Actions for Service NSW's handling of personal information

Service NSW's handling of personal information

Premier and Cabinet
Finance
Cyber security
Fraud
Information technology
Internal controls and governance
Management and administration
Risk
Service delivery

The Auditor-General for New South Wales, Margaret Crawford, released a report today examining the effectiveness of Service NSW’s handling of customers’ personal information to ensure its privacy.

The audit found that Service NSW is not effectively handling personal customer and business information to ensure its privacy. Service NSW continues to use business processes that pose a risk to the privacy of personal information. This includes the routine emailing of personal information between Service NSW service centres and other agencies, which is one of the processes that contributed to the data breach earlier this year. The audit found that previously identified risks and recommended solutions had not been implemented on a timely basis.

The Auditor-General made eight recommendations aimed at ensuring improved processes, technologies, and governance arrangements for how Service NSW handles customers’ personal information.

The Hon. Victor Dominello, MP, Minister for Customer Service, requested this audit under section 27(B)(3)(c) of the Public Finance and Audit Act 1983 following public reports in May 2020 of a cyber security attack which had led to a breach of Service NSW customer information. This audit also included the Department of Customer Service which supports Service NSW with privacy, risk and governance functions.

Service NSW was established in 2013 with the intention that it would, over time, 'become the primary interaction point for customers accessing New South Wales Government transaction services'.

Service NSW's functions are set out in the Service NSW (One stop Access to Government Services) Act 2013. This legislation allows for other NSW Government agencies to delegate to and enter into agreements with the Chief Executive Officer of Service NSW in order for Service NSW to undertake service functions for the agency.

Service NSW now has agreements with 36 NSW Government client agencies to facilitate over 1,200 types of interactions and transactions for the community.

The nature of each agreement between Service NSW and its client agencies varies. Some client agencies have delegated authority to allow Service NSW staff to conduct transactions on their behalf in the agencies' systems. Other arrangements do not include the same degree of delegation. In these cases, Service NSW provides services such as responding to enquiries and validating documents.

In addition, Service NSW conducts transactions for its own programs, such as the Seniors Card. Personal information for these programs, as well as information for customers' MyServiceNSW accounts, are stored by Service NSW on its Salesforce Customer Relationship Management (CRM) system.

In March 2020, Service NSW suffered two cyber security attacks in short succession. Technical analysis undertaken by the Department of Customer Service (DCS) concluded that these attacks resulted from a phishing exercise through which external threat actors gained access to the email accounts of 47 staff members. These attacks resulted in the breach of a large amount of personal customer information that was contained in these email accounts. See Section 1.1 for further details.

This audit is being conducted in response to a request from the Hon. Victor Dominello, Minister for Customer Service, under section 27B(3)(c) of the Public Finance and Audit Act 1983. Minister Dominello requested that the Auditor General conduct a performance audit in relation to Service NSW's handling of sensitive customer and business information.

This audit assessed how effectively Service NSW handles personal customer and business information to ensure its privacy.

It addressed the following:

  • Does Service NSW have processes and governance in place to identify and manage risks to the privacy of personal customer and business information?
  • Does Service NSW have policies, processes and systems in place that support the effective handling of personal customer and business information to ensure its privacy?
  • Has Service NSW effectively implemented its policies, processes and systems for managing personal customer and business information?

Conclusion

Service NSW is not effectively handling personal customer and business information to ensure its privacy. It continues to use business processes that pose a risk to the privacy of personal information. These include routinely emailing personal customer information to client agencies, which is one of the processes that contributed to the March 2020 data breach. Previously identified risks and recommended solutions had not been implemented on a timely basis.

Service NSW identifies privacy as a strategic risk in both its Risk Management Guideline and enterprise risk register and sets out a zero level appetite for privacy risk in its risk appetite statement. That said, the governance, policies, and processes established by Service NSW to mitigate privacy risk are not effective in ensuring the privacy of personal customer and business information. While Service NSW had risk identification and management processes in place at the time of the March 2020 data breach, these did not prevent the breach occurring.

Some of the practices that contributed to the data breach are still being followed by Service NSW staff. For example, business processes still require Service NSW staff to scan and email personal information to some client agencies.

The lack of multi factor authentication has been identified as another key contributing factor to the March 2020 data breach as this enabled the external threat actors to gain access to staff email accounts once they had obtained the user account details through a phishing exercise. Service NSW had identified the lack of multi factor authentication on its webmail platform as a risk more than a year prior to the breach and had committed to addressing this by June 2019. It was not implemented until after the breach occurred.

There are weaknesses in the general IT and security controls implemented by Service NSW over its Salesforce Customer Relationship Management (CRM) system, which holds the personal information of over four million NSW residents.

Internal audits carried out by Service NSW, including one completed in August 2020, have identified significant weaknesses in the general IT and security controls implemented by Service NSW over its Salesforce CRM system. These include deficiencies in the management of role based access, monitoring and audit of user access, and partitioning of program specific transaction information. These deficiencies create an increased risk of unauthorised access to the personal information of over four million customers held in the system.

Lines of responsibility for meeting privacy obligations are not clearly drawn between Service NSW and its client agencies.

Service NSW has agreements in place with client agencies. However, the agreements lack detail and clarity about the roles and responsibilities of the agencies in relation to the collection, storage and security of customer's personal information. This lack of clarity raises the risk that privacy obligations will become confused and missed between the agencies.

Service NSW carries out privacy impact assessments for major new projects but does not routinely review existing processes and systems.

Service NSW carries out privacy impact assessments as part of its routine processes for implementing major new projects, ensuring that privacy management is considered as part of project design. Service NSW does not regularly undertake privacy impact assessments or reviews of existing or legacy processes and systems, which has resulted in some processes continuing despite posing significant risks to the privacy of personal information, such as the scanning, emailing, and storing of identification documents.

1. Key findings

Service NSW identifies privacy risks, but the controls and processes it put in place to mitigate these privacy risks were not adequate to prevent or limit the extent of the data breach that occurred in March 2020

Service NSW’s approach to risk management is framed by its Risk Management Guideline, which defines 'privacy and compliance' as one of the key types of risk for the agency. Service NSW's enterprise risk register identifies four strategic privacy related risks. Service NSW has set out a zero level appetite for privacy risk in its risk appetite statement.

Service NSW has assessed the adequacy of its controls for privacy risks as needing improvement. To be fully effective, the Risk Management Guideline says that these controls should have a focus that is ‘largely preventative and address the root causes’.

One of the business processes that was a key contributing factor to the data breach was the emailing of personal information by Service NSW staff to client agencies.

This process had been identified as a risk prior to the breach and some steps had been put in place to mitigate the risk. In particular, staff were required to manually delete emails that contained personal information. However, these measures were ineffective in preventing the breach, as the external threat actors still gained access to 47 staff email accounts that contained a large amount of personal information.

It is unclear why Service NSW did not effectively mitigate this risk prior to the breaches. However, Service NSW has advised that it implemented measures in June and October 2020 to automatically archive emails likely to contain personal information. This is expected to limit the quantity of information retained in email accounts for extended periods.

Service NSW has not put in place any technical or other solutions to avoid Service NSW staff having to scan and email personal information to some client agencies. Urgent action is needed to remove the requirement for staff to email personal information to client agencies, thereby mitigating the risk inherent in sending and storing this information using email.

There are weaknesses in the general IT and security controls implemented by Service NSW over its Salesforce CRM system, which holds the personal information of over four million customers

There are weaknesses in the general IT and security controls implemented by Service NSW over its Salesforce CRM system. These weaknesses include deficiencies in governance of role based access, monitoring and audit of staff access, and partitioning of program specific transaction information. These deficiencies create an increased risk of unauthorised access to the personal information of over four million customers which is stored in this system.

In addition, there is an absence of important controls to safeguard customers' privacy, such as multi factor authentication and reviewable logs of access history to their information. Such controls, when properly implemented, would enhance the control that customers are able to exercise over their personal information.

A privacy impact assessment conducted on Service NSW’s Salesforce CRM system in 2015 recommended that the system include the ability for customers to review access history to their personal information, as well as the option for customers to apply multi factor authentication to their accounts. While both these recommendations appeared positively received by Service NSW, neither have been implemented.

Since its inception, Service NSW’s use of Salesforce has extended to storing transaction data, particularly for transactions for which Service NSW is responsible, such as the Seniors Card. It also holds details of over four million MyServiceNSW account holders, including name, email address and phone number, and optional address details. It was not originally intended for the system to hold this volume and nature of customer information.

Lines of responsibility for meeting privacy obligations are unclear between Service NSW and its client agencies

Service NSW's privacy management plan does not clearly set out the privacy obligations of Service NSW and its client agencies. It sets out that 'compliance with the privacy principles will primarily be the responsibility of that [client] agency'. However, Service NSW has its own obligations under the security principles of the Privacy and Personal Information Protection Act 1998 (PPIP Act) to take reasonable steps to prevent unauthorised access to personal information, which is not made clear in the privacy management plan.

The agreements between Service NSW and client agencies reviewed for this audit only include general and high level references to privacy. Most do not include details of each parties' privacy responsibilities such as: which agency will provide the customer with a privacy notice explaining how their personal information will be handled, how personal information will be kept secure, how long Service NSW will retain information, what processes will be followed for internal reviews, and what specific planning is in place to respond to data breaches.

Service NSW's privacy management plan has not been updated to include new programs and governance changes

Service NSW's privacy management plan includes most of the matters required by law or good practice, with some exceptions. It does not explain any exemptions that the agency commonly relies on under the PPIP Act and does not address any health information that Service NSW may handle. It had also not been updated to reflect governance changes and the fact that, at the time this audit commenced, Service NSW was disclosing the content of internal review applications (the formal expression for 'complaints') to the Department of Customer Service (DCS). These governance changes were part of the centralisation of Service NSW's corporate support functions into DCS in late 2019, though internal review staff were seconded back into Service NSW during the course of this audit.

The current July 2019 privacy management plan has also not been updated since the rollout of a number of major new initiatives in 2020. These include 2019–20 bushfire emergency recovery initiatives (such as small business grants) and COVID 19 pandemic response initiatives (such as small business grants, border permits and the COVID safe check in app).

Service NSW routinely conducts privacy impact assessments for new initiatives, though privacy risks remain in legacy systems and processes

Service NSW routinely conducts privacy impact assessments for major new initiatives and the assessments reviewed for this audit largely accorded with good practice guidance.

Service NSW does not routinely review existing processes and systems to ensure that they are effective in ensuring the privacy of customer personal information. Business processes that create the highest risk to privacy, such as emailing of personal information, are more common in these longstanding legacy systems.

Service NSW's significant and rapid growth has outpaced the establishment of a robust control environment which has exacerbated privacy risks

Since it was established in 2013, Service NSW has experienced significant growth in the number and diversity of the types of transactions it provides, as well as the number of client agencies with which it works. The pace and extent of this growth has contributed to important controls not being properly implemented on a timely basis, which has heightened privacy risks, particularly in regard to existing, legacy systems and processes.

The pace of change and increasing demand for new program implementation has limited the opportunity for Service NSW, in collaboration with its client agencies, to revisit and redesign legacy business practices which pose a greater privacy risk. This includes the scanning and emailing of personal information.

While 2019–20 has seen additional demands placed on Service NSW in responding to the 2019–20 bushfire emergency and COVID 19 pandemic, it is the nature of the agency’s work that it operates in a fast paced and complex environment, where it is required to respond to multiple client agencies and stakeholders. Ensuring customer privacy should be integral to Service NSW’s business as usual operations.

2. Recommendations

Service NSW commissioned a number of external reviews and investigations stemming from the data breaches. The Auditor General's recommendations below have taken these other reviews into account. In order to offer assurance that it is appropriately protecting the privacy of its customers, Service NSW should address the full breadth of findings and recommendations made across all relevant reviews.

As a matter of urgency, Service NSW should:

1. in consultation with relevant client agencies and the Department of Customer Service, implement a solution for a secure method of transferring personal information between Service NSW and client agencies

2. review the need to store scanned copies of personal information and, if still required, implement a more secure method of storing this information and regular deletion of material.

By March 2021, Service NSW should:

3. ensure that all new agreements entered into with client agencies from 1 April 2021 address the deficiencies identified in this audit, including that they provide clarity on:

  • the content and provision of privacy collection notices
  • the terms by which personal information will be retained, stored, archived, and disposed of when no longer required
  • steps that will be taken by each agency to ensure that personal information is kept secure
  • the circumstances in which, and processes by which, applications for internal review will be referred by one agency to the other
  • how identified breaches of privacy will be handled between agencies

4. in collaboration with the Department of Customer Service, review its privacy management plan to address the deficiencies raised in this audit, including:

  • to clarify Service NSW's understanding of how responsibility for meeting privacy obligations are delineated between Service NSW and client agencies
  • to better reflect the full scope and complexity of personal information handled by Service NSW
  • to better explain how applications for internal review are handled between Service NSW and the Department of Customer Service
  • to ensure regular ongoing review, either according to a schedule or when Service NSW experiences substantial change to its programs and handling of personal information

5. in consultation with the Department of Customer Service, review its policies and processes for the management of privacy risks, including to:

  • ensure that there are appropriate mechanisms to escalate identified privacy risks from business units to the Executive Leadership Team
  • ensure that there are action plans to address strategic privacy risks that are assessed as having ineffective controls.
By June 2021, Service NSW should:

6. address deficiencies in the controls over, and security for, its Salesforce customer relationship management and related systems that hold customer personal information, including:

  • establish policies and processes for regular access reviews and monitoring of user activity in these systems, including for privileged users
  • enable partitioning and role based access restrictions to personal information collected for different programs
  • provide customers the choice to use multi factor authentication to further secure their MyServiceNSW accounts
  • enable customers to view the transaction history of their personal information to detect possible mishandling.
By December 2021, Service NSW should:

7. ensure that all existing agreements with client agencies address the deficiencies identified in this audit, including that they provide clarity on:

  • the content and provision of privacy collection notices
  • the terms by which personal information will be retained, stored, archived, and disposed of when no longer required
  • steps that will be taken by each agency to ensure that personal information is kept secure
  • the circumstances in which, and processes by which, applications for internal review will be referred by one agency to the other
  • how identified breaches of privacy will be handled between agencies

8. carry out a risk assessment of all processes, systems and transactions that involve the handling of personal information and undertake a privacy impact assessment for those that:

  • are identified as high risk and have not previously had a privacy impact assessment
  • have had major changes or updates since the privacy impact assessment was completed.

Appendix one – Responses from agencies

Appendix two – About the audit

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for CBD South East Sydney Light Rail: follow-up performance audit

CBD South East Sydney Light Rail: follow-up performance audit

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk
Service delivery

This is a follow-up to the Auditor-General's November 2016 report on the CBD South East Sydney Light Rail project. This follow-up report assessed whether Transport for NSW has updated and consolidated information about project costs and benefits.

The audit found that Transport for NSW has not consistently and accurately updated project costs, limiting the transparency of reporting to the public.

The Auditor-General reports that the total cost of the project will exceed $3.1 billion, which is above the revised cost of $2.9 billion published in November 2019. $153.84 million of additional costs are due to omitted costs for early enabling works, the small business assistance package and financing costs attributable to project delays.

The report makes four recommendations to Transport for NSW to publicly report on the final project cost, the updated expected project benefits, the benefits achieved in the first year of operations and the average weekly journey times.

Read full report (PDF)

The CBD and South East Light Rail is a 12 km light rail network for Sydney. It extends from Circular Quay along George Street to Central Station, through Surry Hills to Moore Park, then to Kensington and Kingsford via Anzac Parade and Randwick via Alison Road and High Street.

Transport for NSW (TfNSW) is responsible for planning, procuring and delivering the Central Business District and South East Light Rail (CSELR) project. In December 2014, TfNSW entered into a public private partnership with ALTRAC Light Rail as the operating company (OpCo) responsible for delivering, operating and maintaining the CSELR. OpCo engaged Alstom and Acciona, who together form its Design and Construct Contractor (D&C).

On 14 December 2019, passenger services started on the line between Circular Quay and Randwick. Passenger services on the line between Circular Quay and Kingsford commenced on 3 April 2020.

In November 2016, the Auditor-General published a performance audit report on the CSELR project. The audit found that TfNSW would deliver the CSELR at a higher cost with lower benefits than in the approved business case, and recommended that TfNSW update and consolidate information about project costs and benefits and ensure the information is readily accessible to the public.

In November 2018, the Public Accounts Committee (PAC) examined TfNSW's actions taken in response to our 2016 performance audit report on the CSELR project. The PAC recommended that the Auditor-General consider undertaking a follow-up audit on the CSELR project. The purpose of this follow-up performance audit is to assess whether TfNSW has effectively updated and consolidated information about project costs and benefits for the CSELR project.

Conclusion

Transport for NSW has not consistently and accurately updated CSLER project costs, limiting the transparency of reporting to the public. In line with the NSW Government Benefits Realisation Management Framework, TfNSW intends to measure benefits after the project is completed and has not updated the expected project benefits since April 2015.

Between February 2015 and December 2019, Transport for NSW (TfNSW) regularly updated capital expenditure costs for the CSELR in internal monthly financial performance and risk reports. These reports did not include all the costs incurred by TfNSW to manage and commission the CSELR project.

Omitted costs of $153.84 million for early enabling works, the small business assistance package and financing costs attributable to project delays will bring the current estimated total cost of the CSELR project to $3.147 billion.

From February 2015, TfNSW did not regularly provide the financial performance and risk reports to key CSELR project governance bodies. TfNSW publishes information on project costs and benefits on the Sydney Light Rail website. However, the information on project costs has not always been accurate or current.

TfNSW is working with OpCo partners to deliver the expected journey time benefits. A key benefit defined in the business plan was that bus services would be reduced owing to transfer of demand to the light rail - entailing a saving. However, TfNSW reports that the full expected benefit of changes to bus services will not be realised due to bus patronage increasing above forecasted levels.

Appendix one – Response from agency

Appendix two – Governance and reporting arrangements for the CSELR

Appendix three – 2018 CSELR governance changes

Appendix four – About the audit

Appendix five – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #335 - released 11 June 2020

Published

Actions for Train station crowding

Train station crowding

Transport
Management and administration
Risk
Service delivery
Workforce and capability

This report focuses on how Transport for NSW and Sydney Trains manage crowding at selected metropolitan train stations.

The audit found that while Sydney Trains has identified platform crowding as a key strategic risk, it does not have an overarching strategy to manage crowding in the short to medium term. Sydney Trains 'do not have sufficient oversight to know if crowding is being effectively managed’, the Auditor-General said.

Sydney Trains' operational response to crowding involves restricting customer access to platforms or station entries before crowding reaches unsafe levels or when it impacts on-time running. Assuming rail patronage increases, it is likely that Sydney Trains will restrict more customers from accessing platforms or station entries, causing customer delay. ‘Restricting customer access to platforms or station entries is not a sustainable approach to manage station crowding’, said the Auditor-General.

The Auditor-General made seven recommendations to improve Transport for NSW and Sydney Trains' management of station crowding. Transport for NSW have accepted these recommendations on behalf of the Transport cluster.

Public transport patronage has been impacted by COVID-19. This audit was conducted before these impacts occurred.

Read full report (PDF)

Sydney Trains patronage has increased by close to 34 per cent over the last five years, and Transport for NSW (TfNSW) expects the growth in patronage to continue over the next 30 years. As patronage increases there are more passengers entering and exiting stations, moving within stations to change services, and waiting on platforms. As a result, some Sydney metropolitan train stations are becoming increasingly crowded.

There are three main causes of station crowding:

  • patronage growth exceeding the current capacity limits of the rail network
  • service disruptions
  • special events.

Crowds can inhibit movement, cause discomfort and can lead to increased health and safety risks to customers. In the context of a train service, unmanaged crowds can affect service operation as trains spend longer at platforms waiting for customers to alight and board services which can cause service delays. Crowding can also prevent customers from accessing services.

Our 2017 performance audit, ‘Passenger Rail Punctuality’, found that rail agencies would find it hard to maintain train punctuality after 2019 unless they significantly increased the capacity of the network to carry trains and people. TfNSW and Sydney Trains have plans to improve the network to move more passengers. These plans are set out in strategies such as More Trains, More Services and in the continued implementation of new infrastructure such as the Sydney Metro. Since 2017, TfNSW and Sydney Trains have introduced 1,500 more weekly services to increase capacity. Additional network capacity improvements are in progress for delivery from 2022 onwards.

In the meantime, TfNSW and Sydney Trains need to use other ways of managing crowding at train stations until increased capacity comes on line.

This audit examined how effectively TfNSW and Sydney Trains are managing crowding at selected metropolitan train stations in the short and medium term. In doing so, the audit examined how TfNSW and Sydney Trains know whether there is a crowding problem at stations and how they manage that crowding.

TfNSW is the lead agency for transport in NSW. TfNSW is responsible for setting the standard working timetable that Sydney Trains must implement. Sydney Trains is responsible for operating and maintaining the Sydney metropolitan heavy rail passenger service. This includes operating, staffing and maintaining most metropolitan stations. Sydney Trains’ overall responsibility is to run a safe rail network to timetable.

Conclusion

Sydney Trains has identified platform crowding as a key strategic risk, but does not have an overarching strategy to manage crowding in the short to medium term. TfNSW and Sydney Trains devolve responsibility for managing crowding at stations to Customer Area Managers, but do not have sufficient oversight to know if crowding is being effectively managed. TfNSW is delivering a program to influence demand for transport in key precincts but the effectiveness of this program and its impact on station crowding is unclear as Transport for NSW has not evaluated the outcomes of the program.

TfNSW and Sydney Trains do not directly measure or collect data on station crowding. Data and observation on dwell time, which is the time a train waits at a platform for customers to get on and off trains, inform the development of operational approaches to manage crowding at stations. Sydney Trains has KPIs on reliability, punctuality and customer experience and use these to indirectly assess the impact of station crowding. TfNSW and Sydney Trains only formally assess station crowding as part of planning for major projects, developments or events.

Sydney Trains devolve responsibility for crowd management to Customer Area Managers, who rely on frontline Sydney Trains staff to understand how crowding affects individual stations. Station staff at identified key metropolitan train stations have developed customer management plans (also known as crowd management plans). However, Sydney Trains does not have policies to support the creation, monitoring and evaluation of these plans and does not systematically collect data on when station staff activate crowding interventions under these plans.

Sydney Trains stated focus is on providing a safe and reliable rail service. As such, management of station crowding is a by-product of its strategies to manage customer safety and ensure on-time running of services. Sydney Trains' operational response to crowding involves restricting customer access to platforms or stations before crowding reaches unsafe levels, or when it impacts on-time running. As rail patronage increases, it is likely that Sydney Trains will need to increase its use of interventions to manage crowding. As Sydney Trains restrict more customers from accessing platforms or station entries, it is likely these customers will experience delays caused by these interventions.

Since 2015, TfNSW has been delivering the 'Travel Choices' program which aims to influence customer behaviour and to manage the demand for public transport services in key precincts. TfNSW is unable to provide data demonstrating the overall effectiveness of this program and the impact the program has on distributing public transport usage out of peak AM and PM times. TfNSW and Sydney Trains continue to explore initiatives to specifically address crowd management.

Conclusion

TfNSW and Sydney Trains do not directly measure or collect data on station crowding. There are no key performance indicators directly related to station crowding. Sydney Trains uses performance indicators on reliability, punctuality and customer experience to indirectly assess the impact of station crowding. Sydney Trains does not have a routine process for identifying whether crowding contributed to minor safety incidents. TfNSW and Sydney Trains formally assess station crowding as part of planning for major projects, developments or events.

 

Conclusion

Sydney Trains has identified platform crowding as a strategic risk but does not have an overarching strategy to manage station crowding. Sydney Trains' stated focus is on providing a safe and reliable rail service. As such, management of station crowding is a by-product of its strategies to manage customer safety and ensure on-time running of services.

Sydney Trains devolve responsibility for managing crowding at stations to Customer Area Managers but does not have sufficient oversight to know that station crowding is effectively managed. Sydney Trains does not have policies to support the creation, monitoring or evaluation of crowd management plans at key metropolitan train stations. The use of crowding interventions is likely to increase due to increasing patronage, causing more customers to experience delays directly caused by these activities.

TfNSW and Sydney Trains have developed interventions to influence customer behaviour and to manage the demand for public transport services but are yet to evaluate these interventions. As such, their impact on managing station crowding is unclear.

Appendix one – Response from agency

Appendix two – Sydney rail network

Appendix three – Rail services contract

Appendix four – Crowding pedestrian modelling

Appendix five – Airport Link stations case study

Appendix six – About the audit

Appendix seven – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #333 - released 30 April 2020

 

Published

Actions for Transport 2019

Transport 2019

Transport
Asset valuation
Financial reporting
Infrastructure
Internal controls and governance
Management and administration
Service delivery
Workforce and capability

This report details the results of the financial audits of NSW Government's Transport cluster for the financial year ended 30 June 2019. The report focuses on key observations and findings from the most recent financial statement audits of agencies in the Transport cluster.

Unqualified audit opinions were issued for all agencies' financial statements. However, valuations of assets continue to create challenges across the cluster. The Audit Office identified some deficiencies in relation to asset valuations at Transport for NSW, Roads and Maritime Services, Rail Corporation New South Wales and Sydney Metro.

The Audit Office noted an increase in findings on internal controls across the Transport cluster. Key themes related to information technology, asset management and employee leave entitlements. The report also highlights the status of significant infrastructure projects across the Transport cluster.

The report makes several recommendations including:

  • agency finance teams need to be consulted on major business decisions and commercial transactions at the time of their execution to assess the financial reporting impacts
  • the Department of Transport should ensure consistent accounting policies are applied across its controlled entities.

Download the Transport 2019 report (PDF)

This report analyses the results of our audits of financial statements of the Transport cluster for the year ended 30 June 2019. The table below summarises our key observations.

1. Machinery of Government changes
Transport for NSW, as the
lead agency, will absorb the
functions of Roads and
Maritime Services

The NSW Government announced its intention to integrate Roads and Maritime Services (RMS) into Transport for NSW (TfNSW) as part of the Machinery of Government changes.

This change was not included in the Administrative Orders as the Transport Administration Act 1988 No. 109 governs the composition of the Transport cluster. The Transport Administration Amendment (RMS Dissolution) Act 2019 (the Act) received assent on 22 November 2019. The Act dissolves RMS and transfers the assets, rights and liabilities of RMS to TfNSW. As at the date of this Report, the Act is not yet in force.

Transport is considering the impact of the changes on its operating model and financial reporting.

2. Financial reporting
Audit opinions

Unqualified audit opinions were issued on the 2018–19 financial statements of all agencies in the Transport cluster.

TfNSW and Sydney Metro obtained a three-week extension from NSW Treasury to submit their financial statements for audit to resolve accounting issues surrounding the valuation of property, plant and equipment.

The Department of Transport reported total consolidated property, plant and equipment of $158 billion at 30 June 2019. In 2018–19, there were issues with asset valuations at TfNSW, RMS, Sydney Metro and Rail Corporation New South Wales (RailCorp), resulting in adjustments after the submission of financial statements for audit and the correction of a prior period error.

There was also a prior period error resulting from an agreement between TfNSW and the former UrbanGrowth Development Corporation due to a lack of assessment of the financial reporting implications at the time of signing the agreement.

Recommendation: Agency finance teams need to be consulted on major business decisions and commercial transactions to assess their accounting impacts at the time of their execution, rather than at the end of a financial year. Agencies also need to resolve all key accounting issues such as valuations as part of the early close procedures.

This would improve the quality of financial reporting and avoid the need for extensions for agencies to submit their financial statements for audit.

Preparedness for new
accounting standards
Agencies across the cluster are progressing in their implementation of the new accounting standards.

Transport cluster agencies need to improve their contracts registers to ensure they have a complete list of contracts and agreements to assess the impact of the new accounting standards.
Valuation of assets remains
a challenge in the
Transport cluster

Whilst agencies complied with the requirements of the accounting standards and NSW Treasury policies on valuations, the Audit Office identified some deficiencies in relation to asset valuations across the cluster.

TfNSW reported a retrospective correction of a prior period error at 1 July 2017 which resulted in a reduction in the valuation of its Country Rail Network earthworks by $2.1 billion. This was due to survey results which identified the earthworks were flatter and lower than estimated in the valuation at 30 June 2017.

RMS made several adjustments during the year to correct asset values due to changes to valuation assumptions or data improvements. This included:

  • reduction of $318 million in the value of land under roads
  • decrease of $84.9 million to the value of land and buildings
  • changes to the value of traffic control and traffic signal network assets, due to data improvements.

Sydney Metro North West officially opened in May 2019 and reported total assets of $9.1 billion. Sydney Metro derecognised $322 million in assets constructed to facilitate its operation but transferred to councils and utilities.

Inconsistent accounting
policies across the
Transport cluster

There was an inconsistency identified in the cluster relating to the valuation of substratum land. In 2018–19, RailCorp derecognised $109 million of substratum land to ensure consistency in its approach with other Transport agencies.

As the parent entity, the Department of Transport needs to ensure accounting policies are consistently applied across all controlled entities for consolidation purposes. Inconsistencies in the application of accounting standards across agencies will impact comparability of financial reporting and decision making across the Transport cluster.

Recommendation: The Department of Transport should ensure consistent accounting policies are applied across its controlled entities.

Revenue growth

Public transport passenger revenue increased by $89.0 million (5.9 per cent) in 2018–19, and patronage increased by 37.8 million (4.9 per cent) across all modes of transport based on data provided by TfNSW.

The increase in revenue is mainly due to an increase in patronage as well as the annual increase in fares.

Negative Opal cards

Negative balance Opal cards resulted in $2.9 million in revenue not collected in 2018–19 ($10.4 million since the introduction of Opal).

In January 2019, Transport made a change to the Sydney Airport stations to prevent customers with high negative balances exiting the station. In addition, in late 2018, Transport increased the minimum top up values for new cards at the airport stations.

Recommendation (repeat): TfNSW should implement further measures to prevent the loss of revenue from passengers tapping off with negative balance Opal cards.

3. Audit observations
Internal controls There was an increase in findings on internal controls across the Transport cluster. Key themes relate to information technology, employee leave entitlements and asset management.

Twenty-nine per cent of all issues were repeat issues. The majority of the repeat issues related to information technology controls.
Write-off of assets In addition to a $322 million derecognition of assets transferred to councils and utilities by Sydney Metro and a $109 million derecognition of substratum land at RailCorp, the Transport cluster wrote-off $278 million of assets related to roads, bridges, maritime assets, traffic signals and controls network.

These mainly related to roads, bridges, maritime assets, traffic signals and the control network where new infrastructure assets substantially replaced an existing asset as part of construction activities.
Transport Asset Holding
Entity (TAHE)
TAHE was established to be a dedicated asset manager for the delivery of public transport asset management. The Transport Administration Amendment (Transport Entities) Act 2017 will transition RailCorp into TAHE. RailCorp is now expected to transition to TAHE from 1 July 2020 (previously 1 July 2019). Several working groups have been considering various aspects of the TAHE transition including its status as a for profit Public Trading Enterprise, the operating model and the impact of the new accounting standards AASB 16 'Leases' and AASB 1059 'Service Concession Arrangements: Grantors'. The considerations of these aspects identified several challenges in the implementation of TAHE which has led to the revised transition date. Given the delays in implementation, it is important to clarify the intent of the TAHE model.
Excess annual leave

Twenty-six per cent of Transport employees have annual leave balances exceeding 30 days. Of the employees with excess leave balances, 732 (10.3 per cent) did not take any annual leave in 2018–19.

Recommendation (repeat): Transport entities should further review the approach to managing excess annual leave in 2019–20. They should:

  • monitor current and projected leave balances to the end of the financial year each month
  • agree formal leave plans with employees to reduce leave balances over an acceptable timeframe
  • ensure leave plans are actioned appropriately
  • encourage all staff with excess leave balances take a minimum two-week period of leave per year.
Completeness and
accuracy of contracts
registers

There are no centralised processes to record all significant contracts and agreements in a register across the Transport cluster.

Across the Transport cluster, contracts and agreements are maintained by the individual agencies using disparate registers. Agencies must perform detailed assessments of their existing contracts and agreements to quantify the impact of the new accounting standards (AASB 16 ‘Leases’, AASB 15 ‘Revenue from Contracts with Customers’, AASB 1058 ‘Income of Not-for-Profit Entities’ and AASB 1059 'Service Concession Arrangements: Grantors').

In 2018–19, there was also a prior period error resulting from an agreement between TfNSW and another government agency due to a lack of assessment of the financial reporting implications at the time of signing the agreement.

A lack of a complete register of all contracts and agreements increases the risk that agencies may not be able to assess the full impact of the new accounting standards, as well as perform a complete assessment of the financial reporting implications of contracts and agreements.

Recommendation: Transport agencies should implement a process to centrally capture all significant contracts and agreements entered. This will ensure:

  • agencies are fully aware of contractual and other obligations
  • appropriate assessment of financial reporting implications
  • assessment of new accounting standards, in particular AASB 16 ‘Leases’, AASB 15 'Revenue from Contract with Customers', AASB 1058 'Income of Not-for-Profit Entities ' and AASB 1059 'Service Concession Arrangements: Grantors' are accurate and complete.

 

This report provides parliament and other users of the Transport cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

This cluster was impacted by the Machinery of Government changes on 1 July 2019. The NSW Government announced its intention to integrate Roads and Maritime Services (RMS) into Transport for NSW (TfNSW). This report is focused on the Transport cluster prior to these changes. Please refer to the section on Machinery of Government changes for more details.

Machinery of Government refers to how the government organises the structures and functions of the public service. Machinery of Government changes are where the government reorganises these structures and functions, and are given effect by Administrative orders.

The Transport cluster was impacted by recent Machinery of Government changes. These changes were announced by the Department of Premier and Cabinet but were not included in the Administrative Orders as the Transport Administration Act 1988 No. 109 governs the composition of the Transport cluster. It was the intention of government to transfer the functions of the RMS into TfNSW. This requires legislative changes to the Transport Administration Act 1988 No. 109.

Section highlights

Under the Machinery of Government changes, the NSW Government will transfer the functions of RMS into TfNSW.

  • The Transport Administration Amendment (RMS Dissolution) Act 2019 (the Act) received assent on 22 November 2019.
  • The Act will dissolve RMS and transfer its functions, assets, rights and liabilities to TfNSW.
  • As at the date of this report, the Act is not yet in force.
  • There are risks and challenges for asset and liability transfers, governance and retention of knowledge.
  • As of 1 July 2019, administrative arrangements (delegations and reporting line changes) were put in place to enable TfNSW and RMS to operate within a single management structure, while still remaining as separate legal entities.
  • Transport is working on a number of options as to how to implement the changes. 

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Transport cluster for 2019.

Section highlights

  • Unqualified audit opinions were issued on all agencies' financial statements.
  • RMS required an extension from NSW Treasury for their early close procedures.
  • TfNSW and Sydney Metro required extensions to submit their year-end financial statements.
  • Valuation of assets remains a challenge across the cluster.
  • There remains Opal cards with negative balances.
  • Sydney Metro derecognised assets of $322 million in relation to assets constructed for third parties.
  • Inconsistencies in the application of accounting policies across cluster agencies impact comparability of financial reporting across the Transport cluster.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our observations and insights from our financial statement audits of agencies in the Transport cluster.

Section highlights

  • There was an increase in findings on internal controls across the Transport cluster. Twenty-nine per cent of all issues were repeat issues.
  • Transport entities wrote-off over $278 million of assets which were replaced by new assets or technology.
  • Twenty-six per cent of Transport employees have excess annual leave.
  • There are no processes to ensure all significant contracts and agreements are captured by agencies in a centralised register.

Appendix one – Timeliness of financial reporting by agency 

Appendix two – Management letter findings by agency 

Appendix three – List of 2019 recommendations 

Appendix four – Status of 2017 and 2018 recommendations 

Appendix five – Cluster agencies 

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Transport Access Program

Transport Access Program

Transport
Infrastructure
Project management
Service delivery

The following report is available in an Easy English version that is intended to meet the needs of some people with lower literacy skills, some people with an intellectual disability and some people from different cultural backgrounds.

View the Easy English version of the Transport Access Program report

Transport for NSW’s process for selecting and prioritising projects for the third stage of its Transport Access Program balanced compliance with national disability standards with broader customer outcomes. Demographics, deliverability and value for money were also considered. However, Transport for NSW does not know the complete scope of work required for full compliance, limiting its ability to demonstrate that its approach is effective, according to a report released today by the Auditor-General for New South Wales, Margaret Crawford.

Access to transport is critical to ensuring that people can engage in all aspects of community life, including education, employment and recreation. People with disability can encounter barriers when accessing public transport services. In 2015, there were 1.37 million people living with disability in New South Wales.

Accessible public transport is about more than physical accessibility. It also means barrier-free access for people who have vision, hearing or cognitive impairments. All users, not just people with disability, benefit from improvements to the accessibility and inclusiveness of transport services. 

Transport for NSW has an obligation under Australian Government legislation to provide accessible services to people with disabilities in a manner which is not discriminatory. Under the Disability Standards for Accessible Public Transport 2002 (the DSAPT - an instrument of the Disability Discrimination Act 1992 (the Act) (Commonwealth)), there is a requirement to modify and develop new infrastructure, means of transport and services to provide access for people with disabilities. All public transport operators are required to ensure that at least 90 per cent of their networks met DSAPT by December 2017 and the networks will need to be 100 per cent compliant with all parts of the standards by 31 December 2022. Trains are not required to be fully compliant with DSAPT until December 2032. 

The Transport Access Program (TAP) is Transport for NSW's largest program with a specific focus on improving access to public transport for people with disability. The TAP is a series of projects to upgrade existing public transport infrastructure across four networks: Sydney Trains, Intercity Trains, Regional Trains and Sydney Ferries. Transport for NSW established the TAP as a rolling program and, to date, it has delivered the first tranche of TAP (TAP 1) and is completing the final projects for the second tranche (TAP 2). NSW budget papers estimate that by 30 June 2018, Transport for NSW had spent $1.2 billion in the TAP since its commencement in 2011-12.

After the completion of TAP 1 and TAP 2 (as well as through other transport infrastructure programs), Transport for NSW estimates that 58.5 per cent of the Sydney Trains, Regional Trains and Intercity Trains networks, and 66 per cent of the Sydney Ferries network, will be accessible. To close the significant gap in compliance with the DSAPT target, the objective for TAP 3 is ‘to contribute to Disability Discrimination Act 1992 related targets through DSAPT compliance upgrades’. 

The audit assessed whether Transport for NSW has an effective process to select and prioritise projects as part of the TAP, with a specific focus on the third tranche of TAP funding.

In August 2018, at the commencement of this audit, Transport for NSW intended to complete the selection of projects for the TAP 3 final business case in December 2018. Transport for NSW advise that it now intends to complete the development stage and final business case in the first quarter of 2019, prior to the final investment decision of the TAP program. This report is based on the TAP 3 strategic business case and information provided by Transport for NSW up to December 2018.

Conclusion
Transport for NSW’s process for selecting and prioritising projects for TAP 3 balanced DSAPT compliance goals with broader customer outcomes. It also considered demographics, deliverability and value for money. However, Transport for NSW does not know the complete scope of work required for full DSAPT compliance, and this limits its ability to demonstrate that its approach is effective. 
Transport for NSW has applied most of the external review recommendations from previous funding rounds to the implementation of the third round of TAP funding (TAP3), with positive results. Changes made include a clear objective for TAP 3 to focus on improving compliance, improved governance arrangements, and better consideration of deliverability and design during project planning. 
Through TAP 3, Transport for NSW is also trying to better address disability access in a way that balances DSAPT compliance with other considerations - such as population demographics, access to services and value for money. Transport for NSW developed an objective prioritisation and selection methodology to assess projects for TAP 3 funding. 
Transport for NSW cannot quantify the work needed to meet DSAPT compliance targets across the rail and ferry networks as it has not completed a comprehensive audit of compliance. This information is needed to ensure the effective targeting of funding, and to measure the contribution of TAP 3 work to meeting the DSAPT compliance targets. Instead, Transport for NSW has undertaken a phased approach to completing a comprehensive audit of compliance across the networks, with a focus on first assessing compliance at locations that are not wheelchair accessible. This creates two problems. First, Transport for NSW does not know the complete scope of work required to achieve DSAPT compliance. Second, not all wheelchair accessible locations fully meet DSAPT standards.
Transport for NSW's proposed communication plan for the schedule of TAP 3 funded works does not align with its Disability Inclusion Action Plan 2018-2022. The Disability Inclusion Action Plan commits Transport for NSW to providing a full list of stations and wharves to be upgraded with their estimated time of construction when the next round of funding, TAP 3, is announced. Given the long timeframes associated with improving transport infrastructure, this information is important as it allows people to make informed decisions about where they live, work or study. Instead, Transport for NSW plans to communicate information to customers on a project by project basis.

In 2015, there were 1.37 million people living with disability in New South Wales. Access to transport is critical to ensuring that people can engage in all aspects of community life, including education, employment and recreation. People with disability can encounter barriers when accessing public transport services. 

The social model of disability, outlined in the United Nations Convention on the Rights of Persons with Disabilities, views people with disability as not disabled by their impairment but by the barriers in the community and environment that restrict their full and effective participation in society on an equal basis with others. 

Accessible public transport is more than the provision of physical access to premises and conveyances, it provides barrier-free access for people who have vision, hearing or cognitive impairments. All users, not just people with disability, benefit from improvements to the accessibility and inclusiveness of transport services.

According to the Australian Bureau of Statistics, the main types of difficulties experienced by people with disability when using public transport relate to steps (39.9 per cent), difficulty getting to stops and stations (25 per cent), fear and anxiety (23.3 per cent) and lack of seating or difficulty standing (20.7 per cent).

Transport for NSW has a Disability Inclusion Action Plan (the Action Plan) 2018-2022 that sets an overall framework for planning, delivering and reporting on initiatives to increase accessibility of the transport network. It covers all elements of the journey experienced when using public transport, including journey planning, staff training, customer services and interaction between the physical environment and modes of transport. Appendix five outlines the guiding principles of the Action Plan.

Transport for NSW's Transport Social Policy branch developed the Action Plan in consultation with internal and external stakeholders. The director of the Transport Social Policy branch is a member of the TAP executive steering committee, which supports alignment between the Action Plan and TAP.

Transport for NSW's Disability Inclusion Action Plan describes a customer focussed approach to accessibility

One of the guiding principles of the Action Plan is ‘intelligent compliance’. Transport for NSW describes this as compliance that prioritises customer-focused outcomes over a narrow focus on legal compliance with accessibility standards. As well as being compliant, infrastructure should be practical, usable, fit for purpose and convenient. 

The TAP prioritisation and selection methodology reflects Transport for NSW’s focus on intelligent compliance. We consider this a reasonable approach as had Transport for NSW focussed exclusively on achieving compliance with the DSAPT targets by upgrading the most affordable infrastructure, some locations, that are used by more customers, would remain inaccessible to people with disability. However, this approach should not be seen as an alternative to Transport for NSW meeting its DSAPT compliance obligations.

TAP program staff consult with the Accessible Transport Advisory Committee

The Accessible Transport Advisory Committee (ATAC) has representatives from disability and ageing organisations, who provide expert guidance to Transport for NSW on access and inclusion. The ATAC provide guidance and feedback on projects and project solutions, including user testing where appropriate. TAP program staff provide regular updates at ATAC meetings, which include briefings on progress. The ATAC also provides feedback and suggestions to TAP program staff, which is considered and sometimes included in current and future projects.For example, in March 2017 the TAP program team briefed the ATAC on the challenges with respect to a number of ferry wharves and sought support for DSAPT exemptions proposed in the TAP 3 strategic business case.

Case study: Feedback on Braille lettering for lift buttons
In June 2018, the Program team sought feedback on a variety of lift button options to improve accessibility on future TAP projects. In September 2018, during the ATAC meeting attended by the Audit Office, the program team sought feedback on the standard designs for TAP 3. Some ATAC members noted that the standard design included Braille lettering on the lift buttons, and that this was not good practice because people can accidently press the button while reading it. As a result, Transport for NSW are incorporating this feedback into design requirements for the lifts for TAP 3, which will consider larger buttons, clearer Braille and Braille signage adjacent to the button.

Transport for NSW has not briefed the Advisory Committee on the outcome of the prioritisation and selection process

TAP program staff briefed the Advisory Committee about the prioritisation and selection methodology, after the Minister approved it in 2016. However, Transport for NSW have not briefed or consulted the Advisory Committee on the outcome of the prioritisation process. Infrastructure NSW noted this issue during its review of the strategic business case. 

Transport for NSW advised us that it established the ATAC as an advisory group, and that Transport for NSW does not disclose sensitive information to it. Transport for NSW intends to share the outcome of the prioritisation process following the completion of the TAP 3 development stage and final investment decision.

The TAP communication plan does not fully meet the requirements of the Disability Inclusion Action Plan

The Disability Inclusion Action Plan includes an action item to ‘provide a listing of stations and wharves to be upgraded with estimated time of construction as each new tranche of the Transport Access Program is announced’ The TAP Communication Plan that we reviewed does not include this provision instead focussing on communication on a per project basis. Given the long timeframes associated with improving transport infrastructure, this information is important as it allows people to make informed decisions about where they live, work or study.

Published

Actions for Central Agencies 2018

Central Agencies 2018

Treasury
Premier and Cabinet
Finance
Financial reporting
Internal controls and governance
Management and administration
Risk

The Auditor-General for New South Wales, Margaret Crawford, released her report today on the results of the financial audits of NSW Government central agencies. The report focuses on key observations and findings from the most recent financial statement audits of agencies in the Treasury, Premier and Cabinet, and Finance, Services and Innovation clusters. While clear audit opinions were issued on all agency financial statements, the report notes that some complex accounting requirements caused significant errors in agency financial statements submitted for audit, which were corrected before the financial statements were approved. 

This report analyses the results of our audits of the Treasury, Premier and Cabinet and Finance, Services and Innovation cluster agencies for the year ended 30 June 2018. The table below summarises our key observations.

This report provides parliament and other users of the NSW Government's central agencies and their cluster agencies financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations
  • liquidity risk management
  • government financial services.

The central agencies and their key responsibilities are set out below.

Central agencies Key central agency responsibilities Cluster responsibilities
The Treasury
  • Financial and economic advisor to NSW Government
  • Manages the NSW Government’s financial resources.

The cluster:

  • provides investment and debt management services though TCorp
  • manages residual business arising from privatisation of government businesses
  • provides insurance and compensation cover, including workers compensation insurance
  • includes NSW Government superannuation funds.
Department of Premier and Cabinet
  • Drives NSW Government’s objectives and sets targets
  • Works with clusters to coordinate policy and achieve NSW Government priorities.

The cluster:

  • includes integrity agencies, such as the Independent Commission Against Corruption, Audit Office of NSW and Ombudsman’s Office
  • other agencies, such as Barangaroo Delivery Authority and Infrastructure NSW.
Department of Finance, Services and Innovation
  • Supports agency service delivery in relation to the key enabling functions of NSW Government, including procurement, property and asset management, ICT and digital innovation.

The cluster:

  • is responsible for state revenue and rental bond administration
  • regulates statutory insurance schemes, workplace safety and consumer protection
  • provides access to a range of NSW Government services via Service NSW
  • manages the NSW Government communications network.
Public Service Commission
  • Works to promote and maintain a strong ethical culture across the government sector and improve the capabilities, performance and configuration of the sector’s workforce to deliver better services to the public.
  • The Public Service Commission is an independent agency within the Premier and Cabinet cluster.

Note: The Audit Office of NSW is an independent agency included in the Premier and Cabinet cluster for administrative purposes, but not commented on in this report.


A full list of agencies that this report covers by relevant cluster is included in Appendix three.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Treasury, Premier and Cabinet and Finance, Services and Innovation clusters for 2018.

Observation Conclusions and recommendations
2.1 Quality of financial reporting
Unqualified opinions were issued for all agencies' financial statements submitted to the Audit Office.

Complex accounting requirements caused significant errors in some agency financial statements, which were corrected before the financial statements were approved.
Sufficient audit evidence was obtained to conclude the financial statements were free of material misstatement.
Recommendation: Agencies should respond to key accounting issues when they are identified by preparing accounting papers and engaging with Treasury, the Audit Office and their Audit and Risk Committee when these matters are identified.
2.2 Timeliness of financial reporting
Most agencies complied with the statutory timeframe for completion of early close procedures, 48 agencies in the Treasury cluster did not comply with the statutory requirement to prepare financial statements, and the audits of nine agencies in the Treasury cluster were not completed within the statutory timeframe.
All financial statement information of the 48 agencies that did not prepare financial statements has been captured in the consolidated financial statements of their parent entity, which was subject to audit.
Early close procedures allow financial reporting issues and risks to be addressed early in the audit process. The timeliness of financial reporting can be improved by performing more robust early close procedures.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our observations and insights from:

  • our financial statement audits of agencies in the Treasury, Premier and Cabinet and Finance, Services and Innovation cluster for 2018
  • the areas of focus identified in the Audit Office work program.

The Audit Office work program provides a summary of all audits to be conducted within the proposed time period as well as detailed information on the areas of focus for each of the NSW Government clusters.

Observation Conclusions and recommendations
3.1 Internal controls
The 2017–18 audits found one high risk issue and 83 moderate risk issues across the agencies. Nineteen per cent of all issues were repeat issues. Agencies should focus on rectifying repeat issues.
The high risk issue at Service NSW related to several deficiencies in procurement and contract management processes. Service NSW may not be achieving value-for-money
from their procurement and contract management activities. The high risk issue should be rectified as a matter of priority. This includes updating and implementing its procurement, vendor and contract management frameworks and delivering training to key staff involved in procurement and contract management activities.
Property NSW has implemented several controls during the year to rectify the high risk issue identified last year related to its transition to a new property and facility management service provider. However, the service providers performance remains below expectations and there are further opportunities to improve oversight and lift performance. Property NSW can better define roles and accountabilities with the service provider and formalise policies and processes associated with its monitoring and oversight of the service provider.

Implementing relevant KPIs, receiving timely reports and providing timely review and feedback to the service provider may help to lift performance.
GovConnect received unqualified opinions from their service auditor on all business process controls, except for information technology controls provided by Unisys, where a qualified opinion was received from the service auditor. A qualified opinion was received because of several deficiencies in user access controls. These internal control deficiencies increase the risk of unauthorised access to key business systems, and increase audit effort and costs associated with addressing the risks arising from the deficiencies.
3.2 Audit Office annual work program

Remediation of the Barangaroo site is now estimated to cost the Barangaroo Delivery Authority in excess of net $400 million.
 
The increase in the estimate over the last five years is mainly due to the extent of remediation required, as more evidence of contamination has become known.

Measuring the remaining costs to remediate requires the use of estimation techniques and judgements, making the actual outcome inherently uncertain. We reviewed evidence to support the provision for remediation, including future costs estimates and this evidence supported management’s estimate.
The State Insurance Regulatory Authority have administered the refund of $138 million in Green slip refunds to policy holders through Service NSW during 2017–18. At 30 June 2018, $112 million in refunds are yet to be claimed.
 
We reviewed the systems and processes supporting the refund process. While we found that this supports the disbursement of refunds to policyholders there were some deficiencies in Service NSW’s project controls when the program was being developed.

 
Service NSW should apply the lessons learnt from this program to other programs it is delivering or will be delivering for agencies.
Revenue NSW recorded $30.4 billion from taxes, fines and fees in 2017–18 ($30.0 billion in 2016–17) to support the State’s finances. 
 
Crown revenue has steadily increased over the last five years predominately driven by rises in payroll tax and land tax and responsibility for collection of the Emergency Services Levy transferring to Revenue NSW under the Emergency Services Levy Act 2017 effective from July 2017. 
3.3 Managing maintenance
Place Management NSW manages significant commercial and retail leases and maintains public domain spaces and other assets around the harbour foreshore. It has consistently underspent its asset maintenance budget. In 2017–18, asset maintenance expenses were only 34 per cent of budgeted maintenance expense.

Currently, Place Management NSW does not use any ratios or benchmarks to determine the adequacy of its maintenance spend or to monitor whether it is achieving its budgeted maintenance program. 
This may be contributing to a high proportion of unplanned maintenance, which Place Management NSW reports was 38 per cent of total maintenance expense in 2017–18.

Place Management NSW is outsourcing its property and facilities management function from 1 December 2018 to an external service provider. 
 

This chapter outlines our audit observations, conclusions and recommendations specific to NSW Government agencies providing financial services.

Observation Conclusions and recommendation
5.1 Superannuation funds
The SAS Trustee Corporation (STC) Pooled Fund and the Parliamentary Contributory Superannuation (PCS) Fund are not required to comply with the prudential and reporting standards issued by the Australian Prudential Regulation Authority (APRA). 
However, legislation allows the responsible Minister to prescribe prudential standards, reporting and audit requirements. 
Structured and comprehensive prudential oversight of these Funds is important as they operate in a volatile financial sector, have 103,000 members and manage investments of $43.3 billion.
Recommendation: Treasury should consult with the Trustees of the STC Pooled Fund and PCS Fund to prescribe appropriate prudential standards and requirements, including oversight arrangements.
5.2 Insurance and compensation
Nominal Insurer and NSW Self Insurance Corporation investment performance marginally exceeded benchmark over the past five years. Investment returns can impact on the premiums required to maintain an adequate funding ratio in addition to other factors such as claims experience and discount rates.
The Workers Compensation Nominal Insurer (Nominal Insurer) and NSW Self Insurance Corporation's net collected premiums and contributions decreased over the past five years.  The insurance schemes' investment performance and stable claim payments have enabled less reliance on net collected premiums and contributions as a source of funding, over the past five years. 
Reforms were introduced to manage the Home Warranty Scheme's financial sustainability risks.  The Home Warranty Scheme has not collected sufficient premiums to fund expected claims costs, since commencing operations in 2011. In 2017–18, the Crown contributed $181 million for historical shortfalls. New reforms started on 1 January 2018 enabling the Scheme to price premiums based on risk. 

Published

Actions for Transport 2018

Transport 2018

Transport
Asset valuation
Compliance
Financial reporting
Infrastructure
Management and administration
Procurement
Risk
Service delivery
Workforce and capability

The Auditor-General for New South Wales, Margaret Crawford released her report today on key observations and findings from the 30 June 2018 financial statement audits of agencies in the Transport cluster. Unqualified audit opinions were issued for all agencies' financial statements. However, assessing the fair value of the broad range of transport related assets creates challenges.

This report analyses the results of our audits of financial statements of the Transport cluster for the year ended 30 June 2018. The table below summarises our key observations.

This report provides Parliament and other users of the Transport cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Transport cluster for 2018.

Observation Conclusions and recommendations
2.1 Quality of financial reporting
Unqualified audit opinions were issued for all agencies' financial statements Sufficient audit evidence was obtained to conclude the financial statements were free of material misstatement.
2.2 Key accounting issues
Valuation of assets continues to create challenges. Although agencies complied with the requirements of the accounting standards and Treasury policies on valuations, we identified some opportunities for improvements at RMS.

RMS incorporated data from its asset condition assessments for the first time in the valuation methodology which improved the valuation outcome. Overall, we were satisfied with the valuation methodology and key assumptions, but we noted some deficiencies in the asset data in relation to asset component unit rates and old condition data for some components of assets. 

Also, a bypass and tunnel were incorrectly excluded from RMS records and valuation process since 2013. This resulted in an increase for these assets’ value by $133 million.

The valuation inputs for Wetlands and Moorings were revised this year to better reflect the assets' characteristics resulting in a $98.0 million increase.

2.3 Timeliness of financial reporting
Residual Transport Corporation did not submit its financial statements by the statutory reporting deadline. Residual Transport Corporation remained a dormant entity with no transactions for the year ended 30 June 2018.
With the exception of Residual Transport Corporation, all agencies completed early close procedures and submitted financial statements within statutory timeframes. Early close procedures allow financial reporting issues and risks to be addressed early in the reporting and audit process.
2.4 Financial sustainability
NSW Trains and the Chief Investigator of the Office of Transport Safety Investigations reported negative net assets of $75.7 million and $89,000 respectively at 30 June 2018.  NSW Trains and the Chief Investigator of the Office of Transport Safety Investigations continue to require letters of financial support to confirm their ability to pay liabilities as they fall due. 
2.5 Passenger revenue and patronage
Transport agencies revenue growth increased at a higher rate than patronage. Public transport passenger revenue increased by $114 million (8.3 per cent) in 2017–18, and patronage increased by 37.1 million (5.1 per cent) across all modes of transport based on data provided by TfNSW. 
Negative balance Opal Cards resulted in $3.8 million in revenue not collected in 2017–18 and $7.8 million since the introduction of Opal. A total of 1.1 million Opal cards issued since its introduction have negative balances. Transport for NSW advised it is liaising with the ticketing vendor to implement system changes and are investigating other ways to reduce the occurrences.
2.6 Cost recovery from public transport users
Overall cost recovery from users has decreased. Overall cost recovery from public transport users (on rail and bus services by STA) decreased from 23.2 per cent to 22.4 per cent between 2016–17 and 2017–18. The main reason for the decrease is due to expenditure increasing at a faster rate than revenue in 2017–18.


 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our observations and insights from:

  • our financial statement audits of agencies in the Transport cluster for 2018
  • the areas of focus identified in the Audit Office annual work program.

The Audit Office Annual Work Program provides a summary of all audits to be conducted within the proposed time period as well as detailed information on the areas of focus for each of the NSW Government clusters. 

Observation Conclusions and recommendations
3.1 Internal controls 
There was an increase in findings on internal controls across the Transport cluster. Key themes related to information technology, employee leave entitlements and asset management. Eighteen per cent of all issues were repeat issues.
3.2 Audit Office Annual work program
The Transport cluster wrote-off over $200 million of assets which were replaced by new assets or technology.

Majority of this write-off was recognised by RMS, with $199 million relating to the write-off of existing assets which have been replaced during the year. 

RailCorp is expected to convert to TAHE from 1 July 2019. Several working groups are considering different aspects of the TAHE transition including its status as a for-profit Public Trading Enterprise and which assets to transfer to TAHE. We will continue to monitor developments on TAHE for any impact to the financial statements.
RMS' estimated maintenance backlog at 30 June 2018 of $3.4 billion is lower than last year. Sydney Trains' estimated maintenance backlog at 30 June 2018 increased by 20.6 per cent to $434 million. TfNSW does not quantify its backlog maintenance. TfNSW advised it is liaising with Infrastructure NSW to develop a consistent definition of maintenance backlog across all transport service providers. 
Not all agencies monitor unplanned maintenance across the Transport cluster. Unplanned maintenance can be more expensive than planned maintenance. TfNSW should develop a consistent approach to define, monitor and track unplanned maintenance across the cluster.

This chapter outlines certain service delivery outcomes for 2017–18. The data on activity levels and performance is provided by Cluster agencies. The Audit Office does not have a specific mandate to audit performance information. Accordingly, the information in this chapter is unaudited. 

We report this information on service delivery to provide additional context to understand the operations of the Transport cluster and to collate and present service information for different modes of transport in one report. 

In our recent performance audit, Progress and measurement of Premier's Priorities, we identified 12 limitations of performance measurement and performance data. We recommended that the Department of Premier and Cabinet ensure that processes to check and verify data are in place for all agency data sources.

Published

Actions for Mobile speed cameras

Mobile speed cameras

Transport
Compliance
Financial reporting
Information technology
Internal controls and governance
Management and administration
Regulation
Service delivery

Key aspects of the state’s mobile speed camera program need to be improved to maximise road safety benefits, according to a report released today by the Auditor-General for New South Wales, Margaret Crawford. Mobile speed cameras are deployed in a limited number of locations with a small number of these being used frequently. This, along with decisions to limit the hours that mobile speed cameras operate, and to use multiple warning signs, have reduced the broad deterrence of speeding across the general network - the main policy objective of the mobile speed camera program.

The primary goal of speed cameras is to reduce speeding and make the roads safer. Our 2011 performance audit on speed cameras found that, in general, speed cameras change driver behaviour and have a positive impact on road safety.

Transport for NSW published the NSW Speed Camera Strategy in June 2012 in response to our audit. According to the Strategy, the main purpose of mobile speed cameras is to reduce speeding across the road network by providing a general deterrence through anywhere, anytime enforcement and by creating a perceived risk of detection across the road network. Fixed and red-light speed cameras aim to reduce speeding at specific locations.

Roads and Maritime Services and Transport for NSW deploy mobile speed cameras (MSCs) in consultation with NSW Police. The cameras are operated by contractors authorised by Roads and Maritime Services. MSC locations are stretches of road that can be more than 20 kilometres long. MSC sites are specific places within these locations that meet the requirements for a MSC vehicle to be able to operate there.

This audit assessed whether the mobile speed camera program is effectively managed to maximise road safety benefits across the NSW road network.

Conclusion

The mobile speed camera program requires improvements to key aspects of its management to maximise road safety benefits. While camera locations have been selected based on crash history, the limited number of locations restricts network coverage. It also makes enforcement more predictable, reducing the ability to provide a general deterrence. Implementation of the program has been consistent with government decisions to limit its hours of operation and use multiple warning signs. These factors limit the ability of the mobile speed camera program to effectively deliver a broad general network deterrence from speeding.

Many locations are needed to enable network-wide coverage and ensure MSC sessions are randomised and not predictable. However, there are insufficient locations available to operate MSCs that meet strict criteria for crash history, operator safety, signage and technical requirements. MSC performance would be improved if there were more locations.

A scheduling system is meant to randomise MSC location visits to ensure they are not predictable. However, a relatively small number of locations have been visited many times making their deployment more predictable in these places. The allocation of MSCs across the time of day, day of week and across regions is prioritised based on crash history but the frequency of location visits does not correspond with the crash risk for each location.

There is evidence of a reduction in fatal and serious crashes at the 30 best-performing MSC locations. However, there is limited evidence that the current MSC program in NSW has led to a behavioural change in drivers by creating a general network deterrence. While the overall reduction in serious injuries on roads has continued, fatalities have started to climb again. Compliance with speed limits has improved at the sites and locations that MSCs operate, but the results of overall network speed surveys vary, with recent improvements in some speed zones but not others.
There is no supporting justification for the number of hours of operation for the program. The rate of MSC enforcement (hours per capita) in NSW is less than Queensland and Victoria. The government decision to use multiple warning signs has made it harder to identify and maintain suitable MSC locations, and impeded their use for enforcement in both traffic directions and in school zones. 

Appendix one - Response from agency

Appendix two - About the audit

Appendix three - Performance auditing

 

Parliamentary reference - Report number #308 - released 18 October 2018

Published

Actions for Managing risks in the NSW public sector: risk culture and capability

Managing risks in the NSW public sector: risk culture and capability

Finance
Health
Justice
Treasury
Internal controls and governance
Management and administration
Risk
Workforce and capability

The Ministry of Health, NSW Fair Trading, NSW Police Force, and NSW Treasury Corporation are taking steps to strengthen their risk culture, according to a report released today by the Auditor-General, Margaret Crawford. 'Senior management communicates the importance of managing risk to their staff, and there are many examples of risk management being integrated into daily activities', the Auditor-General said.

We did find that three of the agencies we examined could strengthen their culture so that all employees feel comfortable speaking openly about risks. To support innovation, senior management could also do better at communicating to their staff the levels of risk they are willing to accept.

Effective risk management is essential to good governance, and supports staff at all levels to make informed judgements and decisions. At a time when government is encouraging innovation and exploring new service delivery models, effective risk management is about seizing opportunities as well as managing threats.

Over the past decade, governments and regulators around the world have increasingly turned their attention to risk culture. It is now widely accepted that organisational culture is a key element of risk management because it influences how people recognise and engage with risk. Neglecting this ‘soft’ side of risk management can prevent institutions from managing risks that threaten their success and lead to missed opportunities for change, improvement or innovation.

This audit assessed how effectively NSW Government agencies are building risk management capabilities and embedding a sound risk culture throughout their organisations. To do this we examined whether:

  • agencies can demonstrate that senior management is committed to risk management
  • information about risk is communicated effectively throughout agencies
  • agencies are building risk management capabilities.

The audit examined four agencies: the Ministry of Health, the NSW Fair Trading function within the Department of Finance, Services and Innovation, NSW Police Force and NSW Treasury Corporation (TCorp). NSW Treasury was also included as the agency responsible for the NSW Government's risk management framework.

Conclusion
All four agencies examined in the audit are taking steps to strengthen their risk culture. In these agencies, senior management communicates the importance of managing risk to their staff. They have risk management policies and funded central functions to oversee risk management. We also found many examples of risk management being integrated into daily activities.
That said, three of the four case study agencies could do more to understand their existing risk culture. As good practice, agencies should monitor their employees’ attitude to risk. Without a clear understanding of how employees identify and engage with risk, it is difficult to tell whether the 'tone' set by the executive and management is aligned with employee behaviours.
Our survey of risk culture found that three agencies could strengthen a culture of open communication, so that all employees feel comfortable speaking openly about risks. To support innovation, senior management could also do better at communicating to their staff the levels of risk they are willing to accept.
Some agencies are performing better than others in building their risk capabilities. Three case study agencies have reviewed the risk-related skills and knowledge of their workforce, but only one agency has addressed the gaps the review identified. In three agencies, staff also need more practical guidance on how to manage risks that are relevant to their day-to-day responsibilities.
NSW Treasury provides agencies with direction and guidance on risk management through policy and guidelines. Its principles-based approach to risk management is consistent with better practice. Nevertheless, there is scope for NSW Treasury to develop additional practical guidance and tools to support a better risk culture in the NSW public sector. NSW Treasury should encourage agency heads to form a view on the current risk culture in their agencies, identify desirable changes to that risk culture, and take steps to address those changes. 

In assessing an agency’s risk culture, we focused on four key areas:

Executive sponsorship (tone at the top)

In the four agencies we reviewed, senior management is communicating the importance of managing risk. They have endorsed risk management frameworks and funded central functions tasked with overseeing risk management within their agencies.

That said, we found that three case study agencies do not measure their existing risk culture. Without clear measures of how employees identify and engage with risk, it is difficult for agencies to tell whether employee's behaviours are aligned with the 'tone' set by the executive and management.

For example, in some agencies we examined we found a disconnect between risk tolerances espoused by senior management and how these concepts were understood by staff.

Employee perceptions of risk management

Our survey of staff indicated that while senior leaders have communicated the importance of managing risk, more could be done to strengthen a culture of open communication so that all employees feel comfortable speaking openly about risks. We found that senior management could better communicate to their staff the levels of risk they should be willing to accept.

Integration of risk management into daily activities and links to decision-making

We found examples of risk management being integrated into daily activities. On the other hand, we also identified areas where risk management deviated from good practice. For example, we found that corporate risk registers are not consistently used as a tool to support decision-making.

Support and guidance to help staff manage risks

Most case study agencies are monitoring risk-related skills and knowledge of their workforce, but only one agency has addressed the gaps it identified. While agencies are providing risk management training, surveyed staff in three case study agencies reported that risk management training is not adequate.

NSW Treasury provides agencies with direction and guidance on risk management through policy and guidelines. In line with better practice, NSW Treasury's principles-based policy acknowledges that individual agencies are in a better position to understand their own risks and design risk management frameworks that address those risks. Nevertheless, there is scope for NSW Treasury to refine its guidance material to support a better risk culture in the NSW public sector.

Recommendation

By May 2019, NSW Treasury should:

  • Review the scope of its risk management guidance, and identify additional guidance, training or activities to improve risk culture across the NSW public sector. This should focus on encouraging agency heads to form a view on the current risk culture in their agencies, identify desirable changes to that risk culture, and take steps to address those changes.

Published

Actions for Internal Controls and Governance 2017

Internal Controls and Governance 2017

Finance
Education
Community Services
Health
Justice
Whole of Government
Asset valuation
Compliance
Cyber security
Information technology
Internal controls and governance
Project management
Risk

Agencies need to do more to address risks posed by information technology (IT).

Effective internal controls and governance systems help agencies to operate efficiently and effectively and comply with relevant laws, standards and policies. We assessed how well agencies are implementing these systems, and highlighted opportunities for improvement.
 

1. Overall trends

New and repeat findings

The number of reported financial and IT control deficiencies has fallen, but many previously reported findings remain unresolved.

High risk findings

Poor systems implementations contributed to the seven high risk internal control deficiencies that could affect agencies.

Common findings

Poor IT controls are the most commonly reported deficiency across agencies, followed by governance issues relating to cyber security, capital projects, continuous disclosure, shared services, ethics and risk management maturity.

2. Information Technology

IT security

Only two-thirds of agencies are complying with their own policies on IT security. Agencies need to tighten user access and password controls.

Cyber security

Agencies do not have a common view on what constitutes a cyber attack, which limits understanding the extent of the cyber security threat.

Other IT systems

Agencies can improve their disaster recovery plans and the change control processes they use when updating IT systems.

3. Asset Management

Capital investment

Agencies report delays delivering against the significant increase in their budgets for capital projects.

Capital projects

Agencies are underspending their capital budgets and some can improve capital project governance.

Asset disposals

Eleven per cent of agencies were required to sell their real property through Property NSW but didn’t. And eight per cent of agencies can improve their asset disposal processes.

4. Governance

Governance arrangements

Sixty-four per cent of agencies’ disclosure policies support communication of key performance information and prompt public reporting of significant issues.

Shared services

Fifty-nine per cent of agencies use shared services, yet 14 per cent do not have service level agreements in place and 20 per cent can strengthen the performance standards they set.

5. Ethics and Conduct

Ethical framework

Agencies can reinforce their ethical frameworks by updating code‑of‑conduct policies and publishing a Statement of Business Ethics.

Conflicts of interest

All agencies we reviewed have a code of conduct, but they can still improve the way they update and manage their codes to reduce the risk of fraud and unethical behaviour.

6. Risk Management 

Risk management maturity

All agencies have implemented risk management frameworks, but with varying levels of maturity.

Risk management elements

Many agencies can improve risk registers and strengthen their risk culture, particularly in the way that they report risks to their lead agency.

This report covers the findings and recommendations from our 2016–17 financial audits related to the internal controls and governance of the 39 largest agencies (refer to Appendix three) in the NSW public sector. These agencies represent about 95 per cent of total expenditure for all NSW agencies and were considered to be a large enough group to identify common issues and insights.

The findings in this report should not be used to draw conclusions on the effectiveness of individual agency control environments and governance arrangements. Specific financial reporting, controls and service delivery comments are included in the individual 2017 cluster financial audit reports tabled in Parliament from October to December 2017.

This new report offers strategic insight on the public sector as a whole

In previous years, we have commented on internal control and governance issues in the volumes we published on each ‘cluster’ or agency sector, generally between October and December. To add further value, we then commented more broadly about the issues identified for the public sector as a whole at the start of the following year.

This year, we have created this report dedicated to internal controls and governance. This will help Parliament to understand broad issues affecting the public sector, and help agencies to compare their own performance against that of their peers.

Without strong control measures and governance systems, agencies face increased risks in their financial management and service delivery. If they do not, for example, properly authorise payments or manage conflicts of interest, they are at greater risk of fraud. If they do not have strong information technology (IT) systems, sensitive and trusted information may be at risk of unauthorised access and misuse.

These problems can in turn reduce the efficiency of agency operations, increase their costs and reduce the quality of the services they deliver.

Our audits do not review every control or governance measure every year. We select a range of measures, and report on those that present the most significant risks that agencies should mitigate. This report divides these into the following six areas:

  1. Overall trends
  2. Information technology
  3. Asset management
  4. Governance
  5. Ethics and conduct
  6. Risk management.

Internal controls are processes, policies and procedures that help agencies to:

  • operate effectively and efficiently
  • produce reliable financial reports
  • comply with laws and regulations.

This chapter outlines the overall trends for agency controls and governance issues, including the number of findings, level of risk and the most common deficiencies we found across agencies. The rest of this volume then illustrates this year’s controls and governance findings in more detail.

Issues

Recommendations

1.1 New and repeat findings

The number of internal control deficiencies reduced over the past three years, but new higher-risk information technology (IT) control deficiencies were reported in 2016–17.

Deficiencies repeated from previous years still make up a sizeable proportion of all internal control deficiencies.

Recommendation

Agencies should focus on emerging IT risks, but also manage new IT risks, reduce existing IT control deficiencies, and address repeat internal control deficiencies on a more timely basis.

1.2 High risk findings

We found seven high risk internal control deficiencies, which might significantly affect agencies.

Recommendation

Agencies should rectify high risk internal control deficiencies as a priority

1.3 Common findings

The most common internal control deficiencies related to poor or absent IT controls.

We found some common governance deficiencies across multiple agencies.

Recommendation

Agencies should coordinate actions and resources to help rectify common IT control and governance deficiencies.

Information technology (IT) has become increasingly important for government agencies’ financial reporting and to deliver their services efficiently and effectively. Our audits reviewed whether agencies have effective controls in place over their IT systems. We found that IT security remains the source of many control weakness in agencies.

Issues Recommendations

2.1 IT security

User access administration

While 95 per cent of agencies have policies about user access, about two-thirds were compliant with these policies. Agencies can improve how they grant, change and end user access to their systems.

Recommendation

Agencies should strengthen user access administration to prevent inappropriate access to sensitive systems. Agencies should:

  • establish and enforce clear policies and procedures
  • review user access regularly
  • remove user access for terminated staff promptly
  • change user access for transferred staff promptly.

Privileged access

Sixty-eight per cent of agencies do not adequately manage who can access their information systems, and many do not sufficiently monitor or restrict privileged access.

Recommendation

Agencies should tighten privileged user access to protect their information systems and reduce the risks of data misuse and fraud. Agencies should ensure they:

  • only grant privileged access in line with the responsibilities of a position
  • review the level of access regularly
  • limit privileged access to necessary functions and data
  • monitor privileged user account activity on a regular basis.

Password controls

Forty-one per cent of agencies did not meet either their own standards or minimum standards for password controls.

Recommendation

Agencies should review and enforce password controls to strengthen security over sensitive systems. As a minimum, password parameters should include:

  • minimum password lengths and complexity requirements
  • limits on the number of failed log-in attempts
  • password history (such as the number of passwords remembered)
  • maximum and minimum password ages.

2.2 Cyber Security

Cyber security framework

Agencies do not have a common view on what constitutes a cyber attack, which limits understanding the extent of the cyber security threat.

Recommendation

The Department of Finance, Services and Innovation should revisit its existing framework to develop a shared cyber security terminology and strengthen the current reporting requirements for cyber incidents.

Cyber security strategies

While 82 per cent of agencies have dedicated resources to address cyber security, they can strengthen their strategies, expertise and staff awareness.

Recommendations

The Department of Finance, Services and Innovation should:

  • mandate minimum standards and require agencies to regularly assess and report on how well they mitigate cyber security risks against these standards
  • develop a framework that provides for cyber security training.

Agencies should ensure they adequately resource staff dedicated to cyber security.

2.3 Other IT systems

Change control processes

Some agencies need to improve change control processes to avoid unauthorised or inaccurate system changes.

Recommendation

Agencies should consistently perform user acceptance testing before system upgrades and changes. They should also properly approve and document changes to IT systems.

Disaster recovery planning

Agencies can do more to adequately assess critical business systems to enforce effective disaster recovery plans. This includes reviewing and testing their plans on a timely basis.

Recommendation

Agencies should complete business impact analyses to strengthen disaster recovery plans, then regularly test and update their plans.

Agency service delivery relies on developing and renewing infrastructure assets such as schools, hospitals, roads, or public housing. Agencies are currently investing significantly in new assets. Agencies need to manage the scale and volume of current capital projects in order to deliver new infrastructure on time, on budget and realise the intended benefits. We found agencies can improve how they:

  • manage their major capital projects
  • dispose of existing assets.
Issues Recommendations or conclusions

3.1 Capital investment

Capital asset investment ratios

Most agencies report high capital investment ratios, but one-third of agencies’ capital investment ratios are less than one.

Recommendation

Agencies with high capital asset investment ratios should ensure their project management and delivery functions have the capacity to deliver their current and forward work programs.

Volume of capital spending

Most agencies have significant forward spending commitments for capital projects. However, agencies’ actual capital expenditure has been below budget for the last three years.

Conclusion

The significant increase in capital budget underspends warrant investigation, particularly where this has resulted from slower than expected delivery of projects from previous years.

3.2 Capital projects

Major capital projects

Agencies’ major capital projects were underspent by 13 percent against their budgets.

Conclusion

The causes of agency budget underspends warrant investigation to ensure the NSW Government’s infrastructure commitment is delivered on time.

Capital project governance

Agencies do not consistently prepare business cases or use project steering committees to oversee major capital projects.

Conclusion

Agencies that have project management processes that include robust business cases and regular updates to their steering committees (or equivalent) are better able to provide those projects with strategic direction and oversight.

3.3. Asset disposals

Asset disposal procedures

Agencies need to strengthen their asset disposal procedures.

Recommendations

Agencies should have formal processes for disposing of surplus properties.

Agencies should use Property NSW to manage real property sales unless, as in the case for State owned corporations, they have been granted an exemption.

Governance refers to the high-level frameworks, processes and behaviours that help an organisation to achieve its objectives, comply with legal and other requirements, and meet a high standard of probity, accountability and transparency.

This chapter sets out the governance lighthouse model the Audit Office developed to help agencies reach best practice. It then focuses on two key areas: continuous disclosure and shared services arrangements. The following two chapters look at findings related to ethics and risk management.

Issues Recommendations or conclusions

4.1 Governance arrangements

Continuous disclosure

Continuous disclosure promotes improved performance and public trust and aides better decision-making. Continuous disclosure is only mandatory for NSW Government Businesses such as State owned corporations.

Conclusion

Some agencies promote transparency and accountability by publishing on their websites a continuous disclosure policy that provides for, and encourages:

  • regular public disclosure of key performance information
  • disclosure of both positive and negative information
  • prompt reporting of significant issues.

4.2 Shared services

Service level agreements

Some agencies do not have service level agreements for their shared service arrangements.

Many of the agreements that do exist do not adequately specify controls, performance or reporting requirements. This reduces the effectiveness of shared services arrangements.

Conclusion

Agencies are better able to manage the quality and timeliness of shared service arrangements where they have a service level agreement in place. Ideally, the terms of service should be agreed before services are transferred to the service provider and:

  • specify the controls a provider must maintain
  • specify key performance targets
  • include penalties for non-compliance.

Shared service performance

Some agencies do not set performance standards for their shared service providers or regularly review performance results.

Conclusion

Agencies can achieve better results from shared service arrangements when they regularly monitor the performance of shared service providers using key measures for the benefits realised, costs saved and quality of services received.

Before agencies extend or renegotiate a contract, they should comprehensively assess the services received and test the market to maximise value for money.

All government sector employees must demonstrate the highest levels of ethical conduct, in line with standards set by The Code of Ethics and Conduct for NSW government sector employees.

This chapter looks at how well agencies are managing these requirements, and where they can improve their policies and processes.

We found that agencies mostly have the appropriate codes, frameworks and policies in place. But we have highlighted opportunities to improve the way they manage those systems to reduce the risks of unethical conduct.

Issues Recommendations or conclusions

5.1 Ethical framework

Code of conduct

All agencies we reviewed have a code of conduct, but they can still improve the way they update and manage their codes to reduce the risk of fraud and unethical behaviour.

Recommendation

Agencies should regularly review their code-of-conduct policies and ensure they keep their codes of conduct up-to-date.

Statement of business ethics

Most agencies maintain an ethical framework, but some can enhance their related processes, particularly when dealing with external clients, customers, suppliers and contractors.

Conclusion

Agencies can enhance their ethical frameworks by publishing a Statement of Business Ethics, which communicates their values and culture.

5.2 Potential conflicts of interest

Conflicts of interest

All agencies have a conflicts-of-interest policy, but most can improve how they identify, manage and avoid conflicts of interest.

Recommendation

Agencies should improve the way they manage conflicts of interest, particularly by:

  • requiring senior executives to make a conflict-of-interest declaration at least annually
  • implementing processes to identify and address outstanding declarations
  • providing annual training to staff
  • maintaining current registers of conflicts of interest.

Gifts and benefits

While all agencies already have a formal gifts-and-benefits policy, we found gaps in the management of gifts and benefits by some that increase the risk of unethical conduct.

Recommendation

Agencies should improve the way they manage gifts and benefits by promptly updating registers and providing annual training to staff.

Risk management is an integral part of effective corporate governance. It helps agencies to identify, assess and prioritise the risks they face and in turn minimise, monitor and control the impact of unforeseen events. It also means agencies can respond to opportunities that may emerge and improve their services and activities.

This year we looked at the overall maturity of the risk management frameworks that agencies use, along with two important risk management elements: risk culture and risk registers.

Issues Recommendations or conclusions

6.1 Risk management maturity

All agencies have implemented risk management frameworks, but with varying levels of maturity in their application.

Agencies’ averaged a score of 3.1 out of five across five critical assessment criteria for risk management. While strategy and governance fared best, the areas that most need to improve are risk culture, and systems and intelligence.

Conclusion

Agencies have introduced risk management frameworks and practices as required by the Treasury’s:

  • 'Risk Management Toolkit for the NSW Public Sector'
  • 'Internal Audit and Risk Management Policy for the NSW Public Sector'.

However, more can be done to progress risk management maturity and embed risk management in agency culture.

6.2 Risk management elements

Risk culture

Most agencies have started to embed risk management into the culture of their organisation. But only some have successfully done so, and most agencies can improve their risk culture.

 

 

Conclusion

Agencies can improve their risk culture by:

  • setting an appropriate tone from the top
  • training all staff in effective risk management
  • ensuring desired risk behaviours and culture are supported, monitored, and reinforced through business plans, or the equivalent and employees' performance assessments.

Risk registers and reporting

Some agencies do not report their significant risks to their lead agency, which may impair the way resources are allocated in their cluster. Some agencies do not integrate risk registers at a divisional and whole-of-enterprise level.

Conclusion

Agencies not reporting significant risks at the cluster level increases the likelihood that significant risks are not being mitigated appropriately.

Effective risk management can improve agency decision-making, protect reputations and lead to significant efficiencies and cost savings. By embedding risk management directly into their operations, agencies can also derive extra value for their activities and services.