Actions for WestConnex: Assurance to the Government
WestConnex: Assurance to the Government
This audit assesses the assurance provided to the NSW Government for the initial stages of the WestConnex project.
The audit examined the WestConnex project from concept development to the pre-tender phase for Stage 1A – M4 (Parramatta to Homebush Bay). It did not examine the merit of the project or whether it represented value-for-money.
This audit found a number of shortcomings with the governance of the WestConnex project during its early stages and makes recommendations on how to better govern the remainder of the project to minimise the risk of failure.
Parliamentary reference - Report number #247 - released 18 December 2014
Actions for Regional Road Funding - Block Grant and REPAIR Programs
Regional Road Funding - Block Grant and REPAIR Programs
In 2013–14, Roads and Maritime Services (RMS) provided over $170 million to local councils through the Block Grant and REPAIR programs to spend on Regional Roads. Regional Roads are the link between State Roads and Local Roads.
Parliamentary reference - Report number #241 - released 8 May 2014
Actions for Improving road safety: Young drivers
Improving road safety: Young drivers
The audit concluded that the RTA’s licence testing and regulation has been generally effective in ensuring the safety of young drivers. There has been a significant reduction in crash and fatality rates involving young drivers over the last decade, more so than for drivers 26 years and older. This has coincided with the introduction by the RTA of an enhanced GLS. International and national research has demonstrated graduated licensing systems to be effective in reducing crashes and saving lives. Despite these improvements, young drivers are more likely to be involved in fatal crashes than other drivers.
Parliamentary reference - Report number #217 - released 19 October 2011
Actions for Prequalification Scheme: Performance and Management Services
Prequalification Scheme: Performance and Management Services
There have been tangible improvements in the time it takes NSW Government agencies to engage consultants through the Government’s Prequalification Scheme. The Scheme was introduced in February 2008 to improve agencies’ procurement of consultants. More than 300 service providers have been prequalified and over $300 million worth of consultancy services have been provided. Ideally agencies should know what assignments each consultant has won, for what services, what their rates are and how well they have performed. Agencies should then be free to contact other agencies before engaging a consultant.
Parliamentary reference - Report number #216 - released 28 September 2011
Actions for Improving Road Safety: Speed Cameras
Improving Road Safety: Speed Cameras
We found that fixed speed cameras were generally located in areas with high road safety risk. Likewise, safety cameras that enforced speed limits were initially placed at high risk sites. However as all safety cameras will now enforce speed, RTA no longer uses evidence of a speeding problem to select these sites. Overall, total crashes and injuries each fell 26 per cent, and fatalities fell by more than two-thirds, in the three years after the installation of fixed speed camera. Long term trends show that these reductions have been maintained, the average number of speeding fines per fixed and safety cameras declines over time and fixed and safety speed cameras were located in areas with high road safety risk.
Parliamentary reference - Report number #215 - released 27 July 2011
Actions for Government expenditure and transport planning in relation to implementing Barangaroo
Government expenditure and transport planning in relation to implementing Barangaroo
Barangaroo is an ambitious and significant development on Government-owned Sydney Harbour foreshore. Construction on the 22 hectare CBD site is expected to take 12 years to 2023. Developer contributions to Government of $1 billion are to provide for public domain and other Government development costs, including a six hectare Headland Park. When completed the precinct is to service an anticipated 26,000 workers and residents and up to 33,000 visitors a day. The Auditor-General concluded that while there was extensive transport planning and extensive documentation supporting Government financial forecasts, considerable risks remain for the implementation of the Barangaroo project.
Parliamentary reference - Report number #214 - released 15 June 2011
Actions for Transport of Dangerous Goods
Transport of Dangerous Goods
Dangerous goods make up 10-15% of domestic freight and have potential to harm people, property and the environment. They include substances such as explosives, flammable liquids and gases, and oxidising agents. However, Government inspection programs were limited. The Office of Environment and Heritage carried out very few checks in the four years up to 2010, with no inspections made in the metropolitan area. This is despite Port Botany handling around 50,000 containers of dangerous goods per year. Statewide, only 303 inspections were made in 2009/10 and only 20 in 2008/09.
Parliamentary reference - Report number #212 - released 10 May 2011
Actions for Implementing Successful Amalgamations
Implementing Successful Amalgamations
The Better Practice Guide (BPG) aims to provide guidance for those implementing an amalgamation. It provides a series of questions identifying what needs to be done to achieve a successful amalgamation following the formal announcement of the amalgamation and the Administrative Orders for the new arrangements being finalised. The BPG’s aim is to alert those managing an amalgamation to actions that should be considered. How the Guide is applied will depend on circumstances. A lot will depend on how clear the expectations of the amalgamation are and on how complex it is.
Parliamentary reference - Report number #176 - released 5 March 2008
Actions for Managing Departmental Amalgamations
Managing Departmental Amalgamations
Both Commerce and DPI substantially achieved their stated amalgamation savings objectives as set by government. The departments are expected to achieve savings targets of about $150 million and $190 million respectively over their first four years. Our analysis indicates that there are two key factors in successful amalgamations. The first is effective early planning by departments based on clear objectives, supported by quick action. Second, significant synergies in service delivery can be achieved when departments with similar services and customers are amalgamated. The Department of Primary Industries is an example.
Parliamentary reference - Report number #175 - released 5 March 2008
Actions for Condition of State Roads
Condition of State Roads
The Roads and Traffic Authority (RTA) has improved the overall surface condition of State Roads in the last decade. Country road surfaces are now generally much better. Ride quality has improved and cracking has been reduced. The RTA has also achieved a substantial reduction in the number of structurally deficient bridges over the same period.
Despite a significant increase in the State’s contribution to maintenance since 1999-2000, the RTA has deferred road rebuilding projects. The RTA is rebuilding at less than half its long term target, and has not met this target at any time this decade. The RTA has not identified how it will address deferred rebuilding, although it advises it is developing a new road network management plan which will address this.
Parliamentary reference - Report number #157 - released 16 August 2006