Actions for Volume Nine 2010 focus on Transport, Planning and Industry
Volume Nine 2010 focus on Transport, Planning and Industry
The report includes comments on his financial audits of NSW Government transport, planning and industry agencies for 2009-10. A key recommendation from the report is that the New South Wales Government identify lessons learnt from the metro experience and ensure that future decision processes are developed to ensure the State never again expends such a large amount of scarce transport funding dollars and valuable time on a project that does not proceed.
Actions for Volume Six 2010 focus on Human Services and Technology
Volume Six 2010 focus on Human Services and Technology
The report includes comments on his financial audits of NSW Government human services and technology agencies. The audits of these agencies’ financial reports for the year ended 30 June 2010 each resulted in an unqualified Independent Auditor’s Report. The number of supported accommodation places for people with a disability has increased by 517 during 2009-10.
Actions for Volume Five 2010 focus on Public Financing Enterprises
Volume Five 2010 focus on Public Financing Enterprises
The report includes comments on NSW Treasury and agencies in the finance and superannuation sectors. The New South Wales public sector superannuation funds’ investments were $42.2 billion at 30 June 2010, up from $38.5 billion in 2009. Investment returns reached 14.5 per cent in 2009-10. This is a significant improvement on the investment returns of up to negative 18.4 per cent at the peak of the global financial crisis in 2008.
Actions for Helicopter Emergency Medical Service Contract
Helicopter Emergency Medical Service Contract
We found that the contract process was satisfactory. Ambulance data show that the performance of CHC is meeting contract requirements with the exception of the availability of the Wollongong helicopter. Ambulance’s ability to transport patients to the right hospital at the right time has improved. However the cost of the new Greater Sydney helicopter contract is three times higher than before.
Parliamentary reference - Report number #206 - released 22 September 2010
Actions for Volume Two 2010 focus on Universities
Volume Two 2010 focus on Universities
New South Wales’ ten universities recorded a combined operating surplus of $494 million compared to a deficit of $76.9 million last year, reflecting the improvement in global financial markets. This was largely due to investment gains of $38.0 million in 2009 compared to $405 million of losses in 2008. Despite this, financial risks remain for universities. With the recovery in global financial markets remaining fragile, universities with overseas operations and those needing to fund capital works programs, are at most risk. Capital funding is estimated at $2.0 billion for 2010 and 2011.
Actions for Volume One 2010
Volume One 2010
The report includes comments on his annual audit of entitlements paid to Members of NSW Parliament and financial audits of WorkCover, Justice Health, Waste Recycling Processing Corporation and some other NSW Government agencies.
In his audit the Auditor-General had called for a system to be developed to ensure accrued loyalty/reward benefits are used to reduce Members’ parliamentary business travel expenditure, rather than be forfeited when a Member leaves Parliament. He also called for better controls over the Logistic Support Allocation used for transport, communications, printing, stationery, office supplies and equipment.
Actions for Improving the Performance of Metropolitan Bus Services
Improving the Performance of Metropolitan Bus Services
The 2004 Review of Bus Services in NSW always envisaged that there would be a transition period as the new bus contracts were introduced. NSWTI has developed and implemented the new arrangements, and pursued a range of new initiatives including the network improvement program, strategic corridors and uniform bus fares and concessions. The new contracts provided for a performance management regime to hold operators accountable. But this is still being developed four years after the bus contracts came into effect and it remains unproven as a basis for ensuring value for money from the contracts - each of which guarantees monopoly rights to the operators.
Parliamentary reference - Report number #198 - released 10 March 2010
Actions for Managing Forensic Analysis: Fingerprints and DNA
Managing Forensic Analysis: Fingerprints and DNA
Fingerprints and DNA play a critical role in solving crime and serving justice, but DNA evidence can result in more arrests, more prosecutions and more convictions. We found that while police effectively prioritise fingerprint evidence, it could better manage the screening and analysis of both fingerprint and DNA evidence to reduce delays.
Parliamentary reference - Report number #195 - released 10 February 2010
Actions for Condition of State Roads
Condition of State Roads
The Roads and Traffic Authority (RTA) has improved the overall surface condition of State Roads in the last decade. Country road surfaces are now generally much better. Ride quality has improved and cracking has been reduced. The RTA has also achieved a substantial reduction in the number of structurally deficient bridges over the same period.
Despite a significant increase in the State’s contribution to maintenance since 1999-2000, the RTA has deferred road rebuilding projects. The RTA is rebuilding at less than half its long term target, and has not met this target at any time this decade. The RTA has not identified how it will address deferred rebuilding, although it advises it is developing a new road network management plan which will address this.
Parliamentary reference - Report number #157 - released 16 August 2006
Actions for The Cross City Tunnel Project
The Cross City Tunnel Project
In our opinion the Government’s ‘no net cost to government’ requirement was a legitimate (but not the only possible) basis for the tunnel bid process. The Government was entitled to decide that tunnel users meet the tunnel costs. Structuring the bid process on the basis of an upfront reimbursement of costs incurred (or to be incurred) by the Roads and Traffic Authority (RTA) was therefore appropriate.
In our opinion, however, the Government, Treasury and the RTA did not sufficiently consider the implications of an upfront payment involving more than simple project cost reimbursement (i.e. the ‘Business Consideration Fee’ component). In addition, the RTA was wrong to change the toll escalation factor late in 2002 to compensate the tunnel operator, Cross City Motorway Pty Ltd, for additional costs.
Parliamentary reference - Report number #152 - released 31 May 2006