Actions for Sydney Road Maintenance Contracts
Sydney Road Maintenance Contracts
In November 2013, Roads and Maritime Services (RMS) outsourced the maintenance of State roads in the Sydney region south and west zones using an innovative contracting approach called the Stewardship Maintenance Contract (SMC). The SMC links risk to reward, and uses a performance framework where outcomes should drive improved performance over time.
WA | VIC | QLD | NSW | |
---|---|---|---|---|
Roads managed (lane kms) | 52,659 | 50,510 | 71,353 | 80,348 |
Estimated spend ($/lane km) | 5,000 | 4,500 | 6,000 | 7,000 |
Road quality measure (%) | 99 | 99 | 94 | 91 |
Parliamentary reference - Report number #288 - released 15 June 2017
Actions for Dealing with Unlicensed and Unregistered Driving
Dealing with Unlicensed and Unregistered Driving
In our opinion there are inadequacies in the current arrangements for detecting unauthorised driving. For example better information is needed on the extent of unlicensed driving. This may require giving the NSW Police power to conduct random licence and registration checks. In addition, there are technological and legal constraints to the efficient and effective detection of unauthorised driving.
Parliamentary reference - Report number #115 - released 4 September 2003
Actions for Freedom of Information
Freedom of Information
Freedom of Information (FOI) Coordinators and their staff were supportive of the legislation. However, the agencies examined can do considerably more to fully achieve the intentions of the Act. On the positive side, all three agencies had processes in place to handle requests and had made a number of changes to improve the effectiveness of the FOI process. Fees and charges had also been kept to a minimum. No processing fees were requested in the majority of cases, and if charged, were not unreasonable.
Parliamentary reference - Report number #114 - released 28 August 2003
Actions for The Millennium Train Project
The Millennium Train Project
State Rail has made significant improvements since the purchase of the Tangara. It improved measures necessary for handling contracts dealing with technically complex and innovative projects, although some other problems have been encountered, with new lessons to learn. The design and manufacture of new trains requires a significant investment in both time and cost. The Millennium Train has come at a considerably higher price than originally expected. And it is very late compared to the Government’s original announcements, as the development/design took longer than planned.
Parliamentary reference - Report number #112 - released 17 June 2003