Actions for Engagement of probity advisers and probity auditors

Engagement of probity advisers and probity auditors

Transport
Education
Health
Compliance
Internal controls and governance
Procurement
Project management
Workforce and capability

Three key agencies are not fully complying with the NSW Procurement Board’s Direction for engaging probity practitioners, according to a report released today by the Acting Auditor-General for New South Wales, Ian Goodwin. They also do not have effective processes to achieve compliance or assure that probity engagements achieved value for money.

Probity is defined as the quality of having strong moral principles, honesty and decency. Probity is important for NSW Government agencies as it helps ensure decisions are made with integrity, fairness and accountability, while attaining value for money.

Probity advisers provide guidance on issues concerning integrity, fairness and accountability that may arise throughout asset procurement and disposal processes. Probity auditors verify that agencies' processes are consistent with government laws and legislation, guidelines and best practice principles. 

According to the NSW State Infrastructure Strategy 2018-2038, New South Wales has more infrastructure projects underway than any state or territory in Australia. The scale of the spend on procuring and constructing new public transport networks, roads, schools and hospitals, the complexity of these projects and public scrutiny of aspects of their delivery has increased the focus on probity in the public sector. 

A Procurement Board Direction, 'PBD-2013-05 Engagement of probity advisers and probity auditors' (the Direction), sets out the requirements for NSW Government agencies' use and engagement of probity practitioners. It confirms agencies should routinely take into account probity considerations in their procurement. The Direction also specifies that NSW Government agencies can use probity advisers and probity auditors (probity practitioners) when making decisions on procuring and disposing of assets, but that agencies:

  • should use external probity practitioners as the exception rather than the rule
  • should not use external probity practitioners as an 'insurance policy'
  • must be accountable for decisions made
  • cannot substitute the use of probity practitioners for good management practices
  • not engage the same probity practitioner on an ongoing basis, and ensure the relationship remains robustly independent. 

The scale of probity spend may be small in the context of the NSW Government's spend on projects. However, government agencies remain responsible for probity considerations whether they engage external probity practitioners or not.

The audit assessed whether Transport for NSW, the Department of Education and the Ministry of Health:

  • complied with the requirements of ‘PBD-2013-05 Engagement of Probity Advisers and Probity Auditors’
  • effectively ensured they achieved value for money when they used probity practitioners.

These entities are referred to as 'participating agencies' in this report.

We also surveyed 40 NSW Government agencies with the largest total expenditures (top 40 agencies) to get a cross sector view of their use of probity practitioners. These agencies are listed in Appendix two.

Conclusion

We found instances where each of the three participating agencies had not fully complied with the requirements of the NSW Procurement Board Direction ‘PBD-2013-05 Engagement of Probity Advisers and Probity Auditors’ when they engaged probity practitioners. We also found they did not have effective processes to achieve compliance or assure the engagements achieved value for money.

In the sample of engagements we selected, we found instances where the participating agencies did not always:

  • document detailed terms of reference
  • ensure the practitioner was sufficiently independent
  • manage probity practitioners' independence and conflict of interest issues transparently
  • provide practitioners with full access to records, people and meetings
  • establish independent reporting lines   reporting was limited to project managers
  • evaluate whether value for money was achieved.

We also found:

  • agencies tend to rely on only a limited number of probity service providers, sometimes using them on a continuous basis, which may threaten the actual or perceived independence of probity practitioners
  • the NSW Procurement Board does not effectively monitor agencies' compliance with the Direction's requirements. Our enquiries revealed that the Board has not asked any agency to report on its use of probity practitioners since the Direction's inception in 2013. 

There are no professional standards and capability requirements for probity practitioners

NSW Government agencies use probity practitioners to independently verify that their procurement and asset disposal processes are transparent, fair and accountable in the pursuit of value for money. 

Probity practitioners are not subject to regulations that require them to have professional qualifications, experience and capability. Government agencies in New South Wales have difficulty finding probity standards, regulations or best practice guides to reference, which may diminish the degree of reliance stakeholders can place on practitioners’ work.

The NSW Procurement Board provides direction for the use of probity practitioners

The NSW Procurement Board Direction 'PBD-2013-15 for engagement of probity advisers and probity auditors' outlines the requirements for agencies' use of probity practitioners in the New South Wales public sector. All NSW Government agencies, except local government, state owned corporations and universities, must comply with the Direction when engaging probity practitioners. This is illustrated in Exhibit 1 below.

Published

Actions for Managing growth in the NSW prison population

Managing growth in the NSW prison population

Justice
Infrastructure
Management and administration
Project management
Service delivery
Workforce and capability

The Department of Justice has relied heavily on temporary responses to accommodate growing prisoner numbers according to a report released today by the Acting Auditor-General for New South Wales, Ian Goodwin.

At the time of this audit, the NSW Department of Justice (DOJ) was responsible for delivering custodial corrections services in New South Wales through its Corrective Services NSW division (Corrective Services NSW). From 1 July 2019, the Department of Family and Community Services and Justice will be responsible for these functions. 

Within DOJ, Corrective Services NSW is responsible for administering sentences and legal orders through custodial and community-based management of adult offenders. Its key priorities are:

  • providing safe, secure and humane management of prisoners
  • reducing reoffending
  • improving community safety and confidence in the justice system. 

The prison population in New South Wales grew by around 40 per cent between 2012 to 2018, from 9,602 to 13,630 inmates. This rate of growth was higher than experienced prior to 2012. DOJ forecasts growth to continue over the short and longer-term. 

DOJ has responded to inmate population growth by doubling-up and tripling-up the number of prison beds in cells, reactivating previously closed prisons, and a $3.8 billion program of new prison capacity. DOJ has also developed a long-term prison infrastructure strategy that projects long-term needs and recommended investments to meet these needs. 

This audit assessed how efficiently and effectively DOJ is responding to growth in the NSW prison population. In this report, we have not analysed the sources of demand or recommended ways that custody may be avoided. These are largely government policy issues. 

Conclusion
The DOJ has relied heavily on temporary responses to accommodate growth in the NSW prison population. Sustained reliance on these responses is inefficient and creates risks to safety, and timely access to prisoner support services.
DOJ has experienced significant growth in the prison population since 2012. To meet demand, it has relied on temporary responses that are not designed to be sustained, including doubling-up or tripling-up the number of beds in cells, reopening previously closed facilities and using obsolete facilities. DOJ has also regularly moved inmates between its facilities to accommodate the increasing need for beds in metropolitan Sydney. 
Relying on temporary approaches over a long period contributes to prison crowding and has affected DOJ's ability to manage inmates in line with its correctional principles. It has increased risks to staff and prisoner safety, and timely inmate access to prisoner support services and programs. In addition, the cost per prisoner per day increased over the past two years.
DOJ is progressively delivering new capacity to address the growing prison population.
In response to continuing and projected growth in the prison population, the NSW Government announced a one-off $3.8 billion program to deliver around 6,100 beds by May 2021. Under the program, DOJ developed and delivered two rapid build dormitory style prisons within 18 months. DOJ’s capability to deliver the program, including implementation of new beds and new prisons, governance, project management, risk assessment and commissioning has improved over time. Most new capacity will be delivered on existing DOJ sites, mainly in regional New South Wales. 
DOJ has developed a strategy to respond to long-term projected growth in the prison population, but it has yet to be funded. 
The Corrective Services NSW Infrastructure Strategy (CSIS) sets out challenges, strategic priorities, and planned actions to respond to projected growth over the next 20 years and improve overall system efficiency and effectiveness. But, proposed actions are subject to individual business cases and funding decisions. Three versions of the CSIS have been provided to, and endorsed by, the NSW Government. The key challenge identified in the CSIS is to overcome demand for prison beds in the Sydney metropolitan region. DOJ advised that it is developing a final business case to address metropolitan capacity needs, but this is subject to government approval and funding. DOJ should continue to highlight the urgency of this issue until it is addressed, as it prevents planned actions to improve system efficiency and effectiveness.
 

The Productivity Commission’s Report on Government Services outlines the performance indicator framework for corrective services in Australia (Appendix three). We have used measures from this framework to assess the efficiency and effectiveness of DOJ’s responses to prison bed capacity needs. 

In this section, we analyse system-wide indicators as DOJ has not consistently published or reported data for individual correctional centres over the period of review.
 

Published

Actions for Transport Access Program

Transport Access Program

Transport
Infrastructure
Project management
Service delivery

The following report is available in an Easy English version that is intended to meet the needs of some people with lower literacy skills, some people with an intellectual disability and some people from different cultural backgrounds.

View the Easy English version of the Transport Access Program report

Transport for NSW’s process for selecting and prioritising projects for the third stage of its Transport Access Program balanced compliance with national disability standards with broader customer outcomes. Demographics, deliverability and value for money were also considered. However, Transport for NSW does not know the complete scope of work required for full compliance, limiting its ability to demonstrate that its approach is effective, according to a report released today by the Auditor-General for New South Wales, Margaret Crawford.

Access to transport is critical to ensuring that people can engage in all aspects of community life, including education, employment and recreation. People with disability can encounter barriers when accessing public transport services. In 2015, there were 1.37 million people living with disability in New South Wales.

Accessible public transport is about more than physical accessibility. It also means barrier-free access for people who have vision, hearing or cognitive impairments. All users, not just people with disability, benefit from improvements to the accessibility and inclusiveness of transport services. 

Transport for NSW has an obligation under Australian Government legislation to provide accessible services to people with disabilities in a manner which is not discriminatory. Under the Disability Standards for Accessible Public Transport 2002 (the DSAPT - an instrument of the Disability Discrimination Act 1992 (the Act) (Commonwealth)), there is a requirement to modify and develop new infrastructure, means of transport and services to provide access for people with disabilities. All public transport operators are required to ensure that at least 90 per cent of their networks met DSAPT by December 2017 and the networks will need to be 100 per cent compliant with all parts of the standards by 31 December 2022. Trains are not required to be fully compliant with DSAPT until December 2032. 

The Transport Access Program (TAP) is Transport for NSW's largest program with a specific focus on improving access to public transport for people with disability. The TAP is a series of projects to upgrade existing public transport infrastructure across four networks: Sydney Trains, Intercity Trains, Regional Trains and Sydney Ferries. Transport for NSW established the TAP as a rolling program and, to date, it has delivered the first tranche of TAP (TAP 1) and is completing the final projects for the second tranche (TAP 2). NSW budget papers estimate that by 30 June 2018, Transport for NSW had spent $1.2 billion in the TAP since its commencement in 2011-12.

After the completion of TAP 1 and TAP 2 (as well as through other transport infrastructure programs), Transport for NSW estimates that 58.5 per cent of the Sydney Trains, Regional Trains and Intercity Trains networks, and 66 per cent of the Sydney Ferries network, will be accessible. To close the significant gap in compliance with the DSAPT target, the objective for TAP 3 is ‘to contribute to Disability Discrimination Act 1992 related targets through DSAPT compliance upgrades’. 

The audit assessed whether Transport for NSW has an effective process to select and prioritise projects as part of the TAP, with a specific focus on the third tranche of TAP funding.

In August 2018, at the commencement of this audit, Transport for NSW intended to complete the selection of projects for the TAP 3 final business case in December 2018. Transport for NSW advise that it now intends to complete the development stage and final business case in the first quarter of 2019, prior to the final investment decision of the TAP program. This report is based on the TAP 3 strategic business case and information provided by Transport for NSW up to December 2018.

Conclusion
Transport for NSW’s process for selecting and prioritising projects for TAP 3 balanced DSAPT compliance goals with broader customer outcomes. It also considered demographics, deliverability and value for money. However, Transport for NSW does not know the complete scope of work required for full DSAPT compliance, and this limits its ability to demonstrate that its approach is effective. 
Transport for NSW has applied most of the external review recommendations from previous funding rounds to the implementation of the third round of TAP funding (TAP3), with positive results. Changes made include a clear objective for TAP 3 to focus on improving compliance, improved governance arrangements, and better consideration of deliverability and design during project planning. 
Through TAP 3, Transport for NSW is also trying to better address disability access in a way that balances DSAPT compliance with other considerations - such as population demographics, access to services and value for money. Transport for NSW developed an objective prioritisation and selection methodology to assess projects for TAP 3 funding. 
Transport for NSW cannot quantify the work needed to meet DSAPT compliance targets across the rail and ferry networks as it has not completed a comprehensive audit of compliance. This information is needed to ensure the effective targeting of funding, and to measure the contribution of TAP 3 work to meeting the DSAPT compliance targets. Instead, Transport for NSW has undertaken a phased approach to completing a comprehensive audit of compliance across the networks, with a focus on first assessing compliance at locations that are not wheelchair accessible. This creates two problems. First, Transport for NSW does not know the complete scope of work required to achieve DSAPT compliance. Second, not all wheelchair accessible locations fully meet DSAPT standards.
Transport for NSW's proposed communication plan for the schedule of TAP 3 funded works does not align with its Disability Inclusion Action Plan 2018-2022. The Disability Inclusion Action Plan commits Transport for NSW to providing a full list of stations and wharves to be upgraded with their estimated time of construction when the next round of funding, TAP 3, is announced. Given the long timeframes associated with improving transport infrastructure, this information is important as it allows people to make informed decisions about where they live, work or study. Instead, Transport for NSW plans to communicate information to customers on a project by project basis.

In 2015, there were 1.37 million people living with disability in New South Wales. Access to transport is critical to ensuring that people can engage in all aspects of community life, including education, employment and recreation. People with disability can encounter barriers when accessing public transport services. 

The social model of disability, outlined in the United Nations Convention on the Rights of Persons with Disabilities, views people with disability as not disabled by their impairment but by the barriers in the community and environment that restrict their full and effective participation in society on an equal basis with others. 

Accessible public transport is more than the provision of physical access to premises and conveyances, it provides barrier-free access for people who have vision, hearing or cognitive impairments. All users, not just people with disability, benefit from improvements to the accessibility and inclusiveness of transport services.

According to the Australian Bureau of Statistics, the main types of difficulties experienced by people with disability when using public transport relate to steps (39.9 per cent), difficulty getting to stops and stations (25 per cent), fear and anxiety (23.3 per cent) and lack of seating or difficulty standing (20.7 per cent).

Transport for NSW has a Disability Inclusion Action Plan (the Action Plan) 2018-2022 that sets an overall framework for planning, delivering and reporting on initiatives to increase accessibility of the transport network. It covers all elements of the journey experienced when using public transport, including journey planning, staff training, customer services and interaction between the physical environment and modes of transport. Appendix five outlines the guiding principles of the Action Plan.

Transport for NSW's Transport Social Policy branch developed the Action Plan in consultation with internal and external stakeholders. The director of the Transport Social Policy branch is a member of the TAP executive steering committee, which supports alignment between the Action Plan and TAP.

Transport for NSW's Disability Inclusion Action Plan describes a customer focussed approach to accessibility

One of the guiding principles of the Action Plan is ‘intelligent compliance’. Transport for NSW describes this as compliance that prioritises customer-focused outcomes over a narrow focus on legal compliance with accessibility standards. As well as being compliant, infrastructure should be practical, usable, fit for purpose and convenient. 

The TAP prioritisation and selection methodology reflects Transport for NSW’s focus on intelligent compliance. We consider this a reasonable approach as had Transport for NSW focussed exclusively on achieving compliance with the DSAPT targets by upgrading the most affordable infrastructure, some locations, that are used by more customers, would remain inaccessible to people with disability. However, this approach should not be seen as an alternative to Transport for NSW meeting its DSAPT compliance obligations.

TAP program staff consult with the Accessible Transport Advisory Committee

The Accessible Transport Advisory Committee (ATAC) has representatives from disability and ageing organisations, who provide expert guidance to Transport for NSW on access and inclusion. The ATAC provide guidance and feedback on projects and project solutions, including user testing where appropriate. TAP program staff provide regular updates at ATAC meetings, which include briefings on progress. The ATAC also provides feedback and suggestions to TAP program staff, which is considered and sometimes included in current and future projects.For example, in March 2017 the TAP program team briefed the ATAC on the challenges with respect to a number of ferry wharves and sought support for DSAPT exemptions proposed in the TAP 3 strategic business case.

Case study: Feedback on Braille lettering for lift buttons
In June 2018, the Program team sought feedback on a variety of lift button options to improve accessibility on future TAP projects. In September 2018, during the ATAC meeting attended by the Audit Office, the program team sought feedback on the standard designs for TAP 3. Some ATAC members noted that the standard design included Braille lettering on the lift buttons, and that this was not good practice because people can accidently press the button while reading it. As a result, Transport for NSW are incorporating this feedback into design requirements for the lifts for TAP 3, which will consider larger buttons, clearer Braille and Braille signage adjacent to the button.

Transport for NSW has not briefed the Advisory Committee on the outcome of the prioritisation and selection process

TAP program staff briefed the Advisory Committee about the prioritisation and selection methodology, after the Minister approved it in 2016. However, Transport for NSW have not briefed or consulted the Advisory Committee on the outcome of the prioritisation process. Infrastructure NSW noted this issue during its review of the strategic business case. 

Transport for NSW advised us that it established the ATAC as an advisory group, and that Transport for NSW does not disclose sensitive information to it. Transport for NSW intends to share the outcome of the prioritisation process following the completion of the TAP 3 development stage and final investment decision.

The TAP communication plan does not fully meet the requirements of the Disability Inclusion Action Plan

The Disability Inclusion Action Plan includes an action item to ‘provide a listing of stations and wharves to be upgraded with estimated time of construction as each new tranche of the Transport Access Program is announced’ The TAP Communication Plan that we reviewed does not include this provision instead focussing on communication on a per project basis. Given the long timeframes associated with improving transport infrastructure, this information is important as it allows people to make informed decisions about where they live, work or study.

Published

Actions for Property Asset Utilisation

Property Asset Utilisation

Finance
Asset valuation
Infrastructure
Management and administration
Project management

Property NSW’s effectiveness in managing NSW Government owned and leased commercial office property is limited in three areas according to a report released today by the Auditor-General for New South Wales, Margaret Crawford.

At 30 June 2018, the NSW Government owned $160 billion worth of land and buildings. The NSW Treasury predicts this figure will rise over the coming years. Property NSW manages more than 900 leased office properties across the state. Approximately 250 of these are owned by Property NSW. Other NSW Government agencies maintain ownership and control of properties considered essential for service provision, such as schools, prisons and hospitals. Between 2012–13 and 2017–18 sales of property assets across the whole of the NSW Government have raised $10 billion, of which Property NSW has sold property assets of approximately $2 billion.

In September 2012, the Property Asset Utilisation Taskforce (the Taskforce) released its report on ‘real property asset management across government’ and concluded that the government has accumulated, over time, ‘a real property asset portfolio it cannot afford to maintain or protect’. The Taskforce noted that ‘a lack of centralised information seriously inhibits any whole-of-government strategic asset planning’ and that maintaining under-utilised or unnecessary properties diverted funds from areas where they might be better used. The Taskforce’s key findings included:

  • the NSW Government should own property only as a means to deliver or enhance services
  • many government properties were under-utilised, poorly maintained and inappropriate to support service delivery.

The Taskforce recommended the creation of Property NSW, as a replacement for the State Property Authority, to improve property asset utilisation and to drive efficiencies in the government’s owned and leased property portfolio. Property NSW was to achieve these goals by:

  • collating property information across the whole-of-government
  • working with agencies on longer-term strategic real property asset planning to:
    • provide services to agencies as customers
    • bring a whole-of-government perspective to real property asset planning.

In response to the Taskforce report, in December 2012, the Premier's Memorandum M2012-20 (the Memorandum) established Property NSW to improve the management of the NSW Government's owned and leased real property portfolio.

Under the Memorandum, Property NSW is responsible for:

  • management of all leased and owned commercial office accommodation
  • acting as the central acquisition and disposal agency 
  • providing advice to the government on property matters and developing property policy 
  • conducting regular and ongoing reviews of agencies portfolios, working with agencies to identify efficiencies to improve service delivery, in relation to the review of capital planning1
  • maintaining the register of all government owned property.

The Memorandum states that ownership of all commercial office property should be vested in Property NSW. 

This audit assessed whether Property NSW is effective in the management of NSW Government owned and leased commercial office property. To do this we assessed whether NSW Government leased commercial office space is being effectively utilised and whether the Government Property Register, a register of all government owned property, is accurate and up-to-date.

Conclusion
Property NSW’s effectiveness in managing NSW Government owned and leased commercial office property is limited in three areas.
First, Property NSW has not comprehensively reviewed many agency property portfolios to help agencies identify assets, including commercial office properties, that could be better utilised or recycled. Second, the Government Property Register is not being actively maintained and contains incomplete and inaccurate information, limiting Property NSW’s ability to use it to support strategic decisions about the use of government property assets. Third, Property NSW's decisions are not well documented and its processes to reach decisions are not transparent to stakeholders. That said, property utilisation has improved by about 14 per cent since 2012, and Property NSW is actively moving properties out of the Sydney CBD in line with the ‘Decade of Decentralisation’ policy.
Property NSW’s role is to provide a strategic approach to property asset management. Under the 2012 Premier’s Memorandum, this includes a requirement that Property NSW undertake regular reviews of agency property portfolios to identify efficiencies to improve service delivery. Property NSW completed one comprehensive review of an agency, limited reviews of four other agencies, and some reviews of government property in regional towns, prior to 2017.

In December 2017, Property NSW started working across the NSW Government to help agencies identify real property assets, including commercial office properties, that are under-utilised or surplus and that could be recycled, repurposed, or vested to Property NSW.
Following the Memorandum, agencies were directed to vest their commercial office properties to Property NSW. However, without more comprehensive reviews, Property NSW does not know how many commercial properties are yet to be vested. Agencies can approach Property NSW for assistance in managing their property portfolios, and Property NSW arranges the recycling of under utilised and surplus properties that are brought to its attention. Property NSW is improving utilisation of government office space, according to agency self-reported information which Property NSW uses to calculate utilisation rates. 
The Property Asset Utilisation Taskforce report (2012) recommended that the NSW Government needed a ‘single source of truth’ to inform asset retention and disposal decisions, leasing decisions and ongoing strategic property decisions. It concluded that the Government Property Register (GPR) could perform this function ‘if populated appropriately’. However, the GPR is not comprehensively performing this function because it is still incomplete and out of date. Property NSW manages the GPR and NSW Government agencies are required to supply ‘accurate, relevant and useful information’ to populate it. Agencies are not always doing so in a timely manner, limiting its usefulness to support strategic decision making. Property NSW supplements the GPR with information from multiple other sources to assist its decisions, however, there is still no single, complete and accurate picture of the NSW Government property portfolio. 
The work Property NSW does to identify, shortlist and propose new lease and agency relocation options is not well documented. Property NSW records the outcome of the process without detailing how and why decisions were made. There is limited transparency in this process for stakeholders. Record keeping is also inconsistent and many of Property NSW’s divisions do not have procedures or guidelines.

1 Capital Planning was previously referred to as Total Asset Management (TAM).

In December 2017, the NSW Government announced the Property Infrastructure Policy to create a more collaborative approach between Property NSW and NSW Government agencies to review and identify efficiencies in their property portfolios. Before this, Property NSW did not have a plan to assist agencies to identify under-utilised properties for recycling or repurposing. It still does not know how many under-utilised properties exist and will not know until it has completed all of the portfolio reviews it is currently carrying out under the Property Infrastructure Policy.
Between 2013 and 2017, Property NSW had only completed one comprehensive review of an agency, limited reviews of four other agencies, and some regional towns. Outside this process Property NSW chose to rely on other agencies to identify surplus property for recycling, repurposing or vesting ownership to Property NSW.
Property NSW has a role to provide a strategic approach to property asset management and is required to undertake regular reviews of agency property portfolios under the Premier's Memorandum. Property NSW only recently started working to assist agencies to identify under-utilised and surplus properties, or properties to be vested. These reviews should improve the identification of surplus and under-utilised real property assets and assist whole-of-government decisions on the recycling, repurposing of under-utilised assets and vesting of owned office accommodation to Property NSW.
Recommendations
By December 2019, Property NSW should:
  1. combine the results of property portfolio reviews to produce a whole-of-government picture of the NSW Government property portfolio 
  2. devise a strategy and plan to recycle or repurpose under-utilised properties using a whole-of-government picture of the NSW Government property portfolio
  3. develop and report on indicators for progress in reducing the number and value of under-utilised properties at the whole-of-government level, referencing progress against an accurate baseline stocktake.
Property NSW needs to be more proactive in its management of the GPR and in encouraging agencies to provide the information needed to improve this register. In 2012, the Property Asset Utilisation Taskforce report recommended there be a single source of truth on property assets owned by the NSW Government. The GPR is intended to fulfil this role but it is out of date and incomplete.
Without a complete and accurate central register of property, Property NSW cannot provide the NSW Government with a comprehensive picture of its property portfolio, or make whole-of-government decisions about the property portfolio. Property NSW currently supplements the GPR with information from other systems in order to make decisions about leasing, relocations, and property recycling and repurposing. Agencies are required to provide ‘accurate, relevant and useful information’ but are not consistently doing so.
Recommendations
By December 2019, Property NSW should:

4. improve the data held on government owned and leased properties by combining and automating data feeds to construct a single, consolidated and accurate whole-of-government property data set.
Property NSW documents the outcome of decisions about relocations, lease renewals, and utilisation but is unable to provide evidence of how these decisions are reached. Property NSW is also unable to provide evidence of documented guidance for its staff on how decisions should be made. Whilst some level of subjectivity will play a part in such decisions, the lack of documentation and guidance raises issues of consistency, accountability and transparency in decision-making. Property NSW states that it makes decisions based on whole-of-government outcomes rather than equitable and consistent outcomes for client agencies, which is inconsistent with the criteria it reports that it uses when making decisions about leases and relocations.
Recommendations
By December 2019, Property NSW should:

5. document and communicate to stakeholders how its assessment criteria inform key decisions including agency relocations, lease renewals and rectifying under-utilisation
6. include customer satisfaction measures in its annual reports and reviews, in accordance with the requirements set out in the Premier's Memorandum M2012-20
7. improve record-keeping and compliance with the State Records Act 1998 and the Department of Finance, Services and Innovation Records Management Policy.

Published

Actions for Newcastle Urban Transformation and Transport Program

Newcastle Urban Transformation and Transport Program

Transport
Planning
Compliance
Infrastructure
Management and administration
Procurement
Project management

The urban renewal projects on former railway land in the Newcastle city centre are well targeted to support the objectives of the Newcastle Urban Transformation and Transport Program (the Program), according to a report released today by the Auditor-General for New South Wales, Margaret Crawford. The planned uses of the former railway land achieve a balance between the economic and social objectives of the Program at a reasonable cost to the government. However, the evidence that the cost of the light rail will be justified by its contribution to the Program is not convincing.

The Newcastle Urban Transformation and Transport Program (the Program) is an urban renewal and transport program in the Newcastle city centre. The Hunter and Central Coast Development Corporation (HCCDC) has led the Program since 2017. UrbanGrowth NSW led the Program from 2014 until 2017. Transport for NSW has been responsible for delivering the transport parts of the Program since the Program commenced. All references to HCCDC in this report relate to both HCCDC and its predecessor, the Hunter Development Corporation. All references to UrbanGrowth NSW in this report relate only to its Newcastle office from 2014 to 2017.

This audit had two objectives:

  1. To assess the economy of the approach chosen to achieve the objectives of the Program.
  2. To assess the effectiveness of the consultation and oversight of the Program.

We addressed the audit objectives by answering the following questions:

a) Was the decision to build light rail an economical option for achieving Program objectives?
b) Has the best value been obtained for the use of the former railway land?
c) Was good practice used in consultation on key Program decisions?
d) Did governance arrangements support delivery of the program?

Conclusion
1. The urban renewal projects on the former railway land are well targeted to support the objectives of the Program. However, there is insufficient evidence that the cost of the light rail will be justified by its contribution to Program objectives.

The planned uses of the former railway land achieve a balance between the economic and social objectives of the Program at a reasonable cost to the Government. HCCDC, and previously UrbanGrowth NSW, identified and considered options for land use that would best meet Program objectives. Required probity processes were followed for developments that involved financial transactions. Our audit did not assess the achievement of these objectives because none of the projects have been completed yet.

Analysis presented in the Program business case and other planning documents showed that the light rail would have small transport benefits and was expected to make a modest contribution to broader Program objectives. Analysis in the Program business case argued that despite this, the light rail was justified because it would attract investment and promote economic development around the route. The Program business case referred to several international examples to support this argument, but did not make a convincing case that these examples were comparable to the proposed light rail in Newcastle.

The audited agencies argue that the contribution of light rail cannot be assessed separately because it is a part of a broader Program. The cost of the light rail makes up around 53 per cent of the total Program funding. Given the cost of the light rail, agencies need to be able to demonstrate that this investment provides value for money by making a measurable contribution to the Program objectives.

2. Consultation and oversight were mostly effective during the implementation stages of the Program. There were weaknesses in both areas in the planning stages.

Consultations about the urban renewal activities from around 2015 onward followed good practice standards. These consultations were based on an internationally accepted framework and met their stated objectives. Community consultations on the decision to close the train line were held in 2006 and 2009. However, the final decision in 2012 was made without a specific community consultation. There was no community consultation on the decision to build a light rail.

The governance arrangements that were in place during the planning stages of the Program did not provide effective oversight. This meant there was not a single agreed set of Program objectives until 2016 and roles and responsibilities for the Program were not clear. Leadership and oversight improved during the implementation phase of the Program. Roles and responsibilities were clarified and a multi-agency steering committee was established to resolve issues that needed multi-agency coordination.
The light rail is not justified by conventional cost-benefit analysis and there is insufficient evidence that the indirect contribution of light rail to achieving the economic development objectives of the Program will justify the cost.
Analysis presented in Program business cases and other planning documents showed that the light rail would have small transport benefits and was expected to make a modest contribution to broader Program objectives. Analysis in the Program business case argued that despite this, the light rail was justified because it would attract investment and promote economic development around the route. The Program business case referred to several international examples to support this argument, but did not make a convincing case that these examples were comparable to the proposed light rail in Newcastle.
The business case analysis of the benefits and costs of light rail was prepared after the decision to build light rail had been made and announced. Our previous reports, and recent reports by others, have emphasised the importance of completing thorough analysis before announcing infrastructure projects. Some advice provided after the initial light rail decision was announced was overly optimistic. It included benefits that cannot reasonably be attributed to light rail and underestimated the scope and cost of the project.
The audited agencies argue that the contribution of light rail cannot be assessed separately because it is part of a broader Program. The cost of the light rail makes up around 53 per cent of the total Program funding. Given the high cost of the light rail, we believe agencies need to be able to demonstrate that this investment provides value for money by making a measurable contribution to the Program objectives.

Recommendations
For future infrastructure programs, NSW Government agencies should support economical decision-making on infrastructure projects by:
  • providing balanced advice to decision makers on the benefits and risks of large infrastructure investments at all stages of the decision-making process
  • providing scope and cost estimates that are as accurate and complete as possible when initial funding decisions are being made
  • making business cases available to the public.​​​​​​
The planned uses of the former railway land achieve a balance between the economic and social objectives of the Program at a reasonable cost to the government.

The planned uses of the former railway land align with the objectives of encouraging people to visit and live in the city centre, creating attractive public spaces, and supporting growth in employment in the city. The transport benefits of the activities are less clear, because the light rail is the major transport project and this will not make significant improvements to transport in Newcastle.

The processes used for selling and leasing parts of the former railway land followed industry standards. Options for the former railway land were identified and assessed systematically. Competitive processes were used for most transactions and the required assessment and approval processes were followed. The sale of land to the University of Newcastle did not use a competitive process, but required processes for direct negotiations were followed.

Recommendation
By March 2019, the Hunter and Central Coast Development Corporation should:
  • work with relevant stakeholders to explore options for increasing the focus on the heritage objective of the Program in projects on the former railway land. This could include projects that recognise the cultural and industrial heritage of Newcastle.
Consultations about the urban renewal activities followed good practice standards, but consultation on transport decisions for the Program did not.

Consultations focusing on urban renewal options for the Program included a range of stakeholders and provided opportunities for input into decisions about the use of the former railway land. These consultations received mostly positive feedback from participants. Changes and additions were made to the objectives of the Program and specific projects in response to feedback received. 

There had been several decades of debate about the potential closure of the train line, including community consultations in 2006 and 2009. However, the final decision to close the train line was made and announced in 2012 without a specific community consultation. HCCDC states that consultation with industry and business representatives constitutes community consultation because industry representatives are also members of the community. This does not meet good practice standards because it is not a representative sample of the community.

There was no community consultation on the decision to build a light rail. There were subsequent opportunities for members of the community to comment on the implementation options, but the decision to build it had already been made. A community and industry consultation was held on which route the light rail should use, but the results of this were not made public. 

Recommendation
For future infrastructure programs, NSW Government agencies should consult with a wide range of stakeholders before major decisions are made and announced, and report publicly on the results and outcomes of consultations. 

The governance arrangements that were in place during the planning stages of the Program did not provide effective oversight. Project leadership and oversight improved during the implementation phase of the Program.

Multi-agency coordination and oversight were ineffective during the planning stages of the Program. Examples include: multiple versions of Program objectives being in circulation; unclear reporting lines for project management groups; and poor role definition for the initial advisory board. Program ownership was clarified in mid-2016 with the appointment of a new Program Director with clear accountability for the delivery of the Program. This was supported by the creation of a multi-agency steering committee that was more effective than previous oversight bodies.

The limitations that existed in multi-agency coordination and oversight had some negative consequences in important aspects of project management for the Program. This included whole-of-government benefits management and the coordination of work to mitigate impacts of the Program on small businesses.

Recommendations
For future infrastructure programs, NSW Government agencies should: 

  • develop and implement a benefits management approach from the beginning of a program to ensure responsibility for defining benefits and measuring their achievement is clear
  • establish whole-of-government oversight early in the program to guide major decisions. This should include:
    • agreeing on objectives and ensuring all agencies understand these
    • clearly defining roles and responsibilities for all agencies
    • establishing whole-of-government coordination for the assessment and mitigation of the impact of major construction projects on businesses and the community.

By March 2019, the Hunter and Central Coast Development Corporation should update and implement the Program Benefits Realisation Plan. This should include:

  • setting measurable targets for the desired benefits
  • clearly allocating ownership for achieving the desired benefits
  • monitoring progress toward achieving the desired benefits and reporting publicly on the results.

Appendix one - Response from agencies    

Appendix two - About the audit

Appendix three - Performance auditing

 

Parliamentary reference - Report number #310 - released 12 December 2018

Published

Actions for Health 2018

Health 2018

Health
Financial reporting

The Auditor-General, Margaret Crawford, released a report today on the New South Wales Health Cluster. The report focuses on key observations and findings from the most recent financial audits of thirty health entities in New South Wales. Unqualified audit opinions were issued for all health entities’ financial statements. However, assessing the fair value of health entities’ property, plant and equipment created challenges, particularly for local health districts.

This report analyses the results of our audits of financial statements of the Health cluster for the year ended 30 June 2018. The table below summarises our key observations.

This report provides parliament and other users of the Health cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Health cluster for 2018.

Observation Conclusions and recommendations
2.1 Quality of financial reporting
We issued unqualified audit opinions for all health entities. We identified fewer misstatements than last year, but they were more significant. The Ministry of Health sets significant accounting policies centrally and provides a template for the preparation of health entities' financial statements. These processes promote consistent quality in the financial reports of health entities.

Significant errors identified in 2017–18 predominantly related to revaluations of property, plant and equipment.
 
2.2 Timeliness of financial reporting
Entities' continue to bring forward financial statement procedures to 31 March where possible. All entities submitted their financial statements on time. Health entities continue to meet statutory deadlines. 
2.3 Financial and sustainability analysis
NSW Health recorded an operating surplus of $377.7 million in 2017–18. Fewer health entities recorded operating deficits in 2017–18. The operating surplus was $123 million less than budgeted, and $29.0 million less than the surplus recorded for 2016–17. NSW Health budgets for surpluses to help it invest in new facilities, upgrades and redevelopments.
Expenses across NSW Health increased by 5.5 per cent in 2017–18 (4.4 per cent in 2016–17). The expense growth rate for NSW Health is 0.5 percentage points lower than the projected long-term annual expense growth rate of six per cent.
The capital replacement ratio (investment in new assets divided by depreciation) for NSW Health is 2.0. NSW Health's high capital replacement ratios for ten health entities in 2017–18 is driven by its substantial ongoing investment in hospitals and other assets.
2.4 Performance against budget
This year, four out of 17 (ten out of 17 in 2016–17) local health districts and specialty networks reported a budget variance outside of performance expectations. Health entities' budgets are revised frequently throughout the year by the Ministry of Health. In 2017–18 the budgeted expenses of health entities were incrementally increased throughout the year by a total of $807 million.

The Ministry of Health expects health entities not to exceed their revised budgeted expenses by more than 0.5 per cent. Four of the local health districts did not meet this requirement.
 
2.5 Financial impact of health entity employees
Thirty-four per cent of NSW Health’s workforce has excess annual leave balances, compared to 35 per cent in 2016–17.

Managing excess annual leave continues to challenge health entities.
Recommendation: Health entities should further review the approach to managing excess annual leave in 2018–19, and:

  • monitor current and projected leave balances to the end of the financial year on a monthly basis
  • agree formal leave plans with employees to reduce leave balances over an acceptable timeframe
  • encourage staff that perform key control functions to take a minimum of two consecutive weeks' leave a year as a fraud mitigation strategy.
The Ambulance Service of NSW reported an average sick leave rate of 88.9 hours per FTE in 2017–18, an increase from 85.2 hours per FTE in 2016–17. Managing sick leave continues to challenge the Ambulance Service of NSW.
Recommendation: The Ambulance Service of NSW should further implement and monitor targeted human resource strategies to address the high rates of sick leave taken.
The Ambulance Service of NSW reported overtime payments of $74.8 million ($74.6 million in 2016–17). This continues to be significantly higher than other health entities. Recommendation: The Ambulance Service of NSW should further review the effectiveness of its rostering practices to identify strategies to reduce excessive overtime payments.
Weak timesheet approval controls mean unapproved employee timesheets continue to be a problem for health entities. Recommendation: Health entities should, as part of the benefits realisation of HealthRoster, continue to rectify time and leave recording control weaknesses, to reduce the risk of timesheet errors and fraud.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our observations and insights from:

  • our financial statement audits of agencies in the Health cluster for 2018
  • the areas of focus identified in the Audit Office annual work program.

The Audit Office Annual Work Program provides a summary of all audits to be conducted within the proposed time period as well as detailed information on the areas of focus for each of the NSW Government clusters.

Observation Conclusions and recommendations
3.1 Internal control deficiencies
The number of internal control deficiencies decreased. However, almost a quarter of control deficiencies are repeat issues and over a quarter relate to managing employees' leave and time recording. Control deficiencies that relate to managing employees' leave, employees' time recording or information system limitations can be difficult for entities to resolve in a timely manner. Nonetheless, the longer the deficiency remains unaddressed the more likely the vulnerability will contribute to error or fraud.
 
3.2 Audit Office annual work program
Revaluation of property, plant and equipment
Three health entities did not effectively oversee the asset revaluations performed by the experts they engaged in 2017–18. All three entities made material adjustments to their draft financial statements. Valuation of health property, plant and equipment is complex and subjective. Health entities and the Ministry of Health rely on the experts they engage, but needed to do more to review and oversee their work.
Capital projects
NSW Health manages a significant capital program ($1.7 billion in 2017–18). We noted significant revisions to completion dates and budgeted costs for some projects. NSW Health complied with approval requirements for business cases, initial budgets and budget variations for the projects we reviewed. For some projects revisions to planned completion dates and budgeted costs impact on the ability to assess the timeliness and cost effectiveness of projects. Combining stages of projects for simplicity of reporting, as a project progresses also makes it difficult to see how the project is tracking to the original plan.
Asset maintenance
The five health entities with the highest maintenance expense used different methods to estimate budgets for maintenance expense. Entities that calculated maintenance budgets by applying CPI factors to prior year expenses were less likely to deliver within budget. Maintenance budgets are more accurately predicted when estimates are made of expected costs and prepared with the input of asset maintenance staff.
 
Two of the five entities recorded significantly higher unplanned maintenance expenditure. Planned maintenance expenditure for these entities was lower than other entities.

The entities plan to address this by performing condition audits of their assets, increasing planned maintenance and replacing assets.

All five of the entities were using assets that have been fully depreciated. The replacement cost of each entities' fully depreciated assets represented between 3–7 per cent total replacement cost. While entities are now regularly reassessing the useful lives of their assets, they continue to use some assets that were fully depreciated prior to the implementation of these processes.

Published

Actions for Central Agencies 2018

Central Agencies 2018

Treasury
Premier and Cabinet
Finance
Financial reporting
Internal controls and governance
Management and administration
Risk

The Auditor-General for New South Wales, Margaret Crawford, released her report today on the results of the financial audits of NSW Government central agencies. The report focuses on key observations and findings from the most recent financial statement audits of agencies in the Treasury, Premier and Cabinet, and Finance, Services and Innovation clusters. While clear audit opinions were issued on all agency financial statements, the report notes that some complex accounting requirements caused significant errors in agency financial statements submitted for audit, which were corrected before the financial statements were approved. 

This report analyses the results of our audits of the Treasury, Premier and Cabinet and Finance, Services and Innovation cluster agencies for the year ended 30 June 2018. The table below summarises our key observations.

This report provides parliament and other users of the NSW Government's central agencies and their cluster agencies financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations
  • liquidity risk management
  • government financial services.

The central agencies and their key responsibilities are set out below.

Central agencies Key central agency responsibilities Cluster responsibilities
The Treasury
  • Financial and economic advisor to NSW Government
  • Manages the NSW Government’s financial resources.

The cluster:

  • provides investment and debt management services though TCorp
  • manages residual business arising from privatisation of government businesses
  • provides insurance and compensation cover, including workers compensation insurance
  • includes NSW Government superannuation funds.
Department of Premier and Cabinet
  • Drives NSW Government’s objectives and sets targets
  • Works with clusters to coordinate policy and achieve NSW Government priorities.

The cluster:

  • includes integrity agencies, such as the Independent Commission Against Corruption, Audit Office of NSW and Ombudsman’s Office
  • other agencies, such as Barangaroo Delivery Authority and Infrastructure NSW.
Department of Finance, Services and Innovation
  • Supports agency service delivery in relation to the key enabling functions of NSW Government, including procurement, property and asset management, ICT and digital innovation.

The cluster:

  • is responsible for state revenue and rental bond administration
  • regulates statutory insurance schemes, workplace safety and consumer protection
  • provides access to a range of NSW Government services via Service NSW
  • manages the NSW Government communications network.
Public Service Commission
  • Works to promote and maintain a strong ethical culture across the government sector and improve the capabilities, performance and configuration of the sector’s workforce to deliver better services to the public.
  • The Public Service Commission is an independent agency within the Premier and Cabinet cluster.

Note: The Audit Office of NSW is an independent agency included in the Premier and Cabinet cluster for administrative purposes, but not commented on in this report.


A full list of agencies that this report covers by relevant cluster is included in Appendix three.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Treasury, Premier and Cabinet and Finance, Services and Innovation clusters for 2018.

Observation Conclusions and recommendations
2.1 Quality of financial reporting
Unqualified opinions were issued for all agencies' financial statements submitted to the Audit Office.

Complex accounting requirements caused significant errors in some agency financial statements, which were corrected before the financial statements were approved.
Sufficient audit evidence was obtained to conclude the financial statements were free of material misstatement.
Recommendation: Agencies should respond to key accounting issues when they are identified by preparing accounting papers and engaging with Treasury, the Audit Office and their Audit and Risk Committee when these matters are identified.
2.2 Timeliness of financial reporting
Most agencies complied with the statutory timeframe for completion of early close procedures, 48 agencies in the Treasury cluster did not comply with the statutory requirement to prepare financial statements, and the audits of nine agencies in the Treasury cluster were not completed within the statutory timeframe.
All financial statement information of the 48 agencies that did not prepare financial statements has been captured in the consolidated financial statements of their parent entity, which was subject to audit.
Early close procedures allow financial reporting issues and risks to be addressed early in the audit process. The timeliness of financial reporting can be improved by performing more robust early close procedures.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our observations and insights from:

  • our financial statement audits of agencies in the Treasury, Premier and Cabinet and Finance, Services and Innovation cluster for 2018
  • the areas of focus identified in the Audit Office work program.

The Audit Office work program provides a summary of all audits to be conducted within the proposed time period as well as detailed information on the areas of focus for each of the NSW Government clusters.

Observation Conclusions and recommendations
3.1 Internal controls
The 2017–18 audits found one high risk issue and 83 moderate risk issues across the agencies. Nineteen per cent of all issues were repeat issues. Agencies should focus on rectifying repeat issues.
The high risk issue at Service NSW related to several deficiencies in procurement and contract management processes. Service NSW may not be achieving value-for-money
from their procurement and contract management activities. The high risk issue should be rectified as a matter of priority. This includes updating and implementing its procurement, vendor and contract management frameworks and delivering training to key staff involved in procurement and contract management activities.
Property NSW has implemented several controls during the year to rectify the high risk issue identified last year related to its transition to a new property and facility management service provider. However, the service providers performance remains below expectations and there are further opportunities to improve oversight and lift performance. Property NSW can better define roles and accountabilities with the service provider and formalise policies and processes associated with its monitoring and oversight of the service provider.

Implementing relevant KPIs, receiving timely reports and providing timely review and feedback to the service provider may help to lift performance.
GovConnect received unqualified opinions from their service auditor on all business process controls, except for information technology controls provided by Unisys, where a qualified opinion was received from the service auditor. A qualified opinion was received because of several deficiencies in user access controls. These internal control deficiencies increase the risk of unauthorised access to key business systems, and increase audit effort and costs associated with addressing the risks arising from the deficiencies.
3.2 Audit Office annual work program

Remediation of the Barangaroo site is now estimated to cost the Barangaroo Delivery Authority in excess of net $400 million.
 
The increase in the estimate over the last five years is mainly due to the extent of remediation required, as more evidence of contamination has become known.

Measuring the remaining costs to remediate requires the use of estimation techniques and judgements, making the actual outcome inherently uncertain. We reviewed evidence to support the provision for remediation, including future costs estimates and this evidence supported management’s estimate.
The State Insurance Regulatory Authority have administered the refund of $138 million in Green slip refunds to policy holders through Service NSW during 2017–18. At 30 June 2018, $112 million in refunds are yet to be claimed.
 
We reviewed the systems and processes supporting the refund process. While we found that this supports the disbursement of refunds to policyholders there were some deficiencies in Service NSW’s project controls when the program was being developed.

 
Service NSW should apply the lessons learnt from this program to other programs it is delivering or will be delivering for agencies.
Revenue NSW recorded $30.4 billion from taxes, fines and fees in 2017–18 ($30.0 billion in 2016–17) to support the State’s finances. 
 
Crown revenue has steadily increased over the last five years predominately driven by rises in payroll tax and land tax and responsibility for collection of the Emergency Services Levy transferring to Revenue NSW under the Emergency Services Levy Act 2017 effective from July 2017. 
3.3 Managing maintenance
Place Management NSW manages significant commercial and retail leases and maintains public domain spaces and other assets around the harbour foreshore. It has consistently underspent its asset maintenance budget. In 2017–18, asset maintenance expenses were only 34 per cent of budgeted maintenance expense.

Currently, Place Management NSW does not use any ratios or benchmarks to determine the adequacy of its maintenance spend or to monitor whether it is achieving its budgeted maintenance program. 
This may be contributing to a high proportion of unplanned maintenance, which Place Management NSW reports was 38 per cent of total maintenance expense in 2017–18.

Place Management NSW is outsourcing its property and facilities management function from 1 December 2018 to an external service provider. 
 

This chapter outlines our audit observations, conclusions and recommendations specific to NSW Government agencies providing financial services.

Observation Conclusions and recommendation
5.1 Superannuation funds
The SAS Trustee Corporation (STC) Pooled Fund and the Parliamentary Contributory Superannuation (PCS) Fund are not required to comply with the prudential and reporting standards issued by the Australian Prudential Regulation Authority (APRA). 
However, legislation allows the responsible Minister to prescribe prudential standards, reporting and audit requirements. 
Structured and comprehensive prudential oversight of these Funds is important as they operate in a volatile financial sector, have 103,000 members and manage investments of $43.3 billion.
Recommendation: Treasury should consult with the Trustees of the STC Pooled Fund and PCS Fund to prescribe appropriate prudential standards and requirements, including oversight arrangements.
5.2 Insurance and compensation
Nominal Insurer and NSW Self Insurance Corporation investment performance marginally exceeded benchmark over the past five years. Investment returns can impact on the premiums required to maintain an adequate funding ratio in addition to other factors such as claims experience and discount rates.
The Workers Compensation Nominal Insurer (Nominal Insurer) and NSW Self Insurance Corporation's net collected premiums and contributions decreased over the past five years.  The insurance schemes' investment performance and stable claim payments have enabled less reliance on net collected premiums and contributions as a source of funding, over the past five years. 
Reforms were introduced to manage the Home Warranty Scheme's financial sustainability risks.  The Home Warranty Scheme has not collected sufficient premiums to fund expected claims costs, since commencing operations in 2011. In 2017–18, the Crown contributed $181 million for historical shortfalls. New reforms started on 1 January 2018 enabling the Scheme to price premiums based on risk. 

Published

Actions for Transport 2018

Transport 2018

Transport
Asset valuation
Compliance
Financial reporting
Infrastructure
Management and administration
Procurement
Risk
Service delivery
Workforce and capability

The Auditor-General for New South Wales, Margaret Crawford released her report today on key observations and findings from the 30 June 2018 financial statement audits of agencies in the Transport cluster. Unqualified audit opinions were issued for all agencies' financial statements. However, assessing the fair value of the broad range of transport related assets creates challenges.

This report analyses the results of our audits of financial statements of the Transport cluster for the year ended 30 June 2018. The table below summarises our key observations.

This report provides Parliament and other users of the Transport cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Transport cluster for 2018.

Observation Conclusions and recommendations
2.1 Quality of financial reporting
Unqualified audit opinions were issued for all agencies' financial statements Sufficient audit evidence was obtained to conclude the financial statements were free of material misstatement.
2.2 Key accounting issues
Valuation of assets continues to create challenges. Although agencies complied with the requirements of the accounting standards and Treasury policies on valuations, we identified some opportunities for improvements at RMS.

RMS incorporated data from its asset condition assessments for the first time in the valuation methodology which improved the valuation outcome. Overall, we were satisfied with the valuation methodology and key assumptions, but we noted some deficiencies in the asset data in relation to asset component unit rates and old condition data for some components of assets. 

Also, a bypass and tunnel were incorrectly excluded from RMS records and valuation process since 2013. This resulted in an increase for these assets’ value by $133 million.

The valuation inputs for Wetlands and Moorings were revised this year to better reflect the assets' characteristics resulting in a $98.0 million increase.

2.3 Timeliness of financial reporting
Residual Transport Corporation did not submit its financial statements by the statutory reporting deadline. Residual Transport Corporation remained a dormant entity with no transactions for the year ended 30 June 2018.
With the exception of Residual Transport Corporation, all agencies completed early close procedures and submitted financial statements within statutory timeframes. Early close procedures allow financial reporting issues and risks to be addressed early in the reporting and audit process.
2.4 Financial sustainability
NSW Trains and the Chief Investigator of the Office of Transport Safety Investigations reported negative net assets of $75.7 million and $89,000 respectively at 30 June 2018.  NSW Trains and the Chief Investigator of the Office of Transport Safety Investigations continue to require letters of financial support to confirm their ability to pay liabilities as they fall due. 
2.5 Passenger revenue and patronage
Transport agencies revenue growth increased at a higher rate than patronage. Public transport passenger revenue increased by $114 million (8.3 per cent) in 2017–18, and patronage increased by 37.1 million (5.1 per cent) across all modes of transport based on data provided by TfNSW. 
Negative balance Opal Cards resulted in $3.8 million in revenue not collected in 2017–18 and $7.8 million since the introduction of Opal. A total of 1.1 million Opal cards issued since its introduction have negative balances. Transport for NSW advised it is liaising with the ticketing vendor to implement system changes and are investigating other ways to reduce the occurrences.
2.6 Cost recovery from public transport users
Overall cost recovery from users has decreased. Overall cost recovery from public transport users (on rail and bus services by STA) decreased from 23.2 per cent to 22.4 per cent between 2016–17 and 2017–18. The main reason for the decrease is due to expenditure increasing at a faster rate than revenue in 2017–18.


 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our observations and insights from:

  • our financial statement audits of agencies in the Transport cluster for 2018
  • the areas of focus identified in the Audit Office annual work program.

The Audit Office Annual Work Program provides a summary of all audits to be conducted within the proposed time period as well as detailed information on the areas of focus for each of the NSW Government clusters. 

Observation Conclusions and recommendations
3.1 Internal controls 
There was an increase in findings on internal controls across the Transport cluster. Key themes related to information technology, employee leave entitlements and asset management. Eighteen per cent of all issues were repeat issues.
3.2 Audit Office Annual work program
The Transport cluster wrote-off over $200 million of assets which were replaced by new assets or technology.

Majority of this write-off was recognised by RMS, with $199 million relating to the write-off of existing assets which have been replaced during the year. 

RailCorp is expected to convert to TAHE from 1 July 2019. Several working groups are considering different aspects of the TAHE transition including its status as a for-profit Public Trading Enterprise and which assets to transfer to TAHE. We will continue to monitor developments on TAHE for any impact to the financial statements.
RMS' estimated maintenance backlog at 30 June 2018 of $3.4 billion is lower than last year. Sydney Trains' estimated maintenance backlog at 30 June 2018 increased by 20.6 per cent to $434 million. TfNSW does not quantify its backlog maintenance. TfNSW advised it is liaising with Infrastructure NSW to develop a consistent definition of maintenance backlog across all transport service providers. 
Not all agencies monitor unplanned maintenance across the Transport cluster. Unplanned maintenance can be more expensive than planned maintenance. TfNSW should develop a consistent approach to define, monitor and track unplanned maintenance across the cluster.

This chapter outlines certain service delivery outcomes for 2017–18. The data on activity levels and performance is provided by Cluster agencies. The Audit Office does not have a specific mandate to audit performance information. Accordingly, the information in this chapter is unaudited. 

We report this information on service delivery to provide additional context to understand the operations of the Transport cluster and to collate and present service information for different modes of transport in one report. 

In our recent performance audit, Progress and measurement of Premier's Priorities, we identified 12 limitations of performance measurement and performance data. We recommended that the Department of Premier and Cabinet ensure that processes to check and verify data are in place for all agency data sources.

Published

Actions for Justice 2018

Justice 2018

Justice
Financial reporting

The Auditor-General, Margaret Crawford released her report today on NSW Justice cluster agencies. The report focuses on key observations and findings from the most recent financial audits of law and order and emergency services agencies. We are pleased to report that unqualified audit opinions were issued for all Justice agencies’ financial statements.

This report analyses the results of the financial statement audits of the Justice cluster for the year ended 30 June 2018. The table below summarises our key observations.

This report provides parliament and other users of the Justice cluster agencies' financial statements with the results of our audits, including our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations
  • service delivery.

The Justice cluster delivers legal, law enforcement and emergency services across the state and plays the lead role in commemorating the legacy of servicemen and women. 

The commentary in this report covers the following cluster agencies.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making is enhanced when financial reporting is accurate and timely. 

This chapter outlines our audit observations, conclusions and recommendations related to the financial reporting of agencies in the Justice cluster for 2018.

Observation Conclusions and recommendations
2.1 Quality of financial reporting
Unqualified audit opinions were issued for all agencies' 30 June 2018 financial statements. Unqualified audit opinions were issued for all agencies' 30 June 2018 financial statements. However, further actions can be taken by some cluster agencies to enhance quality financial reporting. 
2.2 Timeliness of financial reporting
Mandatory early close procedures were largely completed and all financial statements were submitted and audited within statutory timeframes.  Early close procedures continue to facilitate the timely preparation of financial statements and completion of audits. Agencies can improve the effectiveness of early close procedures by completing revaluations earlier.
2.3 Death and disability schemes
The cost of the NSW Police Blue Ribbon Insurance Scheme decreased to 5.3 per cent of total NSW Police Officers’ remuneration in 2017–18, but remains above the statutory target of 4.6 per cent.  Recommendation: NSW Police should estimate the cost of its Blue Ribbon Insurance Scheme for future years, to understand when the statutory target of 4.6 per cent of total NSW Police Officers’ remuneration, will be met.
The Fire and Rescue NSW Death and Disability Scheme liability has doubled over the past six years. The Scheme’s liability was $184 million at 30 June 2018, double the $92 million recorded at 30 June 2013. Fire and Rescue NSW projections show the liability could increase to $257 million by 30 June 2022.
2.5 Financial sustainability
Funding in the criminal and civil justice system is determined in advance through the annual appropriation process. This does not always reflect required expenditure, which is driven by the level of activity.  Various agencies from across the cluster in conjunction with NSW Treasury have commenced work on a new demand funding model for the criminal and civil justice systems.
2.6 Human resources

More than a third of Justice cluster employees continue to have annual leave balances above the state's target. 

Almost 4,700 employees took little or no annual leave during 2017–18 compared to 4,394 in the prior year. 

Recommendation (repeat issue): 

Cluster agencies with annual leave balances exceeding the state's target should review their approach to managing leave balances. They should: 

  • regularly (e.g. each month) project annual leave balances to the end of the financial year, and
  • for employees with projected balances above target, develop and agree leave plans to reduce their balances over an acceptable timeframe.

Focus should be given to employees who have taken little or no leave in the last 12 months.

2.7 Workplace Health and Safety
Lost hours due to workplace injuries in NSW Police continue to increase. NSW Police data shows frontline staff recorded average workplace injury leave of 71.3 hours per full time employee in 2017–18, an increase of 17.6 hours over the last four years. NSW Police attribute the rising injury leave to an ageing workforce.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our observations and insights from:

  • our financial statement audits of agencies in the Justice cluster for 2018
  • the areas of focus identified in the Audit Office annual work program.

The Audit Office annual work program provides a summary of all audits to be conducted within the proposed time period as well as detailed information on the areas of focus for each of the NSW Government clusters.

Observation Conclusions and recommendations
3.1 Internal controls and governance
The number of internal controls or governance related issues reported increased to 116 (94 in 2016–17).

One in three were repeat issues.
Delays in implementing audit recommendations can prolong the risk of fraud and error.

Recommendation: Audit Office management letter recommendations to address internal control and governance weaknesses should be actioned promptly, with a focus on addressing repeat issues.. 
3.2 Audit Office annual work program
The Department continues to resolve IT, payroll and general finance related issues resulting from the implementation of the interrelated Justice SAP and Business Support Centre projects in 2016–17. During the year, the Department continued to make progress in stabilising its internal control environment, however more effort is required to ensure controls are operating as intended.

Internal control issues continue to collectively pose a high risk to the Department’s overall control environment. However, individually they are rated as low or moderate risk.

The Department provides financial, human resources and IT services to other independently governed agencies within the cluster. The internal control environment at these agencies is similarly impacted by the Department's Justice SAP and BSC issues.
The Department received an exemption from NSW Treasury from completing its asset revaluation as part of early close.

The revaluation results were not robustly reviewed before their inclusion in the financial statements.
While all revaluation matters were resolved and corrected, completing the revaluation process earlier would enable more timely review, identification and resolution of matters.

Recommendation: Revaluations should be performed early and completed by the early close procedures deadline. The Department should quality review the revaluation results before including them in the financial statements.
Capital projects at the Department and NSW Police were underspent against their budgets. The Department spent $671 million on capital projects in 2017–18, which was $905 million or 57.4 per cent less than budget.

Similarly, NSW Police spent $69.0 million or 28.3 per cent less than planned on capital projects. Eleven projects experienced delays in completion ranging from one to six years.
3.3 Managing maintenance
Total backlog maintenance in the Justice cluster is unknown because some agencies assess backlog maintenance, while others do not. When the backlog maintenance is unknown it is difficult for agencies to develop an accurate and effective maintenance plan that focuses on areas of highest need. It also means agencies' maintenance plans are reactive rather than preventative.

Recommendation: Cluster agencies should complete a condition based assessment of their assets to identify any maintenance backlog. This will help the cluster provide more reliable and consistent information on assets and their condition.

Justice cluster agencies we reviewed do not benchmark the adequacy of their maintenance spend.

Recommendation: Cluster agencies should consider establishing benchmarks to help assess the adequacy of their maintenance spend.

Government outcomes can be achieved through effective delivery of the right mix of services, whether from the public, private or not for profit sectors. Service delivery reform will be most successful if there is clear accountability for service delivery outcomes, decisions are aligned to strategic direction and performance is monitored and evaluated.

The Justice cluster is an integrated cluster with key service delivery inter-dependencies. Achieving state priorities and ensuring communities are safe requires both upstream and downstream agencies to be appropriately resourced. This is a delicate balance. Increases in frontline policing can subsequently impact the court system as more offences are identified. More convictions can in turn increase prison overcrowding and limit the opportunities for inmate rehabilitation.

Failure to successfully rehabilitate prisoners and prevent reoffending could impact future police resourcing. 

This chapter outlines certain service delivery outcomes for 2017–18. The data on activity levels and performance is provided by Cluster agencies. The Audit Office does not have a specific mandate to audit performance information. Accordingly, the information in this chapter is unaudited. 

We report this information on service delivery to provide additional context to understand the operations of the Justice cluster and to collate and present service information on law and order and emergency services agencies in one report. 

In our recent performance audit, Progress and measurement of the Premier's Priorities, we identified 12 limitations of performance measurement and performance data. We recommended the Department of Premier and Cabinet ensure that processes to check and verify data are in place for all agency data sources.

Published

Actions for Internal Controls and Governance 2018

Internal Controls and Governance 2018

Education
Community Services
Finance
Health
Industry
Justice
Planning
Premier and Cabinet
Transport
Treasury
Whole of Government
Environment
Compliance
Cyber security
Financial reporting
Fraud
Information technology
Internal controls and governance
Management and administration
Procurement
Project management

The Auditor-General for New South Wales Margaret Crawford found that as NSW state government agencies’ digital footprint increases they need to do more to address new and emerging information technology (IT) risks. This is one of the key findings to emerge from the second stand-alone report on internal controls and governance of the 40 largest NSW state government agencies.

This report analyses the internal controls and governance of the 40 largest agencies in the NSW public sector for the year ended 30 June 2018.

This report covers the findings and recommendations from our 2017–18 financial audits that relate to internal controls and governance at the 40 largest agencies (refer to Appendix three) in the NSW public sector.

This report offers insights into internal controls and governance in the NSW public sector

This is our second report dedicated to internal controls and governance at NSW State Government agencies. The report provides insights into the effectiveness of controls and governance processes in the NSW public sector by:

  • highlighting the potential risks posed by weaknesses in controls and governance processes
  • helping agencies benchmark the adequacy of their processes against their peers
  • focusing on new and emerging risks, and the internal controls and governance processes that might address those risks.

Without strong governance systems and internal controls, agencies increase the risks associated with effectively managing their finances and delivering services to citizens. The way agencies deliver services increasingly relies on contracts and partnerships with the private sector. Many of these arrangements deliver front line services, but others provide less visible back office support. For example, an agency may rely on an IT service provider to manage a key system used to provide services to the community. The contract and service level agreements are only truly effective where they are actively managed to reduce risks to continuous quality service delivery, such as interruptions caused by system outages, cyber security attacks and data security breaches.

Our audits do not review all aspects of internal controls and governance every year. We select a range of measures, and report on those that present heightened risks for agencies to mitigate. This report divides these into the following five areas:

  1. Internal control trends
  2. Information technology (IT), including IT vendor management
  3. Transparency and performance reporting
  4. Management of purchasing cards and taxis
  5. Fraud and corruption control.

The findings in this report should not be used to draw conclusions on the effectiveness of individual agency control environments and governance arrangements. Specific financial reporting, controls and service delivery comments are included in the individual 2018 cluster financial audit reports, which will be tabled in Parliament from November to December 2018.

The focus of the report has changed since last year

Last year's report topics included asset management, ethics and conduct, and risk management. We are reporting on new topics this year. We plan to introduce new topics and re-visit our previous topics in subsequent reports on a cyclical basis. This will provide a baseline against which to measure the NSW public sectors’ progress in implementing appropriate internal controls and governance processes to mitigate existing, new and emerging risks in the public sector.

Agencies selected for the volume account for 95 per cent of the state's expenditure

While we have covered only 40 agencies in this report, those selected are a large enough group to identify common issues and insights. They represent about 95 per cent of total expenditure for all NSW public sector agencies.

Internal controls are processes, policies and procedures that help agencies to:

  • operate effectively and efficiently
  • produce reliable financial reports
  • comply with laws and regulations
  • support ethical government.

This chapter outlines the overall trends for agency controls and governance issues, including the number of findings, level of risk and the most common deficiencies we found across agencies. The rest of this volume presents this year’s controls and governance findings in more detail.

Observation Conclusions and recommendations
2.1 High risk findings
We found six high risk findings (seven in 2016–17), one of which was repeated from both last year and 2015–16. Recommendation: Agencies should reduce risk by addressing high risk internal control deficiencies as a priority.
2.2 Common findings
We found several internal controls and governance findings common to multiple agencies. Conclusion: Central agencies or the lead agency in a cluster can play a lead role in helping ensure agency responses to common findings are consistent, timely, efficient and effective.
2.3 New and repeat findings
Although internal control deficiencies decreased over the last four years, this year has seen a 42 per cent increase in internal control deficiencies. The increase in new IT control deficiencies and repeat IT control deficiencies signifies an emerging risk for agencies.
IT control deficiencies feature in this increase, having risen by 63 per cent since last year. The number of repeat IT control deficiencies has doubled and is driven by the increasing digital footprint left by agencies as government prioritises on-line interfaces with citizens, and the number of transactions conducted through digital channels increases

Recommendation: Agencies should reduce IT risks by:

  • assigning ownership of recommendations to address IT control deficiencies, with timeframes and actions plans for implementation
  • ensuring audit and risk committees and agency management regularly monitor the implementation status of recommendations.

 

Government agencies’ financial reporting is now heavily reliant on information technology (IT). IT is also increasingly important to the delivery of agency services. These systems often provide the data to help monitor the efficiency and effectiveness of agency processes and services they deliver. Our audits reviewed whether agencies have effective controls in place to manage both key financial systems and IT service contracts.

Observation Conclusions and recommendations
3.1 Management of IT vendors
Contract management framework 
Although 87 per cent of agencies have a contract management policy to manage IT vendors, one fifth require review.
 

Conclusion: Agencies can more effectively manage IT vendor contracts by developing policies and procedures to ensure vendor management frameworks are kept up to date, plans are in place to manage vendor performance and risk, and compliance with the framework is monitored by:

  • internal audit focusing on key contracting activities
  • experienced officers who are independent of contract administration performing spot checks or peer reviews
  • targeted analysis of data in contract registers.
Contract risk management
Forty-one per cent of agencies are not using contract management plans and do not assess contract risks. Half of the agencies that did assess contract risks, had not updated the risk assessments since the commencement of the contract.
 
Conclusion: Instead of applying a 'set and forget' approach in relation to management of contract risks, agencies should assess risk regularly and develop a plan to actively manage identified risks throughout the contract lifecycle - from negotiation and commencement, to termination.

Performance management
Eighty-six per cent of agencies meet with vendors to discuss performance. 

Only 24 per cent of agencies sought assurance about the accuracy of vendor reporting against KPIs, yet sixty-seven per cent of the IT contracts allow agencies to determine performance based payments and/or penalise underperformance.

Conclusion: Agencies are monitoring IT vendor performance, but could improve outcomes and more effectively manage under-performance by:

  • a more active, rigorous approach to both risk and performance management
  • checking the accuracy of vendor reporting against those KPIs and where appropriate seeking assurance over their accuracy
  • invoking performance based payments clauses in contracts when performance falls below agreed standards.

Transitioning services
Forty-three per cent of the IT vendor contracts did not contain transitioning-out provisions.

Where IT vendor contracts do make provision for transitioning-out, only 28 per cent of agencies have developed a transitioning-out plan with their IT vendor.

Conclusion: Contract transition/phase out clauses and plans can mitigate risks to service disruption, ensure internal controls remain in place, avoid unnecessary costs and reduce the risk of 'vendor lock-in'.
Contract Registers
Eleven out of forty agencies did not have a contract register, or have registers that are not accurate and/or complete.

Conclusion: A contract register helps to manage an agency’s compliance obligations under the Government Information (Public Access) Act 2009 (the GIPA Act). However, it also helps agencies more effectively manage IT vendors by:

  • monitoring contract end dates and contract extensions, and commence new procurements through their central procurement teams in a timely manner
  • managing their contractual commitments, budgeting and cash flow requirements.

Recommendation: Agencies should ensure their contract registers are complete and accurate so they can more effectively govern contracts and manage compliance obligations.

3.2 IT general controls
Governance
Ninety-five per cent of agencies have established policies to manage key IT processes and functions within the agency, with ten per cent of those due for review.
 
Conclusion: Regular review of IT policies ensures risks are considered and appropriate strategies and procedures are implemented to manage these risks on a consistent basis. An absence of policies can lead to ad-hoc responses to risks, and failure to consider emerging IT risks and changes to agency IT environments. 

User access administration
Seventy-two deficiencies were identified related to user access administration, including:

  • thirty issues related to granting user access across 43 per cent of agencies
  • sixteen issues related to removing user access across 30 per cent of agencies
  • twenty-six issues related to periodic reviews of user access across 50 per cent of agencies.
Recommendation: Agencies should strengthen the administration of user access to prevent inappropriate access to key systems.
Privileged access
Forty per cent of agencies do not periodically review logs of the activities of privileged users to identify suspicious or unauthorised activities.

Recommendation: Agencies should:

  • review the number of, and access granted to privileged users, and assess and document the risks associated with their activities
  • monitor user access to address risks from unauthorised activity.
Password controls
Twenty-three per cent of agencies did not comply with their own policy on password parameters.
Recommendation: Agencies should ensure IT password settings comply with their password policies.
Program changes
Fifteen per cent of agencies had deficient IT program change controls mainly related to segregation of duties and authorisation and testing of IT program changes prior to deployment.
Recommendation: Agencies should maintain appropriate segregation of duties in their IT functions and test system changes before they are deployed.

 

This chapter outlines our audit observations, conclusions and recommendations from our review of how agencies reported their performance in their 2016–17 annual reports. The Annual Reports (Statutory Bodies) Regulation 2015 and Annual Reports (Departments) Regulation 2015 (annual reports regulation) currently prescribes the minimum requirements for agency annual reports.

Observation Conclusion or recommendation
4.1 Reporting on performance

Only 57 per cent of agencies linked reporting on performance to their strategic objectives.

The use of targets and reporting performance over time was limited and applied inconsistently.

Conclusion: There is significant disparity in the quality and consistency of how agencies report on their performance in their annual reports. This limits the reliability and transparency of reported performance information.

Agencies could improve performance reporting by clearly linking strategic objectives to reported outcomes, and reporting on performance against targets over time. NSW Treasury may need to provide more guidance to agencies to support consistent and high-quality performance reporting in annual reports.

There is no independent assurance that the performance metrics agencies report in their annual reports are accurate.

Prior performance audits have noted issues related to the collection of performance information. For example, our 2016 Report on Red Tape Reduction highlighted inaccuracies in how the dollar-value of red tape reduction had been reported.

Conclusion: The ability of Parliament and the public to rely on reported information as a relevant and accurate reflection of an agency's performance is limited.

The relevance and accuracy of performance information is enhanced when:

  • policies and guidance support the consistent and accurate collection of data
  • internal review processes and management oversight are effective
  • independent review processes are established to provide effective challenge to the assumptions, judgements and methodology used to collect the reported performance information.
4.2 Reporting on reports

Agency reporting on major projects does not meet the requirements of the annual reports regulation.

Forty-seven per cent of agencies did not report on costs to date and estimated completion dates for major works in progress. Of the 47 per cent of agencies that reported on major works, only one agency reported detail about significant cost overruns, delays, amendments, deferments or cancellations.

NSW Treasury produce an annual report checklist to help agencies comply with their annual report obligations.

Recommendation: Agencies should comply with the annual reports regulation and report on all mandatory fields, including significant cost overruns and delays, for their major works in progress.

The information the annual reports regulation requires agencies to report deals only with major works in progress. There is no requirement to report on completed works.

Sixteen of 30 agencies reported some information on completed major works.

Conclusion: Agencies could improve their transparency if they reported, or were required to report:

  • on both works in progress and projects completed during the year
  • actual costs and completion dates, and forecast completion dates for major works, against original and revised budgets and original expected completion dates
  • explanations for significant cost overruns, delays and key project performance metrics.

 

This chapter outlines our audit observations, conclusions and recommendations, arising from our review of agency preventative and detective controls over purchasing card and taxi use for 2017–18.

Observation Conclusion or recommendation
5.1 Management of purchasing cards
Volume of credit card spend
Purchasing card expenditure has increased by 76 per cent over the last four years in response to a government review into the cost savings possible from using purchasing cards for low value, high volume procurement.
 
Conclusion: The increasing use of purchasing cards highlights the importance of an effective framework for the use and management of purchasing cards.
Policy framework
We found all agencies that held purchasing cards had a policy in place, but 26 per cent of agencies have not reviewed their purchasing card policy by the scheduled date, or do not have a scheduled revision date stated within their policy.
Recommendation: Agencies should mitigate the risks associated with increased purchasing card use by ensuring policies and purchasing card frameworks remain current and compliant with the core requirements of TPP 17–09 'Use and Management of NSW Government Purchasing Cards'.
Preventative controls
We found that:
  • all agencies maintained purchasing card registers
  • seventy-six per cent provided training to cardholders prior to being issued with a card
  • eighty-nine per cent appointed a program administrator, but only half of these had clearly defined roles and responsibilities
  • thirty-two per cent of agencies place merchant blocks on purchasing cards
  • forty-seven per cent of agencies place geographic restrictions on purchasing cards.

Agencies have designed and implemented preventative controls aimed at deterring the potential misuse of purchasing cards.

Conclusion: Further opportunities exist for agencies to better control the use of purchasing cards, such as:

  • updating purchasing card registers to contain all mandatory fields required by TPP17–09
  • appointing a program administrator for the agency's purchasing card framework and defining their role and responsibility for the function
  • strengthening preventive controls to prevent misuse.

Detective controls
Ninety-two per cent of agencies have designed and implemented at least one control to monitor purchasing card activity.

Major reviews, such as data analytics (29 per cent of agencies) and independent spot checks (49 per cent of agencies) are not widely used.

Agencies have designed and implemented detective controls aimed at identifying potential misuse of purchasing cards.

Conclusion: More effective monitoring using purchasing card data can provide better visibility over spending activity and can be used to:

  • detect misuse and investigate exceptions
  • analyse trends to highlight cost saving opportunities.
5.2 Management of taxis
Policy framework
Thirteen per cent of agencies have not developed and implemented a policy to manage taxi use. In addition:
  • a further 41 per cent of agencies have not reviewed their policies by the scheduled revision date, or do not have a scheduled revision date
  • more than half of all agencies’ policies do not offer alternative travel options. For example, only 36 per cent of policies promoted the use of general Opal cards.
Conclusion: Agencies can promote savings and provide more options to staff where their taxi use policies:
  • limit the circumstances where taxi use is appropriate
  • offer alternate, lower cost options to using taxis, such as general Opal cards and rideshare.
Detective controls
All agencies approve taxi expenditure by expense reimbursement, purchasing card and Cabcharge, and have implemented controls around this approval process. However, beyond this there is minimal monitoring and review activity, such as data monitoring, independent spot checks or internal audit reviews.
Conclusion: Taxi spend at agencies is not significant in terms of its dollar value, but it is significant from a probity perspective. Agencies can better address the probity risk by incorporating taxi use into a broader purchasing card or fraud monitoring program.

 

Fraud and corruption control is one of the 17 key elements of our governance lighthouse. Recent reports from ICAC into state agencies and local government councils highlight the need for effective fraud control and ethical frameworks. Effective frameworks can help protect an agency from events that risk serious reputational damage and financial loss.

Our 2016 Fraud Survey found the NSW Government agencies we surveyed reported 1,077 frauds over the three year period to 30 June 2015. For those frauds where an estimate of losses was made, the reported value exceeded $10.0 million. The report also highlighted that the full extent of fraud in the NSW public sector could be higher than reported because:

  • unreported frauds in organisations can be almost three times the number of reported frauds
  • our 2015 survey did not include all NSW public sector agencies, nor did it include any NSW universities or local councils
  • fraud committed by citizens such as fare evasion and fraudulent state tax self-assessments was not within the scope of our 2015 survey
  • agencies did not estimate a value for 599 of the 1,077 (56 per cent) reported frauds.

Commissioning and outsourcing of services to the private sector and the advancement of digital technology are changing the fraud and corruption risks agencies face. Fraud risk assessments should be updated regularly and in particular where there are changes in agency business models. NSW Treasury Circular TC18-02 NSW Fraud and Corruption Control Policy now requires agencies develop, implement and maintain a fraud and corruption control framework, effective from 1 July 2018. 

Our Fraud Control Improvement Kit provides guidance and practical advice to help organisations implement an effective fraud control framework. The kit is divided into ten attributes. Three key attributes have been assessed below; prevention, detection and notification systems.

This chapter outlines our audit observations, conclusions and recommendations, arising from our review of agency fraud and corruption controls for 2017–18.

Observation Conclusion or recommendation
6.1 Prevention systems

Prevention systems
Ninety-two per cent of agencies have a fraud control plan in place, 81 per cent maintain a fraud database and 79 per cent report fraud and corruption matters as a standing item on audit and risk committee agendas.

Only 54 per cent of agencies have an employment screening policy and all agencies have IT security policies, but gaps in IT security controls could undermine their policies.

Conclusion: Most agencies have implemented fraud prevention systems to reduce the risk of fraud. However poor IT security along with other gaps in agency prevention systems, such as employment screening practices heightens the risk of fraud and inappropriate use of data.

Agencies can improve their fraud prevention systems by:

  • completing regular fraud risk assessments, embedding fraud risk assessment into their enterprise risk management process and reporting the results of the assessment to the audit and risk committee
  • maintaining a fraud database and reviewing it regularly for systemic issues and reporting a redacted version of the database on the agency's website to inform corruption prevention networks
  • developing policies and procedures for employee screening and benchmarking their current processes against ICAC's publication ‘Strengthening Employment Screening Practices in the NSW Public Sector’
  • developing and maintaining up to date IT security policies and monitoring compliance with the policy.
Twenty-three per cent of agencies were not performing fraud risk assessments and some agency fraud risk assessments may not be as robust as they could be.  Conclusion: Agencies' systems of internal controls may be less effective where new and emerging fraud risks have been overlooked, or known weaknesses have not been rectified.
6.2 Detection systems
Detection systems
Several agencies reported they were developing a data monitoring program, but only 38 per cent of agencies had already implemented a program.
 

Studies have shown data monitoring, whereby entire populations of transactional data are analysed for indicators of fraudulent activity, is one of the most effective methods of early detection. Early detection decreases the duration a fraud remains undetected thereby limiting the extent of losses.

Conclusion: Data monitoring is an effective tool for early detection of fraud and is more effective when informed by a comprehensive fraud risk assessment.

6.3 Notification systems
Notification system
All agencies have notification systems for reporting actual or suspected fraud and corruption. Most agencies provide multiple reporting lines, provide training and publicise options for staff to report actual or suspected fraud and corruption.
Conclusion: Training staff about their obligations and the use of fraud notification systems promotes a fraud-aware culture