Actions for Mental health service planning for Aboriginal people in New South Wales
Mental health service planning for Aboriginal people in New South Wales
A report released by the Auditor-General for New South Wales, Margaret Crawford, has found that NSW Health is not forming effective partnerships with Aboriginal communities to plan, design and deliver appropriate mental health services. There is limited evidence that NSW Health is using the knowledge and expertise of Aboriginal communities to guide how mental health care is structured and delivered.
Mental illness (including substance use disorders) is the main contributor to lower life expectancy and increased mortality in the Aboriginal population of New South Wales. It contributes to a higher burden of disease and premature death at rates that are 40 per cent higher than the next highest chronic disease group, cardiovascular disease.1
Aboriginal people have significantly higher rates of mental illness than non Aboriginal people in New South Wales. They are more likely to present at emergency departments in crisis or acute phases of mental illness than the rest of the population and are more likely to be admitted to hospital for mental health treatments.2
In acknowledgement of the significant health disparities between Aboriginal and non Aboriginal people, NSW Health implemented the NSW Aboriginal Health Plan 2013 2023 (the Aboriginal Health Plan). The overarching message of the Aboriginal Health Plan is ‘to build respectful, trusting and effective partnerships with Aboriginal communities’ and to implement ‘integrated planning and service delivery’ with sector partners. Through the Plan, NSW Health commits to providing culturally appropriate and ‘holistic approaches to the health of Aboriginal people'.
The mental health sector is complex, involving Commonwealth, state and non government service providers. In broad terms, NSW Health has responsibility to support patients requiring higher levels of clinical support for mental illnesses, while the Commonwealth and non government organisations offer non acute care such as assessments, referrals and early intervention treatments.
The NSW Health network includes 15 Local Health Districts and the Justice Health and Forensic Mental Health Network that provide care to patients during acute and severe phases of mental illness in hospitals, prisons and community service environments. This includes care to Aboriginal patients in the community at rates that are more than four times higher than the non Aboriginal population. Community services are usually provided as follow up after acute admissions or interactions with hospital services. The environments where NSW Health delivers mental health care include:
- hospital emergency departments, for short term assessment and referral
- inpatient hospital care for patients in acute and sub acute phases of mental illness
- mental health outpatient services in the community, such as support with medications
- custodial mental health services in adult prisons and juvenile justice centres.
The NSW Government is reforming its mental health funding model to incrementally shift the balance from hospital care to enhanced community care. In 2018–19, the NSW Government committed $400 million over four years into early intervention and specialist community mental health teams.
This audit assessed the effectiveness of NSW Health’s planning and coordination of mental health services and service pathways for Aboriginal people in New South Wales. We addressed the audit objective by answering three questions:
- Is NSW Health using evidence to plan and inform the availability of mental health services for Aboriginal people in New South Wales?
- Is NSW Health collaborating with partners to create accessible mental health service pathways for Aboriginal people?
- Is NSW Health collaborating with partners to ensure the appropriateness and quality of mental health services for Aboriginal people?
NSW Health is not meeting the objectives of the NSW Aboriginal Health Plan, to form effective partnerships with Aboriginal Community Controlled Health Services and Aboriginal communities to plan, design and deliver mental health services.
There is limited evidence that existing partnerships between NSW Health and Aboriginal communities meet its own commitment to use the ‘knowledge and expertise of the Aboriginal community (to) guide the health system at every level, including (for) the identification of key issues, the development of policy solutions, the structuring and delivery of services' 3 and the development of culturally appropriate models of mental health care.
NSW Health is planning and coordinating its resources to support Aboriginal people in acute phases of mental illness in hospital environments. However, it is not effectively planning for the supply and delivery of sufficient mental health services to assist Aboriginal patients to manage mental illness in community environments. Existing planning approaches, data and systems are insufficient to guide the $400 million investment into community mental health services announced in the 2018–19 Budget.
NSW Health is not consistently forming partnerships to ensure coordinated care for patients as they move between mental health services. There is no policy to guide this process and practices are not systematised or widespread.
In this report, the term ‘Aboriginal people’ is used to describe both Aboriginal and Torres Strait Islander peoples. The Audit Office of NSW acknowledges the diversity of traditional countries and Aboriginal language groups across the state of New South Wales.
2 Australian Institute of Health and Welfare data 2016–17 (unaudited).
3 NSW Health, The Aboriginal Health Plan 2013-2023.
In May 2019, the Audit Office of New South Wales invited Aboriginal mental health clinicians and policy experts from government and non-government organisations to attend a one-day workshop. Workshop attendees advised on factors that improve the quality and appropriateness of mental health care for Aboriginal people in New South Wales. They described appropriate mental health care as:
- culturally safe, allowing Aboriginal people to draw strength in their identity, culture and community
- person centred and focussed on individual needs
- delivered by culturally competent staff with no bias
- holistic, trauma-informed and focussed on early intervention where possible
- delivered in places that are appropriate including outreach to homes and communities
- welcoming of the involvement of local Aboriginal community and connected to local knowledge and expertise including totems and kinship structures.
The definition of 'appropriate' mental health care for Aboriginal people throughout this report is based on this advice.
Aboriginal people access emergency services at much higher rates than non-Aboriginal people
The choices that people make in relation to health service options provide some insight into the suitability and appropriateness of the service to their needs.
Aboriginal people have different mental health service use patterns than non-Aboriginal people. Aboriginal people are much more likely to be in a crisis situation before receiving mental health services, usually in an emergency department of a hospital.
Aboriginal people make up three per cent of the total New South Wales population, but they constitute 11 per cent of emergency department presentations for mental health treatments. In regional areas, Aboriginal people make up 20.5 per cent of presentations at emergency departments for mental health reasons.
A number of factors help to explain Aboriginal mental health service usage patterns. According to government and non-government mental health organisations:
- emergency department services are better known to Aboriginal people than other mental health services
- community-based models of care are not appropriate for Aboriginal people
- Aboriginal people are reluctant to access community-based mental health services to prevent crisis situations
- community mental health services are not available for Aboriginal people after hours and during the weekend, so emergency services are the only option.
The statewide proportions of Aboriginal people presenting at emergency departments for mental health treatments has been increasing over time (Exhibit 6).
Appendix one – Response from agency
Appendix two – The NSW Aboriginal Health Plan
Appendix three – About the audit
Appendix four – Performance auditing
Parliamentary Reference: Report number #326 - released 29 August 2019
Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.
Actions for Transport Access Program
Transport Access Program
The following report is available in an Easy English version that is intended to meet the needs of some people with lower literacy skills, some people with an intellectual disability and some people from different cultural backgrounds.
View the Easy English version of the Transport Access Program report
Transport for NSW’s process for selecting and prioritising projects for the third stage of its Transport Access Program balanced compliance with national disability standards with broader customer outcomes. Demographics, deliverability and value for money were also considered. However, Transport for NSW does not know the complete scope of work required for full compliance, limiting its ability to demonstrate that its approach is effective, according to a report released today by the Auditor-General for New South Wales, Margaret Crawford.
Access to transport is critical to ensuring that people can engage in all aspects of community life, including education, employment and recreation. People with disability can encounter barriers when accessing public transport services. In 2015, there were 1.37 million people living with disability in New South Wales.
Accessible public transport is about more than physical accessibility. It also means barrier-free access for people who have vision, hearing or cognitive impairments. All users, not just people with disability, benefit from improvements to the accessibility and inclusiveness of transport services.
Transport for NSW has an obligation under Australian Government legislation to provide accessible services to people with disabilities in a manner which is not discriminatory. Under the Disability Standards for Accessible Public Transport 2002 (the DSAPT - an instrument of the Disability Discrimination Act 1992 (the Act) (Commonwealth)), there is a requirement to modify and develop new infrastructure, means of transport and services to provide access for people with disabilities. All public transport operators are required to ensure that at least 90 per cent of their networks met DSAPT by December 2017 and the networks will need to be 100 per cent compliant with all parts of the standards by 31 December 2022. Trains are not required to be fully compliant with DSAPT until December 2032.
The Transport Access Program (TAP) is Transport for NSW's largest program with a specific focus on improving access to public transport for people with disability. The TAP is a series of projects to upgrade existing public transport infrastructure across four networks: Sydney Trains, Intercity Trains, Regional Trains and Sydney Ferries. Transport for NSW established the TAP as a rolling program and, to date, it has delivered the first tranche of TAP (TAP 1) and is completing the final projects for the second tranche (TAP 2). NSW budget papers estimate that by 30 June 2018, Transport for NSW had spent $1.2 billion in the TAP since its commencement in 2011-12.
After the completion of TAP 1 and TAP 2 (as well as through other transport infrastructure programs), Transport for NSW estimates that 58.5 per cent of the Sydney Trains, Regional Trains and Intercity Trains networks, and 66 per cent of the Sydney Ferries network, will be accessible. To close the significant gap in compliance with the DSAPT target, the objective for TAP 3 is ‘to contribute to Disability Discrimination Act 1992 related targets through DSAPT compliance upgrades’.
The audit assessed whether Transport for NSW has an effective process to select and prioritise projects as part of the TAP, with a specific focus on the third tranche of TAP funding.
In August 2018, at the commencement of this audit, Transport for NSW intended to complete the selection of projects for the TAP 3 final business case in December 2018. Transport for NSW advise that it now intends to complete the development stage and final business case in the first quarter of 2019, prior to the final investment decision of the TAP program. This report is based on the TAP 3 strategic business case and information provided by Transport for NSW up to December 2018.
Transport for NSW’s process for selecting and prioritising projects for TAP 3 balanced DSAPT compliance goals with broader customer outcomes. It also considered demographics, deliverability and value for money. However, Transport for NSW does not know the complete scope of work required for full DSAPT compliance, and this limits its ability to demonstrate that its approach is effective.
In 2015, there were 1.37 million people living with disability in New South Wales. Access to transport is critical to ensuring that people can engage in all aspects of community life, including education, employment and recreation. People with disability can encounter barriers when accessing public transport services.
The social model of disability, outlined in the United Nations Convention on the Rights of Persons with Disabilities, views people with disability as not disabled by their impairment but by the barriers in the community and environment that restrict their full and effective participation in society on an equal basis with others.
Accessible public transport is more than the provision of physical access to premises and conveyances, it provides barrier-free access for people who have vision, hearing or cognitive impairments. All users, not just people with disability, benefit from improvements to the accessibility and inclusiveness of transport services.
According to the Australian Bureau of Statistics, the main types of difficulties experienced by people with disability when using public transport relate to steps (39.9 per cent), difficulty getting to stops and stations (25 per cent), fear and anxiety (23.3 per cent) and lack of seating or difficulty standing (20.7 per cent).
Transport for NSW has a Disability Inclusion Action Plan (the Action Plan) 2018-2022 that sets an overall framework for planning, delivering and reporting on initiatives to increase accessibility of the transport network. It covers all elements of the journey experienced when using public transport, including journey planning, staff training, customer services and interaction between the physical environment and modes of transport. Appendix five outlines the guiding principles of the Action Plan.
Transport for NSW's Transport Social Policy branch developed the Action Plan in consultation with internal and external stakeholders. The director of the Transport Social Policy branch is a member of the TAP executive steering committee, which supports alignment between the Action Plan and TAP.
Transport for NSW's Disability Inclusion Action Plan describes a customer focussed approach to accessibility
One of the guiding principles of the Action Plan is ‘intelligent compliance’. Transport for NSW describes this as compliance that prioritises customer-focused outcomes over a narrow focus on legal compliance with accessibility standards. As well as being compliant, infrastructure should be practical, usable, fit for purpose and convenient.
The TAP prioritisation and selection methodology reflects Transport for NSW’s focus on intelligent compliance. We consider this a reasonable approach as had Transport for NSW focussed exclusively on achieving compliance with the DSAPT targets by upgrading the most affordable infrastructure, some locations, that are used by more customers, would remain inaccessible to people with disability. However, this approach should not be seen as an alternative to Transport for NSW meeting its DSAPT compliance obligations.
TAP program staff consult with the Accessible Transport Advisory Committee
The Accessible Transport Advisory Committee (ATAC) has representatives from disability and ageing organisations, who provide expert guidance to Transport for NSW on access and inclusion. The ATAC provide guidance and feedback on projects and project solutions, including user testing where appropriate. TAP program staff provide regular updates at ATAC meetings, which include briefings on progress. The ATAC also provides feedback and suggestions to TAP program staff, which is considered and sometimes included in current and future projects.For example, in March 2017 the TAP program team briefed the ATAC on the challenges with respect to a number of ferry wharves and sought support for DSAPT exemptions proposed in the TAP 3 strategic business case.
In June 2018, the Program team sought feedback on a variety of lift button options to improve accessibility on future TAP projects. In September 2018, during the ATAC meeting attended by the Audit Office, the program team sought feedback on the standard designs for TAP 3. Some ATAC members noted that the standard design included Braille lettering on the lift buttons, and that this was not good practice because people can accidently press the button while reading it. As a result, Transport for NSW are incorporating this feedback into design requirements for the lifts for TAP 3, which will consider larger buttons, clearer Braille and Braille signage adjacent to the button. |
Transport for NSW has not briefed the Advisory Committee on the outcome of the prioritisation and selection process
TAP program staff briefed the Advisory Committee about the prioritisation and selection methodology, after the Minister approved it in 2016. However, Transport for NSW have not briefed or consulted the Advisory Committee on the outcome of the prioritisation process. Infrastructure NSW noted this issue during its review of the strategic business case.
Transport for NSW advised us that it established the ATAC as an advisory group, and that Transport for NSW does not disclose sensitive information to it. Transport for NSW intends to share the outcome of the prioritisation process following the completion of the TAP 3 development stage and final investment decision.
The TAP communication plan does not fully meet the requirements of the Disability Inclusion Action Plan
The Disability Inclusion Action Plan includes an action item to ‘provide a listing of stations and wharves to be upgraded with estimated time of construction as each new tranche of the Transport Access Program is announced’ The TAP Communication Plan that we reviewed does not include this provision instead focussing on communication on a per project basis. Given the long timeframes associated with improving transport infrastructure, this information is important as it allows people to make informed decisions about where they live, work or study.
Appendix one - Response from agency
Appendix two - Compliance requirements of Disability Standards for Accessible Public Transport
Appendix three - TAP 1 and TAP 2 sub-programs
Appendix four - Prioritisation Assessment for the TAP 3 Strategic Business Case
Appendix five - The guiding principles of Transport for NSW's Disability Inclusion Action Plan
Appendix six - Transport projects and programs that contribute to DSAPT compliance
Appendix seven - About the audit
Appendix eight - Performance auditing
Parliamentary Reference - Report number #314 - released 19 February 2019.
Actions for Unsolicited proposal process for the lease of Ausgrid
Unsolicited proposal process for the lease of Ausgrid
In October 2016, the NSW Government accepted an unsolicited proposal from IFM Investors and AustralianSuper to lease 50.4 per cent of Ausgrid for 99 years. The deal followed the Federal Government’s rejection of two bids from foreign investors, for national security reasons.
A performance audit of the lease of Ausgrid has found shortcomings in the unsolicited proposal process. Releasing the audit findings today, the Auditor-General for New South Wales, Margaret Crawford said ‘this transaction involved a $20 billion asset owned by the people of New South Wales. As such, it warranted strict adherence to established guidelines’.
Ausgrid is a distributor of electricity to eastern parts of Sydney, the Central Coast, Newcastle and the Hunter Region.
In June 2014, the then government announced its commitment to lease components of the state's electricity network as part of the Rebuilding NSW plan. Implementation of the policy began after the government was re-elected in 2015. Between November 2015 and August 2016, the NSW Government held a competitive tender process to lease 50.4 per cent of Ausgrid for 99 years. The NSW Government abandoned the process on 19 August 2016 after the Australian Treasurer rejected two bids from foreign investors, for national security reasons. That day, the Premier and Treasurer released a media statement clarifying the government's objective to complete the transaction via a competitive process in time to include the proceeds in the 2017–18 budget.
On 31 August 2016, the state received an unsolicited proposal from IFM Investors and AustralianSuper to acquire an interest in Ausgrid under the same terms proposed by the state during the tender process. In October 2016, the government accepted the unsolicited proposal.
This audit examined whether the unsolicited proposal process for the partial long-term lease of Ausgrid was effectively conducted and in compliance with the government’s 2014 Unsolicited Proposals: Guide for Submission and Assessment (Unsolicited Proposals Guide or the Guide).
The audit focused on how the government-appointed Assessment Panel and Proposal Specific Steering Committee assessed key requirements in the Guide that unsolicited proposals must be demonstrably unique and represent value for money.
The evidence available does not conclusively demonstrate the unsolicited proposal was unique, and there were some shortcomings in the negotiation process, documentation and segregation of duties. That said, before the final commitment to proceed with the lease, the state obtained assurance that the proposal delivered value for money.
It is particularly important to demonstrate unsolicited proposals are unique, in order to justify the departure from other transaction processes that offer greater competition, transparency and certainty about value for money.
The Assessment Panel and the Proposal Specific Steering Committee determined the Ausgrid unsolicited proposal was unique, primarily on the basis that the proponent did not require foreign investment approval from the Australian Treasurer, and the lease transaction could be concluded earlier than through a second tender process. However, the evidence that persuaded the Panel and Committee did not demonstrate that no other proponent could conclude the transaction in time to meet the government’s deadline.
It is not appropriate to determine an unsolicited proposal is unique because it delivers an earlier outcome than possible through a tender process. The Panel and Committee did not contend, and it is not evident, that the unsolicited proposal was the only way to meet the government’s transaction deadline.
The evidence does not demonstrate that the proponent was the only party that would not have needed foreign investment approval to participate in the transaction. It also does not demonstrate that the requirement for foreign investment approval would have reduced the pool of foreign buyers to the degree that it would be reasonable to assume none would emerge.
The Panel, Committee and financial advisers determined that the final price represented value for money, and that retendering offered a material risk of a worse financial outcome. However, an acceptable price was revealed early in the negotiation process, and doing so made it highly unlikely that the proponent would offer a higher price than that disclosed. The Department of Premier and Cabinet (DPC) and NSW Treasury were not able to provide a documented reserve price, bargaining strategy or similar which put the negotiations in context. It is not evident that the Panel or Committee authorised, justified or endorsed negotiations in advance.
Key aspects of governance recommended by the Guide were in place. Some shortcomings relating to role segregation, record keeping and probity assurance weakened the effectiveness of the unsolicited proposal process adopted for Ausgrid.
The reasons for accepting that the proposal and proponent were unique are not compelling.
The Unsolicited Proposals Guide says the 'unique benefits of the proposal and the unique ability of the proponent to deliver the proposal' must be demonstrated.
The conclusion reached by the Panel and Committee that the proposal offered a ‘unique ability to deliver (a) strategic outcome’ was primarily based on the proponent not requiring foreign investment approval from the Australian Treasurer, and allowing the government to complete the lease transaction earlier than by going through a second tender process.
It is not appropriate to determine an unsolicited proposal is unique because it delivers an earlier outcome than possible through a tender process. The Panel and Committee did not contend, and it is not evident, that the unsolicited proposal was the only way to meet the government’s transaction deadline.
The evidence does not demonstrate that the proponent was the only party that would not have needed foreign investment approval to participate in the transaction. Nor does it demonstrate that the requirement for foreign investment approval would have reduced the pool of foreign buyers to the degree that it would be reasonable to assume none would emerge.
That said, the Australian Treasurer’s decision to reject the two bids from the previous tender process created uncertainty about the conditions under which he would approve international bids. The financial advisers engaged for the Ausgrid transaction informed the Panel and Committee that:
- it was not likely another viable proponent would emerge soon enough to meet the government’s transaction deadline
- the market would be unlikely to deliver a better result than offered by the proponent
- going to tender presented a material risk of a worse financial result.
The Unsolicited Proposals Guide says that a proposal to directly purchase or acquire a government-owned entity or property will generally not be unique. The Ausgrid unsolicited proposal fell into this category.
Recommendations:
DPC should ensure future Assessment Panels and Steering Committees considering a proposal to acquire a government business or asset:
- recognise that when considering uniqueness they should:
- require very strong evidence to decide that both the proponent and proposal are the only ones of their kind that could meet the government’s objectives
- give thorough consideration to any reasonable counter-arguments against uniqueness.
- rigorously consider all elements of the Unsolicited Proposals Guide when determining whether a proposal should be dealt with as an unsolicited proposal, and document these deliberations and all relevant evidence
- do not use speed of transaction compared to a market process as justification for uniqueness.
The Panel and Committee concluded the price represented value for money, based on peer-reviewed advice from their financial advisers and knowledge acquired from previous tenders. The financial advisers also told the Panel and Committee that there was a material risk the state would receive a lower price than offered by the unsolicited proposal if it immediately proceeded with a second market transaction.
The state commenced negotiations on price earlier than the Guide says they should have. Early disclosure of a price that the state would accept reduced the likelihood of achieving a price greater than this. DPC says the intent of this meeting was to quickly establish whether the proponents could meet the state’s benchmark rather than spending more time and resources on a proposal which had no prospect of proceeding.
DPC and NSW Treasury were not able to provide a documented reserve price, negotiation strategy or similar which put the negotiations and price achieved in context. It was not evident that the Panel or Committee authorised, justified or endorsed negotiations in advance. However, the Panel and Committee endorsed the outcomes of the negotiations.
The negotiations were informed by the range of prices achieved for similar assets and the specific bids for Ausgrid from the earlier market process.
Recommendations:
DPC should ensure any future Assessment Panels and Steering Committees considering a proposal to acquire a government business or asset:
- document a minimum acceptable price, and a negotiating strategy designed to maximise price, before commencing negotiations
- do not communicate an acceptable price to the proponent, before the negotiation stage of the process, and then only as part of a documented bargaining strategy.
The state established a governance structure in accordance with the Unsolicited Proposals Guide, including an Assessment Panel and Proposal Specific Steering Committee. The members of the Panel and Steering Committee were senior and experienced officers, as befitted the size and nature of the unsolicited proposal.
The separation of negotiation, assessment and review envisaged by the Guide was not maintained fully. The Chair of the Assessment Panel and a member of the Steering Committee were involved in negotiations with the proponent.
DPC could not provide comprehensive records of some key interactions with the proponent or a documented negotiation strategy. The absence of such records means the Department cannot demonstrate engagement and negotiation processes were authorised and rigorous.
The probity adviser reported there were no material probity issues with the transaction. The probity adviser also provided audit services. This is not good practice. The same party should not provide both advisory and audit services on the same transaction.
Recommendations:
DPC should ensure any future Assessment Panels and Steering Committees considering a proposal to acquire a government entity or asset:
• maintain separation between negotiation, assessment and review in line with the Unsolicited Proposals Guide
• keep an auditable trail of documentation relating to the negotiation process
• maintain separation between any probity audit services engaged and the probity advisory and reporting services recommended in the current Guide.
Appendix one - Response from agency
Appendix two - NSW Government’s summary of assessment of the Ausgrid unsolicited proposal
Appendix three - The definition and nature of unsolicited proposals
Appendix four - Ausgrid unsolicited proposal process
Appendix five - About the audit
Appendix six - Performance auditing
Parliamentary reference - Report number #309 - released 11 December 2018
Actions for Mobile speed cameras
Mobile speed cameras
The primary goal of speed cameras is to reduce speeding and make the roads safer. Our 2011 performance audit on speed cameras found that, in general, speed cameras change driver behaviour and have a positive impact on road safety.
Transport for NSW published the NSW Speed Camera Strategy in June 2012 in response to our audit. According to the Strategy, the main purpose of mobile speed cameras is to reduce speeding across the road network by providing a general deterrence through anywhere, anytime enforcement and by creating a perceived risk of detection across the road network. Fixed and red-light speed cameras aim to reduce speeding at specific locations.
Roads and Maritime Services and Transport for NSW deploy mobile speed cameras (MSCs) in consultation with NSW Police. The cameras are operated by contractors authorised by Roads and Maritime Services. MSC locations are stretches of road that can be more than 20 kilometres long. MSC sites are specific places within these locations that meet the requirements for a MSC vehicle to be able to operate there.
This audit assessed whether the mobile speed camera program is effectively managed to maximise road safety benefits across the NSW road network.
The mobile speed camera program requires improvements to key aspects of its management to maximise road safety benefits. While camera locations have been selected based on crash history, the limited number of locations restricts network coverage. It also makes enforcement more predictable, reducing the ability to provide a general deterrence. Implementation of the program has been consistent with government decisions to limit its hours of operation and use multiple warning signs. These factors limit the ability of the mobile speed camera program to effectively deliver a broad general network deterrence from speeding.
Many locations are needed to enable network-wide coverage and ensure MSC sessions are randomised and not predictable. However, there are insufficient locations available to operate MSCs that meet strict criteria for crash history, operator safety, signage and technical requirements. MSC performance would be improved if there were more locations.
A scheduling system is meant to randomise MSC location visits to ensure they are not predictable. However, a relatively small number of locations have been visited many times making their deployment more predictable in these places. The allocation of MSCs across the time of day, day of week and across regions is prioritised based on crash history but the frequency of location visits does not correspond with the crash risk for each location.
There is evidence of a reduction in fatal and serious crashes at the 30 best-performing MSC locations. However, there is limited evidence that the current MSC program in NSW has led to a behavioural change in drivers by creating a general network deterrence. While the overall reduction in serious injuries on roads has continued, fatalities have started to climb again. Compliance with speed limits has improved at the sites and locations that MSCs operate, but the results of overall network speed surveys vary, with recent improvements in some speed zones but not others.
There is no supporting justification for the number of hours of operation for the program. The rate of MSC enforcement (hours per capita) in NSW is less than Queensland and Victoria. The government decision to use multiple warning signs has made it harder to identify and maintain suitable MSC locations, and impeded their use for enforcement in both traffic directions and in school zones.
Appendix one - Response from agency
Appendix two - About the audit
Appendix three - Performance auditing
Parliamentary reference - Report number #308 - released 18 October 2018
Actions for Progress and measurement of the Premier's Priorities
Progress and measurement of the Premier's Priorities
The Premier’s Implementation Unit uses a systematic approach to measuring and reporting progress towards the Premier’s Priorities performance targets, but public reporting needed to improve, according to a report released today by the Auditor-General of NSW, Margaret Crawford.
The Premier of New South Wales has established 12 Premier’s Priorities. These are key performance targets for government.
The 12 Premier's Priorities | |
---|---|
|
|
|
|
|
|
|
|
|
|
|
|
Source: Department of Premier and Cabinet, Premier’s Priorities website.
Each Premier’s Priority has a lead agency and minister responsible for achieving the performance target.
The Premier’s Implementation Unit (PIU) was established within the Department of Premier and Cabinet (DPC) in 2015. The PIU is a delivery unit that supports agencies to measure and monitor performance, make progress toward the Premier’s Priorities targets, and report progress to the Premier, key ministers and the public.
This audit assessed how effectively the NSW Government is progressing and reporting on the Premier's Priorities.
The Premier’s Implementation Unit (PIU) is effective in assisting agencies to make progress against the Premier’s Priorities targets. Progress reporting is regular but transparency to the public is weakened by the lack of information about specific measurement limitations and lack of clarity about the relationship of the targets to broader government objectives.The PIU promotes a systematic approach to measuring performance and reporting progress towards the Premier’s Priorities’ performance targets. Public reporting would be improved with additional information about the rationale for choosing specific targets to report on broader government objectives.
The PIU provides a systematic approach to measuring performance and reporting progress towards the Premier's Priorities performance targets. Public reporting would be improved with additional information about the rationale for choosing specific targets to report on broader government objectives. The data used to measure the Premier’s Priorities comes from a variety of government and external datasets, some of which have known limitations. These limitations are not revealed in public reporting, and only some are revealed in progress reported to the Premier and ministers. This limits the transparency of reporting.
The PIU assists agencies to avoid unintended outcomes that can arise from prioritising particular performance measures over other areas of activity. The PIU has adopted a collaborative approach to assisting agencies to analyse performance using data, and helping them work across organisational silos to achieve the Premier’s Priorities targets.
Data used to measure progress for some of the Premier’s Priorities has limitations which are not made clear when progress is reported. This reduces transparency about the reported progress. Public reporting would also be improved with additional information about the relationship between specific performance measures and broader government objectives.
The PIU is responsible for reporting progress to the Premier, key ministers and the public. Agencies provide performance data and some play a role in preparing progress reports for the Premier and ministers. For 11 of the Premier's Priorities, progress is reported against measurable and time-related performance targets. For the infrastructure priority, progress is reported against project milestones.
Progress of some Priorities is measured using data that has known limitations, which should be noted wherever progress is reported. For example, the data used to report on housing completions does not take housing demolitions into account, and is therefore overstating the contribution of this performance measure to housing supply. This known limitation is not explained in progress reports or on the public website.
Data used to measure progress is sourced from a mix of government and external datasets. Updated progress data for most Premier’s Priorities is published on the Premier’s Priorities website annually, although reported to the Premier and key ministers more frequently. The PIU reviews the data and validates it through fieldwork with front line agencies. The PIU also assists agencies to avoid unintended outcomes that can arise from prioritising single performance measures. Most, but not all, agencies use additional indicators to check for misuse of data or perverse outcomes.
We examined the reporting processes and controls for five of the Premier’s Priorities. We found that there is insufficient assurance over the accuracy of the data on housing approvals.
The relationships between performance measures and broader government objectives is not always clearly explained on the Premier’s Priority website, which is the key source of public information about the Premier’s Priorities. For example, the Premier’s Priority to reduce litter volumes is communicated as “Keeping our Environment Clean.” While the website explains why reducing litter is important, it does not clearly explain why that particular target has been chosen to measure progress in keeping the environment clean.
By December 2018, the Department of Premier and Cabinet should:
- improve transparency of public reporting by:
- providing information about limitations of reported data and associated performance
- clarifying the relationship between the Premier’s Priorities performance targets and broader government objectives.
- ensure that processes to check and verify data are in place for all agency data sources
- encourage agencies to develop and implement additional supporting indicators for all Premier’s Priority performance measures to prevent and detect unintended consequences or misuse of data.
The Premier's Implementation Unit is effective in supporting agencies to deliver progress towards the Premier’s Priority targets.
The PIU promotes a systematic approach to monitoring and reporting progress against a target, based on a methodology used in delivery units elsewhere in the world. The PIU undertakes internal self-evaluation, and commissions regular reviews of methodology implementation from the consultancy that owns the methodology and helped to establish the PIU. However, the unit lacks periodic independent reviews of their overall effectiveness. The PIU has adopted a collaborative approach and assists agencies to analyse performance using data, and work across organisational silos to achieve the Premier’s Priorities targets.
Agency representatives recognise the benefits of being responsible for a Premier's Priority and speak of the value of being held to account and having the attention of the Premier and senior ministers.
By June 2019, the Department of Premier and Cabinet should:
- establish routine collection of feedback about PIU performance including:
- independent assurance of PIU performance
- opportunity for agencies to provide confidential feedback.
Appendix one: Response from agency
Appendix three: About the audit
Appendix four: Performance auditing
Parliamentary reference - Report number #307 - released 13 September 2018
Actions for Managing demand for ambulance services 2017
Managing demand for ambulance services 2017
NSW Ambulance has introduced several initiatives over the past decade to better manage the number of unnecessary ambulance responses and transports to hospital emergency departments. However, there is no overall strategy to guide the development of these initiatives nor do NSW Ambulance's data systems properly monitor their impact. As a result, the Audit Office was unable to assess whether NSW Ambulance's approach to managing demand is improving the efficiency of ambulance services.
NSW Ambulance uses a telephone referral system to manage triple zero calls from people with medical issues that do not require an ambulance. This has the potential to achieve efficiency improvements but there are weaknesses in NSW Ambulance's use and monitoring of this system. Paramedics are now able to make decisions about whether patients need transport to a hospital emergency department. NSW Ambulance does not routinely measure or monitor the decisions paramedics make, so it does not know whether these decisions are improving efficiency. Extended Care Paramedics who have additional skills in diagnosing and treating patients with less urgent medical issues were introduced in 2007. NSW Ambulance analysis indicates that these paramedics have the potential to improve efficiency, but have not been used as effectively as possible.
Our 2013 audit of NSW Ambulance found that accurate monitoring of activity and performance was not being conducted. More than four years later, this remains the case.
NSW Ambulance has recognised the need to change the way it manages demand and has developed initiatives that have the potential to improve efficiency. However, there are significant weaknesses in the strategy for and implementation of its demand management initiatives.
NSW Ambulance has identified the goal of moving from an emergency transport provider to a mobile health service and developed several initiatives to support this. Its demand management initiatives have the potential to contribute to the broader policy directions for the health system in New South Wales. However, there is no clear overall strategy guiding these initiatives and their implementation has been poor.
NSW Ambulance's reasons for changing its approach to demand management have not been communicated proactively to the community. Demand management initiatives that have been operating for over a decade still do not have clear performance measures or targets. Project management of new initiatives has been inadequate, with insufficient organisational resources to oversee them and inadequate engagement with other healthcare providers.
NSW Ambulance uses an in-house Vocational Education and Training course to recruit some paramedics, as well as recruiting paramedics who have completed a university degree. No other Australian ambulance services continue to provide their own Vocational Education and Training qualifications. Paramedics will need more support in several key areas to be able to fulfil their expanded roles in providing a mobile health service. Performance and development systems for paramedics are not used effectively. Up to date technology would help paramedics make better decisions and improve NSW Ambulance's ability to monitor demand management activity.
There are gaps in NSW Ambulance's oversight of the risks of some of the initiatives it has introduced, particularly its lack of information on the outcomes for patients who are not transported to hospital. Weaknesses in the way NSW Ambulance uses its data limit its ability to properly assess the risks of the demand management initiatives it has introduced.
Parliamentary reference - Report number #295 - released 13 December 2017
Actions for Planning and evaluating palliative care services in NSW
Planning and evaluating palliative care services in NSW
NSW Health’s approach to planning and evaluating palliative care is not effectively coordinated. There is no overall policy framework for palliative and end-of-life care, nor is there comprehensive monitoring and reporting on services and outcomes.
Parliamentary reference - Report number #291 - released 17 August 2017
Actions for Passenger Rail Punctuality
Passenger Rail Punctuality
Rail agencies are well placed to manage the forecast increase in passengers up to 2019, including joining the Sydney Metro Northwest to the network at Chatswood. Their plans and strategies are evidence-based, and mechanisms to assure effective implementation are sound.
Appendix one - Response from the agencies
Appendix two - Response from Audit Office
Appendix three - About the audit
Appendix four - Accuracy of punctuality measurement
Appendix five - Train and customer punctuality
Parliamentary reference - Report number #281 - released 11 April 2017
Actions for CBD and South East Light Rail Project
CBD and South East Light Rail Project
Transport for NSW did not effectively plan and procure the CBD and South East Light Rail (CSELR) project to achieve best value for money according to a report released today by NSW Auditor-General, Margaret Crawford.
Transport for NSW is on track to deliver the project, but it will come at a higher cost with lower benefits than in the approved business case.
Parliamentary reference - Report number #278 - released 30 November 2016
Actions for Implementation of the NSW Government’s program evaluation initiative
Implementation of the NSW Government’s program evaluation initiative
The NSW Government’s ‘program evaluation initiative’, introduced to assess whether service delivery programs achieve expected outcomes and value for money, is largely ineffective according to a report released today by NSW Auditor-General, Margaret Crawford.
Government services, in areas such as public order and safety, health and education, are delivered by agencies through a variety of programs. In 2016–17, the NSW Government estimates that it will spend over $73 billion on programs to deliver services.
Parliamentary reference - Report number #277 - released 3 November 2016