Reports

Published

Actions for Volume Ten 2015 Health

Volume Ten 2015 Health

Health
Information technology
Internal controls and governance
Project management
Risk

NSW Health, on average, met the emergency department triage response time targets across all triage categories in 2014-15 for the second consecutive year. However, fewer health entities met all triage targets in 2014-15, according to a report released by the New South Wales Acting Auditor-General, Tony Whitfield. 
 
NSW Health improved its emergency department treatment performance in 2014-15, but did not achieve its target of 81 per cent of patients being admitted, transferred or discharged within four hours of presenting. In 2014-15, the State average was 74.3 per cent compared to 73.9 per cent in 2013-14. Only five local health districts achieved the 81 per cent target in 2014-15.

Published

Actions for Volume Six 2015 Transport

Volume Six 2015 Transport

Transport
Information technology
Internal controls and governance
Project management
Risk

Public transport revenue decreased by 2.7 per cent despite a fare increase and increased patronage. Twenty-five per cent of all Opal trips (over 74 million) were free, including 47 per cent of trips on ferries, according to a report released today by the New South Wales Acting Auditor-General, Tony Whitfield. These trips were valued at $189 million.

Published

Actions for Volume Four 2015 Treasury and State Finances

Volume Four 2015 Treasury and State Finances

Treasury
Whole of Government
Asset valuation
Compliance
Financial reporting
Internal controls and governance

For the third consecutive year, the General Government and Total State Sector Accounts received an unqualified auditor’s opinion following more than a decade of qualifications.
 
Errors in agencies’ financial statements and the Total State Sector Accounts were corrected as necessary to ensure compliance with Australian Accounting Standards and the requirements of the Public Finance and Audit Act 1983.
 
Improvements to year-end financial reporting processes have enabled the Audit Office to issue 229 audit opinions by 2 October 2015, compared to only 67 by the same time in 2011.

Published

Actions for Albert 'Tibby' Cotter Walkway

Albert 'Tibby' Cotter Walkway

Transport
Internal controls and governance
Procurement
Project management

On 17 September 2015, the Acting Auditor-General of New South Wales, Tony Whitfield, released a report on the Albert ‘Tibby’ Cotter Walkway which crosses over Anzac Parade in Moore Park. The Walkway’s primary function is to cater for event patrons in the precinct. Moore Park is listed on the State Heritage Register and is an open space specifically established to cater for public recreation.
 
Roads and Maritime Services (RMS) delivered the Walkway to an extremely tight timeframe. It was operational for the 2015 Cricket World Cup at the Sydney Cricket Ground as promised by the government. However, the World Cup deadline added substantially to the total cost of the Walkway, which is projected to be $38 million.
 
Transport for NSW and RMS could not provide evidence of a compelling economic or financial argument to support the construction of the Walkway or for the tight deadline. Also, the processes they adopted to provide assurance of the project’s value for money were not adequate.

 

Parliamentary reference - Report number #260 - released 17 September 2015

Published

Actions for Sydney metropolitan bus contracts

Sydney metropolitan bus contracts

Transport
Internal controls and governance
Management and administration
Procurement
Project management
Service delivery

On 9 September 2015, the Acting Auditor-General of New South Wales, Tony Whitfield, released a report on Sydney Metropolitan Bus Service Contracts.
 
All scheduled bus services in the Sydney metropolitan area are provided under contracts with the public and private operators. The contracts allow Transport for NSW (TfNSW) to determine what bus services are provided and to whom. This audit assessed the effectiveness of TfNSW’s design and management of these contracts.
 
Bus services provided under the Sydney Metropolitan Bus Service Contracts have largely been effective and efficient. Operators are mostly meeting their key performance indicators. Customer satisfaction is better than under the previous contracts and improving, patronage is increasing, and the unit costs of providing services are now lower than under the previous contracts. 
 
However, punctuality remains a problem. Private operators are mostly starting their trips on time, but rarely meeting their mid and end-of-trip targets. State Transit Authority’s (STA) punctuality is improving but is worse than private operators, and other areas of performance are generally below private operators.
 
The current situation is a substantial improvement over what we found in our 2010 audit on the previous contracts.

 

Parliamentary reference - Report number #258 - released 9 September 2015

Published

Actions for Large construction projects

Large construction projects

Treasury
Transport
Health
Industry
Planning
Premier and Cabinet
Whole of Government
Compliance
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management

The independent assurance given to the NSW Government and sponsor agencies on the viability of large capital projects throughout their lifecycle is inadequate. Government policy is regularly not followed and not properly communicated to those responsible for implementing such policy.
 
This audit sought to test the effectiveness of the NSW capital project assurance system - which includes gateway reviews and reporting - but significant levels of non-compliance identified in our case studies prevented this. The NSW Commission of Audit also identified this issue in 2012. Gateway reviews are conducted by independent reviewers at key stages of a project’s life cycle and provide an independent assessment on a project’s readiness to proceed to the next stage.

 

Parliamentary reference - Report number #252 - released 7 May 2015

Published

Actions for Areas of focus from 2014

Areas of focus from 2014

Education
Community Services
Finance
Health
Industry
Justice
Local Government
Planning
Premier and Cabinet
Transport
Treasury
Universities
Whole of Government
Environment
Compliance
Financial reporting
Fraud
Information technology
Internal controls and governance
Procurement
Project management
Risk

The 2014 audits showed that the quality and timeliness of financial reporting have continued to improve. However, many agencies do not have financial sustainability indicators that provide early warning of management issues, such as an inability to meet financial obligations. Weaknesses were identified in information security, management of leave balances, asset management and internal controls.
 
Governance issues and gaps in performance information and reporting across the sector suggest Chief Financial Officers should have a stronger role and be more involved in strategy and risk management to maximise performance and add value.
 

Published

Actions for Electronic Procurement of Hospital Supplies

Electronic Procurement of Hospital Supplies

Health
Information technology
Management and administration
Procurement

Reform of procurement in the NSW public health system is a huge, complex and difficult task. Much thought has been given to this reform. An immense amount of planning and preparatory work is required, and is apparent. In our opinion, at this time, the NSW public health system is making only limited progress towards achieving the economies in purchasing that its size and market dominance could deliver. While millions of dollars in savings are potentially available, much needs to be done to realise this. It is critical that all those involved, at all levels, ensure that reform is given priority, and driven through to fruition.

 

Parliamentary reference - Report number #102 - released 25 September 2002

Published

Actions for Bus Maintenance and Bus Contracts

Bus Maintenance and Bus Contracts

Transport
Management and administration
Procurement
Service delivery

State Transit has developed fleet management plans and maintenance standards that meet its regulatory and contractual obligations as a bus operator and are consistent with vehicle manufacturers’ standards and best practice. However, assumptions used in fleet management plans to forecast fleet growth may not result in the most efficient and effective outcome for State Transit. Forecasts fail to take account of opportunities to redesign or reduce services where they exceed contract requirements and are difficult to justify on a commercial basis. Of greater concern are the consequences arising from bus maintenance practices not meeting State Transit’s own standards.

 

Parliamentary reference - Report number #97 - released 29 May 2002

Published

Actions for Sale of the TAB

Sale of the TAB

Treasury
Internal controls and governance
Procurement

The Audit Office is of the opinion that:

  • the sale was delivered with reasonable efficiency and effectiveness

  • the sale yielded a satisfactory return to the NSW Government. The possibility for a higher return was limited to about 2% to 4% on gross proceeds of $936m. It would have required setting a higher share price for all investors and adopting a more flexible approach to share allocation

  • the Government’s objective to promote community and investor support was achieved. The scale of the demand for script added to costs and was not fully translated into higher proceeds  

  • generally satisfactory accountability frameworks were put in place for the sale and no probity concerns were identified

  • the frameworks to achieve the Government’s wider reforms of the racing and wagering industries have substantially been implemented.

 

Parliamentary reference - Report number #61 - released 23 December 1998