Actions for Transport 2023

Transport 2023

Transport
Whole of Government
Asset valuation
Compliance
Financial reporting
Information technology
Infrastructure
Internal controls and governance
Management and administration
Procurement
Risk

What this report is about

Result of the Transport portfolio of agencies' financial statement audits for the year ended 30 June 2023.

The audit found

Unqualified audit opinions were issued for all Transport portfolio agencies.

An 'emphasis of matter' paragraph was included in the Transport Asset Holding Entity of New South Wales' (TAHE) independent auditor's report, which draws attention to management's disclosure regarding proposed changes to TAHE's operating model.

Government's decision to convert TAHE into a non-commercial Public Non-Financial Corporation may impact the future valuation and the control of TAHE's assets.

Transport for NSW's valuation of roads and bridges resulted in a net increase to its asset value by $15.7 billion.

Transport for NSW and Sydney Metro have capitalised over $300 million of tender bid costs paid to unsuccessful tender bidders relating to significant infrastructure projects. Whilst NSW Treasury policy provides clarity on the reimbursement of unsuccessful bidders' costs, clearer guidance on how to account for these costs in agency's financial statements is required.

The key audit issues were

The number of issues reported to management decreased from 53 in 2021–22 to 49 in 2022–23.

High-risk findings include:

  • gaps in how Sydney Metro manages its contractors and how conflicts of interest are recorded and managed
  • future financial reporting implications to account for government's proposed changes to TAHE's future operating model, including asset valuations and control assessments of assets and operations
  • Parramatta Park Trust's tree assets' valuation methodology needs to be addressed.

Recommendations were made to address the identified deficiencies.

This report provides Parliament and other users of the Transport portfolio of agencies’ financial statements with the results of our audits, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Transport portfolio of agencies (the portfolio) for 2023.

Section highlights

  • Unqualified audit opinions were issued on all the portfolio agencies’ 30 June 2023 financial statements.
  • An 'Emphasis of Matter' paragraph was included in the Transport Asset Holding Entity of New South Wales’ (TAHE) Independent Auditor's Report to draw attention to management's disclosure regarding the proposed changes to TAHE's future operating model.
  • The total number of errors (including corrected and uncorrected) in the financial statements increased by 59% compared to the prior year.
  • The recent government's decision to convert TAHE into a non-commercial Public Non-Financial Corporation may impact the future valuation and the control of TAHE’s assets.
  • Transport for NSW needs to further improve its quality assurance processes over comprehensive valuations, in particular, ensuring key inputs used in the valuations are properly supported and verified.
  • Transport for NSW and Sydney Metro capitalised over $300 million of bid costs paid to unsuccessful bidders. NSW Treasury’s Bid Cost Contributions Policy does not contemplate how these costs should be recognised in agency’s financial statements. Transport agencies should work with NSW Treasury to develop an accounting policy for the bid cost contributions to ensure consistent application across the sector.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision-making.
This chapter outlines our observations and insights from our financial statement audits of agencies in the Transport portfolio.

Section highlights

  • The 2022–23 audits identified four high risks and 28 moderate risk issues across the portfolio. Thirty-nine per cent of issues were repeat findings.
  • Four high risk findings include:
    • TAHE’s asset valuations (new)
    • TAHE’s control of assets and operations (new)
    • Sydney Metro’s management of contractors and conflicts of interest (new)
    • Parramatta Park Trust’s valuation of trees (repeat).
  • The total number of findings decreased from 53 in 2021–22 to 49 in 2022–23. Many repeat findings related to control weaknesses over the asset valuation, payroll processes, conflicts of interest and information technology user access administration.


Appendix one – Misstatements in financial statements submitted for audit 

Appendix two – Early close procedures

Appendix three – Timeliness of financial reporting 

Appendix four – Financial data 

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Enterprise, Investment and Trade 2023

Enterprise, Investment and Trade 2023

Finance
Asset valuation
Compliance
Cyber security
Financial reporting
Information technology
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Regulation
Risk

What this report is about

Results of the Enterprise, Investment and Trade portfolio of financial statement audits for the year ended 30 June 2023.

What we found

Unqualified audit opinions were issued for all completed Enterprise, Investment and Trade portfolio agencies.

An 'other matter' paragraph was included in the Jobs for NSW Fund's 30 June 2022 independent auditor's report to reflect the non-compliance with the Jobs for NSW Act 2015 (the Act). The Act requires the board to consist of seven members that include the Secretary of the Treasury, the Secretary of the Premier's Department, and five ministerial appointments. The board has consisted of two secretaries since 24 May 2019 when the independent members resigned. The remaining five members have not been appointed by the ministers as required by section 5(2) of the Act.

Financial statements were not prepared for the Responsible Gambling Fund, a special deposit account. Financial statements should be prepared unless NSW Treasury releases a Treasurer's Direction under section 7.8 of the GSF Act that will exempt the SDA from financial reporting requirements.

What the key issues were

The number of issues reported to management decreased from 65 in 2021–22 to 44 in 2022–23. Forty-six per cent of issues were repeated from the prior year.

Two high-risk issues were identified across the portfolio. One was a repeat issue where the Jobs for NSW Fund did not comply with legislation. The other high-risk issue was first identified in 2022–23 when the Department for Enterprise, Investment and Trade incorrectly recorded grants that did not meet the requirements of Australian Accounting Standards.

What we recommended

The Department should develop a robust model to ensure it only provides for grants that meet the eligibility criteria.

This report provides Parliament and other users of the Enterprise, Investment and Trade portfolio of agencies’ financial statements with the results of our audits, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision-making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Enterprise, Investment and Trade portfolio of agencies (the portfolio) for 2023.

Section highlights

  • Unqualified audit opinions were issued on all completed portfolio agencies’ 2022–23 financial statements.
  • An ‘other matter’ paragraph was included for the Jobs for NSW Fund’s 30 June 2022 financial report to reflect non-compliance with the Jobs for NSW Act 2015.
  • The Act requires the board to consist of seven members that include the Secretary of the Treasury, the Secretary of the Department of Premier and Cabinet (or their nominees) and five ministerial appointments, one of whom is to be appointed as Chair of the board. The board has consisted of the two secretaries since 24 May 2019 when the independent members resigned. The remaining five members have not been appointed by the ministers as required by section 5(2) of the Act.
  • An ‘emphasis of matter’ paragraph was included in the Jobs for NSW Fund’s 30 June 2022 financial report to draw attention to the financial report being prepared for the purpose of fulfilling the Jobs for NSW Fund’s financial reporting responsibilities as requested by the Treasurer’s delegate.
  • The total number of errors (including corrected and uncorrected) in the financial statements increased by 12% compared to the prior year.
  • The Responsible Gambling Fund (Special Deposit Account) did not prepare financial statements for the year ended 30 June 2023. Financial statements should be prepared unless NSW Treasury releases a Treasurer’s Direction under section 7.8 of the GSF Act that will exempt the Fund from financial reporting requirements. 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision-making.

This chapter outlines our observations and insights from our financial statement audits of agencies in the Enterprise, Investment and Trade portfolio.

Section highlights

  • The audits identified two high-risk and 20 moderate risk issues across the portfolio. Of these, one was a high-risk repeat issue and ten were moderate-risk repeat issues.
  • One of the high-risk matters related to the Jobs for NSW Fund audit for the year ended 30 June 2022.
  • The other high-risk matter related to overstating grants relating to the Jobs Plus Program as the criteria to pay the grant was not met at 30 June 2023.
  • The total number of findings decreased from 65 to 44 with 2022–23 findings mainly related to deficiencies in accounting for property, plant and equipment and agencies having outdated policies. 

Appendix one – Misstatements in financial statements submitted for audit

Appendix two – Early close procedures

Appendix three – Timeliness of financial reporting

Appendix four – Financial data

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Management of the Critical Communications Enhancement Program

Management of the Critical Communications Enhancement Program

Finance
Health
Justice
Whole of Government
Cyber security
Information technology
Infrastructure
Internal controls and governance
Project management
Risk
Service delivery
Shared services and collaboration

What the report is about

Effective radio communications are crucial to NSW's emergency services organisations.

The Critical Communications Enhancement Program (CCEP) aims to deliver an enhanced public safety radio network to serve the five emergency services organisations (ESOs), as well as a range of other users.

This report assesses whether the NSW Telco Authority is effectively managing the CCEP.

What we found

Where it has already been delivered (about 50% of the state), the enhanced network meets most of the requirements of ESOs.

The CCEP will provide additional infrastructure for public safety radio coverage in existing buildings agreed to with ESOs. However, radio coverage inside buildings constructed after the CCEP concludes will be at risk because building and fire regulations do not address the need for in-building public safety radio coverage.

Around 98% of radios connected to the network can be authenticated to protect against cloning, though only 42% are.

The NSW Telco Authority has not settled with ESOs on how call encryption will be used across the network. This creates the risk that radio interoperability between ESOs will not be maximised.

When completed, the public safety radio network will be the only mission critical radio network for ESOs. It is unclear whether governance for the ongoing running of the network will allow ESOs to participate in future network operational decisions.

The current estimated capital cost for the NSW Telco Authority to complete the CCEP is $1.293 billion. This is up from an estimated cost of $400 million in 2016. The estimated capital cost was not publicly disclosed until $1.325 billion was shown in the 2021–22 NSW Budget Papers.

We estimate that the full cost to government, including costs to the ESOs, of implementing the enhanced network is likely to exceed $2 billion.

We made recommendations about

  • The governance of the enhanced Public Safety Network (PSN) to support agency relationships.
  • The need to finalise a Traffic Mitigation Plan for when the network is congested.
  • The need to provide advice to the NSW Government about the regulatory gap for ensuring adequate network reach in future buildings.
  • The need to clarify how encryption and interoperability will work on the enhanced network.
  • The need for the NSW Telco Authority to comply with its policy on Infrastructure Capacity Reservation.
  • Expediting measures to protect against the risk of cloning by unauthenticated radios.

Public safety radio networks are critical for operational communications among Emergency Services Organisations (ESOs), which in New South Wales include:

  • NSW Ambulance
  • Fire and Rescue NSW
  • NSW Police Force
  • NSW Rural Fire Service
  • NSW State Emergency Service.1

Since 1993, these five ESOs have had access to a NSW Government owned and operated radio communications network, the Public Safety Network (PSN), to support their operational communications. Around 60 to 70 other entities also have access to this network, including other NSW government entities, Commonwealth government entities, local councils, community organisations, and utility companies.

Pursuant to the Government Telecommunications Act 2018 ('the Act'), the New South Wales Government Telecommunications Authority ('NSW Telco Authority') is responsible for the establishment, control, management, maintenance and operation of the PSN.2

Separate to the PSN, all ESOs and other government entities have historically maintained their own radio communication capabilities and networks. Accordingly, the PSN has been a supplementary source of operational radio communications for these entities.

These other radio networks maintained by ESOs and other entities are of varying size and capability, with many ageing and nearing their end-of-life. There was generally little or no interoperability between networks, infrastructure was often co-located and duplicative, and there were large gaps in geographic coverage.

In 2016, the NSW Telco Authority received dedicated NSW Government funding to commence the Critical Communications Enhancement Program (CCEP).

According to NSW Telco Authority's 2021–22 annual report, the CCEP is a transformation program for operational communications for NSW government agencies. The CCEP '…aims to deliver greater access to public safety standard radio communications for the State’s first responders and essential service agencies'. The objective of CCEP is to consolidate the large number of separate radio networks that are owned and operated by various NSW government entities and to enhance the state’s existing shared PSN. The program also aims to deliver increased PSN coverage throughout New South Wales.

The former NSW Government intended that as the enhanced PSN was progressively rolled-out across NSW, ESOs would migrate their radio communications to the enhanced network, before closing and decommissioning their own networks.

About this Audit

This audit assessed whether the CCEP is being effectively managed by the NSW Telco Authority to deliver an enhanced PSN that meets ESOs' requirements for operational communications.

We addressed the audit objective by answering the following two questions:

  1. Have agreed ESO user requirements for the enhanced PSN been met under day-to-day and emergency operational conditions?
  2. Has there been adequate transparency to the NSW Government and other stakeholders regarding whole-of-government costs related to the CCEP?

In answering the first question, we also considered how the agreed user requirements were determined. This included whether they were supported by evidence, whether they were sufficient to meet the intent of the CCEP (including in considering any role for new or alternative technologies), and whether they met any relevant technical standards and compliance obligations (including for cyber security resilience).

While other NSW government agencies and entities use the PSN, we focused on the experience of the five primary ESOs because these will be the largest users of the enhanced PSN.

Both the cost and time required to complete the CCEP roll-out have increased since 2016. While it was originally intended to be completed in 2020, this is now forecast to be 2027. Infrastructure NSW has previously assessed the reasons for the increases in time and cost. A summary of the findings made by Infrastructure NSW is presented in Chapter 1 of this report. Accordingly, as these matters had already been assessed, we did not re-examine them in this performance audit.

The auditee for this performance audit is the NSW Telco Authority, which is a statutory authority within the Department of Customer Service portfolio.

In addition to being responsible for the operation of the PSN, section 5 of the Act also prescribes that the NSW Telco Authority is:

  • to identify, develop and deliver upgrades and enhancements to the government telecommunications network to improve operational communications for government sector agencies
  • to develop policies, standards and guidelines for operational communications using telecommunications networks.

The NSW Telco Authority Advisory Board is established under section 10 of the Act. The role of the board is to advise the NSW Telco Authority and the minister on any matter relating to the telecommunications requirements of government sector agencies and on any other matter relating to the functions of the Authority. As of 2 June 2023, the responsible minister is the Minister for Customer Service and Digital Government.

The five identified ESOs are critical stakeholders of the CCEP and therefore they were consulted during this audit. However, the ESOs were not auditees for this performance audit.

Conclusion

In areas of New South Wales where the enhanced Public Safety Network has been implemented under the Critical Communications Enhancement Program, the NSW Telco Authority has delivered a radio network that meets most of the agreed requirements of Emergency Services Organisations for routine and emergency operations.
In April 2023, the enhanced Public Safety Network (PSN) was approximately 50% completed. In areas where it is used by Emergency Services Organisations (ESOs), the PSN generally meets agreed user requirements. This is demonstrated through extensive performance monitoring and reporting, which shows that agreed performance standards are generally achieved. Reviews by the NSW Government and the NSW Telco Authority found that the PSN performed effectively during major flood events in 2021 and 2022.

Where it is completed, PSN coverage is generally equal to or better than each ESO's individual pre-existing coverage. The NSW Telco Authority has a dedicated work program to address localised coverage gaps (or 'blackspots') in those areas where coverage has otherwise been substantively delivered. Available call capacity on the network far exceeds demand in everyday use. Any operational issues that may occur with the PSN are transparent to ESOs in real time.

The NSW Telco Authority consulted extensively with ESOs on requirements for the enhanced PSN, with relatively few ESO requirements not being included in the specifications for the enhanced PSN. Lessons from previous events, including the 2019–20 summer bushfires, have informed the design and implementation of the enhanced PSN (such as the need to ensure adequate backup power supply to inaccessible sites). The network is based on the Project 25 technical standards for mission-critical radio communications, which is widely-accepted in the public safety radio community throughout Australia and internationally.

There is no mechanism to ensure adequate radio coverage within new building infrastructure after the CCEP concludes, but the NSW Telco Authority and ESOs have agreed an approach to prioritise existing in-building sites for coverage for the duration of the CCEP.
The extent to which the PSN works within buildings and other built structures (such as railway tunnels) is of crucial importance to ESOs, especially the NSW Police Force, NSW Ambulance, and Fire and Rescue NSW. This is because a large proportion of their operational communications occurs within buildings.

There is no mechanism to ensure the adequacy of future in-building coverage for the PSN in new or refurbished buildings after the CCEP concludes. Planning, building, and fire regulations are silent on this issue. We note there are examples in the United States of how in-building coverage for public safety radio networks can be incorporated into building or fire safety codes.

In regard to existing buildings, it is not possible to know whether a building requires its own in-building PSN infrastructure until nearby outside radio sites, including towers and antennae, have been commissioned into the network. Only then can it be determined whether their radio transmissions are capable of penetrating inside nearby buildings. Accordingly, much of this work for in-building coverage cannot be done until outside radio sites are finished and operating.

In March 2023, the NSW Telco Authority and ESOs agreed on a list of 906 mandatory and 7,086

non-mandatory sites for in-building PSN coverage. Most of these sites will likely be able to receive radio coverage via external antennae and towers, however this cannot be confirmed until those nearby external PSN sites are completed. The parties also agreed on an approach to prioritising those sites where coverage is needed but not provided by antennae and towers. Available funding will likely only extend to ensuring coverage in sites deemed mandatory, which is nonetheless expected to meet the overall benchmark of achieving 'same or better' coverage than what ESOs had previously.

There is a risk that radio interoperability between ESOs will not be maximised because the NSW Telco Authority has not settled with ESOs how encryption will be used across the enhanced PSN.
End-to-end encryption of radio transmissions is a security feature that prevents radio transmissions being intercepted or listened to by people who are not meant to. The ability of the PSN to provide end-to-end encryption of operational communications is of critical importance to the two largest prospective users of the PSN: the NSW Police Force and NSW Ambulance. Given that encryption excludes other parties that do not have the requisite encryption keys, its use creates an obstacle to achieving a key intended benefit of the CCEP, that is a more interoperable PSN, where first responders are better able to communicate with other ESOs.

Further planning and collaboration between PSN participants are necessary to consider how these dual benefits can be achieved, including in what operational circumstances encrypted interoperability is necessary or appropriate.

The capital cost to the NSW Telco Authority of the CCEP, originally estimated at $400 million in 2016, was not made public until the 2021–22 NSW Budget disclosed an estimate of $1.325 billon.
The estimated capital cost to complete all stages of the CCEP increased over time. This increasing cost was progressively disclosed to the NSW Government through Cabinet processes between 2015–16 and 2021–22.

In 2016, the full capital cost to the NSW Telco Authority of completing the CCEP was estimated to be $400 million. This estimated cost was not publicly disclosed, nor were subsequent increases, until the cost of $1.325 billion was publicly disclosed in the 2021–22 NSW Budget (revised down in the 2022–23 NSW Budget to $1.293 billion).

There has been no transparency about the whole-of-government cost of implementing the enhanced PSN through the CCEP.
In addition to the capital costs incurred directly by the NSW Telco Authority for the CCEP, ESOs have incurred costs to maintain their own networks due to the delay in implementing the CCEP. The ESOs will continue to incur these costs until they are able to fully migrate to the enhanced PSN, which is expected to be in 2027. These costs have not been tracked or reported as part of transparently accounting for the whole-of-government cost of the enhanced PSN. This is despite Infrastructure NSW in 2019 recommending to the NSW Telco Authority that it conduct a stocktake of such costs so that a whole-of-government cost impact is available to the NSW Government.

1 The definition of 'emergency services organisation' is set out in the State Emergency and Rescue Management Act 1989 (NSW). In addition to the five ESOs discussed in this report, the definition also includes: Surf Life Saving New South Wales; New South Wales Volunteer Rescue Association Inc; Volunteer Marine Rescue NSW; an agency that manages or controls an accredited rescue unit; and a non-government agency that is prescribed by the regulations for the purposes of this definition.
2 Section 15(1) of the Government Telecommunications Act 2018 (NSW).

The NSW Telco Authority established and tracked its own costs for the CCEP

Over the course of the program from 2016, the NSW Telco Authority prepared a series of business cases and program reviews that estimated its cost of implementing the program in full, including those shown in Exhibit 6 below.

Exhibit 6: Estimated costs to fully implement the CCEP
Source Capital cost ($ million) Operating cost
($ million)
Completion date
March 2016 business case 400 37.3 2020
November 2017 internal review 476.7 41.7 2022
March 2020 business case 950–1,050 -- 2025
October 2020 business case 1,263.1 56.1 2026

Source: CCEP business cases as identified.

In response to the 2016 CCEP business case, the then NSW Government approved the NSW Telco Authority implementing the CCEP in full, with funding provided in stages. The NSW Telco Authority tracked its costs against approved funding, with monthly reports provided to the multi-agency Program Steering Committee

Throughout the program, the NSW Government was informed of increasing costs being incurred by the NSW Telco Authority for the CCEP

The various business cases, program updates, and program reviews prepared by the NSW Telco Authority were provided to the NSW Government through the required Cabinet process when seeking approval for the program proceeding and requests for both capital and operational funding. These provided clear indication of the changing overall cost of the CCEP to the NSW Telco Authority, as well as the delays that were being experienced.

There was no transparency to the Parliament and community about changes in the capital cost of the CCEP until the 2021–22 NSW Budget

As the business cases for the CCEP were not publicly available, the only sources of information about capital cost were NSW Budget papers and media releases. The information provided in the annual Budget papers prior to the 2021–22 NSW Budget provided no visibility of the estimated full capital cost to complete all stages of the CCEP. As shown in Exhibit 7 below, this information was fragmented and complex.

Media releases about the progress of the CCEP did not provide the estimated total cost to the NSW Telco Authority of $1.325 billion to complete all stages of the CCEP until June 2021. Prior to this date, media releases only provided funding for the initial stages of the program or for the stages subject to a funding announcement.

Even during the September 2019 and March 2020 Parliamentary Estimate Committee hearings where the costings and delays to the CCEP were raised, the estimated full cost of the CCEP was not revealed.

Exhibit 7: CCEP funding in NSW Budget papers from 2015–16 to 2022–23
Financial year Type of major work Description of expenditure Forecast estimate to complete ($ million) Estimated duration
2015–16 New work Infrastructure Rationalisation Program: Planning and Pilot 18.3 2015–16
2016–17 Work in progress CCEP Planning and Pilot 18.3 2015–17
New work CCEP 45 2016–17
2017–18 New work CCEP 190.75 2017–21
2018–19 Work in progress CCEP North Coast and State-wide Detailed Design 190.75 2017–21
New work CCEP Greater Metropolitan Area 236 2018–22
2019–20 Work in progress CCEP 426.9 2018–22
2020–21 Work in progress CCEP 664.8 2018–22
2021–22 Work in progress CCEP 1,325 2018–26
2022–23 Work in progress CCEP 1,292.8 2018–26

Source: NSW Treasury, Annual State Budget Papers.

The original business case for the CCEP included estimated ESO costs, though these costs were not tracked throughout the program

Estimates for ESO costs for operating and maintaining their own radio networks over the four years from 2016–17 were included in the original March 2016 business case. They included $75.2 million for capital expenditure and $95 million for one-off operating costs. These costs, as well as costs incurred by ESOs due to the delay in the program, were not subsequently tracked by the NSW Telco Authority.

In January 2017, Infrastructure NSW reviewed the CCEP business case of March 2016. In this review, Infrastructure NSW recommended that the NSW Telco Authority identify combined and apportioned costs and cashflow for all ESOs over the CCEP funding period reflecting all associated costs to deliver the CCEP. These to include additional incidental capital costs accruing to ESOs, transition and migration to the new network and the cost (capital and operational) of maintaining existing networks. This recommendation was implemented in the November 2017 program review, with ESO capital costs estimated as $183 million.

In 2019, Infrastructure NSW conducted a Deep Dive Review on the progress of the CCEP. In this review, Infrastructure NSW made what it described as a 'critical recommendation' that the NSW Telco Authority:

…coordinate a stocktake of the costs of operational bridging solutions implemented by PSAs [ESOs] as a result of the 18-month delay, so that a whole-of-government cost impact is available to the NSW Government.  

It should be noted that the delay to CCEP completion now is seven years and that further ‘operational bridging solutions’ have been needed by the ESOs.

'Stay Safe and Keep Operational' costs incurred by ESOs will be significantly higher than originally estimated

Stay Safe and Keep Operational (SSKO) funding was established to provide funding to ESOs to maintain their legacy networks while the CCEP was refreshing and enhancing the PSN. This recognised that much of the network infrastructure relied on by ESOs had reached – or was reaching – obsolescence and would either require extensive maintenance or replacement before the PSN was available for ESOs to migrate to it. ESOs may apply to NSW Treasury for SSKO funding, with their specific proposals being reviewed (and endorsed, where appropriate) by the NSW Telco Authority. Accordingly, SSKO expenditure does not fall within the CCEP budget allocation.

As shown in the table below, extracted from the March 2016 CCEP business case, the total expected cost for SSKO purposes over the course of the CCEP was originally $40 million, assuming the enhanced PSN would be fully available by 2020.

Exhibit 8: Stay Safe and Keep Operational forecast costs, 2017 to 2020
Year 2017 2018 2019 2020 Total
SSKO forecast ($ million) 12.5 15 10 2.5 40

Source: March 2016 CCEP business case.

In October 2022, the expected completion date for the CCEP was re-baselined to August 2027. Accordingly, ESOs will be required to continue to maintain their radio networks using legacy equipment for seven years longer than the original 2020 forecast. This will likely become progressively more expensive and require additional SSKO funding. For example, NSW Telco Authority endorsed SSKO bids for 2022–23 exceeded $35 million for that year alone.

Compared to the original forecast made in the March 2016 CCEP business case of $40 million, we found ESOs had estimated SSKO spending to 2027 will be $292.5 million.

A refresh of paging network used by ESOs and the decommissioning of redundant sites were both removed from the original 2016 scope of the CCEP

Paging

A paging network is considered an important user requirement by the Fire and Rescue NSW, NSW Rural Fire Service, and NSW State Emergency Service. The 2016 CCEP business case included a paging network refresh within the program scope of works. This was reiterated in the November 2017 internal review of the program. These documents did not estimate a cost for this refresh. The March 2020 and October 2020 business cases excluded paging from the program scope. The audit is unable to identify when, why or by whom the decision was made to remove paging from the program scope, something that was also not well communicated to the affected ESOs.

In 2021, after representations from the affected ESOs, the NSW Telco Authority prepared a separate business case for a refresh of the paging network at an estimated capital cost of $60.31 million. This program was subsequently approved by the NSW Government and included in the 2022–23 NSW Budget.

In determining an estimated full whole-of-government cost of delivering the enhanced PSN, we have included the budgeted cost of the paging network refresh on the basis that:

  • it was expressly included in the original approved March 2016 business case
  • the capability is deemed essential to the needs of three ESOs.

Decommissioning costs

The 2016 CCEP business case included cost estimates for decommissioning surplus sites (whether ‘old’ GRN sites or sites belonging to ESOs’ own networks). These estimates were provided for both the NSW Telco Authority ($38 million) and for the ESOs ($55 million). However, while these estimates were described, they were not included as part of the NSW Telco Authority's estimated capital cost ($400 million) or (more relevantly) operating cost ($37.3 million) for the CCEP. This is despite decommissioning being included as one of eight planned activities for the rollout of the program.

In the October 2020 business case, an estimate of $201 million was included for decommissioning agency networks based on a model whereby:

  • funding would be coordinated by the NSW Telco Authority
  • scheduling and reporting through an inter-agency working group and
  • where appropriate, agencies would be appointed as the most appropriate decommissioning party.

This estimated cost is not included in the CCEP budget.

In determining an estimated full whole-of-government cost of the enhanced PSN, we have included the estimated cost of decommissioning on the basis that:

  • decommissioning was included in the 2016 CCEP business case as one of eight 'planned activities for the rollout of the program'
  • effective decommissioning of surplus sites and equipment (including as described in the business case as incorporating asset decommissioning, asset re-use, and site make-good) is an inherent part of the program management for an enhanced PSN
  • costs incurred in decommissioning are entirely a consequence of the CCEP program.

The estimated minimum cost of building an enhanced PSN consistent with the original proposal is over $2 billion

We have derived two estimated minimum whole-of-government costs for delivering an enhanced PSN. These are:

  • $2.04 billion when calculated from NSW Telco Authority data – shown as estimate A in Exhibit 9 below.
  • $2.26 billion when calculated from ESO supplied data – shown as estimate B in Exhibit 9.

Both totals include:

  • budgeted amounts for both CCEP capital expenditure ($1,292.8 million) and operating expenditure ($139 million)
  • the NSW Telco Authority's 2020 estimated cost for decommissioning ($201 million)
  • the NSW Telco Authority's approved funding for paging refresh ($60.3 million).

The two estimated totals primarily vary around the capital expenditure of ESOs (particularly SSKO funding). To determine these costs, we used ESO provided actual SSKO costs to date, as well as their estimates for maintaining their legacy radio networks through to 2027.

The equivalent cost estimates from the NSW Telco Authority were sourced from the November 2017 internal review and the October 2020 business case for CCEP. It should be noted that the amounts for both estimates are not audited, or verified, but do provide an indication of how whole-of-government costs have grown over the course of the program.

The increase in and reasons for the increase in total CCEP costs (capital and one-off operating) incurred or forecast by the NSW Telco Authority (from $437.3 million in 2016 to $1,431.8 million in 2022) have been provided to the NSW Government through various business cases and reviews prepared by the NSW Telco Authority, as well as by reviews conducted by Infrastructure NSW as part of its project assurance responsibilities.

However, the growth in ESO costs and other consequential costs, such as paging and decommissioning, from around $263 million in the 2016 CCEP business case to between $600 million and $800 million, has to a large degree remained invisible and unexplained to the NSW Government and other stakeholders

Exhibit 9: Estimated whole-of-government costs of the enhanced PSN
  Estimated whole-of-government cost, over time
Cost type 20161 20172 20203 2023–Estimate A4 2023–Estimate B5
$ million $ million $ million $ million $ million
CCEP capital expenditure 400a 476.7b 1,263.1c 1,292.8d 1,292.8d
CCEP operating expenditure 37.3a 41.7b 41.5e 139d 139d
CCEP total 437.3 518.4 1,304.6 1,431.8 1,431.8
ESO capital expenditure 75.2a,f 183b,e 75.4e 258.4g 292.5
ESO one-off operating expenditure 93a n.a.l 86.5e 86.5h 273
ESO total 168.2 183 161.9 344.9 565.5
Paging n.a.i n.a.i n.a.j 60.3k 60.3k
Decommissioning 93 n.a.l 201.0 201h 201
Paging and decommissioning total 93 n.a. 201 261.3 261.3
Whole-of-government total 698.5 701.4 1,667.5 2,038 2,258.6

Notes:
  1. Financial year 2016 to Financial year 2020.
  2. Financial year 2016 to Financial year 2021.
  3. Financial year 2016 to Financial year 2025.
  4. Financial year 2016 to Financial year 2026.
  5. Financial year 2022 to Financial year 2025.
  6. Stay Safe and Keep Operational (SSKO) costs plus terminals costs.
  7. November 2017 internal review and October 2020 Business case.
  8. October 2020 Business case.
  9. Included in CCEP capital expenditure at that time.
  10. By 2020, a refresh of the paging network had been removed from the CCEP scope.
  11. A separate business case for a refresh of the paging network was approved by government in 2022.
  12. Figure not included in the source document.
Sources:
  1. March 2016 CCEP business case.
  2. November 2017 Internal Review conducted by the NSW Telco Authority.
  3. October 2020 CCEP business case.
  4. Derived from business cases, with ESO costs drawn from NSW Telco Authority data.
  5. Derived from business cases, with ESO costs based on data provided to the Audit Office of New South Wales by each of the five ESOs.

Appendix one – Response from agency

Appendix two – Trunked public safety radio networks

Appendix three – About the audit

Appendix four – Performance auditing

 

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #383 - released 23 June 2023

 

Published

Actions for Natural disasters

Natural disasters

Community Services
Environment
Finance
Local Government
Planning
Transport
Treasury
Whole of Government
Asset valuation
Compliance
Financial reporting
Infrastructure
Regulation
Risk
Service delivery

What this report is about

This report draws together the financial impact of natural disasters on agencies integral to the response and impact of natural disasters during 2021–22.

What we found

Over the 2021–22 financial year $1.4 billion from a budget of $1.9 billion was spent by the NSW Government in response to natural disasters.

Total expenses were less than the budget due to underspend in the following areas:

  • clean-up assistance, including council grants
  • anticipated temporary accommodation support
  • payments relating to the Northern Rivers Business Support scheme for small businesses.

Natural disaster events damaged council assets such as roads, bridges, waste collection centres and other facilities used to provide essential services. Additional staff, contractors and experts were engaged to restore and repair damaged assets and minimise disruption to service delivery.

At 30 June 2022, the estimated damage to council infrastructure assets totalled $349 million.

Over the first half of the 2022–23 financial year, councils experienced further damage to infrastructure assets due to natural disasters. NSW Government spending on natural disasters continued with a further $1.1 billion spent over this period.

Thirty-six councils did not identify climate change or natural disaster as a strategic risk despite 22 of these having at least one natural disaster during 2021–22.

Section highlights

  • $1.4 billion from a budget of $1.9 billion was spent by the NSW Government in response to natural disasters during 2021–22.
  • Budget underspent for temporary housing and small business support as lower than expected need.

Section highlights

  • 83 local council areas were impacted by natural disasters during 2021–22, with 58 being impacted by more than one type of natural disaster.
  • $349 million damage to council infrastructure assets at 30 June 2022.

 

Published

Actions for Government's acquisition of private property: Sydney Metro project

Government's acquisition of private property: Sydney Metro project

Transport
Planning
Whole of Government
Compliance
Infrastructure
Internal controls and governance
Project management
Risk

What the report is about

Sydney Metro is Australia’s largest public transport project. It requires the acquisition of many private properties, including residential and business properties.

This audit assessed the effectiveness of the acquisition of private properties for the Sydney Metro project. The audited agencies were Sydney Metro, the Department of Planning and Environment (Valuer General NSW) and Transport for NSW (the Centre for Property Acquisition).

The audit assessed agencies against the framework for property acquisitions in New South Wales. It did not re-perform the valuations done for individual properties that were acquired by Sydney Metro.

What we found

Acquisitions of private property for the Sydney Metro project were mostly effective in the sample of acquisitions we assessed. We found Sydney Metro:

  • complied with legislative and policy requirements for compensation and communication with people subject to property acquisitions
  • kept accurate records of its acquisitions and applied probity controls consistently
  • did not complete detailed plans or negotiation strategies for the high-risk and high-value acquisitions we reviewed
  • did not comply with legislative timelines for most compulsory acquisitions because of delays in receiving the required information from the Valuer General in these cases.

The Centre for Property Acquisition has overseen the implementation of reforms to residential acquisition processes, but its assessment of the effectiveness of these reforms has not been comprehensive.

What we recommended

The audit made four recommendations to the audited agencies to improve:

  • plans and strategies for the acquisition of high-risk and high-value properties
  • timeliness of issuing compensation determinations for compulsory acquisitions
  • data quality on the experience of people subject to property acquisitions.

The NSW Government has the power to acquire land that is owned or leased by individuals or businesses, if it is needed for a public purpose. The power arises from the Land Acquisition (Just Terms Compensation) Act 1991 (the Just Terms Act). Government agencies that have the power to compulsorily acquire private property are referred to as ‘acquiring authorities’. People who are subject to acquisitions are referred to as ‘affected parties’ and include property owners (business or residential), businesses with a commercial lease on a property, or individuals with residential tenancy leases. In recent years, the vast majority of acquisitions by the NSW Government have been for public transport or road projects.

Sydney Metro is a NSW Government agency with responsibility for building the Sydney Metro railway project. Sydney Metro is Australia’s largest public transport project. The project requires the acquisition of a large number of private properties. Sydney Metro has been one of the largest acquirers of private property in recent years, completing over 500 acquisitions between 2020 and mid-2022, with a total acquisition value of over $2 billion. Other agencies and statutory officers involved in the acquisition of property for the Sydney Metro project include:

  • the Department of Planning and Environment (DPE), which supports the minister responsible for the Just Terms Act. DPE also provides staff to the Valuer General of NSW
  • the Valuer General of NSW, an independent statutory officer that determines compensation in cases where the acquiring authority and the affected party cannot agree on compensation for property that has been acquired
  • Transport for NSW, which includes the Centre for Property Acquisition (CPA). The CPA does not have a direct role in acquiring properties, but its responsibilities include developing guidance for acquiring agencies and monitoring and reporting on their activities.

About this audit

The objective of this audit was to assess the effectiveness of acquisitions of private properties for Sydney Metro projects. The audit assessed agencies against the legislative and policy requirements in place for government acquisitions of private property in New South Wales. In line with the Audit Office's legislative mandate, the audit does not comment on the merits of the policy objectives reflected in the Just Terms Act.

The audit examined a sample of 20 property acquisitions. This was not a statistically representative sample. While our report provides comments on Sydney Metro’s overall acquisition processes, it does not provide assurance regarding the acquisitions that were not examined for this audit.

The audit did not re-perform the valuations done for individual properties that were acquired by Sydney Metro. Affected parties who disagree with the valuation of their property have the right to seek independent assessment of this via the Valuer General and the Land and Environment Court.

Conclusion

Acquisitions of property for the Sydney Metro project were mostly effective in the sample of acquisitions we assessed. Sydney Metro followed requirements for communication with affected parties. Compensation processes were conducted in compliance with legislative requirements, but compensation determinations for compulsory acquisitions were not completed within legislated time frames due to delays in receiving these from the Valuer General. Governance and probity processes were followed consistently, with some relatively minor exceptions. 

Sydney Metro has detailed guidelines for acquisitions that are based on relevant legislation and government policy. In the 20 acquisitions we assessed for this audit, these procedures were followed consistently. This included adhering to minimum timelines for negotiation periods, engaging independent valuers and other experts when needed, and complying with governance and probity processes.

Sydney Metro staff followed requirements for communication and support for residential acquisitions by assigning ‘personal managers’ and providing additional support to affected parties when needed. The Centre for Property Acquisition (CPA) has overseen reforms to the residential property acquisition process in recent years. These reforms include the introduction of the NSW Property Acquisition Standards and the use of personal managers, in addition to the existing acquisition managers, for residential acquisitions. However, the CPA has not assessed the impact of these changes on the experiences on people affected by property acquisitions.

Sydney Metro did not comply with the legislative requirement to provide a formal compensation notice to the affected party within 45 days of a compulsory acquisition starting in any of the eight relevant acquisitions in our sample. This was because Sydney Metro must wait for the Valuer General to complete a compensation determination before Sydney Metro can send the compensation notice, and the Valuer General did not do this within 45 days. We acknowledge that Sydney Metro does not have full control over this process, and that it has taken steps to mitigate the impact of delays on affected parties. 

This chapter presents our findings on Sydney Metro's acquisition of industrial and commercial properties. Industrial properties include construction businesses and manufacturing facilities. Commercial properties were mostly properties such as shopping centres and office towers. Many of these acquisitions involve businesses and properties that are relatively complex and have high values. This means the valuation process can require multiple experts and can be lengthy and contested. Adherence to governance and probity requirements is important for these acquisitions in order to demonstrate that the acquiring authority has achieved value for money.

This chapter presents our findings on Sydney Metro's acquisition of residential properties, which include apartments and houses, and small business leases, which mostly affected businesses in small shopping centres or arcades. Most of these acquisitions were lower value compared to industrial and commercial property acquisitions and did not require as much expert advice on complex technical issues. However, residential property acquisitions can be personally distressing for the affected parties and require staff from the acquiring authority to provide support and show empathy while ensuring legislative compliance and value for money.

Appendix one – Responses from agencies

Appendix two – About the audit 

Appendix three – Performance auditing 

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #375 - released 9 February 2023

Published

Actions for Design and implementation of the Transport Asset Holding Entity

Design and implementation of the Transport Asset Holding Entity

Transport
Treasury
Asset valuation
Financial reporting
Infrastructure
Procurement
Risk
Service delivery

What the report is about

The Transport Asset Holding Entity (TAHE) is the State's custodian of rail assets. It is a state owned corporation and commenced operating on 1 July 2020.

This audit assessed the effectiveness of NSW Government agencies' design and implementation of TAHE. We audited TAHE, Transport for NSW (TfNSW) and NSW Treasury.

Separate and related audits on TAHE are reported in 'State Finances 2022', 'State Finances 2021' and 'Transport and Infrastructure 2022' reports.

What we found

The design and implementation of TAHE, which spanned seven years, was not effective.

The process was not cohesive or transparent. It delivered an outcome that is unnecessarily complex in order to support an accounting treatment to meet the NSW Government's short-term Budget objectives, while creating an obligation for future governments.

The benefits of TAHE were claimed in the 2015–16 NSW Budget before the enabling legislation was passed by Parliament in 2017. This committed the agencies to implement a solution that justified the 2015–16 Budget impacts, regardless of any challenges that arose.

Rail safety arrangements were a priority throughout TAHE's design and implementation, and risks were raised and addressed.

Agencies relied heavily on consultants on matters related to the creation of TAHE, but failed to effectively manage these engagements. Agencies failed to ensure that consultancies delivered independent advice as an input to decision-making. A small number of firms were used repeatedly to provide advice on the same topic. The final cost of TAHE-related consultancies was $22.6 million compared to the initial estimated cost of $12.9 million.

What we recommended

We recommended that the audited agencies should:

  • improve accountability and transparency for major new fiscal transformation initiatives
  • ensure entities do not reflect the financial impact of significant initiatives in the Budget when there is uncertainty, or it creates perverse incentives
  • review record keeping practices, systems and policies to ensure compliance with the State Records Act 1998, and the NSW Government Information Classification, Labelling and Handling Guidelines
  • review procurement policies to ensure that consultant use complies with all NSW Government policy requirements.

The NSW Government established the Transport Asset Holding Entity (TAHE), a statutory State Owned Corporation (SOC), on 1 July 2020 to replace the former rail infrastructure owner – RailCorp. It is the State's custodian of rail network assets, including rail tracks and other infrastructure, rolling stock, land, train stations and facilities, retail space, and signal and power systems, within metropolitan and regional New South Wales. It is responsible for $2.8 billion of major capital projects in 2022–23.

TAHE was established under Part 2 of the Transport Administration Act 1988 and is governed by a decision-making board. The Treasurer and the Minister for Finance and Employee Relations are the Shareholding Ministers of TAHE, and they annually agree performance expectations articulated in a Statement of Corporate Intent.

Whereas TAHE is the custodian of rail assets, Sydney Trains and NSW Trains operate public rail services. TAHE does not have responsibility for the operation of the heavy rail network or train services, nor does it have network control functions. TAHE, Sydney Trains and NSW Trains are in the Transport and Infrastructure cluster in the public sector (formerly the Transport cluster and renamed in April 2022), which also includes Sydney Metro and Transport for NSW (TfNSW).

TfNSW leads the Transport and Infrastructure cluster. Its role is to set the strategic direction for transport across the State. This involves the shaping of planning, policy, strategy, regulation, resource allocation and other service and non-service delivery functions for all modes of transport.

TAHE's Operating Licence is granted by the Portfolio Minister and authorises the entity to perform the functions required to acquire, develop, finance, divest and hold assets, pursuant to the Transport Administration Act 1988. The Portfolio Minister also issues a Statement of Expectations which outlines the government’s expectation for the business for the next three to five years.

TAHE's original Portfolio Minister was the Minister for Transport who approved, on 30 June 2020, the issuing of an interim 12-month Operating Licence to enable TAHE to commence operating on 1 July 2020. The Portfolio Minister then granted TAHE's current Operating Licence in 2021. After TAHE requested a 12-month extension to its current Operating Licence, its next Operating Licence is due on 1 July 2024. The current Portfolio Minister is the Minister for Infrastructure, Cities and Active Transport.

About this audit

This audit assessed the effectiveness of NSW Government agencies' design and implementation of TAHE. In making this assessment, we considered whether: 

  • the process of designing and implementing TAHE was cohesive and transparent, and delivered an effective outcome
  • agencies' roles and responsibilities were clear in the planning of TAHE
  • agencies effectively identified and managed certain risks.

Conclusion

The design and implementation of TAHE was not effective. The process was not cohesive or transparent. It delivered an outcome that is unnecessarily complex in order to meet the NSW Government's short-term Budget objectives, while creating an obligation for future governments to sustain TAHE through continuing investment, and funding of the state owned rail operators. The ineffective process to design TAHE delivered a model that entails significant uncertainty as to whether the anticipated longer-term financial improvements to the Budget position can be achieved or sustained.

NSW Treasury and TfNSW had different objectives for TAHE

Up to June 2013, RailCorp had been the owner and operator of rail services and maintainer of the metropolitan rail network for almost a decade. It had been operating as a not-for-profit Public Non-Financial Corporation (PNFC).

In 2012, NSW Treasury (hereafter Treasury) decided there was a risk that the Australian Bureau of Statistics (ABS) would reclassify RailCorp to the General Government Sector (GGS), meaning depreciation expenses of approximately $870 million would be reflected in the GGS Budget. Treasury wanted to avoid this impact on the GGS Budget, and considered the establishment of a transport asset holding entity as a means to do so. Capital grants to RailCorp were being treated as an expense to the GGS Budget.

TfNSW also wanted an asset holding entity – but one that would be a non-trading ‘shell’ company with no staff that would hold and manage all public transport assets. TfNSW's concept envisaged the entity would have a structure that would enable future public transport reforms and strategic directions while ensuring vertical integration of operations between asset owners and the rail operators to maintain rail safety.

However, Treasury pursued its objective to improve the GGS Budget result, and sought to expand on TfNSW's 'shell' asset holding entity concept. Treasury wanted an entity that could generate a return on investment, as this meant that government investment in transport assets could be treated as equity investments, rather than a Budget expense, and in turn improve the GGS Budget position. As an example of the potential impact of creating this new entity, capital grants of $2.3 billion were paid to RailCorp in 2013–14. If Treasury's objective was met, grants of this significance would then be treated as an equity investment, rather than an expense in the GGS Budget.

In 2017, Treasury's preferred option was progressed through legislation, but both agencies' central objectives for the proposed asset holding entity would continue to prove difficult to reconcile. To achieve Treasury's objective to improve the Budget result, the entity would need to generate a return on investment (this is further discussed below). However, TfNSW expressed concerns that the prioritisation of rail safety, and the effective management of governance, regulation and operations would be more complex in an entity with commercial imperatives.

Asset holding entities are a common approach to the management of transport assets in Australia and internationally, and there are a range of approaches to how they are structured and used. Such structures should be driven by the goal of improved asset management. Ultimately, TfNSW's objectives could have been delivered through a simpler entity structure. However, reconciling TfNSW's objectives with Treasury's imperative to deliver and justify a Budget improvement in the short-term resulted in an overly lengthy process and an unnecessarily complex outcome that places an obligation on future governments to sustain. There is still significant uncertainty as to whether the short-term improvements to the Budget can continue to be realised in the longer-term.

The Budget benefits of TAHE were claimed before the entity was legislated, committing the agencies to deliver, regardless of the complexities that subsequently arose

The 2015–16 GGS Budget treated the government's investment in TAHE (still known at this time as RailCorp) as an equity contribution. This had the immediate impact of improving the Budget result by $1.8 billion per annum. However, the legislation to enable the establishment of TAHE had not yet been passed by Parliament, key elements of the operating model were still under development, and imminent changes in accounting standards had the potential to impact TAHE's financial model. The decision to book the benefits in the Budget early committed the involved agencies to implement a solution that justified the 2015–16 Budget impacts, irrespective of the challenges that arose. 

TAHE's financial structure requires circular government investment to work

For the NSW Government to continue to treat its investment in TAHE as an equity contribution, rather than an expense to the Budget, there must be a reasonable expectation that TAHE will generate a sufficient rate of return as required by the Government Finance Statistics (GFS) framework. In doing so, it needs to recover a revaluation loss created by a $20.3 billion reduction in the value of its assets which was incurred in its first full year of operation. This loss occurred as a result of a revaluation of TAHE's assets when RailCorp (a not-for profit entity) became TAHE (a for-profit commercial entity) – and is discussed further in the 'Key findings' below.

TAHE generates a small portion of its income from transactions with the private sector but, as noted in our report 'State Finances 2021', TAHE receives the majority of its revenue (more than 80%) from access and licence fee agreements with Sydney Trains and NSW Trains. Both of these entities are funded by grants (a Budget expense) to TfNSW from the GGS Budget.

Based on Treasury’s correspondence with the ABS in 2015, TAHE was initially expected to pay a return on equity of 7% in 2016–17. The assumption of a 7% return persisted through to 2018, after the legislation enabling the establishment of TAHE was passed by Parliament. However, when the initial access and licence fees were agreed on 1 July 2020, this figure had been revised to an expected rate of return of 1.5% excluding the revaluation loss. This was below the long-term inflation target and did not include the recovery of the revaluation loss – risking the government's ability to treat its investment in TAHE as an equity contribution. Importantly, as TAHE is primarily reliant on fees paid by the state owned rail operators that, in turn, are funded by the GGS Budget (as an expense), the decision to change the returns model from 7% to 1.5% would in its own right have had a positive impact on the GGS Budget. However, the decision to use a 1.5% return would ultimately be problematic as it made it difficult to treat the government's contributions to TAHE as an equity investment, as discussed below.

On 14 December 2021, to avoid a qualified audit opinion, the NSW Government made the decision to increase TAHE's expected rate of return to 2.5%, equal to the Reserve Bank’s long-term inflation target.

In 2021-22, TAHE needed to start charging rail operators higher access and licence fees in order to generate a return of 2.5%, so as to support the government's treatment of its investment in TAHE as an equity contribution in the GGS Budget. This meant the government needed to provide additional grant (expense) funding to the state owned rail operators so they could pay the increased access and licence fees to TAHE. Based on current projections, TAHE is not expected to recover the revaluation loss until 2046.

There remains a risk that TAHE will not be able to generate a sufficient return on the NSW Government's investment without relying on increased funding to state owned rail operators so that they can in turn pay the higher access and licence fees. TAHE's ability to generate returns on government investment from other sources are uncertain and may not be achievable or sustainable. Current modelling highlights that TAHE remains largely reliant, through to 2046, on increasing fees (which are assumed to increase at 2.5% per annum from 2031 onwards when the current 10 year contracts with rail operators expire) paid by the state owned rail operators that remain principally reliant on GGS Budget grants.

The process of designing and implementing TAHE was not transparent to independent scrutiny

Our report 'State Finances 2021' commented that Treasury did not always provide this Office with information relating to TAHE on a timely basis. Similarly, during this performance audit, there were also multiple instances where auditees were unable to provide documentation regarding key activities in the process to deliver TAHE. Agencies also applied higher sensitivity classifications to large tranches of documents than was justified or required by policy. Of particular concern is the incorrect classification of documents as Cabinet sensitive information. The incorrect or over-classification of documentation as Cabinet sensitive delayed this Office's ability to provide scrutiny or independent assurance.

There was a lack of clarity around the roles and responsibilities of governance structures set up to oversee the design and implementation of TAHE

From 2014, multiple workstreams and advisory committees were established to progress the design and implementation of TAHE. For some of these committees and workstreams, there is limited information on what they were tasked to do and what they achieved. Most had ceased meeting by 2018, before significant work needed to deliver TAHE was completed.

The lack of clarity around the roles and responsibilities of these governance structures reduced opportunities for TfNSW and Treasury to reconcile their differing objectives for TAHE, and resolve key questions earlier in the process.

There was a heavy reliance on consulting firms throughout the process to establish TAHE, and the management of consultant engagements failed to ensure that agencies received independent advice to support objective decision-making

In 2020, Treasury and TfNSW failed to prevent, identify, or adequately manage a conflict of interest when they engaged the same 'Big 4' consulting firm to work on separate TAHE-related projects. Both agencies used the firm's work to further their respective views with regard to the financial implications of TAHE's operating model. At this time those views were still unreconciled.

Treasury engaged the firm to provide a fiscal risk management strategy and advice on the impact of changes to accounting standards. TfNSW engaged the same firm to develop operating and financial models for TAHE, which raised concerns regarding the viability of TAHE. Disputes arose around the findings of these reports. Treasury disagreed with some of the outcomes of the work commissioned by TfNSW, relating to accounting treatment and fiscal advice.

The management of this conflict (real or perceived) was left to the 'Big 4' consulting firm when it was more appropriate for it to be managed by Treasury and TfNSW. If these agencies had communicated more effectively, used available governance structures consistently, and shared information openly about their use of the firm and the nature of their respective engagements, these disputes might have been avoided. This issue, coupled with deficiencies in procurement by both agencies, reflected and further perpetuated the lack of cohesion in the design and implementation of TAHE.

More broadly, over the period 2014 – 2021, 16 separate consulting firms were employed to work on 36 contracts, valued at over $22.56 million, relating to TAHE ranging from accounting and legal advice, project management, and the provision of administrative support and secretariat services.

Consultants are legitimately used by agencies to provide advice on how to achieve the outcomes determined by government, including advising agencies on the risks and challenges in achieving those outcomes. Similarly, consultants can provide expert knowledge in the service of achieving those outcomes and managing the risks. However, the heavy reliance on consulting firms during the design and implementation of TAHE heightened the risk that agencies were not receiving value for money, were outsourcing tasks that should be performed by the public service, and did not mitigate the risk that the advice received was not objective and impartial. The risk that the role of consultants could have been blurred between providing independent advice to government on options and facilitating a pre-determined outcome was not effectively treated or mitigated. This risk was amplified because a small number of firms were used repeatedly to provide advice on one topic. The effective procurement and management of consultants is an obligation of government agencies.

Appendix one – Responses from audited agencies, and Audit Office clarification of matters raised in the TAHE formal response 

Appendix two – Classification of government entities 

Appendix three – About the audit 

Appendix four – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #372 - released 24 January 2023

 

Published

Actions for Transport and Infrastructure 2022

Transport and Infrastructure 2022

Transport
Asset valuation
Financial reporting
Information technology
Infrastructure
Management and administration
Procurement

What the report is about

Result of the Transport and Infrastructure cluster agencies' financial statement audits for the year ended 30 June 2022.

What we found

Unmodified audit opinions were issued for all Transport and Infrastructure cluster agencies' financial statements.

An 'other matter' paragraph was included in TAHE's Independent Auditor's Report for its 30 June 2022 financial statements which draws attention to Transport and Asset Holding Entity's (TAHE) reliance on government-funded customers.

We included an ‘emphasis of matter’ paragraph in the Independent Auditor’s Report for State Transit Authority of New South Wales’ (the authority) 30 June 2022 financial statements, which draws attention to the financial statements being prepared on a liquidation basis as the authority’s principal activities ceased operations on 3 April 2022.

What the key issues were

The 2021–22 audits identified five high-risk findings:

  • detailed business modelling to support returns from TAHE
  • valuation of assets at TAHE
  • control of assets at TAHE
  • accounting and valuation of tree assets at Centennial Park and Moore Park Trust and Parramatta Park Trust.

Access and licence fees - TAHE

Revised commercial agreements were signed between TAHE, the operators and Transport for NSW on 23 June 2022 to reflect increased access and licence fees detailed in the 18 December 2021 Heads of Agreement.

TAHE’s ability to generate the expected return of 2.5% based on the current modelling is heavily reliant on the government funding the public rail operators (TAHE's customers).

There are risks that:

  • TAHE will not be able to recontract for access and licence fees at a level that is consistent with current projections
  • future governments' funding to TAHE's key customers will not be sufficient to fund payment of access and licence fees at a level that is consistent with current projections
  • TAHE will be unable to grow its non-government revenues.

Valuation of assets - TAHE

Although TAHE's selected valuation of assets falls within an acceptable range, there remains a significant gap between what has been assessed as an acceptable range and TAHE's range.

What we recommended

Control of assets - TAHE

While we accepted TAHE’s position on control for the current year, NSW Treasury and TAHE should continue to monitor the risk that control of TAHE assets could change in future reporting periods. TAHE must continue to demonstrate control of its assets or the current accounting presentation would need to be reconsidered.

This report provides Parliament and other users of the Transport and Infrastructure cluster’s financial statements with the results of our audits, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision-making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Transport and Infrastructure cluster (the cluster) for 2022.

Section highlights

  • Unqualified audit opinions were issued on all Transport and Infrastructure cluster agencies' financial statements.
  • An 'Other Matter' paragraph was included in the Transport Asset Holding Entity of New South Wales' (TAHE) Independent Auditor's Report to draw attention to TAHE's reliance on government-funded customers.
  •  An 'Emphasis of Matter' paragraph was included in the State Transit Authority of New South Wales' (the authority) Independent Auditor's Report to draw attention to management’s disclosures that State Transit Authority of New South Wales' financial statements for the year ended 30 June 2022 were prepared on a liquidation basis as the authority’s principal activities ceased operations on 3 April 2022.
  • While TAHE's valuation of assets at 30 June 2022 was within an acceptable range of valuation outcomes, there remained significant differences in assumptions used when compared with relevant market benchmarks.
  • Sydney Metro corrected two prior period errors of $1.5 billion and $51 million in accounting and valuation of assets, and double counting of assets capitalised in infrastructure as well as assets under construction respectively.

 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision-making.

This chapter outlines our observations and insights from our financial statement audits of agencies in the cluster.

Section highlights

  • The number of findings reported to management decreased from 87 in 2020–21 to 59 in 2021–22.
  • Repeat findings accounted for 54.2% of management letter points. Many repeat findings related to controls over payroll, including management of annual leave and processing of timesheets, management of conflicts of interests, weaknesses in controls over information technology user access administration and password management.
  • One new high-risk issue was identified in 2020–21, and four high-risk repeat issues remained.
  • The five high-risk issues arose from the audit in the cluster, with respect to:
    • control over TAHE assets and operations (repeat)
    • TAHE detailed business modelling to support returns (repeat)
    • valuation of trees (repeat for Parramatta Park Trust and Centennial Park and Moore Park Trust)
    • TAHE asset valuations.

 

Appendix one – Misstatements in financial statements submitted for audit

Appendix two – Early close procedures

Appendix three – Timeliness of financial reporting

Appendix four – Financial data

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Audit Insights 2018-2022

Audit Insights 2018-2022

Community Services
Education
Environment
Finance
Health
Industry
Justice
Local Government
Premier and Cabinet
Planning
Transport
Treasury
Universities
Whole of Government
Asset valuation
Cross-agency collaboration
Compliance
Cyber security
Financial reporting
Fraud
Information technology
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Regulation
Risk
Service delivery
Shared services and collaboration
Workforce and capability

What the report is about

In this report, we have analysed the key findings and recommendations from our audit reports over the past four years.

This analysis includes financial audits, performance audits, and compliance audits of state and local government entities that were tabled in NSW Parliament between July 2018 and February 2022.

The report is framed by recognition that the past four years have seen significant challenges and emergency events.

The scale of government responses to these events has been wide-ranging, involving emergency response coordination, service delivery, governance and policy.

The report is a resource to support public sector agencies and local government to improve future programs and activities.

What we found

Our analysis of findings and recommendations is structured around six key themes:

  • Integrity and transparency
  • Performance and monitoring
  • Governance and oversight
  • Cyber security and data
  • System planning for disruption
  • Resource management.

The report draws from this analysis to present recommendations for elements of good practice that government agencies should consider in relation to these themes. It also includes relevant examples from recent audit reports.

In this report we particularly call out threats to the integrity of government systems, processes and governance arrangements.

The report highlights the need for balanced advice to government on options and risks, for transparent documentation and reporting of directions and decisions, and for early and open sharing of information with integrity bodies and audit.

A number of the matters highlighted in this report are similar to those described in our previous Insights Report, (Performance Audit Insights: key findings from 2014–2018) specifically in relation to cyber and information security, to performance measurement, reporting and evaluation, and system and workforce planning and capability.

Fast facts

  • 72 audits included in the Audit Insights 2018–2022 analysis
  • 4 years of audits tabled by the Auditor-General for New South Wales
  • 6 key themes for Audit Insights 2018–2022.

picture of Margaret Crawford Auditor-General for New South Wales in black dress with city skyline as backgroundI am pleased to present the Audit Insights 2018–2022 report. This report describes key findings, trends and lessons learned from the last four years of audit. It seeks to inform the New South Wales Parliament of key risks identified and to provide insights and suggestions to the agencies we audit to improve performance across the public sector.

The report is framed by a very clear recognition that governments have been responding to significant events, in number, character and scale, over recent years. Further, it acknowledges that public servants at both state and council levels generally bring their best selves to work and diligently strive to deliver great outcomes for citizens and communities. The role of audit in this context is to provide necessary assurance over government spending, programs and services, and make suggestions for continuous improvement.

A number of the matters highlighted in this report are similar to those described in our previous Insights Report, (Performance Audit Insights: key findings from 2014–2018) specifically in relation to cyber and information security, to performance measurement, reporting and evaluation, and system and workforce planning and capability.

However, in this report we particularly call out threats to the integrity of government systems, processes and governance arrangements. We highlight the need for balanced advice to government on options and risks, for transparent documentation and reporting of directions and decisions, and for early and open sharing of information with integrity bodies and audit. Arguably, these considerations are never more important than in an increasingly complex environment and in the face of significant emergency events and they will be key areas of focus in our future audit program.

While we have acknowledged the challenges of the last few years have required rapid responses to address the short-term impacts of emergency events, there is much to be learned to improve future programs. I trust that the insights developed in this report provide a helpful resource to public sector agencies and local government across New South Wales. I would be pleased to receive any feedback you may wish to offer.

Margaret Crawford
Auditor-General for New South Wales

Integrity and transparency Performance and monitoring Governance and oversight Cyber security and data System planning Resource management
Insufficient documentation of decisions reduces the ability to identify, or rule out, misconduct or corruption. Failure to apply lessons learned risks mistakes being repeated and undermines future decisions on the use of public funds. The control environment should be risk-based and keep pace with changes in the quantum and diversity of agency work. Building effective cyber resilience requires leadership and committed executive management, along with dedicated resourcing to build improvements in cyber security and culture. Priorities to meet forecast demand should incorporate regular assessment of need and any emerging risks or trends. Absence of an overarching strategy to guide decision-making results in project-by-project decisions lacking coordination. Governments must weigh up the cost of reliance on consultants at the expense of internal capability, and actively manage contracts and conflicts of interest.
Government entities should report to the public at both system and project level for transparency and accountability. Government activities benefit from a clear statement of objectives and associated performance measures to support systematic monitoring and reporting on outcomes and impact. Management of risk should include mechanisms to escalate risks, and action plans to mitigate risks with effective controls. In implementing strategies to mitigate cyber risk, agencies must set target cyber maturity levels, and document their acceptance of cyber risks consistent with their risk appetite. Service planning should establish future service offerings and service levels relative to current capacity, address risks to avoid or mitigate disruption of business and service delivery, and coordinate across other relevant plans and stakeholders. Negotiations on outsourced services and major transactions must maintain focus on integrity and seeking value for public funds.
Entities must provide balanced advice to decision-makers on the benefits and risks of investments. Benefits realisation should identify responsibility for benefits management, set baselines and targets for benefits, review during delivery, and evaluate costs and benefits post-delivery. Active review of policies and procedures in line with current business activities supports more effective risk management. Governments hold repositories of valuable data and data capabilities that should be leveraged and shared across government and non-government entities to improve strategic planning and forecasting. Formal structures and systems to facilitate coordination between agencies is critical to more efficient allocation of resources and to facilitate a timely response to unexpected events. Transformation programs can be improved by resourcing a program management office.
Clear guidelines and transparency of decisions are critical in distributing grant funding. Quality assurance should underpin key inputs that support performance monitoring and accounting judgements. Governance arrangements can enable input into key decisions from both government and non-government partners, and those with direct experience of complex issues.     Workforce planning should consider service continuity and ensure that specialist and targeted roles can be resourced and allocated to meet community need.
Governments must ensure timely and complete provision of information to support governance, integrity and audit processes.          
Read more Read more Read more Read more Read more Read more

 

This report brings together a summary of key findings arising from NSW Audit Office reports tabled in the New South Wales Parliament between July 2018 and February 2022. This includes analysis of financial audits, performance audits, and compliance audits tabled over this period.

  • Financial audits provide an independent opinion on the financial statements of NSW Government entities, universities and councils and identify whether they comply with accounting standards, relevant laws, regulations, and government directions.
  • Performance audits determine whether government entities carry out their activities effectively, are doing so economically and efficiently, and in accordance with relevant laws. The activities examined by a performance audit may include a selected program or service, all or part of an entity, or more than one government entity. Performance audits can consider issues which affect the whole state and/or the local government sectors.
  • Compliance audits and other assurance reviews are audits that assess whether specific legislation, directions, and regulations have been adhered to.

This report follows our earlier edition titled 'Performance Audit Insights: key findings from 2014–2018'. That report sought to highlight issues and themes emerging from performance audit findings, and to share lessons common across government. In this report, we have analysed the key findings and recommendations from our reports over the past four years. The full list of reports is included in Appendix 1. The analysis included findings and recommendations from 58 performance audits, as well as selected financial and compliance reports tabled between July 2018 and February 2022. The number of recommendations and key findings made across different areas of activity and the top issues are summarised at Exhibit 1.

The past four years have seen unprecedented challenges and several emergency events, and the scale of government responses to these events has been wide-ranging involving emergency response coordination, service delivery, governance and policy. While these emergencies are having a significant impact today, they are also likely to continue to have an impact into the future. There is much to learn from the response to those events that will help the government sector to prepare for and respond to future disruption. The following chapters bring together our recommendations for core elements of good practice across a number of areas of government activity, along with relevant examples from recent audit reports.

This 'Audit Insights 2018–2022' report does not make comparative analysis of trends in public sector performance since our 2018 Insights report, but instead highlights areas where government continues to face challenges, as well as new issues that our audits have identified since our 2018 report. We will continue to use the findings of our Insights analysis to shape our future audit priorities, in line with our purpose to help Parliament hold government accountable for its use of public resources in New South Wales.

Appendix one – Included reports, 2018–2022

Appendix two – About this report

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Transport 2021

Transport 2021

Transport
Asset valuation
Compliance
Financial reporting
Information technology
Infrastructure
Internal controls and governance

What the report is about

The results of the Transport cluster agencies’ financial statement audits for the year ended 30 June 2021.

What we found

Unmodified financial statement audit opinions were issued for all Transport cluster agencies. Resolution of issues delayed signing the Transport Asset Holding Entity of NSW (TAHE) until 24 December 2021. Matters relating to TAHE are also reported in the report on State Finances 2021.

Emphasis of Matter - TAHE

An Emphasis of Matter paragraph was included in TAHE's audit opinion to draw attention to uncertainty associated with:

  • future access and licence fees that are subject to re-signed agreements
  • an additional $4.1 billion of funding that is outside the forward estimates period
  • a significant portion of the fair value of TAHE’s non-financial assets is reflected in the terminal value, which is outside the ten-year contract period to 30 June 2031, and the risk that TAHE will not be able to negotiate contract terms to support current projections.

TAHE's transition from RailCorp also changed its valuation of assets to an income approach, resulting in a $20.3 billion decrease to the fair value. The fair value decrease was because the cash flows were not sufficient to support the previous recorded value.

TAHE corrected a misstatement of $1.2 billion relating to the valuation of its assets. This followed significant deliberation on key judgements and assumptions, with TAHE adopting risk assumptions in its valuation that were not in line with comparable benchmarks.

Emphasis of Matter - State Transit Authority of New South Wales

An Emphasis of Matter paragraph was included in the State Transit Authority of NSW's (the Authority) audit opinion to draw attention to the financial statements not prepared on a going concern basis. This was because the NSW Government put the Authority's bus contracts out to competitive tender and accordingly, management assessed the Authority's principal activities are not expected to operate for a full 12 months after 30 June 2021.

The implementation of AASB 1059 ‘Service Concession Arrangements: Grantors’ resulted in a net increase in assets of $23.5 billion across the Transport cluster.

The 2020–21 audits identified six high-risk and 45 moderate risk issues across the cluster. Fourteen of the moderate risk issues were repeat issues, including information technology controls around management of user access for key financial systems and payroll processes.

The high-risk issues, in addition to those related to TAHE and previously reported in the report on State Finances 2021, include:

  • absence of conflict of declarations related to land acquisition processes at Transport for NSW
  • no evidence of conflict of interest declarations obtained by TAHE from consultants and contractors regarding involvement in other engagements.

What we recommended

TAHE needs to:

  • finalise revised commercial agreements to reflect fees detailed in a Heads of Agreement signed on 18 December 2021
  • prepare robust projections and business plans to support the required rate of return.

NSW Treasury and TAHE should monitor the risk that control of TAHE assets could change in the future.

Transport for NSW needs to significantly improve its processes to ensure all key information is identified and shared with the Audit Office.

Transport agencies should implement a process to ensure conflicts of interest declarations are completed for land acquisitions and applied consistently across the cluster.

Transport agencies should implement a process to capture all contracts and agreements entered to ensure:

  • agencies are aware of contractual obligations
  • financial reporting implications are assessed, particularly with respect to leases, revenue and service concession arrangements.

Fast facts

The Transport cluster plans and delivers infrastructure and integrated services across all modes of transport. This includes road, rail, bus, ferry, light rail, cycling and walking. There are 11 agencies in the cluster.

  • $128b road and maritime system infrastructure assets as at 30 June 2021
  • 100% unqualified audit opinions were issued on agencies 30 June 2021 financial statements
  • 26 monetary misstatements were reported in 2020–21
  • $24.9b rail systems infrastructure assets as at 30 June 2021
  • high-risk management letter findings were identified
  • 37% of reported issues were repeat issues

 

This report provides Parliament and other users of the transport cluster (the cluster) agencies’ financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the cluster for 2021.

Section highlights

  • Unqualified audit opinions were issued on all Transport agencies' financial statements.
  • An 'Emphasis of Matter' paragraph was included in the Transport Asset Holding Entity of New South Wales' (TAHE) Independent Auditor's Report to draw attention to significant uncertainty associated with the judgements, estimates and assumptions supporting the valuation of TAHE’s property, plant and equipment (PPE) and intangible assets.
  • In 2020–21, the former RailCorp transitioned to TAHE, a for-profit state-owned corporation. When TAHE became a for-profit entity, it was required to change its valuation approach. The value of a for-profit entity's assets cannot exceed the cash flows they might realise either through their sale or continued use. This change in the basis of valuation resulted in a decrease of $20.3 billion in the fair value of the assets. The decrease in fair value was because the cash flows, which support measurement under the income approach, were insufficient to support the previous valuation based on the current replacement cost of those assets.
  • TAHE also corrected a misstatement of $1.2 billion relating to the valuation of its assets after significant deliberation on key judgements and assumptions, with TAHE adopting higher risk assumptions in its valuation when compared to the relevant market benchmarks.
  • On 18 December 2021, a Heads of Agreement (HoA) was signed between TAHE, Transport for NSW, Sydney Trains and NSW Trains. This HoA reflected TAHE's intention to negotiate higher access and licence fees in order to meet the shareholding ministers' revised expectation of a higher rate of return. This matter resolved the treatment of a significant accounting issue in the State’s consolidated (whole-of-government) financial statements. Refer to the Report on State Finances tabled on 9 February 2022. The expectation of an additional $5.2 billion in fees added to the valuation of TAHE's PPE and intangibles, with a final value of $17.15 billion.
  • The implementation of AASB 1059 ‘Service Concession Arrangements: Grantors’ resulted in a net increase in assets of $23.5 billion across the cluster. AASB 1059 had a significant impact on Transport for NSW, Sydney Metro, Sydney Ferries and TAHE's 2020–21 financial statements.
  • TAHE corrected a misstatement of $97.2 million relating to the application of AASB 1059 'Service Concession Arrangements: Grantors' for the Airport Link Company Contract. 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our observations and insights from our financial statement audits of agencies in the cluster.

Section highlights

  • The number of findings reported to management increased from 56 in 2019–20 to 73 in 2020–21.
  • Thirty-seven per cent were repeat findings. Many repeat issues related to information technology controls around user access management and payroll processes. These included deficiencies in the monitoring of privileged user access to key financial systems, review of user access to key financial systems and segregation of duties between preparer and reviewer for new employee hires.
  • Six new high-risk issues were identified in 2020–21, an increase of three compared to last year.
  • One high-risk issue related to conflicts of interests not being declared by all officers involved in the land acquisition process at Transport for NSW.
  • Five high-risk issues arose from the audit of TAHE, with respect to:
    • control over TAHE assets and operations
    • asset valuations
    • access price build up
    • detailed business modelling to support returns
    • conflict of interest management.
  • Based on the access and licence agreements signed at 30 June 2021 between TAHE, Sydney Trains and NSW Trains, our review of the expected returns calculated by NSW Treasury did not support the assumption that there was a reasonable expectation that a sufficient rate of return could be achieved from the NSW Government's investment in TAHE.
  • On 14 December 2021 the shareholding ministers' increased their expectations as to TAHE's target average return from 1.5 per cent to the expected long-term inflation rate of 2.5 per cent.
  • On 18 December 2021 the revised shareholder expectations were confirmed in a signed Heads of Agreement. The Heads of Agreement will increase access fees paid by rail operators to TAHE by $5.2 billion.
  • TAHE's access and licence agreements specified fees that were well short of the IPART regulated maximum (ceiling price).
  • The finalisation of the access and licence agreements with Sydney Trains and NSW Trains resulted in a significant write-down of TAHE's asset value by $20.3 billion. The revaluation loss will need to be recovered as part of the shareholders’ rate of return of 2.5 per cent in order to sustain the whole-of-government accounting treatment of cash contributions recorded as an equity contribution and not a grant expense.
  • There was a significant adjustment to TAHE’s valuation between the financial statements originally submitted for the audit and the final, signed financial statements due to differences in risk assumptions resulting in a correction of a $1.2 billion misstatement. 

Findings reported to management

The number of findings reported to management has increased, and 37 per cent of all issues were repeat issues

Breakdowns and weaknesses in internal controls increase the risk of fraud and error. Deficiencies in internal controls, matters of governance interest and unresolved issues were reported to management and those charged with governance of agencies. The Audit Office does this through management letters, which include observations, related implications, recommendations and risk ratings.

In 2020–21, there were 73 findings raised across the cluster (56 in 2019–20) and 37 per cent of all issues were repeat issues (43 per cent in 2019–20).

In view of the recent performance audit ‘Managing Cyber Risks’ and compliance audit ‘Compliance with the NSW Cyber Security Policy’ involving the cluster, it is noted with concern that the most common repeat issues related to weaknesses in controls over information technology user access administration and password management. Moderate risk issues included completeness and accuracy of contract registers, accounting for assets and management of supplier and payroll masterfiles.

A delay in implementing audit recommendations increases the risk of intentional and accidental errors in processing information, producing management reports, and generating financial statements. This can impair decision-making, affect service delivery and expose agencies to fraud, financial loss and reputational damage. Control deficiencies may also mean agency staff are less likely to follow internal policies, inadvertently causing the agency not to comply with legislation, regulation, and central agency policies.

The table below describes the common issues identified across the cluster by category and risk rating. 

Risk rating Issue
Information technology
Moderate: 7 new, 4 repeat**

The financial audits identified opportunities for agencies to improve information technology processes and controls that support the integrity of financial data used to prepare agencies' financial statements. Of particular concern are issues associated with:

  • monitoring of privileged user access
  • user access management
  • password configuration management.
Low: 4 new, 1 repeat***
Internal control deficiencies or improvements
High: 1 new*

The financial audits identified internal control deficiencies across key business processes, including:

  • declarations of conflicts of interest over land acquisitions (see further details below)
  • management of contracts and agreement register
  • accounting for assets
  • management of payroll and supplier masterfiles
  • payroll processes.
Moderate: 15 new, 8 repeat**
Low: 2 new, 5 repeat***
Financial reporting
High: 3 new*

The financial audits identified opportunities for agencies to strengthen financial reporting, including:

  • asset valuations (see further details below)
  • detailed business modelling to support returns (see further details below)
  • access price build-up (see further details below)
  • timely capitalisation of completed assets.
Moderate: 3 new, 1 repeat**
Low: 2 new***
Governance and oversight
High: 1 new*

The financial audits identified opportunities for agencies to improve governance and oversight processes, including:

  • control over TAHE assets and operations
  • governance over Cyber Security.
Moderate: 2 new**
Non-compliance with key legislation and/or central agency policies
High: 1 new*

The financial audits identified the need for agencies to improve its compliance with key legislation and central agency policies, including:

  • conflict of interest (COI) management
  • outdated policies and procedures
  • incomplete probation procedures.
Moderate: 4 new, 1 repeat**
Low: 1 new, 7 repeat***

* High-risk from the consequence and/or likelihood of an event that has had, or may have a negative impact on the entity.
** Moderate risk from the consequence and/or likelihood of an event that has had, or may have a negative impact on the entity.
*** Low risk from the consequence and/or likelihood of an event that has had, or may have a negative impact on the entity.
Note: Management letter findings are based either on final management letters issued to agencies.

2020–21 audits identified six high-risk findings

High-risk findings were reported at the following cluster agencies.

Agency Description
2020–21 findings
Transport for NSW (new finding)

Declaration of conflicts of interest in the land acquisition process

In 2021, we conducted a performance audit over the Acquisition of 4–6 Grand Avenue, Camellia which examined:

  • whether Transport for NSW conducted an effective process to purchase 4–6 Grand Avenue, Camellia
  • whether Transport for NSW has effective processes and procedures to identify and acquire property required to deliver the NSW Government’s major infrastructure projects.

The report made several recommendations over Transport for NSW’s internal policies and procedures to guide the land acquisition process. As part of the financial audit, we obtained an understanding of key controls and processes relating to the acquisition of land, relevant to the audit of the financial statements. We found that conflicts of interests were not always declared by all officers involved in the land acquisition process. Furthermore, processes for declaring conflicts of interests are not consistently applied across cluster agencies.

Out of a sample of 19 land acquisitions tested, we identified:

  • 14 instances where there was no evidence of declarations of conflicts of interests made by the team members involved in the acquisition process
  • 2 instances where conflicts of interest declarations were completed by key members of the acquisition team only at a project level
  • 1 instance where conflicts of interest declarations were only completed by the property negotiator and the valuer, but not the other members of the acquisition team.

Management advised that the land acquisition processes, at the time of the land acquisitions, did not require formal conflicts of interests to be declared as they believe that as per Transport for NSW code of conduct, declaration is only required where the staff member considers that a potential or perceived Conflict of Interest exists. However, Transport for NSW's Procurement Policy requires the documentation of formal declarations from all staff involved in procurement activities to formally disclose any conflicts of interest or state that they do not have a conflict of interest.

This matter has been included as a high-risk finding in the management letter as absence of rigorous and consistent management of conflicts of interests, and non-compliance with established policies increases the risk that Transport for NSW may be exposed to reputational damage or financial losses in relation to land acquisitions. Furthermore, this may result in lack of probity or value-for money considerations during the land acquisition process.

Further details are elaborated below under 'Land acquisitions'.

Transport Asset Holding Entity of New South Wales (new finding)

Control over TAHE assets and operations

The State-Owned Corporations Act 1989 maintains that all decisions relating to the operation of a statutory state-owned corporation (SOC) are to be made by or under the authority of the board. However, under the Transport Administration Act 1988 (TAA), the functions of TAHE may only be exercised under one or more operating licences issued by the portfolio minister. The current Operating Licence confers terms and conditions for TAHE to carry out its functions, and imposes constraints on TAHE, including (but not limited to):

  • railway operations not permitted
  • transport services not permitted
  • TAHE must not carry out maintenance of its assets.

Such operating licences are short term in nature, and the TAA allows the transport minister (portfolio minister) to grant one or more operating licences to TAHE and may amend, substitute, or impose, amend or revoke conditions of the operating licence.

For the current year, the legal form of the arrangements established in its first year of operation imply TAHE has control over the assets based on the Implementation Deed and the agreements signed with the public operators.

However, risks remain as TAHE is in its early stages, and the actual substance of operations will need to be observed and considered.

Given the restrictions that can be placed on the entity through the Operating Licence, and the ability to make further changes to the Operating Licence and Statement of Expectations set by the portfolio minister, there is a risk there could be limitations placed on the Board of Directors to operate with sufficient independence in its decision-making with respect to the operations of TAHE. Over time, this may further impact the degree of control required by TAHE to satisfy the recognition criteria over its assets. It may also fundamentally change the presentation of TAHE’s financial statements.

Future limitations to the degree of control TAHE, and its Board, can exercise over its functions may impact the degree of control TAHE has over its assets going forward. As part of the 2021–22 audit, we will monitor and assess whether, in substance, these assets continue to be controlled by TAHE and whether, in substance, TAHE can operate as an independent SOC. We require management continue to demonstrate that TAHE continues to maintain control over its assets and has the ability to operate as an independent SOC. Further details are described below under 'Transport Asset Holding Entity'.

Transport Asset Holding Entity of New South Wales (new finding)

Asset valuation

The final updated valuation was based on cash flows that were in a signed Heads of Agreement, which stated that it set out the proposed indicative future access and licence fees which will form the basis of the negotiations between TAHE, Transport for NSW, Sydney Trains and NSW Trains, who will work together to review access fees and licence fees payable under the agreements and to make all necessary changes to the Operating Agreements by 1 July 2022.

This adds uncertainty in the cash flows. It is crucial that TAHE formalises these updated fees in legally binding signed access and licence agreements with the relevant parties as soon as possible.

Refer below for further details on the Heads of Agreement.

Transport Asset Holding Entity of New South Wales (new finding)

Conflict of interest (COI) management

For procurement transactions through direct negotiation with single quotes, there was no evidence of COI declarations obtained from the consultants and contractors regarding involvement in other engagements. Contractors and consultants are required to declare actual COI. However, there was no requirement to confirm nil conflict of interest. In addition, there is a risk that perceived COI may not be adequately assessed or managed. TAHE is expected to operate as an independent SOC and would need to ensure any perceived or actual conflict of interest is adequately addressed.

Management should implement a process to:

  • ensure conflicts of interest declarations are completed when engaging all consultants and contractors (including involvement with other engagements and confirmation of nil conflicts of interests)
  • ensure probity is undertaken to identify any actual or perceived conflicts of interest.

The declarations should consider individuals and relationships that may create, or may be perceived to create, conflicts of interest.

Transport Asset Holding Entity of New South Wales (new finding)

Detailed business modelling to support returns

On 18 December 2021, Transport for NSW, TAHE and the operators, Sydney Trains and NSW Trains entered into a Heads of Agreement (HoA). This HoA forms the basis of negotiations to revise the pricing within the existing 10-year contracts and deliver upon the shareholders' expectation of a return of 2.5 per cent per annum of contributed equity, including recovering the revaluation loss incurred in 2020–21.

TAHE needs to revise its business plan and include detailed business modelling that supports the shareholding ministers' revised expectations of return (2.5 per cent return on the State’s equity injections and recovery of the write-down of assets over the average useful life of those assets) and align the business plan and Statement of Corporate Intent. This requires more detailed projections, estimates and plans that support how TAHE expects to recover the asset write-down and expected returns to government. The current modelling for ten years needs to be enhanced with modelling over the expected recovery period of approximately 33 years.

Transport Asset Holding Entity of New South Wales (new finding)

Access price build-up

Management explained that in determining access and licence fees for the agreements with Sydney Trains and NSW Trains, assets prior to the commencement of equity injections in 2015–16 were excluded from the calculations. Management explained the premise being that these assets were previously funded by government through capital grants. The replacement and refurbishment of these assets is expected to be through government funded maintenance performed through the public rail operators and/or the equity injections from NSW Treasury rather than through access and licence fees.


The number of moderate risk findings increased from prior year

Forty-five moderate risk findings were reported in 2020–21, representing a 73.1 per cent increase from 2019–20. Of these, 14 were repeat findings, and 31 were new issues. 

Key moderate risk findings related to:

  • weaknesses in user access management to key financial systems
  • management of contracts and agreements register
  • management of supplier and payroll masterfiles
  • accounting for assets
  • control deficiencies at service organisations
  • segregation of duties relating to the hiring of employees
  • conflict of interest management
  • annual leave management
  • review of internal audit charter
  • disaster recovery planning.

Transport Asset Holding Entity of New South Wales

Background

The establishment of TAHE was originally announced by the NSW Government in the 2015–16 State Budget. On 1 July 2020, the former Rail Corporation New South Wales (RailCorp), a not-for-profit entity, transitioned to the Transport Asset Holding Entity of New South Wales (TAHE), a for-profit statutory state-owned corporation under the Transport Administration Act 1988. There was no change in the structure of TAHE as a new entity was not created. Ownership remains fully with the government. TAHE, and the former RailCorp, were both classified as Public Non-Financial Corporation (PNFC) entities within the Total State Sector Accounts.

Prior to 1 July 2015, the government paid appropriations to Transport for NSW, a General Government Sector (GGS) agency, to construct transport assets. When completed, these assets were granted to the former RailCorp, a not for-profit entity within the PNFC sector. The grants to the former RailCorp were recorded as an expense in the State’s GGS budget result.

From 1 July 2015, the government announced the creation of TAHE (a dedicated asset manager). Funding for new capital projects was to be provided through equity injections and was no longer recorded as an expense to the GGS budget, even though the business model was yet to be determined. The change, as explained in the 2015–16 State Budget, was due to the expectation that the former RailCorp will transition to TAHE, which was intended, over time to provide a commercial return. That Budget also highlighted how the change, which was largely a change in the basis of accounting, was intended to improve the GGS budget result each year. In total, the GGS has contributed approximately $11.1 billion to TAHE since 2015–16. This includes the equity injections from the GGS to TAHE made in the current year of $2.4 billion.

NSW Treasury initially set a timetable for the stand-up of TAHE of 1 July 2019, which included finalising the business model, operating model and contracts for the use of TAHE's assets. The enactment of the Transport Administration Act 1988 resulted in RailCorp transitioning to TAHE on 1 July 2020, 12 months after its originally planned operational date. Contributions paid to the former RailCorp and subsequently to TAHE by the GGS were treated as equity investments from July 2015 forward. This treatment continued, despite delays in settling the business model. In 2020, the Audit Office raised a high-risk finding due to the significance of the financial reporting impacts and business risks for NSW Treasury and TAHE.

The business model adopted and the flow of funds between transport agencies in the GGS and PNFC sectors is shown in the diagram below. For further details refer to the Report on State Finances 2021.

Appendix one – Misstatements in financial statements submitted for audit

Appendix two – Early close procedures

Appendix three – Financial data

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Building regulation: combustible external cladding

Building regulation: combustible external cladding

Finance
Local Government
Planning
Compliance
Infrastructure
Regulation
Risk

What the report is about

The report focuses on how effectively the Department of Customer Service (DCS) and Department of Planning and Environment (DPE) led reforms addressing the unsafe use of combustible external cladding on existing residential and public buildings.

Nine local councils were included in the audit because they have responsibilities and powers needed to implement the NSW Government’s reforms.

What we found

After the June 2017 Grenfell Tower fire in London, the NSW Government committed to a ten-point action plan, which included establishing the NSW Cladding Taskforce, chaired by DCS, and with DPE as a key member. The Taskforce co-ordinates and oversees the implementation of the plan.

Depending on the original source of development approval, either individual local councils or DPE are responsible for ensuring that buildings are identified, assessed, and remediated. NSW Government-owned buildings are the responsibility of each department.

Identifying buildings potentially at risk was complex and resource intensive. However, on balance, it is likely that most affected buildings have now been identified.

By October 2021, around 40 per cent of assessed high-risk buildings that are the responsibility of local councils had either been remediated or found not to pose an unacceptable fire risk.

By February 2022, almost 50 per cent of affected NSW Government-owned buildings, and 90 per cent of buildings that are the responsibility of DPE, have either been cleared or are in the process of being remediated.

Earlier guidance on some key issues could have been provided by DCS and DPE in the two years after the Grenfell Tower fire. This may have reduced confusion and inconsistency across local councils we audited, and in some NSW Government departments. This especially relates to the application of the Fair Trading Commissioner's product use ban.

Given the inherent risks posed by combustible external cladding, buildings initially assessed as low-risk may also still warrant further action.

While most high-risk buildings have likely been identified, poor information handling makes it difficult to keep track of all buildings from identification, through to risk assessment and remediation.

What we recommended

DCS and DPE should:

  1. address the confusion surrounding the application of the Commissioner for Fair Trading's product use ban for aluminium composite panels with polyethylene content greater than 30 per cent
  2. develop an action plan to address buildings assessed as low-risk
  3. improve information systems to track all buildings from identification through to remediation.

Fast facts

Authority responsible for
ensuring that owners make
their buildings safe
Approximate number of
buildings referred for further
investigation*
Approximate percentage of
buildings remediated or
assessed to be safe
Local councils 1,200 40%
NSW Government owned 66 50%
DPE under delegation from
the Minister for Planning
137 90%
*After initial inspection by Fire and Rescue NSW, and/or preliminary inquiries by the consent authority, it was identified that the building may be at high-risk of
fire from combustible external cladding.

 

NSW Government's response to the risks posed by combustible external cladding

The NSW Government first became aware of the potential heightened risks posed by combustible external cladding on building exteriors after the 2014 Lacrosse Tower fire in Melbourne. However, it was the tragic loss of life from the Grenfell Tower fire in London, in June 2017, that gave added urgency to the need to address these risks.

Within six weeks of the London fire, the NSW Government committed to a ten-point plan of action for NSW to:

  • identify and remediate any buildings with combustible external cladding
  • ensure that regulation prevented the unsafe use of such cladding
  • ensure that experts involved in providing advice and certifying fire safety measures had the necessary skills and experience.

One of the actions in the ten-point plan was the creation of the NSW Government's Fire Safety and External Wall Cladding Taskforce (the Cladding Taskforce) chaired by the Department of Customer Service (DCS) and with the Department of Planning and Environment (DPE) as a key member.

The ten-point plan also specified that NSW Government departments would be responsible, in regard to buildings they owned to '…audit their buildings and determine if they have aluminium cladding'.

Local councils play a key role in implementing the Government's reforms, given their responsibilities and powers under the Environmental Planning and Assessment Act 1979 (EPA Act) and Local Government Act 1993 (Local Government Act) to approve building works (as 'consent authorities'), as well as to ensure fire safety standards are met. DPE plays an equivalent role for a smaller number of 'State Significant Developments' for which it is the consent authority under delegation from the Minister for Planning.

Commissioner for Fair Trading's building product use ban

On 18 December 2017, the Building Products (Safety) Act 2017 (BPS Act) came into effect in NSW, introducing new laws to prevent the use of unsafe building products. Notably, the BPS Act gave the Secretary of DCS and the Commissioner for Fair Trading the power to ban unsafe uses of building products.

After an extensive consultative process, the Commissioner for Fair Trading used these powers to issue a product use ban on 15 August 2018. This banned the use of external wall cladding of aluminium composite panels with a core comprised of more than 30 per cent polyethylene by mass on new buildings, unless the proposed use was subject to independent fire propagation testing of the specific product and method of application to a building in accordance with relevant Australian Standards.

Buildings occupied before the product use ban came into force are not automatically required to have the banned product removed. Under the BPS Act, consent authorities may determine necessary actions to eliminate or minimise the risk posed by the banned material on existing buildings.

Project Remediate

Project Remediate is a three-year NSW Government program announced in November 2020. The program was designed by the NSW Government to assist building owners of multi-storey apartments (two storeys or more) with high-risk combustible cladding to remediate their building to a high standard and for a fair price.

The scheme is voluntary and includes government paying for the interest on ten-year loans, as well as incorporating assurance and project management services to provide technical and practical support to owners’ corporations and strata managing agents. Building remediations under the program are expected to commence in 2022.

About this audit

This audit assessed whether DCS and DPE effectively led reforms to manage the fire safety risk of combustible external cladding on existing residential and public buildings.

In making this assessment, we considered whether the expressed policy intent of the NSW Government's ten-point plan for fire safety reform had been achieved by asking:

  • are the fire safety risks of combustible external cladding on existing buildings identified and remediated?
  • is there a comprehensive building product safety scheme that prevents the dangerous use of combustible external cladding products on existing buildings?
  • is fire safety certification for combustible external cladding on existing buildings carried out impartially, ethically and in the public interest by qualified experts?

Consistent with the focus of the Cladding Taskforce on multi-storey residential buildings and public buildings, the scope of our audit is limited to buildings categorised under the Building Code of Australia (BCA) as class 2, 3 and 9. These classes are defined in detail in section 1.2, but include: multi-unit residential apartments, hotels, motels, hostels, back-packers, and buildings of a public nature, including health care buildings, schools, and aged care buildings. The scope was also limited to existing buildings, which is defined as buildings occupied by 22 October 2018.

Auditees

The Department of Customer Service chairs the NSW Government's Cladding Taskforce, which is responsible for coordinating the combustible external cladding reforms. The Commissioner of Fair Trading sits within DCS and DCS regulates the industry accreditation scheme for fire safety practitioners, as well as administering the BPS Act.

The Department of Planning and Environment administers the EPA Act and the Environmental Planning and Assessment Regulation 2000 (EPA Regulation), which regulate the building development process. As well as being the delegated consent authority for State Significant Developments, DPE is also responsible for maintaining the mandatory cladding register requiring building owners of multi-storey (BCA class 2, 3 or 9) buildings to register buildings with combustible external cladding on an online portal.

Functions and responsibilities between DCS and DPE varied over time. For example, in October 2019, the DPE building policy team responsible for co-ordinating the DPE response to the combustible cladding issue was transferred to DCS, following changes to agency responsibilities resulting from machinery of government changes. DPE advised this resulted in a lessening of DPE's subsequent policy work on combustible cladding and its involvement in the Cladding Taskforce.

While the focus of the audit was on the oversight and coordination provided by DCS and DPE, nine councils were also auditees for this performance audit. Councils play an essential part as consent authorities for building development approvals in NSW, as well as having responsibilities and powers to ensure fire safety standards. To fully understand how well their activities were overseen and coordinated, a sample of councils was included as auditees.

Nine councils were selected to represent both metropolitan and regional areas, noting that there are very few in-scope buildings in rural areas. The audited councils were:

  • Bayside Council
  • City of Canterbury Bankstown Council
  • Cumberland City Council
  • Liverpool City Council
  • City of Newcastle Council
  • City of Parramatta Council
  • City of Ryde Council
  • City of Sydney Council
  • Wollongong City Council.

Terminology

The two NSW Government department auditees have, over time, been subject to machinery of government changes, which have changed some of their functions and what the departments are called.

Relevant to this audit, the effect of these changes has been:

  • the Department of Finance, Services, and Innovation (DFSI) became the Department of Customer Services (DCS) on 1 July 2019
  • on 1 July 2019, the Department of Planning and Environment became the Department of Planning, Industry, and Environment (DPIE)
  • on 21 December 2021, DPIE became the Department of Planning and Environment (DPE).

To avoid confusion, we use the titles by which these departments are known at the date of this report: the Department of Customer Service and the Department of Planning and Environment.

Conclusion

At July 2017, immediately after the Grenfell Tower fire, there was no reliable source to identify buildings that may have had combustible external cladding. However, it is now likely that most high-risk buildings have been identified.

Following the 2014 Lacrosse Tower fire in Melbourne, the NSW Government recognised that there was a need to be able to identify buildings in NSW that could have combustible external cladding.

The process of identifying buildings that could have combustible external cladding has been complex, resource-intensive, and inefficient principally due to the lack of centralised and coordinated building records in NSW. In total, approximately 1,200 BCA class 2, 3 and 9 buildings have been brought to the attention of councils by either Fire and Rescue NSW (FRNSW), the Cladding Taskforce, or through councils' own inspection for possible further action. In addition, approximately 2,000 more buildings were inspected by FRNSW but not referred to local councils because they either had no combustible external cladding or had combustible external cladding not assessed as being high-risk.

A multi-pronged approach to identifying buildings has been used by the DCS and DPE, through the Cladding Taskforce. While it is impossible to know the full scope of potentially affected buildings, the approach appears thorough in having identified most relevant buildings.

The process of clearing buildings with combustible external cladding has been inconsistent.

In the more than four years since the NSW Government's ten-point plan was announced, around 40 per cent of the buildings brought to the attention of councils have been cleared by either rectification or being found not to pose an unacceptable fire risk. Also, around 50 per cent of NSW Government-owned buildings identified with combustible external cladding and almost 90 per cent of identified buildings for which DPE is consent authority have been cleared or remediation is underway.

While DCS and DPE did seek to work cooperatively with councils and provided high-level guidance on the NSW Government’s fire safety reforms, it took until September 2019 before a model process and other detailed advice was provided to councils to encourage consistent processes. DCS and DPE advice to councils and NSW Government-building owners should have been more timely on two key issues:

  • the use of experts in the process of assessing and remediating existing buildings, and
  • the implementation of the product use ban on aluminium composite panels with polyethylene content 30 per cent or greater.

Clarifying the application of the product use ban may require consent authorities and building owners to revisit how some buildings have been cleared.

The management of buildings assessed as low-risk by FRNSW, estimated to be over 500, has not been a priority of the Cladding Taskforce to date, despite those buildings potentially posing unacceptable fire risks.

Information management by the Cladding Taskforce is inadequate to provide a high-level of assurance that all known affected buildings have been given proper attention.

While most high-risk buildings have likely been identified, information management is not sufficiently robust to reliably track all buildings through the process from identification, through to risk assessment and, where necessary, remediation.

Reforms to certifier registration schemes are limited to new buildings and do not apply to the existing buildings covered by this audit.

While reforms are limited in application to new buildings, some consent authorities took steps to obtain greater assurance on the quality of the work done by fire safety experts regarding combustible external cladding on existing buildings. For example, by requiring fire safety experts to be appropriately qualified and requiring peer review of cladding risk assessments and proposed remediation plans.

 

This chapter considers the part played by DCS and DPE as key members of the Cladding Taskforce in ensuring that buildings with combustible external cladding were effectively identified and remediated through processes implemented by:

  • local councils or DPE, where those bodies were consent authorities under the EPA Act for the relevant buildings
  • in the case of NSW Government buildings, the departments that owned those buildings.

This chapter considers what has been done to deliver a comprehensive building product safety scheme that prevents the dangerous use of combustible external cladding products.

 

This chapter considers whether reforms have ensured that only people with the necessary skills and experience are certifying buildings and signing off on fire-safety.

Inspections of existing buildings and development of any subsequent action plans to address combustible external cladding are not activities covered by accreditation or registration schemes for building certifiers

Almost all the risk assessment and remediation work done on buildings in the scope of this audit have been undertaken under fire safety orders issued by consent authorities using their powers under the EPA Act. This has been the recommended approach by DPE and DCS since at least 2016 (that is, before the Grenfell Tower fire in London).

While there have been reforms to certifier registrations scheme, these were not intended to ensure that combustible cladding-remediation on existing buildings is supported by people with the necessary skills and experience in fire safety under the fire safety order process. Instead, they are focused on offering better assurance for work done in respect to new building projects where accredited experts certify that building work is carried out in accordance with BCA under the DCS managed certifier registration schemes.

No steps have been taken to ensure the quality of the work done by experts inspecting, assessing the fire risk and developing action plans to address combustible external cladding on existing buildings, other than where consent authorities have chosen to exercise their discretion. This includes requiring fire safety experts to be appropriately qualified and requiring peer review of some cladding risk assessments and remediation plans.

Consent authorities determine whether individuals with accreditation are required for combustible cladding inspection, risk assessments and remediation on existing buildings

Whether an individual with certifier accreditation participates in a cladding inspection, risk assessment, or remediation for an existing building will be determined by what councils as consent authorities specify in their fire safety orders unless building owners opt to use such experts without being directed to do so by the consent authority.

As discussed earlier, councils acting as consent authorities vary in whether they require building owners to engage individuals with certifier accreditation. In most of the councils we audited, A1 or C10 accredited experts were either required, or recommended, to perform functions such as auditing suspected combustible cladding, or conducting fire safety risk assessments and developing plans to rectify combustible cladding.

However, these types of work are not functions covered by the accreditation or registration schemes that apply to building and development certifiers.

Certifier accreditation schemes do not cover cladding remediation work done under fire safety orders

While councils may require or recommend that independent accredited A1 or C10 certifiers be engaged by building owners for cladding risk assessment and remediation, they are not performing those functions as certifiers — they are, in effect, more akin to expert consultants. Accordingly, how they perform their functions and duties is not covered by the legislation supporting the accreditation scheme for certifiers that was operated until July 2020 by the Building Professional Board.

Instead, their use in this process is a convenient and practical way for consent authorities to ensure that building owners use appropriate experts who have the qualifications, skills and experience needed to investigate and identify combustible cladding, and then to formulate appropriate action to deal with such cladding. However, these individuals are not performing regulated or accredited work, are not subject to regulatory oversight, and are not accountable to any accreditation body for the quality of the work they perform.

While councils could (and sometimes do) choose to decline poor quality or incomplete cladding-related work prepared by A1 or C10 certifiers, the burden of resolving poor quality would fall on the building owner, who would have to seek amended or additional risk assessments or rectification plans.

In the absence of regulatory oversight, disincentives for poor quality cladding-related work, may include litigation being commenced by the property owner, harm to the expert's reputation in a small and competitive market, and the potential impact on whether the individual could retain their professional indemnity insurance at a reasonable cost (especially in an environment when many insurance providers withdrew coverage for cladding related work).

Reforms impact on regulated experts doing work on new buildings

The reforms that commenced on 1 July 2020, replaced categories of accreditation with classes of registration, and varied the classes such that:

  • accredited building surveyor category A1 became registered building surveyor-unrestricted
  • accredited certifier—fire safety engineer category C10 became registered certifiers-fire safety.

The legislation that introduced these reforms, the Building and Development Certifiers Act 2018, also repealed the pre-existing Building Professionals Act 2005 and abolished the Building Professionals Board. The new Act was accompanied by the Building and Development Certifiers Regulation 2020.

While the scope of this audit is limited to existing buildings, we note that there are buildings with combustible external cladding that are yet to be remediated. Just as these processes previously drew on the expertise of A1 and C10 category certifiers, it seems inevitable that the remediation of existing buildings will continue to draw on the expertise of the equivalent new classes of registered building surveyor-unrestricted and registered certifier-fire safety.

 

Appendix one – Response from agencies

Appendix two – About the audit

Appendix three – Performance auditing

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #364 - released 13 April 2022.