccine clinics and would not manage bookings. To overcome this, NSW Health amended an internal-use system to be publicly facing. This solution was not user-friendly for staff or those seeking to make an appointment. Between June to September 2021, NSW Health progressively resolved booking system related issues, by developing and rolling out a new purpose-built booking solution for NSW Health vaccination clinics.

Appendix one – Response from agency

Appendix two – Australian audits on the vaccine rollouts

Appendix three – Committee members 

Appendix four – About the audit 

Appendix five – Performance auditing 

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #369 - released 7 December 2022

Published

Actions for Facilitating and administering Aboriginal land claim processes

Facilitating and administering Aboriginal land claim processes

Planning
Environment
Industry
Local Government
Premier and Cabinet
Whole of Government
Cross-agency collaboration
Compliance
Management and administration

What the report is about

The Aboriginal Land Rights Act 1983 (NSW) (the Act) provides land rights over certain Crown land for Aboriginal Land Councils in NSW.

If a claim is made over Crown land (land owned and managed by government) and meets other criteria under the Act, ownership of that land is to be transferred to the Aboriginal Land Council.

This process is intended to provide compensation for the dispossession of land from Aboriginal people in NSW. It is a different process to the recognition of native title rights under Commonwealth law.

We examined whether relevant agencies are effectively facilitating and administering Aboriginal land claim processes. The relevant agencies are:

  • Department of Premier and Cabinet (DPC)
  • Department of Planning and Environment (DPE)
  • NSW Aboriginal Land Council (NSWALC).

We consulted with Local Aboriginal Land Councils (LALCs) and other Aboriginal community representative groups to hear about their experiences.

What we found

Neither DPC nor DPE have established the resources required for the NSW Government to deliver Aboriginal land claim processes in a coordinated way, and which transparently commits to the requirements and intent of the Act.

Delays in determining land claims result in Aboriginal Land Councils being denied the opportunity to realise their statutory right to certain Crown land. Delays also create risks due to uncertainty around the ownership, use and development of Crown land.

DPC has not established governance arrangements to ensure accountability for outcomes under the Act, and effective risk management.

DPE lacks clear performance measures for the timely and transparent delivery of its claim assessment functions. DPE also lacks a well-defined framework for prioritising assessments.

LALCs have concerns about delays, and lack of transparency in the process.

Reviews since at least 2014 have recommended actions to address numerous issues and improve outcomes, but limited progress has been made.

The database used by DPC (Office of the Registrar) for the statutory register of land claims has not been upgraded or fully validated since the 1990s.

In 2020, DPE identified the transfer of claimable Crown land to LALCs to enable economic and cultural outcomes as a strategic priority. DPE has some activities underway to do this, and to improve how it engages with Aboriginal Land Councils – but DPE still lacks a clear, resourced strategy to process over 38,000 undetermined claims within a reasonable time.

What we recommended

In summary:

  • DPC should lead strategic governance to oversee a resourced, coordinated program that is accountable for delivering Aboriginal land claim processes
  • DPE should implement a resourced, ten-year plan that increases the rate of claim processing, and includes an initial focus on land grants
  • DPE and DPC should jointly establish operational arrangements to deliver a coordinated interagency program for land claim processes
  • DPC should plan an interagency, land claim spatial information system, and the Office of the Registrar should remediate and upgrade the statutory land claims register
  • DPC and NSWALC should implement an education program (for state agencies and the local government sector) about the Act and its operations
  • DPE should implement a five-year workforce development strategy for its land claim assessment function
  • DPE should finalise updates to its land claim assessment procedures
  • DPE should enhance information sharing with Aboriginal Land Councils to inform their claim making
  • NSWALC should enhance information sharing and other supports to LALCs to inform their claim making and build capacity.

Fast facts

  • 53,800 the number of claims lodged since the Act was introduced in 1983
  • 38,200 the number of claims awaiting DPE assessment and determination (about 70 per cent of all claims lodged)
  • 207 the number of claims granted by DPE in six months to December 2021
  • 120 LALCs, and the NSWALC, have the right to make a claim and have it determined
  • +5 years around 60 per cent of claims have been awaiting determination for more than five years
  • 22 years the time it will take DPE to determine existing claims, based on current targets

The return of land under the Aboriginal Land Rights Act 1983 (NSW) (the Act) is intended to provide compensation for the dispossession of land from Aboriginal people in New South Wales. A claim on Crown land1 made by an Aboriginal Land Council that meets criteria under the Act is to be transferred to the claimant council as freehold title. The 2021 statutory review of the Act recognises the spiritual, social, cultural and economic importance of land to Aboriginal people.

The Minister for Aboriginal Affairs administers the Act, with support from Aboriginal Affairs NSW (AANSW) in the Department of Premier and Cabinet (DPC). AANSW also leads the delivery of Opportunity, Choice, Healing, Responsibility and Empowerment (OCHRE), the NSW Government's plan for Aboriginal affairs, and assists the Minister to implement the National Agreement on Closing the Gap – which includes a target for increasing the area of land covered by Aboriginal and Torres Strait Islander people's legal rights or interests.

The Act gives responsibility for registering land claims to an independent statutory officer, the Registrar of the Aboriginal Land Rights Act (the Registrar), whose functions are supported by the Office of the Registrar (ORALRA) which is resourced by AANSW.2

The Land and Environment Court of New South Wales has stated that there is an implied obligation for land claims to be determined within a reasonable time. The Minister administering the Crown Land Management Act 2016 (NSW) is responsible for determining land claims. This function is supported by the Department of Planning and Environment (DPE),3 whose staff assess and recommend claims for determination based on the criteria under section 36(1) of the Act. There is also a mechanism under the Act for land claims to be negotiated in good faith through an Aboriginal Land Agreement.

The NSW Aboriginal Land Council (NSWALC) is a statutory corporation constituted under the Act with a mandate to provide for the development of land rights for Aboriginal people in NSW, in conjunction with the network of 120 Local Aboriginal Land Councils (LALCs). LALCs are constituted over specific areas to represent Aboriginal communities across NSW. Both NSWALC and LALCs can make land claims.

DPC and DPE are responsible for governance and, in partnership with NSWALC, operational and information-sharing activities that are required to coordinate Aboriginal land claim processes. LALCs, statutory officers, government agencies, local councils, and other parties need to be engaged so that these processes are coordinated effectively and managed in a way that is consistent with the intent of the Act, and other legislative requirements.

The first land claim was lodged in 1983. The number of undetermined land claims has increased over time, and at 31 December 2021 DPE data shows 38,257 undetermined claims.

The issue of undetermined land claims has been publicly reported by the Audit Office since 2007. Recommendations to agencies to better facilitate processes and improve how functions are administered have been made in multiple reviews, including two Parliamentary inquiries in 2016.

The objective of this audit was to assess whether relevant agencies are effectively facilitating and administering Aboriginal land claim processes. In making this assessment, we considered whether:

  • agencies (DPE, DPC (AANSW and ORALRA) and NSWALC) coordinate information and activities to effectively facilitate Aboriginal land claim processes
  • agencies (DPE and DPC (ORALRA)) are effectively administering their roles in the Aboriginal land claim process.

We consulted with LALCs to hear about their experiences and priorities with respect to Aboriginal land claim processes and related outcomes. We have aimed to incorporate their insights into our understanding of their expectations of government with respect to delivering requirements, facilitating processes, and identifying opportunities for improved outcomes. 

Conclusion

The Department of Premier and Cabinet (DPC) and the Department of Planning and Environment (DPE) are not effectively facilitating or administering Aboriginal land claim processes. Neither agency has established the resources required for the NSW Government to operate a coordinated program of activities to deliver land claim processes in a way that transparently commits to the requirements and intent of the Aboriginal Land Rights Act 1983 (NSW) (the Act). Arrangements to engage the NSW Aboriginal Land Council (NSWALC) in these activities have not been clearly defined.

There are more than 38,000 undetermined land claims that cover approximately 1.12 million hectares of Crown land. As such, DPE has not been meeting its statutory requirement to determine land claims nor its obligation to do so within a reasonable time. Over 60 per cent of these claims were lodged with the Registrar of the Aboriginal Land Rights Act, for DPE to determine, more than five years ago.

DPE’s Aboriginal Outcomes Strategy 2020–23 identifies transferring claimable Crown land to Local Aboriginal Land Councils (LALCs) as a priority to enable economic and cultural outcomes. Since mid-2020 DPE has largely focused on supporting LALCs to identify priority land claims for assessment and on negotiating Aboriginal Land Agreements. This work may support the compensatory intent of the Act but is in its early stages and is unlikely to increase the pace at which land claims are determined. Based on current targets, it will take DPE around 22 years to process existing undetermined land claims.

Delays in processing land claims result in Aboriginal Land Councils being denied the opportunity to realise their statutory right to certain Crown land in NSW. The intent of the Act to provide compensation to Aboriginal people for the dispossession of land has been significantly constrained over time.

Since 2014, numerous reviews have made recommendations to agencies to address systemic issues, improve processes, and enhance outcomes: but DPC and DPE have made limited progress with implementing these. Awareness of the intent and operations of the Act was often poor among staff from some State government agencies and local government representatives we interviewed for the audit.

DPC has not established culturally informed, interagency governance to effectively oversee Aboriginal land claim processes – and ensure accountability for outcomes consistent with the intent of the Act, informed by the expectations of the NSWALC and LALCs. Such governance has not existed since at least 2017 (the audited period) and we have not seen evidence earlier. DPE still does not have performance indicators for its land claim assessment function that are based on a clear analysis of resources, that demonstrate alignment to defined outcomes, and which are reported routinely to key stakeholders, including NSWALC and LALCs.

LALCs have raised strong concerns during our consultations, describing delays in the land claim process and the number of undetermined land claims as disrespectful. LALCs have also noted a lack of transparency in, and opportunity to engage with, Aboriginal land claim processes. DPE’s role in assessing Aboriginal land claims, and identifying opportunities for Aboriginal Land Agreements, requires specific expertise, evidence gathering and an understanding of the complex interaction between the Act and other legislative frameworks, including the Native Title Act 1993 (Cth) and the Crown Land Management Act 2016 (NSW). In mid-2020, DPE created an Aboriginal Land Strategy Directorate within its Crown lands division, increased staffing in land claim assessment functions, and set a target to increase the number of land claims to be granted in 2021–22. In the six months to December 2021, DPE granted more land claims (207 claims) than in most years prior. DPE has also assisted some LALCs to identify priority land claims for assessment.

But the overall number of claims processed per year remains well below the historical (five-year) average number of claims lodged (2,506 claims). As such, DPE has not yet established an appropriately resourced workforce to assess the large number of undetermined land claims and engage effectively with Aboriginal Land Councils and other parties in the process. There also are notable gaps in DPE’s procedures that impact the transparency of the process, especially with respect to timeframes and the prioritisation of land claims for assessment.

DPC (the Office of the Registrar of the Aboriginal Land Rights Act, ORALRA) has not secured or applied resources that would assist the Registrar to use discretionary powers, introduced in 2015, not to refer certain land claims to DPE for assessment (those not on Crown land). This could have improved the efficiency and coordination of end-to-end land claim processes.

DPC (ORALRA) is also not effectively managing data and ensuring the functionality of the statutory Register of Aboriginal land claims. This contributes to inefficient coordination with DPE and NSWALC, and creates a risk of inconsistent information sharing with LALCs, government agencies, local councils and other parties. More broadly, responsibilities for sharing information about the location and status of land under claim are not well defined across agencies. These factors contribute to risks to Crown land with an undetermined land claim, which case law has found to establish inchoate property rights for the claimant Aboriginal Land Council.4 It can also lead to uncertainty around the ownership, use and development of Crown land, with financial implications for various parties.


1 Crown land is land that is owned and managed by the NSW Government.
 AANSW and ORALRA were previously part of the Department of Education, before the 1 July 2019 Machinery of Government changes.
 Previously, these functions were undertaken by the Department of Industry (2017–June 2019) and the Department of Planning, Industry and Environment (July 2019 to December 2021). 
 The lodgement of a land claim creates an unformed property interest for the claimant Aboriginal Land Council over the claimed land. This interest will be realised if the Crown Lands Minister determines that the land is claimable.

Since 1983, 53,861 Aboriginal land claims have been lodged with the Registrar.25

The Land and Environment Court of New South Wales has stated there is an implied obligation on the Crown Lands Minister to determine land claims within a reasonable time.26

As at 31 December 2021, DPE has processed less than a third (31 per cent) of these land claims: 14,273 were determined by the Crown Lands Minister (that is, granted or refused, in whole or part) and 2,562 were withdrawn. This amounts to 16,835 claims processed, including the negotiated settlement of 15 claims through three Aboriginal Land Agreements. As a result, DPE reports that approximately 163,900 hectares of Crown land has been granted to Aboriginal Land Councils since 1983 up to 31 December 2021.

There are 38,257 land claims awaiting determination, which cover about 1.12 million hectares of Crown land.

The 2017 report on the statutory review of the Act noted that the land claims ‘backlog’ was one of the ‘Top 5’ priorities identified by LALCs during consultations. The importance of this issue is consistent with findings from our consultations with LALCs in 2021 (see Exhibit 7).

Exhibit 7: LALCs report that delays undermine the compensatory intent of the Act

LALCs raised concerns about delays in the Aboriginal land claim process, including waiting decades for claims to be assessed and years for land to be transferred once granted.

The large number of undetermined claims has been described by LALCs as disrespectful, and as reflecting under-resourcing by governments.

LALCs reported that these delays undermine the compensatory intent of the Act, including by creating uncertainty for their plans to support the social and economic aspirations of their communities.

Source: NSW Audit Office consultation with LALCs.

Delays in delivering on the statutory requirement to determine land claims, and limited use of other mechanisms to process claims in consultation or agreement with NSWALC and LALCs, undermines the beneficial and remedial intent of Aboriginal land rights under the Act. It also:

  • impacts negatively on DPE’s ability to comply with the statutory requirement to determine land claims, because often the older a claim becomes the more difficult it can be to gather the evidence required to assess it
  • creates uncertainty around the ownership, use and development of Crown land, which can have financial impacts on Aboriginal Land Councils, government agencies, local councils and developers.

Risks that arise in the context of undetermined claims are discussed further in section 3.3.


25 According to DPC (ORALRA) data in the ALC Register up to 31 December 2021. DPC (ORALRA) data indicates that the Registrar has refused to refer claims to DPE for assessment under section 36(4A) of the Act in a small number of cases – for example, seven times in 2017 and none since that time.
26 Jerrinja Local Aboriginal Land Council v Minister Administering the Crown Lands Act [2007] NSWLEC 577 at 125. The Court stated, ‘While a reasonable time may vary on a case-by-case basis, a delay of 15 to 20 years in determining claims does not accord with any idea of reasonableness’.

NSW Treasury describes public sector governance as providing strategic direction, ensuring objectives are achieved, and managing risks and the use of resources responsibly with accountability.

Consistent with the NSW Treasury’s Risk Management Toolkit (TPP-12-03b), governance arrangements for Aboriginal land claim processes should ensure their effective facilitation and administration. That is, arrangements are expected to contribute to and oversee the performance of administrative processes and service delivery towards outcomes, and ensure that legal and policy compliance obligations are met consistent with community expectations of accountability and transparency.

DPC and DPE are responsible for governance and, in partnership with NSWALC, operational and information-sharing activities required to coordinate Aboriginal land claim processes. LALCs, statutory officers, government agencies, local councils, and other parties (such as native title groups and those with an interest in development on Crown land) need to be engaged so that these processes are coordinated effectively with risks managed – consistent with the intent of the Act, and other legislative requirements.

Policy commitments to Aboriginal people and communities made by the NSW Government in the OCHRE Plan and Closing the Gap priority reforms establish an expectation for culturally informed governance.

Exhibit 12: LALCs want their voices to be heard and responded to by government

LALCs expressed a strong desire to have their voices heard so that outcomes in the Aboriginal land claim process are informed by LALC aspirations and consistent with the intent of the Act. The importance of respect and transparency were consistently raised.

The following quotes are from our consultations with LALCs during this audit which illustrate the inherent cultural value of land being returned, as well as the importance of its social and economic value and potential.

There’s batches of land in and around town. This land is significant…We want to get the land activated to encourage economic development, and promote the community…our job is to step up to create infrastructure, employment, maintenance and services and lead by example.

One of the best things we were able to do is develop a long term 20-year plan and where Crown Land could directly see where land was transferred to us and it was going to things like education, housing, health and other social programs…

There has been a claim lodged on a parcel of land that has long lasting cultural significance, a place that is very special to the Aboriginal community members and holds a lot of history. If the claim lodged was successful this land would be used to strengthen the cultural knowledge of the local youth, through placing signage that depicts stories that have been passed down by the Elders, cultural talks and tours and school group visits. This land, although not large in size, has a significant number of cultural trees and artefacts. Aboriginal families and members of the LALC that have lived in our town are very protective of the site and others surrounding it, respecting the importance of the cultural history of the site. There is one, which is a cultural one. We received a land claim that contained a cultural site. This is the high point: we were given back lands that contained rock engravings, carvings. A real diamond for us, especially as an urban based land council.

At the heart of the ALRA is the ability to claim Crown Land…The slow determination of claims gets in the way of us doing what we want to do, which is focus on our communities and address our real needs which are about health, wellbeing and culture. If we could realise these rights, we can address all sorts of socio-economic needs. We would become an economic benefit to the state…If it was operating well there could be more caring for Country too.

Note: Permission has been granted by LALC interviewees to use these quotes in this context.
Source: Excerpts from NSW Audit Office interviews with LALC representatives, facilitated by Indigenous consultants.

The Crown Lands Minister, supported by DPE, is required to determine whether Aboriginal land claims meet the criteria to be ‘claimable Crown lands’ under section 36(1) of the Act. DPE staff within its Crown Lands division are responsible for assessing land claims and preparing recommendation briefs to the Crown Lands Minister, or their delegate, on determination outcomes. That is, on whether to grant or refuse the claim.38 DPE staff also make decisions about which land claims within the large number of undetermined claims should be processed first.

 

Appendix one – Response from agencies

Appendix two – About the audit

Appendix three – Performance auditing

Banner image used with permission.
Title: Forces of Nature
Artist: Lee Hampton – Koori Kicks Art
Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #365 - released 28 April 2022.