Actions for Volume Six 2015 Transport
Volume Six 2015 Transport
Public transport revenue decreased by 2.7 per cent despite a fare increase and increased patronage. Twenty-five per cent of all Opal trips (over 74 million) were free, including 47 per cent of trips on ferries, according to a report released today by the New South Wales Acting Auditor-General, Tony Whitfield. These trips were valued at $189 million.
Actions for Large construction projects
Large construction projects
The independent assurance given to the NSW Government and sponsor agencies on the viability of large capital projects throughout their lifecycle is inadequate. Government policy is regularly not followed and not properly communicated to those responsible for implementing such policy.
This audit sought to test the effectiveness of the NSW capital project assurance system - which includes gateway reviews and reporting - but significant levels of non-compliance identified in our case studies prevented this. The NSW Commission of Audit also identified this issue in 2012. Gateway reviews are conducted by independent reviewers at key stages of a project’s life cycle and provide an independent assessment on a project’s readiness to proceed to the next stage.
Parliamentary reference - Report number #252 - released 7 May 2015
Actions for Areas of focus from 2014
Areas of focus from 2014
Actions for Security of critical IT infrastructure
Security of critical IT infrastructure
Roads and Maritime Services and Transport for NSW have deployed many controls to protect traffic management systems but these would have been only partially effective in detecting and preventing incidents and unlikely to support a timely response. There was a potential for unauthorised access to sensitive information and systems that could have disrupted traffic.
Until Roads and Maritime Services’ IT disaster recovery site is fully commissioned, a disaster involving the main data centre is likely to lead to higher congestion in the short-term as traffic controllers would be operating on a regional basis without the benefit of the Traffic Management Centre.
Parliamentary reference - Report number #248 - released 21 January 2015
Actions for Volume Seven 2013 focusing on Superannuation and Insurance
Volume Seven 2013 focusing on Superannuation and Insurance
Unqualified audit opinions were issued on the NSW Government controlled insurance and compensation entities’ 30 June 2013 financial statements, except the NSW Self Insurance Corporation (SICorp). SICorp’s audit opinion was qualified due to non-compliance with Australian Accounting Standards applicable to general insurance contracts. The auditor’s reports drew attention to the significant uncertainty in estimating outstanding claims liabilities of $14.0 billion in the Workers’ Compensation Nominal Insurer and $2.1 billion in the Lifetime Care and Support Authority. The audit of the Building Insurers’ Guarantee Corporation was not complete at the time of this report and is excluded from this commentary.
Actions for Condition of State Roads
Condition of State Roads
The Roads and Traffic Authority (RTA) has improved the overall surface condition of State Roads in the last decade. Country road surfaces are now generally much better. Ride quality has improved and cracking has been reduced. The RTA has also achieved a substantial reduction in the number of structurally deficient bridges over the same period.
Despite a significant increase in the State’s contribution to maintenance since 1999-2000, the RTA has deferred road rebuilding projects. The RTA is rebuilding at less than half its long term target, and has not met this target at any time this decade. The RTA has not identified how it will address deferred rebuilding, although it advises it is developing a new road network management plan which will address this.
Parliamentary reference - Report number #157 - released 16 August 2006
Actions for The Cross City Tunnel Project
The Cross City Tunnel Project
In our opinion the Government’s ‘no net cost to government’ requirement was a legitimate (but not the only possible) basis for the tunnel bid process. The Government was entitled to decide that tunnel users meet the tunnel costs. Structuring the bid process on the basis of an upfront reimbursement of costs incurred (or to be incurred) by the Roads and Traffic Authority (RTA) was therefore appropriate.
In our opinion, however, the Government, Treasury and the RTA did not sufficiently consider the implications of an upfront payment involving more than simple project cost reimbursement (i.e. the ‘Business Consideration Fee’ component). In addition, the RTA was wrong to change the toll escalation factor late in 2002 to compensate the tunnel operator, Cross City Motorway Pty Ltd, for additional costs.
Parliamentary reference - Report number #152 - released 31 May 2006
Actions for Agencies working together to improve services
Agencies working together to improve services
In the cases we examined, we found that agencies working together can improve services or results. However, the changes were not always as great as anticipated or had not reached maximum potential. Establishing the right governance framework and accountability requirements between partners at the start of the project is critical to success. And joint responsibility requires new funding and reporting arrangements to be developed.
Parliamentary reference - Report number #149 - released 22 March 2006
Actions for Management of road passenger transport regulation
Management of road passenger transport regulation
The Audit Office is of the opinion that the Department’s levels of regulatory activity in respect of road passenger transport regulation may have exceeded optimum levels. The Department’s current focus on processing activity limits the Department in achieving all of its desired outcomes. The Audit Office considers that a change in the approach to undertaking and managing road passenger transport regulatory activities would achieve better outcomes for the community and a better use of resources within the Department.
The Audit Office believes that while there is scope to make some improvements from procedural changes, such changes would not be sufficient to generate significant improvements.
Parliamentary reference - Report number #75 - released 6 September 2000