Actions for Acquisition of 4–6 Grand Avenue, Camellia

Acquisition of 4–6 Grand Avenue, Camellia

Transport
Asset valuation
Compliance
Fraud
Infrastructure
Internal controls and governance
Management and administration
Procurement
Risk

The Auditor-General for New South Wales, Margaret Crawford, has today released a report on Transport for NSW’s (TfNSW) acquisition of 4–6 Grand Avenue in Camellia.

This audit, which was requested on 17 November 2020 by the Hon. Andrew Constance MP, the Minister for Transport and Roads, examined:

  • whether TfNSW conducted an effective process to purchase 4–6 Grand Avenue, Camellia
  • whether TfNSW has effective processes and procedures to identify and acquire property required to deliver the NSW Government’s major infrastructure projects.

The audit found that TfNSW conducted an ineffective process when it purchased 4–6 Grand Avenue, Camellia. The audit also found that TfNSW’s internal policies and procedures to guide the transaction were, and continue to be, insufficient.

The Auditor-General has made seven recommendations to address the issues identified in the report.

On 17 November 2020, the Hon. Andrew Constance MP, the Minister for Transport and Roads, requested this audit under section 27B(3)(c) of the Public Finance and Audit Act 1983.

On 15 June 2016, Transport for New South Wales (TfNSW) acquired 6.3 hectares of land at 4–6 Grand Avenue, Camellia, by agreement from Grand 4 Investments Pty Ltd. Grand 4 Investments was a business entity established by the owners of Billbergia Pty Ltd, a property development and investment company.

TfNSW paid Grand 4 Investments $53.5 million and assumed liability for addressing environmental issues and contamination associated with the site. This took place seven months after the vendor acquired the land as part of a competitive Expression of Interest process, in which TfNSW also participated, for $38.15 million.

TfNSW is the NSW Government agency responsible for most major transport infrastructure projects in New South Wales. TfNSW acquired the Camellia site for use as a stabling and maintenance depot to support the Parramatta Light Rail (PLR) project.

Consistent with the minister’s request, this audit assessed:

  • whether TfNSW conducted an effective process to purchase 4–6 Grand Avenue, Camellia
  • whether TfNSW has effective processes and procedures to identify and acquire property required to deliver the NSW Government’s major infrastructure projects.

In considering the effectiveness of the processes for this purchase, the audit considered:

  • the requirements of the Land Acquisition (Just Terms Compensation) Act 1991 (the Act)
  • the application of sound processes to manage risk to the NSW Government and to achieve value for money
  • the application of disciplines associated with complex procurement, such as probity, in a NSW Government context.
The acquisition of the 4–6 Grand Avenue site in Camellia was consistent with a 2014 feasibility study for the PLR, but occurred before the completion of detailed project planning or an acquisition strategy.

TfNSW made two attempts to acquire the 4–6 Grand Avenue site in Camellia, and was successful on the second attempt. TfNSW recognised the risks associated with early acquisition and had high-level strategies in place should the site not be required.

The specific site had been identified in a feasibility study for the PLR commissioned by TfNSW in 2014 as one of several options in Camellia for a stabling and maintenance depot. However, TfNSW had not done any substantive analysis of the various options to identify a preferred location before the two opportunities to acquire 4–6 Grand Avenue were brought to TfNSW’s attention by the landowners (or their agents). On both occasions, TfNSW chose to actively pursue acquisition in advance of any such analysis.

The acquisition was also not informed by a Property Acquisition Strategy, which TfNSW policy recommends in order to guide the process and manage acquisition specific risks.

In 2015, TfNSW identified that it would require a stabling and maintenance depot in the Camellia area for the Parramatta Light Rail

In 2014, TfNSW commissioned an external engineering consultancy to undertake a feasibility design study for the Parramatta Light Rail - the Parramatta Transport Corridor Strategy Feasibility Design study (herein referred to as ‘the feasibility study’). In early 2015, TfNSW received the feasibility study, which was one of several key sources that informed the development of business cases for the PLR.

The feasibility study recommended that TfNSW should consolidate the maintenance and cleaning operations with overnight stabling facilities on one site. The study noted that the optimal location for any such site would be in close proximity to the proposed network, and noted that the site must have access to road connections to accommodate access for cars and trucks.

The study found that a centrally located stabling and maintenance facility would be required for all routes serving the Parramatta CBD, and that the Camellia industrial area was a preferred location for such a facility. The study noted that the Camellia area was contaminated.

The feasibility study notes that its conclusions were based on assumptions about the light rail system adopted and decisions made by the future operator of the system, who had not yet been selected or appointed.

TfNSW's decision to progress a potential acquisition in 2015 considered the risk that the site may not be required

TfNSW's FIC was responsible for making decisions on funding allocations at a whole of program level within TfNSW. FIC was also responsible for approving ‘high-risk/high-value’ variations to program budgets. Members of the FIC included:

  • Secretary of Transport for NSW
  • Deputy Secretary, Infrastructure and Services
  • Deputy Secretary, Freight, Strategy and Planning
  • Deputy Secretary, Customer Services
  • Deputy Secretary Finance and Investment
  • Deputy Secretary People and Corporate Services.

An April 2015 submission, from the then Deputy Director-General to the agency’s FIC, sought authorisation and funding approval to participate in an Expression of Interest sale process. It noted the risk that the project may not go ahead. The submission advised that:

By acquiring a strategic site now, it reduces the risk of having to pay an improved value or a value that may be subject to rapidly improving land values due to changes in land use and rezoning.

The property can be acquired for the project, held strategically and income generated by leasing the site as hardstand 1 space until the project requires the land for the Parramatta Light Rail project.

If the project does not proceed in the medium to longer term, the property can be sold at a premium to what has been paid today as property fundamentals improve.

This submission acknowledged the risks associated with environmental contamination and proposed that these risks would be managed by negotiating a contract where the remediation and associated expenses would be at the landowner’s cost. 

TfNSW assessed the 4–6 Grand Avenue site as one of several sites in Camellia that was a feasible location for a stabling and maintenance facility

The Departmental feasibility study assessed six potential sites for a stabling and maintenance facility, including 4–6 Grand Avenue, noting strengths and weaknesses of each site. A different site on Grand Avenue was assessed as the ‘base case’ option (1 Grand Avenue). The study’s comments on the 4–6 Grand Avenue site included the following:

With an area of approximately 63,000m2, this site has sufficient space for a depot with the required stabling yard and maintenance facilities. The location allows for good road access and LRT [light rail transit] access would be from Grand Avenue, which may require a road crossing or signalised intersection. The site has been used for general industrial uses; however the land has been cleared and is currently undergoing remediation 2. The site is not affected by flooding based on one in 100-year flood data.

In early 2015, once the opportunity to acquire 4–6 Grand Avenue emerged, TfNSW commissioned a specific feasibility study of the 4–6 Grand Avenue site. The feasibility studies clearly documented the existence of environmental contamination. In April 2015, the report concluded:

Given the limitations of this report and within the parameters that have been set it is concluded that from a spatial and geographic perspective the site at 6 Grand Avenue would be suitable as a stabling and maintenance depot for the Parramatta light rail project. There are few engineering and environmental constraints that would affect the feasibility level analysis of this site and all issues identified, within this desk study, are considered to be resolvable. However this being said there is a significant amount of work necessary to reach the final layout and definition of the stabling and maintenance depot. There are numerous items which require further consideration and conformation; planning approvals could impose restrictions on building heights, noise mitigation measures, light and visual impact requirements all of which can have significant impacts on the spatial requirements of any stabling and maintenance depot. 

The acquisition of 4–6 Grand Avenue was not informed by a Property Acquisition Strategy

For major projects, TfNSW typically requires the project team to complete a Property Acquisition Strategy, which is intended to guide both process as well as specific acquisition issues expected to be faced during the project. The Property Acquisition Strategy is not a mandated document but is a recommended tool to support property acquisition as part of major projects.

TfNSW did not have a Property Acquisition Strategy in place to guide the 2015 Expression of Interest process. On 6 November 2015, the then Project Director for the PLR project emailed the property team, noting a need to develop a Property Acquisition Strategy to close off the scoping design and preliminary business case.

In January 2016, TfNSW developed a draft Property Acquisition Strategy for the Parramatta Light Rail Project, although it was silent on the potential sites for the stabling and maintenance facility.

TfNSW focussed on 4–6 Grand Avenue because it was available and aligned to TfNSW's strategic interests

In early 2015, officials commenced monitoring the market for industrial real estate in the Camellia area and surrounds for possible sites for a stabling and maintenance facility.

In March 2015, then owner of the site, Akzo Nobel Pty Limited released the 4–6 Grand Avenue site through an Expression of Interest process managed by CBRE.

TfNSW’s then Deputy Director-General, Planning, sought approval from FIC to lodge an Expression of Interest up to $30.0 million. Approval was sought on the basis that it would ‘provide certainty for the Parramatta Light Rail project by allowing for a depot site in a suitable location and potentially avoid higher costs or longer timeframes associated with compulsory acquisition following completion of the project’s business case’. FIC approved the request at its meeting on 9 April 2015.

At this time, TfNSW had not conducted any analysis of financial or operational benefits and costs of the potential sites identified in earlier feasibility studies. TfNSW staff advised us that the decision to participate in the Expression of Interest process for 4–6 Grand Avenue was because it was available. There is no documentation substantiating this statement, which TfNSW staff provided verbally as part of this audit.

In November 2015, TfNSW was advised that it was unsuccessful in the Expression of Interest process and that Grand 4 Investments (a related entity of Billbergia) had purchased 4–6 Grand Avenue. TfNSW did not conduct any further analysis of alternative potential sites in Camellia between this date and commencing discussions with Grand 4 Investments in April 2016. In that time there had been some movement on other properties that were included in the feasibility study, including 37–39a Grand Avenue being under offer in September 2015.

In March 2016, TfNSW approached CBRE to organise a meeting with Grand 4 Investments. On 1 April 2016, TfNSW met with Grand 4 Investments.

TfNSW advises that a perceived benefit of the 4–6 Grand Avenue site was that it was not subject to other uses or leaseholds that would increase the cost of compulsory acquisition. Officers involved in the acquisition advised that other nominated sites in the feasibility study were subject to other uses or leaseholds. 


1  A hardstand space is a large, paved area to store cars, heavy vehicles and machinery.
2  Officers familiar with the acquisition could not confirm the nature of remediation being undertaken, but noted that the previous landowner had cleared buildings from the site, which may have been considered part of remediation.
TfNSW's independent valuation, which it commissioned and received after the acquisition, specifically excluded consideration of environmental contamination risk. As a result, TfNSW is exposed to the risk that the acquisition was not fully compliant with the Land Acquisition (Just Terms Compensation) Act 1991 (the Act) because it did not use an accurate estimate of market value during negotiations. That said, the acquisition of 4–6 Grand Avenue by agreement was consistent with preferred processes described in the Act.

TfNSW acquired the site from the landowner by agreement, and this is consistent with provisions in the Act. Obtaining approval for compulsory acquisition should negotiations for agreement break down is also consistent with the Act. That said, TfNSW did not at any time assess whether a compulsory acquisition could have resulted in acquisition at a lower cost than what was negotiated by agreement.

Despite the high risks associated with the acquisition, TfNSW did not commission a formal valuation in time to inform the negotiation and purchase. Instead, TfNSW relied on internal advice to estimate market value, but did not obtain a formal valuation from those advisors. For high-risk transactions, the greater expertise and arm's-length independence of an external specialist valuer should be preferred over an agency's own staff.

On 15 June 2016, the settlement date for the acquisition, TfNSW commissioned a formal independent valuation of the site. On 23 November 2016, TfNSW received the final formal valuation report. By not obtaining a formal independent valuation of the property in advance of acquisition to inform the acquisition value, TfNSW exposed itself to non-compliance with the Act by not establishing the market value as the basis for the acquisition price. TfNSW also breached its own internal policies.

TfNSW instructed the valuer to conduct its valuation within the following parameters:

  • Market valuation on an ‘as is’ basis – market value based on the methodology described in the Act. This approach valued the site at $25.0 million.
  • Market valuation on a speculative development basis – market value based on the financial value of the vendor's intended use of the site which, in this case, involved leasing the site for industrial use. This approach valued the site at $52.0 million, and TfNSW advised us this valuation supported the purchase price.
  • Disregard the impact of environmental contamination – TfNSW specifically instructed the independent valuer to disregard any known (or unknown) site contamination. As TfNSW knew of the significant environmental contamination affecting the site, this parameter resulted in a valuation that overstated the value of the site as it did not consider the cost of environmental remediation. The valuer applied this assumption for both market valuation approaches.

Additionally, as the independent valuer completed the valuation after the purchase was finalised, there is a risk that the valuation may have been influenced by the known purchase price.

TfNSW's failure to acquire a formal valuation and an assessment of the financial impact of environmental remediation before it purchased 4–6 Grand Avenue represents ineffective administration and governance.
TfNSW acquired the site at a time when there was demand and increasing prices for industrial property in the area. However, TfNSW did not effectively assess and manage the risks associated with the acquisition, and gaps in process led to increased risk. Briefings to decision-makers did not contain important information, and we found no evidence that gaps in advice were queried or explored by decision-makers.

TfNSW did not have plans or advice in place to assist in managing risk, such as:

  • a property acquisition plan
  • a comprehensive and up-to-date risk management plan
  • a negotiation strategy, or any authorisation limit or minimal acceptable position
  • an independent professional evaluation
  • external expert advice (with the exception of legal advice relating to the contract of sale).

TfNSW was aware of contamination issues affecting the land and had access to considerable information about the environmental conditions, such as site environmental audit reports and information on the NSW Environment Protection Authority's contaminated land register. However, TfNSW had not analysed specific technical information about the contamination and therefore was not aware of the risk implications and cost for remediation. Despite this, TfNSW changed its position from not accepting the risks and costs of contamination, to acquiring the site unconditionally. The basis for this decision is unclear and undocumented.

Briefing to senior leaders on the acquisition was silent on a number of important matters that would have been important for approvers to consider, including:

  • an explanation of the 40 per cent increase in purchase price between November 2015 and May 2016, and a 165 per cent increase from TfNSW’s offer in April 2015
  • the contamination risks associated with the site and an evidence-based estimate of potential costs to remediate the site
  • advice that an independent valuation had not been obtained, inconsistent with TfNSW policy.

Consideration of the acquisition by FIC was based on a summary business paper and was managed out-of-session, thereby removing the ability for comprehensive consideration of the acquisition proposal and its risks.

The probity management controls and assurances in place for the acquisition of the 4–6 Grand Avenue site were insufficient. These insufficiencies were exacerbated by the probity risk profile of the transaction.

The 4–6 Grand Avenue acquisition was a high-risk/high-value transaction, undertaken in a volatile property market in a short timeframe under pressure from Grand 4 Investments. TfNSW was engaging in a direct negotiation in advance of detailed planning for the acquisition, or the PLR as a whole. These circumstances contribute to heightened probity risk.

TfNSW did not establish a probity plan and sought no probity support throughout the acquisition. Also, with one exception, the staff involved in the acquisition did not complete conflict of interest declarations.

TfNSW was aware of the potential for probity or integrity issues with the transaction when it commissioned an internal audit in connection with the transaction in 2019. Internal discussions considered whether a misconduct investigation may be more appropriate, however no such investigation was undertaken.

TfNSW's insufficient probity practices, in addition to its failure to keep complete or comprehensive records of negotiations or decisions, reduce transparency of the process and its outcome and expose TfNSW to a greater risk of misconduct, corruption and maladministration.

At the time of the transaction, the TfNSW policy framework was not sufficiently risk-focussed and did not provide clarity on when officers ought to apply specific guidance or procedures. TfNSW's policies and procedures are more focussed on acquiring land to meet project needs and timeframes, and less on assuring value for money and managing risks.

At the time of its acquisition of 4–6 Grand Avenue, TfNSW had property acquisitions policies and procedures in place. Each of these were broadly sound in their content and intent. However, they lacked specificity on how or when to apply guidance, and when risk levels should elevate the importance of recommended guidance.

TfNSW's key guidance was principles based and relied on agency staff using their experience and expertise to apply guidance according to the circumstances of an individual transaction. This guidance was not duly applied in the acquisition of 4–6 Grand Avenue, Camellia. In addition, TfNSW does not have quality or control assurance to identify when TfNSW officers did not apply important policies or processes.

The primary focus of the TfNSW’s property acquisition guidance is to achieve vacant possession of land in a timeframe that meets the need of the relevant transport project. There is less specific focus on the need to meet the requirements of the NSW Government financial management framework.

Appendix one – Response from agency 

Appendix two – About the audit 

Appendix three – Performance auditing

 

Copyright Notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #349 - released (18 May 2021).

Published

Actions for Transport 2020

Transport 2020

Transport
Asset valuation
Cyber security
Financial reporting
Information technology
Infrastructure
Project management

1. Financial Reporting

Audit opinion Unmodified audit opinions issued for the financial statements of all Transport cluster entities.
Quality and timeliness of financial reporting All cluster agencies met the statutory deadlines for completing the early close and submitting the financial statements.

Transport cluster agencies continued to experience some challenges with accounting for land and infrastructure assets. The former Roads and Maritime Services and Sydney Metro recorded prior period corrections to property, plant and equipment balances.
Impact of COVID-19 on passenger revenue and patronage Total patronage and revenue for public transport decreased by approximately 18 per cent in 2019–20 due to COVID-19.

The Transport cluster received additional funding from NSW Treasury during the year to support the reduced revenue and additional costs incurred such as cleaning on all modes of public transport and additional staff to manage physical distancing.
Completion of the CBD and South East Light Rail The CBD and South East Light Rail project was completed and commenced operations in this financial year. At 30 June 2020, the total cost of the project related to the CBD and South East Light Rail was $3.3 billion. Of this total cost, $2.6 billion was recorded as assets, whilst $700 million was expensed.

2. Audit Observations

Internal control While internal controls issues raised in management letters in the Transport cluster have decreased compared to the prior year, control weaknesses continue to exist in access security for financial systems. We identified 56 management letter findings across the cluster and 43 per cent of all issues were repeat issues. The majority of the repeat issues relate to information technology controls around user access management.

There were three high risk issues identified - two related to financial reporting of assets and one for implementation of TAHE (see below).
Agency responses to emergency events Transport for NSW established the COVID-19 Taskforce in March 2020 to take responsibility for the overall response of planning and coordination for the Transport cluster. It also implemented the COVIDSafe Transport Plan which incorporates guidance on physical distancing, increasing services to support social distancing and cleaning.
RailCorp transition to TAHE On 1 July 2020, RailCorp was renamed Transport Asset Holding Entity of New South Wales (TAHE) and converted to a for-profit statutory State-Owned Corporation. TAHE is a commercial for-profit Public Trading Entity with the intent to provide a commercial return to its shareholders.

A plan was established by NSW Treasury to transition RailCorp to TAHE which covered the period 1 July 2015 to 1 July 2019. A large portion of the planned arrangements were not implemented by 1 July 2020. As at the time of this report, the TAHE operating model, Statement of Corporate Intent (SCI) and other key plans and commercial agreements are not finalised. The State Owned Corporations Act 1989 generally requires finalisation of an SCI three months after the commencement of each financial year. However, under the Transport Administration Act 1988, TAHE received an extension from the voting shareholders, the Treasurer and Minister for Finance and Small Business, to submit its first SCI by 31 December 2020. In accordance with the original plan, interim commercial access arrangements were supposed to be in place with RailCorp prior to commencement of TAHE.

Under the transitional arrangements, TAHE is continuing to operate in accordance with the asset and safety management plans of RailCorp. The final operating model is expected to include considerations of safety, operational, financial and fiscal risks. This should include a consideration of the potential conflicting objectives of a commercial return, and maintenance and safety measures.

This matter has been included as a high risk finding in our management letter due to the significance of the financial reporting impacts and business risks for TAHE.

Recommendation: TAHE management should:
  • establish an operating model in line with the original intent of a commercial return
  • finalise commercial agreements with the public rail operators
  • confirm forecast financial information to assess valuation of TAHE infrastructure
  • finalise asset and safety management plans.

Resolution of the above matters are critical as they may significantly impact the financial reporting arrangements for TAHE for 2020–21, in particular, accounting policies adopted as well as measurement principles of its significant infrastructure asset base.

Completeness and accuracy of contracts registers Across the Transport cluster, contracts and agreements are maintained by the transport agencies using disparate registers.

Recommendation (repeat): Transport agencies should continue to implement a process to centrally capture all contracts and agreements entered. This will ensure:
  • agencies are fully aware of contractual and other obligations
  • appropriate assessment of financial reporting implications
  • ongoing assessments of accounting standards, in particular AASB 16 ‘Leases’, AASB 15 'Revenue from Contract with Customers', AASB 1058 'Income of Not-for-Profit Entities' and new accounting standard AASB 1059 'Service Concession Arrangements: Grantors' are accurate and complete.

 

This report provides parliament and other users of the Transport cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations
  • the impact of emergencies and the pandemic.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Transport cluster for 2020, including any financial implications from the recent emergency events.

Section highlights

  • Total patronage and revenue for public transport decreased by approximately 18 per cent in 2019–20 due to COVID-19.
  • Unqualified audit opinions were issued on all Transport agencies' financial statements.
  • Transport cluster agencies continued to experience challenges with accounting of land and infrastructure assets.

 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our:

  • observations and insights from our financial statement audits of agencies in the Transport cluster
  • assessment of how well cluster agencies adapted their systems, policies and procedures, and governance arrangements in response to recent emergencies.

Section highlights

  • While there was a decrease in findings on internal controls across the Transport cluster, 43 per cent of all issues were repeat issues. Many repeat issues related to information technology controls around user access management.
  • RailCorp transitioned to TAHE on 1 July 2020. TAHE's operating model and commercial arrangements with public rail operators has not been finalised despite government original plans to be operating from 1 July 2019. TAHE management should finalise its operating model and commercial agreements with public rail operators as they may significantly impact the financial reporting arrangements for TAHE for 2020–21.
  • Completeness and accuracy of contracts registers remains an ongoing issue for the Transport cluster.

Appendix one – List of 2020 recommendations

Appendix two – Status of 2019, 2018 and 2017 recommendations

Appendix three – Management letter findings

Appendix four – Financial data

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Managing the health, safety and wellbeing of nurses and junior doctors in high demand hospital environments

Managing the health, safety and wellbeing of nurses and junior doctors in high demand hospital environments

Health
Internal controls and governance
Management and administration
Workforce and capability

The Auditor-General for New South Wales, Margaret Crawford, released a report today examining NSW Health’s management of health and safety risks to nurses and junior doctors in high demand hospital wards over the past five years, including during the first six months of the 2020 COVID-19 health emergency.

The Auditor-General found that while NSW Health effectively managed most incidents and risks to the physical health and safety of hospital staff during ‘business as usual’ activities, systems and resources are not fully effective to manage staff psychological and wellbeing risks, particularly for nurses.

The Auditor-General found that NSW Health was effective in managing most COVID-19 health and safety risks to hospital staff. Overall effectiveness could have been improved had pandemic preparedness training been delivered across all Local Health Districts. Additionally, state-wide communication systems could have been improved to provide hospital clinicians with access to a ‘single source of truth’ with the latest advice from NSW Health authorities.

NSW Health’s planning and preparation for the supply of Personal Protective Equipment (PPE) was partially effective. At various times, some PPE items could not be sourced from established suppliers. Face masks, goggles and protective gowns were substituted with products that differed in shape, size and fitting from usual items, and in some hospitals, substituted masks were used without being locally fit tested by hospital staff.

The Auditor-General made seven recommendations aimed at enhancing hospital health and safety risk reporting practices, along with a recommendation that NSW Health conduct a post pandemic 'lessons learned' review and make policy and operational recommendations for future pandemic responses.

Over the past decade, there have been increases in the numbers of health and safety incidents affecting nurses and junior doctors in NSW hospitals. These increases have been associated with higher numbers of patients with acute mental health conditions, age-related cognitive impairments, and patients presenting in emergency departments under the influence of drugs and alcohol.  

This audit commenced in August 2019, with a focus on the health, safety and wellbeing of nurses and junior doctors in high demand hospital wards. Our audit focused on emergency departments, mental health wards and aged care wards during 'business as usual’ periods of hospital operations. 

In the early months of 2020, the novel coronavirus (COVID-19) brought new health and safety risks to hospital staff. These risks included the potential for infection amongst health workers, increased staff workloads, and impacts on staff wellbeing.  

In May 2020, we expanded the focus of the audit to assess the effectiveness of NSW Health’s management of the health and safety risks to staff during the COVID-19 health emergency. We assessed the impacts on emergency departments and intensive care units, as these were the wards where staff were most likely to come into contact with COVID-19.  

The Audit Office acknowledges the ongoing health and safety challenges that the pandemic has brought to NSW Health staff – in particular to hospital clinicians and the managers who support them.  

This audit assessed the effectiveness of NSW Health’s:

  • systems, forums and workplace cultures to support reporting and generate data about risk
  • initiatives to support safe workplaces and effectively respond to health and safety incidents
  • actions to continuously improve staff health, safety and wellbeing in hospital environments.

The first three chapters of this report describe the effectiveness of NSW Health’s ‘business as usual’ health and safety risk management. The fourth and fifth chapters describe the effectiveness of NSW Health’s health and safety risk management during the COVID-19 pandemic.  

Conclusion
NSW Health’s management of health and safety risks in NSW hospitals

NSW Health is effectively monitoring and managing most incidents and risks to the physical health and safety of nurses and junior doctors in NSW hospitals. However, systems and resources are not fully effective across all Local Health Districts for monitoring or managing psychological and wellbeing risks - particularly in relation to nurses.

NSW Health’s incident management system is effective for recording health and safety incidents in hospital wards where incidents occur infrequently, and staff have time to log incident details during shift hours. However, in high demand wards where incidents and risks are common, staff report that they are unable to log all incidents due to the frequency of events, and the time it takes to record incidents in the system.

NSW Health is taking reasonable steps to manage and respond to physical health and safety incidents in NSW hospitals, but psychological and wellbeing risks and incidents are not routinely recorded or escalated to managers. Stress debriefing is not consistently available to staff after difficult or traumatic workplace incidents.

The Ministry of Health could improve its information sharing and data reporting on state-wide health and safety risks in NSW hospitals, and communicate risk trends to the wider NSW health system. This would assist managers to identify common health and safety issues, and target their responses. The Ministry has not set up systems or strategies to identify or support the expansion of successful health and safety initiatives across the NSW health system.

NSW Health’s management of health and safety risks associated with COVID-19

To date, NSW Health has effectively managed most COVID-19 related health and safety risks to hospital staff. The overall effectiveness of NSW Health's preparations and responses to COVID-19 could have been improved in the early phases of the health emergency - from January to early April 2020 - by ensuring that hospital staff in all Local Health Districts had access to pandemic training, that all emergency response policies had been updated and circulated, that state-wide communication systems were able to be rapidly upscaled to deliver consistent messages to hospital staff across the health system, and that PPE supply lines could provide sufficient stock to meet requirements during all pandemic response phases.

Local Health District executives and hospital managers effectively guided and supported nurses and junior doctors to manage and minimise most COVID-19 health and safety risks in hospital environments. However, communication with frontline staff could have been improved in the early stages of the pandemic. The Ministry did not set up a centralised communication channel to communicate consistent messages and advice to hospital clinicians until April 2020. This finding is consistent with a finding from the 2009 review into NSW Health’s response to the H1N1 influenza outbreak. Clinical staff advised that the lack of a centralised communication channel, substantially increased their workloads as they checked numerous sources for the latest and most authoritative advice.

Prior to COVID-19, pandemic response training was limited across the NSW Health system. Nurse managers of emergency departments and intensive care units reported that there was limited training or familiarisation with the NSW Pandemic Plan. Key policies describing infection control principles for emergency departments and intensive care units were outdated and had not been revised within required timelines.

NSW Health's planning and preparation for the supply and management of personal protective equipment (PPE) has been partially effective, with PPE available to hospital staff at all times. However, at various intervals, some PPE could not be sourced from established suppliers. Face masks, goggles and protective gowns were substituted with products that differed in shape, size and fitting, from the usual PPE stock. Staff reported that in the early stages of the pandemic, substituted masks were not locally fit tested by hospital staff in some emergency departments.

1. Audit recommendations

By December 2021, NSW Health should:

  1. Evaluate the effectiveness of the new incident management system to enable full reporting of health and safety incidents and risks in all hospital wards, including those where incidents and risks are common, and monitor for consistency of reporting over time
  2. Expand the categories of hospital incident data reported to Ministry executives in the Work Health and Safety Dashboard reports, including by linking injury data to incident types by hospital ward category, and monitor in conjunction with Local Health Districts for emerging trends and improvement over time
  3. Ensure that nurses and junior doctors have regular opportunities to report on risks to their psychological health and wellbeing, and that system managers have access to aggregate data to guide responses to mitigate these risks
  4. Develop and implement an evidence-based guiding framework and strategy to support hospital staff in the aftermath of traumatic or unexpected workplace incidents, and monitor implementation
  5. At regular intervals, publicly report aggregate Root Cause Analysis data detailing the hospital system factors that contribute to clinical incidents
  6. Develop and implement a systemwide platform for sharing research and information about hospital health and safety initiatives across the health system
  7. Conduct a post-pandemic 'lessons learned' review focusing on the effectiveness of key strategies deployed in the management of the COVID-19 pandemic and make policy and operational recommendations for future pandemic responses. In particular, ensure:
    • regular scenario-based pandemic training for hospital staff
    • updated policies and protocols for hospital infection controls
    • capability to upscale authoritative communication with frontline health workers at the earliest notification of a health emergency and for the duration of the emergency
    • systems and safeguards to ensure the supply and availability of clinically appropriate personal protective equipment (PPE) during all phases of a pandemic.

Local Health Districts were effective in leading health and safety infection control activity

According the NSW Health Influenza Pandemic Plan (Pandemic Plan), the Chief Executives of Local Health Districts have ultimate responsibility for public health unit preparations during health emergencies. If necessary, they can ‘draw on the support of the State Pandemic Management Team and local emergency management resources’.

During the preparations and early response phases to the COVID-19 pandemic, Local Health Districts were at the forefront of most NSW hospital activity. They took the lead role in developing hospital infection control protocols and guidance about the appropriate uses of Personal Protective Equipment (PPE). Each Local Health District established its own responses to the health emergency, based on the best clinical advice available to them. The localised approach meant that there were some minor differences in infection control practices across the NSW health system.

Throughout February and March 2020, there was limited centralised policy or guidance from the Ministry and its Pillar Health agencies about COVID-19 infection control practices. It was not possible to mandate practices at a time when information about the virus was evolving. Clinical responses were changing as more became known about COVID-19, especially about its patterns of transmission and its impacts on people with the disease.

During February and March 2020, Local Health District executives communicated with hospital staff via a range of methods. Some sent daily e-memos with the latest updates. Some scheduled more regular meetings with hospital clinicians. Some Districts set up extensive staff training sessions and information briefings to keep all personnel updated with the latest advice. Physical distancing made it difficult to bring staff together in large groups, so a range of communications measures were implemented.

Clinical staff also utilised their clinical training and expertise to prepare their wards and train frontline staff in infection control procedures. Some sourced information from national and international colleagues to add to localised knowledge of the virus.

When the first evidence of COVID-19 community transmission was identified in the Northern Sydney Local Health District, hospital staff followed infection control protocols that were based on local guidance and information. With the support from the District executive team and infectious diseases experts, hospital clinicians set up their own infection control protocols and PPE protections. Within a week the District had produced a matrix to guide staff in the uses of PPE during COVID-19 procedures, and had circulated the guidance to all hospital clinicians.

At the end of March 2020, a version of the Northern Sydney PPE matrix was published on the Clinical Excellence Commission’s website and it has now become NSW Health’s standard guideline for PPE during COVID-19 procedures. Once this guideline was published centrally, infection control practices were standardised across NSW hospitals.

This form of District-led policy making is not ‘business as usual’ practice for NSW Health. Policy making processes were somewhat reversed during the early response phases to COVID-19. This flexible policy approach supports the governance arrangements described in the Pandemic Plan, which assigns responsibility for ‘supporting and maintaining quality care across health services and implementing infection control measures as appropriate’ to Local Health Districts.

In non-health emergency situations, clinical policy and protocols are usually initiated and developed by the Ministry and the Clinical Excellence Commission and are subsequently shared across the health system after a quality control process. The localised approach adopted in the months from February to March 2020, allowed for rapid and flexible responses to changing information – to protect the health and safety of the hospital workforce and the wider community.

Hospital staff across NSW would have been better prepared for COVID-19 if pandemic training had been delivered across all Local Health Districts in the past decade

Local Health Districts are responsible for training hospital staff in preparation for public health emergencies. NSW’s policy describing Public Health Emergency Response Preparedness Minimum Standards requires that clinical staff participate in at least one annual emergency training exercise if they hold a position where they are likely to be called upon in an emergency. Staff must participate in an actual response exercise or a relevant training session. The training must also include re-familiarisation with PPE.

Available evidence about emergency response training in NSW indicates that at least two Local Health Districts have delivered pandemic focussed training in the past decade. Our interviews with managers of emergency departments and intensive care units indicates that most other Districts have focused their emergency training on mass patient trauma incidents such as plane crashes, train crashes and terrorist attacks. While the potential for these types of mass trauma events is real, and warrants training and preparation, significant global outbreaks of diseases have also had potential to threaten NSW communities. In previous decades, global health communities have been at risk of diseases such as the Severe Acute Respiratory Syndrome (SARS) and Middle East Respiratory Syndrome (MERS).

In the two Districts where pandemic training was provided in NSW, staff participated in community influenza vaccination exercises. These were focused on upskilling staff to follow emergency command structures, manage high volume patient flows, and organise sanitisation logistics during a hospital-based training exercise.

Our interviews with nurse managers in emergency departments and intensive care units indicate that in the majority of other Local Health Districts, key personnel were unaware of the NSW Pandemic Plan. Interviewed staff also reported insufficient scenario-based training in pandemic responses over the last ten years.

The Ministry, the Clinical Excellence Commission and the Health Education and Training Institute (HETI) are responsible for online training and 'state-wide strategies and resources to maintain high levels of compliance with infection control and patient safety recommendations'. The HETI website contains online training modules in infection control and PPE donning and doffing procedures. Other infection control information and research is available on the websites of the Clinical Excellence Commission and the Agency for Clinical Innovation.

Online training modules are effective for upskilling staff in a range of skills, but are not a substitute for real-time, rapid incident response training. Face-to-face training provides opportunities for first responders to test procedures in hospital environments. Incident response training provides opportunities for staff to assess their levels of compliance with protocols and their competence with equipment in scenario situations. It is the responsibility of Local Health Districts to provide this form of training to the health staff in their District.

Two NSW Health policies that govern clinical arrangements during pandemics are outdated

The Ministry had not updated two policies that had the potential to assist emergency departments and intensive care units in aspects of their ward preparation for the COVID-19 pandemic. Both policies were on the NSW Health website, but neither were shared with hospital staff in the planning phases for the pandemic. Both policies are out of date and have not been revised within required timeframes.

The 2010 Influenza Pandemic - Providing Critical Care policy was due for review in May 2015 and was not updated at the time of the COVID-19 health emergency. Similarly, the 2007 policy Hospital Response to Pandemic Influenza Part 1: Emergency Department Response was due for review in June 2012 and has not been updated.

These policies were designed to assist clinical staff to make necessary ward arrangements for infection control. They set out the steps for rapid identification of contingent workforces, isolation procedures, and management of patient flows to separate those with suspected infection from other patient cohorts. They were a potential addendum to the NSW Pandemic Plan which describes the command and control responsibilities of health agencies in health emergencies.

Our interviews with nurse managers from emergency departments and intensive care units indicate that in the absence of pandemic policy, they sought clinical guidance from external sources and Local Health District experts. Interviewees told us that a lack of policy guidance about ward arrangements and infection control practices in a pandemic increased their workloads and hours of overtime in the early response phases to COVID-19. With the support of Local Health Districts, clinical staff made rapid adjustments in order to respond to changing testing requirements and ward arrangements.

The Ministry was slow to establish a centralised communication channel to communicate with frontline staff

NSW Health’s governance and communication arrangements during a pandemic are set out in the Pandemic Plan. The Plan requires that government agencies ‘commence enhanced arrangements, establish communications measures’ and confirm ‘governance arrangements’ when there is evidence of person to person transmission during an influenza outbreak. NSW Health received the first notifications of the novel coronavirus risks in January 2020.

During the preparation and early response phases to COVID-19, the Ministry and its central agencies were slow in establishing a single, authoritative channel through which to communicate consistent messages to frontline staff. Clinical staff required up-to-date information about COVID-19 testing criteria as requirements were changing rapidly, sometimes daily. While there was no expectation for fixed policy at this time, hospital staff required the latest instructions about treatment requirements, and updates on the numbers of COVID-19 infections in their region.

As information about COVID-19 was evolving, information was communicated across the health system via ‘multiple channels and sources’. While the Ministry and its central agencies communicated extensively with Local Health Districts during March 2020, hospital staff reported to us that they weren’t always sure where they could find the latest advice about testing protocols or infection controls.

Frontline staff told audit office staff that they were checking multiple sources and time-stamping advice to ensure they had the most up to date information on a daily basis. While some Local Health Districts managed clear communication links with frontline staff, nurse managers told us that communication was ‘chaotic’ during the early phases of pandemic preparation. Key personnel were not always available outside business hours and nurse managers advise that they spent hours at the end of shifts, seeking and printing the latest advice for weekend and night shift personnel. By the end of March 2020, the Ministry and the Clinical Excellence Commission websites became better organised to communicate with frontline clinicians.

A recommendation to the Ministry of Health after H1N1 swine flu could be equally applied in the COVID-19 context. The NSW Government’s report: Key Recommendations on Pandemic (H1N1) 2009 Influenza recommended the establishment of ‘clear pathways of communication … so that all employees have confidence in where their information will come from and who they should approach if they need additional information.’

NSW Health acknowledges the challenges and the lessons from the early phases of the COVID-19 pandemic. For example, a strategy released in August 2020, sets out NSW Health’s own recommendation for the future management of PPE including: ‘Aligning a single source of truth for PPE education and evidence-based guidance to ensure clarity of information on appropriate use, supported by an influential network of Infection Prevention and Control (IPC) practitioners at the forefront.

Ministry executives advise that communication with health staff has improved since the early phases of the pandemic. The Ministry now sends weekly COVID-19 updates to over 130,000 health staff via email. In addition, NSW Health now has two COVID-19 tabs on its website with current information, including COVID-19 testing advice. According to Ministry executives, these communication channels could be used or replicated if needed for future health emergencies. The Ministry also provides health information and updates via a phone application called Med App. This App is preferred by doctors and is less likely to be used by nurses. As at October 2020, there are 13,000 users of Med App. Push notifications can be made on Med App through SMS alerts.

Personal protective equipment (PPE) was not always available in required sizes and some hospital masks and gowns were substituted with products that differed from the usual items

Since the emergence of COVID-19 in Australia, all clinicians in NSW hospitals have had access to some form of PPE for their clinical requirements. If staff did not have appropriate equipment for each COVID-19 related procedure, they were guided by the formal advice issued to the NSW Health workforce on 11 March 2020 stating that: ‘The safety of NSW Health staff is a priority at all times, especially during COVID-19. Where safe working practices confirm specific PPE (e.g. face shields/masks or other equipment) are required for the protection of staff due to COVID-19, in all circumstances:

  • staff are to wear prescribed PPE as instructed
  • staff are not to undertake or be required to undertake tasks requiring PPE if the PPE is not available for use. Any such tasks are not to proceed until required PPE is available
  • any staff member who is concerned about their safety must raise their concerns immediately to their manager.’

At periods during March and April 2020, some PPE items were not available in the required sizes or the regular brands to which staff were accustomed. HealthShare NSW was not able to source PPE from usual suppliers. HealthShare NSW sourced PPE including N95 masks from non-traditional suppliers. Some PPE items differed in shape and size from the usual hospital equipment. While senior executives from HealthShare NSW advise that all products were approved by the Therapeutic Goods Administration (TGA), in some hospitals, nurse managers advise that staff were not able to ‘fit test’ substituted masks. Fit testing determines the type and the size of the respirator mask that achieves an adequate seal on an individual’s face.

In March and April 2020, ‘duck bill’ (N95) masks were not available in some hospitals. According to stock managers and clinical managers in Local Health Districts, duck bills are the preferred mask for staff with smaller faces, particularly female staff members. The duck bill mask is a standard PPE product, and as such, is fit tested during mandatory PPE training. During the early response phases to COVID-19, most Local Health Districts were provided with substitute N95 masks. Fit testing of the substituted N95 masks was not able to be conducted in all NSW hospitals during the early phases of COVID-19. During the first wave of COVID-19 in March and April 2020, hospital staff told audit staff that there was no time and a lack of equipment to appropriately fit test substituted N95 masks.

Nurse managers in emergency departments advise that in some instances, staff made adaptations to PPE to improve protections, such as doubling masks, adding elastics or bringing their own equipment. These adaptations were not consistent with guidelines. Nurse managers advise that in some cases, adaptations to PPE or ill-fitting masks created pressure sores and contact dermatitis. Just over half of the stock managers of Local Health Districts advised that PPE stock was procured from outside the HealthShare NSW system. Stock managers in some Districts advise that facial shields and goggles sourced from non-traditional suppliers by HealthShare NSW were of a lesser quality than standard equipment. Stock managers and nurse managers reported that the changes in PPE products caused confusion and stress amongst staff.

Local Health Districts were proactive in assisting hospital staff to mitigate risks of COVID-19 infections. Some Local Health Districts assigned ‘tiger teams’ to assist staff with their PPE practices. Tiger teams provide clinical expertise and advice to staff, answer questions about infection control and provide training on PPE practice in hospital ward environments. They assist and support PPE donning and doffing practices to ensure the appropriate sequencing of applying and removing PPE for effective infection control. They provide mask fit checking guidance to assist staff in correct PPE practices.

Districts ran extensive refresher PPE training sessions for clinical staff. Some hospitals ran regular PPE demonstrations so that staff could observe correct PPE procedures at set times during the day. These activities assisted staff to implement appropriate infection control in the period before the Clinical Excellence Commission’s web-based materials and videos became available in late March and early April 2020. These online resources now provide comprehensive guidance to hospital staff in PPE practices.

HealthShare NSW placed limits or caps on some high-demand PPE items that were too low to meet requirements in some Local Health Districts and had to be adjusted to meet actual demand

The NSW Pandemic Plan describes the responsibilities of the Ministry and its central agencies to manage and maintain the State Medical Stockpile of essential PPE supplies and antiviral medications. During a pandemic, HealthShare NSW has responsibility for warehousing, monitoring and distributing health supplies to the health workforce.

Due to a reported global shortage of PPE and limits to the NSW stockpile, HealthShare NSW placed limits on the provision of approximately 100 high-demand items to NSW hospitals. HealthShare NSW advise that the PPE order capping ceilings were implemented ‘to ensure local stockpiling does not occur’. A centralised ordering process was established with Local Health Districts so that PPE product ordering occurred through single hospital locations (214 across the State), rather than at the ward level. Escalation processes were established to allow Districts to request one-off increases to supply, and a process was set up to permanently increase the order cap limit for any PPE item by facility.

According to HealthShare NSW, ‘as incoming central supply has improved, order caps have subsequently increased in line with strong engagement and governance with the Local Health Districts to ensure the appropriate levels of supply are provided’. The original capped levels were determined by assessing PPE usage in wards during the flu season of 2019. As the flu season case numbers of 2019 were relatively low, some Local Health District managers advised that the levels of PPE during 2019 were not comparable to the level of PPE required for the COVID-19 pandemic.

After advocacy from hospital stock managers and clinicians, HealthShare NSW increased capped PPE levels in many Local Health Districts.

Executive members of the State Health Emergency Operations Centre (SHEOC) advise that its PPE supply strategy needs to be carefully developed as there are vast differences in PPE usage rates during 'business as usual' periods and pandemic periods. If NSW Health kept the level of PPE required in planning for a worst-case scenario, this would equate to an extensive surplus of PPE that could not be utilised during business as usual periods. The SHEOC Executive advise that it is not feasible or economical to store this level of PPE. They advise that given the costs of PPE, and the fact that the products have a shelf life, a diversified supply line is a more reliable method for ensuring PPE during surge and non-surge periods.

Early data modelling showed ICU patient numbers at levels not manageable with levels of ventilators and equipment

Early projections of patient numbers requiring acute care for COVID-19, were at levels that would not have been manageable with the equipment and resources of NSW hospitals. Throughout March through to May 2020, government data modelling indicated significant surges of community infections and surges in intensive care patients.

Early estimates were based on overseas trends, and if actual cases had matched projections, NSW hospitals would not have had sufficient ventilators to meet demand. The knowledge of this shortfall caused high levels of anxiety among nursing and medical staff.

While the data was based on the best available information, it had negative implications for the health and safety of the nurse and junior doctor workforce. Managers of intensive care wards and emergency departments reported stress amongst the workforce. Staff concerns were primarily about being faced with ‘the unmanageable’, along with heightened fears about contracting the virus with the knowledge that there was insufficient equipment to treat acute patients.

As it transpired, overall numbers of COVID-19 infections were lower than projected during the early months of the pandemic. The lower infection rates in the general population have meant fewer instances of patients requiring intensive care in NSW hospitals. In addition, HealthShare NSW has been able to increase the numbers of ventilators in NSW hospitals to prepare for future surges in patients requiring acute respiratory care.

SHEOC Executive advise that NSW Health undertook an accelerated procurement strategy in early 2020 to increase its stock of ventilators, and that ventilator capacity has always far-exceeded actual requirements.

NSW Health has developed a strategy to improve the management of PPE for the NSW health workforce

In August 2020, NSW Health released a strategy that sets out its future management and planning approaches to the provision of PPE for the NSW Health workforce. NSW Health’s Personal Protective Equipment (PPE) Strategy describes the learnings and challenges during the COVID-19 pandemic in sourcing and distributing PPE. It sets out the systems and methods for distributing PPE to staff and patients and focuses on how staff are kept informed on the appropriate use of PPE at all times. A supporting communications strategy has been developed to support its implementation.

The strategy contains enhanced transparency measures to regularly inform staff about PPE stock levels and to provide data about PPE usage rates by item types in wards in NSW hospitals. The NSW Health PPE strategy describes a changed approach to ordering, storing and allocating PPE. This includes diversifying the supply lines for PPE products to increase supply options in circumstances where supply lines become disrupted. It includes a centralised system for coordinating the supply of hospital PPE through Local Heath District coordination points and centralised distribution points in large hospitals.

Our interviews with hospital PPE stock managers and nurse managers indicate that staff find the new ordering system to be an improvement upon the previous stock ordering method.

According to the Personal Protective Equipment (PPE) Strategy, NSW health is upgrading its models for monitoring and benchmarking PPE usage across the health system. Systems are being improved for forecasting demand volumes during business as usual periods and during health emergency surges.

Appendix one – Response from agency

Appendix two – Audit methodology

Appendix three – About the audit 

Appendix four – Performance auditing 

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #344 - released 9 December 2020

Published

Actions for Internal controls and governance 2020

Internal controls and governance 2020

Education
Environment
Community Services
Finance
Health
Industry
Justice
Premier and Cabinet
Transport
Treasury
Compliance
Cyber security
Information technology
Internal controls and governance
Management and administration
Procurement

The Auditor-General for New South Wales, Margaret Crawford today released her report on the findings and recommendations from the 2019–20 financial audits that relate to internal controls and governance at 40 of the largest agencies in the NSW public sector.

The bushfire and flood emergencies and the COVID‑19 pandemic continue to have a significant impact on the people and public sector of New South Wales. The scale of the government response to these events has been significant. The report focuses on the effectiveness of internal controls and governance processes, including relevant agencies’ response to the emergencies. In particular, the report focuses on:

  • financial and information technology controls
  • business continuity and disaster recovery planning arrangements
  • procurement, including emergency procurement
  • delegations that support timely and effective decision-making.

Due to the ongoing impact of COVID‑19 agencies have not yet returned to a business‑as‑usual environment. ‘Agencies will need to assess their response to the recent emergencies and update their business continuity, disaster recovery and other business resilience frameworks to reflect the lessons learnt from these events’ the Auditor-General said.

The report noted that special procurement provisions were put in place to allow agencies to better respond to the COVID-19 pandemic. The Auditor-General recommended agencies update their procurement policies to reflect the current requirements of the NSW Procurement Framework and the emergency procurement requirements.

Read the PDF report

This report analyses the internal controls and governance of 40 of the largest agencies in the NSW public sector for the year ended 30 June 2020. These 40 agencies constitute an estimated 85 per cent of total expenditure for all NSW public sector agencies.

1. Internal control trends
New, repeat and high risk findings

Internal control deficiencies increased by 13 per cent compared to last year. This is predominately due to a seven per cent increase in new internal control deficiencies and 24 per cent increase in repeat internal control deficiencies. There were ten high risk findings compared to four last year.

The recent emergencies have consumed agency time and resources and may have contributed to the increase in internal control deficiencies, particularly repeat deficiencies.

Agencies should:

  • prioritise addressing high-risk findings
  • address repeat internal control deficiencies by re-setting action plans and timeframes and monitoring the implementation status of recommendations.
Common findings

A number of findings remain common across multiple agencies over the last four years, including:

  • out of date or missing policies to guide appropriate decisions
  • poor record keeping and document retention
  • incomplete or inaccurate centralised registers or gaps in these registers.
2. Information technology controls
IT general controls

We found deficiencies in information security controls over key financial systems including:

  • user access administration deficiencies relating to inadequate oversight of the granting, review and removal of user access at 53 per cent of agencies
  • privileged users were not appropriately monitored at 43 per cent of agencies
  • deficient password controls that did not align to the agency's own password policies at 25 per cent of agencies.

The deficiencies above increase the risk of non-compliance with the NSW Cyber Security Policy, which requires agencies to have processes in place to manage user access, including privileged user access to sensitive information or systems and remove that access once it is not required or employment is terminated.

3. Business continuity and disaster recovery planning
Assessing risks to business continuity and Scenario testing

The response to the recent emergencies and the COVID-19 pandemic has encompassed a wide range of activities, including policy setting, on-going service delivery, safety and availability of staff, availability of IT and other systems and financial management. Agencies were required to activate their business continuity plans in response, and with the continued impact of COVID-19 have not yet returned to a business-as-usual environment.

Our audits focused on the preparedness of agency business continuity and disaster recovery planning arrangements prior to the onset of the COVID-19 pandemic.

We identified deficiencies in agency business continuity and disaster recovery planning arrangements. Twenty-three per cent of agencies had not conducted a business impact analysis (BIA) to identify critical business functions and determine business continuity priorities. Agencies can also improve the content of their BIA. For example, ten per cent of agencies' BIAs did not include recovery time objectives and six per cent of agencies did not identify key IT systems that support critical business functions. Scenario testing improves the effectiveness with which a live crisis is handled, but 40 per cent of agencies had not conducted a business continuity scenario testing exercise in the period from 1 January 2019 to 31 December 2019. There were also opportunities to improve the effectiveness of scenario testing exercises by:

  • involving key dependent or inter-dependent third parties who support or deliver critical business functions
  • testing one or more high impact scenarios identified in their business continuity plan
  • preparing a formalpost-exercise report documenting the outcome of their scenario testing.

Agencies have responded to the recent emergencies but addressing deficiencies will ensure agencies have adequate safeguards in their processes to again respond in the future, if required.

During 2020–21 we plan to conduct a performance audit on 'Business continuity and disaster recovery planning'. This audit will consider the effectiveness of agency business continuity planning arrangements to maintain business continuity through the recent emergencies and/or COVID-19 pandemic and return to a business-as-usual environment. We also plan to conduct a performance audit on whole-of-government 'Coordination of emergency responses'.

Responding to disruptions

We found agencies' governance functions could have been better informed about responses to disruptive incidents that had activated a business continuity or disaster recovery response between 1 January 2019 to 31 December 2019. For instance:

in 89 per cent of instances where a business continuity response was activated, a post-incident review had been performed. In 82 per cent of these instances, the outcomes were reported to a relevant governance or executive management committee

in 95 per cent of instances where a disaster recovery response was activated, a post incident review had been performed. In 86 per cent of these instances, the outcomes were reported to a relevant governance committee or executive management committee.

Examples of recorded incidents included extensive air quality issues and power outages due to bushfires, system and network outages, and infected and hijacked servers.

Agencies should assess their response to the recent emergencies and the COVID-19 pandemic and update business continuity, disaster recovery and other business resilience frameworks to incorporate lessons learned. Agencies should report to those charged with governance on the results and planned actions.

Management review and oversight Eighty-two per cent and 86 per cent of agencies report to their audit and risk committees (ARC) on their business continuity and disaster recovery planning arrangements, respectively. Only 18 per cent and five per cent of ARCs are briefed on the results of respective scenario testing. Briefing ARCs on the results of scenario testing exercises helps inform their decisions about whether sound and effective business continuity and disaster recovery arrangements have been established.
4. Procurement, including emergency procurement
Policy framework

Agency procurement policies did not capture the requirements of several key NSW Procurement Board Directions (the Directions), increasing the risk of non-compliance with the Directions. We noted: 

  • 67 per cent of agencies did specify that procurement above $650,000 must be open to market unless exempt or procured through an existing Whole of Government Scheme or contract
  • 36 per cent of agencies did specify that procurements above $500,000 payable in foreign currencies must be hedged
  • 69 per cent of agencies' policies did specify that the agency head or cluster CFO must authorise the engagement of consultants where the engagement of the supplier does not comply with the standard commercial framework.

Recommendation: Agencies should review their procurement policies and guidelines to ensure they capture the key requirements of the NSW Government Procurement Policy Framework, including NSW Procurement Board Directions.

Managing contracts

Eighty-eight per cent of agencies maintain a central contract register to record all details of contracts above $150,000, which is a requirement of GIPA legislation. Of the agencies that maintained registers, 13 per cent did not capture all contracts and eight per cent did not include all relevant contract details.

Sixteen per cent of agencies did not periodically review their contract register. Timely review increases compliance with GIPA legislation, and enhances the effectiveness with which procurement business units monitor contract end dates, contract extensions and commence new procurement.

Training and support

Ninety-three per cent of agencies provide training to staff involved in procurement processes, and a further 77 per cent of agencies provide this training on an on-going basis. Of the seven per cent of agencies that had not provided training to staff, we noted gaps in aspects of their procurement activity, including:

  • not conducting value for money assessments prior to renewing or extending the contract with their existing supplier
  • not obtaining approval from a delegated authority to commence the procurement process
  • procurement documentation not specifying certain key details such as the conditions for participation including any financial guarantees and dates for the delivery of goods or supply of services.

Training on procurement activities ensures there is effective management of procurement processes to support operational requirements, and compliance with procurement directions.

Procurement activities While agencies had implemented controls for tender activities above $650,000, 43 per cent of unaccredited agencies did not comply with the NSW Procurement Policy Framework because they had not had their procurement endorsed by an accredited agency within the cluster or by NSW Procurement. This endorsement aims to ensure the procurement is properly planned to deliver a value for money outcome before it commences.
Emergency procurement

As at 30 June 2020, agencies within the scope of this report reported conducting 32,239 emergency procurements with a total contract value of $316,908,485. Emergency procurement activities included the purchase of COVID-19 cleaning and hygiene supplies.

The government, through NSW Procurement released the 'COVID-19 Emergency procurement procedure', which relaxed procurement requirements to allow agencies to make COVID-19 emergency procurements. Our review against the emergency procurement measures found most agencies complied with requirements. For example:

  • 95 per cent of agencies documented an assessment of the need for the emergency procurement for the good and/or service
  • 86 per cent of agencies obtained authorisation of the emergency procurement by the agency head or the nominated employee under Public Works and Procurement Regulation 2019
  • 76 per cent of agencies reported the emergency procurement to the NSW Procurement Board.

Complying with the procedure helps to ensure government resources are being efficiently, effectively, economically and in accordance with the law.

Recommendation: Agency procurement frameworks should be reviewed and updated so they can respond effectively to emergency situations that may arise in the future. This includes:

  • updating procurement policies and guidelines to define an emergency situation, specify who can approve emergency procurement and capture other key requirements
  • using standard templates and documentation to prompt users to capture key requirements, such as needs analysis, supplier selection criteria, price assessment criteria, licence and insurance checks
  • having processes for reporting on emergency procurements to those charged with governance and NSW Procurement.
5. Delegations
Instruments of delegation

We found that agencies have established financial and human resources delegations, but some had not revisited their delegation manuals following the legislative and machinery of government changes. For those agencies impacted by machinery of government changes we noted:

  • 16 per cent of agencies had not updated their financial delegations to reflect the changes
  • 16 per cent of agencies did not update their human resources delegations to reflect the changes.

Delegations manuals are not always complete; 16 per cent of agencies had no delegation for writing off bad debts and 26 per cent of agencies had no delegation for writing off capital assets.

Recommendation: Agencies should ensure their financial and human resources delegation manuals contain regular set review dates and are updated to reflect the Government Sector Finance Act 2018, machinery of government changes and their current organisational structure and roles and responsibilities.

Compliance with delegations

Agencies did not understand or correctly apply the requirements of the Government Sector Finance Act 2018 (GSF Act), resulting in non-compliance with the Act. We found that 18 per cent of agencies spent deemed appropriations without obtaining an authorised delegation from the relevant Minister(s), as required by sections 4.6(1) and 5.5(3) of the GSF Act.

Further detail on this issue will be included in our Auditor-General's Reports to Parliament on Central Agencies, Education, Health and Stronger Communities, which will be tabled throughout December 2020.

Recommendation: Agencies should review financial and human resources delegations to ensure they capture all key functions of laws and regulations, and clearly specify the relevant power or function being conferred on the officer.

6. Status of 2019 recommendations
Progress implementing last year's recommendations

Recommendations were made last year to improve transparency over reporting on gifts and benefits and improve the visibility management and those charged with governance had over actions taken to address conflicts of interest that may arise. This year, we continue to note:

  • 38 per cent of agencies have not updated their gifts and benefits register to include all the key fields required under the minimum standards set by the Public Service Commission
  • 56 per cent of agencies have not provided training to staff and 63 per cent of agencies have not implemented an annual attestation process for senior management
  • 97 per cent of agencies have not published their gifts and benefits register on their website and 41 per cent of agencies are not reporting on trends in the gifts and benefits register to those charged with governance.

While we acknowledge the significance of the recent emergencies, which have consumed agency time and resources, we note limited progress has been made implementing these recommendations. Further detail on the status of implementing all recommendations is in Appendix 2.

Recommendation: Agencies should re-visit the recommendations made in last year's report on internal controls and governance and action these recommendations.

Internal controls are processes, policies and procedures that help agencies to:

  • operate effectively and efficiently
  • produce reliable financial reports
  • comply with laws and regulations
  • support ethical government.

This chapter outlines the overall trends for agency controls and governance issues, including the number of audit findings, the degree of risk those deficiencies pose to the agency, and a summary of the most common deficiencies we found across agencies. The rest of this report presents this year’s controls and governance findings in more detail.

Section highlights

We identified ten high risk findings, compared to four last year with two findings repeated from the previous year. There was an overall increase of 13 per cent in the number of internal control deficiencies compared to last year due to a seven per cent increase in new internal control deficiencies, and a 24 per cent increase in repeat internal control deficiencies. The recent emergencies have consumed agency time and resources and may have contributed to the increase in internal control deficiencies, particularly repeat deficiencies.

We identified a number of findings that remain common across multiple agencies over the last four years. Some of these findings related to areas that are fundamental to good internal control environments and effective organisational governance. Examples include:

  • out of date or missing policies to guide appropriate decisions
  • poor record keeping and document retention
  • incomplete or inaccurate centralised registers, or gaps in these registers.

Policies, procedures and internal controls should be properly designed, be appropriate for the current organisational structure and its business activities, and work effectively.

This chapter outlines our audit observations, conclusions and recommendations, arising from our review of agency controls to manage key financial systems.

Section highlights

Government agencies’ financial reporting is heavily reliant on information technology (IT). We continue to see a high number of deficiencies related to IT general controls, particularly those related to user access administration. These controls are key in adequately protecting IT systems from inappropriate access and misuse.

IT is also important to the delivery of agency services. These systems often provide the data to help monitor the efficiency and effectiveness of agency processes and services they deliver. Our financial audits do not review all agency IT systems. For example, IT systems used to support agency service delivery are generally outside the scope of our financial audit. However, agencies should also consider the relevance of our findings to these systems.

Agencies need to continue to focus on assessing the risks of inappropriate access and misuse and the implementation of controls to adequately protect their systems, focussing on the processes in place to grant, remove and monitor user access, particularly privileged user access.

 

This chapter outlines our audit observations, conclusions and recommendations, arising from our review of agency business continuity and disaster recovery planning arrangements.

Section highlights

We identified deficiencies in agency business continuity and disaster recovery planning arrangements and opportunities for agencies to enhance their business continuity management and disaster recovery planning arrangements. This will better prepare them to respond to a disruption to their critical functions, resulting from an emergency or other serious event. Twenty-three per cent of agencies had not conducted a business impact analysis (BIA) to identify critical business functions and determine business continuity priorities and 40 per cent of agencies had not conducted a business continuity scenario testing exercise in the period from 1 January 2019 to 31 December 2019. Scenario testing improves the effectiveness with which a live crisis is handled.

This section focusses on the preparedness of agency business continuity and disaster recovery planning arrangements prior to the onset of the COVID-19 pandemic. While agencies have responded to the recent emergencies, proactively addressing deficiencies will ensure agencies have adequate safeguards in their processes to again respond in the future, if required.

During 2020–21 we plan to conduct a performance audit on 'Business continuity and disaster recovery planning'. This audit will consider the effectiveness of agency business continuity planning arrangements to maintain business continuity through the recent emergencies and/or COVID-19 pandemic and return to a business-as-usual environment. We also plan to conduct a performance audit on whole-of-government 'Coordination of emergency responses'.

 

This chapter outlines our audit observations, conclusions and recommendations, arising from our review of procurement agency procurement policies and procurement activity.

Section highlights

We found agencies have procurement policies in place to manage procurement activity, but the content of these policies was not sufficiently detailed to ensure compliance with NSW Procurement Board Directions (the Directions). The Directions aim to ensure procurement activity achieves value for money and meets the principles of probity and fairness.

Agencies have generally implemented controls over their procurement process. In relation to emergency procurement activity, agencies reported conducting 32,239 emergency procurements with a total contract value of $316,908,485 up to 30 June 2020. Our review of emergency procurement activity conducted during 2019–20 identified areas where some agencies did not fully comply with the 'COVID-19 Emergency procurement procedure'.

We also found not all agencies are maintaining complete and accurate contract registers. This not only increases the risk of non-compliance with GIPA legislation, but also limits the effectiveness of procurement business units to monitor contract end dates, contract extensions and commence new procurement in a timely manner. We noted instances where agencies renewed or extended contracts without going through a competitive tender process during the year.

 

This chapter outlines our audit observations, conclusions and recommendations, arising from our review of agency compliance with financial and human resources delegations.

Section highlights
We found that agencies are not always regularly reviewing and updating their financial and human resources delegations when there are changes to legislation or other organisational changes within the agency or from machinery of government changes. For example, agencies did not understand or correctly apply the requirements of the GSF Act, resulting in non-compliance with the Act. We found that 18 per cent of agencies spent deemed appropriations without obtaining an authorised delegation from the relevant Minister(s), as required by sections 4.6(1) and 5.5(3) of the GSF Act.
In order for agencies to operate efficiently, make necessary expenditure and human resource decisions quickly and lawfully, particularly in emergency situations, it is important that delegations are kept up to date, provide clear authority to decision makers and are widely communicated.

Appendix one – List of 2020 recommendations 

Appendix two – Status of 2019 recommendations

Appendix three – Cluster agencies

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Government advertising 2018-19 and 2019-20

Government advertising 2018-19 and 2019-20

Whole of Government
Finance
Community Services
Compliance
Management and administration
Procurement

A report released today by the Auditor-General for New South Wales, Margaret Crawford found that select advertising campaigns conducted by Service NSW and the NSW Rural Fire Service met most requirements of the Government Advertising Act, regulations, Guidelines and other laws. However, the audit found that Service NSW inappropriately used its post campaign evaluation to measure sentiment towards and confidence in the NSW Government.  

While agency analysis shows that the ‘Cost of Living’ (phases 2 and 3)  and ‘How Fireproof is Your Plan?’ campaigns achieved most of their objectives, the campaign objectives and targets set by both agencies were not sufficient to measure all aspects of campaign effectiveness. 

The report makes two recommendations to the Department of Customer Service. The first is to review its guidance to ensure agencies are not using post campaign evaluations to measure sentiment towards the government. The second, to review its guidance and the new process of peer review to ensure they support agencies to comply with the Act, the regulations and the Guidelines. 

The Government Advertising Act 2011 requires the Auditor General to conduct an annual performance audit of one or more government agencies to see whether their advertising activities were carried out in an effective, economical and efficient manner and in compliance with the Government Advertising Act 2011.
 

Read full report (PDF)

The Government Advertising Act 2011 (the Act) requires the Auditor-General to conduct a performance audit on the activities of one or more government agencies in relation to government advertising campaigns in each financial year. The performance audit assesses whether a government agency or agencies have carried out activities in relation to government advertising in an effective, economical and efficient manner and in compliance with the Act, the regulations, other laws and the Government Advertising Guidelines (the Guidelines). This audit examined two campaigns run during the 2018–19 and 2019–20 financial years respectively:

  • the 'Cost of Living' campaign run by Service NSW (phases 2 and 3 delivered in 2018–19)
  • the 'How Fireproof Is Your Plan?' (Fireproof) campaign run by NSW Rural Fire Service (year two of a three-year campaign delivered in 2019–20).

Section 6 of the Act prohibits political advertising. Under this section, material that is part of a government advertising campaign must not contain the name, voice or image of a minister, member of parliament or a candidate nominated for election to parliament or the name, logo or any slogan of a political party. Further, a campaign must not be designed to influence (directly or indirectly) support for a political party.

Conclusion

Neither campaign breached the prohibition on political advertising contained in section 6 of the Act. While both campaigns met most requirements of the Act, the regulations, other laws and the Guidelines, we identified some instances of non-compliance. Service NSW inappropriately used its post campaign evaluation to measure sentiment towards and confidence in the NSW Government.

Service NSW used its post-campaign evaluation to measure sentiment towards and confidence in the NSW Government. While neither campaign breached the prohibition on political advertising contained in section 6 of the Act, measuring sentiment towards and confidence in the NSW Government is not an appropriate use of the post-campaign evaluation and creates a risk that the results may be used for party political purposes. This risk is heightened as both phases 2 and 3 of the Cost of Living campaign were run immediately before the NSW state election. We have made this finding previously in our report 'Government advertising 2017–18'.

The campaign objectives and targets set by both agencies were not sufficient to fully measure campaign effectiveness. Service NSW advertised seven rebates in phase 2 of the campaign but only set targets for the awareness and uptake of three of these rebates. NSW Rural Fire Service set objectives and targets to be achieved over the life of the three-year campaign but did not set targets to be achieved for each year of the campaign. While the Fireproof campaign is a three-year campaign, each year of the campaign is subject to a separate approval and peer review process.

Agency analysis shows that both campaigns achieved most of their objectives. There was some overlap in the timing of phases 2 and 3 of the Cost of Living campaign and both phases had similar high-level objectives to increase awareness of rebates, making it difficult to evaluate the effectiveness of each distinct campaign phase. NSW Rural Fire Service conducted a post-campaign evaluation for year two of the Fireproof campaign (2019–20) but although this showed positive results against the overall objectives of the three-year campaign, NSW Rural Fire Service did not set specific targets for year two of the campaign, making it difficult to evaluate effectiveness for that year.

Service NSW was not able to demonstrate that its campaign was economical as it directly negotiated with a single supplier for the creative materials for phase 2. This is contrary to the NSW Government's procurement rules which require agencies to obtain three quotes when using suppliers on a prequalification scheme. Service NSW did not comply with its own procurement policy, which restricts Service NSW employees from entering into discussions with a supplier until the appropriate delegate approves a direct procurement. NSW Rural Fire Service achieved cost efficiencies by re-using creative material developed in the first year of the campaign. NSW Rural Fire Service also received $4 million worth of free advertising time and space.

The cost benefit analyses prepared by both agencies did not fully meet the requirements in the Guidelines. Both agencies identified an alternative to advertising but did not assess the costs and benefits of that alternative. We have made this finding previously in our report 'Government advertising 2017–18' and in our report 'Government advertising 2015–16 and 2016–17'.

In 2018–19, Service NSW delivered phases 2 and 3 of the 'Cost of Living' campaign. The Cost of Living advertising campaign aimed to build awareness of the help available to ease the cost of living for people under financial pressure including awareness of specific rebates that can be claimed. As part of the Cost of Living program, Service NSW developed a webpage designed as a single portal to access more than 40 NSW Government savings, rebates and initiatives (which originated from over 12 different agencies). It also launched the Cost of Living service which includes face to face meetings and phone interviews to help people claim rebates from the NSW Government. Phase 2 of the campaign ran from September 2018 to August 2019. Phase 3 of the campaign ran from January 2019 to July 2019. The budgets for phases 2 and 3 were $4.127 million and $934,800 respectively. See Appendix two for more details on this campaign.

Service NSW complied with most requirements of the Act, the Regulations and the Guidelines. Campaign materials that we reviewed did not breach the prohibition on political advertising contained in section 6 of the Act. However, Service NSW used its post-campaign evaluation to measure sentiment towards, and confidence in, the NSW Government. This is not an appropriate use of the post-campaign evaluation and creates a risk that the results may be used for party political purposes. This risk is heightened as both phases 2 and 3 of the Cost of Living campaign were run immediately before the NSW state election.
The post-campaign evaluation shows that the campaign was effective in achieving most of its objectives. However, in phase 2, Service NSW did not set targets for all of the rebates it advertised. There was some overlap in the timing of phases 2 and 3 of the Cost of Living campaign and both phases had similar high-level objectives to increase awareness of rebates, making it difficult to evaluate the effectiveness of each distinct campaign phase.
Service NSW was not able to demonstrate that its campaign was economical as it directly negotiated with a single supplier for the creative materials in phase 2 (total cost $731,480). This is contrary to the NSW Government's procurement rules which require agencies to obtain three quotes when using suppliers on a prequalification scheme where the estimated cost is more than $150,000. Service NSW did not comply with its own procurement policy, which restricts Service NSW employees from entering into discussions with a supplier until the appropriate delegate approves a direct procurement.
The cost benefit analysis for phase 2 did not accurately assess the benefits of the campaign as Service NSW did not know which rebates would be included in the advertisements at the time the cost benefit analysis was developed. The cost benefit analysis for phase 2 did not assess the costs and benefits of alternatives to advertising.

Campaign materials we reviewed did not breach section 6 of the Act

The audit team reviewed campaign materials developed as part of the paid advertising campaign including radio transcripts, digital videos and display. The audit team did not review the use of social media outside paid social media content as section four of the Act defines government advertising as the dissemination of information which is funded by or on behalf of a government agency. See Appendix two for examples of campaign materials for this campaign.

Section 6 of the Act prohibits political advertising as part of a government advertising campaign. A government advertising campaign must not:

  • be designed to influence (directly or indirectly) support for a political party
  • contain the name, voice or image of a minister, a member of parliament or a candidate nominated for election to parliament
  • contain the name, logo, slogan or any other reference to a political party.

The audit found no breaches of section 6 of the Act in the campaign material we reviewed. 

Post-campaign evaluations measured sentiment towards and confidence in the NSW Government

The post-campaign evaluation for phases 2 and 3 measured levels of confidence with the statement ‘the NSW Government has your best interests at heart’, despite the fact this was not a stated objective of the campaign. This is not an appropriate use of the post-campaign evaluation, which should measure the success of the campaign against its stated objectives. The post-campaign evaluation for phase 3 found that exposure to the campaign improved sentiment towards the government amongst those who did not have confidence in the NSW Government.

Service NSW advised that it was important to measure the sentiment of the advertising including the wording 'best interests' as it did not want the whole of government brand to be detrimental to customer engagement with applying for the rebates.

Following phase 2, Service NSW conducted analysis of media sentiment using the key words 'cost of living' and the names of the Premier, Treasurer and Minister for Customer Service. The analysis presented the level of positive, negative and neutral media sentiment. The Government Advertising Guidelines 2012 list the purposes that government advertising may serve which do not include improving the perception of the government. The inclusion of this analysis in Service NSW's post-campaign evaluation creates a risk that the results may be used for party political purposes.

Section 10 of the Act restricts agencies from carrying out a campaign after 26 January in the calendar year before the Legislative Assembly is due to expire and before the election for the Legislative Assembly in that year. Service NSW authorised a media agency to book media in line with the media plans for the campaign. The media plans for the campaign show that Service NSW did not authorise or plan to run any advertisements between 27 January 2019 and 23 March 2019.

Service NSW did not set targets for all rebates advertised in phase 2

Service NSW did not set targets for four of the seven rebates that were advertised as part of phase 2 of the campaign. These rebates were the Family Energy Rebate, Appliance Replacement Offer, National Parks Concession Offer and the Pensioner Travel Voucher. As a result, it was unable to evaluate whether the advertisements for these rebates were effective. Service NSW advised that at the time the campaign went to peer review, when campaign objectives are set, it did not know which rebates would be included in the advertisements.

Service NSW stated in its submission to the Department of Premier and Cabinet that it may change the creative content for phase 2 as it announced new initiatives and rebates. The peer review process should have ensured that Service NSW set targets for any additional rebates or savings it intended to advertise before that advertising commenced to ensure a strategic approach to the campaigns that clearly demonstrated anticipated benefits were in place.

The post-campaign evaluation for phase 2 shows that the advertising campaign met most of its objectives

Service NSW set overall campaign objectives and specific targets for some rebates advertised as part of phase 2 of the campaign. The objectives, targets and results for phase 2 are shown in Exhibit 5. In phase 2, Service NSW established baseline data on levels of awareness of government rebates during the peer review process. The baseline level of awareness for government rebates was 44 per cent. The level of awareness for specific rebates was 46 per cent for the Compulsory Third Party (CTP) green slip refund, and 21 per cent for both Active Kids and Toll Relief.

Post-campaign evaluation reports for phase 2 show that the campaign met its objective to raise awareness of NSW Government rebates, achieving a 16 per cent increase in awareness from 44 per cent to 51 per cent. The campaign did not meet its target to increase awareness of the CTP green slip refund by ten per cent.

Service NSW did not report the results of the uptake of the CTP green slip refund, Active Kids and Toll Relief in its post campaign effectiveness report submitted to the Department of Premier and Cabinet. However, other post-campaign evaluation documentation, which Service NSW advise was submitted to the Department of Premier and Cabinet, show that these targets were met.

Service NSW did not report to the Department of Premier and Cabinet on whether it achieved the target of a ten per cent increase of average monthly visits to the Cost of Living webpage. Service NSW reported that it had achieved an average of 11,753 visitors to the webpage per day during the campaign. These average daily results indicate that the target was met.

Exhibit 5: Phase 2 - campaign objectives, targets and results
Campaign objectives and targets Does the post-campaign evaluation show that the target was met?
1. a) Increase awareness of rebates from the NSW Government by ten per cent.
Image
mauve circle with tick inside

    b) Increase average monthly visits to the Cost of Living webpage by ten per cent.

Image
mauve circle with tick inside and asterisk to the right

2. Increase awareness of rebates and savings by ten per cent for:

 
  • CTP green slip refund
Image
gold circle with white minus symbol inside
  • Active Kids
Image
mauve circle with tick inside
  • Toll Relief.
Image
mauve circle with tick inside
3. Increase awareness that NSW Government initiatives relating to the cost of living are available via Service NSW by ten per cent.
Image
mauve circle with tick inside
4. Increase the uptake of rebates and savings for the CTP green slip refund, Active Kids and Toll Relief by ten per cent.
Image
mauve circle with tick inside and asterisk to the right
Key
Image
mauve circle with tick inside
Yes
Image
gold circle with white minus symbol inside
Not Fully

*  Some issues with reporting on target.
Source: Service NSW. Audit Office analysis.

The post-campaign evaluation for phase 3 shows that the advertising campaign met most of its objectives

Service NSW set overall campaign objectives and specific targets for the two rebates advertised as part of phase 3 of the campaign. The objectives, targets and results for phase 3 are shown in Exhibit 6.

In phase 3, Service NSW established baseline data on levels of awareness during the peer review process. The baseline level of awareness for government rebates was 44 per cent. This is the same baseline that was used to measure performance for phase 2 of the campaign. Service NSW did not set baselines for awareness and uptake of Energy Switch and Creative Kids as these were new services.

Post-campaign evaluation reports for phase 3 show that the campaign met its objective to raise awareness of NSW Government rebates by ten per cent, achieving a 30 per cent increase in awareness from 44 per cent to 57 per cent. The overall increase in message take-out was met with 43 per cent agreeing with the message that the NSW Government is taking steps to ease the cost of living. The campaign achieved awareness and uptake targets for the specific rebates included in phase 3, except for awareness of Creative Kids which achieved 28 per cent awareness, falling short of the 30 per cent awareness target.

Exhibit 6: Phase 3 - campaign objectives, targets and results
Campaign objectives and targets Does the post-campaign evaluation show that the target was met?
1. Increase message takeout that ‘The NSW Government is taking steps to help ease the cost of living in NSW’ by ten per cent for those who can recall the campaign.
2. Increase awareness that the NSW Government has a range of rebates and savings by ten per cent.
3. Generate awareness with NSW residents aged 18+ of:
 
 
  • Energy Switch (15 per cent awareness)
  • Creative Kids (30 per cent awareness).
4. Create uptake of Energy Switch and Creative Kids (8,356 clicks on the Energy Switch website and 107,938 Creative Kids vouchers downloaded with 70 per cent conversion).
Key
Yes
Not Fully

Source: Service NSW. Audit Office analysis.

The timing of campaign phases meant that it was difficult for Service NSW to evaluate each distinct campaign phase and reduced opportunities to incorporate learnings from previous phases

Service NSW commenced planning for phase 2 of the campaign while phase 1 was still underway. This limited the opportunity for Service NSW to incorporate learnings from phase 1 into phase 2. There was some overlap in the timing of phase 2 and the start of phase 3 of the campaign, making it difficult to evaluate the effectiveness of each distinct campaign phase. Both phases 2 and 3 had the same high-level outcome objective to raise awareness of rebates by ten per cent. The baseline measures that were used to evaluate performance for phase 3 were the same as those used to evaluate phase 2. As a result, Service NSW was not able to separately evaluate these two phases of the campaign. This is important given the budgets for phases 2 and 3 were $4.127million and $934,800 respectively.

Service NSW allocated 7.5 per cent of its media budget to communications with culturally and linguistically diverse (CALD) and Aboriginal audiences

The NSW Government CALD and Aboriginal Advertising Policy requires that agencies spend at least 7.5 per cent of an advertising campaign media budget on direct communications with CALD and Aboriginal audiences. Service NSW authorised a media company to book media in line with the media plans for the campaign. The media plans for phases 2 and 3 of the campaign indicate that Service NSW met this requirement, with 7.5 per cent of the budget allocated to these audiences in phase 2 and 10.4 per cent in phase 3.

The post campaign evaluation for phases 1 and 2 of the Cost of Living campaign contained a recommendation to look at other opportunities to reach CALD audiences. Effective communication with CALD audiences was particularly important in phase 3 of the campaign, where they made up 30 per cent of the target audience for the Creative Kids advertisement. The post-campaign analysis for phase 3 showed that the campaign performed well with some, but not all CALD audiences. The post-campaign analysis also showed low awareness and uptake with Aboriginal audiences. Pre-campaign focus groups in phase 3 found Aboriginal audiences had a negative reaction to the campaign tag line ‘NSW Government is helping with the cost of living’ however this tagline was still used in some advertisements in phase 3.

The cost-benefit analysis (CBA) for phase 2 did not accurately assess the benefits of the campaign and did not assess the costs and benefits of alternatives to advertising

Under the Government Advertising Act 2011, agencies are required to prepare a CBA when the cost of the campaign is likely to exceed $1 million. The CBA conducted by Service NSW for phase 2 includes $8 million in benefits attributed to the advertisements for the Energy Switch tool and $6.9 million in benefits attributed to the advertisements for Creative Kids vouchers. These benefits should not have been included in the CBA for phase 2 as they were not included in this phase of the campaign. The CBA did not estimate the benefits of some other rebates and savings advertised in phase 2 of the campaign. This means that the CBA did not accurately assess the benefits of the campaign. Service NSW advised that at the time the CBA was developed it had not selected the rebates to be included in the campaign.

The Government Advertising Guidelines require agencies to consider options other than advertising to achieve the desired objective including a comparison of costs and benefits. The CBA developed as part of phase 2 identified using existing NSW Government communication channels as an alternative to advertising but did not assess the costs and benefits of this alternative.

This is a repeat finding from two previous government advertising audits. The report ‘Government Advertising: 2015–16 and 2016–17’ found that both agencies subject to the audit did not meet the requirements in the guidelines to consider alternatives to advertising. The report made a recommendation to the Department of Premier and Cabinet to work with Treasury to ensure the requirements of the guidelines are fully reflected in the 'Cost-Benefit Analysis Framework for Government Advertising and Information Campaigns'. The report ‘Government advertising 2017–18’ found that one agency subject to the audit did not identify to what extent the benefits could be achieved without advertising, nor did it consider alternatives to advertising which could achieve the same impact as the advertising campaign.

Service NSW negotiated with a single creative agency in phase 2, making it difficult to demonstrate value for money

Agencies are required to obtain three quotes when procuring a creative agency on the prequalification scheme if the estimated cost of the creative content is greater than $150,000. In phase 2 of the campaign, Service NSW extended the contract with the creative agency used for phase 1 of the campaign and did not obtain three quotes despite the cost of the creative content for phase 2 being $731,480. The requirement to obtain three quotes was met in phase 1 when initially selecting this creative agency.

Service NSWs procurement policy details that direct negotiation may be appropriate where there is a compelling reason to renew or rollover a contract beyond temporal or convenience reasons or in the cases of a genuine emergency. In its briefing to the Chief Executive, Service NSW stated that this contract extension was sought due to the time-sensitive nature of the project and that if work was delayed by a tender process, Service NSW may not be able to meet marketing milestones and this could result in limited customer uptake. This reason is not a genuine emergency and is not compelling as it does not explain what consequences would occur if it did not meet the marketing milestones or if there was limited customer uptake.

Service NSW's procurement policy also states that under no circumstances must Service NSW employees enter into discussions with a supplier until the delegate has formally made their decision to enter into direct negotiation. Service NSW briefed the Chief Executive of Service NSW in relation to extending the contract on 5 September 2018. The briefing states that the creative agency had already begun developing creative content for phase 2 and Service NSW had already received quotes from the creative provider for the proposed work prior to 5 September 2018. Procurement sign-offs were not completed until 7 September 2018. The engagement of the creative provider prior to appropriate approvals was contrary to Service NSWs procurement policy.

The economy of the campaign may have been limited by not meeting the procurement requirements in phase 2. It is possible that the creative provider may have offered a more competitive rate if it was aware that Service NSW was seeking quotes from other creative providers. Additionally, it is possible that another creative provider could have provided better value for money.

In phase 3 of the campaign, the estimated cost of the creative exceeded $150,000 however Service NSW chose to contract two different creative agencies, and the cost for each agency fell below the threshold to obtain three quotes. Agencies are permitted to obtain one quote when using a creative provider on the prequalification scheme if the cost is between $50,000 to $150,000. Service NSW advised that it contracted two creative providers as two different project teams were responsible for the rebates, each with separate marketing budgets.

Service NSW allowed sufficient time for cost-efficient media placement

During the peer review process, the Department of Premier and Cabinet advised agencies about the time they should allow to ensure cost-efficient media placement. For example, the Department of Premier and Cabinet advised that agencies book television advertising six to 12 weeks in advance and that agencies book radio advertising two to eight weeks in advance.

Service NSW allowed sufficient time between the completion of the peer review process and the commencement of the first advertising. Service NSW signed the agreement with the approved Media Agency Services provider with sufficient time to achieve cost-efficient media placement for all types of media used in this campaign.

The campaign may have been misleading for some people who were not eligible for rebates

Advertisements we reviewed focused on the amount of savings that could be obtained from rebates, for example ‘Save up to $285’, and ended with a statement ‘To save, visit service.nsw.gov.au. This directed viewers to the Cost of Living website which contains eligibility information. However, the advertisements in phases 2 and 3 we reviewed did not contain any details on the eligibility for these rebates and not all advertisements stated that eligibility criteria apply. Service NSW advised that the eligibility criteria for each rebate is extensive and that it was not possible to include this in the creative material.

Post-campaign evaluations in phase 3 recommended that advertisements for Creative Kids should indicate eligibility (e.g. age criteria) as statements on savings have the potential to be misleading when not all viewers will be eligible for rebates. Social media analysis conducted following phase 2 showed ineligibility or inability to claim rebates or refunds caused anger for some respondents.

Some advertisements in phase 2 stated ‘we've got something for everyone’. However, as rebates were subject to eligibility criteria, it is possible that some residents in NSW would not be eligible for any rebates as part of the Cost of Living initiative. As such, this statement has the potential to be misleading.

The campaign included statements that underestimated the savings that some customers could obtain

The Guidelines require accuracy in the presentation of all facts, statistics, comparisons and other arguments. The Guidelines also require that all claims of fact included in government advertising campaigns must be able to be substantiated.

In phase 2, the possible savings customers could obtain for two rebates or savings exceeded the amounts stated in the advertising campaign. Exhibit 7 shows some advertisements in phase 2 which stated, ‘My Green Slip Saving Save up to $60’. However, the State Insurance Regulatory Authority website shows that savings for some types of motor vehicles under the 2017 CTP scheme exceed $60. The State Insurance Regulatory Authority website states that the average saving under this scheme has been $129. Service NSW advised that these advertisements were designed for regional markets and that it used different advertisements for metropolitan areas which contained different amounts of savings.

Some advertisements in phase 2 stated, ‘My Toll Relief save up to $700’. The Service NSW website states that drivers can obtain free vehicle registration if they have spent $1,352 or more in tolls in the previous financial year. The cost of registration for some vehicles exceeds $700. This means the savings detailed in the advertisement were lower than what some customers could actually save.

NSW Rural Fire Service conducted the 'How FireProof Is Your Plan?' (Fireproof) campaign. The Fireproof campaign is a three-year campaign which ran in 2018–19 (year one), 2019–20 (year two) and is planned for 2020–21 (year three). This audit examined year two of the campaign (2019–20).

The Fireproof campaign is a public safety campaign encouraging people to plan and prepare for bush fires across the summer period. The campaign aims to improve the quality of bush fire planning and preparation in the community and decrease the impact of fires on the community when they occur.

The Fireproof campaign (year two) complied with most requirements of the Act, the Regulations and the Guidelines. The campaign materials that we reviewed did not breach the prohibition on political advertising contained in section 6 of the Act. NSW Rural Fire Service set objectives and targets to be achieved over the life of the three-year Fireproof campaign. Post-campaign evaluation shows that the Fireproof campaign was effective in achieving increases against its three-year objectives during year two. However, NSW Rural Fire Service did not set targets to be achieved for each year of the campaign, making it difficult to evaluate the effectiveness of year two of the campaign. NSW Rural Fire Service achieved cost efficiencies by re-using creative material developed in the first year of the campaign. NSW Rural Fire Service received $4 million worth of free advertising time and space. The cost benefit analysis for the Fireproof campaign did not assess the costs and benefits of alternatives to advertising.

Campaign materials we reviewed did not breach section 6 of the Act

The audit team reviewed campaign materials developed as part of the paid advertising campaign for example radio advertisements, television commercials and digital displays. The audit team did not review the use of social media outside paid social media content as section four of the Act defines government advertising as the dissemination of information which is funded by or on behalf of a government agency. Examples of campaign materials are shown in Appendix two.

Section 6 of the Act prohibits political advertising as part of a government advertising campaign. A government advertising campaign must not:

  • be designed to influence (directly or indirectly) support for a political party
  • contain the name, voice or image of a minister, a member of parliament or a candidate nominated for election to parliament
  • contain the name, logo, slogan or any other reference to a political party.

The audit found no breaches of section 6 of the Act in the campaign material we reviewed. 

NSW Rural Fire Service did not set targets for the second year of the campaign

The second year of the Fireproof campaign (2019–20) had the same objectives as the first year of the campaign (2018–19), however no specific targets were set for the second year. The advertising submission for the first year of the campaign (2018–19) details the targets for each objective as an increase of ten per cent against the baseline data to be achieved by March 2021, at the end of the three-year campaign.

The second year of the Fireproof campaign (2019–20) was one of the first campaigns approved under the new budget and peer review processes introduced by the Department of Customer Service in 2019–20. The new process for peer review introduced a new template for campaign submissions. The former template for campaign submissions contained more prompts for agencies to ensure the submission contained sufficient detail of campaign objectives, baseline measures, targets, dates for measurement and detail on how they would measure objectives. Despite this, the peer review process should have identified that NSW Rural Fire Service did not set targets for the second year of the campaign.

The 2016 Guidelines for Implementing NSW Government Evaluation Framework for Advertising and Communications requires campaign objectives to be SMART (specific, measurable, achievable, realistic and timed). NSW Rural Fire Service did not meet this requirement for year two of the Fireproof campaign.

Post-campaign evaluations showed increases against four out of five objectives, however there were no specific targets

NSW Rural Fire Service set three campaign objectives at the time it submitted the second year of the campaign (2019–20) to the Department of Customer Service for peer review. However, the post-campaign effectiveness report submitted to the Department of Customer Service measured campaign effectiveness against five campaign objectives. The objectives in the post-campaign effectiveness report were the same objectives set for the first year of the campaign, which is appropriate as this was a repeat campaign.

NSW Rural Fire Service achieved increases against four of their five objectives. However, as noted above there were no specific targets (such as percentage increases) against which performance of the 2019–20 campaign could be measured. Despite this, at the end of the second year, the Fireproof campaign had already achieved some of the targets that NSW Rural Fire Service had set for the end of the third year of the campaign. The post-campaign research showed that both audience recall and exposure to the campaign increased significantly from the prior year. The campaign objectives and results are shown in Exhibit 8.

For those people who already have a bush fire plan, the campaign aimed to increase the number of those plans which have included two or more elements from the Guide to Making a Bush Fire Survival Plan. Elements from the Guide to Making A Bush Fire Survival Plan include actions such as deciding what to take with you if you leave, ensuring you have the right equipment for defending your home and allocating responsibilities to members of a household. The post-campaign evaluation showed that the campaign did not achieve an increase against this objective for people who planned to stay and defend their property rather than leave.

Exhibit 8: Campaign objectives and results
Campaign objectives Does the post-campaign evaluation show increases against the objective?
1. Continue to increase the number of people that have discussed and/or written a plan with regards to what they will do in the event of a fire.
2. Of those who indicate they have a plan, increase the number of people who have included two or more elements from the Guide to Making a Bush Fire Survival Plan:  
  • for those who plan to leave
  • for those who plan to stay and defend.
3. Increase the frequency in completing preparation activities around a person’s property.
4. Increase the number of people who correctly assess it is their responsibility to complete preparation activities and enact their plan without direct intervention from emergency services.
5. Visits to MyFirePlan website.
Key
Yes
No

Source: NSW Rural Fire Service. Audit Office analysis.

NSW Rural Fire Service achieved cost efficiencies by reusing creative content developed in the first year of the campaign

Total creative and production costs incurred in year one of the campaign were $1.08 million. Rather than commissioning new creative materials, NSW Rural Fire Service re-used the same creative content in year two of the campaign. NSW Rural Fire Service incurred $100,000 in creative and production costs in year two of the campaign and achieved cost-efficiencies by reusing the same creative developed in the prior year.

NSW Rural Fire Service allowed sufficient time for cost-efficient media placement and received free media placements

The Department of Customer Service advises agencies to work with media contacts to book media in advance to ensure a cost-efficient placement. Prior to 2019–20, the Department of Premier and Cabinet provided suggested timeframes for agencies to book media as part of the peer review process. For example, it advised agencies to book television six to 12 weeks in advance and book radio advertising two to eight weeks in advance. NSW Rural Fire Service allowed sufficient time for a cost-efficient media placement.

NSW Rural Fire Service received $4 million of free advertising time and space donated by media companies due to the extent and impact of the 2019–20 fire season.

The cost benefit analysis (CBA) did not assess the costs and benefits of alternatives to advertising

Under the Government Advertising Act 2011, agencies are required to prepare a CBA when the cost of the campaign is likely to exceed $1 million. As part of the CBA, the Government Advertising Guidelines require agencies to consider options other than advertising to achieve the desired objective including a comparison of costs and benefits.

The CBA for the Fireproof campaign (year two) notes that the proposed campaign is one component of a broader community engagement strategy which has been developed over time and is based on research and evaluation. The CBA considers two options to achieve the objectives of the campaign. The first option is community engagement activities without an advertising campaign and the second option is community engagement activities alongside an advertising campaign. The CBA does not identify and assess the costs and benefits of both of the options in order to assess the most cost-efficient option.

This is a repeat finding from two previous government advertising audits. The report ‘Government Advertising: 2015–16 and 2016–17’ found that both agencies subject to the audit did not meet the requirements in the guidelines to consider alternatives to advertising. The report made a recommendation to the Department of Premier and Cabinet to work with Treasury to ensure the requirements of the guidelines are fully reflected in the 'Cost-Benefit Analysis Framework for Government Advertising and Information Campaigns'. The report ‘Government advertising 2017–18’ found that one agency subject to the audit did not identify to what extent the benefits could be achieved without advertising, nor did it consider alternatives to advertising which could achieve the same impact as the advertising campaign.

Appendix one – Responses from agencies

Appendix two – About the campaigns

Appendix three – About the audit

Appendix four – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #342 - released 19 November 2020

Published

Actions for Health capital works

Health capital works

Health
Compliance
Infrastructure
Procurement
Project management

This report examines whether NSW Health effectively planned and delivered major capital works to meet the demand for health services in New South Wales.

The report found that NSW Health has substantially expanded health infrastructure across New South Wales since 2015. However, the program was driven by Local Health District priorities without assessment of the State’s broader and future‑focussed health requirements.

The report found that unclear decision making roles and responsibilities between Health Infrastructure and the Ministry of Health limited the ability of NSW Health to effectively test and analyse investment options.

Project delays and budget overruns on some major projects indicate that Health Infrastructure's project governance, risk assessment and management systems could be improved.

The Auditor‑General recommends that NSW Health ensure its capital projects offer the greatest value to New South Wales by establishing effective policy guidance and enhancing project governance and management systems.

Read full report (PDF)

Since 2011–12, NSW Health has aimed to improve its facilities and build 'future focused' infrastructure. The NSW Government’s 2015–16 election commitments established a four-year $5.0 billion capital program for NSW Health to build and upgrade more than 60 hospitals and health services. The 2019–20 State Budget committed a further $10.1 billion over four years for another 29 projects. This is the largest investment to date on health capital works in New South Wales.

Recent reviews of infrastructure have recognised that population and demographic growth will require a change in the delivery and composition of health infrastructure, including considering greater use of non-traditional, non-capital health service options and assets.

To ensure that expenditure on capital works represents the best value for money, NSW Health's business cases need to be robust and supported by evidence that demonstrates they are worthy investments. The NSW Process of Facility Planning has been the main framework guiding the detailed planning and development of NSW Health's capital works proposals. This framework was developed by the then NSW Department of Health in 2010. Its aim is to ensure investment proposals are supported by rigorous planning processes that address health service needs and provide value for money.

Infrastructure projects of the complexity and scale being delivered by NSW Health carry inherent risks. For example, unplanned cost escalations can potentially impact on the State’s finances. Unforeseen delays can also reduce the intended benefits. The growth in the State’s health capital spend and project profile, means its exposure to such risks has increased over time.

The objective of this audit was to assess the effectiveness of planning and delivery of major capital works to meet demand for health services in New South Wales. To address this objective, the audit examined whether:

  • the Ministry of Health has effective procedures for planning and prioritising investments in major health capital works
  • Health Infrastructure develops robust business cases for initiated major capital works that reliably inform government decision making
  • Health Infrastructure has effective project governance and management systems that support delivering projects on-time, within budget and achievement of intended benefits.

The audit focused on the Ministry of Health and Health Infrastructure – being the lead agencies within NSW Health responsible for prioritising, planning and delivering major health capital works across the State. The audit examined 13 business cases for eight discrete projects over a ten-year period.

Conclusion

NSW Health has substantially expanded health infrastructure across New South Wales since 2015. However, its planning and prioritisation processes were not assessed against a long-term statewide health infrastructure plan and lacked rigorous assessment against non-capital options creating a risk that they do not maximise value for New South Wales.

The scale of NSW Health's capital investment is significant and has grown substantially in recent years. The NSW Government’s election commitments in 2015–16 and 2019–20 collectively set out a $15.0 billion capital program to build and upgrade 89 hospitals and health services. NSW Health developed this infrastructure program in the absence of a statewide health infrastructure strategy and investment framework to focus its planning and decisions on the types of capital investments required to meet the long-term needs of the NSW health system.

Consequently, locally focused priorities of the State’s 17 Local Health Districts have been the primary drivers of NSW Health’s capital investments since 2015–16. Local Health District investment proposals for hospitals were developed without consideration of alternative health options such as community health service models, technology-driven eHealth care, or private sector options. Without rigorous assessment against a range of potential health service options, there is a risk that selected projects do not maximise value for New South Wales.

In recognition of the need for a statewide approach to infrastructure planning, the Ministry of Health recently developed a 20-year Health Infrastructure Strategy and prioritisation framework in 2019. The strategy was approved by the NSW Government in April 2020.

NSW Health's ability to effectively test and analyse its capital investment options has been compromised by unclear decision-making roles and responsibilities between its Health Infrastructure and the Ministry of Health agencies.

While both Health Infrastructure and the Ministry of Health have responsibilities for the assessment of business cases for proposed infrastructure projects, confusion about the roles of each agency at key steps compromised the efficacy of the process. Health Infrastructure and the Ministry of Health have differing views about which agency is responsible for testing business case inputs and conducting comprehensive options appraisals.

As a result of this confusion, Health Infrastructure and the Ministry of Health did not rigorously test Local Health District capital investment proposals against defined statewide health infrastructure investment priorities. The NSW Process of Facility Planning does not clarify the responsibilities of all parties in validating and prioritising Local Health District's Clinical Service Plans and progressing them to business cases.

NSW Health's infrastructure priorities are not sufficiently supported by transparent documentation of selection methodology and the rationale for decisions. Consequently, there is a risk that recommended options, whilst having some economic and health service merit, do not represent the greatest value.

Substantial delays and budget overruns on some major projects indicate that Health Infrastructure's project governance, risk assessment and management systems could be improved.

Health Infrastructure did not fully comply with NSW Government guidelines for developing business cases and making economic appraisals for proposed capital investments. These weaknesses, along with delays and budget overruns on some projects, demonstrate a need for Health Infrastructure to strengthen its project governance, management and quality control systems.

 

Over the period of review, NSW Government policies for business case development and submission have emphasised that effective governance arrangements are critical to a proposal's successful implementation.

NSW Health's Process of Facility Planning similarly highlights the importance of effective governance and project management for achieving good outcomes. It prescribes a general governance structure managed by Health Infrastructure that can be tailored to the planning and delivery of health infrastructure projects greater than $10.0 million.

Project challenges indicate opportunities for strengthening governance and project management

The three major hospital redevelopments examined in metropolitan, regional and rural areas had a combined Estimated Total Cost of more than $1.2 billion and comprised eight discrete projects and 13 separate business cases.

Almost all these projects experienced delivery challenges which impacted achievement of their original objectives and intended benefits. This is expected in complex and large-scale health infrastructure programs. However, in some projects the impacts were significant and resulted in substantial delays, unforeseen costs, and diversion of resources from other priority areas.

Our review of the selected case studies highlighted opportunities for enhancing governance and project management. Specifically, it indicates a need for improving transparency in the management of contingencies, risk management and assessments particularly relating to adverse site conditions and the selection of contractors. There is also a need to strengthen forward planning for options to address unfunded priorities within business cases that risk complicating the delivery of future project stages resulting in unforeseen costs and potentially avoidable budget overruns.

Need for increased transparency and accountability in the management of contingency funds

In February 2017, the Ministry's Capital Strategy Group approved the use of surplus funds of $13.76 million from Stage 1 of the Hornsby Ku-ring-gai Hospital Redevelopment for new works deemed needed to support Stage 2. Following this decision, Health Infrastructure finalised and submitted a business case addendum for Stage 1 to the Ministry in March 2017, addressing the new works comprising a two-storey building for medical imaging and paediatric floors. The business case addendum also addressed options to fit out and procure major medical imaging equipment. The Ministry approved the Stage 1 business case in July 2017, noting the Ministry's Capital Strategy Group had already approved the use of remaining Stage 1 funds to deliver the new works.

Stage 1 was completed in 2015, almost two years before the Stage 1 business case addendum was prepared in February 2017.

The Ministry's decision to approve the new works using $13.76 million of surplus Stage 1 funds did not comply with the NSW Treasury Circular TC 12/20. This policy establishes the Treasurer's approval must be sought and received before a new capital project with an Estimated Total Cost of $5.0 million or more can be approved by NSW Health. The Ministry therefore exceeded its delegated authority in making this decision, as it was not evident it had sought and received the Treasurer's approval prior to doing so.

Consequently, the surplus Stage 1 funds should not have been used by the Ministry to deliver new works in the circumstances. Instead, they should have been released from the Stage 1 project in accordance with established NSW Health procedures, and the Stage 1 Estimated Total Cost revised down accordingly. This did not occur, and NSW Health ultimately directed $11.0 million in surplus Stage 1 funds to the new works.

These circumstances indicate a need to strengthen transparency and accountability within NSW Health for the approval of new projects, and how contingency funds are used in the management of major health capital works. They also demonstrate the impact of weaknesses with options appraisal as the initial Stage 1 business case did not consider alternative options for addressing the initially unfunded works later covered by the Stage 1 business case addendum and ultimately funded from the Stage 1 contingency provision.

Weaknesses in service delivery planning resulted in unaccounted-for costs

In addition to proposing the above-noted new works, the 2017 Stage 1 Business Case Addendum for the Hornsby-Ku-ring-gai development sought to retrospectively address the estimated funding gap of around $14.0 million for the internal fit out, supply of major medical imaging equipment, and cost to operate the medical imaging service at Hornsby Ku-ring-gai Hospital also not addressed in the originally Stage 1 business case.

The Stage 1 business case addendum considered various procurement options to purchase and run the medical imaging services ranging from State operation purchase options to private operation purchase options.

It recommended outsourcing the operation and provision of equipment to the private sector based on estimated savings to the public sector initially of around $650,000 per annum reducing over time to $270,000. The Ministry endorsed this option in June 2017, but it did not ultimately proceed.

A July 2018 report to the Executive Steering Committee on the project shows NSW Health later decided to deliver operation of the medical imaging unit 'traditionally' with an updated estimate of the cost at approximately $16.4 million. The report also shows the Ministry supported the costs now being met by the Northern Sydney Local Health District.

This means the funding gap previously identified in the Stage 1 business case addendum for fitting out the medical imaging building and supply of major medical equipment would need to be met fully by the State, representing a $16.4 million cost overrun for the project.

Examined reports to the Executive Steering Committee show this was largely funded by the Northern Sydney Local Health District via the disposal of land realising approximately $15.0 million in proceeds.

This initially unforeseen cost, along with the additional $11.0 million for the new works approved under the Stage 1 business case addendum, were ultimately merged with the Stage 2 project initially approved in 2017–18 with an Estimated Total Cost of $200 million.

The extent of budget variation on the Hornsby Kur-ring-gai development has not been transparent

The 2019–20 State Budget provided an additional $65.0 million for a further Stage 2A to deliver additional built capacity to support outpatient services, enhanced allied health services, re-housed community health services and the delivery of prioritised clinical services unfunded as part of Stage 2. The funds were approved based on an Investment Decision Template (IDT) that examined two options in addition to the base case representing scoping alternatives to the preferred master planned capital solution.

However, we found the IDT showed around 23 per cent of the $65.0 million sought (i.e. $15.0 million) was to be allocated to fund the deficit in Stage 2, which had arisen as a result of project delays due to adverse site conditions. This was not discussed in the IDT.

The February 2020 report to the Executive Steering Committee shows a combined Stage 2 and 2A final forecast cost of $292.6 million against a potential budget of $290.7 million representing an overall deficit for the project of around 0.6 per cent.

However, this favourable final budget position does not transparently show the funding challenges experienced over the project's implementation to-date. The three major budget issues include:

  • inappropriate use of around $11.0 million in Stage 1 contingency for originally unfunded works contrary to Treasury policy
  • the additional $16.4 million cost unforeseen in the Stage 1 business case for delivering medical imaging services mostly funded through the sale of land
  • an additional $15.0 million from Stage 2A to cover the budget overrun in Stage 2 due to adverse site conditions.

The cumulative impact of these events is that Stages 1 and 2 of the Hornsby project cost approximately $42.4 million than it should have in the circumstances around 14 per cent more than what the revised combined Estimated Total Cost for both stages should have been after releasing the $11.0 million in surplus Stage 1 funds, with Stage 2 delayed by around 14 months.

Opportunity for strengthening risk management for adverse site conditions

Major construction projects often experience adverse site conditions which can be difficult to fully detect in advance. However, we found this was a common occurrence in the projects we examined sometimes with significant time and/or budget impacts indicating scope to enhance related risk and cost assessments. Specifically:

  • Hornsby Ku-ring-gai Hospital Redevelopment Stage 2: adverse site conditions during demolition works resulted in an 11-month delay for delivering the medical imaging unit and 14-month delay completing Stage 2 main works including need for additional $15.0 million in funds to cover the resultant budget deficit for the project.
  • Blacktown Mt Druitt Hospital Redevelopment Stage 2: adverse site conditions combined with project complexity delayed completion of the early works by approximately five months. This contributed to the delay in completing the main construction works which occurred around nine months later than planned in the business case.
  • Dubbo Health Service Redevelopment Stages 3 and 4: Health Infrastructure advised adverse site conditions including asbestos containing materials and ground conditions delayed works for the main building with completion forecast for March 2021, around 21 months later than planned in the final business case. This resulted in the need for additional $13.5 million to cover increased construction costs and risks, increasing the Stage 3 and 4 forecast final cost from $150 million to $163.5 million as at February 2020.

These examples indicate a risk the cumulative impact of adverse site conditions may be substantial when measured across both time and Health Infrastructure's full delivery program. They also point to potential for Health Infrastructure to achieve efficiencies and improved outcomes from strengthening its approach to assessing and mitigating the risks from adverse site conditions.

Limited due diligence with prospective contractors risks avoidable delays and costs

Main construction works on Stage 1 of the Dubbo Health Service Redevelopment were completed in October 2015, approximately 13 months later than planned in the final business case. Delays were mainly due to insolvency of the early works contractor resulting in their departure from the project. The ensuing 11-month delay in completing the early works significantly impacted the overall schedule and delivery of main construction works.

The insolvency event was significant as it affected nine separate Health Infrastructure projects – three of which had yet to reach practical completion. It also affected state-funded projects in other sectors. It resulted in the need for additional funding of $11.5 million that was provided in the 2014–15 State Budget increasing the total Stage 1 and 2 budget from $79.8 million to $91.3 million.

Health Infrastructure’s analysis of lessons learned shows it worked actively to mitigate the impacts of the insolvency event across all affected projects. However, it also indicates a risk the lessons were mainly focused on mitigating the impacts after an insolvency event occurred rather than on prevention.

Although Health Infrastructure initially commissioned a financial assessment of the now insolvent early works contractor before engagement, it did not detect any risks of the impending insolvency and instead concluded the contractor was in a strong financial position. However, the contractor became insolvent shortly after commencement approximately seven months later. This indicates a risk of weaknesses in the assessment performed that was not explicitly addressed by the lessons learned.

Delivery of the main construction works were further impacted by disputes with the main works contractor over the scope of works for the renal unit resulting in Health Infrastructure terminating the contract in November 2016 following lengthy negotiations over several months.

The scope of works relating to the renal unit were ultimately transferred to Stages 3 and 4 and were delivered in December 2019, around five years later than originally planned in the business case.

Health Infrastructure advised the delay was ultimately beneficial to the project because the refurbishment works for the renal unit, initially scheduled for Stages 1 and 2, would have been demolished to accommodate the new Western Cancer Centre proposed after Stages 1 and 2 and currently being delivered in parallel with Stages 3 and 4.

Health Infrastructure advised the actual cost of Stages 1 and 2 was $84.7 million against the budget of $91.3 million. The residual $6.6 million relates to the renal works not delivered during Stage 1 and 2 and transferred to Stage 3 and 4.

Health Infrastructure advised the contractual provisions for mitigating insolvency events 'in-flight' are limited highlighting the importance of proactive and effective due diligence prior to engaging contractors for significant construction projects.

Need for a quality framework linked to staff training and capability development

Health Infrastructure's 2017-20 Corporate Plan identifies the development of a quality framework to support delivery of future-focused outcomes as a key organisational priority. Related initiatives within the Corporate Plan describe a framework underpinned by a Quality Committee providing advice on:

  • records management, to meet the requirements of the State Records Act 1998
  • project assurance, to ensure future focused outcomes and enhance Health Infrastructure's Standards, Policies, Procedures and Guidelines, Templates and Design Guidance Notes
  • knowledge management and library services, to promote and leverage from project learnings.

Although Health Infrastructure has some elements of a quality framework it is not yet fully in place. Health Infrastructure advised it had yet to establish the quality framework and related committee described in its Corporate Plan due in part to its focus on responding to the growth of its capital program.

Health Infrastructure's Development and Innovation team has been active in supporting continuous improvement in knowledge and project management including development of business cases. Although useful, these initiatives have relied heavily on leveraging and disseminating insights from Gateway reviews and have not formed part of a systematic quality and continuous improvement framework.

The limited focus on the quality of business cases is reflected in internal performance monitoring and reporting which focuses mainly on tracking the delivery of projects against internal benchmarks, often revised from the baselines in the business case, and expenditure against cashflow targets. There is no evident internal monitoring and/or reporting to the Chief Executive and Board on defined quality metrics linked to business case development and staff capability.

Performance reporting on balanced scorecard metrics has similarly focused mainly on process rather than quality and has been inconsistent in recent years.

Appendix one – Response from agency

Appendix two – About the audit

Appendix three – Performance auditing

Appendix four – Ministry of Health planning tools and guidelines

Appendix five – Streamlined investment decision process for Health Capital Projects

Appendix six – Timeline of business cases and relevant policy guidelines

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #338 - released 12 August 2020

Published

Actions for CBD South East Sydney Light Rail: follow-up performance audit

CBD South East Sydney Light Rail: follow-up performance audit

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk
Service delivery

This is a follow-up to the Auditor-General's November 2016 report on the CBD South East Sydney Light Rail project. This follow-up report assessed whether Transport for NSW has updated and consolidated information about project costs and benefits.

The audit found that Transport for NSW has not consistently and accurately updated project costs, limiting the transparency of reporting to the public.

The Auditor-General reports that the total cost of the project will exceed $3.1 billion, which is above the revised cost of $2.9 billion published in November 2019. $153.84 million of additional costs are due to omitted costs for early enabling works, the small business assistance package and financing costs attributable to project delays.

The report makes four recommendations to Transport for NSW to publicly report on the final project cost, the updated expected project benefits, the benefits achieved in the first year of operations and the average weekly journey times.

Read full report (PDF)

The CBD and South East Light Rail is a 12 km light rail network for Sydney. It extends from Circular Quay along George Street to Central Station, through Surry Hills to Moore Park, then to Kensington and Kingsford via Anzac Parade and Randwick via Alison Road and High Street.

Transport for NSW (TfNSW) is responsible for planning, procuring and delivering the Central Business District and South East Light Rail (CSELR) project. In December 2014, TfNSW entered into a public private partnership with ALTRAC Light Rail as the operating company (OpCo) responsible for delivering, operating and maintaining the CSELR. OpCo engaged Alstom and Acciona, who together form its Design and Construct Contractor (D&C).

On 14 December 2019, passenger services started on the line between Circular Quay and Randwick. Passenger services on the line between Circular Quay and Kingsford commenced on 3 April 2020.

In November 2016, the Auditor-General published a performance audit report on the CSELR project. The audit found that TfNSW would deliver the CSELR at a higher cost with lower benefits than in the approved business case, and recommended that TfNSW update and consolidate information about project costs and benefits and ensure the information is readily accessible to the public.

In November 2018, the Public Accounts Committee (PAC) examined TfNSW's actions taken in response to our 2016 performance audit report on the CSELR project. The PAC recommended that the Auditor-General consider undertaking a follow-up audit on the CSELR project. The purpose of this follow-up performance audit is to assess whether TfNSW has effectively updated and consolidated information about project costs and benefits for the CSELR project.

Conclusion

Transport for NSW has not consistently and accurately updated CSLER project costs, limiting the transparency of reporting to the public. In line with the NSW Government Benefits Realisation Management Framework, TfNSW intends to measure benefits after the project is completed and has not updated the expected project benefits since April 2015.

Between February 2015 and December 2019, Transport for NSW (TfNSW) regularly updated capital expenditure costs for the CSELR in internal monthly financial performance and risk reports. These reports did not include all the costs incurred by TfNSW to manage and commission the CSELR project.

Omitted costs of $153.84 million for early enabling works, the small business assistance package and financing costs attributable to project delays will bring the current estimated total cost of the CSELR project to $3.147 billion.

From February 2015, TfNSW did not regularly provide the financial performance and risk reports to key CSELR project governance bodies. TfNSW publishes information on project costs and benefits on the Sydney Light Rail website. However, the information on project costs has not always been accurate or current.

TfNSW is working with OpCo partners to deliver the expected journey time benefits. A key benefit defined in the business plan was that bus services would be reduced owing to transfer of demand to the light rail - entailing a saving. However, TfNSW reports that the full expected benefit of changes to bus services will not be realised due to bus patronage increasing above forecasted levels.

Appendix one – Response from agency

Appendix two – Governance and reporting arrangements for the CSELR

Appendix three – 2018 CSELR governance changes

Appendix four – About the audit

Appendix five – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #335 - released 11 June 2020

Published

Actions for Train station crowding

Train station crowding

Transport
Management and administration
Risk
Service delivery
Workforce and capability

This report focuses on how Transport for NSW and Sydney Trains manage crowding at selected metropolitan train stations.

The audit found that while Sydney Trains has identified platform crowding as a key strategic risk, it does not have an overarching strategy to manage crowding in the short to medium term. Sydney Trains 'do not have sufficient oversight to know if crowding is being effectively managed’, the Auditor-General said.

Sydney Trains' operational response to crowding involves restricting customer access to platforms or station entries before crowding reaches unsafe levels or when it impacts on-time running. Assuming rail patronage increases, it is likely that Sydney Trains will restrict more customers from accessing platforms or station entries, causing customer delay. ‘Restricting customer access to platforms or station entries is not a sustainable approach to manage station crowding’, said the Auditor-General.

The Auditor-General made seven recommendations to improve Transport for NSW and Sydney Trains' management of station crowding. Transport for NSW have accepted these recommendations on behalf of the Transport cluster.

Public transport patronage has been impacted by COVID-19. This audit was conducted before these impacts occurred.

Read full report (PDF)

Sydney Trains patronage has increased by close to 34 per cent over the last five years, and Transport for NSW (TfNSW) expects the growth in patronage to continue over the next 30 years. As patronage increases there are more passengers entering and exiting stations, moving within stations to change services, and waiting on platforms. As a result, some Sydney metropolitan train stations are becoming increasingly crowded.

There are three main causes of station crowding:

  • patronage growth exceeding the current capacity limits of the rail network
  • service disruptions
  • special events.

Crowds can inhibit movement, cause discomfort and can lead to increased health and safety risks to customers. In the context of a train service, unmanaged crowds can affect service operation as trains spend longer at platforms waiting for customers to alight and board services which can cause service delays. Crowding can also prevent customers from accessing services.

Our 2017 performance audit, ‘Passenger Rail Punctuality’, found that rail agencies would find it hard to maintain train punctuality after 2019 unless they significantly increased the capacity of the network to carry trains and people. TfNSW and Sydney Trains have plans to improve the network to move more passengers. These plans are set out in strategies such as More Trains, More Services and in the continued implementation of new infrastructure such as the Sydney Metro. Since 2017, TfNSW and Sydney Trains have introduced 1,500 more weekly services to increase capacity. Additional network capacity improvements are in progress for delivery from 2022 onwards.

In the meantime, TfNSW and Sydney Trains need to use other ways of managing crowding at train stations until increased capacity comes on line.

This audit examined how effectively TfNSW and Sydney Trains are managing crowding at selected metropolitan train stations in the short and medium term. In doing so, the audit examined how TfNSW and Sydney Trains know whether there is a crowding problem at stations and how they manage that crowding.

TfNSW is the lead agency for transport in NSW. TfNSW is responsible for setting the standard working timetable that Sydney Trains must implement. Sydney Trains is responsible for operating and maintaining the Sydney metropolitan heavy rail passenger service. This includes operating, staffing and maintaining most metropolitan stations. Sydney Trains’ overall responsibility is to run a safe rail network to timetable.

Conclusion

Sydney Trains has identified platform crowding as a key strategic risk, but does not have an overarching strategy to manage crowding in the short to medium term. TfNSW and Sydney Trains devolve responsibility for managing crowding at stations to Customer Area Managers, but do not have sufficient oversight to know if crowding is being effectively managed. TfNSW is delivering a program to influence demand for transport in key precincts but the effectiveness of this program and its impact on station crowding is unclear as Transport for NSW has not evaluated the outcomes of the program.

TfNSW and Sydney Trains do not directly measure or collect data on station crowding. Data and observation on dwell time, which is the time a train waits at a platform for customers to get on and off trains, inform the development of operational approaches to manage crowding at stations. Sydney Trains has KPIs on reliability, punctuality and customer experience and use these to indirectly assess the impact of station crowding. TfNSW and Sydney Trains only formally assess station crowding as part of planning for major projects, developments or events.

Sydney Trains devolve responsibility for crowd management to Customer Area Managers, who rely on frontline Sydney Trains staff to understand how crowding affects individual stations. Station staff at identified key metropolitan train stations have developed customer management plans (also known as crowd management plans). However, Sydney Trains does not have policies to support the creation, monitoring and evaluation of these plans and does not systematically collect data on when station staff activate crowding interventions under these plans.

Sydney Trains stated focus is on providing a safe and reliable rail service. As such, management of station crowding is a by-product of its strategies to manage customer safety and ensure on-time running of services. Sydney Trains' operational response to crowding involves restricting customer access to platforms or stations before crowding reaches unsafe levels, or when it impacts on-time running. As rail patronage increases, it is likely that Sydney Trains will need to increase its use of interventions to manage crowding. As Sydney Trains restrict more customers from accessing platforms or station entries, it is likely these customers will experience delays caused by these interventions.

Since 2015, TfNSW has been delivering the 'Travel Choices' program which aims to influence customer behaviour and to manage the demand for public transport services in key precincts. TfNSW is unable to provide data demonstrating the overall effectiveness of this program and the impact the program has on distributing public transport usage out of peak AM and PM times. TfNSW and Sydney Trains continue to explore initiatives to specifically address crowd management.

Conclusion

TfNSW and Sydney Trains do not directly measure or collect data on station crowding. There are no key performance indicators directly related to station crowding. Sydney Trains uses performance indicators on reliability, punctuality and customer experience to indirectly assess the impact of station crowding. Sydney Trains does not have a routine process for identifying whether crowding contributed to minor safety incidents. TfNSW and Sydney Trains formally assess station crowding as part of planning for major projects, developments or events.

 

Conclusion

Sydney Trains has identified platform crowding as a strategic risk but does not have an overarching strategy to manage station crowding. Sydney Trains' stated focus is on providing a safe and reliable rail service. As such, management of station crowding is a by-product of its strategies to manage customer safety and ensure on-time running of services.

Sydney Trains devolve responsibility for managing crowding at stations to Customer Area Managers but does not have sufficient oversight to know that station crowding is effectively managed. Sydney Trains does not have policies to support the creation, monitoring or evaluation of crowd management plans at key metropolitan train stations. The use of crowding interventions is likely to increase due to increasing patronage, causing more customers to experience delays directly caused by these activities.

TfNSW and Sydney Trains have developed interventions to influence customer behaviour and to manage the demand for public transport services but are yet to evaluate these interventions. As such, their impact on managing station crowding is unclear.

Appendix one – Response from agency

Appendix two – Sydney rail network

Appendix three – Rail services contract

Appendix four – Crowding pedestrian modelling

Appendix five – Airport Link stations case study

Appendix six – About the audit

Appendix seven – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #333 - released 30 April 2020

 

Published

Actions for Transport 2019

Transport 2019

Transport
Asset valuation
Financial reporting
Infrastructure
Internal controls and governance
Management and administration
Service delivery
Workforce and capability

This report details the results of the financial audits of NSW Government's Transport cluster for the financial year ended 30 June 2019. The report focuses on key observations and findings from the most recent financial statement audits of agencies in the Transport cluster.

Unqualified audit opinions were issued for all agencies' financial statements. However, valuations of assets continue to create challenges across the cluster. The Audit Office identified some deficiencies in relation to asset valuations at Transport for NSW, Roads and Maritime Services, Rail Corporation New South Wales and Sydney Metro.

The Audit Office noted an increase in findings on internal controls across the Transport cluster. Key themes related to information technology, asset management and employee leave entitlements. The report also highlights the status of significant infrastructure projects across the Transport cluster.

The report makes several recommendations including:

  • agency finance teams need to be consulted on major business decisions and commercial transactions at the time of their execution to assess the financial reporting impacts
  • the Department of Transport should ensure consistent accounting policies are applied across its controlled entities.

Download the Transport 2019 report (PDF)

This report analyses the results of our audits of financial statements of the Transport cluster for the year ended 30 June 2019. The table below summarises our key observations.

1. Machinery of Government changes
Transport for NSW, as the
lead agency, will absorb the
functions of Roads and
Maritime Services

The NSW Government announced its intention to integrate Roads and Maritime Services (RMS) into Transport for NSW (TfNSW) as part of the Machinery of Government changes.

This change was not included in the Administrative Orders as the Transport Administration Act 1988 No. 109 governs the composition of the Transport cluster. The Transport Administration Amendment (RMS Dissolution) Act 2019 (the Act) received assent on 22 November 2019. The Act dissolves RMS and transfers the assets, rights and liabilities of RMS to TfNSW. As at the date of this Report, the Act is not yet in force.

Transport is considering the impact of the changes on its operating model and financial reporting.

2. Financial reporting
Audit opinions

Unqualified audit opinions were issued on the 2018–19 financial statements of all agencies in the Transport cluster.

TfNSW and Sydney Metro obtained a three-week extension from NSW Treasury to submit their financial statements for audit to resolve accounting issues surrounding the valuation of property, plant and equipment.

The Department of Transport reported total consolidated property, plant and equipment of $158 billion at 30 June 2019. In 2018–19, there were issues with asset valuations at TfNSW, RMS, Sydney Metro and Rail Corporation New South Wales (RailCorp), resulting in adjustments after the submission of financial statements for audit and the correction of a prior period error.

There was also a prior period error resulting from an agreement between TfNSW and the former UrbanGrowth Development Corporation due to a lack of assessment of the financial reporting implications at the time of signing the agreement.

Recommendation: Agency finance teams need to be consulted on major business decisions and commercial transactions to assess their accounting impacts at the time of their execution, rather than at the end of a financial year. Agencies also need to resolve all key accounting issues such as valuations as part of the early close procedures.

This would improve the quality of financial reporting and avoid the need for extensions for agencies to submit their financial statements for audit.

Preparedness for new
accounting standards
Agencies across the cluster are progressing in their implementation of the new accounting standards.

Transport cluster agencies need to improve their contracts registers to ensure they have a complete list of contracts and agreements to assess the impact of the new accounting standards.
Valuation of assets remains
a challenge in the
Transport cluster

Whilst agencies complied with the requirements of the accounting standards and NSW Treasury policies on valuations, the Audit Office identified some deficiencies in relation to asset valuations across the cluster.

TfNSW reported a retrospective correction of a prior period error at 1 July 2017 which resulted in a reduction in the valuation of its Country Rail Network earthworks by $2.1 billion. This was due to survey results which identified the earthworks were flatter and lower than estimated in the valuation at 30 June 2017.

RMS made several adjustments during the year to correct asset values due to changes to valuation assumptions or data improvements. This included:

  • reduction of $318 million in the value of land under roads
  • decrease of $84.9 million to the value of land and buildings
  • changes to the value of traffic control and traffic signal network assets, due to data improvements.

Sydney Metro North West officially opened in May 2019 and reported total assets of $9.1 billion. Sydney Metro derecognised $322 million in assets constructed to facilitate its operation but transferred to councils and utilities.

Inconsistent accounting
policies across the
Transport cluster

There was an inconsistency identified in the cluster relating to the valuation of substratum land. In 2018–19, RailCorp derecognised $109 million of substratum land to ensure consistency in its approach with other Transport agencies.

As the parent entity, the Department of Transport needs to ensure accounting policies are consistently applied across all controlled entities for consolidation purposes. Inconsistencies in the application of accounting standards across agencies will impact comparability of financial reporting and decision making across the Transport cluster.

Recommendation: The Department of Transport should ensure consistent accounting policies are applied across its controlled entities.

Revenue growth

Public transport passenger revenue increased by $89.0 million (5.9 per cent) in 2018–19, and patronage increased by 37.8 million (4.9 per cent) across all modes of transport based on data provided by TfNSW.

The increase in revenue is mainly due to an increase in patronage as well as the annual increase in fares.

Negative Opal cards

Negative balance Opal cards resulted in $2.9 million in revenue not collected in 2018–19 ($10.4 million since the introduction of Opal).

In January 2019, Transport made a change to the Sydney Airport stations to prevent customers with high negative balances exiting the station. In addition, in late 2018, Transport increased the minimum top up values for new cards at the airport stations.

Recommendation (repeat): TfNSW should implement further measures to prevent the loss of revenue from passengers tapping off with negative balance Opal cards.

3. Audit observations
Internal controls There was an increase in findings on internal controls across the Transport cluster. Key themes relate to information technology, employee leave entitlements and asset management.

Twenty-nine per cent of all issues were repeat issues. The majority of the repeat issues related to information technology controls.
Write-off of assets In addition to a $322 million derecognition of assets transferred to councils and utilities by Sydney Metro and a $109 million derecognition of substratum land at RailCorp, the Transport cluster wrote-off $278 million of assets related to roads, bridges, maritime assets, traffic signals and controls network.

These mainly related to roads, bridges, maritime assets, traffic signals and the control network where new infrastructure assets substantially replaced an existing asset as part of construction activities.
Transport Asset Holding
Entity (TAHE)
TAHE was established to be a dedicated asset manager for the delivery of public transport asset management. The Transport Administration Amendment (Transport Entities) Act 2017 will transition RailCorp into TAHE. RailCorp is now expected to transition to TAHE from 1 July 2020 (previously 1 July 2019). Several working groups have been considering various aspects of the TAHE transition including its status as a for profit Public Trading Enterprise, the operating model and the impact of the new accounting standards AASB 16 'Leases' and AASB 1059 'Service Concession Arrangements: Grantors'. The considerations of these aspects identified several challenges in the implementation of TAHE which has led to the revised transition date. Given the delays in implementation, it is important to clarify the intent of the TAHE model.
Excess annual leave

Twenty-six per cent of Transport employees have annual leave balances exceeding 30 days. Of the employees with excess leave balances, 732 (10.3 per cent) did not take any annual leave in 2018–19.

Recommendation (repeat): Transport entities should further review the approach to managing excess annual leave in 2019–20. They should:

  • monitor current and projected leave balances to the end of the financial year each month
  • agree formal leave plans with employees to reduce leave balances over an acceptable timeframe
  • ensure leave plans are actioned appropriately
  • encourage all staff with excess leave balances take a minimum two-week period of leave per year.
Completeness and
accuracy of contracts
registers

There are no centralised processes to record all significant contracts and agreements in a register across the Transport cluster.

Across the Transport cluster, contracts and agreements are maintained by the individual agencies using disparate registers. Agencies must perform detailed assessments of their existing contracts and agreements to quantify the impact of the new accounting standards (AASB 16 ‘Leases’, AASB 15 ‘Revenue from Contracts with Customers’, AASB 1058 ‘Income of Not-for-Profit Entities’ and AASB 1059 'Service Concession Arrangements: Grantors').

In 2018–19, there was also a prior period error resulting from an agreement between TfNSW and another government agency due to a lack of assessment of the financial reporting implications at the time of signing the agreement.

A lack of a complete register of all contracts and agreements increases the risk that agencies may not be able to assess the full impact of the new accounting standards, as well as perform a complete assessment of the financial reporting implications of contracts and agreements.

Recommendation: Transport agencies should implement a process to centrally capture all significant contracts and agreements entered. This will ensure:

  • agencies are fully aware of contractual and other obligations
  • appropriate assessment of financial reporting implications
  • assessment of new accounting standards, in particular AASB 16 ‘Leases’, AASB 15 'Revenue from Contract with Customers', AASB 1058 'Income of Not-for-Profit Entities ' and AASB 1059 'Service Concession Arrangements: Grantors' are accurate and complete.

 

This report provides parliament and other users of the Transport cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

This cluster was impacted by the Machinery of Government changes on 1 July 2019. The NSW Government announced its intention to integrate Roads and Maritime Services (RMS) into Transport for NSW (TfNSW). This report is focused on the Transport cluster prior to these changes. Please refer to the section on Machinery of Government changes for more details.

Machinery of Government refers to how the government organises the structures and functions of the public service. Machinery of Government changes are where the government reorganises these structures and functions, and are given effect by Administrative orders.

The Transport cluster was impacted by recent Machinery of Government changes. These changes were announced by the Department of Premier and Cabinet but were not included in the Administrative Orders as the Transport Administration Act 1988 No. 109 governs the composition of the Transport cluster. It was the intention of government to transfer the functions of the RMS into TfNSW. This requires legislative changes to the Transport Administration Act 1988 No. 109.

Section highlights

Under the Machinery of Government changes, the NSW Government will transfer the functions of RMS into TfNSW.

  • The Transport Administration Amendment (RMS Dissolution) Act 2019 (the Act) received assent on 22 November 2019.
  • The Act will dissolve RMS and transfer its functions, assets, rights and liabilities to TfNSW.
  • As at the date of this report, the Act is not yet in force.
  • There are risks and challenges for asset and liability transfers, governance and retention of knowledge.
  • As of 1 July 2019, administrative arrangements (delegations and reporting line changes) were put in place to enable TfNSW and RMS to operate within a single management structure, while still remaining as separate legal entities.
  • Transport is working on a number of options as to how to implement the changes. 

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Transport cluster for 2019.

Section highlights

  • Unqualified audit opinions were issued on all agencies' financial statements.
  • RMS required an extension from NSW Treasury for their early close procedures.
  • TfNSW and Sydney Metro required extensions to submit their year-end financial statements.
  • Valuation of assets remains a challenge across the cluster.
  • There remains Opal cards with negative balances.
  • Sydney Metro derecognised assets of $322 million in relation to assets constructed for third parties.
  • Inconsistencies in the application of accounting policies across cluster agencies impact comparability of financial reporting across the Transport cluster.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our observations and insights from our financial statement audits of agencies in the Transport cluster.

Section highlights

  • There was an increase in findings on internal controls across the Transport cluster. Twenty-nine per cent of all issues were repeat issues.
  • Transport entities wrote-off over $278 million of assets which were replaced by new assets or technology.
  • Twenty-six per cent of Transport employees have excess annual leave.
  • There are no processes to ensure all significant contracts and agreements are captured by agencies in a centralised register.

Appendix one – Timeliness of financial reporting by agency 

Appendix two – Management letter findings by agency 

Appendix three – List of 2019 recommendations 

Appendix four – Status of 2017 and 2018 recommendations 

Appendix five – Cluster agencies 

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Health 2019

Health 2019

Health
Asset valuation
Compliance
Financial reporting
Fraud
Information technology
Internal controls and governance
Management and administration
Procurement
Project management

This report focuses on key observations and findings from the most recent financial audits of the Ministry of Health, local health districts, specialty health networks, health corporations and independent health agencies in New South Wales. The report also summarises self-reported performance measures across the network.

The number and value of adjustments to financial statements of entities in the Health Cluster decreased from the prior year. And unqualified audit opinions were issued for all heath entities’ financial statements.

Audit findings relating to internal controls deficiencies increased across health entities. Contributing to this increase were deficiencies in information system controls, which accounted for nearly a quarter of all control deficiencies. Repeat audit findings also accounted for more than a quarter of all control deficiencies.

The report notes health entities continued to experience challenges with managing employees’ excessive annual leave and time recording practices. The Ambulance Service of New South Wales continued to report high overtime payments to its employees. 

Download Health 2019 report (PDF).

This report analyses the results of our audits of financial statements of the agencies comprising the Health cluster for the year ended 30 June 2019. The table below summarises our key observations.

1. Machinery of Government changes

Cluster changes Machinery of Government (MoG) changes refer to how the government reorganises agency structures and functions and realigns ministerial responsibilities. The Health cluster was not impacted by the MoG changes.

2. Financial reporting

Financial reporting

The financial statements of NSW Health and its controlled entities received unqualified audit opinions before the legislative deadline.

The number of corrected and uncorrected misstatements decreased from the prior year.

Management implemented more robust processes for its oversight of complex asset revaluations in 2018–19. We found no significant errors in 2018–19.

Financial performance Overall, NSW Health recorded an operating surplus of $1.1 billion in 2018–19, an increase of $699 million from 2017–18. This was the result of additional funding received for capital expenditure on the construction of new facilities, upgrades and redevelopments.

Budgeted expense for the 15 local health districts and two speciality networks increased from $18.3 billion to $19.4 billion in 2018–19. The 15 health entities recorded unfavourable variances between actual and budgeted expenses.
Excess annual leave

Managing excess annual leave remains a challenge for NSW Health, 36.9 per cent of the workforce have excess annual leave balances.

Recommendation: Health entities should further review their approach to managing excess annual leave in 2019–20, and:

  • monitor current and projected leave balances to the end of the financial year on a monthly basis
  • agree formal leave plans with employees to reduce leave balances over an acceptable timeframe
  • encourage staff who perform key control functions to take at least two consecutive weeks’ leave a year to mitigate fraud risks.
Overtime payments NSW Health entities generally manage overtime well. The Ambulance Service of NSW’s overtime payments of $83.1 million (9.8 per cent of total salaries and wages), remain significantly higher than other health entities.

Recommendation: The Ambulance Service of NSW should further review the effectiveness of its rostering practices to identify strategies to reduce overtime payments.

3. Audit observations

Internal control deficiencies We identified more internal control deficiencies in 2018–19. The number of repeat issues from prior years also remains high with more than one quarter of issues having been previously reported. More than a quarter of deficiencies related to information system controls.
Infrastructure delivery NSW Health defines projects with a budgeted cost greater than $50.0 million as 'major projects'. There were significant revisions to planned financial completion dates and budgeted costs of these projects. The revised total budgets for the 30 ongoing major capital projects at 30 June 2019 is $10.2 billion, $2.2 billion more than the original budget.
Health Infrastructure completed three major capital projects during 2018–19.
Asset maintenance The total cost of maintaining the health entities’ $19.8 billion of assets was $635 million for 2018–19. Health entities' approaches to setting maintenance budgets vary. Most entities are addressing their backlog maintenance, although many were not able to quantify the full extent of their backlog maintenance. Although health entities continue to use fully depreciated assets, the replacement cost of these assets is decreasing.

 

 

This report provides parliament and other users of the financial statements of agencies within the Health cluster with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas for the year ended 30 June 2019:

  • financial reporting
  • audit observations. 

 The Health cluster was not impacted by the Machinery of Government changes on 1 July 2019. 

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the health cluster for 2019.

Section highlights

  • We issued unqualified audit opinions for all health entities’ financial statements and identified fewer misstatement than last year. Health entities continue to meet statutory deadlines.
  • The Ministry of Health sets significant accounting policies centrally and provides a template for the preparation of health entities’ financial statements. These processes promote consistent quality in the financial reports of health entities and reduce the number of misstatements we identify.
  • NSW Health recorded an operating surplus of $1.1 billion, an increase of $699 million from 2017–18. This is because of additional capital grants for new facilities, upgrades and redevelopments. The capital replacement ratio (investment in new assets divided by depreciation) for NSW Health is 2.6.
  • NSW Health’s expenses increased by 7.0 per cent in 2018–19 (5.5 per cent in 2017–18). This is one percentage point higher than the projected long-term annual expense growth rate of six per cent. The primary causes for the growth in expenses are increased:
    • employee related expenses because provisions for employee benefits increased when the discount rate decreased
    • operating expenses associated with the opening of Northern Beaches Hospital.
  • Excess annual leave balances continue to increase for the NSW Health workforce, with excess annual leave balances impacting 37 per cent of employees (34 per cent in 2017–18).
  • Health entities should further review their approach to managing excess annual leave in 2019–20 by monitoring current and projected leave balances on a regular basis, agreeing formal leave plans with employees and encouraging staff that perform key control functions to take a minimum of two consecutive weeks’ leave a year as a fraud mitigation strategy.
  • The Ambulance Services continued to report overtime payments higher than other health entities. The Ambulance Service paid its employees $83.1 million in overtime payments in 2018–19 ($74.8 million in 2017–18).
  • We issued a qualified audit opinion for the Ministry of Health's Annual Prudential Compliance Statement for aged care facilities operated by NSW Health. We identified 40 instances of material non-compliance with the Fees and Payments Principles 2014 (No. 2) (the Principles) in 2018–19 (17 in 2017–18).

Audit opinions 

We issued unqualified audit opinions for all health entities and quality of financial reporting continues to improve

We identified fewer misstatements this year, and the errors were less significant. In 2018–19 no errors exceeded $5.0 million (eight errors recorded in 2017–18). Ten health entities conducted a full revaluation of their land, buildings and infrastructure systems in 2018–19, but more robust processes avoided the errors identified in the previous year.

Number of misstatements
Year ended 30 June 2019 2018 2017
  green circle with white tick red circle with white exclamation mark green circle with white tick red circle with white exclamation mark green circle with white tick red circle with white exclamation mark
Less than $50,000 -- -- -- 6 3 3
$50,000 to $249,999 -- 1 -- -- 2 3
$250,000 to $999,999 1 -- -- -- 1 3
$1 million to $4,999,999 -- 2 -- 2 1 5
$5 million and greater -- -- 6 2 1 2
Total number of misstatements 1 3 6 10 8 16

green circle white tick Corrected mistatements. red circle white exclamation mark Uncorrected statements.
Source: Statutory Audit Reports issued by the Audit Office.

We issued a qualified audit opinion for our compliance audit of the Ministry of Health's Annual Prudential Compliance Statement

The Ministry of Health operates eight aged care facilities in NSW and is required to comply with the Fees and Payments Principles 2014 (No. 2) (the Principles) when entering into agreements with and managing payments to and from care recipients. The Principles are set by the Commonwealth Assistant Minister for Social Services. We identified 40 instances of material non-compliance in 2018–19, including:

  • not agreeing maximum accommodation amounts payable with aged care recipients before they entered the residential care services
  • not entering into accommodation agreements with care recipients within the specified period
  • charging incorrect fees for activities or services to one care recipient
  • not refunding two bond balances within the statutory framework
  • not paying the correct amount of interest for 14 care recipients’ bonds refunded during the year.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our observations and insights from our financial statement audits of agencies in the health cluster.

Section highlights

  • The number of internal control deficiencies has increased since 2017–18. More than a quarter of control deficiencies are repeat issues and almost a quarter relate to information system controls. Both employee time recording and leave management remain as repeat issues in 2018–19.
  • Control deficiencies that relate to managing employees' leave, employees’ time recording or information system limitations can be difficult for entities to resolve in a timely manner.
  • Agreements for the treatment of New South Wales residents while they are interstate, and interstate residents while they are in New South Wales, are unsigned for Queensland, Victoria and the Australian Capital Territory for 2016–17, 2017–18 and 2018–19.
  • NSW Health recorded $113.6 million in revenue from fees charged to Medicare ineligible patients during 2018–19 but has received payment for less than half of this.
  • NSW Health reported that they completed three major capital projects during 2018–19.
  • As at 30 June 2019 there were 30 ongoing major capital health projects in NSW. The revised capital budget for these projects in total was $2.2 billion more than the original budget of $8.0 billion.
  • Health entities spent $635 million maintaining assets with a fair value of $19.8 billion of assets. Almost all entities were working through backlog maintenance during 2018–19, although several were unable to quantify the backlog.
  • While entities are now regularly reassessing the useful lives of their assets, entities are still using a high volume of assets that are fully depreciated. Due to the age and nature of these assets the impact was not material.

Appendix one – List of 2019 recommendations

Appendix two – Status of 2018 recommendations

Appendix three – Financial data 

Appendix four – Analysis of financial indicators

Appendix five – Analysis of performance against budget

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.