Reports

Published

Actions for Newcastle Urban Transformation and Transport Program

Newcastle Urban Transformation and Transport Program

Transport
Planning
Compliance
Infrastructure
Management and administration
Procurement
Project management

The urban renewal projects on former railway land in the Newcastle city centre are well targeted to support the objectives of the Newcastle Urban Transformation and Transport Program (the Program), according to a report released today by the Auditor-General for New South Wales, Margaret Crawford. The planned uses of the former railway land achieve a balance between the economic and social objectives of the Program at a reasonable cost to the government. However, the evidence that the cost of the light rail will be justified by its contribution to the Program is not convincing.

The Newcastle Urban Transformation and Transport Program (the Program) is an urban renewal and transport program in the Newcastle city centre. The Hunter and Central Coast Development Corporation (HCCDC) has led the Program since 2017. UrbanGrowth NSW led the Program from 2014 until 2017. Transport for NSW has been responsible for delivering the transport parts of the Program since the Program commenced. All references to HCCDC in this report relate to both HCCDC and its predecessor, the Hunter Development Corporation. All references to UrbanGrowth NSW in this report relate only to its Newcastle office from 2014 to 2017.

This audit had two objectives:

  1. To assess the economy of the approach chosen to achieve the objectives of the Program.
  2. To assess the effectiveness of the consultation and oversight of the Program.

We addressed the audit objectives by answering the following questions:

a) Was the decision to build light rail an economical option for achieving Program objectives?
b) Has the best value been obtained for the use of the former railway land?
c) Was good practice used in consultation on key Program decisions?
d) Did governance arrangements support delivery of the program?

Conclusion
1. The urban renewal projects on the former railway land are well targeted to support the objectives of the Program. However, there is insufficient evidence that the cost of the light rail will be justified by its contribution to Program objectives.

The planned uses of the former railway land achieve a balance between the economic and social objectives of the Program at a reasonable cost to the Government. HCCDC, and previously UrbanGrowth NSW, identified and considered options for land use that would best meet Program objectives. Required probity processes were followed for developments that involved financial transactions. Our audit did not assess the achievement of these objectives because none of the projects have been completed yet.

Analysis presented in the Program business case and other planning documents showed that the light rail would have small transport benefits and was expected to make a modest contribution to broader Program objectives. Analysis in the Program business case argued that despite this, the light rail was justified because it would attract investment and promote economic development around the route. The Program business case referred to several international examples to support this argument, but did not make a convincing case that these examples were comparable to the proposed light rail in Newcastle.

The audited agencies argue that the contribution of light rail cannot be assessed separately because it is a part of a broader Program. The cost of the light rail makes up around 53 per cent of the total Program funding. Given the cost of the light rail, agencies need to be able to demonstrate that this investment provides value for money by making a measurable contribution to the Program objectives.

2. Consultation and oversight were mostly effective during the implementation stages of the Program. There were weaknesses in both areas in the planning stages.

Consultations about the urban renewal activities from around 2015 onward followed good practice standards. These consultations were based on an internationally accepted framework and met their stated objectives. Community consultations on the decision to close the train line were held in 2006 and 2009. However, the final decision in 2012 was made without a specific community consultation. There was no community consultation on the decision to build a light rail.

The governance arrangements that were in place during the planning stages of the Program did not provide effective oversight. This meant there was not a single agreed set of Program objectives until 2016 and roles and responsibilities for the Program were not clear. Leadership and oversight improved during the implementation phase of the Program. Roles and responsibilities were clarified and a multi-agency steering committee was established to resolve issues that needed multi-agency coordination.
The light rail is not justified by conventional cost-benefit analysis and there is insufficient evidence that the indirect contribution of light rail to achieving the economic development objectives of the Program will justify the cost.
Analysis presented in Program business cases and other planning documents showed that the light rail would have small transport benefits and was expected to make a modest contribution to broader Program objectives. Analysis in the Program business case argued that despite this, the light rail was justified because it would attract investment and promote economic development around the route. The Program business case referred to several international examples to support this argument, but did not make a convincing case that these examples were comparable to the proposed light rail in Newcastle.
The business case analysis of the benefits and costs of light rail was prepared after the decision to build light rail had been made and announced. Our previous reports, and recent reports by others, have emphasised the importance of completing thorough analysis before announcing infrastructure projects. Some advice provided after the initial light rail decision was announced was overly optimistic. It included benefits that cannot reasonably be attributed to light rail and underestimated the scope and cost of the project.
The audited agencies argue that the contribution of light rail cannot be assessed separately because it is part of a broader Program. The cost of the light rail makes up around 53 per cent of the total Program funding. Given the high cost of the light rail, we believe agencies need to be able to demonstrate that this investment provides value for money by making a measurable contribution to the Program objectives.

Recommendations
For future infrastructure programs, NSW Government agencies should support economical decision-making on infrastructure projects by:
  • providing balanced advice to decision makers on the benefits and risks of large infrastructure investments at all stages of the decision-making process
  • providing scope and cost estimates that are as accurate and complete as possible when initial funding decisions are being made
  • making business cases available to the public.​​​​​​
The planned uses of the former railway land achieve a balance between the economic and social objectives of the Program at a reasonable cost to the government.

The planned uses of the former railway land align with the objectives of encouraging people to visit and live in the city centre, creating attractive public spaces, and supporting growth in employment in the city. The transport benefits of the activities are less clear, because the light rail is the major transport project and this will not make significant improvements to transport in Newcastle.

The processes used for selling and leasing parts of the former railway land followed industry standards. Options for the former railway land were identified and assessed systematically. Competitive processes were used for most transactions and the required assessment and approval processes were followed. The sale of land to the University of Newcastle did not use a competitive process, but required processes for direct negotiations were followed.

Recommendation
By March 2019, the Hunter and Central Coast Development Corporation should:
  • work with relevant stakeholders to explore options for increasing the focus on the heritage objective of the Program in projects on the former railway land. This could include projects that recognise the cultural and industrial heritage of Newcastle.
Consultations about the urban renewal activities followed good practice standards, but consultation on transport decisions for the Program did not.

Consultations focusing on urban renewal options for the Program included a range of stakeholders and provided opportunities for input into decisions about the use of the former railway land. These consultations received mostly positive feedback from participants. Changes and additions were made to the objectives of the Program and specific projects in response to feedback received. 

There had been several decades of debate about the potential closure of the train line, including community consultations in 2006 and 2009. However, the final decision to close the train line was made and announced in 2012 without a specific community consultation. HCCDC states that consultation with industry and business representatives constitutes community consultation because industry representatives are also members of the community. This does not meet good practice standards because it is not a representative sample of the community.

There was no community consultation on the decision to build a light rail. There were subsequent opportunities for members of the community to comment on the implementation options, but the decision to build it had already been made. A community and industry consultation was held on which route the light rail should use, but the results of this were not made public. 

Recommendation
For future infrastructure programs, NSW Government agencies should consult with a wide range of stakeholders before major decisions are made and announced, and report publicly on the results and outcomes of consultations. 

The governance arrangements that were in place during the planning stages of the Program did not provide effective oversight. Project leadership and oversight improved during the implementation phase of the Program.

Multi-agency coordination and oversight were ineffective during the planning stages of the Program. Examples include: multiple versions of Program objectives being in circulation; unclear reporting lines for project management groups; and poor role definition for the initial advisory board. Program ownership was clarified in mid-2016 with the appointment of a new Program Director with clear accountability for the delivery of the Program. This was supported by the creation of a multi-agency steering committee that was more effective than previous oversight bodies.

The limitations that existed in multi-agency coordination and oversight had some negative consequences in important aspects of project management for the Program. This included whole-of-government benefits management and the coordination of work to mitigate impacts of the Program on small businesses.

Recommendations
For future infrastructure programs, NSW Government agencies should: 

  • develop and implement a benefits management approach from the beginning of a program to ensure responsibility for defining benefits and measuring their achievement is clear
  • establish whole-of-government oversight early in the program to guide major decisions. This should include:
    • agreeing on objectives and ensuring all agencies understand these
    • clearly defining roles and responsibilities for all agencies
    • establishing whole-of-government coordination for the assessment and mitigation of the impact of major construction projects on businesses and the community.

By March 2019, the Hunter and Central Coast Development Corporation should update and implement the Program Benefits Realisation Plan. This should include:

  • setting measurable targets for the desired benefits
  • clearly allocating ownership for achieving the desired benefits
  • monitoring progress toward achieving the desired benefits and reporting publicly on the results.

Appendix one - Response from agencies    

Appendix two - About the audit

Appendix three - Performance auditing

 

Parliamentary reference - Report number #310 - released 12 December 2018

Published

Actions for Managing risks in the NSW public sector: risk culture and capability

Managing risks in the NSW public sector: risk culture and capability

Finance
Health
Justice
Treasury
Internal controls and governance
Management and administration
Risk
Workforce and capability

The Ministry of Health, NSW Fair Trading, NSW Police Force, and NSW Treasury Corporation are taking steps to strengthen their risk culture, according to a report released today by the Auditor-General, Margaret Crawford. 'Senior management communicates the importance of managing risk to their staff, and there are many examples of risk management being integrated into daily activities', the Auditor-General said.

We did find that three of the agencies we examined could strengthen their culture so that all employees feel comfortable speaking openly about risks. To support innovation, senior management could also do better at communicating to their staff the levels of risk they are willing to accept.

Effective risk management is essential to good governance, and supports staff at all levels to make informed judgements and decisions. At a time when government is encouraging innovation and exploring new service delivery models, effective risk management is about seizing opportunities as well as managing threats.

Over the past decade, governments and regulators around the world have increasingly turned their attention to risk culture. It is now widely accepted that organisational culture is a key element of risk management because it influences how people recognise and engage with risk. Neglecting this ‘soft’ side of risk management can prevent institutions from managing risks that threaten their success and lead to missed opportunities for change, improvement or innovation.

This audit assessed how effectively NSW Government agencies are building risk management capabilities and embedding a sound risk culture throughout their organisations. To do this we examined whether:

  • agencies can demonstrate that senior management is committed to risk management
  • information about risk is communicated effectively throughout agencies
  • agencies are building risk management capabilities.

The audit examined four agencies: the Ministry of Health, the NSW Fair Trading function within the Department of Finance, Services and Innovation, NSW Police Force and NSW Treasury Corporation (TCorp). NSW Treasury was also included as the agency responsible for the NSW Government's risk management framework.

Conclusion
All four agencies examined in the audit are taking steps to strengthen their risk culture. In these agencies, senior management communicates the importance of managing risk to their staff. They have risk management policies and funded central functions to oversee risk management. We also found many examples of risk management being integrated into daily activities.
That said, three of the four case study agencies could do more to understand their existing risk culture. As good practice, agencies should monitor their employees’ attitude to risk. Without a clear understanding of how employees identify and engage with risk, it is difficult to tell whether the 'tone' set by the executive and management is aligned with employee behaviours.
Our survey of risk culture found that three agencies could strengthen a culture of open communication, so that all employees feel comfortable speaking openly about risks. To support innovation, senior management could also do better at communicating to their staff the levels of risk they are willing to accept.
Some agencies are performing better than others in building their risk capabilities. Three case study agencies have reviewed the risk-related skills and knowledge of their workforce, but only one agency has addressed the gaps the review identified. In three agencies, staff also need more practical guidance on how to manage risks that are relevant to their day-to-day responsibilities.
NSW Treasury provides agencies with direction and guidance on risk management through policy and guidelines. Its principles-based approach to risk management is consistent with better practice. Nevertheless, there is scope for NSW Treasury to develop additional practical guidance and tools to support a better risk culture in the NSW public sector. NSW Treasury should encourage agency heads to form a view on the current risk culture in their agencies, identify desirable changes to that risk culture, and take steps to address those changes. 

In assessing an agency’s risk culture, we focused on four key areas:

Executive sponsorship (tone at the top)

In the four agencies we reviewed, senior management is communicating the importance of managing risk. They have endorsed risk management frameworks and funded central functions tasked with overseeing risk management within their agencies.

That said, we found that three case study agencies do not measure their existing risk culture. Without clear measures of how employees identify and engage with risk, it is difficult for agencies to tell whether employee's behaviours are aligned with the 'tone' set by the executive and management.

For example, in some agencies we examined we found a disconnect between risk tolerances espoused by senior management and how these concepts were understood by staff.

Employee perceptions of risk management

Our survey of staff indicated that while senior leaders have communicated the importance of managing risk, more could be done to strengthen a culture of open communication so that all employees feel comfortable speaking openly about risks. We found that senior management could better communicate to their staff the levels of risk they should be willing to accept.

Integration of risk management into daily activities and links to decision-making

We found examples of risk management being integrated into daily activities. On the other hand, we also identified areas where risk management deviated from good practice. For example, we found that corporate risk registers are not consistently used as a tool to support decision-making.

Support and guidance to help staff manage risks

Most case study agencies are monitoring risk-related skills and knowledge of their workforce, but only one agency has addressed the gaps it identified. While agencies are providing risk management training, surveyed staff in three case study agencies reported that risk management training is not adequate.

NSW Treasury provides agencies with direction and guidance on risk management through policy and guidelines. In line with better practice, NSW Treasury's principles-based policy acknowledges that individual agencies are in a better position to understand their own risks and design risk management frameworks that address those risks. Nevertheless, there is scope for NSW Treasury to refine its guidance material to support a better risk culture in the NSW public sector.

Recommendation

By May 2019, NSW Treasury should:

  • Review the scope of its risk management guidance, and identify additional guidance, training or activities to improve risk culture across the NSW public sector. This should focus on encouraging agency heads to form a view on the current risk culture in their agencies, identify desirable changes to that risk culture, and take steps to address those changes.

Published

Actions for Detecting and responding to cyber security incidents

Detecting and responding to cyber security incidents

Finance
Cyber security
Information technology
Internal controls and governance
Management and administration
Workforce and capability

A report released today by the Auditor-General for New South Wales, Margaret Crawford, found there is no whole-of-government capability to detect and respond effectively to cyber security incidents. There is very limited sharing of information on incidents amongst agencies, and some agencies have poor detection and response practices and procedures.

The NSW Government relies on digital technology to deliver services, organise and store information, manage business processes, and control critical infrastructure. The increasing global interconnectivity between computer networks has dramatically increased the risk of cyber security incidents. Such incidents can harm government service delivery and may include the theft of information, denial of access to critical technology, or even the hijacking of systems for profit or malicious intent.

This audit examined cyber security incident detection and response in the NSW public sector. It focused on the role of the Department of Finance, Services and Innovation (DFSI), which oversees the Information Security Community of Practice, the Information Security Event Reporting Protocol, and the Digital Information Security Policy (the Policy).

The audit also examined ten case study agencies to develop a perspective on how they detect and respond to incidents. We chose agencies that are collectively responsible for personal data, critical infrastructure, financial information and intellectual property.

Conclusion
There is no whole‑of‑government capability to detect and respond effectively to cyber security incidents. There is limited sharing of information on incidents amongst agencies, and some of the agencies we reviewed have poor detection and response practices and procedures. There is a risk that incidents will go undetected longer than they should, and opportunities to contain and restrict the damage may be lost.
Given current weaknesses, the NSW public sector’s ability to detect and respond to incidents needs to improve significantly and quickly. DFSI has started to address this by appointing a Government Chief Information Security Officer (GCISO) to improve cyber security capability across the public sector. Her role includes coordinating efforts to increase the NSW Government’s ability to respond to and recover from whole‑of‑government threats and attacks.

Some of our case study agencies had strong processes for detection and response to cyber security incidents but others had a low capability to detect and respond in a timely way.

Most agencies have access to an automated tool for analysing logs generated by their IT systems. However, coverage of these tools varies. Some agencies do not have an automated tool and only review logs periodically or on an ad hoc basis, meaning they are less likely to detect incidents.

Few agencies have contractual arrangements in place for IT service providers to report incidents to them. If a service provider elects to not report an incident, it will delay the agency’s response and may result in increased damage.

Most case study agencies had procedures for responding to incidents, although some lack guidance on who to notify and when. Some agencies do not have response procedures, limiting their ability to minimise the business damage that may flow from a cyber security incident. Few agencies could demonstrate that they have trained their staff on either incident detection or response procedures and could provide little information on the role requirements and responsibilities of their staff in doing so.

Most agencies’ incident procedures contain limited information on how to report an incident, who to report it to, when this should occur and what information should be provided. None of our case study agencies’ procedures mentioned reporting to DFSI, highlighting that even though reporting is mandatory for most agencies their procedures do not require it.

Case study agencies provided little evidence to indicate they are learning from incidents, meaning that opportunities to better manage future incidents may be lost.

Recommendations

The Department of Finance, Services and Innovation should:

  • assist agencies by providing:
    • better practice guidelines for incident detection, response and reporting to help agencies develop their own practices and procedures
    • training and awareness programs, including tailored programs for a range of audiences such as cyber professionals, finance staff, and audit and risk committees
    • role requirements and responsibilities for cyber security across government, relevant to size and complexity of each agency
    • a support model for agencies that have limited detection and response capabilities
       
  • revise the Digital Information Security Policy and Information Security Event Reporting Protocol by
    • clarifying what security incidents must be reported to DFSI and when
    • extending mandatory reporting requirements to those NSW Government agencies not currently covered by the policy and protocol, including State owned corporations.

DFSI lacks a clear mandate or capability to provide effective detection and response support to agencies, and there is limited sharing of information on cyber security incidents.

DFSI does not currently have a clear mandate and the necessary resources and systems to detect, receive, share and respond to cyber security incidents across the NSW public sector. It does not have a clear mandate to assess whether agencies have an acceptable detection and response capability. It is aware of deficiencies in agencies and across whole‑of‑government, and has begun to conduct research into this capability.

Intelligence gathering across the public sector is also limited, meaning agencies may not respond to threats in a timely manner. DFSI has not allocated resources for gathering of threat intelligence and communicating it across government, although it has begun to build this capacity.

Incident reporting to DFSI is mandatory for most agencies, however, most of our case study agencies do not report incidents to DFSI, reducing the likelihood of containing an incident if it spreads to other agencies. When incidents have been reported, DFSI has not provided dedicated resources to assess them and coordinate the public sector’s response. There are currently no formal requirements for DFSI to respond to incidents and no guidance on what it is meant to do if an incident is reported. The lack of central coordination in incident response risks delays and increased damage to multiple agencies.

DFSI's reporting protocol is weak and does not clearly specify what agencies should report and when. This makes agencies less likely to report incidents. The lack of a standard format for incident reporting and a consistent method for assessing an incident, including the level of risk associated with it, also make it difficult for DFSI to determine an appropriate response.

There are limited avenues for sharing information amongst agencies after incidents have been resolved, meaning the public sector may be losing valuable opportunities to improve its protection and response.

Recommendations

The Department of Finance, Services and Innovation should:

  • develop whole‑of‑government procedure, protocol and supporting systems to effectively share reported threats and respond to cyber security incidents impacting multiple agencies, including follow-up and communicating lessons learnt
  • develop a means by which agencies can report incidents in a more effective manner, such as a secure online template, that allows for early warnings and standardised details of incidents and remedial advice
  • enhance NSW public sector threat intelligence gathering and sharing including formal links with Australian Government security agencies, other states and the private sector
  • direct agencies to include standard clauses in contracts requiring IT service providers report all cyber security incidents within a reasonable timeframe
  • provide assurance that agencies have appropriate reporting procedures and report to DFSI as required by the policy and protocol by:
    • extending the attestation requirement within the DISP to cover procedures and reporting
    • reviewing a sample of agencies' incident reporting procedures each year.

Published

Actions for Government Advertising 2009

Government Advertising 2009

Premier and Cabinet
Finance
Treasury
Compliance
Management and administration
Procurement
Regulation

We found that the two NSW Health campaigns had followed the required approval processes and were appropriate. We had some concerns with the two Department of Premier and Cabinet (DPC) campaigns. The revised Guidelines, which incorporate recommendations from earlier audit reports, are a positive step towards reducing the risk that publicly funded advertising could be used inappropriately. But there are still parts of the Guidelines that require a subjective judgement and therefore do little to help manage this risk. While we did not have any concerns with the two NSW Health campaigns, the two DPC campaigns highlighted these risks.

 

Parliamentary reference - Report number #194 - released 9 December 2009

Published

Actions for Handback of the M4 Tollway

Handback of the M4 Tollway

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management

This audit focuses on the M4 handback. It looks at whether the road will be in good condition when the State gets it back, and whether it will cope with the extra traffic after the toll is removed. These are critical issues for taxpayers and motorists. Taxpayers don’t want to be responsible for a large repair bill and motorists don’t want to be stuck in traffic jams.

To ensure that future private sector partnerships (PPP) deal adequately with handback, we recommend that the Roads and Traffic Authority (RTA):

  • ensure deeds spell out an appropriate inspection and testing program to determine repairs required to bring roads up to a satisfactory condition at handback (p.11)
  • ensure deeds link condition standards and maintenance approaches to changing industry standards and approaches over the life of the PPP (p.11)
  • consider including in deeds a requirement that operators provide a performance bond or similar security over the cost of handback repairs (p.11)
  • review the lessons learnt from the M4 tollway handback and determine whether it should seek to negotiate changes to existing tollway deeds to better deal with handback, by June 2010 (p.11)

 

Parliamentary reference - Report number #193 - released 27 October 2009

Published

Actions for Connecting with public transport

Connecting with public transport

Transport
Information technology
Infrastructure
Internal controls and governance
Management and administration
Project management
Service delivery
Workforce and capability

We see considerable potential for the Ministry of Transport to plan and manage interchanges more effectively, so as to make better use of our public transport network. We believe that the Ministry now needs to focus more on multi-modal transport planning and interchange performance. It needs to assign responsibility for the coordination and oversight of inter-modal operations to an entity resourced for the purpose. Without this it will continue to be very difficult to identify and address unmet needs, seek and secure stakeholder funding, and monitor and evaluate system performance.

 

Parliamentary reference - Report number #168 - released 6 June 2007

Published

Actions for Bus Maintenance and Bus Contracts

Bus Maintenance and Bus Contracts

Transport
Management and administration
Procurement
Service delivery

State Transit has developed fleet management plans and maintenance standards that meet its regulatory and contractual obligations as a bus operator and are consistent with vehicle manufacturers’ standards and best practice. However, assumptions used in fleet management plans to forecast fleet growth may not result in the most efficient and effective outcome for State Transit. Forecasts fail to take account of opportunities to redesign or reduce services where they exceed contract requirements and are difficult to justify on a commercial basis. Of greater concern are the consequences arising from bus maintenance practices not meeting State Transit’s own standards.

 

Parliamentary reference - Report number #97 - released 29 May 2002

Published

Actions for Government office accommodation

Government office accommodation

Treasury
Finance
Asset valuation
Management and administration
Procurement

The Audit Office has undertaken an audit on Government Office Accommodation. The audit examined the cost effectiveness of long-term leasing versus ownership and the housing of agencies involved with the delivery of core government activities.  Core activities are those intrinsically linked to basic and ongoing functions of Government and Parliament.

It recommends that:

  • the Government consider owning office accommodation, as opposed to leasing, for its long-term core needs, subject to a case by case analysis of the relevant financial and nonfinancial factors

  • the Government undertake an analysis of the costs/savings from proposed asset sales of office accommodation in light of the demonstrated need for long-term office accommodation (for core needs) New, Expired and Expiring Leases

  • given the findings of the own versus lease case studies presented in this report, it is recommended that the Government require agencies to undertake, in collaboration with the Department of Public Works and Services (DPWS) a cost/benefit analysis of available accommodation options prior to committing to any proposed major new leases

  • the Government direct the DPWS, in collaboration with all agencies, to negotiate the renewal of all major expired/expiring leases (where continued occupancy is warranted) in order to reduce the financial risk of above-market rent increases and the risk of cancellation of leases (Major leases are defined, for the purposes of these recommendations, to be those over $500,000 rental per annum or a net lettable area over 1,000 square metres) Management of Property Information

  •  in order to improve the integrity of the Government Office Accommodation Database, agencies be required to respond to the annual data request from DPWS by a predetermined date

  • a senior officer within each agency be required to certify to the accuracy of information provided by an agency as input to the database maintained by DPWS

  • DPWS verify, on a sample basis, information provided by agencies as input to the Government Office Accommodation Database Premier’s Memorandum No 97-2

  • the compliance by agencies with Premier’s Memorandum No 97-2 Government Office Accommodation and Property Disposal be established by DPWS.

 

Parliamentary reference - Report number #45 - released 11 December 1997

Published

Actions for Review of Eastern Distributor

Review of Eastern Distributor

Transport
Infrastructure
Procurement
Project management

Following a resolution of the Legislative Council, the Audit Office has undertaken a performance audit of the Eastern Distributor. For a number of reasons, The Audit Office is not in the position to determine “whether the proposed toll and concession period represents the best deal”. In part this is the result of time constraints which do not allow a careful analysis of many toll and concession options. Similarly, the audit does not answer “whether the current proposal represents the best environmental outcome”. But each of these issues (toll and concession and environmental consequences) is discussed in the audit report.

The Audit Office recommends that the Roads and Traffic Authority (RTA), for any further major project of this type, ensures that it establishes a process which allows all decision makers to have a thorough understanding of the reasonableness of the proponents’ offers and their implications for the State and for the public. The Audit Office also recommends that the RTA should at the outset consult with TCorp in respect of each major project put to tender.

 

Parliamentary reference - Report number #42 - released 31 July 1997