Actions for CBD and South East Light Rail: follow-up performance audit

CBD and South East Light Rail: follow-up performance audit

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk
Service delivery

The CBD and South East Light Rail is a 12 km light rail network for Sydney. It extends from Circular Quay along George Street to Central Station, through Surry Hills to Moore Park, then to Kensington and Kingsford via Anzac Parade and Randwick via Alison Road and High Street. Transport for NSW (TfNSW) is responsible for planning, procuring and delivering the Central Business District and South East Light Rail (CSELR) project. In December 2014, TfNSW ent

Published

Actions for Health 2016

Health 2016

Health
Asset valuation
Compliance
Cyber security
Financial reporting
Fraud
Information technology
Internal controls and governance
Project management

This report analyses the results of the financial statement audits of the Health cluster agencies for 2015–16.

Published

Actions for Transport 2016

Transport 2016

Transport
Asset valuation
Compliance
Financial reporting
Fraud
Information technology
Internal controls and governance
Procurement
Project management

Financial reporting within the Transport Cluster continues to improve with reported misstatements down 96 per cent since 2011-12 to just three in 2015-16, according to a report released today by the NSW Auditor-General, Margaret Crawford.

Published

Actions for CBD and South East Light Rail Project

CBD and South East Light Rail Project

Transport
Compliance
Financial reporting
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk

Transport for NSW did not effectively plan and procure the CBD and South East Light Rail (CSELR) project to achieve best value for money according to a report released today by NSW Auditor-General, Margaret Crawford. Transport for NSW is on track to deliver the project, but it will come at a higher cost with lower benefits than in the approved business case.   Parliamentary reference - Report number #278 - released 30 November 2016

Published

Actions for Finance, Services and Innovation 2016

Finance, Services and Innovation 2016

Finance
Asset valuation
Financial reporting
Information technology
Internal controls and governance
Project management
Risk

This report analyses the results of the financial statement audits of the Finance, Services and Innovation cluster entities for the year ended 30 June 2016.

Published

Actions for Red tape reduction

Red tape reduction

Premier and Cabinet
Finance
Financial reporting
Internal controls and governance
Management and administration
Project management
Regulation
Shared services and collaboration

Overall, NSW Government initiatives and processes to prevent and reduce red tape were not effective, according to a report released today by the NSW Auditor-General. In 2015, the Government reported that its red tape reduction initiatives, implemented between 2011 and 2015, had resulted in $896 million in savings. While these initiatives resulted in some savings, the total value of savings is unknown because estimates for some initiatives were based on

Published

Actions for Handback of the M4 Tollway

Handback of the M4 Tollway

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management

This audit focuses on the M4 handback. It looks at whether the road will be in good condition when the State gets it back, and whether it will cope with the extra traffic after the toll is removed. These are critical issues for taxpayers and motorists. Taxpayers don’t want to be responsible for a large repair bill and motorists don’t want to be stuck in traffic jams. To ensure that future private sector partnerships (PPP) deal adequately with handback,

Published

Actions for Government Licensing Project

Government Licensing Project

Finance
Information technology
Internal controls and governance
Management and administration
Project management
Shared services and collaboration

The Government Licensing Project (GLP) is standardising and simplifying processes of agencies which issue licences. However, it is currently running over the original anticipated completion date, exceeding the original budget and expected to produce savings less than originally planned.   Parliamentary reference - Report number #192 - released 7 October 2009

In progress

Actions for WestConnex: Changes since 2014

WestConnex: Changes since 2014

Transport
Compliance
Financial reporting
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk
Service delivery

The WestConnex project is a motorway project that will link the M4 and M5 motorways with 33km of new motorway tunnels in Sydney. We conducted a performance audit of the WestConnex business case review process in 2014. Since then, the scope and projects included in WestConnex have changed. This audit will assess whether Transport for NSW and Infrastructure NSW effectively assessed and justified major scope changes to the WestConnex project since December

Planned

Actions for Health capital works

Health capital works

Health
Asset valuation
Financial reporting
Infrastructure
Management and administration
Project management
Regulation
Service delivery

According to the 2018 Auditor-General’s Report to Parliament on Health, the value of assets held by NSW Health increased from $18.6 billion at 30 June 2017 to $20.1 billion at 30 June 2018. Most of this increase is attributed to capital expenditure on new facilities, upgrades and redevelopments. The same report also notes that two capital projects were completed on time and under budget in the same financial year. Completion dates were revised for ten ot