Refine search Expand filter

Reports

Published

Actions for CBD and South East Light Rail Project

CBD and South East Light Rail Project

Transport
Compliance
Financial reporting
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk

Transport for NSW did not effectively plan and procure the CBD and South East Light Rail (CSELR) project to achieve best value for money according to a report released today by NSW Auditor-General, Margaret Crawford.

Transport for NSW is on track to deliver the project, but it will come at a higher cost with lower benefits than in the approved business case.

 

Parliamentary reference - Report number #278 - released 30 November 2016

Published

Actions for Red tape reduction

Red tape reduction

Premier and Cabinet
Finance
Financial reporting
Internal controls and governance
Management and administration
Project management
Regulation
Shared services and collaboration

Overall, NSW Government initiatives and processes to prevent and reduce red tape were not effective, according to a report released today by the NSW Auditor-General.

In 2015, the Government reported that its red tape reduction initiatives, implemented between 2011 and 2015, had resulted in $896 million in savings. While these initiatives resulted in some savings, the total value of savings is unknown because estimates for some initiatives were based on unverified assumptions, cost transfers or unrealised projections.

 

Parliamentary reference - Report number #272 - released 25 August 2016

Published

Actions for Franchising of Sydney Ferries Network services

Franchising of Sydney Ferries Network services

Transport
Procurement
Service delivery

Franchising services on the Sydney Ferries Network was justified, and Transport for NSW’s management of the franchise has been largely effective according to a report released today by the NSW Acting Auditor-General, Tony Whitfield.

'Franchising has resulted in cost savings, good service performance, and effective risk transfer from government to the private sector operator', said Mr Whitfield.

 

Parliamentary reference - Report number #265 - released 4 February 2016

Published

Actions for Reducing Ambulance Turnaround Time at Hospitals

Reducing Ambulance Turnaround Time at Hospitals

Health
Compliance
Management and administration
Service delivery

NSW Health has put in place initiatives to reduce the time ambulance crews have to wait at a hospital before they are able to leave and attend to other calls. Despite these actions, ambulance crews are waiting longer at NSW hospitals. Crews now wait on average nearly 32 minutes at a hospital before handing over a patient, up from about 24 minutes seven years ago.

 

Parliamentary reference - Report number #233 - released 24 July 2013

Published

Actions for Managing Operating Theatre Efficiency for Elective Surgery

Managing Operating Theatre Efficiency for Elective Surgery

Health
Compliance
Management and administration
Service delivery

Waiting times for elective surgery will continue to increase if NSW Health does not improve its management of operating theatres. On the positive side NSW public hospitals are performing more elective surgery than in previous years and are treating patients substantially within national clinical timeframes. However, more operations will be needed as targets are getting tighter and demand is growing.

 

Parliamentary reference - Report number #232 - released 17 July 2013