CBD and South East Light Rail Project
Transport for NSW did not effectively plan and procure the CBD and South East Light Rail (CSELR) project to achieve best value for money according to a report released today by NSW Auditor-General, Margaret Crawford.
Transport for NSW is on track to deliver the project, but it will come at a higher cost with lower benefits than in the approved business case.
Parliamentary reference - Report number #278 - released 30 November 2016
Actions for Fraud Survey
Fraud Survey
In a report released today, the NSW Auditor-General, Margaret Crawford provides a snapshot of reported fraud in the NSW public sector and an analysis of NSW Government agencies’ fraud controls based on a survey of 102 agencies.
Actions for Finance, Services and Innovation 2016
Finance, Services and Innovation 2016
This report analyses the results of the financial statement audits of the Finance, Services and Innovation cluster entities for the year ended 30 June 2016.
Actions for Red tape reduction
Red tape reduction
Overall, NSW Government initiatives and processes to prevent and reduce red tape were not effective, according to a report released today by the NSW Auditor-General.
In 2015, the Government reported that its red tape reduction initiatives, implemented between 2011 and 2015, had resulted in $896 million in savings. While these initiatives resulted in some savings, the total value of savings is unknown because estimates for some initiatives were based on unverified assumptions, cost transfers or unrealised projections.
Parliamentary reference - Report number #272 - released 25 August 2016
Actions for Franchising of Sydney Ferries Network services
Franchising of Sydney Ferries Network services
Franchising services on the Sydney Ferries Network was justified, and Transport for NSW’s management of the franchise has been largely effective according to a report released today by the NSW Acting Auditor-General, Tony Whitfield.
'Franchising has resulted in cost savings, good service performance, and effective risk transfer from government to the private sector operator', said Mr Whitfield.
Parliamentary reference - Report number #265 - released 4 February 2016
Actions for Condition of State Roads
Condition of State Roads
The Roads and Traffic Authority (RTA) has improved the overall surface condition of State Roads in the last decade. Country road surfaces are now generally much better. Ride quality has improved and cracking has been reduced. The RTA has also achieved a substantial reduction in the number of structurally deficient bridges over the same period.
Despite a significant increase in the State’s contribution to maintenance since 1999-2000, the RTA has deferred road rebuilding projects. The RTA is rebuilding at less than half its long term target, and has not met this target at any time this decade. The RTA has not identified how it will address deferred rebuilding, although it advises it is developing a new road network management plan which will address this.
Parliamentary reference - Report number #157 - released 16 August 2006
Actions for The Cross City Tunnel Project
The Cross City Tunnel Project
In our opinion the Government’s ‘no net cost to government’ requirement was a legitimate (but not the only possible) basis for the tunnel bid process. The Government was entitled to decide that tunnel users meet the tunnel costs. Structuring the bid process on the basis of an upfront reimbursement of costs incurred (or to be incurred) by the Roads and Traffic Authority (RTA) was therefore appropriate.
In our opinion, however, the Government, Treasury and the RTA did not sufficiently consider the implications of an upfront payment involving more than simple project cost reimbursement (i.e. the ‘Business Consideration Fee’ component). In addition, the RTA was wrong to change the toll escalation factor late in 2002 to compensate the tunnel operator, Cross City Motorway Pty Ltd, for additional costs.
Parliamentary reference - Report number #152 - released 31 May 2006
Actions for Review of Walsh Bay
Review of Walsh Bay
The decision to seek development of Walsh Bay without a Master Plan and/or detailed study as to the state of the precinct presented significant problems throughout the life of the project. Now, four years later, negotiations still continue on the details of the final scheme. Based on the latest estimates, it will not provide a financial return as was originally expected. The audit found no evidence to indicate why the former Government wished to expedite Walsh Bay, but it is aware that there was an election due. Many of the problems which have been encountered could have been avoided with more careful and more extensive consideration at the start, particularly in the light of Property Services Group's recommendations.
Parliamentary reference - Report number #58 - released 17 December 1998