Refine search Expand filter

Reports

Published

Actions for Design and implementation of the Transport Asset Holding Entity

Design and implementation of the Transport Asset Holding Entity

Transport
Treasury
Asset valuation
Financial reporting
Infrastructure
Procurement
Risk
Service delivery

What the report is about

The Transport Asset Holding Entity (TAHE) is the State's custodian of rail assets. It is a state owned corporation and commenced operating on 1 July 2020.

This audit assessed the effectiveness of NSW Government agencies' design and implementation of TAHE. We audited TAHE, Transport for NSW (TfNSW) and NSW Treasury.

Separate and related audits on TAHE are reported in 'State Finances 2022', 'State Finances 2021' and 'Transport and Infrastructure 2022' reports.

What we found

The design and implementation of TAHE, which spanned seven years, was not effective.

The process was not cohesive or transparent. It delivered an outcome that is unnecessarily complex in order to support an accounting treatment to meet the NSW Government's short-term Budget objectives, while creating an obligation for future governments.

The benefits of TAHE were claimed in the 2015–16 NSW Budget before the enabling legislation was passed by Parliament in 2017. This committed the agencies to implement a solution that justified the 2015–16 Budget impacts, regardless of any challenges that arose.

Rail safety arrangements were a priority throughout TAHE's design and implementation, and risks were raised and addressed.

Agencies relied heavily on consultants on matters related to the creation of TAHE, but failed to effectively manage these engagements. Agencies failed to ensure that consultancies delivered independent advice as an input to decision-making. A small number of firms were used repeatedly to provide advice on the same topic. The final cost of TAHE-related consultancies was $22.6 million compared to the initial estimated cost of $12.9 million.

What we recommended

We recommended that the audited agencies should:

  • improve accountability and transparency for major new fiscal transformation initiatives
  • ensure entities do not reflect the financial impact of significant initiatives in the Budget when there is uncertainty, or it creates perverse incentives
  • review record keeping practices, systems and policies to ensure compliance with the State Records Act 1998, and the NSW Government Information Classification, Labelling and Handling Guidelines
  • review procurement policies to ensure that consultant use complies with all NSW Government policy requirements.

The NSW Government established the Transport Asset Holding Entity (TAHE), a statutory State Owned Corporation (SOC), on 1 July 2020 to replace the former rail infrastructure owner – RailCorp. It is the State's custodian of rail network assets, including rail tracks and other infrastructure, rolling stock, land, train stations and facilities, retail space, and signal and power systems, within metropolitan and regional New South Wales. It is responsible for $2.8 billion of major capital projects in 2022–23.

TAHE was established under Part 2 of the Transport Administration Act 1988 and is governed by a decision-making board. The Treasurer and the Minister for Finance and Employee Relations are the Shareholding Ministers of TAHE, and they annually agree performance expectations articulated in a Statement of Corporate Intent.

Whereas TAHE is the custodian of rail assets, Sydney Trains and NSW Trains operate public rail services. TAHE does not have responsibility for the operation of the heavy rail network or train services, nor does it have network control functions. TAHE, Sydney Trains and NSW Trains are in the Transport and Infrastructure cluster in the public sector (formerly the Transport cluster and renamed in April 2022), which also includes Sydney Metro and Transport for NSW (TfNSW).

TfNSW leads the Transport and Infrastructure cluster. Its role is to set the strategic direction for transport across the State. This involves the shaping of planning, policy, strategy, regulation, resource allocation and other service and non-service delivery functions for all modes of transport.

TAHE's Operating Licence is granted by the Portfolio Minister and authorises the entity to perform the functions required to acquire, develop, finance, divest and hold assets, pursuant to the Transport Administration Act 1988. The Portfolio Minister also issues a Statement of Expectations which outlines the government’s expectation for the business for the next three to five years.

TAHE's original Portfolio Minister was the Minister for Transport who approved, on 30 June 2020, the issuing of an interim 12-month Operating Licence to enable TAHE to commence operating on 1 July 2020. The Portfolio Minister then granted TAHE's current Operating Licence in 2021. After TAHE requested a 12-month extension to its current Operating Licence, its next Operating Licence is due on 1 July 2024. The current Portfolio Minister is the Minister for Infrastructure, Cities and Active Transport.

About this audit

This audit assessed the effectiveness of NSW Government agencies' design and implementation of TAHE. In making this assessment, we considered whether: 

  • the process of designing and implementing TAHE was cohesive and transparent, and delivered an effective outcome
  • agencies' roles and responsibilities were clear in the planning of TAHE
  • agencies effectively identified and managed certain risks.

Conclusion

The design and implementation of TAHE was not effective. The process was not cohesive or transparent. It delivered an outcome that is unnecessarily complex in order to meet the NSW Government's short-term Budget objectives, while creating an obligation for future governments to sustain TAHE through continuing investment, and funding of the state owned rail operators. The ineffective process to design TAHE delivered a model that entails significant uncertainty as to whether the anticipated longer-term financial improvements to the Budget position can be achieved or sustained.

NSW Treasury and TfNSW had different objectives for TAHE

Up to June 2013, RailCorp had been the owner and operator of rail services and maintainer of the metropolitan rail network for almost a decade. It had been operating as a not-for-profit Public Non-Financial Corporation (PNFC).

In 2012, NSW Treasury (hereafter Treasury) decided there was a risk that the Australian Bureau of Statistics (ABS) would reclassify RailCorp to the General Government Sector (GGS), meaning depreciation expenses of approximately $870 million would be reflected in the GGS Budget. Treasury wanted to avoid this impact on the GGS Budget, and considered the establishment of a transport asset holding entity as a means to do so. Capital grants to RailCorp were being treated as an expense to the GGS Budget.

TfNSW also wanted an asset holding entity – but one that would be a non-trading ‘shell’ company with no staff that would hold and manage all public transport assets. TfNSW's concept envisaged the entity would have a structure that would enable future public transport reforms and strategic directions while ensuring vertical integration of operations between asset owners and the rail operators to maintain rail safety.

However, Treasury pursued its objective to improve the GGS Budget result, and sought to expand on TfNSW's 'shell' asset holding entity concept. Treasury wanted an entity that could generate a return on investment, as this meant that government investment in transport assets could be treated as equity investments, rather than a Budget expense, and in turn improve the GGS Budget position. As an example of the potential impact of creating this new entity, capital grants of $2.3 billion were paid to RailCorp in 2013–14. If Treasury's objective was met, grants of this significance would then be treated as an equity investment, rather than an expense in the GGS Budget.

In 2017, Treasury's preferred option was progressed through legislation, but both agencies' central objectives for the proposed asset holding entity would continue to prove difficult to reconcile. To achieve Treasury's objective to improve the Budget result, the entity would need to generate a return on investment (this is further discussed below). However, TfNSW expressed concerns that the prioritisation of rail safety, and the effective management of governance, regulation and operations would be more complex in an entity with commercial imperatives.

Asset holding entities are a common approach to the management of transport assets in Australia and internationally, and there are a range of approaches to how they are structured and used. Such structures should be driven by the goal of improved asset management. Ultimately, TfNSW's objectives could have been delivered through a simpler entity structure. However, reconciling TfNSW's objectives with Treasury's imperative to deliver and justify a Budget improvement in the short-term resulted in an overly lengthy process and an unnecessarily complex outcome that places an obligation on future governments to sustain. There is still significant uncertainty as to whether the short-term improvements to the Budget can continue to be realised in the longer-term.

The Budget benefits of TAHE were claimed before the entity was legislated, committing the agencies to deliver, regardless of the complexities that subsequently arose

The 2015–16 GGS Budget treated the government's investment in TAHE (still known at this time as RailCorp) as an equity contribution. This had the immediate impact of improving the Budget result by $1.8 billion per annum. However, the legislation to enable the establishment of TAHE had not yet been passed by Parliament, key elements of the operating model were still under development, and imminent changes in accounting standards had the potential to impact TAHE's financial model. The decision to book the benefits in the Budget early committed the involved agencies to implement a solution that justified the 2015–16 Budget impacts, irrespective of the challenges that arose. 

TAHE's financial structure requires circular government investment to work

For the NSW Government to continue to treat its investment in TAHE as an equity contribution, rather than an expense to the Budget, there must be a reasonable expectation that TAHE will generate a sufficient rate of return as required by the Government Finance Statistics (GFS) framework. In doing so, it needs to recover a revaluation loss created by a $20.3 billion reduction in the value of its assets which was incurred in its first full year of operation. This loss occurred as a result of a revaluation of TAHE's assets when RailCorp (a not-for profit entity) became TAHE (a for-profit commercial entity) – and is discussed further in the 'Key findings' below.

TAHE generates a small portion of its income from transactions with the private sector but, as noted in our report 'State Finances 2021', TAHE receives the majority of its revenue (more than 80%) from access and licence fee agreements with Sydney Trains and NSW Trains. Both of these entities are funded by grants (a Budget expense) to TfNSW from the GGS Budget.

Based on Treasury’s correspondence with the ABS in 2015, TAHE was initially expected to pay a return on equity of 7% in 2016–17. The assumption of a 7% return persisted through to 2018, after the legislation enabling the establishment of TAHE was passed by Parliament. However, when the initial access and licence fees were agreed on 1 July 2020, this figure had been revised to an expected rate of return of 1.5% excluding the revaluation loss. This was below the long-term inflation target and did not include the recovery of the revaluation loss – risking the government's ability to treat its investment in TAHE as an equity contribution. Importantly, as TAHE is primarily reliant on fees paid by the state owned rail operators that, in turn, are funded by the GGS Budget (as an expense), the decision to change the returns model from 7% to 1.5% would in its own right have had a positive impact on the GGS Budget. However, the decision to use a 1.5% return would ultimately be problematic as it made it difficult to treat the government's contributions to TAHE as an equity investment, as discussed below.

On 14 December 2021, to avoid a qualified audit opinion, the NSW Government made the decision to increase TAHE's expected rate of return to 2.5%, equal to the Reserve Bank’s long-term inflation target.

In 2021-22, TAHE needed to start charging rail operators higher access and licence fees in order to generate a return of 2.5%, so as to support the government's treatment of its investment in TAHE as an equity contribution in the GGS Budget. This meant the government needed to provide additional grant (expense) funding to the state owned rail operators so they could pay the increased access and licence fees to TAHE. Based on current projections, TAHE is not expected to recover the revaluation loss until 2046.

There remains a risk that TAHE will not be able to generate a sufficient return on the NSW Government's investment without relying on increased funding to state owned rail operators so that they can in turn pay the higher access and licence fees. TAHE's ability to generate returns on government investment from other sources are uncertain and may not be achievable or sustainable. Current modelling highlights that TAHE remains largely reliant, through to 2046, on increasing fees (which are assumed to increase at 2.5% per annum from 2031 onwards when the current 10 year contracts with rail operators expire) paid by the state owned rail operators that remain principally reliant on GGS Budget grants.

The process of designing and implementing TAHE was not transparent to independent scrutiny

Our report 'State Finances 2021' commented that Treasury did not always provide this Office with information relating to TAHE on a timely basis. Similarly, during this performance audit, there were also multiple instances where auditees were unable to provide documentation regarding key activities in the process to deliver TAHE. Agencies also applied higher sensitivity classifications to large tranches of documents than was justified or required by policy. Of particular concern is the incorrect classification of documents as Cabinet sensitive information. The incorrect or over-classification of documentation as Cabinet sensitive delayed this Office's ability to provide scrutiny or independent assurance.

There was a lack of clarity around the roles and responsibilities of governance structures set up to oversee the design and implementation of TAHE

From 2014, multiple workstreams and advisory committees were established to progress the design and implementation of TAHE. For some of these committees and workstreams, there is limited information on what they were tasked to do and what they achieved. Most had ceased meeting by 2018, before significant work needed to deliver TAHE was completed.

The lack of clarity around the roles and responsibilities of these governance structures reduced opportunities for TfNSW and Treasury to reconcile their differing objectives for TAHE, and resolve key questions earlier in the process.

There was a heavy reliance on consulting firms throughout the process to establish TAHE, and the management of consultant engagements failed to ensure that agencies received independent advice to support objective decision-making

In 2020, Treasury and TfNSW failed to prevent, identify, or adequately manage a conflict of interest when they engaged the same 'Big 4' consulting firm to work on separate TAHE-related projects. Both agencies used the firm's work to further their respective views with regard to the financial implications of TAHE's operating model. At this time those views were still unreconciled.

Treasury engaged the firm to provide a fiscal risk management strategy and advice on the impact of changes to accounting standards. TfNSW engaged the same firm to develop operating and financial models for TAHE, which raised concerns regarding the viability of TAHE. Disputes arose around the findings of these reports. Treasury disagreed with some of the outcomes of the work commissioned by TfNSW, relating to accounting treatment and fiscal advice.

The management of this conflict (real or perceived) was left to the 'Big 4' consulting firm when it was more appropriate for it to be managed by Treasury and TfNSW. If these agencies had communicated more effectively, used available governance structures consistently, and shared information openly about their use of the firm and the nature of their respective engagements, these disputes might have been avoided. This issue, coupled with deficiencies in procurement by both agencies, reflected and further perpetuated the lack of cohesion in the design and implementation of TAHE.

More broadly, over the period 2014 – 2021, 16 separate consulting firms were employed to work on 36 contracts, valued at over $22.56 million, relating to TAHE ranging from accounting and legal advice, project management, and the provision of administrative support and secretariat services.

Consultants are legitimately used by agencies to provide advice on how to achieve the outcomes determined by government, including advising agencies on the risks and challenges in achieving those outcomes. Similarly, consultants can provide expert knowledge in the service of achieving those outcomes and managing the risks. However, the heavy reliance on consulting firms during the design and implementation of TAHE heightened the risk that agencies were not receiving value for money, were outsourcing tasks that should be performed by the public service, and did not mitigate the risk that the advice received was not objective and impartial. The risk that the role of consultants could have been blurred between providing independent advice to government on options and facilitating a pre-determined outcome was not effectively treated or mitigated. This risk was amplified because a small number of firms were used repeatedly to provide advice on one topic. The effective procurement and management of consultants is an obligation of government agencies.

Appendix one – Responses from audited agencies, and Audit Office clarification of matters raised in the TAHE formal response 

Appendix two – Classification of government entities 

Appendix three – About the audit 

Appendix four – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #372 - released 24 January 2023

 

Published

Actions for Acquisition of 4–6 Grand Avenue, Camellia

Acquisition of 4–6 Grand Avenue, Camellia

Transport
Asset valuation
Compliance
Fraud
Infrastructure
Internal controls and governance
Management and administration
Procurement
Risk

The Auditor-General for New South Wales, Margaret Crawford, has today released a report on Transport for NSW’s (TfNSW) acquisition of 4–6 Grand Avenue in Camellia.

This audit, which was requested on 17 November 2020 by the Hon. Andrew Constance MP, the Minister for Transport and Roads, examined:

  • whether TfNSW conducted an effective process to purchase 4–6 Grand Avenue, Camellia
  • whether TfNSW has effective processes and procedures to identify and acquire property required to deliver the NSW Government’s major infrastructure projects.

The audit found that TfNSW conducted an ineffective process when it purchased 4–6 Grand Avenue, Camellia. The audit also found that TfNSW’s internal policies and procedures to guide the transaction were, and continue to be, insufficient.

The Auditor-General has made seven recommendations to address the issues identified in the report.

On 17 November 2020, the Hon. Andrew Constance MP, the Minister for Transport and Roads, requested this audit under section 27B(3)(c) of the Public Finance and Audit Act 1983.

On 15 June 2016, Transport for New South Wales (TfNSW) acquired 6.3 hectares of land at 4–6 Grand Avenue, Camellia, by agreement from Grand 4 Investments Pty Ltd. Grand 4 Investments was a business entity established by the owners of Billbergia Pty Ltd, a property development and investment company.

TfNSW paid Grand 4 Investments $53.5 million and assumed liability for addressing environmental issues and contamination associated with the site. This took place seven months after the vendor acquired the land as part of a competitive Expression of Interest process, in which TfNSW also participated, for $38.15 million.

TfNSW is the NSW Government agency responsible for most major transport infrastructure projects in New South Wales. TfNSW acquired the Camellia site for use as a stabling and maintenance depot to support the Parramatta Light Rail (PLR) project.

Consistent with the minister’s request, this audit assessed:

  • whether TfNSW conducted an effective process to purchase 4–6 Grand Avenue, Camellia
  • whether TfNSW has effective processes and procedures to identify and acquire property required to deliver the NSW Government’s major infrastructure projects.

In considering the effectiveness of the processes for this purchase, the audit considered:

  • the requirements of the Land Acquisition (Just Terms Compensation) Act 1991 (the Act)
  • the application of sound processes to manage risk to the NSW Government and to achieve value for money
  • the application of disciplines associated with complex procurement, such as probity, in a NSW Government context.
The acquisition of the 4–6 Grand Avenue site in Camellia was consistent with a 2014 feasibility study for the PLR, but occurred before the completion of detailed project planning or an acquisition strategy.

TfNSW made two attempts to acquire the 4–6 Grand Avenue site in Camellia, and was successful on the second attempt. TfNSW recognised the risks associated with early acquisition and had high-level strategies in place should the site not be required.

The specific site had been identified in a feasibility study for the PLR commissioned by TfNSW in 2014 as one of several options in Camellia for a stabling and maintenance depot. However, TfNSW had not done any substantive analysis of the various options to identify a preferred location before the two opportunities to acquire 4–6 Grand Avenue were brought to TfNSW’s attention by the landowners (or their agents). On both occasions, TfNSW chose to actively pursue acquisition in advance of any such analysis.

The acquisition was also not informed by a Property Acquisition Strategy, which TfNSW policy recommends in order to guide the process and manage acquisition specific risks.

In 2015, TfNSW identified that it would require a stabling and maintenance depot in the Camellia area for the Parramatta Light Rail

In 2014, TfNSW commissioned an external engineering consultancy to undertake a feasibility design study for the Parramatta Light Rail - the Parramatta Transport Corridor Strategy Feasibility Design study (herein referred to as ‘the feasibility study’). In early 2015, TfNSW received the feasibility study, which was one of several key sources that informed the development of business cases for the PLR.

The feasibility study recommended that TfNSW should consolidate the maintenance and cleaning operations with overnight stabling facilities on one site. The study noted that the optimal location for any such site would be in close proximity to the proposed network, and noted that the site must have access to road connections to accommodate access for cars and trucks.

The study found that a centrally located stabling and maintenance facility would be required for all routes serving the Parramatta CBD, and that the Camellia industrial area was a preferred location for such a facility. The study noted that the Camellia area was contaminated.

The feasibility study notes that its conclusions were based on assumptions about the light rail system adopted and decisions made by the future operator of the system, who had not yet been selected or appointed.

TfNSW's decision to progress a potential acquisition in 2015 considered the risk that the site may not be required

TfNSW's FIC was responsible for making decisions on funding allocations at a whole of program level within TfNSW. FIC was also responsible for approving ‘high-risk/high-value’ variations to program budgets. Members of the FIC included:

  • Secretary of Transport for NSW
  • Deputy Secretary, Infrastructure and Services
  • Deputy Secretary, Freight, Strategy and Planning
  • Deputy Secretary, Customer Services
  • Deputy Secretary Finance and Investment
  • Deputy Secretary People and Corporate Services.

An April 2015 submission, from the then Deputy Director-General to the agency’s FIC, sought authorisation and funding approval to participate in an Expression of Interest sale process. It noted the risk that the project may not go ahead. The submission advised that:

By acquiring a strategic site now, it reduces the risk of having to pay an improved value or a value that may be subject to rapidly improving land values due to changes in land use and rezoning.

The property can be acquired for the project, held strategically and income generated by leasing the site as hardstand 1 space until the project requires the land for the Parramatta Light Rail project.

If the project does not proceed in the medium to longer term, the property can be sold at a premium to what has been paid today as property fundamentals improve.

This submission acknowledged the risks associated with environmental contamination and proposed that these risks would be managed by negotiating a contract where the remediation and associated expenses would be at the landowner’s cost. 

TfNSW assessed the 4–6 Grand Avenue site as one of several sites in Camellia that was a feasible location for a stabling and maintenance facility

The Departmental feasibility study assessed six potential sites for a stabling and maintenance facility, including 4–6 Grand Avenue, noting strengths and weaknesses of each site. A different site on Grand Avenue was assessed as the ‘base case’ option (1 Grand Avenue). The study’s comments on the 4–6 Grand Avenue site included the following:

With an area of approximately 63,000m2, this site has sufficient space for a depot with the required stabling yard and maintenance facilities. The location allows for good road access and LRT [light rail transit] access would be from Grand Avenue, which may require a road crossing or signalised intersection. The site has been used for general industrial uses; however the land has been cleared and is currently undergoing remediation 2. The site is not affected by flooding based on one in 100-year flood data.

In early 2015, once the opportunity to acquire 4–6 Grand Avenue emerged, TfNSW commissioned a specific feasibility study of the 4–6 Grand Avenue site. The feasibility studies clearly documented the existence of environmental contamination. In April 2015, the report concluded:

Given the limitations of this report and within the parameters that have been set it is concluded that from a spatial and geographic perspective the site at 6 Grand Avenue would be suitable as a stabling and maintenance depot for the Parramatta light rail project. There are few engineering and environmental constraints that would affect the feasibility level analysis of this site and all issues identified, within this desk study, are considered to be resolvable. However this being said there is a significant amount of work necessary to reach the final layout and definition of the stabling and maintenance depot. There are numerous items which require further consideration and conformation; planning approvals could impose restrictions on building heights, noise mitigation measures, light and visual impact requirements all of which can have significant impacts on the spatial requirements of any stabling and maintenance depot. 

The acquisition of 4–6 Grand Avenue was not informed by a Property Acquisition Strategy

For major projects, TfNSW typically requires the project team to complete a Property Acquisition Strategy, which is intended to guide both process as well as specific acquisition issues expected to be faced during the project. The Property Acquisition Strategy is not a mandated document but is a recommended tool to support property acquisition as part of major projects.

TfNSW did not have a Property Acquisition Strategy in place to guide the 2015 Expression of Interest process. On 6 November 2015, the then Project Director for the PLR project emailed the property team, noting a need to develop a Property Acquisition Strategy to close off the scoping design and preliminary business case.

In January 2016, TfNSW developed a draft Property Acquisition Strategy for the Parramatta Light Rail Project, although it was silent on the potential sites for the stabling and maintenance facility.

TfNSW focussed on 4–6 Grand Avenue because it was available and aligned to TfNSW's strategic interests

In early 2015, officials commenced monitoring the market for industrial real estate in the Camellia area and surrounds for possible sites for a stabling and maintenance facility.

In March 2015, then owner of the site, Akzo Nobel Pty Limited released the 4–6 Grand Avenue site through an Expression of Interest process managed by CBRE.

TfNSW’s then Deputy Director-General, Planning, sought approval from FIC to lodge an Expression of Interest up to $30.0 million. Approval was sought on the basis that it would ‘provide certainty for the Parramatta Light Rail project by allowing for a depot site in a suitable location and potentially avoid higher costs or longer timeframes associated with compulsory acquisition following completion of the project’s business case’. FIC approved the request at its meeting on 9 April 2015.

At this time, TfNSW had not conducted any analysis of financial or operational benefits and costs of the potential sites identified in earlier feasibility studies. TfNSW staff advised us that the decision to participate in the Expression of Interest process for 4–6 Grand Avenue was because it was available. There is no documentation substantiating this statement, which TfNSW staff provided verbally as part of this audit.

In November 2015, TfNSW was advised that it was unsuccessful in the Expression of Interest process and that Grand 4 Investments (a related entity of Billbergia) had purchased 4–6 Grand Avenue. TfNSW did not conduct any further analysis of alternative potential sites in Camellia between this date and commencing discussions with Grand 4 Investments in April 2016. In that time there had been some movement on other properties that were included in the feasibility study, including 37–39a Grand Avenue being under offer in September 2015.

In March 2016, TfNSW approached CBRE to organise a meeting with Grand 4 Investments. On 1 April 2016, TfNSW met with Grand 4 Investments.

TfNSW advises that a perceived benefit of the 4–6 Grand Avenue site was that it was not subject to other uses or leaseholds that would increase the cost of compulsory acquisition. Officers involved in the acquisition advised that other nominated sites in the feasibility study were subject to other uses or leaseholds. 


1  A hardstand space is a large, paved area to store cars, heavy vehicles and machinery.
2  Officers familiar with the acquisition could not confirm the nature of remediation being undertaken, but noted that the previous landowner had cleared buildings from the site, which may have been considered part of remediation.
TfNSW's independent valuation, which it commissioned and received after the acquisition, specifically excluded consideration of environmental contamination risk. As a result, TfNSW is exposed to the risk that the acquisition was not fully compliant with the Land Acquisition (Just Terms Compensation) Act 1991 (the Act) because it did not use an accurate estimate of market value during negotiations. That said, the acquisition of 4–6 Grand Avenue by agreement was consistent with preferred processes described in the Act.

TfNSW acquired the site from the landowner by agreement, and this is consistent with provisions in the Act. Obtaining approval for compulsory acquisition should negotiations for agreement break down is also consistent with the Act. That said, TfNSW did not at any time assess whether a compulsory acquisition could have resulted in acquisition at a lower cost than what was negotiated by agreement.

Despite the high risks associated with the acquisition, TfNSW did not commission a formal valuation in time to inform the negotiation and purchase. Instead, TfNSW relied on internal advice to estimate market value, but did not obtain a formal valuation from those advisors. For high-risk transactions, the greater expertise and arm's-length independence of an external specialist valuer should be preferred over an agency's own staff.

On 15 June 2016, the settlement date for the acquisition, TfNSW commissioned a formal independent valuation of the site. On 23 November 2016, TfNSW received the final formal valuation report. By not obtaining a formal independent valuation of the property in advance of acquisition to inform the acquisition value, TfNSW exposed itself to non-compliance with the Act by not establishing the market value as the basis for the acquisition price. TfNSW also breached its own internal policies.

TfNSW instructed the valuer to conduct its valuation within the following parameters:

  • Market valuation on an ‘as is’ basis – market value based on the methodology described in the Act. This approach valued the site at $25.0 million.
  • Market valuation on a speculative development basis – market value based on the financial value of the vendor's intended use of the site which, in this case, involved leasing the site for industrial use. This approach valued the site at $52.0 million, and TfNSW advised us this valuation supported the purchase price.
  • Disregard the impact of environmental contamination – TfNSW specifically instructed the independent valuer to disregard any known (or unknown) site contamination. As TfNSW knew of the significant environmental contamination affecting the site, this parameter resulted in a valuation that overstated the value of the site as it did not consider the cost of environmental remediation. The valuer applied this assumption for both market valuation approaches.

Additionally, as the independent valuer completed the valuation after the purchase was finalised, there is a risk that the valuation may have been influenced by the known purchase price.

TfNSW's failure to acquire a formal valuation and an assessment of the financial impact of environmental remediation before it purchased 4–6 Grand Avenue represents ineffective administration and governance.
TfNSW acquired the site at a time when there was demand and increasing prices for industrial property in the area. However, TfNSW did not effectively assess and manage the risks associated with the acquisition, and gaps in process led to increased risk. Briefings to decision-makers did not contain important information, and we found no evidence that gaps in advice were queried or explored by decision-makers.

TfNSW did not have plans or advice in place to assist in managing risk, such as:

  • a property acquisition plan
  • a comprehensive and up-to-date risk management plan
  • a negotiation strategy, or any authorisation limit or minimal acceptable position
  • an independent professional evaluation
  • external expert advice (with the exception of legal advice relating to the contract of sale).

TfNSW was aware of contamination issues affecting the land and had access to considerable information about the environmental conditions, such as site environmental audit reports and information on the NSW Environment Protection Authority's contaminated land register. However, TfNSW had not analysed specific technical information about the contamination and therefore was not aware of the risk implications and cost for remediation. Despite this, TfNSW changed its position from not accepting the risks and costs of contamination, to acquiring the site unconditionally. The basis for this decision is unclear and undocumented.

Briefing to senior leaders on the acquisition was silent on a number of important matters that would have been important for approvers to consider, including:

  • an explanation of the 40 per cent increase in purchase price between November 2015 and May 2016, and a 165 per cent increase from TfNSW’s offer in April 2015
  • the contamination risks associated with the site and an evidence-based estimate of potential costs to remediate the site
  • advice that an independent valuation had not been obtained, inconsistent with TfNSW policy.

Consideration of the acquisition by FIC was based on a summary business paper and was managed out-of-session, thereby removing the ability for comprehensive consideration of the acquisition proposal and its risks.

The probity management controls and assurances in place for the acquisition of the 4–6 Grand Avenue site were insufficient. These insufficiencies were exacerbated by the probity risk profile of the transaction.

The 4–6 Grand Avenue acquisition was a high-risk/high-value transaction, undertaken in a volatile property market in a short timeframe under pressure from Grand 4 Investments. TfNSW was engaging in a direct negotiation in advance of detailed planning for the acquisition, or the PLR as a whole. These circumstances contribute to heightened probity risk.

TfNSW did not establish a probity plan and sought no probity support throughout the acquisition. Also, with one exception, the staff involved in the acquisition did not complete conflict of interest declarations.

TfNSW was aware of the potential for probity or integrity issues with the transaction when it commissioned an internal audit in connection with the transaction in 2019. Internal discussions considered whether a misconduct investigation may be more appropriate, however no such investigation was undertaken.

TfNSW's insufficient probity practices, in addition to its failure to keep complete or comprehensive records of negotiations or decisions, reduce transparency of the process and its outcome and expose TfNSW to a greater risk of misconduct, corruption and maladministration.

At the time of the transaction, the TfNSW policy framework was not sufficiently risk-focussed and did not provide clarity on when officers ought to apply specific guidance or procedures. TfNSW's policies and procedures are more focussed on acquiring land to meet project needs and timeframes, and less on assuring value for money and managing risks.

At the time of its acquisition of 4–6 Grand Avenue, TfNSW had property acquisitions policies and procedures in place. Each of these were broadly sound in their content and intent. However, they lacked specificity on how or when to apply guidance, and when risk levels should elevate the importance of recommended guidance.

TfNSW's key guidance was principles based and relied on agency staff using their experience and expertise to apply guidance according to the circumstances of an individual transaction. This guidance was not duly applied in the acquisition of 4–6 Grand Avenue, Camellia. In addition, TfNSW does not have quality or control assurance to identify when TfNSW officers did not apply important policies or processes.

The primary focus of the TfNSW’s property acquisition guidance is to achieve vacant possession of land in a timeframe that meets the need of the relevant transport project. There is less specific focus on the need to meet the requirements of the NSW Government financial management framework.

Appendix one – Response from agency 

Appendix two – About the audit 

Appendix three – Performance auditing

 

Copyright Notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #349 - released (18 May 2021).

Published

Actions for Train station crowding

Train station crowding

Transport
Management and administration
Risk
Service delivery
Workforce and capability

This report focuses on how Transport for NSW and Sydney Trains manage crowding at selected metropolitan train stations.

The audit found that while Sydney Trains has identified platform crowding as a key strategic risk, it does not have an overarching strategy to manage crowding in the short to medium term. Sydney Trains 'do not have sufficient oversight to know if crowding is being effectively managed’, the Auditor-General said.

Sydney Trains' operational response to crowding involves restricting customer access to platforms or station entries before crowding reaches unsafe levels or when it impacts on-time running. Assuming rail patronage increases, it is likely that Sydney Trains will restrict more customers from accessing platforms or station entries, causing customer delay. ‘Restricting customer access to platforms or station entries is not a sustainable approach to manage station crowding’, said the Auditor-General.

The Auditor-General made seven recommendations to improve Transport for NSW and Sydney Trains' management of station crowding. Transport for NSW have accepted these recommendations on behalf of the Transport cluster.

Public transport patronage has been impacted by COVID-19. This audit was conducted before these impacts occurred.

Read full report (PDF)

Sydney Trains patronage has increased by close to 34 per cent over the last five years, and Transport for NSW (TfNSW) expects the growth in patronage to continue over the next 30 years. As patronage increases there are more passengers entering and exiting stations, moving within stations to change services, and waiting on platforms. As a result, some Sydney metropolitan train stations are becoming increasingly crowded.

There are three main causes of station crowding:

  • patronage growth exceeding the current capacity limits of the rail network
  • service disruptions
  • special events.

Crowds can inhibit movement, cause discomfort and can lead to increased health and safety risks to customers. In the context of a train service, unmanaged crowds can affect service operation as trains spend longer at platforms waiting for customers to alight and board services which can cause service delays. Crowding can also prevent customers from accessing services.

Our 2017 performance audit, ‘Passenger Rail Punctuality’, found that rail agencies would find it hard to maintain train punctuality after 2019 unless they significantly increased the capacity of the network to carry trains and people. TfNSW and Sydney Trains have plans to improve the network to move more passengers. These plans are set out in strategies such as More Trains, More Services and in the continued implementation of new infrastructure such as the Sydney Metro. Since 2017, TfNSW and Sydney Trains have introduced 1,500 more weekly services to increase capacity. Additional network capacity improvements are in progress for delivery from 2022 onwards.

In the meantime, TfNSW and Sydney Trains need to use other ways of managing crowding at train stations until increased capacity comes on line.

This audit examined how effectively TfNSW and Sydney Trains are managing crowding at selected metropolitan train stations in the short and medium term. In doing so, the audit examined how TfNSW and Sydney Trains know whether there is a crowding problem at stations and how they manage that crowding.

TfNSW is the lead agency for transport in NSW. TfNSW is responsible for setting the standard working timetable that Sydney Trains must implement. Sydney Trains is responsible for operating and maintaining the Sydney metropolitan heavy rail passenger service. This includes operating, staffing and maintaining most metropolitan stations. Sydney Trains’ overall responsibility is to run a safe rail network to timetable.

Conclusion

Sydney Trains has identified platform crowding as a key strategic risk, but does not have an overarching strategy to manage crowding in the short to medium term. TfNSW and Sydney Trains devolve responsibility for managing crowding at stations to Customer Area Managers, but do not have sufficient oversight to know if crowding is being effectively managed. TfNSW is delivering a program to influence demand for transport in key precincts but the effectiveness of this program and its impact on station crowding is unclear as Transport for NSW has not evaluated the outcomes of the program.

TfNSW and Sydney Trains do not directly measure or collect data on station crowding. Data and observation on dwell time, which is the time a train waits at a platform for customers to get on and off trains, inform the development of operational approaches to manage crowding at stations. Sydney Trains has KPIs on reliability, punctuality and customer experience and use these to indirectly assess the impact of station crowding. TfNSW and Sydney Trains only formally assess station crowding as part of planning for major projects, developments or events.

Sydney Trains devolve responsibility for crowd management to Customer Area Managers, who rely on frontline Sydney Trains staff to understand how crowding affects individual stations. Station staff at identified key metropolitan train stations have developed customer management plans (also known as crowd management plans). However, Sydney Trains does not have policies to support the creation, monitoring and evaluation of these plans and does not systematically collect data on when station staff activate crowding interventions under these plans.

Sydney Trains stated focus is on providing a safe and reliable rail service. As such, management of station crowding is a by-product of its strategies to manage customer safety and ensure on-time running of services. Sydney Trains' operational response to crowding involves restricting customer access to platforms or stations before crowding reaches unsafe levels, or when it impacts on-time running. As rail patronage increases, it is likely that Sydney Trains will need to increase its use of interventions to manage crowding. As Sydney Trains restrict more customers from accessing platforms or station entries, it is likely these customers will experience delays caused by these interventions.

Since 2015, TfNSW has been delivering the 'Travel Choices' program which aims to influence customer behaviour and to manage the demand for public transport services in key precincts. TfNSW is unable to provide data demonstrating the overall effectiveness of this program and the impact the program has on distributing public transport usage out of peak AM and PM times. TfNSW and Sydney Trains continue to explore initiatives to specifically address crowd management.

Conclusion

TfNSW and Sydney Trains do not directly measure or collect data on station crowding. There are no key performance indicators directly related to station crowding. Sydney Trains uses performance indicators on reliability, punctuality and customer experience to indirectly assess the impact of station crowding. Sydney Trains does not have a routine process for identifying whether crowding contributed to minor safety incidents. TfNSW and Sydney Trains formally assess station crowding as part of planning for major projects, developments or events.

 

Conclusion

Sydney Trains has identified platform crowding as a strategic risk but does not have an overarching strategy to manage station crowding. Sydney Trains' stated focus is on providing a safe and reliable rail service. As such, management of station crowding is a by-product of its strategies to manage customer safety and ensure on-time running of services.

Sydney Trains devolve responsibility for managing crowding at stations to Customer Area Managers but does not have sufficient oversight to know that station crowding is effectively managed. Sydney Trains does not have policies to support the creation, monitoring or evaluation of crowd management plans at key metropolitan train stations. The use of crowding interventions is likely to increase due to increasing patronage, causing more customers to experience delays directly caused by these activities.

TfNSW and Sydney Trains have developed interventions to influence customer behaviour and to manage the demand for public transport services but are yet to evaluate these interventions. As such, their impact on managing station crowding is unclear.

Appendix one – Response from agency

Appendix two – Sydney rail network

Appendix three – Rail services contract

Appendix four – Crowding pedestrian modelling

Appendix five – Airport Link stations case study

Appendix six – About the audit

Appendix seven – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #333 - released 30 April 2020

 

Published

Actions for Property Asset Utilisation

Property Asset Utilisation

Finance
Asset valuation
Infrastructure
Management and administration
Project management

Property NSW’s effectiveness in managing NSW Government owned and leased commercial office property is limited in three areas according to a report released today by the Auditor-General for New South Wales, Margaret Crawford.

At 30 June 2018, the NSW Government owned $160 billion worth of land and buildings. The NSW Treasury predicts this figure will rise over the coming years. Property NSW manages more than 900 leased office properties across the state. Approximately 250 of these are owned by Property NSW. Other NSW Government agencies maintain ownership and control of properties considered essential for service provision, such as schools, prisons and hospitals. Between 2012–13 and 2017–18 sales of property assets across the whole of the NSW Government have raised $10 billion, of which Property NSW has sold property assets of approximately $2 billion.

In September 2012, the Property Asset Utilisation Taskforce (the Taskforce) released its report on ‘real property asset management across government’ and concluded that the government has accumulated, over time, ‘a real property asset portfolio it cannot afford to maintain or protect’. The Taskforce noted that ‘a lack of centralised information seriously inhibits any whole-of-government strategic asset planning’ and that maintaining under-utilised or unnecessary properties diverted funds from areas where they might be better used. The Taskforce’s key findings included:

  • the NSW Government should own property only as a means to deliver or enhance services
  • many government properties were under-utilised, poorly maintained and inappropriate to support service delivery.

The Taskforce recommended the creation of Property NSW, as a replacement for the State Property Authority, to improve property asset utilisation and to drive efficiencies in the government’s owned and leased property portfolio. Property NSW was to achieve these goals by:

  • collating property information across the whole-of-government
  • working with agencies on longer-term strategic real property asset planning to:
    • provide services to agencies as customers
    • bring a whole-of-government perspective to real property asset planning.

In response to the Taskforce report, in December 2012, the Premier's Memorandum M2012-20 (the Memorandum) established Property NSW to improve the management of the NSW Government's owned and leased real property portfolio.

Under the Memorandum, Property NSW is responsible for:

  • management of all leased and owned commercial office accommodation
  • acting as the central acquisition and disposal agency 
  • providing advice to the government on property matters and developing property policy 
  • conducting regular and ongoing reviews of agencies portfolios, working with agencies to identify efficiencies to improve service delivery, in relation to the review of capital planning1
  • maintaining the register of all government owned property.

The Memorandum states that ownership of all commercial office property should be vested in Property NSW. 

This audit assessed whether Property NSW is effective in the management of NSW Government owned and leased commercial office property. To do this we assessed whether NSW Government leased commercial office space is being effectively utilised and whether the Government Property Register, a register of all government owned property, is accurate and up-to-date.

Conclusion
Property NSW’s effectiveness in managing NSW Government owned and leased commercial office property is limited in three areas.
First, Property NSW has not comprehensively reviewed many agency property portfolios to help agencies identify assets, including commercial office properties, that could be better utilised or recycled. Second, the Government Property Register is not being actively maintained and contains incomplete and inaccurate information, limiting Property NSW’s ability to use it to support strategic decisions about the use of government property assets. Third, Property NSW's decisions are not well documented and its processes to reach decisions are not transparent to stakeholders. That said, property utilisation has improved by about 14 per cent since 2012, and Property NSW is actively moving properties out of the Sydney CBD in line with the ‘Decade of Decentralisation’ policy.
Property NSW’s role is to provide a strategic approach to property asset management. Under the 2012 Premier’s Memorandum, this includes a requirement that Property NSW undertake regular reviews of agency property portfolios to identify efficiencies to improve service delivery. Property NSW completed one comprehensive review of an agency, limited reviews of four other agencies, and some reviews of government property in regional towns, prior to 2017.

In December 2017, Property NSW started working across the NSW Government to help agencies identify real property assets, including commercial office properties, that are under-utilised or surplus and that could be recycled, repurposed, or vested to Property NSW.
Following the Memorandum, agencies were directed to vest their commercial office properties to Property NSW. However, without more comprehensive reviews, Property NSW does not know how many commercial properties are yet to be vested. Agencies can approach Property NSW for assistance in managing their property portfolios, and Property NSW arranges the recycling of under utilised and surplus properties that are brought to its attention. Property NSW is improving utilisation of government office space, according to agency self-reported information which Property NSW uses to calculate utilisation rates. 
The Property Asset Utilisation Taskforce report (2012) recommended that the NSW Government needed a ‘single source of truth’ to inform asset retention and disposal decisions, leasing decisions and ongoing strategic property decisions. It concluded that the Government Property Register (GPR) could perform this function ‘if populated appropriately’. However, the GPR is not comprehensively performing this function because it is still incomplete and out of date. Property NSW manages the GPR and NSW Government agencies are required to supply ‘accurate, relevant and useful information’ to populate it. Agencies are not always doing so in a timely manner, limiting its usefulness to support strategic decision making. Property NSW supplements the GPR with information from multiple other sources to assist its decisions, however, there is still no single, complete and accurate picture of the NSW Government property portfolio. 
The work Property NSW does to identify, shortlist and propose new lease and agency relocation options is not well documented. Property NSW records the outcome of the process without detailing how and why decisions were made. There is limited transparency in this process for stakeholders. Record keeping is also inconsistent and many of Property NSW’s divisions do not have procedures or guidelines.

1 Capital Planning was previously referred to as Total Asset Management (TAM).

In December 2017, the NSW Government announced the Property Infrastructure Policy to create a more collaborative approach between Property NSW and NSW Government agencies to review and identify efficiencies in their property portfolios. Before this, Property NSW did not have a plan to assist agencies to identify under-utilised properties for recycling or repurposing. It still does not know how many under-utilised properties exist and will not know until it has completed all of the portfolio reviews it is currently carrying out under the Property Infrastructure Policy.
Between 2013 and 2017, Property NSW had only completed one comprehensive review of an agency, limited reviews of four other agencies, and some regional towns. Outside this process Property NSW chose to rely on other agencies to identify surplus property for recycling, repurposing or vesting ownership to Property NSW.
Property NSW has a role to provide a strategic approach to property asset management and is required to undertake regular reviews of agency property portfolios under the Premier's Memorandum. Property NSW only recently started working to assist agencies to identify under-utilised and surplus properties, or properties to be vested. These reviews should improve the identification of surplus and under-utilised real property assets and assist whole-of-government decisions on the recycling, repurposing of under-utilised assets and vesting of owned office accommodation to Property NSW.
Recommendations
By December 2019, Property NSW should:
  1. combine the results of property portfolio reviews to produce a whole-of-government picture of the NSW Government property portfolio 
  2. devise a strategy and plan to recycle or repurpose under-utilised properties using a whole-of-government picture of the NSW Government property portfolio
  3. develop and report on indicators for progress in reducing the number and value of under-utilised properties at the whole-of-government level, referencing progress against an accurate baseline stocktake.
Property NSW needs to be more proactive in its management of the GPR and in encouraging agencies to provide the information needed to improve this register. In 2012, the Property Asset Utilisation Taskforce report recommended there be a single source of truth on property assets owned by the NSW Government. The GPR is intended to fulfil this role but it is out of date and incomplete.
Without a complete and accurate central register of property, Property NSW cannot provide the NSW Government with a comprehensive picture of its property portfolio, or make whole-of-government decisions about the property portfolio. Property NSW currently supplements the GPR with information from other systems in order to make decisions about leasing, relocations, and property recycling and repurposing. Agencies are required to provide ‘accurate, relevant and useful information’ but are not consistently doing so.
Recommendations
By December 2019, Property NSW should:

4. improve the data held on government owned and leased properties by combining and automating data feeds to construct a single, consolidated and accurate whole-of-government property data set.
Property NSW documents the outcome of decisions about relocations, lease renewals, and utilisation but is unable to provide evidence of how these decisions are reached. Property NSW is also unable to provide evidence of documented guidance for its staff on how decisions should be made. Whilst some level of subjectivity will play a part in such decisions, the lack of documentation and guidance raises issues of consistency, accountability and transparency in decision-making. Property NSW states that it makes decisions based on whole-of-government outcomes rather than equitable and consistent outcomes for client agencies, which is inconsistent with the criteria it reports that it uses when making decisions about leases and relocations.
Recommendations
By December 2019, Property NSW should:

5. document and communicate to stakeholders how its assessment criteria inform key decisions including agency relocations, lease renewals and rectifying under-utilisation
6. include customer satisfaction measures in its annual reports and reviews, in accordance with the requirements set out in the Premier's Memorandum M2012-20
7. improve record-keeping and compliance with the State Records Act 1998 and the Department of Finance, Services and Innovation Records Management Policy.

Published

Actions for Managing risks in the NSW public sector: risk culture and capability

Managing risks in the NSW public sector: risk culture and capability

Finance
Health
Justice
Treasury
Internal controls and governance
Management and administration
Risk
Workforce and capability

The Ministry of Health, NSW Fair Trading, NSW Police Force, and NSW Treasury Corporation are taking steps to strengthen their risk culture, according to a report released today by the Auditor-General, Margaret Crawford. 'Senior management communicates the importance of managing risk to their staff, and there are many examples of risk management being integrated into daily activities', the Auditor-General said.

We did find that three of the agencies we examined could strengthen their culture so that all employees feel comfortable speaking openly about risks. To support innovation, senior management could also do better at communicating to their staff the levels of risk they are willing to accept.

Effective risk management is essential to good governance, and supports staff at all levels to make informed judgements and decisions. At a time when government is encouraging innovation and exploring new service delivery models, effective risk management is about seizing opportunities as well as managing threats.

Over the past decade, governments and regulators around the world have increasingly turned their attention to risk culture. It is now widely accepted that organisational culture is a key element of risk management because it influences how people recognise and engage with risk. Neglecting this ‘soft’ side of risk management can prevent institutions from managing risks that threaten their success and lead to missed opportunities for change, improvement or innovation.

This audit assessed how effectively NSW Government agencies are building risk management capabilities and embedding a sound risk culture throughout their organisations. To do this we examined whether:

  • agencies can demonstrate that senior management is committed to risk management
  • information about risk is communicated effectively throughout agencies
  • agencies are building risk management capabilities.

The audit examined four agencies: the Ministry of Health, the NSW Fair Trading function within the Department of Finance, Services and Innovation, NSW Police Force and NSW Treasury Corporation (TCorp). NSW Treasury was also included as the agency responsible for the NSW Government's risk management framework.

Conclusion
All four agencies examined in the audit are taking steps to strengthen their risk culture. In these agencies, senior management communicates the importance of managing risk to their staff. They have risk management policies and funded central functions to oversee risk management. We also found many examples of risk management being integrated into daily activities.
That said, three of the four case study agencies could do more to understand their existing risk culture. As good practice, agencies should monitor their employees’ attitude to risk. Without a clear understanding of how employees identify and engage with risk, it is difficult to tell whether the 'tone' set by the executive and management is aligned with employee behaviours.
Our survey of risk culture found that three agencies could strengthen a culture of open communication, so that all employees feel comfortable speaking openly about risks. To support innovation, senior management could also do better at communicating to their staff the levels of risk they are willing to accept.
Some agencies are performing better than others in building their risk capabilities. Three case study agencies have reviewed the risk-related skills and knowledge of their workforce, but only one agency has addressed the gaps the review identified. In three agencies, staff also need more practical guidance on how to manage risks that are relevant to their day-to-day responsibilities.
NSW Treasury provides agencies with direction and guidance on risk management through policy and guidelines. Its principles-based approach to risk management is consistent with better practice. Nevertheless, there is scope for NSW Treasury to develop additional practical guidance and tools to support a better risk culture in the NSW public sector. NSW Treasury should encourage agency heads to form a view on the current risk culture in their agencies, identify desirable changes to that risk culture, and take steps to address those changes. 

In assessing an agency’s risk culture, we focused on four key areas:

Executive sponsorship (tone at the top)

In the four agencies we reviewed, senior management is communicating the importance of managing risk. They have endorsed risk management frameworks and funded central functions tasked with overseeing risk management within their agencies.

That said, we found that three case study agencies do not measure their existing risk culture. Without clear measures of how employees identify and engage with risk, it is difficult for agencies to tell whether employee's behaviours are aligned with the 'tone' set by the executive and management.

For example, in some agencies we examined we found a disconnect between risk tolerances espoused by senior management and how these concepts were understood by staff.

Employee perceptions of risk management

Our survey of staff indicated that while senior leaders have communicated the importance of managing risk, more could be done to strengthen a culture of open communication so that all employees feel comfortable speaking openly about risks. We found that senior management could better communicate to their staff the levels of risk they should be willing to accept.

Integration of risk management into daily activities and links to decision-making

We found examples of risk management being integrated into daily activities. On the other hand, we also identified areas where risk management deviated from good practice. For example, we found that corporate risk registers are not consistently used as a tool to support decision-making.

Support and guidance to help staff manage risks

Most case study agencies are monitoring risk-related skills and knowledge of their workforce, but only one agency has addressed the gaps it identified. While agencies are providing risk management training, surveyed staff in three case study agencies reported that risk management training is not adequate.

NSW Treasury provides agencies with direction and guidance on risk management through policy and guidelines. In line with better practice, NSW Treasury's principles-based policy acknowledges that individual agencies are in a better position to understand their own risks and design risk management frameworks that address those risks. Nevertheless, there is scope for NSW Treasury to refine its guidance material to support a better risk culture in the NSW public sector.

Recommendation

By May 2019, NSW Treasury should:

  • Review the scope of its risk management guidance, and identify additional guidance, training or activities to improve risk culture across the NSW public sector. This should focus on encouraging agency heads to form a view on the current risk culture in their agencies, identify desirable changes to that risk culture, and take steps to address those changes.

Published

Actions for Detecting and responding to cyber security incidents

Detecting and responding to cyber security incidents

Finance
Cyber security
Information technology
Internal controls and governance
Management and administration
Workforce and capability

A report released today by the Auditor-General for New South Wales, Margaret Crawford, found there is no whole-of-government capability to detect and respond effectively to cyber security incidents. There is very limited sharing of information on incidents amongst agencies, and some agencies have poor detection and response practices and procedures.

The NSW Government relies on digital technology to deliver services, organise and store information, manage business processes, and control critical infrastructure. The increasing global interconnectivity between computer networks has dramatically increased the risk of cyber security incidents. Such incidents can harm government service delivery and may include the theft of information, denial of access to critical technology, or even the hijacking of systems for profit or malicious intent.

This audit examined cyber security incident detection and response in the NSW public sector. It focused on the role of the Department of Finance, Services and Innovation (DFSI), which oversees the Information Security Community of Practice, the Information Security Event Reporting Protocol, and the Digital Information Security Policy (the Policy).

The audit also examined ten case study agencies to develop a perspective on how they detect and respond to incidents. We chose agencies that are collectively responsible for personal data, critical infrastructure, financial information and intellectual property.

Conclusion
There is no whole‑of‑government capability to detect and respond effectively to cyber security incidents. There is limited sharing of information on incidents amongst agencies, and some of the agencies we reviewed have poor detection and response practices and procedures. There is a risk that incidents will go undetected longer than they should, and opportunities to contain and restrict the damage may be lost.
Given current weaknesses, the NSW public sector’s ability to detect and respond to incidents needs to improve significantly and quickly. DFSI has started to address this by appointing a Government Chief Information Security Officer (GCISO) to improve cyber security capability across the public sector. Her role includes coordinating efforts to increase the NSW Government’s ability to respond to and recover from whole‑of‑government threats and attacks.

Some of our case study agencies had strong processes for detection and response to cyber security incidents but others had a low capability to detect and respond in a timely way.

Most agencies have access to an automated tool for analysing logs generated by their IT systems. However, coverage of these tools varies. Some agencies do not have an automated tool and only review logs periodically or on an ad hoc basis, meaning they are less likely to detect incidents.

Few agencies have contractual arrangements in place for IT service providers to report incidents to them. If a service provider elects to not report an incident, it will delay the agency’s response and may result in increased damage.

Most case study agencies had procedures for responding to incidents, although some lack guidance on who to notify and when. Some agencies do not have response procedures, limiting their ability to minimise the business damage that may flow from a cyber security incident. Few agencies could demonstrate that they have trained their staff on either incident detection or response procedures and could provide little information on the role requirements and responsibilities of their staff in doing so.

Most agencies’ incident procedures contain limited information on how to report an incident, who to report it to, when this should occur and what information should be provided. None of our case study agencies’ procedures mentioned reporting to DFSI, highlighting that even though reporting is mandatory for most agencies their procedures do not require it.

Case study agencies provided little evidence to indicate they are learning from incidents, meaning that opportunities to better manage future incidents may be lost.

Recommendations

The Department of Finance, Services and Innovation should:

  • assist agencies by providing:
    • better practice guidelines for incident detection, response and reporting to help agencies develop their own practices and procedures
    • training and awareness programs, including tailored programs for a range of audiences such as cyber professionals, finance staff, and audit and risk committees
    • role requirements and responsibilities for cyber security across government, relevant to size and complexity of each agency
    • a support model for agencies that have limited detection and response capabilities
       
  • revise the Digital Information Security Policy and Information Security Event Reporting Protocol by
    • clarifying what security incidents must be reported to DFSI and when
    • extending mandatory reporting requirements to those NSW Government agencies not currently covered by the policy and protocol, including State owned corporations.

DFSI lacks a clear mandate or capability to provide effective detection and response support to agencies, and there is limited sharing of information on cyber security incidents.

DFSI does not currently have a clear mandate and the necessary resources and systems to detect, receive, share and respond to cyber security incidents across the NSW public sector. It does not have a clear mandate to assess whether agencies have an acceptable detection and response capability. It is aware of deficiencies in agencies and across whole‑of‑government, and has begun to conduct research into this capability.

Intelligence gathering across the public sector is also limited, meaning agencies may not respond to threats in a timely manner. DFSI has not allocated resources for gathering of threat intelligence and communicating it across government, although it has begun to build this capacity.

Incident reporting to DFSI is mandatory for most agencies, however, most of our case study agencies do not report incidents to DFSI, reducing the likelihood of containing an incident if it spreads to other agencies. When incidents have been reported, DFSI has not provided dedicated resources to assess them and coordinate the public sector’s response. There are currently no formal requirements for DFSI to respond to incidents and no guidance on what it is meant to do if an incident is reported. The lack of central coordination in incident response risks delays and increased damage to multiple agencies.

DFSI's reporting protocol is weak and does not clearly specify what agencies should report and when. This makes agencies less likely to report incidents. The lack of a standard format for incident reporting and a consistent method for assessing an incident, including the level of risk associated with it, also make it difficult for DFSI to determine an appropriate response.

There are limited avenues for sharing information amongst agencies after incidents have been resolved, meaning the public sector may be losing valuable opportunities to improve its protection and response.

Recommendations

The Department of Finance, Services and Innovation should:

  • develop whole‑of‑government procedure, protocol and supporting systems to effectively share reported threats and respond to cyber security incidents impacting multiple agencies, including follow-up and communicating lessons learnt
  • develop a means by which agencies can report incidents in a more effective manner, such as a secure online template, that allows for early warnings and standardised details of incidents and remedial advice
  • enhance NSW public sector threat intelligence gathering and sharing including formal links with Australian Government security agencies, other states and the private sector
  • direct agencies to include standard clauses in contracts requiring IT service providers report all cyber security incidents within a reasonable timeframe
  • provide assurance that agencies have appropriate reporting procedures and report to DFSI as required by the policy and protocol by:
    • extending the attestation requirement within the DISP to cover procedures and reporting
    • reviewing a sample of agencies' incident reporting procedures each year.

Published

Actions for Public sector management reforms

Public sector management reforms

Finance
Industry
Premier and Cabinet
Planning
Whole of Government
Environment
Management and administration
Workforce and capability

The Public Service Commission is making good progress with leading the implementation of public sector management reforms, according to a report released today by the Acting New South Wales Auditor-General, Tony Whitfield.

'The Commission developed a sound evidence base for the reforms and gained wide public sector support by engaging with agency heads and using public sector working groups to develop options', said the Acting Auditor-General. 'They developed good guidance for government agencies and have improved the senior executive structure in the NSW public sector', he added.

 

Parliamentary reference - Report number #264 - released 28 January 2016

Published

Actions for Managing Overtime: RailCorp and Roads and Maritime Services

Managing Overtime: RailCorp and Roads and Maritime Services

Transport
Management and administration
Workforce and capability

Overtime is a significant cost for RailCorp and Roads and Maritime Services, adding about ten per cent to the cost of regular salaries. RailCorp’s overtime cost was $133.7 million in 2010–11, and at Roads and Maritime Services it cost $49.3 million.

 

Parliamentary reference - Report number #223 - released 20 June 2012

Published

Actions for Prequalification Scheme: Performance and Management Services

Prequalification Scheme: Performance and Management Services

Premier and Cabinet
Finance
Compliance
Internal controls and governance
Management and administration
Regulation
Risk
Workforce and capability

There have been tangible improvements in the time it takes NSW Government agencies to engage consultants through the Government’s Prequalification Scheme. The Scheme was introduced in February 2008 to improve agencies’ procurement of consultants. More than 300 service providers have been prequalified and over $300 million worth of consultancy services have been provided. Ideally agencies should know what assignments each consultant has won, for what services, what their rates are and how well they have performed. Agencies should then be free to contact other agencies before engaging a consultant.

 

Parliamentary reference - Report number #216 - released 28 September 2011

Published

Actions for Injury Management in the NSW Public Sector

Injury Management in the NSW Public Sector

Premier and Cabinet
Treasury
Finance
Management and administration
Workforce and capability

We found that during Working Together, agencies reduced the impact of workplace injuries. Most of the results have been positive in both our sample agencies and the public sector, and savings have been achieved. Between 2005 and 2008, while the number of claims in the sample agencies remained at around 15,000, the average cost of claims reduced by around 22 per cent from $22,349 to $17,360. The incidence rate of claims for the sample agencies also decreased by nine per cent to 7.3 claims per 100 staff.

 

Parliamentary reference - Report number #199 - released 31 March 2010