Refine search Expand filter

Reports

Published

Actions for Building regulation: combustible external cladding

Building regulation: combustible external cladding

Finance
Local Government
Planning
Compliance
Infrastructure
Regulation
Risk

What the report is about

The report focuses on how effectively the Department of Customer Service (DCS) and Department of Planning and Environment (DPE) led reforms addressing the unsafe use of combustible external cladding on existing residential and public buildings.

Nine local councils were included in the audit because they have responsibilities and powers needed to implement the NSW Government’s reforms.

What we found

After the June 2017 Grenfell Tower fire in London, the NSW Government committed to a ten-point action plan, which included establishing the NSW Cladding Taskforce, chaired by DCS, and with DPE as a key member. The Taskforce co-ordinates and oversees the implementation of the plan.

Depending on the original source of development approval, either individual local councils or DPE are responsible for ensuring that buildings are identified, assessed, and remediated. NSW Government-owned buildings are the responsibility of each department.

Identifying buildings potentially at risk was complex and resource intensive. However, on balance, it is likely that most affected buildings have now been identified.

By October 2021, around 40 per cent of assessed high-risk buildings that are the responsibility of local councils had either been remediated or found not to pose an unacceptable fire risk.

By February 2022, almost 50 per cent of affected NSW Government-owned buildings, and 90 per cent of buildings that are the responsibility of DPE, have either been cleared or are in the process of being remediated.

Earlier guidance on some key issues could have been provided by DCS and DPE in the two years after the Grenfell Tower fire. This may have reduced confusion and inconsistency across local councils we audited, and in some NSW Government departments. This especially relates to the application of the Fair Trading Commissioner's product use ban.

Given the inherent risks posed by combustible external cladding, buildings initially assessed as low-risk may also still warrant further action.

While most high-risk buildings have likely been identified, poor information handling makes it difficult to keep track of all buildings from identification, through to risk assessment and remediation.

What we recommended

DCS and DPE should:

  1. address the confusion surrounding the application of the Commissioner for Fair Trading's product use ban for aluminium composite panels with polyethylene content greater than 30 per cent
  2. develop an action plan to address buildings assessed as low-risk
  3. improve information systems to track all buildings from identification through to remediation.

Fast facts

Authority responsible for
ensuring that owners make
their buildings safe
Approximate number of
buildings referred for further
investigation*
Approximate percentage of
buildings remediated or
assessed to be safe
Local councils 1,200 40%
NSW Government owned 66 50%
DPE under delegation from
the Minister for Planning
137 90%
*After initial inspection by Fire and Rescue NSW, and/or preliminary inquiries by the consent authority, it was identified that the building may be at high-risk of
fire from combustible external cladding.

 

NSW Government's response to the risks posed by combustible external cladding

The NSW Government first became aware of the potential heightened risks posed by combustible external cladding on building exteriors after the 2014 Lacrosse Tower fire in Melbourne. However, it was the tragic loss of life from the Grenfell Tower fire in London, in June 2017, that gave added urgency to the need to address these risks.

Within six weeks of the London fire, the NSW Government committed to a ten-point plan of action for NSW to:

  • identify and remediate any buildings with combustible external cladding
  • ensure that regulation prevented the unsafe use of such cladding
  • ensure that experts involved in providing advice and certifying fire safety measures had the necessary skills and experience.

One of the actions in the ten-point plan was the creation of the NSW Government's Fire Safety and External Wall Cladding Taskforce (the Cladding Taskforce) chaired by the Department of Customer Service (DCS) and with the Department of Planning and Environment (DPE) as a key member.

The ten-point plan also specified that NSW Government departments would be responsible, in regard to buildings they owned to '…audit their buildings and determine if they have aluminium cladding'.

Local councils play a key role in implementing the Government's reforms, given their responsibilities and powers under the Environmental Planning and Assessment Act 1979 (EPA Act) and Local Government Act 1993 (Local Government Act) to approve building works (as 'consent authorities'), as well as to ensure fire safety standards are met. DPE plays an equivalent role for a smaller number of 'State Significant Developments' for which it is the consent authority under delegation from the Minister for Planning.

Commissioner for Fair Trading's building product use ban

On 18 December 2017, the Building Products (Safety) Act 2017 (BPS Act) came into effect in NSW, introducing new laws to prevent the use of unsafe building products. Notably, the BPS Act gave the Secretary of DCS and the Commissioner for Fair Trading the power to ban unsafe uses of building products.

After an extensive consultative process, the Commissioner for Fair Trading used these powers to issue a product use ban on 15 August 2018. This banned the use of external wall cladding of aluminium composite panels with a core comprised of more than 30 per cent polyethylene by mass on new buildings, unless the proposed use was subject to independent fire propagation testing of the specific product and method of application to a building in accordance with relevant Australian Standards.

Buildings occupied before the product use ban came into force are not automatically required to have the banned product removed. Under the BPS Act, consent authorities may determine necessary actions to eliminate or minimise the risk posed by the banned material on existing buildings.

Project Remediate

Project Remediate is a three-year NSW Government program announced in November 2020. The program was designed by the NSW Government to assist building owners of multi-storey apartments (two storeys or more) with high-risk combustible cladding to remediate their building to a high standard and for a fair price.

The scheme is voluntary and includes government paying for the interest on ten-year loans, as well as incorporating assurance and project management services to provide technical and practical support to owners’ corporations and strata managing agents. Building remediations under the program are expected to commence in 2022.

About this audit

This audit assessed whether DCS and DPE effectively led reforms to manage the fire safety risk of combustible external cladding on existing residential and public buildings.

In making this assessment, we considered whether the expressed policy intent of the NSW Government's ten-point plan for fire safety reform had been achieved by asking:

  • are the fire safety risks of combustible external cladding on existing buildings identified and remediated?
  • is there a comprehensive building product safety scheme that prevents the dangerous use of combustible external cladding products on existing buildings?
  • is fire safety certification for combustible external cladding on existing buildings carried out impartially, ethically and in the public interest by qualified experts?

Consistent with the focus of the Cladding Taskforce on multi-storey residential buildings and public buildings, the scope of our audit is limited to buildings categorised under the Building Code of Australia (BCA) as class 2, 3 and 9. These classes are defined in detail in section 1.2, but include: multi-unit residential apartments, hotels, motels, hostels, back-packers, and buildings of a public nature, including health care buildings, schools, and aged care buildings. The scope was also limited to existing buildings, which is defined as buildings occupied by 22 October 2018.

Auditees

The Department of Customer Service chairs the NSW Government's Cladding Taskforce, which is responsible for coordinating the combustible external cladding reforms. The Commissioner of Fair Trading sits within DCS and DCS regulates the industry accreditation scheme for fire safety practitioners, as well as administering the BPS Act.

The Department of Planning and Environment administers the EPA Act and the Environmental Planning and Assessment Regulation 2000 (EPA Regulation), which regulate the building development process. As well as being the delegated consent authority for State Significant Developments, DPE is also responsible for maintaining the mandatory cladding register requiring building owners of multi-storey (BCA class 2, 3 or 9) buildings to register buildings with combustible external cladding on an online portal.

Functions and responsibilities between DCS and DPE varied over time. For example, in October 2019, the DPE building policy team responsible for co-ordinating the DPE response to the combustible cladding issue was transferred to DCS, following changes to agency responsibilities resulting from machinery of government changes. DPE advised this resulted in a lessening of DPE's subsequent policy work on combustible cladding and its involvement in the Cladding Taskforce.

While the focus of the audit was on the oversight and coordination provided by DCS and DPE, nine councils were also auditees for this performance audit. Councils play an essential part as consent authorities for building development approvals in NSW, as well as having responsibilities and powers to ensure fire safety standards. To fully understand how well their activities were overseen and coordinated, a sample of councils was included as auditees.

Nine councils were selected to represent both metropolitan and regional areas, noting that there are very few in-scope buildings in rural areas. The audited councils were:

  • Bayside Council
  • City of Canterbury Bankstown Council
  • Cumberland City Council
  • Liverpool City Council
  • City of Newcastle Council
  • City of Parramatta Council
  • City of Ryde Council
  • City of Sydney Council
  • Wollongong City Council.

Terminology

The two NSW Government department auditees have, over time, been subject to machinery of government changes, which have changed some of their functions and what the departments are called.

Relevant to this audit, the effect of these changes has been:

  • the Department of Finance, Services, and Innovation (DFSI) became the Department of Customer Services (DCS) on 1 July 2019
  • on 1 July 2019, the Department of Planning and Environment became the Department of Planning, Industry, and Environment (DPIE)
  • on 21 December 2021, DPIE became the Department of Planning and Environment (DPE).

To avoid confusion, we use the titles by which these departments are known at the date of this report: the Department of Customer Service and the Department of Planning and Environment.

Conclusion

At July 2017, immediately after the Grenfell Tower fire, there was no reliable source to identify buildings that may have had combustible external cladding. However, it is now likely that most high-risk buildings have been identified.

Following the 2014 Lacrosse Tower fire in Melbourne, the NSW Government recognised that there was a need to be able to identify buildings in NSW that could have combustible external cladding.

The process of identifying buildings that could have combustible external cladding has been complex, resource-intensive, and inefficient principally due to the lack of centralised and coordinated building records in NSW. In total, approximately 1,200 BCA class 2, 3 and 9 buildings have been brought to the attention of councils by either Fire and Rescue NSW (FRNSW), the Cladding Taskforce, or through councils' own inspection for possible further action. In addition, approximately 2,000 more buildings were inspected by FRNSW but not referred to local councils because they either had no combustible external cladding or had combustible external cladding not assessed as being high-risk.

A multi-pronged approach to identifying buildings has been used by the DCS and DPE, through the Cladding Taskforce. While it is impossible to know the full scope of potentially affected buildings, the approach appears thorough in having identified most relevant buildings.

The process of clearing buildings with combustible external cladding has been inconsistent.

In the more than four years since the NSW Government's ten-point plan was announced, around 40 per cent of the buildings brought to the attention of councils have been cleared by either rectification or being found not to pose an unacceptable fire risk. Also, around 50 per cent of NSW Government-owned buildings identified with combustible external cladding and almost 90 per cent of identified buildings for which DPE is consent authority have been cleared or remediation is underway.

While DCS and DPE did seek to work cooperatively with councils and provided high-level guidance on the NSW Government’s fire safety reforms, it took until September 2019 before a model process and other detailed advice was provided to councils to encourage consistent processes. DCS and DPE advice to councils and NSW Government-building owners should have been more timely on two key issues:

  • the use of experts in the process of assessing and remediating existing buildings, and
  • the implementation of the product use ban on aluminium composite panels with polyethylene content 30 per cent or greater.

Clarifying the application of the product use ban may require consent authorities and building owners to revisit how some buildings have been cleared.

The management of buildings assessed as low-risk by FRNSW, estimated to be over 500, has not been a priority of the Cladding Taskforce to date, despite those buildings potentially posing unacceptable fire risks.

Information management by the Cladding Taskforce is inadequate to provide a high-level of assurance that all known affected buildings have been given proper attention.

While most high-risk buildings have likely been identified, information management is not sufficiently robust to reliably track all buildings through the process from identification, through to risk assessment and, where necessary, remediation.

Reforms to certifier registration schemes are limited to new buildings and do not apply to the existing buildings covered by this audit.

While reforms are limited in application to new buildings, some consent authorities took steps to obtain greater assurance on the quality of the work done by fire safety experts regarding combustible external cladding on existing buildings. For example, by requiring fire safety experts to be appropriately qualified and requiring peer review of cladding risk assessments and proposed remediation plans.

 

This chapter considers the part played by DCS and DPE as key members of the Cladding Taskforce in ensuring that buildings with combustible external cladding were effectively identified and remediated through processes implemented by:

  • local councils or DPE, where those bodies were consent authorities under the EPA Act for the relevant buildings
  • in the case of NSW Government buildings, the departments that owned those buildings.

This chapter considers what has been done to deliver a comprehensive building product safety scheme that prevents the dangerous use of combustible external cladding products.

 

This chapter considers whether reforms have ensured that only people with the necessary skills and experience are certifying buildings and signing off on fire-safety.

Inspections of existing buildings and development of any subsequent action plans to address combustible external cladding are not activities covered by accreditation or registration schemes for building certifiers

Almost all the risk assessment and remediation work done on buildings in the scope of this audit have been undertaken under fire safety orders issued by consent authorities using their powers under the EPA Act. This has been the recommended approach by DPE and DCS since at least 2016 (that is, before the Grenfell Tower fire in London).

While there have been reforms to certifier registrations scheme, these were not intended to ensure that combustible cladding-remediation on existing buildings is supported by people with the necessary skills and experience in fire safety under the fire safety order process. Instead, they are focused on offering better assurance for work done in respect to new building projects where accredited experts certify that building work is carried out in accordance with BCA under the DCS managed certifier registration schemes.

No steps have been taken to ensure the quality of the work done by experts inspecting, assessing the fire risk and developing action plans to address combustible external cladding on existing buildings, other than where consent authorities have chosen to exercise their discretion. This includes requiring fire safety experts to be appropriately qualified and requiring peer review of some cladding risk assessments and remediation plans.

Consent authorities determine whether individuals with accreditation are required for combustible cladding inspection, risk assessments and remediation on existing buildings

Whether an individual with certifier accreditation participates in a cladding inspection, risk assessment, or remediation for an existing building will be determined by what councils as consent authorities specify in their fire safety orders unless building owners opt to use such experts without being directed to do so by the consent authority.

As discussed earlier, councils acting as consent authorities vary in whether they require building owners to engage individuals with certifier accreditation. In most of the councils we audited, A1 or C10 accredited experts were either required, or recommended, to perform functions such as auditing suspected combustible cladding, or conducting fire safety risk assessments and developing plans to rectify combustible cladding.

However, these types of work are not functions covered by the accreditation or registration schemes that apply to building and development certifiers.

Certifier accreditation schemes do not cover cladding remediation work done under fire safety orders

While councils may require or recommend that independent accredited A1 or C10 certifiers be engaged by building owners for cladding risk assessment and remediation, they are not performing those functions as certifiers — they are, in effect, more akin to expert consultants. Accordingly, how they perform their functions and duties is not covered by the legislation supporting the accreditation scheme for certifiers that was operated until July 2020 by the Building Professional Board.

Instead, their use in this process is a convenient and practical way for consent authorities to ensure that building owners use appropriate experts who have the qualifications, skills and experience needed to investigate and identify combustible cladding, and then to formulate appropriate action to deal with such cladding. However, these individuals are not performing regulated or accredited work, are not subject to regulatory oversight, and are not accountable to any accreditation body for the quality of the work they perform.

While councils could (and sometimes do) choose to decline poor quality or incomplete cladding-related work prepared by A1 or C10 certifiers, the burden of resolving poor quality would fall on the building owner, who would have to seek amended or additional risk assessments or rectification plans.

In the absence of regulatory oversight, disincentives for poor quality cladding-related work, may include litigation being commenced by the property owner, harm to the expert's reputation in a small and competitive market, and the potential impact on whether the individual could retain their professional indemnity insurance at a reasonable cost (especially in an environment when many insurance providers withdrew coverage for cladding related work).

Reforms impact on regulated experts doing work on new buildings

The reforms that commenced on 1 July 2020, replaced categories of accreditation with classes of registration, and varied the classes such that:

  • accredited building surveyor category A1 became registered building surveyor-unrestricted
  • accredited certifier—fire safety engineer category C10 became registered certifiers-fire safety.

The legislation that introduced these reforms, the Building and Development Certifiers Act 2018, also repealed the pre-existing Building Professionals Act 2005 and abolished the Building Professionals Board. The new Act was accompanied by the Building and Development Certifiers Regulation 2020.

While the scope of this audit is limited to existing buildings, we note that there are buildings with combustible external cladding that are yet to be remediated. Just as these processes previously drew on the expertise of A1 and C10 category certifiers, it seems inevitable that the remediation of existing buildings will continue to draw on the expertise of the equivalent new classes of registered building surveyor-unrestricted and registered certifier-fire safety.

 

Appendix one – Response from agencies

Appendix two – About the audit

Appendix three – Performance auditing

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #364 - released 13 April 2022.

Published

Actions for State Finances 2021

State Finances 2021

Whole of Government
Finance
Asset valuation
Compliance
Financial reporting
Internal controls and governance
Management and administration

What the report is about

The results of the consolidated General Government Sector (GGS) and Total State Sector (TSS) financial statements audits for the year ended 30 June 2021.

What we found

The Independent Auditor’s Report on the 2020–21 GGS and TSS financial statements was unqualified but contained an emphasis of matter. The resolution of significant issues delayed signing until 24 December 2021.

The emphasis of matter draws attention to significant uncertainties associated with key assumptions related to the recognition by the GGS of a $2.4 billion investment in the Transport Asset Holding Entity (TAHE).

The Audit Office advised NSW Treasury that it intended to issue a qualified audit opinion, but actions by the NSW Government avoided this outcome. All evidence provided prior to 14 December indicated that the GGS’s return on the $2.4 billion cash contributed to TAHE was insufficient to support accounting for it as an investment. Projected returns were below the long term inflation rate and were insufficient to recover:

  • TAHE's revaluation loss of $20.3 billion in 2020–21
  • an average rate of return of at least 2.5 per cent of equity invested in TAHE.

In these circumstances, the $2.4 billion contributed to TAHE should have been expensed. This could have impacted the GGS’s budget result.

The NSW Government’s actions to avoid a qualified audit opinion included:

  • a government decision made on 14 December approving TAHE’s shareholding ministers communicating that their expectation of a return had increased to 2.5 per cent
  • reflecting the revised shareholding ministers’ expectations in the 2021–22 ‘NSW Half-Yearly Review’ on 16 December. The NSW Government provided an additional $1.1 billion to fund increased access and license fees to TAHE from the public sector operators (Sydney Trains and NSW Trains)
  • signing a Heads of Agreement (HoA) on 18 December between Transport for NSW (TfNSW),TAHE and the public sector operators. The HoA reflected the parties’ intent to renegotiate contracts to increase TAHE’s licence and access fees by $5.2 billion.

The uncertainty raised in our emphasis of matter relates to:

  • TAHE’s future estimated access and licence fees, which remain subject to re-negotiation and must meet or exceed the indicative future access and licence fees set out in the HoA
  • continued funding for TAHE's key customers (Sydney Trains and NSW Trains) to meet the price increases outlined in the HoA
  • the 2021–22 'NSW Budget Half Yearly Review', which provides for $1.1 billion of the additional funding over the forward estimates period to 2024–25. A further $4.1 billion is required over the following six years (2026–31), which are outside the forward estimates period
  • further significant cash flows required to support the funding model are outside the 10-year contract period. That is, beyond 30 June 2031.

There remains a risk that:

  • TAHE will not be able to re-contract with the rail operators for access and licence fees at a level that is consistent with current projections
  • future government's funding to TAHE’s key customers, the rail operators, may not be consistent with the current shareholding ministers’ expectations
  • TAHE will be unable to grow its non-government revenues.

The audit found a risk of undue reliance on consultants, a need to improve quality controls on materials submitted to audit and an extreme risk finding raised with respect to providing key information on a timely basis.

The GGS Budget Result for the 2020–21 financial year was a deficit of $7.1 billion compared to an original forecast budget deficit of $16 billion.

The State did not achieve its fiscal target of maintaining annual expenditure growth below the long-term revenue growth target of 5.6 per cent. In 2020–21, the GGS expenditure grew by 6.9 per cent mainly due to grants and subsidies paid from the COVID-19 stimulus packages received from the Commonwealth.

What we recommended

Significant matters concerning TAHE

We recommend NSW Treasury:

  • implement effective quality review processes over key accounting information
  • establish a policy to determine the minimum expected rate of return on its equity injections into public sector entities
  • report on the performance of investments in TAHE and all other public sector entities
  • ensure the revised commercial agreements between TAHE and NSW rail operators reflect access and licence fees set out in the Heads of Agreement
  • with TAHE, prepare robust projections and business plans to support returns beyond FY2031
  • liaise with the Australian Bureau of Statistics (ABS) and reconfirm the sector classifications of TAHE, NSW Trains and Sydney Trains
  • with TAHE, monitor the risk that control of TAHE assets could change in future reporting periods
  • significantly improve its processes to ensure all key information is identified and shared on a timely basis
  • consider whether there is sufficient competent oversight of its use of consultants and assess the risk of an overdependence on consultants at the cost of internal capability.

A number of other non-TAHE related recommendations have been raised in Section 6 ‘Key Audit Findings’.

Fast facts 

The Total State Sector comprises the General Government Sector, the Public Non-Financial Corporation (PNFC) Sector and the Public Financial Corporation (PFC) Sector.

The 2020–21 consolidated financial statements of the General Government and Total State Sectors provide the financial performance and position of the NSW Government.

  • $391b government property, plant and equipment in the Total State Sector as at 30 June 2021
  • $3.3b government net contributions to other public sectors in 2020–21. $2.4 billion was contributed to TAHE
  • $19.3b net holding losses from the GGS's investment in other public sector entities recognised outside of the 2020–21 budget result
  • $7.1b budget deficit of the General Government Sector in 2021
  • 7 - six high risk and one extreme risk management letter findings related to the General Government Sector's investment into TAHE
  • 24 monetary misstatements exceeding $20 million were identified in agencies financial statements in 2020–21
Image
Margaret Crawford, Auditor-General for New South Wales

Pursuant to the Government Sector Audit Act 1983 I present my report on State Finances 2021. My independent auditor’s opinion on the State’s consolidated financial statements, albeit delayed, is unqualified. My independent auditor’s report however, does include an emphasis of matter drawing attention to significant uncertainties remaining in relation to the State’s equity investment in the Transport Asset Holding Entity (TAHE).

The 2020–21 year was challenging from many perspectives, not least being the continuing impact of and response to the COVID-19 pandemic. Once again, NSW Treasury provided government agencies extensions of time to submit financial statements for audit. Finance staff and management right across government must be congratulated for their responsiveness in meeting their financial reporting obligations in such challenging circumstances.

The General Government’s 2020–21 budget result, reflected within the Total State Sector Accounts, was a deficit of $7.1 billion. This compares with the original budgeted deficit of $16 billion. The factors that contributed to this outcome are presented in this Report to Parliament along with other significant matters related to the audit of the Total State Sector Accounts.

One section of my report is dedicated to issues related to the accounting for TAHE. This year’s audit was significantly delayed by protracted disagreement over the treatment of the government’s cash contribution to TAHE. This matter was further frustrated by the fact that information was withheld and not shared with my Office on a timely basis. This has warranted an extreme risk finding for NSW Treasury to significantly improve governance processes to ensure complete and timely sharing of information. This is key to preserving trust, which is one of the foundations that underpins my Office’s engagement with agencies in the conduct of their audits.

The challenges encountered in completing this year’s audit were extraordinary and tested the constructive partnership between the Audit Office and NSW Treasury. I want to acknowledge the enormous efforts of staff of both agencies to correct material errors and ultimately achieve my unmodified audit opinion. I saw first-hand the professionalism, resilience and dedication of my staff. A commitment to accurate and transparent financial reporting is a key basis upon which confidence in the financial management of New South Wales’ resources can be assured.

Margaret Crawford

Auditor-General for New South Wales

9 February 2022

The Independent Auditor's Report, which includes an emphasis of matter was issued on 24 December 2021

While the audit opinion on the State's 2020–21 financial statements was ultimately unmodified, NSW Treasury delayed signing the NSW Total State Sector Accounts (TSSA) in order to resolve significant accounting issues that were material to the TSSA, in particular the treatment of the General Government Sector's (GGS) investment in the Transport Asset Holding Entity (TAHE) during 2020–21.

The Treasurer and NSW Treasury signed the consolidated financial statements on 24 December 2021, eleven weeks later than the 2018–19 pre-pandemic timetable.

The Audit Office advised NSW Treasury that the 2020–21 TSSA would be qualified with respect to TAHE

Our review of all evidence received prior to 14 December indicated the GGS's expected returns were below the long-term inflation rate and that there was no expectation it should recover a significant asset revaluation loss. The levels of projected returns did not support the accounting treatment of the GGS's cash contribution of $2.4 billion to TAHE as an equity injection.

The TSSA are prepared in accordance with Australian Accounting Standards and particularly AASB 1049 ‘Whole-of-Government and General Government Sector Financial Reporting’. This standard requires contributions from owners to comply with the Australian Bureau of Statistics (ABS) Government Finance Statistics Manual 20151 (GFSM) where it would not conflict with Australian Accounting Standards.

The ABS GFSM states that an equity contribution is recognised unless there is no reasonable expectation that a sufficient rate of return can be generated by that investment, in which case the transfer is expensed. A realistic rate of return is defined in the ABS GFSM as the intention to earn a rate of return that is sufficient to generate dividends (including income tax equivalents) and holding gains or losses at a later date. Holding losses include the final asset revaluation decrement of $20.3 billion, which TAHE incurred on its property plant and equipment assets when it became a for-profit entity and was required to value its assets on the basis of the cash flows they are expected to generate. The lower the commercial returns (cashflows), the greater the potential valuation losses of a for-profit entity's assets. This $20.3 billion valuation loss is disclosed within notes 1 'Significant Accounting policies - TAHE Reform in 2020–21', Note 11 'Equity Investments in Other Public Sector Entities' and Note 14 'Property, Plant & Equipment of the Total State Sector and GGS' financial statements.

Multiple versions of models estimating the GGS's expected rate of return were submitted to the Audit Office by NSW Treasury attempting to demonstrate the commerciality of the GGS's investment in TAHE. Until 14 December 2021, our review of all calculations indicated the existing access and licence fees set up under commercial arrangements effective 1 July 2021 did not support a reasonable expectation that a sufficient rate of return would be earned on the equity injections to TAHE. The existing revenue arrangements reflected a shareholders' expected rate of return of only 1.5 per cent per annum of contributed equity and did not include recovery of the revaluation loss of $20.3 billion incurred in 2020–21.

Having reviewed all evidence provided, the Audit Office communicated to NSW Treasury that unless corrected, the State's accounts would be qualified as the $2.4 billion transfer made by the GGS to TAHE should have been reported as a grant expense instead of an investment. The GGS's estimated rate of return was not sufficient to cover:

  • TAHE's final revaluation loss of $20.3 billion in 2020–21
  • a dollar value equal to, or exceeding a 2.5 per cent rate of return on the equity invested in TAHE (ie: at least equal to the long term inflation rate).

Action was required by the NSW Government to avoid a qualified audit opinion

NSW Government actions avoided a qualified audit opinion related to the GGS’s cash contribution of $2.4 billion to TAHE. To support the TAHE structure as a commercial arrangement earning a sufficient rate of return, the NSW Government agreed to provide additional future funding to TAHE's key government customers (Sydney Trains and NSW Trains) to support increases in access and licence fees to be paid to TAHE.

Shareholding ministers increased their expectations as to TAHE's target average return to the expected long-term inflation rate of 2.5 per cent

On 14 December 2021, a government decision was made resulting in the TAHE shareholding ministers requesting that TAHE re-negotiate the access fees and license fees payable under the Operating Agreements between TAHE and the public operators (Sydney Trains and NSW Trains). The renegotiation was to target an average return to the GGS of 2.5 per cent on the equity contributed. TAHE's existing ten year agreements with the operators provide a mechanism by which the parties meet annually and consult in order to determine the amount of the access fees and licence fees that will be payable in the following financial year.

The revised shareholder expectations for TAHE were published in the 2021–22 'NSW Budget Half Yearly Review' on 16 December 2021. The revised expectations changed the basis of the expected returns on equity from the 10-year Commonwealth bond rate of only 1.5 per cent, to the expected long-term inflation rate of 2.5 per cent. This is consistent with the Reserve Bank's target band and the Commonwealth's Department of Finance's expected return on government investments in other sectors.

The revised shareholder expectations were confirmed in a signed Heads of Agreement

On 18 December 2021, Transport for NSW (TfNSW), TAHE and the operators, Sydney Trains and NSW Trains entered into a Heads of Agreement (HoA). This HoA forms the basis of negotiations to revise the pricing within the existing 10-year contracts and deliver upon the shareholders' expectation of a return of 2.5 per cent per annum of contributed equity. This revised return includes:

  • income earned over the estimated weighted average remaining useful lives of TAHE’s assets
  • recovery of the revaluation losses in 2020–21 on TAHE’s property, plant and equipment assets incurred when TAHE commenced operations as a for-profit entity, albeit the recovery of the revaluation loss is projected to take up to 2052.

The HoA reflects an intention between all parties to revise the contractual agreements to increase future access and license fees by $5.2 billion. This included $1.1 billion for the period FY2023–25, which is reflected in the 2021–22 'NSW Budget Half Yearly Review'. Further detail on the HoA is reported in Section 3 of this report ‘Investment in the Transport Asset Holding Entity’.

NSW Treasury revised its calculations to reflect the increased future returns

Following these changes, NSW Treasury revised its calculations of estimated returns to reflect a cumulative return equivalent to the expected long-term inflation rate, and recovery of the 2021 valuation loss by 2052. The rate of return period is consistent with the weighted average remaining useful life of TAHE's assets. The changes supported the financial reporting treatment of the $2.4 billion transfer from the GGS to TAHE as an investment rather than an expense, even though TAHE is currently heavily reliant on revenues from the public rail operators, Sydney Trains and NSW Trains. If the cash contribution had to be treated as a capital grant expense, it would have reduced the GGS's budget result by $2.4 billion.

The Independent Auditor’s Report includes an emphasis of matter drawing attention to uncertainty relating to the General Government Sector's investment in the Transport Asset Holding Entity (TAHE)

Despite the investment in TAHE being better supported, and the independent auditor's opinion being unqualified, the Independent Auditor’s Report includes an emphasis of matter, which draws attention to the significant uncertainties remaining in relation to the GGS’s equity investment in TAHE. The significant uncertainty is associated with key assumptions that support the recognition by the GGS of its $2.4 billion investment in TAHE during 2020–21.

As at the time of signing the Independent Auditor's Report, there was significant uncertainty with regards to judgements around the commerciality of TAHE's operations because:

  • TAHE’s future estimated access and licence fees, which are critical to its ability to earn a realistic rate of return, remain subject to re-negotiation and re-signing of the current access agreements. The proposed indicative future access and licence fees, which are set out in the HoA are intended to form the basis of the re-negotiation.
  • $1.1 billion in additional funding for TAHE's key customers, Sydney Trains and NSW Trains, was provided in the 2021–22 'NSW Budget Half Yearly Review' consistent with the terms in the HoA. However, this funding only extends to the end of the forward estimates period in 2024–25. There is an additional $4.1 billion required over the following six years, which falls outside of the forward estimates period (up to the end of the 10-year contract period). While this has been communicated to the government's Expenditure Review Committee, it is yet to be provided for in government's budget figures. As TAHE's projections are currently highly dependent on its government customers, it is critical that the government continue to provide sufficient funding to the GGS to support increases in the prices government customers will pay for access to TAHE's assets.
  • A further significant portion of the required returns is earned outside of the 10-year contract period (terminating 30 June 2031). NSW Treasury has estimated $37.9 billion in returns from its investment in TAHE over the period from 1 July 2022 to 30 June 2052, but has not identified the source or means of these returns beyond 2031. Currently, TAHE derives the majority of its revenue from access and licence fee agreements with Sydney Trains and NSW trains, who in turn are both funded by grants to Transport for NSW from the GGS. The projected returns calculated by NSW Treasury beyond 2031 are calculated by assuming a 2.5 per cent growth rate. About 87 per cent of these estimated returns are being earned beyond the ten years, with $32.9 billion estimated over the period 2032–52. There remains risk that:
    • TAHE will not be able to re-contract for access and licence fees at a level that is consistent with current projections
    • future governments' funding to TAHE's key customers will not be sufficient to fund payment of access and licence fees at a level that is consistent with current projections
    • TAHE will be unable to grow its non-government revenues.

Significant accounting issues relating to TAHE are detailed in Section 3 to this report titled ‘Investment in the Transport Asset Holding Entity’. Other significant matters related to the TSSA audit are covered in section 6 to this report titled ‘Key Audit findings’.

Other financial reporting matters

The State extended the date for submission of agency financial statements for audit to provide relief to agencies impacted by the New South Wales' COVID-19 lockdowns

All agencies were given a one-week extension (two weeks in 2019–20) to prepare their financial statements and submit them for audit by 2 August 2021. Further extensions were subsequently approved for the following ten agencies and funds (11 in 2019–20) to submit completed financial statements for audit:

  • Department of Communities and Justice (9 August 2021 for disclosures related to cloud computing costs)
  • Investment NSW (13 August 2021)
  • Jobs for NSW (13 August 2021)
  • TCorp IM Funds (19 August 2021)
  • Lord Howe Island Board (22 October 2021)
  • Department of Customer Service (31 August 2021 for disclosures related to AASB 1059 'Service Concession Arrangements: Grantors')
  • Department of Transport (20 August 2021)
  • Sydney Olympic Park Authority (12 August 2021)
  • Planning Ministerial Corporation (12 August 2021)
  • Transport Asset Holding Entity (16 August 2021).

Additional extensions provided agencies with more time to resolve accounting issues relating to:

  • asset valuations
  • first time implementation of AASB 1059
  • asset transfers and treatment of software as service costs.

The extensions outlined above resulted in a two-week delay submitting the State’s draft consolidated financial statements for audit.

In 2020–21, agency financial statements presented for audit contained 24 errors exceeding $20 million (19 in 2019–20). The total value of these errors was $6.6 billion, a significant increase from the previous year ($1.4 billion in 2019–20)

The graph below shows the number of reported errors exceeding $20 million over the past five years in agencies’ financial statements presented for audit.

The errors resulted from:

  • incorrect application of Australian Accounting Standards and NSW Treasury Policies
  • incorrect judgements and assumptions when valuing non-current physical assets and liabilities
  • human error or lack of oversight.

The completion of the 2020–21 Total State Sector Accounts was significantly delayed as material accounting issues were resolved. These issues related to how the General Government Sector’s (GGS)2 investment in the Transport Asset Holding Entity was accounted for. The key areas of audit concern, which required considerable effort to satisfactorily resolve, included our assessment of:

  • the accounting treatment of funds transferred to TAHE from the GGS, specifically:
    • whether funds transferred to TAHE from the GGS should be considered an equity investment or capital grant expense, with the latter having implication to the presentation of the NSW Government Budget positions. Funds are expensed unless, as an investment, there is a reasonable expectation to generate a sufficient rate of return
    • forming a view as to what a ‘reasonable expectation of a sufficient rate of return on investment3’ should be with respect to the Australian Bureau of Statistics' Government Finance Statistics Manual 2015 (GFSM)
    • the valuation of TAHE’s property, plant and equipment at 30 June 2021
  • whether TAHE was correctly classified as a Public Non-Financial Corporation (PNFC) entity
  • whether, under the agreements in place for the use and price of TAHE's assets, TAHE controlled its property, plant and equipment.

Our assessments were hindered by errors and omissions in information and models provided by NSW Treasury to demonstrate expected returns from TAHE, as well as a lack of timeliness and completeness in their responses to requests for documentation to support NSW Treasury's proposed accounting of government's contributions to TAHE.

Up until 13 December 2021, evidence provided by NSW Treasury to support the treatment of a $2.4 billion equity transfer from the GGS to TAHE did not demonstrate a sufficient rate of return on the State's investment. Instead, the evidence suggested the transfer was of the nature of a capital grant expense, which would impact the GGS budget result. Unless corrected, by either reversing the equity investment to a capital grant expense (impacting the GGS budget result) or providing additional resources to the rail operators to support additional TAHE access and licence fees (adding additional expenses to future GGS budget results), this matter would have caused the State's accounts to have been qualified.

After the Audit Office communicated the likely audit outcome to NSW Treasury, significant changes were made by government from 14 December 2021. Government decisions that avoided qualification of the TSSA included:

  • On 14 December, a government decision approved communicating revised shareholders' expectations of rate of return of 2.5 per cent being the long-term inflation rate, and increased grants to Transport for NSW for the rail operators to pay increased access and licence fees to TAHE to support of the new rate of return (previously 1.5 per cent).
  • On 16 December, the 2021–22 'NSW Budget Half Yearly Review' included an increase in expected returns to be derived through higher access and license fees charged by TAHE. To facilitate these returns, an increased allocation of funds of $1.1 billion was made to Transport for NSW (TfNSW) from 1 July 2022 as part of the forward estimates for the period 2022–25. This was to pay for the proposed increased access and licence fees the operators would be required to pay TAHE.
  • On 18 December, TfNSW, TAHE and the operators Sydney Trains and NSW Trains signed a Heads of Agreement (HoA) forming the basis of negotiations to revise annual operating agreements to facilitate the shareholders’ expected returns of 2.5 per cent of contributed equity. The HoA included indicative access and licence charges to be used as a basis of renegotiation, increasing access fees and licence fees to be paid by Sydney Trains and NSW Trains over the 10-year period from 2022–2031 by a further $5.2 billion. Most of this increase occurs outside the forward estimates. The majority of the additional funding may need to be funded by future governments.

NSW Treasury has projected returns to be earned to 2052 (a period covering the weighted average remaining useful lives of TAHE's assets) as sufficient to recover the revaluation loss of $20.3 billion which arose when TAHE revalued its assets under the income approach. These assets were valued on a discounted cash flow basis as at 30 June 2021.

These key decisions and the circumstances leading up to these changes are detailed later in this section.

Background

On 1 July 2020, the former Rail Corporation of New South Wales (RailCorp), a not-for-profit entity, was renamed the Transport Asset Holding Entity of New South Wales (TAHE) transitioning to a for-profit statutory State-Owned Corporation under the Transport Administration Act 1988. There was no change in the structure of TAHE as a new entity was not created. Ownership remains fully with the government. TAHE, and the former RailCorp, were both classified as Public Non-Financial Corporation (PNFC) entities within the Total State Sector Accounts. TAHE was not a newly created entity, nor was it the result of a change in administrative re-arrangements (such as Machinery of Government change).

Prior to 1 July 2015, the government paid appropriations to TfNSW, a GGS agency, to construct transport assets. When completed, these assets were granted to RailCorp, a not for-profit entity within the PNFC sector. The grants to RailCorp were recorded as an expense in the State’s GGS budget result and in the NSW Total State Sector Accounts (TSSA).

From 1 July 2015, the government announced the creation of TAHE (a dedicated asset manager). Funding for new capital projects was to be provided through equity injections, even though the business model was yet to be determined. NSW Treasury initially set a timetable for finalising the business model, operating model and contracts for the use of TAHE's assets of 1 July 2019.

Contributions paid to TAHE by the GGS were treated as equity investments from July 2015 forward. This treatment continued, despite delays in settling the business model. In 2020, the Audit Office raised a high risk finding due to the significance of the financial reporting impacts and business risks for NSW Treasury and TAHE.

The business model eventually adopted was one whereby:

  • The GGS invests in TAHE with an expectation of a sufficient rate of return.
  • TAHE charges the operators (predominantly Sydney Trains and NSW Trains) to use network and rolling stock to deliver services. The operators remain responsible for both the delivery of the services and the maintenance and safe operation of the assets. The operators are primarily funded by TfNSW through grants.
  • The GGS grants funds to operators, which allows them to pay access fees to TAHE. The amount of these grants impacts the budget result.
  • TAHE pays a return back to GGS by way of dividends and tax equivalents. The return may also include holding gains and losses on the fair value of the net assets of TAHE.

TAHE earns relatively small amounts of income from transactions with the private sector. While the TAHE Board envisages that, over time, they will enhance the commerciality of TAHE’s operations, it is currently highly dependent on revenues from government contracts (over 80 per cent). The circularity in flow of funds between transport agencies in the GGS and PNFC sectors is shown in the diagram below:

The government continues to respond to the impacts of the COVID-19 pandemic on New South Wales through its economic stimulus measures

The COVID-19 pandemic continues to significantly impact the State’s finances, reducing revenue and increasing expenses especially in sectors directly responsible for responding to the COVID-19 pandemic, such as Health. Over 2020–21, the government allocated an additional $5.6 billion to agencies as part of its economic stimulus and pandemic response. Measures included:

  • $1.8 billion in health measures including essential medical equipment purchases, vaccine distribution, quarantine, contract tracing and maintaining clinical health capacity (such as intensive care units)
  • $508 million in additional cleaning services primarily to the Department of Education and Transport for NSW
  • $500 million as part of the ‘Dine & Discovery NSW’ voucher program to the Department of Customer Service
  • $350 million in combined land tax relief and small business recovery grants to Department of Customer Service and NSW Treasury respectively.

Around $4.5 billion of this package was spent in 2020–21, leaving $1.1 billion unspent and carried forward into 2021–22. The graph below shows the total allocation and spend by cluster for 2021 compared to their target spend.

Deficit of $7.1 billion compared with a budgeted deficit of $16 billion

The outcomes of the government’s overall activity and policies are reflected its net operating balance (Budget Result). This is the difference between the cost of general government service delivery and the revenue earned to fund these sectors.

The General Government Sector, which comprises 204 entities, generally provides goods and services funded centrally by the State.

In addition to the 204 entities within the General Government Sector, a further 98 government controlled businesses are included within the consolidated Total State Sector financial statements. These businesses generally provide goods and services, such as water, electricity and financial services for which consumers pay for directly.

The Budget Result for the 2020–21 financial year was a deficit of $7.1 billion compared to an original forecast of a budget deficit of $16 billion.

Revenues increased $5.6 billion to $91.8 billion

In 2020–21, the State’s total revenues increased by $5.6 billion to $91.8 billion, 6.5 per cent higher than previous year. A decrease of 0.3 per cent was recorded in 2019–20. The main contributors to the increase in the State's revenues were an increase in taxation revenue of $4.6 billion and an increase in grants and subsidies of $1.4 billion when compared to the prior financial year.

Taxation revenue increased by 15.3 per cent

Taxation revenue increased by $4.6 billion, mainly due to:

  • $2.9 billion higher stamp duties collected from property sales driven by:
    • $2.7 billion increase in contracts and conveyance duties (transfer duties) from both higher transaction volumes and strong property price growth during 2020–21
    • $200 million increase in motor vehicle registration duty driven by increases in new vehicle sales
  • $520 million higher Gambling and Betting Taxes was earned as 2019–20. The previous year's revenues were impacted by club and hotel closures due to COVID-19. The operation of these venues in 2020–21 returned to normal for most of the year resulting in higher club gaming tax revenue of $216 million and hotel gaming taxes of $265 million
  • $439 million higher collections of payroll taxes. The previous year's revenues were impacted by tax relief measures implemented by the government in response to COVID-19. Lower payroll tax was collected in 2019–20 as employment levels dropped during the State’s first lock down
  • $416 million higher land tax revenues, driven by an average 3.2 per cent increase in valuer general land values, which are the basis for determining land tax values.

Stamp duties of $11.7 billion remains the largest source of taxation revenue, $2.9 billion higher than payroll tax of $8.8 billion, the second-largest source of taxation revenue.

Expenses increased $4.1 billion to $101 billion

The State’s expenses increased 4.3 per cent compared with 2019–20. Most of the increase was due to higher employee expenses, depreciation and amortisation, other operating costs and grants and subsidies expense.

Employee expenses, including superannuation, increased 3.6 per cent to $44.1 billion

Salaries and wages increased to $36.3 billion ($34.8 billion in 2019–20). This was mainly due to increases in staff numbers and an average increase of approximately three per cent in the cost of NSW's employees across the sector. Salaries and wages for the Education and Health sectors increased by $511 million and $619 million respectively.

The Health sector employed an additional 4,893 full time staff in 2020–21 (2,763 in 2019–20) and incurred an extra $28 million in overtime mainly in response to COVID-19. Education increased staff numbers by 2,418 full time equivalents in 2020–21 (4,866 in 2019–20). This year, the health and education sectors received a 0.3 per cent award increase in pay rates.

The Public Service Commission (PSC) noted in the ‘State of the NSW Public Sector Report, 2021’ that the government sector senior executive headcount increased by 347 to 3,680 (3,333 in 2019–20). The Transport cluster represented the majority of the increase in the government sector's senior executive headcount, with an increase of 182. The PSC report noted the increase was due to the growing portfolio of major transport infrastructure projects.

Historically, the government wages policy aims to limit growth in employee remuneration and other employee related costs to no more than 2.5 per cent per annum.

Depreciation and amortisation expense increased 7.6 per cent to $10.3 billion

Depreciation and amortisation increased to $10.3 billion in 2020–21 ($9.6 billion in 2019–20). This increase was mainly driven by the depreciation of completed infrastructure projects including the State’s WestConnex M8 and M5 East Motorways, and other road projects such as Woolgoolga to Ballina project. This year also includes twelve months of depreciation relating to the CBD and South-East Light Rail versus six months in the previous financial year.

Furthermore, the first time adoption of AASB 1059 ‘Service Concession Arrangements’ resulted in the State recognising $45.4 billion of service concession assets in its capacity as grantor under arrangements with operators. More than 87 per cent of this balance was recognised by the Transport cluster. These assets are valued at current replacement cost and are depreciated on an annual basis. A service concession arrangement is an arrangement whereby the government as grantor, contracts with an operator to develop (or upgrade), operate and maintain the grantor's public service assets such as roads, bridges or hospitals. The grantor controls or regulates what services the operator must provide using the assets, to whom, and at what price. The grantor also retains any significant residual interest in the assets at the end of the arrangement. Further details about AASB 1059 are included in the ‘Implementation of new accounting standards’ section of this report.

Grants and subsidies increased $1.5 billion to $15.6 billion

The increase in grants and subsidies is due to payments made by the State in supporting businesses and local communities in response to COVID-19. These mainly included $240 million in Dine & Discover voucher payments, $156 million in land tax relief assistance, $160 million increase in grants to non-government schools (including $31 million to support Covid intensive learning support programs), and $109 million relating to small business grant payments.

The State also transferred $592 million in newly constructed assets to local councils. These mainly related to $378 million in assets transferred following completion of WestConnex stage 2 and $180 million from Northern Roads.

Other operating expenses increased two per cent to $27.5 billion

Operating expenses increased to $27.5 billion in 2020–21 ($26.9 billion in 2019–20) due to higher operating activities as agencies responded to the pandemic.

Supplies and Other Services increased by $1.7 billion. This was mainly due to funding of $533 million in hotel quarantine and associated services, and $495 million in medical equipment for the health sector.

Inventories consumed increased by $266 million. This included $217 million in COVID-19 medical equipment that was written off because it had expired or did not meet the TGA regulatory standards. Contractor expenses increased by $306 million because of increased capital works activity, primarily in the Transport sector.

The increase was offset by $1.6 billion in lower insurance claims expense. In 2019–20 financial year, higher claims were made in respect to natural disaster events, including bush fires.

Health costs remain the State’s highest expense

Total expenses of the State were $101 billion ($96.4 billion in 2019–20). In 2020–21, Health remains the highest contributor of expenses for the State with $25.7 billion ($24.2 billion in 2019–20). Education remains the second highest contributor of expenses reporting $18.4 billion in 2020–21 ($17.5 billion in 2019–20).

The following sectors have the highest expenses as a percentage of total State expenses:

  • Health – 25.6 per cent (25.1 per cent in 2019–20)
  • Education – 18.3 per cent (18.2 per cent in 2019–20)
  • Transport – 14.5 per cent (13.3 per cent in 2019–20).

Assets grew by $12.3 billion to $526 billion

The State’s assets include physical assets such as land, buildings and infrastructure, and financial assets such as cash, and other financial instruments and equity investments. The value of total assets increased by $12.3 billion to $526 billion. This was a 2.4 per cent increase compared with 2019–20, mostly due to changes in asset carrying values.

Valuing the State’s physical assets

State’s physical assets valued at $391 billion

The value of the State’s physical assets increased by $1.7 billion to $391 billion in 2020–21 ($37.9 billion increase in 2019–20). The State’s physical assets include land and buildings ($172 billion), infrastructure systems ($202 billion) and plant and equipment ($16.7 billion).

The movement in physical asset values between years includes additions, disposals, depreciation and valuation adjustments. Other movements include assets reclassified to held for sale and other opening balance adjustments.

Liabilities increased $16.4 billion to $291 billion

The State borrowed additional funds in response to COVID-19

The State’s borrowings rose by $15.8 billion to $134 billion at 30 June 2021. This accounted for most of the increase in the State’s total liabilities.

The value of TCorp bonds on issue increased by $16.8 billion to $114 billion, which largely funded the State's capital expenditure and response to the COVID-19 pandemic.

TCorp bonds are traded in financial markets and are guaranteed by the NSW Government.

Over 2020–21, TCorp continued to take advantage of lower interest rates, buying back short-term bonds and replacing them with longer dated debt. This lengthens the portfolio matching liabilities with the funding requirements for infrastructure assets.

The State’s fiscal objective published in the 2021–22 Budget Papers is to repair the operating position by returning the budget to surplus by 2024–25 and rebuilding balance sheet capacity by bringing net debt down towards seven per cent of Gross State Product (GSP) over the medium-term. The State measures net debt as the sum of deposits held, government securities, loans payable and other borrowings, less the sum of cash and deposits, advances paid and investments, loans receivable and placements.

The chart below shows the actual net debt to GSP for NSW compared to the Commonwealth net debt to Gross Domestic Product (GDP) over the past six years. The trend shows an increase in net debt, particularly in the past two years, which is mainly driven by additional borrowings needed to fund stimulus measures when responding to COVID-19 and natural disaster relief.

GSF Act and GSF Regulation

Financial reporting provisions in the Government Sector Finance Act 2018 (GSF Act) have now commenced

From 1 July 2021, the Public Finance and Audit Act 1983 (PF&A Act) financial reporting provisions were repealed. Agencies prepared their 2020–21 financial statements under Part 7 of the GSF Act. They were audited under the Government Sector Audit Act (GSA Act). The GSF Act requires the timeframe for annual financial statement submission be specified in the Treasurer’s Directions.

Under the GSF Act, all reporting GSF agencies are required to prepare annual financial statements, unless exempt from the definition of a reporting agency under the Government Sector Finance Regulation 2018 (GSF Regulation). Those agencies exempt from preparing financial statements include certain small agencies, Crown Land Managers, special purpose staff agencies and retained State interests. These agencies must meet prescribed requirements or thresholds and self-assess each year to determine whether they remain exempt against the criteria in the GSF Regulation.

Most of the financial reporting provisions of the GSF Act have now commenced except for requirements concerning special deposit accounts (SDA) and special purpose financial reports, which are scheduled to commence on 1 July 2023, subject to approval from the Governor.

The GSF Act now includes most of the provisions applicable to GSF agencies, as requirements for appropriations, expenditure, financial services, and other matters were enacted on 1 December 2018 and 1 July 2019.

Once fully commenced, the GSF Act will consolidate and replace reporting provisions of four Acts:

  • PF&A Act
  • Public Authorities (Financial Arrangements) Act 1987
  • Annual Reports (Departments) Act 1985
  • Annual Reports (Statutory Bodies) Act 1984.

GSA Act and GSA Regulation

The PF&A Act was renamed the GSA Act on 1 July 2021 and now only contains provisions relating to the Auditor-General and the Audit Office, the audit of government sector finances and governance of the Public Accounts Committee.

Of note in the renamed GSA Act is that:

  • a new principal object was added that specifically provides the Auditor-General is an independent and accountable statutory officer
  • the previous financial reporting provisions in the PF&A Act were repealed as the financial reporting provisions are contained in Part 7 of the GSF Act. As a result, there are no longer financial reporting provisions in the GSA Act
  • a new section 34 was added, which contains the requirements for the audit of State sector agencies’ financial statements. These were previously contained in two separate sections.

The GSA Regulation commenced on 1 July 2021, replacing the Public Finance and Audit Regulation 2015 (PF & A Regulation). The GSA Regulation contains the list of entities, funds and accounts prescribed for the purpose of audits under the GSA Act.

Inconsistencies exist in the GSF Act and GSA Act related to key statutory timeframes

There are inconsistencies between key statutory timeframes imposed on the Treasurer and Auditor-General in the GSF Act and GSA Act which has been brought to the attention of NSW Treasury. The inconsistencies identified include:

  • Section 34(3)(a) of the GSA Act defines the audit period for the Statements be as soon as practicable after the Auditor-General is given the Statements. This appears to be inconsistent with section 49(3) of the GSA Act, which requires that the Auditor-General, on or before 22 October transmit the Statements and audit report to the Treasurer. Neither provision is a paramount provision.
  • Section 49(3) of the GSA Act also appears to be inconsistent with section 52(1) of the GSA Act which provides that the Statements are to be given to the Auditor-General in accordance with section 7.17 of the GSF Act. Section 7.17 of the GSF Act requires that the Statements are to be prepared and given to the Auditor-General by an agreed date to enable the audit of the Statements. Part 7 of the GSF Act is a paramount provision under section 1.8 of the GSF Act, which means the requirements in section 7.17 of the GSF Act prevail.

There are also inconsistencies in key statutory reporting timeframes imposed on the Treasurer under the GSF Act.

The audited Statements are a key accountability mechanism that provides information on the State’s financial performance and position. Ambiguity in the statutory reporting timeframes could impact on the future timely provision of this information to Parliament. As noted at the beginning of this report, the delay in issuing the audit report for the 30 June 2021 Statements was due to NSW Treasury’s resolution of accounting issues that were material to the Statements, in particular the treatment of the General Government Sectors investment in TAHE during 2020–21. NSW Treasury's management letter will include a high risk finding with regards to the inconsistencies between the GSF Act and GSA Act.

Recommendation

NSW Treasury should seek legislative amendments in Parliament to resolve the inconsistencies in the GSF Act and GSA Act relating to key statutory reporting time frames.

Appropriations framework

NSW Treasury lacks a framework to monitor and provide assurance to ministers that they are in compliance with their appropriation authority

The GSF Act requires that money not be paid out of the Consolidated Fund except under the authority of an Act, such as the annual Appropriation Act or GSF Act. This means a minister is only authorised to spend out of the Consolidated Fund the amount they have been appropriated by the relevant Act(s).

Generally, money is authorised to be paid out of the Consolidated Fund either through:

  • The Annual Appropriation Act - this is an act to appropriate out of the Consolidated Fund sums for the services of the government for the relevant financial year. These appropriations are made to the responsible ministers of principal departments, Special Offices and certain SDAs.
  • The GSF Act - this act allows the responsible minister of a GSF agency to be given an appropriation out of the Consolidated Fund, at the time the agency receives or recovers any deemed appropriation money. Deemed appropriation money is defined in section 4.7(3) of the GSF Act.

Ministers can delegate and sub-delegate appropriation expenditure functions to accountable authorities and officers of GSF agencies. Any spending by accountable authorities and officers of GSF agencies in excess of the amount appropriated to their relevant minister would be made contrary to section 4.6(1) of the GSF Act.

The Budget Papers are an additional mechanism by which the government controls the level of expenditure by agencies both at the individual and departmental administrative cluster level. The Budget Papers set an administrative limit imposed by the government. Separately, the Treasurer can issue a Budget control authority under section 5.1 of the GSF Act. A Budget control authority can regulate expenditure of money by GSF agencies in a variety of ways, as set out in section 5.1(2) of the GSF Act.

In July 2021, NSW Treasury advised the Audit Office that it had received advice from the Crown Solicitor's Office, in January 2021, that payments between agencies in different administrative clusters would not meet the definition of a 'deemed appropriation' under the GSF Act by the receiving agency. This applies to money paid and received by two agencies across different administrative clusters that continue to hold the money in the Consolidated Fund. These intra-government receipts increase the amount an agency has available to spend, without there being a corresponding increase in the responsible minister’s appropriated expenditure limits, thus increasing the risk an agency’s expenditure could cause a minister to exceed their appropriated expenditure authority.

After being made aware of the issue, the Audit Office worked with NSW Treasury officers to clarify potential implications. The Audit Office also obtained further advice from the Crown Solicitor’s Office to clarify certain aspects of the appropriations framework more broadly. In the advice to the Audit Office, the Crown Solicitor advised that an agency is not subject to its own legally appropriated expenditure limit (assuming it is not subject to any annual spending limit imposed through an instrument of delegation or a budget control authority issued by the Treasurer under section 5.1 of the GSF Act). In effect, because responsible ministers are given appropriations, these legal expenditure limits, rest in aggregate, with the principal department and agencies the minister is responsible for. The advice also confirmed:

  • a deemed appropriation for the services of an agency would ordinarily be available for the services of other agencies, if the officers of the other agencies had a delegation from the minister(s) to expend the deemed appropriation and funds remained available under those deemed appropriations
  • that the ‘exhaustion’ of a minister’s appropriation may be precipitated by one agency’s level of expenditure in the financial year, but the effect is that the relevant appropriation is exhausted for all agencies (and their officers) that may otherwise rely on it
  • whether expenditure by an agency occurred beyond the scope of its authority would require a progressive examination of the total amounts expended from the minister’s appropriation
  • amounts expended from the Consolidated Fund without the authority of an appropriation are spent contrary to section 4.6(1) of the GSF Act
  • a minister is responsible to Parliament for (i) the manner in which appropriations are expended, and (ii) any ‘overspends’ (that is, expenditure without authority) by agencies for which they are responsible.

Determining whether expenditure has occurred without the authority of an appropriation is complex and it is not possible for an individual agency to monitor or determine at what ‘point in time’ expenditure has been incurred in excess of the minister’s appropriation authority. As noted earlier, there are mechanisms in place to manage agencies' administrative expenditure limits set by the Budget Papers, but there is no mechanism in place to ensure expenditure by agencies does not exceed a minister’s appropriation authority received under the annual Appropriations Act and GSF Act.

Recommendation

NSW Treasury should ensure a framework exists to monitor and provide assurance to ministers that expenditure incurred across a financial year by agencies under the relevant minister’s coordination does not exceed the appropriation authority conferred by the annual Appropriation Act and the GSF Act.

In addition, principal departments and agencies that hold money in the Consolidated Fund are required by Australian Accounting Standard AASB 1058 'Income of Not-for-Profit Entities' and NSW Treasury Circular TC20/08 'Mandates of options and major policy decisions under Australian Accounting Standards' to prepare a Summary of Compliance in their financial statements. The Summary of Compliance applies to agencies that obtain part or all of their spending authority from a Parliamentary appropriation. It is intended to provide information on the amounts appropriated or authorised for an agency’s use and whether those expenditures were authorised. There remains uncertainty around how the Crown Solicitor’s Office advice received by the Audit Office impacts these disclosures, as the total spending authority given by Parliamentary appropriations and expenditure against these appropriations cannot generally be attributed to an individual agency. Such a scenario is not contemplated by the relevant Australian Accounting Standard. NSW Treasury's management letter will include high risk findings about improving mechanisms in place to manage agencies administrative expenditure limits, uncertainties related to appropriation spending authority on agencies summary of compliance disclosures.

Recommendation

NSW Treasury should assess how the requirement to prepare a Summary of Compliance under Australian Accounting Standards impacts relevant principal departments and agencies' financial statement disclosures.

Delegations to incur expenditure

Further to last year's reporting, some agencies have again spent monies without an authorised delegation

The delegation to incur expenditure is an important accountability mechanism of responsible government.

Last year’s Report on State Finances reported instances where government agencies did not understand or correctly apply the requirements of the GSF Act for deemed appropriations, resulting in some agencies spending deemed appropriations money without an authorised delegation from the relevant minister(s) as required by sections 4.6(1) and 5.5(3) of the GSF Act.

This year’s financial audits identified that further agencies: TAFE Commission, Multicultural NSW and the Office of the Ageing and Disability Commissioner spent money received from an annual Appropriation and/or deemed appropriation money without an authorised delegation from the relevant minister(s), as required by sections 4.6(1) and 5.5(3) of the GSF Act. NSW Treasury's management letter will include high risk issues about improving mechanisms in place to ensure agencies have appropriate delegations in place to spend Appropriation and/or deemed appropriation money.

In addition, the audit of the Jobs for NSW Fund (the Fund) special purpose statements identified that five payments from the Fund were authorised by an officer without the necessary delegation from the minister as required by section 14 of the Jobs for NSW Act 2015 and sections 5.5(2) and 5.5(3) of the GSF Act.

Recommendation

Given the continued instances of non-compliance, NSW Treasury needs to promptly improve the guidance it provides agencies to ensure that expenditure of public monies is properly supported by authorised delegations.

Implementation of new accounting standards

This year, the State implemented the requirements of AASB 1059

AASB 1059 ‘Service Concession Arrangements: Grantors’

AASB 1059 is an Australian Accounting Standard that requires public sector entities (grantors) that enter service concession arrangements with private sector operators for the delivery of public services recognise service concession assets and liabilities in their financial statements. The standard was effective from 1 July 2020.

AASB 1059 requires a grantor to:

  • recognise an asset provided by the operator as a service concession asset if the grantor controls the asset
  • initially measure the service concession asset at current replacement cost (CRC) in accordance with AASB 13 ‘Fair Value Measurement’
  • recognise a corresponding liability measured initially at the fair value (CRC) of the service concession asset, adjusted for any consideration between the grantor and the operator
  • make sufficient disclosure in the financial statements so that users can understand the nature, amount and timing of assets, liabilities, revenue and cash flows arising from these.

The adoption of AASB 1059 increased the State’s total assets and liabilities by $19.5 billion and $19.6 billion respectively, with net worth reducing by $131 million at 1 July 2019

The State adopted a modified retrospective approach when adopting AASB 1059 and recognised and measured service concession assets and liabilities at the date of initial application of 1 July 2019, with any net adjustments recognised in accumulated funds at that date. This means comparatives were restated to reflect the impact of AASB 1059.

Most of the service concession assets recognised by the State related to Property, Plant & Equipment, in particular infrastructure assets.

Agencies had to devote significant effort to implement AASB 1059 and ensure their 2020–21 financial statements materially complied with the standard's requirements. Last year, the Audit Office highlighted advance preparation was key to ensuring agencies effectively transitioning to this new standard. Despite the new standard being issued well in advance of its commencement date, Sydney Water Corporation, Department of Customer Service, Transport for NSW (TfNSW) and TAHE did not prepare sufficiently for their respective implementations.

Whilst most agencies in 2019–20 had commenced assessing their existing commercial arrangements to determine whether they were within the scope of AASB 1059, calculating and posting the accounting entries to support the implementation of this standard was delayed for TfNSW. TfNSW had not finalised its opening balance adjustments in time for the Audit Office’s early close review. Critical assessments of AASB 1059 to identify the accounting implications for the Transport sector, in particular TfNSW and TAHE were still being considered as late as 30 September 2021.

Restart NSW

Restart NSW was established in 2011 to fund the State’s major infrastructure projects

Restart NSW funds Rebuilding NSW, the government’s 10-year plan to invest $23 billion in new infrastructure. Its infrastructure projects, including Sydney Metro West and Parramatta Light Rail, are primarily funded by proceeds from the government’s asset recycling program. The Restart Fund had a balance of $12.4 billion at 30 June 2021 ($15 billion in 2019–20).

The Fund paid $3.8 billion for infrastructure projects in 2020–21 ($4.3 billion in 2020–21). The largest payments were for transport projects, including Sydney Metro West, Parramatta Light Rail, and contributed $319 million of the $2.4 billion equity contribution to the Transport Asset Holding Entity (TAHE).

The funds are invested in the NSW Infrastructure Future Fund (NIFF), which is allowed under the Restart NSW Fund Act 2011 (Restart Act). The NIFF is an investment vehicle for the fund to help the NSW Government meet its infrastructure objectives and this fund is managed by TCorp. In 2020–21, the fund earned a net return of 7.9 per cent, higher than its annual benchmark return of 4.2 per cent, benefiting from improved returns in financial markets over 2020–21.

The fund directed 30.1 per cent of its payments towards rural and regional infrastructure projects in 2020–21

The Restart Act requires the fund to report on the percentage of payments directed to rural and regional infrastructure projects and whether this represents at least 30 per cent of the total payments from the fund. The Restart NSW Fund Amendment (Rural and Regional Infrastructure Funding) Bill 2020 introduced in Parliament in 2020 would amend the Restart Act by requiring at least 30 per cent of the total payments each financial year and for the life of the Restart NSW Fund be made on infrastructure projects in rural and regional areas.

This year the fund exceeded its target of directing at least 30 per cent of funding towards rural and regional infrastructure projects. However, since the funds’ commencement, only 23 per cent of total payments went towards rural and regional infrastructure projects. Current projections for the life of the fund indicate only 27.5 per cent of funding will be spent on rural and regional projects, which is below the funds target of 30 per cent target for the life of the fund.

Audit Office’s work plan for 2021–22

The Audit Office’s 2021–22 work plan focuses on the State’s response, recovery and impact from the COVID-19 pandemic and natural disaster emergencies

The COVID-19 pandemic continues to have a significant impact on the people and the public sector of New South Wales. Government continues to assist communities in their recovery from the 2019–20 bushfires and subsequent flooding. The scale of government responses to these events has been significant and has required a wide-ranging response involving emergency response coordination, service delivery, governance and policy.

Significant resources have been directed toward these responses, and in assisting rebuilding and economic recovery. Some systems and processes have changed to reflect the need for quick responses to immediate needs. The increasing and changing risk environment presented by these events has meant that we have recalibrated and focused our efforts on providing assurance on how effectively aspects of these emergency responses have been delivered. This includes financial and governance risks arising from the scale and complexity of government responses to these events.

While these emergencies are having a significant impact today, they are also likely to continue to have an impact into the future. We will take a phased approach to ensuring that our work addresses the following elements of the emergencies and government responses:

Appendix one – Prescribed entities

Appendix two – Legal opinions

Appendix three – TSS sectors and entities
 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Customer Service 2021

Customer Service 2021

Finance
Asset valuation
Cyber security
Financial reporting
Information technology
Internal controls and governance
Shared services and collaboration

This report analyses the results of our audits of the Customer Service cluster agencies for the year ended 30 June 2021.

Our preferred approach is to table the ‘Report on State Finances’ in Parliament before any other cluster report. This is because the ‘Report on State Finances’ focuses on the audit results and observations relating to the Total State Sector Accounts, in effect a consolidation of all government agencies. This year the ‘Report on State Finances’ has been delayed due to significant accounting issues being considered in the Total State Sector Accounts and which may impact the Treasury and Transport clusters.

As there are no outstanding matters relating to audits in the Customer Service cluster impacting the Total State Sector Accounts we have decided to break with normal practice and table this cluster report ahead of the ‘Report on State Finances’.

What the report is about

The results of Customer Service cluster agencies' financial statement audits for the year ended 30 June 2021.

What we found

Unmodified audit opinions were issued for all Customer Service cluster agencies.

The number of monetary misstatements decreased from 48 in 2019–20 to 46 in 2020–21.

Seven out of eight agencies did not complete all mandatory early close procedures.

What the key issues were

Upon the implementation of AASB 1059 'Service Concession Arrangements: Grantors', the Department of Customer Service (the department) recognised a service concession asset, the land titling database, totalling $845 million for the first time at 1 July 2019.

The department reported several retrospective corrections of prior period errors.

The 2020–21 audits identified three high-risk and 59 moderate risk issues across the cluster. The high-risk issues were related to:

  • the Department of Customer Service – internal control qualifications and control deviations in GovConnect service providers
  • the Department of Customer Service – significant control deficiencies in information technology change management controls
  • Rental Bond Board – uncertainties in the accounting treatment of rental bonds.

The percentage of repeat issues we report to management and those charged with governance in management letters increased from 29 per cent in prior year to 42 per cent in 2020–21 while the number of items decreased from 94 to 93.

The magnitude and number of internal control exceptions in GovConnect service providers increased resulting in additional audit procedures to address the risks of fraud and errors in the financial statements.

What we recommended

The department should improve the validation process of key valuation assumptions and inputs provided by the private operator NSW Land Registry Services. It should revisit its accounting treatment of new land titling records.

The department should ensure GovConnect service providers prioritise the remediation of control deficiencies in information technology services.

The department should continue to improve controls in cyber security management.

Cyber Security NSW and NSW Government agencies need to prioritise improvements to their cyber security resilience as a matter of urgency.

The New South Wales Government Telecommunications Authority should improve its fixed assets management and financial reporting process to accommodate its growing fixed assets profile.

Fast facts

The Customer Service cluster aims to plan, prioritise, fund and drive digital transformation and customer service across every cluster in the NSW Government.

  • $3.9b total expenditure incurred in 2020–21 
  • $34.1b total administered income managed on behalf of the NSW Government in 2020–21
  • 100% unqualified audit opinions were issued on agencies' 30 June 2021 financial statements 
  • 3 high-risk management letter findings were identified
  • 46 monetary misstatements were reported in 2020–21
  • 42% of reported issues were repeat issues.

This report provides Parliament and other users of the Customer Service cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision-making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Customer Service cluster (the cluster) for 2021.

Section highlights

  • Unqualified audit opinions were issued on the financial statements of cluster agencies.
  • The number of reported misstatements has decreased from 48 in 2019–20 to 46 in 2020–21.
  • Agencies could do more work to improve the quality and timeliness of completing mandatory early close procedures.
  • The Department of Customer Service implemented the new accounting standard AASB 1059 'Service Concession Arrangements: Grantors', which resulted in recognition of a service concession asset of $845 million at 1 July 2019. The valuation of land titling database requires significant judgements and estimations.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision-making.

This chapter outlines our observations and insights from our financial statement audits of agencies in the Customer Service.

Section highlights

  • The 2020–21 audits identified three high-risk and 59 moderate risk issues across the cluster. Twenty-six moderate risk issues were repeat issues. The most common repeat issues related to information technology controls around user access management.
  • The magnitude and number of internal control qualification issues from GovConnect service providers have increased. Ineffective controls at service providers increase the risk of fraud, error and security to data. Urgent attention is required to remediate the internal control exceptions in information and technology services.
  • The NSW Public Sector's cyber security resilience needs urgent attention. Cyber Security NSW and NSW Government agencies need to prioritise improvements to their cyber security resilience as a matter of urgency.

Findings reported to management

Forty-two per cent of findings reported to management were repeat issues

Breakdowns and weaknesses in internal controls increase the risk of fraud and error. Deficiencies in internal controls, matters of governance interest and unresolved issues were reported to management and those charged with governance of agencies. The Audit Office does this through management letters, which include observations, related implications, recommendations and risk ratings.

In 2020–21, there were 93 findings raised across the cluster (94 in 2019–20). Forty-two per cent of all issues were repeat issues (29 per cent in 2019–20).

The most common repeat issues related to weaknesses in controls over information technology user access administration.

A delay in implementing audit recommendations increases the risk of intentional and accidental errors in processing information, producing management reports and generating financial statements. This can impair decision-making, affect service delivery and expose agencies to fraud, financial loss and reputational damage. Poor controls may also mean agency staff are less likely to follow internal policies, inadvertently causing the agency not to comply with legislation, regulation and central agency policies.

The table below describes the common issues identified across the cluster by category and risk rating. 

Risk rating Issue
Information technology
High3
1 new,
1 repeat

The financial audits identified the need for agencies to improve information technology processes and controls that support the integrity of financial data used to prepare agencies' financial statements. Of particular concern are issues associated with:

  • internal control exceptions in information and technology services provided by GovConnect service providers
  • inadequate change management controls
  • poor user access administration and no monitoring of privileged user activities
  • insufficient cybersecurity controls and processes.

High-risk issues are discussed later in the chapter.

Moderate2
5 new,
8 repeat

Low1
7 new,
5 repeat

Internal control deficiencies or improvements

Moderate2
5 new,
3 repeat

The financial audits identified internal control weaknesses across key business processes, including:

  • lack of documentation support for payroll transactions
  • untimely removal of unused transaction negotiation authority facility and old bank signatories
  • inadequate fixed asset management controls including timely capitalisation of project overhead costs.

 Low1
3 new,
2 repeat

Financial reporting

High3
1 new

The financial audits identified opportunities for agencies to strengthen financial reporting, including:

  • uncertainties in legislation to support accounting of rental bonds as funds held in trust
  • improvements required in lease accounting including the review of extension options, assessing indicators of impairment and reviewing the lease reports for completeness and accuracy 
  • the removal of fully depreciated assets in the fixed asset register was not timely
  • the quality and timeliness of completing early close procedures required improvement.

High-risk issues are discussed later in the chapter.

Moderate2
9 new,
8 repeat

Low1
7 new,
3 repeat

Governance and oversight
Moderate2
10 new,
3 repeat

The financial audits identified opportunities for agencies to improve governance and oversight processes, including:

  • renewing or finalising service arrangement agreements between agencies were required 
  • lack of formalised documentation regarding arrangements with external providers for leasing and use of assets.
Low1
3 new
Non-compliance with key legislation and/or central agency policies
Moderate2
4 new,
4 repeat

The financial audits identified the need for agencies to improve its compliance with key legislation and central agency policies, including:

  • non-compliance with contract and procurement management policy, including the use of purchasing cards
  • non-compliance with TC 21-02 'Statutory Act of Grace Payments'
  • annual leave in excess of 30 days where Circular 2020-12 requires agency heads to reduce employee recreation leave balances to 30 days or less.
Low1
1 repeat

4 Extreme risk from the consequence and/or likelihood of an event that has had, or may have a negative impact on the entity.
3 High-risk from the consequence and/or likelihood of an event that has had, or may have a negative impact on the entity.
2 Moderate risk from the consequence and/or likelihood of an event that has had, or may have a negative impact on the entity.
1 Low risk from the consequence and/or likelihood of an event that has had, or may have a negative impact on the entity.
Note: Management letter findings are based on management letters issued to agencies.

2020–21 audits identified three high-risk findings

High-risk findings, including repeat findings, were reported at the following cluster agencies. One of the 2019–20 high-risk findings were not resolved.

Agency Description
2020–21 findings  
Department of Customer Service
Repeat finding:
Qualifications and control deviations in GovConnect NSW controls assurance reports

The GovConnect information technology general controls (ITGC) provided by the department, Infosys and Unisys were qualified in 2020–21. The key controls over user access, system changes and batch process failed in all ITGC reports. Most of these deviations were not mitigated or sufficiently mitigated to address the risk of unauthorised user access.

The control deficiencies in ITGC increase:

  • the risk of unauthorised transactions, system and configuration changes (workflow approvals, three-way match etc.) and modifications to the system reports
  • incomplete, invalid and inappropriate system access, segregation of duties controls and system reports for the customers using the SAPConnect.

The role of the department has changed significantly from a coordinating agency on behalf of GovConnect customers to a GovConnect IT service provider. It is leading a new IT operating model called ‘Service Integration and Application Management’ (SIAM) to strengthen governance and improve performance of GovConnect service providers. The Department is responsible for the remediation of control deficiencies and continuous improvement in the GovConnect environment.

This matter was assessed as high-risk, if not adequately addressed, it had the potential to result in material fraud and error in the department's financial statements and reputation damages.

This issue is further discussed later in this chapter.

2020–21 findings  
Department of Customer Service
New finding:
Change management significant control deficiencies

Revenue NSW, a division of the department has a key role in managing the State’s finances. It administers State taxes, manages fines, recovers State debt and administers grants and subsidies.

The audit team found significant control deficiencies in change management controls:

  •  appropriate system controls were not in place to restrict developers from releasing changes to the live business systems
  • 8 developers had direct access to the business application servers used for calculating and administering State taxes.

We have included this matter as a high-risk management letter finding, as the audit team could not identify mitigating controls. The system activity of these developers was also not being independently logged and monitored. This increases the risk of unauthorised system change. This can significantly affect the integrity of tax calculation, business process approvals, invalid changes to bank accounts, unauthorised refunds and write-offs. The audit team conducted a risk analysis over the relevant business processes affected by this issue and performed additional audit procedures to address the audit risk.

Rental Bond Board
Repeat finding: Accounting treatment of rental bonds held in trust

The Rental Bond Board (the Board) holds rental bonds totalling $1.7 billion at 30 June 2021. The Board treated the rental bonds off-balance sheet and disclosed the rental bonds as ‘trust funds’. This treatment is based on management’s judgement that the Board does not have control of these funds.

Previously the Board obtained advices from the Crown Solicitors who stated that in their view the rental bond funds held in the rental bond account were not moneys held in trust and the Residential Tenancies Act 2010 (the Act) should be reviewed and amended to better support its accounting treatment of rental bonds. The Board has initiated the need to amend the Act, however the implementation of the legislative amendments is still pending.

This matter was assessed as high-risk, if not adequately supported, it had the potential to result in material misstatements in the Board's financial statements.


The number of moderate risk findings increased from prior year

Fifty-nine moderate risk findings were reported in 2020–21, which was a 11.3 per cent increase from 2019–20. Of these, 26 were repeat findings, and 33 were new issues.

Moderate risk findings include:

  • weaknesses in user access management, such as untimely access removal for terminated staff, and a lack of periodic user access review
  • accounting for leases such as the review of extension options, assessing indicators of impairment and reviewing the lease reports for completeness and accuracy
  • formalising arrangements between agencies including corporate service arrangements, funding arrangements, leases, use of SAP system and computer assets
  • use of purchasing cards where our data analytics performed indicated potential gaps and controls and non-compliance with government policies.

The magnitude and number of internal control exceptions in GovConnect service providers have increased

In 2015, the NSW Government selected Unisys Australia Pty Limited’s (Unisys) as an information technology (IT) outsourced service provider and Infosys Limited (Infosys) as a business process outsourced service provider. The outsourced services arrangement was branded GovConnect NSW (GovConnect). The Department of Customer Service (the department) is the contract authority for the NSW Government. In 2019, the NSW Government transitioned a number of Unisys’ IT services progressively to the department and ceased all Unisys's IT services in May 2021. In 2020-21, Infosys, Unisys and the Department were co-providers of business processes and information technology services that constitute the GovConnect environment.

The role of the department has changed significantly from a coordinating agency on behalf of GovConnect customers to a GovConnect IT service provider. The department is responsible for the remediation of control deficiencies and continuous improvement in GovConnect internal control environment.

The department leads the project management of GovConnect services, including the arrangement to provide internal control assurance reports to customers in 2020–21. It engages an independent service auditor (service auditor) from the private sector to perform annual assurance reviews of controls at GovConnect service providers in accordance with Australian Standard on Assurance Engagements 3402 'Assurance Reports on Controls at a Service Organisation' (ASAE 3402). The service auditor reports on the internal controls at a service organisation, which are relevant to a user entity's internal control environment.

The service auditor issued eight ASAE 3402 reports covering business processes controls and information technology general controls (ITGC) provided by the service providers. Four out of eight reports were qualified, a significant increase from previous years.

The table below shows the service auditor's ASAE 3402 opinions issued in various business processes and information technology services provided by service providers for the last five years.

ASAE 3402 controls report# 2015–16^ 2016–17 2017–18 2018–19 2019–20 2020–21
Infosys Accounts receivable Qualified Unqualified Unqualified Unqualified Unqualified Qualified
Infosys Accounts payable Qualified Qualified Unqualified Unqualified Unqualified Unqualified
Infosys Fixed assets Qualified Unqualified Unqualified Unqualified Unqualified Unqualified
Infosys General ledger Qualified Qualified Unqualified Unqualified Unqualified Unqualified
Infosys Payroll Adverse Qualified Unqualified Unqualified Unqualified Unqualified
Infosys ITGC Qualified Qualified Unqualified Unqualified Unqualified Qualified
Unisys ITGC Qualified Unqualified Qualified Qualified Unqualified Qualified
The department ITGC* -- -- -- -- Qualified Qualified
ServiceFirst** Disclaimer -- -- -- -- --

# The ASAE 3402 controls reports were issued by an independent private sector service auditor appointed by the Department of Customer Service.
* Information technology services were transitioned from Unisys to the department in phases from 2019–20 to 2020–21.
** ServiceFirst was the shared service centre and its last reporting period was from 1 July 2015 to 13 December 2015.
^ GovConnect first reporting period from 14 December 2015 to 30 June 2016.

In 2020–21, the information technology services controls reports issued to the department, Infosys and Unisys were qualified. Infosys' accounts receivable business process controls report was also qualified. The audit qualifications were because:

  • the service auditor did not get access to the complete set of records processed during the financial year for several ITGC controls. The system that stored these records was hosted at Unisys. From December 2019 to 28 May 2021, the services at Unisys were progressively migrated to the department's IT environment but this system could not be migrated to the department in the required format, resulting in audit scope limitation for service auditors
  • of the deviations identified during sample testing of ITGC controls
  • the monthly follow up of outstanding receivables was not performed regularly, which was the only key control to address the timely collection of accounts receivable.

Internal control exceptions in GovConnect information and technology services require urgent remediations

The relevant controls over user access, system changes and password controls failed in all three ASAE 3402 GovConnect ITGC reports. These control failures can lead to unauthorised system access, system and configuration changes (workflow approvals, three-way match, etc.) and modifications to key reports. It increases the risk of:

  • fraud and error in the financial statements
  • ineffective segregation of duties controls
  • accuracy and completeness of system generated reports for the agencies using the SAPConnect system.

The table shows the number of ITGC control deviations compared to prior year:

Year ended 30 June 2021 2020
  Total controls tested Total number of control deviations and findings Total controls tested Total number of control deviations and findings
Infosys ITGC 41 16 35 8
Unisys ITGC 25 11 33 4
DCS ITGC 31 9 10 5

Most of these deviations were not mitigated or sufficiently mitigated to address the risk of unauthorised user access.

The service auditor identified significant areas for remediation:

  • governance arrangement of the IT services
  • user access management controls
  • SAP database controls
  • logical access
  • incident management.

In response to the internal control qualifications, the audit teams performed data analytics over payroll and accounts payable. The data analytics identified several terminated employees that were paid long after their termination dates which resulted in salary overpayments during 2020–21. While management had put processes in place to recover these overpayments, the payroll processing controls need to be improved to prevent such overpayments.

The Department of Customer Service advised that it established a ‘Control Reframe Project’ (the project) to address the internal control exceptions at GovConnect service providers. The objective of the project is to ensure the GovConnect assurance model is aligned with clear lines of responsibility and remediation actions are in place to support the delivery of services and achieve an improved outcome for future years.

Recommendation

We recommend the Department of Customer Service:

  • improve governance and internal control environment over the information technology services
  • ensure GovConnect service providers prioritise remediation actions to address internal control exceptions
  • perform a post-implementation review of the transition of the Unisys arrangement to identify lessons learnt and continuous improvement
  • develop data analytics to help analyse and identify high-risk patterns and anomalies in GovConnect key transaction systems, augmenting their existing monitoring and detective controls.

The NSW Public Sector's cyber security resilience needs urgent attention

The 2020 'Central Agencies' Report to Parliament highlighted the need for Cyber Security NSW, a business unit within the Department of Customer Service, and NSW Government agencies to prioritise improvements to their cyber security resilience as a matter of urgency. A status update of the 2020 recommendation is included in Appendix five of this report.

The Audit Office's Annual Work Program identifies cyber security as a focus area for the Audit Office in 2021–24. It outlines a three-pronged approach to auditing cyber security in this period:

  • considering how agencies are responding to the risks associated with cyber security across our financial audits across the NSW public sector
  • examining the effectiveness of cyber security planning and governance arrangements for large NSW state government agencies for our Internal Controls and Governance report
  • conducting deep-dive performance audits of the effectiveness of specific agency activities in preparing for, and responding to cyber security risks.

A performance audit 'Managing cyber risks' was tabled in Parliament in July 2021. The audit made several recommendations to audited agencies to uplift their cyber security management. It also recommended the Department of Customer Service to:

  • clarify the requirement of the NSW Cyber Security Policy (CSP) reporting to all systems
  • require agencies to report the target level of maturity for each mandatory requirement.

A compliance audit 'Compliance with the NSW Cyber Security Policy' was tabled in October 2021. The audit examined whether agencies are complying with the NSW Cyber Security Policy to ensure all NSW Government departments and public service agencies are managing cyber security risks to their information and systems.

The report found that key elements to strengthen cyber security governance, controls and culture are not sufficiently robust and not consistently applied. There has been insufficient progress to improve cyber security safeguards across NSW Government agencies. The poor levels of cyber security maturity are a significant concern. Improvement requires dedicated leadership and resourcing. To comply with some elements of the government’s policy agencies will have to invest in technical uplift and some measures may take time to implement. However, other elements of the policy do not require any investment in technology. They simply require leadership and management commitment to improve cyber literacy and culture. And they require accountability and transparency. Transparent reporting of performance is a key means to improve performance.

The report noted that the CSP was not achieving the objective of improved cyber governance, controls and culture. The compliance audit made several recommendations to Cyber Security NSW and other NSW Government agencies.

The 2021 maturity self-assessment results against the Australian Cyber Security Centre Essential 8 for the 25 largest NSW State Government agencies are reported in the 2021 'Internal Control and Governance' Report to Parliament.

Repeat recommendation

Cyber Security NSW and NSW Government agencies need to prioritise improvements to their cyber security resilience as a matter of urgency.

Management of cyber security risk

Our 2020-21 financial audit assessed whether cyber security risks represent a risk of material misstatement to the department's own financial statements. A request performance audit 'Service NSW's handling of personal information' was tabled on 18 December 2020. The audit followed two cyber security incidents that resulted in data breaches of customer information. As part of our audit procedures, we obtained an understanding of the controls the department has in place to address the risk of cyber security incidents and respond to any incidences which may have occurred during the year, including its impact on the audit.

Our assessment of the department’s own cyber risk management shows that:

  • an approved security incident response plan was not in place during the reporting period. There was a lack of testing over incident detection and monitoring process
  • a formal process over patch management that includes assessment, determining relevance and priority, timely rollout and escalation and reporting of long outstanding patches to senior management is being established.

The department provides information security services including cyber security management to cluster agencies. We found that there were insufficient communications within the Customer Service cluster over the controls and assurance over cyber security risk management. Some cluster agencies had put in place limited controls over cyber security risk management.

Recommendation

We recommend the Department of Customer Service:

  • establish an approved security incident response plan and formal process over patch management
  • improve communications with cluster agencies over the controls and assurance in cyber security management.

Appendix one – Misstatements in financial statements submitted for audit

Appendix two – Early close procedures

Appendix three – Timeliness of financial reporting

Appendix four – Financial data

Appendix five – Status of 2020 recommendations

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Health 2021

Health 2021

Health
Asset valuation
Compliance
Cyber security
Financial reporting
Infrastructure
Internal controls and governance
Procurement

This report analyses the results of our audits of the Health cluster agencies for the year ended 30 June 2021.

Our preferred approach is to table the ‘Report on State Finances’ in Parliament before any other cluster report. This is because the 'Report on State Finances' focuses on the audit results and observations relating to the Total State Sector Accounts, in effect a consolidation of all government agencies. This year the 'Report on State Finances' has been delayed due to significant accounting issues being considered in the Total State Sector Accounts and which may impact the Treasury and Transport clusters.

As there are no outstanding matters relating to audits in the Health cluster impacting the Total State Sector Accounts we have decided to break with normal practice and table this cluster report ahead of the ‘Report on State Finances’.

What the report is about

The results of Health cluster (the cluster) agencies' financial statements audits for the year ended 30 June 2021.

What we found

Unmodified audit opinions were issued for the financial statements of all Health cluster agencies.

The COVID-19 pandemic increased the complexity and number of accounting matters faced by the cluster. The total gross value of corrected misstatements in 2020–21 was $250.2 million, of which $226.0 million were pandemic related.

A qualified audit opinion was issued on the Annual Prudential Compliance Statement. The basis of the qualification related to 19 instances (18 in 2018–19) of non-compliance relating to three of the 20 prudential requirements across five aged care facilities.

What the key issues were

The total number of matters we reported to management across the cluster increased from 112 in 2019–20 to 116 in 2020–21. Of the 116 issues raised in 2020–21, three were high risk (one in 2019–20) and 57 were moderate risk (47 in 2019–20). Nearly one half of the issues were repeat issues.

The three new high-risk issues identified were:

Hotel Quarantine (HQ) fees

The absence of a tailored debt recovery strategy, data integrity issues and uncertainties around future HQ arrangements increased risks around the recoverability of HQ fees from travellers.

COVID-19 inventories

Data errors and anomalies in the impairment model and difficulties forecasting key factors impacting the management of Personal Protective Equipment (PPE) increased uncertainty associated with the valuation and impairment of COVID-19 inventories.

COVID-19 vaccines

The Commonwealth did not provide information about the cost of vaccines provided to NSW free of charge, which required the performance of internal valuations to reflect the consumption of vaccines in the financial statements.

What we recommended

Hotel Quarantine (HQ) fees

Develop a tailored assessment methodology to estimate recoverability of HQ fees and work with Revenue NSW to develop a tailored debt recovery strategy.

COVID-19 inventories

Review the current stocktaking and impairment methodology to incorporate validation of data key to the management of COVID-19 related PPE.

COVID-19 vaccines

Work with the Commonwealth to obtain primary price information on COVID-19 vaccines.

Fast facts

The Health cluster, comprising 15 local health districts, five pillars agencies, two specialty health networks and six shared state-wise services agencies, deliver health services to the people of New South Wales.

  • 100% unqualified audit opinions were issued on agencies' 30 June 2021 financial statements
  • 24 monetary misstatements were reported in 2020–21
  • high risk management letter findings were identified
  • 47.4% of reported issues were repeat issues
  • $23.5b property, plant and equipment as at 30 June 2021
  • $26.8b total expenditure incurred in 2020–21

This report provides Parliament and other users of the Health cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision-making are enhanced when financial reporting is accurate and timely. This chapter outlines our audit observations related to the financial reporting of agencies in the Health cluster (the cluster) for 2021.

Section highlights

  • Unqualified audit opinions were issued for all cluster agencies required to prepare general-purpose financial statements.

  • The total gross value of all corrected monetary misstatements for 2020–21 was $250.2 million, of which $226.0 million were related to complexities arising from the COVID-19 pandemic.

  • A qualified audit opinion was issued on the Ministry's Annual Prudential Compliance Statement.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision-making. This chapter outlines our observations and insights from our financial statement audits of agencies in the Health cluster.

Section highlights

  • The total number of internal control deficiencies has increased from 112 issues in 2019–20 to 116 in 2020–21. Of the 116 issues raised in 2020–21, three were high (one in 2019–20) and 57 were moderate (47 in 2019–20); with nearly one half of all control deficiencies reported in 2020–21 being repeat issues.
  • The complexities arising from accounting for agreements between governments to respond to the COVID-19 pandemic presented three new high risk audit findings with respect to the:
    • expected rate of recoverability of outstanding Hotel Quarantine fees
    • procurement, stocktaking and impairment of COVID-19 inventories
    • valuation and recognition of COVID-19 vaccines received from the Commonwealth Government.
  • Management of excessive leave balances and poor quality or lack of documentation supporting key agreements were amongst the repeat issues observed again in the 2020–21 financial reporting period.

Findings reported to management

The number of findings reported to management has increased, with 47.4 per cent of all issues being repeat issues

Breakdowns and weaknesses in internal controls increase the risk of fraud and error. Deficiencies in internal controls, matters of governance interest and unresolved issues were reported to management and those charged with governance of cluster agencies. The Audit Office does this through our management letters, which include observations, implications, recommendations and risk ratings.

In 2020–21, there were 116 findings raised across the cluster (112 in 2019–20). 47.4 per cent of all issues were repeat issues (38.4 per cent in 2019–20).

A delay in implementing audit recommendations increases the risk of intentional and accidental errors in processing information, producing management reports and generating financial statements. This can impair decision-making, affect service delivery and expose agencies to fraud, financial loss and reputational damage. Poor controls may also mean agency staff are less likely to follow internal policies, inadvertently causing the agency not to comply with legislation, regulation and central agency policies.

The table below describes the common issues identified across the cluster by category and risk rating.

Risk rating Issue
Information technology

Moderate2
7 new,
3 repeat

We identified the need for agencies to improve information technology processes and controls that support the integrity of financial data used to prepare agencies' financial statements. Of particular concern are issues associated with:

  • lack of reviews of user access and privileged user access for
  • HealthRoster
  • Assets and Facilities Management Online
  • vMoney Powerhouse
  • Patient Billing and Revenue Collection system.

Repeat issues included:

  • deficient password controls
  • no independent review for data integrity of any changes made to HealthRoster
  • incomplete reviews of StaffLink User Access.

Low1
4 new,
5 repeat

Internal control deficiencies or improvements

High3

1 new, 

0 repeat

We identified internal control weaknesses across key business processes, including new issues relating to:

  • procurement, stocktaking and impairment of COVID-19 inventories (personal protective equipment)
  • instances where employees' timesheets were approved in advance
  •  monthly reconciliations not reviewed in a timely manner
  • asset revaluation processes at Illawarra Shoalhaven Local Health District.
     

Repeat issues included:

  • forced finalisation of rosters in order to finalise processing of payroll
  • partial repeat issue relating to HealthShare NSW's stocktake process, refer to details in the following section of this report.

Moderate2
6 new,
12 repeat

 Low1
10 new,
4 repeat

Financial reporting

High3

2 new, 
0 repeat

We identified weaknesses with respect to financial reporting in relation to the:

  • expected rate of recoverability of outstanding Hotel Quarantine fees
  • valuation and recognition of COVID-19 vaccines received from the Commonwealth Government
  • application of AASB 16 'Leases'
  • improvement in health agencies' grant register to better support management's accounting treatment under the applicable revenue accounting standards.

Moderate2
6 new,
1 repeat

Low1
8 new,
3 repeat

Governance and oversight
Moderate2
9 new,
5 repeat

We identified opportunities for agencies to improve governance and oversight processes, including:

  • ensure better documentation around governance arrangements for major health capital works delivered by Health Infrastructure
  • absence of documented practices at health agencies level relating to Visiting Medical Officer claims.
     

Repeat issues include:

  • delegations manual for Health Infrastructure remains in draft and has done so since 2017.
Low1
2 new,
2 repeat
Non-compliance with key legislation and/or central agency policies
Moderate2
1 new,
7 repeat

We identified the need for agencies to improve compliance with key legislation and central agency policies, with new findings including:

  • bank signatories list not updated to remove terminated employees
  • subsequent changes made to Junior Medical Officers' approved rosters not approved by an authorised delegate.
     

Repeat issues include:

  • management of excessive annual leave
  • non-compliance with the Government Information (Public Access) Act 2009 (GIPA Act) by Ambulance NSW.
Low1
5 new,
13 repeat

4Extreme risk from the consequence and/or likelihood of an event that has had, or may have a negative impact on the entity.
3 High risk from the consequence and/or likelihood of an event that has had, or may have a negative impact on the entity.
2 Moderate risk from the consequence and/or likelihood of an event that has had, or may have a negative impact on the entity.
1 Low risk from the consequence and/or likelihood of an event that has had, or may have a negative impact on the entity.

Note: Management letter findings are based either on final management letters issued to agencies, or draft letters where findings have been agreed with management.

Complexities arising from the COVID-19 response

The 2020–21 audit identified three new high-risk findings

COVID-19 has presented the cluster with several new accounting challenges. New and evolving matters arose from changes to operating conditions, which characterised the 2020–21 financial reporting period. Issues with a high degree of estimation uncertainty will require ongoing attention as the strategies employed to deal with the COVID-19 pandemic evolve.

Expected rate of recovery of outstanding Hotel Quarantine invoices

The estimation of the amount likely to be recovered is complicated not only by the uncertainties that exist regarding the assumptions those estimations rely upon, but also the debt collection processes and strategies put into place to manage the accumulated debtors' balance. Debt collection is not administered by the cluster, but rather Revenue NSW. We observed an absence of a methodology to assess the likelihood of recovery. Instead, Sydney Local Health District was relying on Revenue NSW to develop and execute on a collection strategy. Sydney Local Health District was using the same approach to hotel quarantine debts as it did to other Health receivables. As the approach to managing international borders evolves over time, so too will the cluster's need to develop robust estimation models to assess the likely collectability of debtors. 

Procurement, management and impairment of COVID-19 inventories

$656.2 million of COVID-19 inventories were procured in 2020–21, with $220.2 million consumed; $558.7 million impaired and a further $217.1 million written off. Estimates of the degree to which inventories are expired, not fit for purpose or are faulty is often based on management judgement at all stages in the procurement cycle.

With respect to the stocktaking methodology applied, the following issues were identified:

  • discrepancies noted in the stock bin listing provided for audit
  • discrepancies in the recount sheet generated
  • inconsistent application of the stocktake methodology
  • inconsistent labelling of quarantined stock
  • a lack of an approach for validating stock expiry dates, which is a key input to the impairment calculations.

Although management had developed processes and a methodology to count as well as to assess the level of inventory that was not fit for purpose, ongoing attention to the operating environment that emerges post pandemic will be important in assessing the degree to which existing COVID-19 inventories can be integrated into a ‘business as usual’ model going forward. Further refinement of the key elements of the stocktaking methodology will also be required to ensure that key inputs upon which management relies to calculate the year-end inventory impairment provision can be appropriately validated.

Valuation and recognition of COVID-19 vaccines received from the Commonwealth Government

The 2020–21 financial reporting period saw the Commonwealth acquire COVID-19 vaccines and provide these to state jurisdictions to dispense to their communities. The vaccines, although provided free of charge require recognition. However, Health entities were not responsible for acquiring the vaccines and data on the vaccines' cost was not shared by the Commonwealth. Management undertook a valuation using publicly available data to estimate the value to attribute to the vaccine inventory; developed new systems and leveraged existing pharmacy systems to track physical quantities received from the Commonwealth and ultimately distributed to NSW citizens. As the response to the pandemic evolves, larger quantities, and new lines of vaccine stock will be dealt with, and policy settings will need to adapt when patterns of distribution of those vaccines (e.g., timing of third booster shots) emerge. The Ministry of Health will need to ensure that the valuations applied to the prices of inventory distributed and held in stock are as accurate as possible. This can be done through further refinement of the existing valuation methodology, obtaining price information from the Commonwealth and engaging specialist pharmaceutical valuers.

Emerging trends

Recognition of provisions without sufficient support

Several NSW Health entities raised accruals and provisions in 2020–21, which did not have an appropriate basis for recognition. Liabilities can only be recognised where there is a present obligation to make a payment arising from a past event. A number of these errors remain uncorrected in the financial statements of those entities as they are not material, individually or in aggregate to the financial statements as a whole. Increased training and guidance are required to ensure that treatment within the cluster is consistent and reflects events that have occurred and give rise to obligations.

Treatment of Commonwealth funding

In the 2020–21 and 2019–20 financial reporting periods, we observed prior period errors arising from the treatment of Commonwealth funding. These errors related to recognising revenue under funding agreements entered into with the Commonwealth in the incorrect period. The conditions of these funding arrangements, the transactional information requiring validation and the circumstances when revenue should be recognised are not always clear and can be complex. Early and continuous engagement with the Commonwealth is required to ensure that revenue recognition principles are consistently applied across the cluster.

Key repeat issues

Management of excessive annual leave

NSW Treasury guidelines stipulate annual leave balances exceeding 30 days are considered excess annual leave balances. Managing excess annual leave balances has been reported as an issue for the cluster for more than five years, with the average percentage of employees with excessive leave balances over the last five years being 36.1 per cent (35.5 per cent over five years covering 2015–16 to 2019–20).

The operational demands required to manage the COVID-19 pandemic have presented new challenges for the cluster in trying to manage its excessive leave balances. 39.2 per cent of employees now have excess leave balances at 30 June 2021 (35.4 per cent at 30 June 2020).

The state's leave policy C2020-12 Managing Accrued Recreation Leave Balances requires agencies to manage excessive leave balances to 30 days or less to maintain their workforces physical and mental health.

Accurate time recording

Forced-finalisation of time records by system administrators within HealthRoster remains an issue and we continue to observe time records forced-finalised by system administrators so pay runs can be finalised on a timely basis. During 2020–21, a total of two million (2.2 million in 2019–20) time records were force approved, which represents 5.7 per cent of total time records (6.9 per cent in 2019–20).

Existence, completeness and accuracy of key agreements

Delivery of major capital projects

Health Infrastructure (a division of the Health Administration Corporation) is responsible for the delivery of major capital projects with a budgeted spend of more than $10.0 million. Health Infrastructure oversee the planning, design, procurement, and construction phases. Capital works in progress are recognised in the financial statements of the health entity that intends to use those assets upon completion. The health entities recognise both the capital work in progress and the revenue associated with the capital funding from the Ministry for the construction of the assets. Capital funding is currently agreed with health entities as part of the annual Service Agreement. The assumption that the health entities control the assets during their construction is consistent with Health Infrastructure's role as an agent for the health entity and the Ministry's policy directive PD2020-033 'Management and control of Health Administration Corporation owned Real Property'.

We continued to observe a lack of clarity regarding agreements between Health Infrastructure, the Ministry and the cluster agency that will eventually receive the completed asset. This can lead to confusion and uncertainty around the rights and obligations of each party to the transaction.

Cross border patient funding arrangements

When patients require medical care in a jurisdiction where they are not generally domiciled, there are arrangements in place to provide funding to support cross border patient treatments. We have previously observed that agreements between NSW and other jurisdictions have not been finalised, and this continues to be the case. In the case of Victoria, no agreement has been finalised for the past seven years.

We continue to note that the cluster has long outstanding receivables and payables with other states. The absence of formal agreements between the states hampers the settlement of the debts relating to the treatment of cross border patients. The following table shows the status of Cross Border Agreements between NSW and other jurisdictions:

States 2014–15 2015–16 2016–17 2017–18 2018–19 2019–20 2020–21
Queensland Signed Signed Signed Signed Signed Not finalised Not finalised
Victoria Not finalised Not finalised Not finalised Not finalised Not finalised Not finalised Not finalised
Australian Capital Territory Signed Signed Signed Signed Signed Signed Not finalised
South Australia Signed Signed Signed Signed Signed Signed Not finalised
Tasmania Signed Signed Signed Signed Signed Signed Not finalised
Northern Territory Signed Signed Signed Signed Signed Signed Not finalised
Western Australia Signed Signed Signed Signed Signed Signed Not finalised

Albury Base Hospital

Albury Base hospital is located on the border of NSW and Victoria and services residents of both states. Documentation supporting the extension of the expired Intergovernmental Agreement 2009–2017 between NSW and Victoria in relation to the integration of health services in Wodonga and Albury could not be located.

Appendix one – Misstatements in financial statements submitted for audit

Appendix two – Early close procedures

Appendix three – Timeliness of financial reporting

Appendix four – Financial data

 

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Rail freight and Greater Sydney

Rail freight and Greater Sydney

Transport
Information technology
Infrastructure
Management and administration
Project management
Service delivery

What the report is about

The movement of freight contributes $66 billion annually to the NSW economy. Two thirds of all freight in NSW moves through Greater Sydney, and the volume of freight moving through Greater Sydney is expected to increase by 48 per cent by 2036.

This audit assessed the effectiveness of transport agencies in improving the use of rail freight capacity in Greater Sydney, and to meet current and future freight demand.

What we found

Transport agencies do not have strategies or targets in place to improve the efficiency or capacity of the metropolitan shared rail network for freight.

The transport agencies acknowledge that they do not have sufficient information to achieve the most efficient freight outcomes and they do not know how to use the shared rail network to maximise freight capacity without compromising passenger rail services.

The Freight and Ports Plan 2018-2023 contains one target for rail freight - to increase the use of rail at Port Botany to 28 per cent by 2021. However, Transport for NSW (TfNSW)'s data indicates this target will not be met.

Sydney Trains records data on train movements and collects some data on delays and incidents. TfNSW collects data for the construction of the Standard Working Timetable and third-party contracts.

However, a lack of clarity around what data is gathered and who has ownership of the data makes data sharing difficult and limits its analysis and reporting.

The Freight and Ports Plan 2018-2023 includes the goal of 'Reducing avoidable rail freight delays', but the transport agencies do not have any definition for an avoidable delay and, as a result, do not measure or report them.

TfNSW and Sydney Trains are appointed to manage and deliver the Transport Asset Holding Entity of New South Wales (TAHE)'s obligations to allow rail freight operators to use the shared rail network. There are no performance measures in rail freight operator contracts or inter-agency agreements. This limits transport agencies' ability to improve performance.

TfNSW’s Freight Branch is working on four freight-specific strategies; a review of the Plan, a freight rail strategy, a port efficiency strategy and a freight data strategy.

TfNSW has not yet determined the timeframes or intended outcomes of these strategies.

What we recommended

Transport agencies should:

  • commit, as part of the review of Future Transport 2056, to delivering the freight-specific strategies currently in development and develop whole-of-cluster accountability for this work including timeframes, specific targets and clear roles and responsibilities 
  • improve the collection and sharing of freight data
  • develop a plan to reduce avoidable freight delays
  • systematically collect data on the management of all delays involving and/or impacting rail-freight
  • develop and implement key performance indicators for the agreements between the transport agencies.

Fast facts    

  • 288 million tonnes of freight volume predicted to pass through Greater Sydney in 2036, up from 194 million in 2016 (an increase of 48%)

  • 54 trucks that can be replaced by one 600 m long port shuttle freight train    

  • 26,671 freight trains that passed through the metropolitan shared rail network between 1 July 2020 and 30 June 2021

The movement of freight contributes $66.0 billion annually to the New South Wales economy — or 13 per cent of the Gross State Product. Two thirds of all freight in New South Wales moves through Greater Sydney, and the volume of freight moving through Greater Sydney is expected to increase by 48 per cent by 2036. This increasing demand is driven by increasing population and economic growth.

The sequence of activities required to move goods from their point of origin to the eventual consumer (the supply chain) is what matters most to shippers and consumers. Road can provide a single-mode door-to-door service, whereas conveying goods by rail typically involves moving freight onto road at some point. In Greater Sydney, 80 per cent of all freight is moved on road. Freight often passes through intermodal terminals (IMTs) as it transitions from one mode of transport to the next.

In 2016, Transport for NSW (TfNSW) released Future Transport 2056 - the NSW Government's 40-year vision for transport in New South Wales, which is intended to guide investment over the longer term. In Future Transport 2056, TfNSW noted that New South Wales will struggle to meet increasing demand for freight movements unless rail plays a larger role in the movement of freight.

Sydney Trains manages the metropolitan shared rail network, which is made up of rail lines that are used by both passenger and freight trains. The Transport Administration Act 1988 requires that, for the purposes of network control and timetabling, NSW Government transport agencies give ‘reasonable priority’ to passenger trains on shared lines. As the Greater Sydney population and rail patronage continue to grow, so too will competition for access to the shared rail network. See Appendix two for details of the area encompassed by Greater Sydney.

Freight operators can also use dedicated rail freight lines operated by the Australian Rail Track Corporation (ARTC - an Australian Government statutory-owned corporation). As the metropolitan shared rail network connects with dedicated freight lines, freight operators often use both to complete a journey.

TfNSW, Sydney Trains and the Transport Asset Holding Entity (TAHE) work in conjunction with other rail infrastructure owners and private sector entities, including port operators, privately operated IMTs and freight-shipping companies. TfNSW and Sydney Trains are responsible for managing the movement of freight across the metropolitan shared rail network. TAHE is the owner of the rail infrastructure that makes up the metropolitan shared rail network. The NSW Government established TAHE, a NSW Government state-owned corporation, on 1 July 2020 to replace the former rail infrastructure owner - RailCorp. The Auditor-General for New South Wales has commenced a performance audit on TAHE which is expected to table in 2022.

On 1 July 2021, TAHE entered into new agreements with TfNSW and Sydney Trains to operate, manage and maintain the metropolitan shared rail network. Until 30 June 2021, and in accordance with TAHE's Implementation Deed, TAHE operated under the terms of RailCorp's existing arrangements and agreements.

This audit assessed the effectiveness of TfNSW, Sydney Trains and TAHE in improving the use of rail freight capacity in Greater Sydney, and to meet current and future freight demand.

The audit focused on:

  • the monitoring of access to shared rail lines
  • the management of avoidable delays of rail freight movements
  • steps to increase the use of rail freight capacity in Greater Sydney.

Conclusion

Transport agencies do not have clear strategies or targets in place to improve the freight efficiency or capacity of the metropolitan shared rail network. They also do not know how to make best use the rail network to achieve the efficient use of its rail freight capacity. These factors expose the risk that rail freight capacity will not meet anticipated increases in freight demand.

Future Transport 2056 notes that opportunities exist to shift more freight onto rail, and that making this change remains an important priority for the NSW Government. However, the transport agencies acknowledge that they do not have sufficient information to achieve the most efficient freight outcomes. In particular, transport agencies do not know how to use the shared rail network in a way that maximises freight capacity without compromising passenger rail services.

Neither Future Transport 2056 nor the Freight and Ports Plan 2018–2023 give any guidance on how transport agencies will improve the efficiency or capacity of the shared rail network. Other than a target for rail freight movements to and from Port Botany, which TfNSW's data indicates will not be met, there are no targets for improving rail freight capacity across the shared network. The lack of specific strategies, objectives and targets reduces accountability and makes it difficult for transport agencies to effectively improve the use of rail freight capacity in line with their commitment to do so.

Sydney Trains and Transport for NSW do not effectively use data to improve rail freight performance and capacity.

To drive performance improvement when planning for the future, transport agencies need good quality data on freight management and movements. Sydney Trains records data on train movements in real-time and collects some data on delays and incidents. TfNSW collects data for the construction of the Standard Working Timetable (SWTT) and third-party contracts. However, the different types of data gathered and the separation between the teams responsible mean that there is a lack of clarity around what data is gathered and who has ownership it. This lack of coordination prevents best use of the data to develop a single picture of how well the network is operating or how performance could be improved.

Sydney Trains' ability to evaluate the effectiveness of its incident and delay mitigation strategies is also limited by a lack of information on its management of rail-freight related delays or incidents. While Sydney Trains collects data on major incidents, it can only use this to conduct event-specific analysis on the causes of an incident, and to review the operational and management response. The use of complete and accurate incident data would assist to define, identify and reduce avoidable delays. Reducing avoidable delays is a goal of the Freight and Ports Plan 2018–2023. More complete data on all incidents would help TfNSW to have more effective performance discussions with rail freight operators to help improve performance.

TfNSW has started developing strategies to identify how it can use rail freight capacity to achieve efficient freight outcomes, but it has not committed to implementation timeframes for this work.

TfNSW’s Freight Branch has started work on four freight-specific strategies to improve freight efficiency: a review of the Plan, a freight rail strategy, a port efficiency strategy and a freight data strategy. However, none of these strategies will be fully developed before the end of 2022. TfNSW has not yet determined the implementation timeframes or intended outcomes of these strategies, although TfNSW reports that it is taking an iterative approach and some recommendations and initiatives will be developed during 2022. 

Appendix one - Response from agencies

Appendix two - The Greater Sydney region

Appendix three - TfNSW strategic projects 

Appendix four - Sydney Trains path priority principles 

Appendix five - Sydney Trains delay management

Appendix six - About the audit 

Appendix seven - Performance auditing
 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #357 - released (19 October 2021).

Published

Actions for Managing cyber risks

Managing cyber risks

Whole of Government
Transport
Cyber security
Information technology
Internal controls and governance
Procurement
Risk

What the report is about

This audit assessed how effectively Transport for NSW (TfNSW) and Sydney Trains identify and manage their cyber security risks.

The NSW Cyber Security Policy (CSP) sets out 25 mandatory requirements for agencies, including implementing the Australian Cyber Security Centre’s Essential 8 strategies to mitigate cyber security incidents, and identifying the agency’s most vital systems, their ‘crown jewels’. 

The audited agencies have requested that we do not disclose detail of the significant vulnerabilities detected during the audit, as these vulnerabilities are not yet remediated. We provided a detailed report to the agencies in December 2020 outlining significant issues identified in the audit. We have conceded to the agencies' request but it is disappointing that transparency to the Parliament and the public on issues that potentially directly affect them needs to be limited in this way.

What we found

TfNSW and Sydney Trains are not effectively managing their cyber security risks.

Both agencies have assessed their cyber security risks as unacceptably high and both agencies had not identified all of the risks we detected during this audit – some of which are significant.

Both agencies have cyber security plans in place that aim to address cyber security risks. TfNSW and Sydney Trains have combined this into the Transport Cyber Defence Rolling Program, part of the Cyber Defence Portfolio (CDP). 

However, neither agency has reached its target ratings for the CSP and the Essential 8 and maturity is low in relation to significant risks and vulnerabilities exposed.

Further, neither agency is fostering a culture where cyber security risk management is an important and valued aspect of decision-making.

TfNSW is not implementing cyber security training effectively across the cluster with only 7.2% of staff having completed basic cyber security training.

What we recommended

TfNSW and Sydney Trains should:

  • develop and implement a plan to uplift the Essential 8 controls to the agency's target state
  • as a matter of priority, address the vulnerabilities identified as part of this audit and previously described in a detailed Audit Office report provided to both agencies
  • ensure cyber security risk reporting to executives and the Audit and Risk Committee
  • collect supporting information for the CSP self assessments 
  • classify all information and systems according to importance and integrate this with the crown jewels identification process
  • require more rigorous analysis to re-prioritise CDP funding 
  • increase uptake of cyber security training.

TfNSW should assess the appropriateness of its target rating for each of the CSP mandatory requirements.

Department of Customer Service should:

  • clarify the requirement for the CSP reporting to apply to all systems
  • require agencies to report the target level of maturity for each mandatory requirement.

Fast facts

  • $42m Total value of the Transport Cyber Defence Rolling Program over three years.
  • 7.2% Percentage of staff across the Transport cluster who had completed introductory cyber security training

Response to requests by audited agencies to remove information from this report

In preparing this audit report, I have considered how best to balance the need to support public accountability and transparency with the need to avoid revealing information that could pose additional risk to agencies’ systems. This has involved an assessment of the appropriate level of detail to include in the report about the cyber security vulnerabilities identified in this audit.

In making this assessment, the audit team consulted with Transport for NSW (TfNSW), Sydney Trains, and Cyber Security NSW to identify content which could potentially pose a threat to the agencies’ cyber security.

In December 2020, my office also provided TfNSW and Sydney Trains with a detailed report of many of the significant vulnerabilities identified in this audit, to enable the agencies to address the cyber security risks identified. The detailed report was produced as a result of a 'red team' exercise, which was conducted with both agencies' knowledge and consent. The scope of this exercise reflected the significant input provided by both agencies. More information on this exercise is at page 12 of this report.

TfNSW and Sydney Trains have advised that in the six months from December 2020 and at the time of tabling this audit report, they have not yet remediated all the vulnerabilities identified. As a result, they, along with Cyber Security NSW, have requested that we not disclose all information contained in this audit report to reduce the likelihood of an attack on their systems and resulting harm to the community. I have conceded to this request because the vulnerabilities identified have not yet been remediated and leave the agencies exposed to significant risk.

It should be stressed that the risks identified in the detailed report exist due to the continued presence of these previously identified vulnerabilities, rather than due to their potential publication. The audited agencies, alone, are accountable for remediating these vulnerabilities and addressing the risks they pose.

It is disappointing that transparency to the Parliament and the public on issues that potentially directly affect them needs to be limited in this way.

That said, the conclusions drawn in this report are significant in terms of risk and remain valid, and the recommendations should be acted upon with urgency.

Cyber security risk is an increasing area of concern for governments in Australia and around the world. In recent years, there have been a number of high-profile cyber security attacks on government entities in Australia, including in New South Wales. Malicious cyber activity in Australia is increasing in frequency, scale, and sophistication. The Audit Office of New South Wales is responding to these risks with a program of audits in this area, which aim to identify the effectiveness of particular agencies in managing cyber risks, as well as their compliance with relevant policy.

Cyber Security NSW, part of the Department of Customer Service (DCS) releases and manages the NSW Cyber Security Policy (CSP). The CSP sets out 25 mandatory requirements for agencies, including making it mandatory for agencies to implement the Australian Cyber Security Centre Essential 8 Strategies to Mitigate Cyber Security Incidents (the Essential 8). The Essential 8 are key controls which serve as a baseline set of protections which agencies can put in place to make it more difficult for adversaries to compromise a system. Agencies are required to self-assess their maturity against the CSP and the Essential 8, and report that assessment to Cyber Security NSW annually.

The CSP makes agencies responsible for identifying and managing their cyber security risks. The CSP sets out responsibilities and governance regarding risk identification, including making agencies responsible for identifying their 'crown jewels', the agency's most valuable and operationally vital systems. Once these risks are identified, agencies are responsible for developing a cyber security plan to mitigate those risks.

This audit focussed on two agencies: Transport for NSW (TfNSW) and Sydney Trains. TfNSW is the lead agency for the Transport cluster and provides a number of IT services to the entire cluster, including Sydney Trains. This audit focussed on the activities of TfNSW's Transport IT function, which is responsible for providing cyber security across the cluster, as well as directly overseeing four of TfNSW's crown jewels. Sydney Trains is one of the agencies in the Transport cluster. While it receives some services from TfNSW, it is also responsible for implementing its own IT controls, as well as controls to protect its Operational Technology (OT) environment. This OT environment includes systems which are necessary for the operation and safety of the train network.

To test the mitigations in place and the effectiveness of controls, this audit involved a 'red team' simulated exercise. A red team involves authorised attackers seeking to achieve certain objectives within the target's environment. The red team simulated a determined external cyber threat actor seeking to gain access to TfNSW's systems. The red team also sought to test the physical security of some Sydney Trains' sites relevant to the agency's cyber security. The red team exercise was conducted with the knowledge of TfNSW and Sydney Trains.

This audit included the Department of Customer Service as an auditee, as they have ownership of the CSP through Cyber Security NSW. This audit did not examine the management of cyber risk in the Department of Customer Service.

This audit assessed how effectively selected agencies identify and manage their cyber security risks. The audit assessed this with the following criteria:

  • Are agencies effectively identifying and planning for their cyber security risks?
  • Are agencies effectively managing their cyber security risks?

Following this in-depth portfolio assessment, the Auditor-General for NSW will also table a report on NSW agencies' compliance with the CSP in the first quarter of 2021–22.

Conclusion

Transport for NSW and Sydney Trains are not effectively managing their cyber security risks. Significant weaknesses exist in their cyber security controls, and both agencies have assessed that their cyber risks are unacceptably high. Neither agency has reached its Essential 8 or Cyber Security Policy target levels. This low Essential 8 maturity exposes both agencies to significant risk. Both agencies are implementing cyber security plans to address identified cyber security risks.
This audit identified other weaknesses, such as low numbers of staff receiving basic cyber security awareness training. Cyber security training is important for building and supporting a cyber security culture. Not all of the weaknesses identified in this audit had previously been identified by the agencies, indicating that their cyber security risk identification is only partially effective.
Agency executives do not receive regular detailed information about cyber risks and how they are being managed, such as information on mitigations in place and the effectiveness of controls for cyber risk. As a result, neither agency is fostering a culture where cyber security risk management is an important and valued aspect of executive decision-making.
TfNSW and Sydney Trains are partially effective at identifying their cyber security risks and both agencies have cyber security plans in place

Both agencies regularly carry out risk assessments and have identified key cyber security risks, including risks that impact on the agencies' crown jewels. These risks have been incorporated into the overall enterprise risk process. However, neither agency regularly reports detailed cyber risk information to agency executives to adequately inform them about cyber risk. The Cyber Security Policy (CSP) requires agencies to foster a culture where cyber security risk management is an important and valued aspect of decision-making. By not informing agency executives in this way, TfNSW and Sydney Trains are not fulfilling this requirement.

Agencies' cyber security risk assessment processes are not sufficiently comprehensive to identify all potential risks. Not all of the weaknesses identified in this audit had previously been identified by the agencies.

To address identified cyber security risks, both agencies have received funding approval to implement cyber security plans. TfNSW first received approval for its cyber security plan in 2017. Sydney Trains received approval for its cyber security plan in February 2020. In 2020–21 TfNSW and Sydney Trains combined their plans into the Transport Cyber Defence Rolling Program business case valued at $42.0 million over three years. This is governed as part of a broader Cyber Defence Portfolio (CDP). The CDP largely takes a risk-based approach to annual funding. The Cyber Defence Portfolio Steering Committee and Board can re-allocate funds from an approved project to a different project. This re-allocation process could be improved by making it more risk-based.

TfNSW and Sydney Trains are not effectively managing their cyber security risks

Neither agency has fully mitigated its cyber security risks. These risks are significant. Neither TfNSW nor Sydney Trains have reduced their cyber risk to levels acceptable to the agencies. Both agencies have set a risk tolerance for cyber security risks, and the identified enterprise-level cyber security risks remain above this rating. Both agencies' self-attested maturity against the Essential 8 remains low in comparison to the agencies' target levels, and in relation to the significant risks and vulnerabilities that are exposed. Little progress was made against the Essential 8 in 2020.

Neither agency has reached its target levels of maturity for the CSP mandatory requirements. Not reaching the target rating of the CSP mandatory requirements risks information and systems being managed inconsistently or not in alignment with good governance principles. The Transport Cyber Defence Rolling Program has a KPI to achieve a target rating of three for all CSP requirements where business appropriate. TfNSW considers this target rating to be its target for all the CSP requirements. However TfNSW has not undertaken analysis to determine whether this target is appropriate to its business.

The CSP makes agencies accountable for the cyber risks of their ICT service providers. While both agencies usually included their cyber security expectations in contracts with third-party suppliers, neither agency was routinely conducting audits to ensure that these expectations were being met.

The CSP requires agencies to make staff aware of cyber security risks and deliver cyber security training. TfNSW is responsible for delivering cyber security training across the Transport cluster, including in Sydney Trains. TfNSW was not effectively delivering cyber security training across the cluster because training was not mandatory for all staff at the time of the audit and completion rates among those staff assigned the training was low. As such, only 7.2 per cent of staff across the Transport cluster had completed introductory cyber security training as at January 2021.

Agencies have assessed their cyber risks as being above acceptable levels

An agency's risk tolerance is the amount of risk which the agency will accept or tolerate without developing further strategies to modify the level of risk. Risks that are within an agency's risk tolerance may not require further mitigation and may be deemed acceptable, while risks which are above the agency's risk tolerance likely require further mitigation before they become acceptable to the agency.

Both agencies have defined their risk tolerance and have identified risks which are above this level, indicating that they are unacceptable to the agency. TfNSW has defined 'very high' risks as generally intolerable and 'high' risks as undesirable. Its risk tolerance is 'medium'. Sydney Trains has four classifications of risk: A, B, C and D. A and B risks are deemed 'unacceptable' and 'undesirable' respectively, while C risks are considered 'tolerable'. This aligns with the TfNSW definition of a medium risk tolerance.

Transport IT reported five enterprise-level cyber security risks through its enterprise risk reporting tool in September 2020, all of which relate to cyber security or have causes relating to cyber security. These risks are in aggregate form, rather than relating to specific vulnerabilities. At the time of the audit, one of these risks was rated as very high and the other four rated as high. At this time, Transport IT had identified a further seven divisional-level risks which were above the agency’s risk tolerance.

Similarly, Sydney Trains has identified one main cyber security risk in its IT enterprise-level risk register and another with a potential cyber cause. Both of these IT risks are deemed to have a residual risk of ‘unacceptable’.

Similarly, two cyber-related OT risks have been determined to be above the agency's risk tolerance. One risk is rated as 'unacceptable'. Another risk, while not entirely cyber rated, is rated 'undesirable' and is deemed to have some causes which may stem from a cyber-attack.

Agencies have assessed their current cyber risk mitigations as requiring improvement

In addition to the risk ratings stated above, at the time of the audit neither agency believed that its controls were operating effectively. Transport IT had rated the control environments for its cyber security enterprise risks as 'requires improvement'. Mitigations were listed in the risk register for these risks but, in some cases, they were unlikely to reduce the risk to the target state or by the target date. For example, one risk had actions listed as 'under review' and no further treatment actions listed, but a due date of July 2021, while another risk was being treated by the CDP with a due date of July 2021. The CDP identified in May 2020 that while the average risk identified as part of that program will be reduced to a medium level by this date, ten high risks will still remain. Given the delays in the program, this number may be higher. As such, it seems unlikely that the enterprise risk will be reduced to below a 'high' level by July 2021.

Sydney Trains’ IT and OT risk registers cross-reference controls and mitigations against the causes and consequences. The IT cyber security risk identified in the register had causes with no mitigations designed for them. Further, some of these causes did not have future mitigations designed for them. This risk also had controls in place which are identified as partially effective. For the unacceptable OT risk noted above, while there was a control designed for each of the potential causes, Sydney Trains had identified all of the controls in place as either partially effective or ineffective. This indicates that Sydney Trains was not effectively mitigating the causes of its cyber risks and, even where it had designed controls or mitigations, these were not always implemented to fully mitigate the cause of the risk.

Additional information on gaps in cyber mitigations which were exposed in the course of this audit has been detailed to both agencies. The Foreword of this report provides information about why this detail is not included here.

Essential 8 maturity is low across TfNSW and Sydney Trains and little progress was made in 2020

CSP mandatory requirement 3.2 states that agencies must implement the ACSC Essential 8. Agencies must also rate themselves against each of the Essential 8 on a maturity scale from zero to three and report this to Cyber Security NSW. A full list of the Essential 8 can be found in Exhibit 1. Both agencies have a low level of maturity against the Essential 8 not just in comparison to the targets they have set, but also in relation to the risks and vulnerabilities exposed. Both agencies have set target maturity ratings for the Essential 8 but none of the Essential 8 ratings across either agency are currently implemented to this level. Having a low level of Essential 8 maturity exposes both agencies to significant risks and vulnerabilities. Little progress was made between the 2019 and 2020 attestation periods.

Transport IT has set a target rating of three across all of the Essential 8. Sydney Trains has set a target rating of three for its IT systems. Sydney Trains had an interim target of two for its OT systems in 2020 and advised that this has since increased to three. It should be noted that not all the Essential 8 are applicable to OT systems.

None of the Essential 8 ratings across either agency are currently implemented to the target levels. Given that the Essential 8 provide the controls which are most commonly able to deter cyber-attacks, having maturity at a low level potentially exposes agencies to a cyber security attack.

Some work is underway across both TfNSW and Sydney Trains to improve the Essential 8 control ratings. The CDP provided some resources to the Essential 8 over 2019–20, with uplift focusing on specific systems. The CDP work in 2019 and 2020 relevant to the Essential 8 largely focussed on determining the current state of the Essential 8 and creating a target state roadmap. As a result, there was little improvement between the 2019 and 2020 attestation periods. The CDP has a workstream for the Essential 8 in its FY 2020–21 funding allocation, however as noted above in Exhibit 6 this was delayed as resources were redeployed to Project La Brea. Regardless, work on some specific aspects of the Essential 8 remain part of the 2020–21 CDP allocation, with workstreams allocated to improving three of the Essential 8. In addition, some work from Project La Brea should lead to an improvement in the Essential 8.

Sydney Trains' Cyber Uplift Program included a workstream which had in scope the uplift in the Essential 8 in IT. There were also other workstreams which aimed to improve some of the Essential 8 for OT systems. Work is also ongoing as part of the CDP to uplift these scores in Sydney Trains.

TfNSW and Sydney Trains have not reached their target maturity across the CSP mandatory requirements and TfNSW has not evaluated its cluster-wide target to ensure it is appropriate

Cyber Security NSW allows each agency to determine its target level of maturity for the first 20 CSP mandatory requirements. Agencies can tailor their target levels to their risk profile. Not reaching the target rating of the CSP mandatory requirements risks information and systems being managed inconsistently or not in alignment with good governance principles.

Sydney Trains has set its target level of maturity for IT and OT. All of Sydney Trains' target maturity levels are at least a three (defined), with a target of four (quantitatively managed) for many of the mandatory requirements. While Cyber Security NSW does not currently mandate a minimum level of maturity, in 2019 there was a requirement for each agency to target a minimum level of three.

Sydney Trains has not met its target ratings across the mandatory requirements.

The Transport Cyber Defence Rolling Program has a program KPI to ensure that the entire cluster reaches a minimum maturity level of three against all the CSP requirements by 2023. TfNSW has not reviewed its CSP mandatory requirement targets to determine if a three is desirable for all requirements or if a higher target level may be more appropriate. It is important for senior management to set cyber security objectives as a demonstration of leadership and a commitment to cyber security.

TfNSW has not met its target ratings across the mandatory requirements for its Group IT ISMS, which was the focus of this audit.

Both agencies claimed progress in their implementation of the mandatory requirements between 2019 and 2020. The audit did not seek to verify the self-assessed results from either agency.

Both agencies operate ISMS in line with the CSP

CSP mandatory requirement 3.1 requires agencies to implement an Information Security Management System (ISMS) or Cyber Security Framework (CSF), with scope at least covering systems identified as the agency's ‘crown jewels’. The ISMS or CSF should be compliant with, or modelled on, one or more recognised IT or OT standard. As noted in the introduction, an ISMS ‘consists of the policies, procedures, guidelines, and associated resources and activities, collectively managed by an organisation, in the pursuit of protecting its information assets.’ Both agencies operate an ISMS compliant with the CSP requirement.

As noted in the introduction, TfNSW operates four ISMS. The Transport IT ISMS is certified against ISO27001, the most common standard for ISMS certification. Three of TfNSW’s six crown jewels are managed within this ISMS. The other ISMS are not certified to relevant standards, though TfNSW claims that they align with relevant controls. This is sufficient for the purposes of the CSP.

Sydney Trains operates two ISMS, one for IT and another for OT. Neither of these are certified to relevant ISMS Standards, however there have been conformance reviews of both IT and OT with relevant standards. These ISMS cover all crown jewels in the agency.

There are currently 11 ISMS in operation across the Transport cluster. TfNSW has proposed moving towards a holistic approach to these ISMS, with the CDP Board responsible for governing the available security controls and directing agency IT and OT teams to implement these.

Agencies are not routinely conducting audits of third-party suppliers to ensure compliance with contractual obligations

CSP mandatory requirement 1.5 makes agencies accountable for the cyber risks of their ICT service providers and ensuring that providers comply with the CSP and any other relevant agency security policies. The ACSC has provided advice on what organisations should do when managing third party suppliers of ICT. The ACSC advises that organisations should use contracts to define cyber security expectations and seek assurance to ensure that these contract expectations are being met. While both agencies usually include specific cyber security expectations in contracts, neither is routinely seeking assurance that these expectations are being met.

The NSW Government has mandated the use of the 'Core& One' contract template for low-value IT procurements and the Procure IT contract template for high-value IT procurements. Both of these contracts contain space for the procuring agency to include cyber security controls for the contractor to implement. The Procure IT contract template also includes a right-to-audit clause which allows agencies to receive assurance around the implementation of these controls. TfNSW and Sydney Trains used the mandated contracts for relevant contracts examined as part of this audit.

TfNSW included security controls in all the contracts examined as part of this audit. Compliance with ISO27001 was the most commonly stated security expectation. Of the contracts examined as part of this audit, only one contract did not have a right-to-audit clause. This contract was signed in October 2016. While these clauses are in place, TfNSW rarely conducted these audits on its third-party providers. Of the eight TfNSW contracts examined in detail, only two of these had been audited to confirm compliance with the stated security controls.

Sydney Trains included security controls in all but one of the contracts examined as part of this audit. Sydney Trains did not require contractors to be compliant with ISO27001, but only required compliance with whole-of-government policies. Sydney Trains does not routinely conduct audits of its third-party suppliers, however it did conduct deep-dive risk analyses of its top ten highest risk IT suppliers. This involved a detailed review of both the suppliers' security posture and also the contract underpinning the relationship with the supplier.

The CDP funding for 2020–21 includes a workstream for strategic third-party contract remediation. This funding is to conduct some foundational work which will allow the CDP to make further improvements in future years. While this funding will not address gaps in contract requirements or management across all contracts, this workstream aims to reduce the risks posed by strategic suppliers covering critical assets. Similarly, work is currently underway as part of the CDP to conduct OT risk assessments for key suppliers to Sydney Trains in a similar way to the work undertaken for IT suppliers.

Sydney Trains has risk assessed its third-party suppliers but TfNSW has not done so

It is important to conduct a risk assessment of suppliers to identify high-risk contractors. This allows agencies to identify those contractors who may require additional controls stated in the contract, those who require additional oversight, and also where auditing resources are best targeted.

Sydney Trains has risk assessed all its IT suppliers and, as noted above, has conducted a deep-dive risk analysis of its top ten highest risk suppliers. TfNSW has not undertaken similar analysis of its key suppliers, however it has identified risks attached to each of its strategic suppliers and has documented these. As a result of not risk assessing its suppliers, TfNSW cannot take a targeted approach to its contract management.

TfNSW demonstrated poor records handling relating to the contracts examined as part of this audit

TfNSW was not able to locate one of the contracts requested as part of the audit's sample. Other documentation, such as contract management plans, could not be located for many of the other contracts requested as part of this audit. These poor document handling practices limits TfNSW's ability to effectively oversee service providers and ensure that they are implementing agreed controls. It also limits public transparency on the effectiveness of these controls.

The Transport cluster is not effectively implementing cyber security awareness training

Agencies are responsible for implementing regular cyber security education for all employees and contractors under mandatory requirement 2.1 in the CSP. TfNSW is responsible for delivering this training to the whole Transport cluster, including Sydney Trains. The Transport cluster has basic cyber awareness training available for all staff. TfNSW also offers additional training provided by Cyber Security NSW targeted at executives and executive assistants. While TfNSW has training available to staff, it is not delivering this effectively. TfNSW does not make training mandatory for most staff nor does it require staff to repeat training regularly. Even among those staff who have been assigned the training, completion rates are low, meaning that delivery is not effectively monitored. Cyber security training is important for building and supporting a cyber security culture.

TfNSW is responsible for creating and rolling out all forms of training to agencies within the Transport cluster. Both TfNSW and Sydney Trains have the same mandatory cyber awareness training that is automatically assigned to new starters. At the time of the audit, this training was not mandatory for ongoing staff. TfNSW does make additional cyber security training available to staff who can choose to undertake the training themselves, or can be assigned the training by their manager. All TfNSW cyber security training is delivered via online modules and it is the responsibility of managers to ensure that it is completed.

Cyber security training completion rates for both TfNSW and Sydney Trains are low. Only 13.5 per cent of staff across the Transport cluster had been assigned the Cyber Safety for New Starters training as of January 2021. Although this course is mandatory for new starters, only 53 per cent of staff assigned the Cyber Safety for New Starters training module had completed the course by January 2021. As a result, only 7.2 per cent of staff across the entire Transport cluster had completed this training at that time. In Sydney Trains, less than one per cent of staff had completed this training as at January 2021 and a further 7.6 per cent of staff have completed the 'Cyber Security: Beyond the Basics' training. These low completion rates indicate that TfNSW is not effectively rolling out cyber security training across the cluster.

In October 2020, the Department of Customer Service released 'DCS-2020-05 Cyber Security NSW Directive - Practice Requirement for NSW Government', which made annual cyber security training mandatory for all staff from 2021. In line with this requirement, TfNSW has advised that it will be gradually implementing mandatory annual training from July 2021 for all staff.

The Transport cluster undertakes activities to build a cyber-aware culture in accordance with the CSP, but awareness remains low

Increasing staff awareness of cyber security risks and maintaining a cyber secure culture are both mandatory requirements of the CSP. While TfNSW does undertake some activities to build a cyber aware culture, awareness of cyber security risks remains low. This can be demonstrated by the low training rates outlined above, and the 'Spot the Scammer' exercise, described in Exhibit 7. TfNSW is responsible for delivering these awareness raising activities across the cluster.

TfNSW frequently communicates with staff across the Transport cluster about various cyber security risks through multiple avenues. Both agencies use the intranet, emails and other awareness raising activities to highlight the importance for staff to be aware of the seriousness of cyber risks. Advice given on the intranet includes tips for spotting scammers on mobile phones, promoting the cluster-wide training courses, as well as various advice that staff could use when dealing with cyber risks in the workplace.

In addition to these awareness raising activities, TfNSW has also undertaken a cluster-wide phishing email exercise called 'Spot the Scammer'. This is outlined in Exhibit 7. This exercise was carried out in 2019 and 2020 and allowed the Transport cluster to measure the degree to which staff were able to identify phishing emails. As can be seen in Exhibit 7, the results of this exercise indicate that staff awareness of phishing emails remains low.

Exhibit 7 - Spot the Scammer exercise
In both 2019 and 2020, TfNSW performed a ‘Spot the Scammer’ exercise in which they sent out over 25,000 emails to staff based on a real phishing attack in order to measure awareness and response. The exercise tested staff 'click through rate', the percentage of staff who clicked on the fake phishing link. In 2019, these results were then compared to industry benchmarks, with over a 20 per cent click through rate being considered 'very high'. Both TfNSW and Sydney Trains were considered to have a ‘very high’ click through rate in comparison to these benchmarks in both 2019 and 2020. This indicates that staff awareness of phishing emails was low. The click through rate for TfNSW was 24 per cent in 2020, an increase from 22 per cent in 2019. For Sydney Trains, the click through rate in 2020 was 32 per cent, which was a decrease from 40 per cent in 2019.
Source: Audit Office analysis of TfNSW documents.

Appendix one – Response from agencies

Appendix two – Cyber Security Policy mandatory requirements

Appendix three – About the audit

Appendix four – Performance auditing

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #353 - released (13 July 2021).

Published

Actions for WestConnex: changes since 2014

WestConnex: changes since 2014

Transport
Compliance
Infrastructure
Internal controls and governance
Management and administration
Project management
Risk

What the report is about

The report examined whether Transport for NSW (TfNSW) and Infrastructure NSW (INSW) effectively assessed and justified major scope changes to the WestConnex project since 2014.

What we found

NSW Government decisions to fund WestConnex-related projects outside WestConnex's $16.812 billion budget have reduced transparency and understate the full cost of WestConnex.

The NSW Government's decision to separate Sydney Gateway from WestConnex has reduced transparency over the cost of the road component of Sydney Gateway. $1.76 billion of the cost to complete Sydney Gateway is funded outside the WestConnex budget.

Network integration costs, currently estimated at $2.3 billion, are also funded outside the WestConnex budget. Many of these costs are directly attributable to WestConnex and ought to be included in the reported budget.

The Parramatta Road Urban Amenity Improvement Program, costing $198 million, should also be included as part of the WestConnex reported budget.

Decisions to exclude or remove these elements from WestConnex without justification have seen $4.26 billion of projects funded outside the $16.8 billion budget.

Positively, robust analysis was used to develop and incorporate design improvements into the 2015 WestConnex Updated Strategic Business Case.

The separate components of WestConnex underwent all required assurance reviews. However, the NSW Government's assurance framework does not require ongoing ‘whole-of-program’ assurance for large and complex projects like WestConnex. The absence of a holistic review of WestConnex allows for some costs and benefits to avoid scrutiny.

What we recommended

TfNSW should:

  • review the impact of scope changes on project objectives, costs and benefits for complex infrastructure projects
  • ensure that estimated costs and benefits of works which are reasonably required to meet consent conditions are included in business cases for complex large infrastructure projects
  • establish centralised and project specific record keeping for major infrastructure projects.

Infrastructure NSW should provide transparent whole of program assurance on total costs and benefits when complex projects are split into sub-projects.

Government should consider enhancing public transparency of existing infrastructure assurance processes by requiring that large complex infrastructure programs undergo periodic review at a whole-of-program level.

Fast facts

  • $16.812b 2015 WestConnex business case budget
  • $2.3b current estimated cost of network integration works to enable WestConnex, funded outside the WestConnex budget
  • $1.76b cost to complete Sydney Gateway to enable WestConnex and also funded outside the WestConnex budget
  • $198m Parramatta Road Urban Amenity Improvement Program, originally part of WestConnex but now funded outside the WestConnex budget

WestConnex

WestConnex is a 33 km motorway network that will link the western and south‑western suburbs with the Sydney CBD and the Airport and Port Botany precinct. It will also connect with proposed future motorway links to the north shore, northern beaches, and southern Sydney. The project is being delivered in three stages, with completion scheduled for 2023.

When first conceived by Infrastructure NSW (INSW) in 2012, WestConnex was described as a single integrated concept. In August 2013, government approved a business case for an integrated concept of WestConnex, with an estimated cost of $14.881 billion (in nominal outturn costs). Transport for NSW (TfNSW) is the government agency (sponsor agency) accountable for the delivery of WestConnex in accordance with the business case. In August 2014, the NSW Government established the Sydney Motorway Corporation to fund, deliver and operate WestConnex.

In November 2015, the NSW Government publicly released an updated WestConnex business case with greater detail and design enhancements, which increased the estimated cost to $16.812 billion.

Subsequent to this update, further changes were made to the design, including realignment of the M4 to M5 Link connection to the Western Harbour Tunnel project, an expanded interchange at Rozelle, the deletion of the Camperdown Intersection, and the addition of the Iron Cove Link. The reported budget for WestConnex was not changed as a result of these design updates.

To fund WestConnex, Sydney Motorway Corporation consolidated a concessional loan of $2 billion from the Australian Government, private sector debt and equity funding from the State. The Australian Government also provided a $1.5 billion contribution to the State to partially fund construction of WestConnex.

In August 2018, the NSW Government sold 51 per cent of its stake in Sydney Motorway Corporation for $9.26 billion. At the time of writing, the NSW Government is in the process of selling its remaining 49 per cent stake of Sydney Motorway Corporation.

About this audit

In the course of delivering a complex major infrastructure project, it is reasonable to expect changes to the original design and scope. Changes may occur as the design moves from a high‑level concept to a detailed design for project delivery, as new risks or issues are identified, as demands change, or as other interdependent projects are approved. Changes can also occur in response to potential cost or delivery overruns which arise as a result of planning deficiencies. Where design and scope changes significantly change the project costs and/or expected benefits, the justification for these changes should be robust and transparent.

Following our 2014 performance audit, 'WestConnex: Assurance to the government', the NSW Government established the Infrastructure Investor Assurance Framework (IIAF) to improve accountability and transparency over major projects that are developed, procured, or delivered by government agencies. Under the framework, TfNSW, as project sponsor, is responsible for ensuring the WestConnex project meets all IIAF requirements. These include ensuring the project remains strategically aligned and viable, and benefits are on track. INSW is responsible for coordinating the assurance review process and reporting directly to NSW Cabinet on project delivery against time, budget and risks to project delivery.

The objective of this performance audit is to assess whether TfNSW and INSW effectively assessed and justified major scope changes to the WestConnex project since 2014.

 

Conclusion

Government decisions to separate WestConnex related projects and deliver them outside WestConnex's 2015 business case budget of $16.812 billion has understated the total cost of WestConnex achieving its objectives. The rationale for separating these elements from the WestConnex project scope has not been transparent. Together, these projects represent costs of $4.26 billion funded outside the $16.812 billion WestConnex budget.

Since 2015, the NSW Government has removed several projects from the scope described in the 2015 WestConnex business case, and funded them separately:
  • In mid‑2017, the Sydney Gateway became a separate project outside WestConnex. This project, estimated in 2015 to cost $800 million, now has an estimated cost of $2.56 billion. The project remains partly funded by an $800 million contribution from the $16.812 billion WestConnex budget, with $1.76 billion funded outside the WestConnex budget.
  • In late 2018, the Parramatta Road Urban Amenity Improvement Program became a separate project outside the 2015 WestConnex budget. This project was part of the 2015 WestConnex Business Case and is intended to create urban renewal opportunities around Paramatta Road. It is estimated to cost $198 million.

Work required to integrate WestConnex with existing roads ('network integration') was funded outside the $16.812 billion budget for the November 2015 WestConnex business case. TfNSW is obliged to deliver network integration works to meet the conditions of planning approval for WestConnex. As such, these costs should be included in the WestConnex budget. The current estimated cost of these network integration works is $2.3 billion.

The rationale to exclude or remove each of these elements from the WestConnex project scope has not been transparent, nor supported by robust analysis and justification. These elements are required for WestConnex to achieve its objectives. The additional project costs will also deliver additional benefits not included in the 2015 WestConnex business case. Removing them understates the total cost of achieving the objectives set out in the 2013 and 2015 WestConnex business cases.

WestConnex's complex financing arrangements further reduce transparency on costs.

Transparency over the total cost of WestConnex – including elements funded from other project budgets – is further limited by the project's complex financing arrangements.

Prior to 2018, the Audit Office provided assurance on costs borne and levied by Sydney Motorway Corporation and its controlled entities. Since the NSW Government sold its majority stake in WestConnex in August 2018, the Auditor‑General no longer has the mandate to provide this assurance. Considering this, and the lack of transparency on the cost of projects removed from the WestConnex project scope, there is no transparent or comprehensive view of the total cost to deliver WestConnex – nor of how these cost would be offset by the sale of the government's remaining stake.

There is no 'whole‑of‑program' assurance over the WestConnex program of works. This limits transparency and confidence that WestConnex will meet intended objectives within its budget.

After INSW conducted a gateway review of a draft of the 2015 WestConnex Business Case under the IIAF, the project was broken up into separate components to support staged delivery. Each of these projects, including the Sydney Gateway, as well as the Network Integration Program, underwent the required assurance reviews under the IIAF. INSW also provided monthly progress updates to government. These individual projects are, in themselves, significant in scale and complexity. Addressing them as discrete components for the purposes of the assurance review process is justified and there is no requirement under the IIAF to holistically review projects which together deliver final benefits of the WestConnex program. However, whole‑of‑program review would improve transparency over total costs and benefits.

In 2016, TfNSW revised the design of the M4‑M5 Link and Rozelle to address traffic and integration issues.

TfNSW identified that the concept designs used for the M4‑M5 Link and Rozelle Interchange in the 2015 WestConnex Business Case would not integrate well with surface roads, including the proposed Bays Precinct, and would result in increased traffic on Victoria Road and the ANZAC Bridge. Following a comprehensive review conducted in mid‑2016, TfNSW refined the design of the M4‑M5 Link and Rozelle Interchange to address these limitations without increasing the cost of delivery. TfNSW documented the rationale for the design changes, including how the changes improved on the original design to increase capacity, improve traffic conditions and create more open space.

1. Key findings

Government decisions to fund WestConnex related projects outside of WestConnex's $16.812 billion reported budget have reduced transparency over costs and understate the full cost of WestConnex

In 2015, the work required to integrate WestConnex with existing roads ('network integration') was funded as a separate project with an estimated cost of $1.534 billion outside the 2015 WestConnex budget of $16.812 billion. TfNSW then created the Network Integration Program to respond to the conditions of planning approval for WestConnex. The current estimated cost to deliver all network integration works is $2.3 billion.

Since the 2015 WestConnex Business Case, the NSW Government has removed several elements from the scope of WestConnex and funded them as separate projects, while keeping the published WestConnex budget at an estimated $16.812 billion. Projects removed include:

  • Sydney Gateway, currently costed at $2.56 billion (with an $800 million contribution from WestConnex)
  • Parramatta Road Urban Amenity Improvement Program, costed at $198 million in late 2018 and funded though new funding to the Greater Sydney Commission.

Together, these projects represent costs of $4.26 billion that are not included in the WestConnex budget, but are required for WestConnex to achieve the objectives of the 2013 and 2015 WestConnex Business Cases. The costs of these elements in supporting the objectives of WestConnex is not tracked centrally, and there is no single point of oversight over them. Exhibit 1 compares total WestConnex forecast costs (including related projects) between November 2015 and April 2021.

 

November 2015
($ million)

April 2021
($ million)
WestConnex
Stage 1
Stage 1A (M4 Widening) 497 517
Stage 1B (M4 East) 3,802 3,782
Total 4,299 4,299
Stage 2
King Georges Road Interchange 131 131
New M5 4,335 4,335
Sydney Gateway Contribution 800 800
Total 5,266 5,266
Stage 3
M4‑M5 Link and Rozelle Interchange 7,049 7,049
Urban renewal (Parramatta Road) 198 ‑‑
Urban renewal (Rozelle) ‑‑ 198
Total 7,247 7,247
Total reportable WestConnex 16,812 16,812

Exhibit 1: WestConnex and related projects forecast costs
  November 2015
($ million)
April 2021
($ million)
Related projects
Network integration 1,534 2,300
Urban renewal (Parramatta Road) ‑‑ 198
Sydney Gateway Road Component ‑‑ 1,760
Total 1,534 4,258

Source: AO research.

Many network integration costs are directly attributable to WestConnex and ought to be included in the reported budget for WestConnex

Prior to 2015, the scope of WestConnex included enabling works needed before or during construction, as well as funding for future works to address any adverse traffic outcomes created by WestConnex which become apparent after its opening. These works are also known as network integration works.

When government approved the 2015 WestConnex Business Case, it noted that the project would require $1.534 billion for network integration works to address the impacts of WestConnex on the road network. However, the WestConnex project budget of $16.812 billion did not include funding for network integration works. Instead, Roads and Maritime Services (RMS, now TfNSW) was to fund network integration through its normal budget allocation.

It is important to recognise these costs as part of the total WestConnex project cost because:

  • TfNSW created the Network Integration Program to respond to network traffic and transport elements of the planning conditions of approval for WestConnex granted by the then NSW Department of Planning and Environment under the Environment, Planning and Assessment Act 1979.
  • NSW Treasury guidelines for business cases note that accurate cost estimates include assessment of the financial impact of meeting the conditions of planning approval.
  • Travel time and vehicle operating cost benefits attributed to the WestConnex project in the 2015 WestConnex Business Case assume that some network integration works, then costed at $373 million, were in place.

Refer to Appendix two for more detail on network integration works.

Some of the projects in the WestConnex Network Integration Program provide community and place benefits, such as parklands and cycleways. These benefits have not been attributed to WestConnex. Additionally, some network integration works are likely to deliver additional traffic related benefits to WestConnex. As the Network Integration Program’s primary purpose is to meet the conditions of planning approval for WestConnex, TfNSW should attribute all the costs and benefits of the program to WestConnex.

To September 2021, the total funded cost of the Network Integration Program is approximately $2.077 billion. TfNSW estimates that it will need a further $222 million to complete all expected network integration works.

The NSW Government's decision to separate Sydney Gateway from WestConnex has reduced transparency and accountability for TfNSW's underestimation of the cost of the road component of Sydney Gateway

Sydney Gateway is a high‑capacity connection between the new St Peters Interchange and the Sydney Airport and Port Botany precinct. It includes a road and rail components. The road component was included in the scope of WestConnex in the 2015 WestConnex Business Case. The November 2015 design, which TfNSW costed at $800 million, involved separate roadways from the St Peters Interchange to the International terminal, and to the domestic terminals and Mascot airport precinct.

By October 2016, TfNSW was aware that the $800 million budget for Sydney Gateway was insufficient and revised the forecast cost for the road component to $1.8 billion. The original cost estimate did not sufficiently consider the cost of:

  • constructing a complex design adjacent to the airport precinct
  • obtaining access to land required for the project
  • managing environmental contamination.

On 9 August 2017, the then Minister for WestConnex announced that the Sydney Gateway project was not part of WestConnex.

The 2015 WestConnex Business Case notes that material changes to the WestConnex budget, funding, scope, or timeframe are subject to Cabinet approval processes. It states that, when seeking approval for material changes, the portfolio Minister will make a submission to the relevant Cabinet Committee. Changes in project scope required the approval of the then Cabinet Committee on Infrastructure and should have been endorsed by the WestConnex Interdepartmental Steering Committee.

TfNSW and the NSW Department of Premier and Cabinet (DPC) assert that there is no documentation to support the government’s decision to separate Sydney Gateway from the WestConnex Program, or the WestConnex Interdepartmental Steering Committee's endorsement of a submission to Cabinet seeking approval for the separation.

The established governance processes for major scope changes were not followed in this instance. The lack of transparency regarding government's decision to separate Sydney Gateway from WestConnex also reduces visibility of TfNSW's underestimation of the cost of delivering the road component of Sydney Gateway.

The November 2018 Final Business Case for Sydney Gateway, which was approved by the government, included an estimate of $2.45 billion (nominal outturn cost) for the road component. This estimate included an $800 million contribution from WestConnex. A more recent estimate (late 2020) for this project is $2.56 billion (nominal outturn cost).

The Parramatta Road Urban Amenity Improvement Program should be included as part of the WestConnex budget

A specific objective of the 2015 WestConnex Business Case was the creation of opportunities for urban renewal along and around Parramatta Road. The business case included an allocation of $198 million in the $16.812 billion WestConnex budget for the Parramatta Road Urban Amenity Improvement program, designed to implement aspects of the objective. In November 2018, the NSW Government removed the Parramatta Road Urban Amenity Improvement Program from the WestConnex program of works and reallocated the $198 million (inside the $16.812 billion WestConnex budget) for urban renewal works around the Rozelle Interchange. As part of this decision, government approved new funding of $198 million to the Greater Sydney Commission for the urban amenity program, outside the $16.812 billion WestConnex budget. This understates the cost of WestConnex meeting its objectives by $198 million.

There is no requirement for ongoing ‘whole‑of‑program’ assurance of the WestConnex program of works, including related projects

In August 2015, INSW conducted its first Gateway Review of WestConnex as a program consisting of composite projects. Following that review, TfNSW registered each of the components of WestConnex with INSW as individual projects, rather than keeping WestConnex registered as a program or mega‑project. This is not inconsistent with the IIAF and all WestConnex related projects, including Sydney Gateway and the Network Integration Program, have undergone independent assurance reviews as individual projects under the IIAF.

Once a program like WestConnex is broken down into its composite parts, there is no requirement for the sponsor agency (TfNSW) or INSW to provide independent assurance on the program as a whole until it is completed. This is then done as part of the Gateway review for benefits realisation, which examines whether project benefits are being measured and meet expectations. These individual projects are, in themselves, significant in scale and complexity. While addressing them as discrete components for the purposes of the assurance review process can be justified, the absence of strategic, holistic reviews of WestConnex allows for total costs and benefits to become opaque and avoid scrutiny. Programs of this scale require greater ongoing transparency on total costs and benefits in order to ensure confidence they will meet intended objectives within budget.

There is a lack of public transparency on the total costs and benefits of the WestConnex project

Prior to 2018, the Audit Office provided assurance on costs borne and levied by Sydney Motorway Corporation and its controlled entities. Since the NSW Government sold 51 per cent of its stake in WestConnex in August 2018, the Auditor‑General no longer has the mandate to provide this assurance. The Audit Office is also unable to provide any assurance regarding the performance of tolling concessions.

This means that the total costs of WestConnex, including those levied on road users through tolling, are not reported alongside the full cost of delivering the project. This information, and independent assurance over that information, would provide transparency and context to the outcome of government's sale of its interest in WestConnex.

To enhance the transparency of existing infrastructure assurance processes, government could consider requiring large and complex infrastructure programs to undergo periodic review at a whole‑of‑program level. This could take the form of annual reports to Parliament on the total costs and benefits of selected large and complex projects by the responsible agency. The reports could include an assessment of the cost to government and cost to the community of funding and financing. Independent assurance of the agency report would provide Parliament with greater confidence that infrastructure is delivered economically and providing value for money for the people of NSW.

The Australian National Audit Office provides similar assurance on selected Department of Defence acquisition projects as part of its annual Major Projects Report.

Design enhancements included in the 2015 WestConnex Updated Strategic Business Case were supported by robust analysis

The 2015 WestConnex Business Case contained more detail than the 2013 WestConnex business case. Design enhancements were made as a result of modelling analysis conducted over the two years since the 2013 business case. Enhancements included a full underground link between Kingsgrove and St Peters as part of the New M5 and re‑alignment of the M4‑M5 link tunnel (Stage 3) to include the Rozelle Interchange. The Rozelle Interchange will provide a direct connection to the Anzac Bridge and Victoria Road, and will enable a connection to the proposed Western Harbour Tunnel and Beaches Link. A map and description of these elements can be found at Exhibits 2 and 3 of this report.

In 2016, TfNSW revised the design of the M4‑M5 Link and Rozelle to address traffic and integration issues

As part of preparing the 2015 WestConnex Business Case, TfNSW prepared a Project Definition and Delivery Report (PDDR) for the M4‑M5 Link. This report describes the scope of the project, including a high‑level concept design. TfNSW identified limitations with the proposed design of the M4‑M5 in the PDDR, which it would need to address as the project moved to a detailed design stage. In particular, these limitations included:

  • poor integration with the Bays Precinct masterplan
  • traffic capacity constraints on Victoria Road and Anzac Bridge
  • construction complexity.

Following a comprehensive review in mid‑2016, TfNSW changed the design of the M4‑M5 Link and Rozelle Interchange to address these limitations. These changes included:

  • deletion of the Camperdown intersection to improve traffic conditions on Parramatta Road
  • a fully underground and larger Rozelle Interchange with 10‑hectare dedicated parklands
  • a toll‑free tunnel link from Iron Cove Bridge to Anzac Bridge
  • increasing the lanes in the dual tunnels from three to four each way.

TfNSW documented, but did not publish, the rationale for the design changes, including how the changes addressed the limitations of the previous design while providing increased community benefit through the creation of open space. TfNSW undertook cost comparison studies which estimated that these changes would have a neutral impact on the estimated project cost while achieving the same or improved benefits.

TfNSW's record‑keeping systems for large infrastructure investments negatively impact accountability and transparency

In response to our formal requests for relevant information, made during the conduct of this audit, TfNSW advised that complete and valid records of key decision‑making processes, analysis and advice were unavailable. Additionally, TfNSW often provided information that was incomplete or unverifiable (for instance, unsigned briefing notes). This is not consistent with accepted governance practices and does not comply with the requirements of the State Records Act 1998.

We also requested that TfNSW provide a list of relevant documents held by the Sydney Motorway Corporation (SMC). While TfNSW acknowledged that SMC may hold material relevant to the audit, TfNSW did not have a list or description of these documents. As SMC is now a majority privately held entity, both the Audit Office and TfNSW have limited power to require SMC to provide documentation.

The delivery timeframe for large and complex infrastructure projects such as WestConnex frequently exceeds five years, and some projects can take over a decade to deliver. These projects represent a significant investment of public resources and government agencies should expect independent review and assurance activities such as performance audits. The establishment of dedicated record keeping facilities for major infrastructure projects, such as data rooms, would improve transparency and accountability. This would ensure that the use of public resources is fully auditable in line with public expectations and the requirements of the Government Sector Finance Act 2018, the State Records Act 1998 and the Public Finance and Audit Act 1983.

2. Recommendations

By December 2021, TfNSW should:

1. review the impact of scope changes on project objectives, costs and benefits for complex infrastructure projects

2. when preparing business cases for complex large infrastructure projects, ensure that the estimated costs and benefits of works which are reasonably expected to meet consent conditions are included in the overall project cost and its benefits (as per Treasury guidelines)

3. establish and maintain centralised and project‑specific record keeping, including through dedicated project data rooms, to ensure major infrastructure projects can readily be subject to external oversight and assurance.

By June 2022, INSW should:

4. provide transparent whole‑of‑program assurance on total costs and benefits throughout the project life‑cycle when complex projects are split into sub‑projects.

By June 2022, NSW Government should:

5. consider enhancing the public transparency of existing infrastructure assurance processes by requiring that large complex infrastructure programs undergo periodic review at a whole‑of‑program level. This could take the form of reports to Parliament on the total costs and benefits on selected large and complex projects by the responsible agency, including cost to government and cost to community of funding and financing, as well as an accompanying independent assessment of the agency report.

Following our 2014 performance audit report 'WestConnex: Assurance to the government', the NSW Government established the Infrastructure Investor Assurance Framework (IIAF). INSW is responsible for the development, implementation and administration of the IIAF. The assurance framework involves gateway reviews, health checks, deep dive reviews, and project monitoring and reporting at various stages in the lifecycle of a project. The main aims of the IIAF are to help ensure major infrastructure projects are delivered on time and on budget, and to ensure that reports are regularly monitored by the Cabinet of the NSW Government. The IIAF gateway review process is compulsory for all significant investments and expenditure under the NSW Treasury Gateway Policy.

In accordance with the IIAF, INSW is responsible for the following:

  • providing a dedicated Assurance Team including Gateway Review Managers to coordinate Reviews
  • determining appropriate expert reviewers, and manages scheduling, commissioning and administration of Assurance Review reports. Infrastructure NSW is independent of the Expert Review Team
  • monitoring Tier 1 – High Profile/High Risk projects, Tier 2 and Tier 3 (if required) project performance through independent Assurance Reviews
  • providing independent analysis and advice on key risks and any corrective actions recommended for Tier 1 – High Profile/High Risk, Tier 2 and Tier 3 projects
  • escalating projects to Infrastructure Investor Assurance Committee (IIAC) and Cabinet where projects present ‘red flag issues’ and where corrective action is needed
  • working with delivery agencies to register all capital projects with an estimated cost greater than $10.0 million and ensures they are risk profiled and assigned a risk‑based project tier with an endorsed IIAF Project Registration report
  • preparing forward looking annual Cluster Assurance Plans
  • maintaining and continuously improves the IIAF process
  • reporting to the IIAC, Cabinet and Infrastructure NSW Board
  • regularly report to NSW Treasury on the performance of the IIAF.

In relation to WestConnex, TfNSW is the sponsor agency responsible for meeting relevant IIAF requirements, including:

  • registering and risk profiling projects
  • IIAF gateway, health check, and deep dive assurance reviews
  • regular reporting.

Under the IIAF, it is mandatory for all capital projects valued over $10.0 million to be registered with INSW. Capital projects can be registered either as a program (comprising of a group of related projects or activities) or as a project (which may or may not be part of a program).

According to the IIAF, programs tend to have a lifespan of several years and aim to deliver outcomes and benefits related to an organisation's strategic objectives. Projects tend to have a shorter lifespan, and deal with outputs. Projects can, however, be grouped under a single program if they are similar in nature or if they are aimed at collectively achieving a strategic objective. Complex projects can be delivered in multiple stages, under different contracts, and across different time periods.

The last assurance review of the entire WestConnex program of works as a whole was in 2015

INSW conducted the first IIAF gateway review of WestConnex in August 2015. TfNSW developed a draft WestConnex Updated Strategic Business Case to consolidate the latest analysis on WestConnex, and to confirm that the project remained fit for purpose, economically viable, and financially deliverable. The review followed a recommendation in our 2014 performance audit report that business cases be thoroughly revisited.

During September 2015, INSW conducted additional informal reviews to identify strategic risks associated with public release of the WestConnex business case. Subsequently, INSW gave the Premier of NSW its views on the draft business case, including the following points:

  • The $398 million budget for Sydney Gateway was insufficient to meet the benefits claimed in the business case for a ‘functional’ connection to Sydney Airport and Port Botany. INSW studies indicate a future‑proof solution would require a minimum spend of $755 million.
  • Enabling works for WestConnex estimated at $1.534 billion were excluded from the cost of WestConnex. Significant work remained for RMS to identify mitigation measures to address planning approvals and network performance issues.
  • Enabling works (a Southern Connector), an access ramp and surface road improvements within St Peters were excluded from the draft 2015 business case despite their inclusion in the WestConnex scope in the 2014–15 State Budget.
  • The overall cost of works not funded within the WestConnex budget ranged from $2.011 billion to $2.196 billion. This included the enabling works, access ramp and surface road improvements and the shortfall for Sydney Gateway.

All WestConnex related projects, including Sydney Gateway have undergone independent assurance reviews under the IIAF

Since INSW submitted the first WestConnex progress update report to Cabinet in June 2015, INSW has been reporting monthly on the different stages of the WestConnex Program, including Sydney Gateway, as the projects were registered with INSW as High‑Profile, High‑Risk projects. Separate reporting enabled INSW to report and review each stage with more detailed scrutiny, compared to the reporting and reviewing at a program level.

WestConnex Stage 2 (New M5) underwent both mandatory and non‑mandatory reviews at key points in the project lifecycle. Three mandatory gateway reviews – at Gate 2 (Final business case), Gate 3 (Readiness for market), and Gate 4 (Tender evaluation) – were conducted by TfNSW before the introduction of IIAF. Four non‑mandatory health check reviews and one non‑mandatory deep dive review were conducted after the introduction of the IIAF managed by INSW.

Similarly, WestConnex Stage 3 projects – M4‑M5 link, M4‑M5 Tunnels, and Rozelle Interchange – also underwent mandatory and non‑mandatory reviews at key points in their lifecycle under IIAF.

The M4‑M5 Link had two mandatory gateway reviews and one non‑mandatory health check review under IIAF. These reviews were conducted before Stage 3 was split into two stages, due to major design changes to the Rozelle Interchange and the M4‑M5 tunnels.

The M4‑M5 tunnels had two mandatory gateway reviews (at Gates 3 and 4), one non‑mandatory health check review, and one non‑mandatory deep dive review under IIAF.

Rozelle Interchange also underwent three mandatory gateway reviews at Gate 3 (part 1), Gate 3 (part 2), and Gate 4, two non‑mandatory health check reviews, and one non‑mandatory deep dive review under IIAF.

Since mid‑2017, the Sydney Gateway project has undergone required independent assurance reviews, as well as a number of optional assurance reviews

In November 2016, INSW conducted a mandatory Gate 1 gateway review on a strategic business case for the Sydney Gateway Project. TfNSW did not proceed with this business case. Following the separation of Sydney Gateway from WestConnex in mid‑2017, TfNSW developed a new business case for Sydney Gateway. It has undergone the required Gate 1, Gate 2, and Gate 3 gateway reviews, as well as two non‑mandatory health check reviews, and three non‑mandatory deep dive reviews under IIAF.

Network integration works have undergone all IIAF required assurance reviews

TfNSW completed a strategic business case for the Network Integration Program in August 2020, and INSW completed a gateway review in November 2020. This is despite network integration projects starting as early as 2015, with $645 million having been spent by June 2020. The strategic business case included a prioritisation process for completing remaining works in the program. Prior to November 2020, TfNSW registered individual network integration projects with INSW, and these projects have undergone gateway reviews where required.

The Network Integration Program strategic business case does not include Rozelle interchange network integration works ($353 million) and additional network integration works to settle a contractor claim adjacent to St Peters Interchange ($190 million). These were excluded from the business case on the basis they had already been approved by government, and as such were not subject to the prioritisation elements of the business case. TfNSW has not developed separate business cases for these works, although the scope of the St Peters Interchange works was developed through a negotiated process.

TfNSW did not prepare business cases for some network integration works which have commenced, including the $323 million Campbell Road/Euston Road works

Prior to its development of the August 2020 strategic business case, TfNSW did not prepare business cases for many network integration works that have commenced, and in some instances were completed, before 2019. Significantly, TfNSW did not prepare a business case for the Campbell Road/Euston Road works, which cost $323 million and have been completed.

In 2016, TfNSW’s Business Case Policy requires the creation of business cases for capital projects costing over $1.0 million. At the time of writing this report, TfNSW’s draft policy requires full business cases for capital projects costing $10.0 million or more.

There is no requirement for ongoing ‘whole‑of‑program’ assurance of the WestConnex program of works, including related projects

INSW conducted its first gateway review of WestConnex (as a program, which consisted of composite projects) in August 2015. Following that review, TfNSW registered each of the components of WestConnex with INSW as individual projects, rather than keeping WestConnex registered as a program or complex project. The IIAF allows this to occur.

Separate registration enabled INSW to report and review each stage with more scrutiny compared to whole‑of‑program level review.

Such an approach has merit, considering the individual stages (and components of these stages) are multi‑million dollar works in their own right. Each project has its own timing for gateway reviews at stages such as 'Readiness for Market' and 'Tender Evaluation'.

Once a program such as WestConnex is broken down into its composite parts, there is no requirement for the sponsor agency (TfNSW) or INSW to conduct independent assurance on the program of works as a whole until the whole program is completed as part of the Benefits Realisation (Gate 6) gateway review. The absence of strategic, holistic reviews of projects of the scale and complexity such as WestConnex during their delivery allows for total costs and benefits to become opaque and avoid scrutiny. Projects of this scale require greater ongoing transparency on total costs and benefits in order to ensure confidence they will meet intended objectives within budget.

INSW has advised us that it has prepared a proposal to expand its assurance function to include whole‑of‑program review of inter‑related infrastructure projects.

Appendix one – Responses from agencies

Appendix two – Network integration works

Appendix three – About the audit

Appendix four – Performance auditing

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #351 - released (17 June 2021).

Published

Actions for Acquisition of 4–6 Grand Avenue, Camellia

Acquisition of 4–6 Grand Avenue, Camellia

Transport
Asset valuation
Compliance
Fraud
Infrastructure
Internal controls and governance
Management and administration
Procurement
Risk

The Auditor-General for New South Wales, Margaret Crawford, has today released a report on Transport for NSW’s (TfNSW) acquisition of 4–6 Grand Avenue in Camellia.

This audit, which was requested on 17 November 2020 by the Hon. Andrew Constance MP, the Minister for Transport and Roads, examined:

  • whether TfNSW conducted an effective process to purchase 4–6 Grand Avenue, Camellia
  • whether TfNSW has effective processes and procedures to identify and acquire property required to deliver the NSW Government’s major infrastructure projects.

The audit found that TfNSW conducted an ineffective process when it purchased 4–6 Grand Avenue, Camellia. The audit also found that TfNSW’s internal policies and procedures to guide the transaction were, and continue to be, insufficient.

The Auditor-General has made seven recommendations to address the issues identified in the report.

On 17 November 2020, the Hon. Andrew Constance MP, the Minister for Transport and Roads, requested this audit under section 27B(3)(c) of the Public Finance and Audit Act 1983.

On 15 June 2016, Transport for New South Wales (TfNSW) acquired 6.3 hectares of land at 4–6 Grand Avenue, Camellia, by agreement from Grand 4 Investments Pty Ltd. Grand 4 Investments was a business entity established by the owners of Billbergia Pty Ltd, a property development and investment company.

TfNSW paid Grand 4 Investments $53.5 million and assumed liability for addressing environmental issues and contamination associated with the site. This took place seven months after the vendor acquired the land as part of a competitive Expression of Interest process, in which TfNSW also participated, for $38.15 million.

TfNSW is the NSW Government agency responsible for most major transport infrastructure projects in New South Wales. TfNSW acquired the Camellia site for use as a stabling and maintenance depot to support the Parramatta Light Rail (PLR) project.

Consistent with the minister’s request, this audit assessed:

  • whether TfNSW conducted an effective process to purchase 4–6 Grand Avenue, Camellia
  • whether TfNSW has effective processes and procedures to identify and acquire property required to deliver the NSW Government’s major infrastructure projects.

In considering the effectiveness of the processes for this purchase, the audit considered:

  • the requirements of the Land Acquisition (Just Terms Compensation) Act 1991 (the Act)
  • the application of sound processes to manage risk to the NSW Government and to achieve value for money
  • the application of disciplines associated with complex procurement, such as probity, in a NSW Government context.
The acquisition of the 4–6 Grand Avenue site in Camellia was consistent with a 2014 feasibility study for the PLR, but occurred before the completion of detailed project planning or an acquisition strategy.

TfNSW made two attempts to acquire the 4–6 Grand Avenue site in Camellia, and was successful on the second attempt. TfNSW recognised the risks associated with early acquisition and had high-level strategies in place should the site not be required.

The specific site had been identified in a feasibility study for the PLR commissioned by TfNSW in 2014 as one of several options in Camellia for a stabling and maintenance depot. However, TfNSW had not done any substantive analysis of the various options to identify a preferred location before the two opportunities to acquire 4–6 Grand Avenue were brought to TfNSW’s attention by the landowners (or their agents). On both occasions, TfNSW chose to actively pursue acquisition in advance of any such analysis.

The acquisition was also not informed by a Property Acquisition Strategy, which TfNSW policy recommends in order to guide the process and manage acquisition specific risks.

In 2015, TfNSW identified that it would require a stabling and maintenance depot in the Camellia area for the Parramatta Light Rail

In 2014, TfNSW commissioned an external engineering consultancy to undertake a feasibility design study for the Parramatta Light Rail - the Parramatta Transport Corridor Strategy Feasibility Design study (herein referred to as ‘the feasibility study’). In early 2015, TfNSW received the feasibility study, which was one of several key sources that informed the development of business cases for the PLR.

The feasibility study recommended that TfNSW should consolidate the maintenance and cleaning operations with overnight stabling facilities on one site. The study noted that the optimal location for any such site would be in close proximity to the proposed network, and noted that the site must have access to road connections to accommodate access for cars and trucks.

The study found that a centrally located stabling and maintenance facility would be required for all routes serving the Parramatta CBD, and that the Camellia industrial area was a preferred location for such a facility. The study noted that the Camellia area was contaminated.

The feasibility study notes that its conclusions were based on assumptions about the light rail system adopted and decisions made by the future operator of the system, who had not yet been selected or appointed.

TfNSW's decision to progress a potential acquisition in 2015 considered the risk that the site may not be required

TfNSW's FIC was responsible for making decisions on funding allocations at a whole of program level within TfNSW. FIC was also responsible for approving ‘high-risk/high-value’ variations to program budgets. Members of the FIC included:

  • Secretary of Transport for NSW
  • Deputy Secretary, Infrastructure and Services
  • Deputy Secretary, Freight, Strategy and Planning
  • Deputy Secretary, Customer Services
  • Deputy Secretary Finance and Investment
  • Deputy Secretary People and Corporate Services.

An April 2015 submission, from the then Deputy Director-General to the agency’s FIC, sought authorisation and funding approval to participate in an Expression of Interest sale process. It noted the risk that the project may not go ahead. The submission advised that:

By acquiring a strategic site now, it reduces the risk of having to pay an improved value or a value that may be subject to rapidly improving land values due to changes in land use and rezoning.

The property can be acquired for the project, held strategically and income generated by leasing the site as hardstand 1 space until the project requires the land for the Parramatta Light Rail project.

If the project does not proceed in the medium to longer term, the property can be sold at a premium to what has been paid today as property fundamentals improve.

This submission acknowledged the risks associated with environmental contamination and proposed that these risks would be managed by negotiating a contract where the remediation and associated expenses would be at the landowner’s cost. 

TfNSW assessed the 4–6 Grand Avenue site as one of several sites in Camellia that was a feasible location for a stabling and maintenance facility

The Departmental feasibility study assessed six potential sites for a stabling and maintenance facility, including 4–6 Grand Avenue, noting strengths and weaknesses of each site. A different site on Grand Avenue was assessed as the ‘base case’ option (1 Grand Avenue). The study’s comments on the 4–6 Grand Avenue site included the following:

With an area of approximately 63,000m2, this site has sufficient space for a depot with the required stabling yard and maintenance facilities. The location allows for good road access and LRT [light rail transit] access would be from Grand Avenue, which may require a road crossing or signalised intersection. The site has been used for general industrial uses; however the land has been cleared and is currently undergoing remediation 2. The site is not affected by flooding based on one in 100-year flood data.

In early 2015, once the opportunity to acquire 4–6 Grand Avenue emerged, TfNSW commissioned a specific feasibility study of the 4–6 Grand Avenue site. The feasibility studies clearly documented the existence of environmental contamination. In April 2015, the report concluded:

Given the limitations of this report and within the parameters that have been set it is concluded that from a spatial and geographic perspective the site at 6 Grand Avenue would be suitable as a stabling and maintenance depot for the Parramatta light rail project. There are few engineering and environmental constraints that would affect the feasibility level analysis of this site and all issues identified, within this desk study, are considered to be resolvable. However this being said there is a significant amount of work necessary to reach the final layout and definition of the stabling and maintenance depot. There are numerous items which require further consideration and conformation; planning approvals could impose restrictions on building heights, noise mitigation measures, light and visual impact requirements all of which can have significant impacts on the spatial requirements of any stabling and maintenance depot. 

The acquisition of 4–6 Grand Avenue was not informed by a Property Acquisition Strategy

For major projects, TfNSW typically requires the project team to complete a Property Acquisition Strategy, which is intended to guide both process as well as specific acquisition issues expected to be faced during the project. The Property Acquisition Strategy is not a mandated document but is a recommended tool to support property acquisition as part of major projects.

TfNSW did not have a Property Acquisition Strategy in place to guide the 2015 Expression of Interest process. On 6 November 2015, the then Project Director for the PLR project emailed the property team, noting a need to develop a Property Acquisition Strategy to close off the scoping design and preliminary business case.

In January 2016, TfNSW developed a draft Property Acquisition Strategy for the Parramatta Light Rail Project, although it was silent on the potential sites for the stabling and maintenance facility.

TfNSW focussed on 4–6 Grand Avenue because it was available and aligned to TfNSW's strategic interests

In early 2015, officials commenced monitoring the market for industrial real estate in the Camellia area and surrounds for possible sites for a stabling and maintenance facility.

In March 2015, then owner of the site, Akzo Nobel Pty Limited released the 4–6 Grand Avenue site through an Expression of Interest process managed by CBRE.

TfNSW’s then Deputy Director-General, Planning, sought approval from FIC to lodge an Expression of Interest up to $30.0 million. Approval was sought on the basis that it would ‘provide certainty for the Parramatta Light Rail project by allowing for a depot site in a suitable location and potentially avoid higher costs or longer timeframes associated with compulsory acquisition following completion of the project’s business case’. FIC approved the request at its meeting on 9 April 2015.

At this time, TfNSW had not conducted any analysis of financial or operational benefits and costs of the potential sites identified in earlier feasibility studies. TfNSW staff advised us that the decision to participate in the Expression of Interest process for 4–6 Grand Avenue was because it was available. There is no documentation substantiating this statement, which TfNSW staff provided verbally as part of this audit.

In November 2015, TfNSW was advised that it was unsuccessful in the Expression of Interest process and that Grand 4 Investments (a related entity of Billbergia) had purchased 4–6 Grand Avenue. TfNSW did not conduct any further analysis of alternative potential sites in Camellia between this date and commencing discussions with Grand 4 Investments in April 2016. In that time there had been some movement on other properties that were included in the feasibility study, including 37–39a Grand Avenue being under offer in September 2015.

In March 2016, TfNSW approached CBRE to organise a meeting with Grand 4 Investments. On 1 April 2016, TfNSW met with Grand 4 Investments.

TfNSW advises that a perceived benefit of the 4–6 Grand Avenue site was that it was not subject to other uses or leaseholds that would increase the cost of compulsory acquisition. Officers involved in the acquisition advised that other nominated sites in the feasibility study were subject to other uses or leaseholds. 


1  A hardstand space is a large, paved area to store cars, heavy vehicles and machinery.
2  Officers familiar with the acquisition could not confirm the nature of remediation being undertaken, but noted that the previous landowner had cleared buildings from the site, which may have been considered part of remediation.
TfNSW's independent valuation, which it commissioned and received after the acquisition, specifically excluded consideration of environmental contamination risk. As a result, TfNSW is exposed to the risk that the acquisition was not fully compliant with the Land Acquisition (Just Terms Compensation) Act 1991 (the Act) because it did not use an accurate estimate of market value during negotiations. That said, the acquisition of 4–6 Grand Avenue by agreement was consistent with preferred processes described in the Act.

TfNSW acquired the site from the landowner by agreement, and this is consistent with provisions in the Act. Obtaining approval for compulsory acquisition should negotiations for agreement break down is also consistent with the Act. That said, TfNSW did not at any time assess whether a compulsory acquisition could have resulted in acquisition at a lower cost than what was negotiated by agreement.

Despite the high risks associated with the acquisition, TfNSW did not commission a formal valuation in time to inform the negotiation and purchase. Instead, TfNSW relied on internal advice to estimate market value, but did not obtain a formal valuation from those advisors. For high-risk transactions, the greater expertise and arm's-length independence of an external specialist valuer should be preferred over an agency's own staff.

On 15 June 2016, the settlement date for the acquisition, TfNSW commissioned a formal independent valuation of the site. On 23 November 2016, TfNSW received the final formal valuation report. By not obtaining a formal independent valuation of the property in advance of acquisition to inform the acquisition value, TfNSW exposed itself to non-compliance with the Act by not establishing the market value as the basis for the acquisition price. TfNSW also breached its own internal policies.

TfNSW instructed the valuer to conduct its valuation within the following parameters:

  • Market valuation on an ‘as is’ basis – market value based on the methodology described in the Act. This approach valued the site at $25.0 million.
  • Market valuation on a speculative development basis – market value based on the financial value of the vendor's intended use of the site which, in this case, involved leasing the site for industrial use. This approach valued the site at $52.0 million, and TfNSW advised us this valuation supported the purchase price.
  • Disregard the impact of environmental contamination – TfNSW specifically instructed the independent valuer to disregard any known (or unknown) site contamination. As TfNSW knew of the significant environmental contamination affecting the site, this parameter resulted in a valuation that overstated the value of the site as it did not consider the cost of environmental remediation. The valuer applied this assumption for both market valuation approaches.

Additionally, as the independent valuer completed the valuation after the purchase was finalised, there is a risk that the valuation may have been influenced by the known purchase price.

TfNSW's failure to acquire a formal valuation and an assessment of the financial impact of environmental remediation before it purchased 4–6 Grand Avenue represents ineffective administration and governance.
TfNSW acquired the site at a time when there was demand and increasing prices for industrial property in the area. However, TfNSW did not effectively assess and manage the risks associated with the acquisition, and gaps in process led to increased risk. Briefings to decision-makers did not contain important information, and we found no evidence that gaps in advice were queried or explored by decision-makers.

TfNSW did not have plans or advice in place to assist in managing risk, such as:

  • a property acquisition plan
  • a comprehensive and up-to-date risk management plan
  • a negotiation strategy, or any authorisation limit or minimal acceptable position
  • an independent professional evaluation
  • external expert advice (with the exception of legal advice relating to the contract of sale).

TfNSW was aware of contamination issues affecting the land and had access to considerable information about the environmental conditions, such as site environmental audit reports and information on the NSW Environment Protection Authority's contaminated land register. However, TfNSW had not analysed specific technical information about the contamination and therefore was not aware of the risk implications and cost for remediation. Despite this, TfNSW changed its position from not accepting the risks and costs of contamination, to acquiring the site unconditionally. The basis for this decision is unclear and undocumented.

Briefing to senior leaders on the acquisition was silent on a number of important matters that would have been important for approvers to consider, including:

  • an explanation of the 40 per cent increase in purchase price between November 2015 and May 2016, and a 165 per cent increase from TfNSW’s offer in April 2015
  • the contamination risks associated with the site and an evidence-based estimate of potential costs to remediate the site
  • advice that an independent valuation had not been obtained, inconsistent with TfNSW policy.

Consideration of the acquisition by FIC was based on a summary business paper and was managed out-of-session, thereby removing the ability for comprehensive consideration of the acquisition proposal and its risks.

The probity management controls and assurances in place for the acquisition of the 4–6 Grand Avenue site were insufficient. These insufficiencies were exacerbated by the probity risk profile of the transaction.

The 4–6 Grand Avenue acquisition was a high-risk/high-value transaction, undertaken in a volatile property market in a short timeframe under pressure from Grand 4 Investments. TfNSW was engaging in a direct negotiation in advance of detailed planning for the acquisition, or the PLR as a whole. These circumstances contribute to heightened probity risk.

TfNSW did not establish a probity plan and sought no probity support throughout the acquisition. Also, with one exception, the staff involved in the acquisition did not complete conflict of interest declarations.

TfNSW was aware of the potential for probity or integrity issues with the transaction when it commissioned an internal audit in connection with the transaction in 2019. Internal discussions considered whether a misconduct investigation may be more appropriate, however no such investigation was undertaken.

TfNSW's insufficient probity practices, in addition to its failure to keep complete or comprehensive records of negotiations or decisions, reduce transparency of the process and its outcome and expose TfNSW to a greater risk of misconduct, corruption and maladministration.

At the time of the transaction, the TfNSW policy framework was not sufficiently risk-focussed and did not provide clarity on when officers ought to apply specific guidance or procedures. TfNSW's policies and procedures are more focussed on acquiring land to meet project needs and timeframes, and less on assuring value for money and managing risks.

At the time of its acquisition of 4–6 Grand Avenue, TfNSW had property acquisitions policies and procedures in place. Each of these were broadly sound in their content and intent. However, they lacked specificity on how or when to apply guidance, and when risk levels should elevate the importance of recommended guidance.

TfNSW's key guidance was principles based and relied on agency staff using their experience and expertise to apply guidance according to the circumstances of an individual transaction. This guidance was not duly applied in the acquisition of 4–6 Grand Avenue, Camellia. In addition, TfNSW does not have quality or control assurance to identify when TfNSW officers did not apply important policies or processes.

The primary focus of the TfNSW’s property acquisition guidance is to achieve vacant possession of land in a timeframe that meets the need of the relevant transport project. There is less specific focus on the need to meet the requirements of the NSW Government financial management framework.

Appendix one – Response from agency 

Appendix two – About the audit 

Appendix three – Performance auditing

 

Copyright Notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #349 - released (18 May 2021).

Published

Actions for Health 2020

Health 2020

Health
Compliance
Financial reporting
Infrastructure
Internal controls and governance
Service delivery

This report analyses the results of our audits of financial statements of the Health cluster for the year ended 30 June 2020. The table below summarises our key observations.

1. Financial reporting

Financial reporting

Unqualified financial audit opinions

The financial statements of NSW Health and its 25 controlled entities received unqualified opinions.

The number of corrected and uncorrected misstatements increased from the prior year. Misstatements related predominantly to the implementation of new accounting standards, asset revaluations and accounting for new revenue streams to cover the cost of HSW Health’s response to the COVID-19 pandemic.

Qualified compliance audit opinion

We issued a qualified audit opinion for the Ministry of Health’s Annual Prudential Compliance Statement for aged care facilities operated by NSW Health. We identified 18 instances of material non-compliance with the Fees and Payments Principles 2014 (No. 2) (the Principles) in 2019–20 (30 in 2018–19).

Financial performance

NSW Health received an additional $3.3 billion in funding to cover costs associated with its response to the COVID-19 pandemic.

The impacts of the COVID-19 pandemic on the cluster were significant for health entities and included changes to operations, increased revenues, expenditure, assets and liabilities. Cancellation of elective surgery and decreased emergency department presentations meant that despite the pandemic, activity levels at many health entities decreased. Health Pathology and HealthShare were notable exceptions.

In the period to the 30 June 2020, NSW Health reported that over 900,000 COVID-19 tests were conducted. Health Pathology conducted over 500,000 of these tests. Health Pathology's surge requirements were enhanced through arrangements with 13 private sector providers. HealthShare purchased $864.2 million of personal protective equipment.

Overall, NSW Health recorded an operating surplus of $3.1 billion in 2019–20, an increase of $2.0 billion from 2018–19. As in previous years, the surplus largely resulted from additional revenue received to fund capital projects including the construction of new facilities, upgrades and redevelopments. In 2019–20 additional Commonwealth and State funding for the purchase and stockpiling of personal protective equipment also contributed to the operating surplus.

Overtime payments The Ambulance Service of NSW’s (NSW Ambulance) reduced their overtime payments to $79.7 million in 2019–20 ($83.1 million in 2018–19). Overtime payments in 2019–20 included $6.8 million related to the response to the 2019–20 bushfire season. NSW Ambulance overtime payments represent 16.8 per cent of total overtime payments in the cluster.

2. Audit observations

Internal control deficiencies

We identified more internal control deficiencies in 2019–20. The number of repeat issues from prior years also remains high.

NSW Health addressed 18 out of the 25 information system control deficiencies during the year.

Several key agreements lacked formal documentation. This included agreements between the Ministry and health entities, between health entities and agencies in other clusters and between the Ministry and health departments in other jurisdictions.

Infrastructure delivery NSW Health had 44 ongoing major capital projects at 30 June 2020 with a total revised budget of $12.3 billion. The revised total budget of $12.3 billion is $2.0 billion more than the original budget. NSW Health revises budgets when it combines project stages.

This report provides parliament and other users of the Health cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

The impacts of the COVID-19 pandemic on the cluster were significant and included changes to the operations of the health entities and increased revenue, expenditure, assets and liabilities.

As a part of this year's audits of health entities, we have considered:

  • financial implications of the COVID-19 emergency at both health entity and cluster levels
  • changes to agencies' operating models
  • agencies' access to technology and the maturity of systems and controls to prevent unauthorised and fraudulent access to data.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

The response to the COVID-19 pandemic primarily impacted the financial reporting of NSW Health through:

  • additional revenue from the State government in the form of grants and stimulus payments
  • additional revenue from the Commonwealth government under the National Partnership Agreement for COVID-19 to cover part of the cost of responding to the COVID-19 pandemic
  • increased expenses, largely due to increased payments to private health operators to maintain their viability during the COVID-19 pandemic and later to assist with public patient elective surgery waitlists and increased cleaning costs
  • increased purchases of personal protective equipment.

Chapter one outlines the impacts of NSW Health’s response to the COVID-19 pandemic. This chapter outlines our other audit observations related to the financial reporting of agencies in the Health cluster for 2020.

Section highlights

  • Unqualified audit opinions were issued for all health entities’ financial statements, although more misstatements were identified than last year.
  • NSW Health recorded an operating surplus of $3.1 billion, an increase of $2.0 billion from 2018–19. This is largely due to additional capital grants for new facilities, upgrades and redevelopments and additional Commonwealth and State funding for the purchase of personal protective equipment.
  • NSW Health’s expenses increased by 5.5 per cent in 2019–20 (7.0 per cent in 2018–19) despite the impact of the COVID-19 pandemic. The primary causes for the growth in expenses are increases in:
    • employee related expenses due to higher employee numbers, increased overtime and a 2.5 per cent award increase
    • payments to private health operators to maintain their viability during the COVID-19 pandemic and later to assist with public patient elective surgery waitlists
    • payments to private health operators due to the first full year of operation of the Northern Beaches hospital.
  • The Ambulance Service of NSW (NSW Ambulance) continued to report higher overtime payments than other health entities. However, despite the response to the 2019–20 bushfire season, their overtime payments were lower than last year. NSW Ambulance paid $79.7 million in overtime payments in 2019–20 ($83.1 million in 2018–19).
  • A qualified audit opinion was issued for the Ministry of Health’s Annual Prudential Compliance Statement for aged care facilities operated by NSW Health. There were 18 instances of material non-compliance with the Fees and Payments Principles 2014 (No. 2) (the Principles) in 2019–20 (30 in 2018–19)

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

The primary impact of the COVID-19 pandemic on the effectiveness of the internal controls of NSW Health and health entities relates to the effectiveness of controls implemented by HealthShare relating to the stocktake of personal protective equipment inventories. Inventory managed by HealthShare increased by 2,746 per cent during 2019–20. HealthShare’s inventory controls did not maintain pace with the sudden, significant increase.

The impacts of NSW Health’s response to the COVID-19 pandemic are outlined in chapter one. This chapter outlines other observations and insights from our financial statement audits of agencies in the Health cluster.

Section highlights

  • The number of internal control deficiencies has increased since 2018–19. More than a third of control deficiencies are repeat issues.
  • Control deficiencies that relate to managing employees’ leave and employee’s time recording continue to be difficult for entities to resolve, particularly during the ongoing response to the COVID-19 pandemic.
  • Several key agreements were undocumented. These included agreements between the Ministry and the health entities, between health entities, and between the Ministry and entities in other clusters and jurisdictions. These related to:
    • a loan arrangement between the Ministry and HealthShare for $319 million.
    • Northern Sydney Local Health District's use of land and buildings owned by the Graythwaite Charitable Trust
    • agreements for the treatment of New South Wales residents while they are interstate, and interstate residents receiving treatment while they are in New South Wales from Queensland, Victoria, South Australia and the ACT for both 2019–20 and 2018–19.
  • NSW Health reported that they completed nine major capital projects during 2019–20. As at 30 June 2020 there were 44 ongoing major capital health projects in NSW. The revised capital budget for these projects in total was $2.0 billion more than the original budget of $10.3 billion. NSW Health reported the budget revisions are largely the result of combining project stages.

Appendix one – List of 2020 recommendations 

Appendix two – Status of 2019 recommendations 

Appendix three – Financial data

Appendix four – Analysis of financial indicators 

Appendix five – Analysis of performance against budget

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Auditor-General’s Report to Parliament

Health 2020

11 December 2020

This corrigendum has been prepared to amend the following text within the Auditor-General’s Report to Parliament on Health 2020, dated 10 December 2020.

NSW Health emergency department treatment times

On page five the original text was as follows:

NSW Health also measures the percentage of patients whose clinical care in emergency departments is completed within four hours. The measure is used as an indicator of accessibility to public hospital services.

NSW Health aims to complete clinical care in the emergency department for 81 per cent of patients within four hours. In 2019–20 NSW Health reports it completed clinical care within four hours for 72.1 per cent of patients (a 7.3 per cent decrease from 2018–19).

At Western Sydney Local Health District, 59 per cent of patients were treated within the targeted timeframe. NSW Health attribute this to the profile of patients presenting in emergency departments and additional time taken processing COVID-19 patients to ensure staff safety.

The original text has now been changed to:

NSW Health also measures the percentage of patients with total time in the emergency department of four hours or less for each local health district. The measure is used as an indicator of accessibility to public hospital services.

Local Health Districts Target % (2019–20) Actual % (2019–20)
Central Coast 77.0 59.9
Far West 90.2 86.6
Hunter New England 81.0 72.5
Illawarra Shoalhaven 79.0 60.2
Mid North Coast 82.0 76.7
Murrumbidgee 85.3 81.9
Nepean Blue Mountains 79.0 65.5
Northern NSW 81.0 78.2
Northern Sydney 79.0 73.9
South Eastern Sydney 78.0 70.3
South Western Sydney 78.0 61.2
Southern NSW 85.0 83.0
Sydney 76.0 70.9
Sydney Children’s Hospitals Network 80.0 72.1
Western NSW 85.9 81.0
Western Sydney 78.0 59.0
St Vincent's Health Network* 75.0 65.4
* St Vincent’s Health Network Sydney (SVHNS) comprises of St Vincent’s Hospital Sydney Limited as the affiliated health organisation in respect of four recognised establishments under the Health Services Act 1997 (NSW) (Health Services Act). Under the Health Services Act, St Vincent’s Hospital Sydney Limited, is treated as a Network for the purposes of the National Health Reform Agreement in respect of the three recognised establishments: St Vincent’s Hospital, Darlinghurst; Sacred Heart Health Service, Darlinghurst; St Joseph’s Hospital, Auburn; and St Vincent's Correctional Health, Parklea.
Source: NSW Health (unaudited)

The above changes will be reflected in the version of the report published on the Audit Office website and should be considered the true and accurate version.

Published

Actions for Transport 2020

Transport 2020

Transport
Asset valuation
Cyber security
Financial reporting
Information technology
Infrastructure
Project management

1. Financial Reporting

Audit opinion Unmodified audit opinions issued for the financial statements of all Transport cluster entities.
Quality and timeliness of financial reporting All cluster agencies met the statutory deadlines for completing the early close and submitting the financial statements.

Transport cluster agencies continued to experience some challenges with accounting for land and infrastructure assets. The former Roads and Maritime Services and Sydney Metro recorded prior period corrections to property, plant and equipment balances.
Impact of COVID-19 on passenger revenue and patronage Total patronage and revenue for public transport decreased by approximately 18 per cent in 2019–20 due to COVID-19.

The Transport cluster received additional funding from NSW Treasury during the year to support the reduced revenue and additional costs incurred such as cleaning on all modes of public transport and additional staff to manage physical distancing.
Completion of the CBD and South East Light Rail The CBD and South East Light Rail project was completed and commenced operations in this financial year. At 30 June 2020, the total cost of the project related to the CBD and South East Light Rail was $3.3 billion. Of this total cost, $2.6 billion was recorded as assets, whilst $700 million was expensed.

2. Audit Observations

Internal control While internal controls issues raised in management letters in the Transport cluster have decreased compared to the prior year, control weaknesses continue to exist in access security for financial systems. We identified 56 management letter findings across the cluster and 43 per cent of all issues were repeat issues. The majority of the repeat issues relate to information technology controls around user access management.

There were three high risk issues identified - two related to financial reporting of assets and one for implementation of TAHE (see below).
Agency responses to emergency events Transport for NSW established the COVID-19 Taskforce in March 2020 to take responsibility for the overall response of planning and coordination for the Transport cluster. It also implemented the COVIDSafe Transport Plan which incorporates guidance on physical distancing, increasing services to support social distancing and cleaning.
RailCorp transition to TAHE On 1 July 2020, RailCorp was renamed Transport Asset Holding Entity of New South Wales (TAHE) and converted to a for-profit statutory State-Owned Corporation. TAHE is a commercial for-profit Public Trading Entity with the intent to provide a commercial return to its shareholders.

A plan was established by NSW Treasury to transition RailCorp to TAHE which covered the period 1 July 2015 to 1 July 2019. A large portion of the planned arrangements were not implemented by 1 July 2020. As at the time of this report, the TAHE operating model, Statement of Corporate Intent (SCI) and other key plans and commercial agreements are not finalised. The State Owned Corporations Act 1989 generally requires finalisation of an SCI three months after the commencement of each financial year. However, under the Transport Administration Act 1988, TAHE received an extension from the voting shareholders, the Treasurer and Minister for Finance and Small Business, to submit its first SCI by 31 December 2020. In accordance with the original plan, interim commercial access arrangements were supposed to be in place with RailCorp prior to commencement of TAHE.

Under the transitional arrangements, TAHE is continuing to operate in accordance with the asset and safety management plans of RailCorp. The final operating model is expected to include considerations of safety, operational, financial and fiscal risks. This should include a consideration of the potential conflicting objectives of a commercial return, and maintenance and safety measures.

This matter has been included as a high risk finding in our management letter due to the significance of the financial reporting impacts and business risks for TAHE.

Recommendation: TAHE management should:
  • establish an operating model in line with the original intent of a commercial return
  • finalise commercial agreements with the public rail operators
  • confirm forecast financial information to assess valuation of TAHE infrastructure
  • finalise asset and safety management plans.

Resolution of the above matters are critical as they may significantly impact the financial reporting arrangements for TAHE for 2020–21, in particular, accounting policies adopted as well as measurement principles of its significant infrastructure asset base.

Completeness and accuracy of contracts registers Across the Transport cluster, contracts and agreements are maintained by the transport agencies using disparate registers.

Recommendation (repeat): Transport agencies should continue to implement a process to centrally capture all contracts and agreements entered. This will ensure:
  • agencies are fully aware of contractual and other obligations
  • appropriate assessment of financial reporting implications
  • ongoing assessments of accounting standards, in particular AASB 16 ‘Leases’, AASB 15 'Revenue from Contract with Customers', AASB 1058 'Income of Not-for-Profit Entities' and new accounting standard AASB 1059 'Service Concession Arrangements: Grantors' are accurate and complete.

 

This report provides parliament and other users of the Transport cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations
  • the impact of emergencies and the pandemic.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Transport cluster for 2020, including any financial implications from the recent emergency events.

Section highlights

  • Total patronage and revenue for public transport decreased by approximately 18 per cent in 2019–20 due to COVID-19.
  • Unqualified audit opinions were issued on all Transport agencies' financial statements.
  • Transport cluster agencies continued to experience challenges with accounting of land and infrastructure assets.

 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our:

  • observations and insights from our financial statement audits of agencies in the Transport cluster
  • assessment of how well cluster agencies adapted their systems, policies and procedures, and governance arrangements in response to recent emergencies.

Section highlights

  • While there was a decrease in findings on internal controls across the Transport cluster, 43 per cent of all issues were repeat issues. Many repeat issues related to information technology controls around user access management.
  • RailCorp transitioned to TAHE on 1 July 2020. TAHE's operating model and commercial arrangements with public rail operators has not been finalised despite government original plans to be operating from 1 July 2019. TAHE management should finalise its operating model and commercial agreements with public rail operators as they may significantly impact the financial reporting arrangements for TAHE for 2020–21.
  • Completeness and accuracy of contracts registers remains an ongoing issue for the Transport cluster.

Appendix one – List of 2020 recommendations

Appendix two – Status of 2019, 2018 and 2017 recommendations

Appendix three – Management letter findings

Appendix four – Financial data

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.