Actions for Effectiveness of SafeWork NSW in exercising its compliance functions

Effectiveness of SafeWork NSW in exercising its compliance functions

Finance
Industry
Health
Compliance
Internal controls and governance
Management and administration
Procurement
Project management
Regulation
Risk

What this report is about 

This report assesses how effectively SafeWork NSW, a part of the Department of Customer Service (DCS), has performed its regulatory compliance functions for work health and safety in New South Wales. 

The report includes a case study examining SafeWork NSW's management of a project to develop a realtime monitoring device for airborne silica in workplaces. 

Findings 

There is limited transparency about SafeWork NSW's effectiveness as a regulator. The limited performance information that is available is either subsumed within DCS reporting (or other sources) and is focused on activity, not outcomes. 

As a work health and safety (WHS) regulator, SafeWork NSW lacks an effective strategic and data-driven approach to respond to emerging WHS risks. 

It was slow to respond to the risk of respirable crystalline silica in manufactured stone. 

SafeWork NSW is constrained by an information management system that is over 20 years old and has passed its effective useful life. 

While it has invested effort into ensuring consistent regulatory decisions, SafeWork NSW needs to maintain a focus on this objective, including by ensuring that there is a comprehensive approach to quality assurance. 

SafeWork NSW's engagement of a commercial partner to develop a real-time silica monitoring device did not comply with key procurement obligations. 

There was ineffective governance and process to address important concerns about the accuracy of the real-time silica monitoring device. 

As such, SafeWork NSW did not adequately manage potential WHS risks. 

Recommendations 

The report recommended that DCS should: 

  • ensure there is an independent investigation into the procurement of the research partner for the real-time silica detector 
  • embed a formal process to review and set its annual regulatory priorities 
  • publish a consolidated performance report 
  • set long-term priorities, including for workforce planning and technology uplift 
  • improve its use of data, and start work to replace its existing complaints handling system 
  • review its risk culture and its risk management framework 
  • review the quality assurance measures that support consistent regulatory decisions

 

Read the PDF report.

Parliamentary reference - Report number #390 - released 27 February 2024
 

Published

Actions for Driver vehicle system

Driver vehicle system

Transport
Finance
Cyber security
Information technology
Internal controls and governance
Project management
Service delivery

What this report is about

Transport for NSW (TfNSW) uses the Driver vehicle System (DRIVES) to support its regulatory functions. The system covers over 6.2 million driver licences and over seven million vehicle registrations.

DRIVES first went live in 1991 and has been significantly extended and updated since, though is still based around the same core system. The system is at end of life but has become an important service for Service NSW and the NSW Police Force.

DRIVES now includes some services to other parts of government and non-government entities which have little or no connection to transport. There are 141 users of DRIVES in total, including commercial insurers, national regulators, and individual citizens.

This audit assessed whether TfNSW is effectively managing DRIVES and planning to transition it to a modernised system.

Audit findings

TfNSW has not effectively planned the replacement of DRIVES.

It is now working on its third business case for a replacement system but has failed to learn lessons from its past attempts.

In the meantime, TfNSW has not taken a strategic approach to managing DRIVES’ growth.

TfNSW has been slow to reduce the risk of misuse of personal information held in DRIVES. With its delivery partner Service NSW, TfNSW has also been slow to develop and implement automatic monitoring of access.

TfNSW uses recognised processes for managing most aspects of DRIVES, but has not kept the system consistently available for users. TfNSW has lacked accurate service availability information since June 2022, when it changed its technology support provider.

TfNSW needs to significantly prioritise cyber security improvements to DRIVES. TfNSW is seeking to lift DRIVES’ cyber defences, but it will not achieve its stated target safeguard level until December 2025.

Even then, one of the target safeguards will not be achieved in full until DRIVES is modernised.

Audit recommendations

TfNSW should:

  • implement a service management framework including insight into the views of DRIVES users, and ensuring users can influence the service
  • ensure it can accurately and cost effectively calculate when DRIVES is unavailable due to unplanned downtime
  • ensure implementation of a capability to automatically detect anomalous patterns of access to DRIVES
  • ensure that DRIVES has appropriate cyber security and resilience safeguards in place as a matter of priority
  • develop a clear statement of the future role in whole of government service delivery for the system
  • resolve key issues currently faced by the DRIVES replacement program including by:
    • clearly setting out a strategy and design for the replacement
    • preparing a specific business case for replacement.

Read the PDF report

Parliamentary reference - Report number #388 - released 20 February 2024

Published

Actions for Procurement of services for the Park'nPay app

Procurement of services for the Park'nPay app

Finance
Local Government
Information technology
Internal controls and governance
Procurement
Project management

What this report is about

The report assesses whether the Department of Customer Service (the department) complied with legislation and NSW government policy when it directly negotiated with Duncan Solutions to procure backend services relating to the Park'nPay app.

The Park'nPay app, developed by the department, enables users to locate and pay for parking remotely using their smart mobile device.

The audit found

The department failed to establish the grounds for entering a direct negotiation procurement strategy, without any competitive tendering, for services for the Park'nPay app. It rushed a decision to trial the app in The Rocks, without considering how this might affect its procurement obligations.

There is no evidence that the procurement achieved value for money. Despite being required by legislation, as well as mandatory NSW government policy, the department did not consider how it would ensure value for money, nor did it demonstrate an adequate understanding of what is meant by value for money on this occasion.

The department failed to implement key probity requirements. There was no effective management of conflicts of interest. Key decisions were not documented. There was a lack of clarity, transparency, and oversight of the relationship between the Minister's office and staff in the department.

The audit made recommendations about

  1. making and retaining complete and accurate records, particularly on decisions to commit or expend public money
  2. ensuring department staff understand how to exercise their financial delegations and procurement processes
  3. ensuring that only staff with appropriate delegations are committing or approving the spending of public money
  4. consistency with the contract extension provisions of the NSW Government Procurement Policy Framework, particularly regarding ensuring value for money
  5. protocols to guide the interactions between department staff and Minister and Minister's staff
  6. the need for proper management and oversight of contingent workers, such as contractors.

 

On 27 February 2019 the then Minister for Finance, Services and Property announced the commencement of a Park’nPay app trial in The Rocks precinct of Sydney.

The app was intended to enable users to locate and pay for parking remotely, using their smart mobile device such as a phone or tablet, rather than needing to physically be at a parking meter.

In July 2019, following a direct negotiation procurement conducted by the then Department of Finance, Services and Innovation, a contract was executed with Duncan Solutions for an estimated value of $1,260,600 over three-years, with three single-year options to extend. The contract required Duncan Solutions to provide development services to link the Park'nPay app to its Parking Enterprise Management System platform and to provide ongoing software support services.

This audit assessed whether the department complied with the procurement obligations that applied at the time it procured these services from Duncan Solutions.

This audit focussed on the department's processes and decision-making relating to:

  • the direct negotiation with Duncan Solutions at the exclusion of any other potential supplier
  • the negotiation, execution and management of the contract with Duncan Solutions.

As this audit focusses on the department's procurement and contract management processes, it does not comment on the activities of Duncan Solutions. The detailed audit objective, criteria and audit approach are in Appendix three.

The auditee is the Department of Customer Service. As a result of machinery of government changes, the Department of Finance, Services, and Innovation became the Department of Customer Service from 1 July 2019. To avoid confusion, this report simply uses ‘the department’ to refer to either. Where the report refers to the Minister, it relates to the former Minister in office at the time.

Conclusion

The department failed to establish the grounds for entering a direct negotiation procurement strategy for services for the Park'nPay app. It rushed a decision to trial the app in The Rocks, without considering how this might affect its procurement requirements.

As part of a direct negotiation process, the department was required to, but did not:

  • undertake a comprehensive analysis of the market and all relevant factors to demonstrate that a competitive process does not need to be conducted
  • conduct a risk assessment for the procurement approach
  • follow the internal delegation process, including obtaining approval of the department's delegate and endorsement of the Chief Procurement Officer.

There is no evidence that the procurement to support Park'nPay represented value for money. Despite it being required by legislation, as well as mandatory NSW Government policy, the department did not consider how to ensure value for money, nor demonstrate an adequate understanding of what is meant by value for money in this case.

The department issued no tender or expression of interest documents against which any proposal could be assessed, and it had no tender evaluation plan, committee, or criteria. Without any objective standards against which the supplier's proposal could be assessed, it was not possible for the department to determine if value for money was achieved, and no value for money has been demonstrated.

The department failed to implement key probity requirements. There was no effective management of conflicts of interest. Key decisions were not documented. There was a lack of clarity, transparency, and oversight of the relationship between the Minister's office and staff in the department.

No conflict of interest declarations were made by staff until almost one year after the direct negotiations commenced and even then they were not made by all members of the negotiation team and key decision-makers.

The department did not document the reasons for its decisions or minute key meetings, such as when, why and by whom the decision was made to transform the procurement from a 'trial' to a contract of up to six years duration. The department had no policies guiding the interactions between the Minister, the Minister's office and staff in the department (including contractors) in relation to this initiative, resulting in blurred and uncertain roles, responsibilities, and accountabilities.

The department initially sought to withhold information from the Audit Office pertaining to Park'nPay. When questions were raised through external scrutiny, there was little evidence of genuine inquiry or review into its practices to ensure improvement and compliance.

The department deliberately sought to withhold information from the Audit Office of NSW when initial inquiries were lawfully made about the Park'nPay project in the context of the audit of the department's financial statements in May 2021.

There is also limited evidence to demonstrate the department has reviewed the decisions and practices around the Park'nPay project, despite receiving internal legal advice at the time that questioned the characterisation of the procurement as a 'pilot', and external scrutiny via the NSW Parliament's Budget Estimates Committee hearings. This indicates a risk that opportunities to review and improve the department's procurement practices based on learnings from this process have been missed.

 

Appendix one – Response from auditee

Appendix two – Key requirements of the department's procurement manual 

Appendix three – About the audit 

Appendix four– Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #387 - released 14 December 2023

 

Published

Actions for Regional road safety

Regional road safety

Transport
Health
Community Services
Internal controls and governance
Management and administration
Project management
Risk

What this report is about

Around one-third of the state’s population lives in regional NSW, but deaths on regional roads make up around two-thirds of the state’s road toll.

Transport for NSW (TfNSW) is responsible for managing road safety outcomes across the NSW road network. This audit assessed the effectiveness of TfNSW’s delivery of road safety strategies, plans and policies in regional areas.

The NSW Road Safety Action Plan 2022–2026 has the stated goal of ‘no death or serious injury occurring on the road transport network’ by 2050.

What we found

There is a disproportionate amount of trauma on regional roads, but there are no specific road safety plans or trauma reduction targets for regional NSW.

TfNSW advises that the setting of state-wide road safety targets is consistent with other jurisdictions and international best practice. However, the proportion of road fatalities and serious injuries in regional NSW is almost the same as ten years ago.

There is no regional implementation plan to assist TfNSW to target the Road Safety Action Plan 2026 to regional areas.

TfNSW considers that local road safety outcomes should be managed by councils, but only 52% of regional councils participated in its Local Government Road Safety Program (LGRSP) in 2022–23. This program has not been updated since 2014, despite commitments to do so in 2021 and 2022.

TfNSW has not undertaken a systematic and integrated analysis of the combined impact of its road safety strategies and plans in regional NSW since 2012.

TfNSW reports against the Community Road Safety Fund (CRSF) annually but there is no consolidated, public reporting on total road safety funding allocated to regional NSW. The Fund underspend increased from 12% in 2019–20 to 20% in 2022–23.

What we recommended

We recommended TfNSW:

  • develop a regional implementation plan to support the NSW Road Safety Action Plan, including a framework to annually measure, analyse and publicly report on progress
  • develop a plan to measure and mitigate risks causing underspend in the CRSF
  • expedite the review of the LGRSP including recommendations to increase involvement of regional councils.

Disclosure of confidential information

Under the Government Sector Audit Act 1983 (the Act), the Auditor-General may disclose confidential information if, in the Auditor-General’s opinion, the disclosure is in the public interest, and that disclosure is necessary for the exercise of the Auditor-General’s functions.

Confidential information in the Act means Cabinet information or information subject to legal privilege. This performance audit report contained confidential information.

The NSW Premier has certified that in his opinion the disclosure of the confidential information was not in the public interest.

The confidential information has been redacted from this report.

Under section 36A(2) of the Government Sector Audit Act 1983, the Auditor-General may authorise the disclosure of confidential information if, in the Auditor-General’s opinion, the disclosure is in the public interest and necessary for the exercise of the Auditor-General’s functions. Confidential information under the Government Sector Audit Act 1983 means Cabinet information, or information that could be subject to a claim of privilege by the State or a public official in a court of law. This performance audit report contained confidential information which, in the opinion of the Auditor-General, is in the public interest to disclose and that disclosure is necessary for the exercise of the Auditor-General’s functions.

On 26 October 2023, pursuant to section 36A(2)(b) of the Government Sector Audit Act 1983, the Auditor-General notified the NSW Premier of the intention to include this information in the published report, having formed the opinion that its disclosure is in the public interest and is necessary for the exercise of the Auditor-General’s functions.

On 23 November 2023, pursuant to section 36A(2)(c) of the Government Sector Audit Act 1983, the NSW Premier certified that, in his opinion, the proposed disclosure of the confidential information contained in this report was not in the public interest. The Premier’s certificate follows. Section 36A(4) states that a certificate of the Premier that it is not in the public interest to disclose confidential information is conclusive evidence of that fact.

The issuance of the certificate by the NSW Premier prevents the publication of this information. The relevant sections of the report containing confidential information have been redacted.

One-third of the New South Wales population resides in regional areas, but two-thirds of the state’s road crash fatalities take place on regional roads.

Between 2017 and 2021, the average number of fatalities for every 100,000 of the population living in regional New South Wales was 8.33 — approximately four times higher than the equivalent measure for Greater Sydney. Similarly, the average number of serious injuries in regional New South Wales over the same period was 75.24 per 100,000 of the population, compared with 50.53 in Greater Sydney. Further, more than 70% of people who lose their lives in accidents on regional roads are residents of regional areas.

Residents of regional areas face particular transport challenges. They often need to travel longer distances for work, health care, or recreation purposes, yet their public transport options are more limited than metropolitan residents. Vehicle safety is also an issue. According to the NSW Road Safety Progress Report 2021, of the light vehicles registered in New South Wales that were manufactured in or after 2000, 48.4% of light vehicles in regional areas had a five-star Australasian New Car Assessment Program (ANCAP) rating, compared to 54.8% in metropolitan areas. Road conditions in regional areas can also be more challenging for drivers.

Regional New South Wales covers 98.5% of the total area of the state. The road network in New South Wales is vast — spanning approximately 200,000 kilometres.

The road network includes major highways, state roads and local roads. Speed limits range from 10 km/hr in high pedestrian shared zones, up to 110 km/hr on high volume and critical road corridors. Eighty per cent of the network has a 100 km/h speed limit, which is mostly applied as a default speed limit, regardless of the presence of safety features and treatments.

Speed is the primary causal factor in more crashes in New South Wales than any other factor, and car crashes in regional areas are more likely to be fatal because of the higher average speeds involved.

The responsibility for managing road safety outcomes across the entire New South Wales road network lies with Transport for NSW (TfNSW), pursuant to Schedule 1 of the Transport Administration Act 1988.

While its safety responsibilities are state-wide, TfNSW does not own or directly manage all of the road network in regional New South Wales, which spans approximately 200,000 kilometres. Approximately 80% of the roads are classified as Local Roads and are administered and managed by local councils. Local councils also maintain Regional Roads that run through their local government areas. TfNSW is responsible for managing State Roads (approximately 20% of roads), which are major arterial roads. It also provides funding for councils to manage over 18,000 km (approximately 10%) of state-significant Regional Roads.

According to TfNSW, between 2016 and 2020, there were 9,776 people killed or seriously injured on roads in regional New South Wales. Adding to the tragic loss of life, according to TfNSW, the estimated cost to the community between 2016 and 2020 resulting from regional road trauma and fatalities was around $13.7 billion.

TfNSW also noted that the ‘risk of road trauma is pervasive, and a combination of effective road safety measures is required to systematically reduce this risk’.

TfNSW released its first long-term road-safety strategy in December 2012, which introduced the goal of ‘Vision Zero’ — a long-term goal of zero deaths or serious injuries on NSW roads. The terminology was changed to ‘Towards Zero’ in the 2021 Road Safety Plan and has been retained in the NSW Road Safety Action Plan 2022–2026. Towards Zero has the stated goal of ‘no death or serious injury occurring on the road transport network’ by 2050.

The objective of this audit is to assess the effectiveness of TfNSW’s delivery of ‘Towards Zero’ in regional areas.

In making this assessment, the audit examined whether TfNSW:

  • is effectively reducing the number of fatalities and serious injuries on regional roads
  • has an effective framework, including governance arrangements, for designing and refreshing the NSW Road Safety Strategy 2012–2021 and the NSW Road Safety Action Plan 2022–2026
  • effectively makes use of whole-of-government and other relevant sources of data to support decision-making, and to evaluate progress and outcomes
  • effectively manages accountabilities, including roles and responsibilities, with respect to road safety outcomes and the use of data.

This audit focused on the policies and strategies used by TfNSW for managing road safety outcomes in regional areas. We did not evaluate individual road safety projects, programs and initiatives as part of this audit.

Whilst Regional Roads and Local Roads (as defined by the Road Network Classifications) are owned and maintained by local councils, we included these roads in this audit as TfNSW may advise and assist councils to promote and improve road safety, as well as manage grant programs that focus on improving road safety outcomes on these roads. Hereafter, unless otherwise stated, references to ‘regional roads’ refer to all classifications of roads in the state which are in regional New South Wales, irrespective of their ownership.

Local councils in regional areas are key stakeholders for the purposes of this audit, and we interviewed eight as part of the audit process (noting that this was not intended to be a representative sample). Road asset management by local councils is also out of scope for this audit as it is the focus of a subsequent performance audit by the Audit Office of New South Wales.b

The Audit Office of New South Wales has undertaken several performance audits relating to road safety since 2009 and these have been referenced while undertaking this audit. They include:

  • Condition of State Roads (August 2006)
  • Improving Road Safety: Heavy Vehicles (May 2009)
  • Improving Road Safety: School Zones (March 2010)
  • Improving Road Safety: Speed Cameras (July 2011)
  • Regional Assistance Programs (May 2018)
  • Mobile speed cameras (October 2018)
  • Rail freight and Greater Sydney (October 2021).

Conclusion

TfNSW has acknowledged that there is a disproportionate amount of road trauma on regional roads in the NSW Road Safety Strategy 2012–2021, the NSW Road Safety Plan 2021, and the NSW Road Safety Action Plan 2022–2026. However, TfNSW has not articulated or evaluated a strategy for implementing road safety policy in regional New South Wales to assist in guiding targeted activities to address regional road trauma. There is also no transparency about the total amount of funding invested in improving road safety outcomes for regional New South Wales.

People living in regional New South Wales make up one-third of the state’s population, but deaths on regional roads make up around two-thirds of the state’s total road toll. This statistic is almost the same in 2023 as it was ten years ago when TfNSW released its first long-term road safety strategy.

More than 70% of people who died on roads between 2012 and 2022 in regional New South Wales were residents of regional areas. Speed is the greatest contributing factor to road fatalities and serious injuries across the entire state. However, it is responsible for more fatalities on regional roads (43%) than in Greater Sydney (34%).

TfNSW’s road safety strategies and plans acknowledge that most road fatalities occur in regional New South Wales but none of its existing strategies or plans show evidence of tailoring measures to suit particular regional settings or ‘hot spots’. There are infrastructure initiatives (such as Saving Lives on Country Roads) and behavioural programs targeting regional areas (such as Driver Reviver). However, these activities are not aligned to a regional-specific strategy or plan that addresses issues specific to regional areas.

TfNSW has state-wide responsibility for managing road safety outcomes. TfNSW advised the audit that a regional plan and regional trauma reduction targets are not needed as the state-wide plan and targets apply equally for all areas of New South Wales, and local road safety factors are best managed by local councils. TfNSW partners with local councils. However, only 52% of councils in regional New South Wales participate in TfNSW’s Local Government Road Safety Program, compared to 84% of councils in metropolitan areas. TfNSW has not undertaken any evaluations to determine whether projects completed under the Local Government Road Safety Program have reduced road trauma at the local level.

Notwithstanding the above points, TfNSW works with local councils (who are road authorities for local roads in their respective areas under the Roads Act 1993) and other key stakeholders such as the NSW Police Force to achieve the NSW Government’s road safety policy objectives.

TfNSW advised that ‘the setting of state-wide road safety targets is consistent with other jurisdictions and international best practice. Importantly, delivery of road safety countermeasures is tailored and applied with a focus on road user groups across all geographic locations to maximise trauma reductions’. There may be legitimate reasons for the existing approach, as articulated by TfNSW. However, the proportion of road fatalities in regional New South Wales roads has not reduced since 2012 – despite a long-term reduction in the overall number of deaths on the state’s roads between 2012–2021. The audit report has recommended that a regionally focused implementation plan could address this issue. TfNSW has accepted this report’s recommendation that such a plan be developed.

Specific road safety initiatives targeted to regional areas have not been implemented or expanded

Text removed pursuant to section 36A of the Government Sector Audit Act 1983 (NSW), in compliance with the issuance of a Premier’s certificate preventing the publication of this information.

TfNSW increased the use of other forms of automated enforcement (such as tripling enforcement hours in mobile speed cameras).
However, the use of automated enforcement has a strong metropolitan focus with most red light and fixed speed cameras being in metropolitan areas. Average speed cameras are the only camera type overwhelmingly located in regional areas but these apply only to heavy vehicles and are positioned on major freight routes. 

There is no consolidated, public reporting of what proportion of total road safety funding is directed to regional New South Wales each year. The main source of funding for road safety in New South Wales, the Community Road Safety Fund, has been underspent since 2019.

Fines from camera-detected speeding, red-light and mobile phone use offences are required to be used solely for road safety purposes through the Community Road Safety Fund (CRSF), as set out in the Transport Administration Amendment (Community Road Safety Fund) Act 2012.

The CRSF has been underspent every year since 2019–20. The underspend has increased from 12% in 2019–20 to 20% in 2022–23 where the full year underspend was forecasted to be $104 million. Of this underspend, $13.5 million was dedicated for regional road infrastructure projects. TfNSW advised the audit that much of the underspend is the result of delays to infrastructure projects due to COVID-19, bushfires, and floods, as well as skills shortages. However, TfNSW has not provided any evidence that it had a plan to mitigate these risks – meaning the level of underspend could continue to grow. TfNSW also advised ‘there is no reason to expect budget management and controls will not return to pre-COVID circumstances’.

In total, TfNSW received $700 million in funding for road safety in 2021–22 (including federal contributions and the Community Road Safety Fund). Of this, $411 million (or ~59%) was directed to regional New South Wales. This is the most recent comprehensive financial data that was provided by TfNSW to the audit team. The 2022–23 NSW Budget allocated $880 million for road safety in 2022–23, with a forecasted total allocation for road safety of $1.6 billion in recurrent expenses and $0.8 billion in capital expenditure over the period 2022–23 to 2025–26.

Appendix one – Response from Transport for NSW

Appendix two – The Safe Systems framework and NSW road safety strategies and plans

Appendix three – About the audit

Appendix four – Performance auditing

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #386 - released 30 November 2023

Published

Actions for Management of the Critical Communications Enhancement Program

Management of the Critical Communications Enhancement Program

Finance
Health
Justice
Whole of Government
Cyber security
Information technology
Infrastructure
Internal controls and governance
Project management
Risk
Service delivery
Shared services and collaboration

What the report is about

Effective radio communications are crucial to NSW's emergency services organisations.

The Critical Communications Enhancement Program (CCEP) aims to deliver an enhanced public safety radio network to serve the five emergency services organisations (ESOs), as well as a range of other users.

This report assesses whether the NSW Telco Authority is effectively managing the CCEP.

What we found

Where it has already been delivered (about 50% of the state), the enhanced network meets most of the requirements of ESOs.

The CCEP will provide additional infrastructure for public safety radio coverage in existing buildings agreed to with ESOs. However, radio coverage inside buildings constructed after the CCEP concludes will be at risk because building and fire regulations do not address the need for in-building public safety radio coverage.

Around 98% of radios connected to the network can be authenticated to protect against cloning, though only 42% are.

The NSW Telco Authority has not settled with ESOs on how call encryption will be used across the network. This creates the risk that radio interoperability between ESOs will not be maximised.

When completed, the public safety radio network will be the only mission critical radio network for ESOs. It is unclear whether governance for the ongoing running of the network will allow ESOs to participate in future network operational decisions.

The current estimated capital cost for the NSW Telco Authority to complete the CCEP is $1.293 billion. This is up from an estimated cost of $400 million in 2016. The estimated capital cost was not publicly disclosed until $1.325 billion was shown in the 2021–22 NSW Budget Papers.

We estimate that the full cost to government, including costs to the ESOs, of implementing the enhanced network is likely to exceed $2 billion.

We made recommendations about

  • The governance of the enhanced Public Safety Network (PSN) to support agency relationships.
  • The need to finalise a Traffic Mitigation Plan for when the network is congested.
  • The need to provide advice to the NSW Government about the regulatory gap for ensuring adequate network reach in future buildings.
  • The need to clarify how encryption and interoperability will work on the enhanced network.
  • The need for the NSW Telco Authority to comply with its policy on Infrastructure Capacity Reservation.
  • Expediting measures to protect against the risk of cloning by unauthenticated radios.

Public safety radio networks are critical for operational communications among Emergency Services Organisations (ESOs), which in New South Wales include:

  • NSW Ambulance
  • Fire and Rescue NSW
  • NSW Police Force
  • NSW Rural Fire Service
  • NSW State Emergency Service.1

Since 1993, these five ESOs have had access to a NSW Government owned and operated radio communications network, the Public Safety Network (PSN), to support their operational communications. Around 60 to 70 other entities also have access to this network, including other NSW government entities, Commonwealth government entities, local councils, community organisations, and utility companies.

Pursuant to the Government Telecommunications Act 2018 ('the Act'), the New South Wales Government Telecommunications Authority ('NSW Telco Authority') is responsible for the establishment, control, management, maintenance and operation of the PSN.2

Separate to the PSN, all ESOs and other government entities have historically maintained their own radio communication capabilities and networks. Accordingly, the PSN has been a supplementary source of operational radio communications for these entities.

These other radio networks maintained by ESOs and other entities are of varying size and capability, with many ageing and nearing their end-of-life. There was generally little or no interoperability between networks, infrastructure was often co-located and duplicative, and there were large gaps in geographic coverage.

In 2016, the NSW Telco Authority received dedicated NSW Government funding to commence the Critical Communications Enhancement Program (CCEP).

According to NSW Telco Authority's 2021–22 annual report, the CCEP is a transformation program for operational communications for NSW government agencies. The CCEP '…aims to deliver greater access to public safety standard radio communications for the State’s first responders and essential service agencies'. The objective of CCEP is to consolidate the large number of separate radio networks that are owned and operated by various NSW government entities and to enhance the state’s existing shared PSN. The program also aims to deliver increased PSN coverage throughout New South Wales.

The former NSW Government intended that as the enhanced PSN was progressively rolled-out across NSW, ESOs would migrate their radio communications to the enhanced network, before closing and decommissioning their own networks.

About this Audit

This audit assessed whether the CCEP is being effectively managed by the NSW Telco Authority to deliver an enhanced PSN that meets ESOs' requirements for operational communications.

We addressed the audit objective by answering the following two questions:

  1. Have agreed ESO user requirements for the enhanced PSN been met under day-to-day and emergency operational conditions?
  2. Has there been adequate transparency to the NSW Government and other stakeholders regarding whole-of-government costs related to the CCEP?

In answering the first question, we also considered how the agreed user requirements were determined. This included whether they were supported by evidence, whether they were sufficient to meet the intent of the CCEP (including in considering any role for new or alternative technologies), and whether they met any relevant technical standards and compliance obligations (including for cyber security resilience).

While other NSW government agencies and entities use the PSN, we focused on the experience of the five primary ESOs because these will be the largest users of the enhanced PSN.

Both the cost and time required to complete the CCEP roll-out have increased since 2016. While it was originally intended to be completed in 2020, this is now forecast to be 2027. Infrastructure NSW has previously assessed the reasons for the increases in time and cost. A summary of the findings made by Infrastructure NSW is presented in Chapter 1 of this report. Accordingly, as these matters had already been assessed, we did not re-examine them in this performance audit.

The auditee for this performance audit is the NSW Telco Authority, which is a statutory authority within the Department of Customer Service portfolio.

In addition to being responsible for the operation of the PSN, section 5 of the Act also prescribes that the NSW Telco Authority is:

  • to identify, develop and deliver upgrades and enhancements to the government telecommunications network to improve operational communications for government sector agencies
  • to develop policies, standards and guidelines for operational communications using telecommunications networks.

The NSW Telco Authority Advisory Board is established under section 10 of the Act. The role of the board is to advise the NSW Telco Authority and the minister on any matter relating to the telecommunications requirements of government sector agencies and on any other matter relating to the functions of the Authority. As of 2 June 2023, the responsible minister is the Minister for Customer Service and Digital Government.

The five identified ESOs are critical stakeholders of the CCEP and therefore they were consulted during this audit. However, the ESOs were not auditees for this performance audit.

Conclusion

In areas of New South Wales where the enhanced Public Safety Network has been implemented under the Critical Communications Enhancement Program, the NSW Telco Authority has delivered a radio network that meets most of the agreed requirements of Emergency Services Organisations for routine and emergency operations.
In April 2023, the enhanced Public Safety Network (PSN) was approximately 50% completed. In areas where it is used by Emergency Services Organisations (ESOs), the PSN generally meets agreed user requirements. This is demonstrated through extensive performance monitoring and reporting, which shows that agreed performance standards are generally achieved. Reviews by the NSW Government and the NSW Telco Authority found that the PSN performed effectively during major flood events in 2021 and 2022.

Where it is completed, PSN coverage is generally equal to or better than each ESO's individual pre-existing coverage. The NSW Telco Authority has a dedicated work program to address localised coverage gaps (or 'blackspots') in those areas where coverage has otherwise been substantively delivered. Available call capacity on the network far exceeds demand in everyday use. Any operational issues that may occur with the PSN are transparent to ESOs in real time.

The NSW Telco Authority consulted extensively with ESOs on requirements for the enhanced PSN, with relatively few ESO requirements not being included in the specifications for the enhanced PSN. Lessons from previous events, including the 2019–20 summer bushfires, have informed the design and implementation of the enhanced PSN (such as the need to ensure adequate backup power supply to inaccessible sites). The network is based on the Project 25 technical standards for mission-critical radio communications, which is widely-accepted in the public safety radio community throughout Australia and internationally.

There is no mechanism to ensure adequate radio coverage within new building infrastructure after the CCEP concludes, but the NSW Telco Authority and ESOs have agreed an approach to prioritise existing in-building sites for coverage for the duration of the CCEP.
The extent to which the PSN works within buildings and other built structures (such as railway tunnels) is of crucial importance to ESOs, especially the NSW Police Force, NSW Ambulance, and Fire and Rescue NSW. This is because a large proportion of their operational communications occurs within buildings.

There is no mechanism to ensure the adequacy of future in-building coverage for the PSN in new or refurbished buildings after the CCEP concludes. Planning, building, and fire regulations are silent on this issue. We note there are examples in the United States of how in-building coverage for public safety radio networks can be incorporated into building or fire safety codes.

In regard to existing buildings, it is not possible to know whether a building requires its own in-building PSN infrastructure until nearby outside radio sites, including towers and antennae, have been commissioned into the network. Only then can it be determined whether their radio transmissions are capable of penetrating inside nearby buildings. Accordingly, much of this work for in-building coverage cannot be done until outside radio sites are finished and operating.

In March 2023, the NSW Telco Authority and ESOs agreed on a list of 906 mandatory and 7,086

non-mandatory sites for in-building PSN coverage. Most of these sites will likely be able to receive radio coverage via external antennae and towers, however this cannot be confirmed until those nearby external PSN sites are completed. The parties also agreed on an approach to prioritising those sites where coverage is needed but not provided by antennae and towers. Available funding will likely only extend to ensuring coverage in sites deemed mandatory, which is nonetheless expected to meet the overall benchmark of achieving 'same or better' coverage than what ESOs had previously.

There is a risk that radio interoperability between ESOs will not be maximised because the NSW Telco Authority has not settled with ESOs how encryption will be used across the enhanced PSN.
End-to-end encryption of radio transmissions is a security feature that prevents radio transmissions being intercepted or listened to by people who are not meant to. The ability of the PSN to provide end-to-end encryption of operational communications is of critical importance to the two largest prospective users of the PSN: the NSW Police Force and NSW Ambulance. Given that encryption excludes other parties that do not have the requisite encryption keys, its use creates an obstacle to achieving a key intended benefit of the CCEP, that is a more interoperable PSN, where first responders are better able to communicate with other ESOs.

Further planning and collaboration between PSN participants are necessary to consider how these dual benefits can be achieved, including in what operational circumstances encrypted interoperability is necessary or appropriate.

The capital cost to the NSW Telco Authority of the CCEP, originally estimated at $400 million in 2016, was not made public until the 2021–22 NSW Budget disclosed an estimate of $1.325 billon.
The estimated capital cost to complete all stages of the CCEP increased over time. This increasing cost was progressively disclosed to the NSW Government through Cabinet processes between 2015–16 and 2021–22.

In 2016, the full capital cost to the NSW Telco Authority of completing the CCEP was estimated to be $400 million. This estimated cost was not publicly disclosed, nor were subsequent increases, until the cost of $1.325 billion was publicly disclosed in the 2021–22 NSW Budget (revised down in the 2022–23 NSW Budget to $1.293 billion).

There has been no transparency about the whole-of-government cost of implementing the enhanced PSN through the CCEP.
In addition to the capital costs incurred directly by the NSW Telco Authority for the CCEP, ESOs have incurred costs to maintain their own networks due to the delay in implementing the CCEP. The ESOs will continue to incur these costs until they are able to fully migrate to the enhanced PSN, which is expected to be in 2027. These costs have not been tracked or reported as part of transparently accounting for the whole-of-government cost of the enhanced PSN. This is despite Infrastructure NSW in 2019 recommending to the NSW Telco Authority that it conduct a stocktake of such costs so that a whole-of-government cost impact is available to the NSW Government.

1 The definition of 'emergency services organisation' is set out in the State Emergency and Rescue Management Act 1989 (NSW). In addition to the five ESOs discussed in this report, the definition also includes: Surf Life Saving New South Wales; New South Wales Volunteer Rescue Association Inc; Volunteer Marine Rescue NSW; an agency that manages or controls an accredited rescue unit; and a non-government agency that is prescribed by the regulations for the purposes of this definition.
2 Section 15(1) of the Government Telecommunications Act 2018 (NSW).

The NSW Telco Authority established and tracked its own costs for the CCEP

Over the course of the program from 2016, the NSW Telco Authority prepared a series of business cases and program reviews that estimated its cost of implementing the program in full, including those shown in Exhibit 6 below.

Exhibit 6: Estimated costs to fully implement the CCEP
Source Capital cost ($ million) Operating cost
($ million)
Completion date
March 2016 business case 400 37.3 2020
November 2017 internal review 476.7 41.7 2022
March 2020 business case 950–1,050 -- 2025
October 2020 business case 1,263.1 56.1 2026

Source: CCEP business cases as identified.

In response to the 2016 CCEP business case, the then NSW Government approved the NSW Telco Authority implementing the CCEP in full, with funding provided in stages. The NSW Telco Authority tracked its costs against approved funding, with monthly reports provided to the multi-agency Program Steering Committee

Throughout the program, the NSW Government was informed of increasing costs being incurred by the NSW Telco Authority for the CCEP

The various business cases, program updates, and program reviews prepared by the NSW Telco Authority were provided to the NSW Government through the required Cabinet process when seeking approval for the program proceeding and requests for both capital and operational funding. These provided clear indication of the changing overall cost of the CCEP to the NSW Telco Authority, as well as the delays that were being experienced.

There was no transparency to the Parliament and community about changes in the capital cost of the CCEP until the 2021–22 NSW Budget

As the business cases for the CCEP were not publicly available, the only sources of information about capital cost were NSW Budget papers and media releases. The information provided in the annual Budget papers prior to the 2021–22 NSW Budget provided no visibility of the estimated full capital cost to complete all stages of the CCEP. As shown in Exhibit 7 below, this information was fragmented and complex.

Media releases about the progress of the CCEP did not provide the estimated total cost to the NSW Telco Authority of $1.325 billion to complete all stages of the CCEP until June 2021. Prior to this date, media releases only provided funding for the initial stages of the program or for the stages subject to a funding announcement.

Even during the September 2019 and March 2020 Parliamentary Estimate Committee hearings where the costings and delays to the CCEP were raised, the estimated full cost of the CCEP was not revealed.

Exhibit 7: CCEP funding in NSW Budget papers from 2015–16 to 2022–23
Financial year Type of major work Description of expenditure Forecast estimate to complete ($ million) Estimated duration
2015–16 New work Infrastructure Rationalisation Program: Planning and Pilot 18.3 2015–16
2016–17 Work in progress CCEP Planning and Pilot 18.3 2015–17
New work CCEP 45 2016–17
2017–18 New work CCEP 190.75 2017–21
2018–19 Work in progress CCEP North Coast and State-wide Detailed Design 190.75 2017–21
New work CCEP Greater Metropolitan Area 236 2018–22
2019–20 Work in progress CCEP 426.9 2018–22
2020–21 Work in progress CCEP 664.8 2018–22
2021–22 Work in progress CCEP 1,325 2018–26
2022–23 Work in progress CCEP 1,292.8 2018–26

Source: NSW Treasury, Annual State Budget Papers.

The original business case for the CCEP included estimated ESO costs, though these costs were not tracked throughout the program

Estimates for ESO costs for operating and maintaining their own radio networks over the four years from 2016–17 were included in the original March 2016 business case. They included $75.2 million for capital expenditure and $95 million for one-off operating costs. These costs, as well as costs incurred by ESOs due to the delay in the program, were not subsequently tracked by the NSW Telco Authority.

In January 2017, Infrastructure NSW reviewed the CCEP business case of March 2016. In this review, Infrastructure NSW recommended that the NSW Telco Authority identify combined and apportioned costs and cashflow for all ESOs over the CCEP funding period reflecting all associated costs to deliver the CCEP. These to include additional incidental capital costs accruing to ESOs, transition and migration to the new network and the cost (capital and operational) of maintaining existing networks. This recommendation was implemented in the November 2017 program review, with ESO capital costs estimated as $183 million.

In 2019, Infrastructure NSW conducted a Deep Dive Review on the progress of the CCEP. In this review, Infrastructure NSW made what it described as a 'critical recommendation' that the NSW Telco Authority:

…coordinate a stocktake of the costs of operational bridging solutions implemented by PSAs [ESOs] as a result of the 18-month delay, so that a whole-of-government cost impact is available to the NSW Government.  

It should be noted that the delay to CCEP completion now is seven years and that further ‘operational bridging solutions’ have been needed by the ESOs.

'Stay Safe and Keep Operational' costs incurred by ESOs will be significantly higher than originally estimated

Stay Safe and Keep Operational (SSKO) funding was established to provide funding to ESOs to maintain their legacy networks while the CCEP was refreshing and enhancing the PSN. This recognised that much of the network infrastructure relied on by ESOs had reached – or was reaching – obsolescence and would either require extensive maintenance or replacement before the PSN was available for ESOs to migrate to it. ESOs may apply to NSW Treasury for SSKO funding, with their specific proposals being reviewed (and endorsed, where appropriate) by the NSW Telco Authority. Accordingly, SSKO expenditure does not fall within the CCEP budget allocation.

As shown in the table below, extracted from the March 2016 CCEP business case, the total expected cost for SSKO purposes over the course of the CCEP was originally $40 million, assuming the enhanced PSN would be fully available by 2020.

Exhibit 8: Stay Safe and Keep Operational forecast costs, 2017 to 2020
Year 2017 2018 2019 2020 Total
SSKO forecast ($ million) 12.5 15 10 2.5 40

Source: March 2016 CCEP business case.

In October 2022, the expected completion date for the CCEP was re-baselined to August 2027. Accordingly, ESOs will be required to continue to maintain their radio networks using legacy equipment for seven years longer than the original 2020 forecast. This will likely become progressively more expensive and require additional SSKO funding. For example, NSW Telco Authority endorsed SSKO bids for 2022–23 exceeded $35 million for that year alone.

Compared to the original forecast made in the March 2016 CCEP business case of $40 million, we found ESOs had estimated SSKO spending to 2027 will be $292.5 million.

A refresh of paging network used by ESOs and the decommissioning of redundant sites were both removed from the original 2016 scope of the CCEP

Paging

A paging network is considered an important user requirement by the Fire and Rescue NSW, NSW Rural Fire Service, and NSW State Emergency Service. The 2016 CCEP business case included a paging network refresh within the program scope of works. This was reiterated in the November 2017 internal review of the program. These documents did not estimate a cost for this refresh. The March 2020 and October 2020 business cases excluded paging from the program scope. The audit is unable to identify when, why or by whom the decision was made to remove paging from the program scope, something that was also not well communicated to the affected ESOs.

In 2021, after representations from the affected ESOs, the NSW Telco Authority prepared a separate business case for a refresh of the paging network at an estimated capital cost of $60.31 million. This program was subsequently approved by the NSW Government and included in the 2022–23 NSW Budget.

In determining an estimated full whole-of-government cost of delivering the enhanced PSN, we have included the budgeted cost of the paging network refresh on the basis that:

  • it was expressly included in the original approved March 2016 business case
  • the capability is deemed essential to the needs of three ESOs.

Decommissioning costs

The 2016 CCEP business case included cost estimates for decommissioning surplus sites (whether ‘old’ GRN sites or sites belonging to ESOs’ own networks). These estimates were provided for both the NSW Telco Authority ($38 million) and for the ESOs ($55 million). However, while these estimates were described, they were not included as part of the NSW Telco Authority's estimated capital cost ($400 million) or (more relevantly) operating cost ($37.3 million) for the CCEP. This is despite decommissioning being included as one of eight planned activities for the rollout of the program.

In the October 2020 business case, an estimate of $201 million was included for decommissioning agency networks based on a model whereby:

  • funding would be coordinated by the NSW Telco Authority
  • scheduling and reporting through an inter-agency working group and
  • where appropriate, agencies would be appointed as the most appropriate decommissioning party.

This estimated cost is not included in the CCEP budget.

In determining an estimated full whole-of-government cost of the enhanced PSN, we have included the estimated cost of decommissioning on the basis that:

  • decommissioning was included in the 2016 CCEP business case as one of eight 'planned activities for the rollout of the program'
  • effective decommissioning of surplus sites and equipment (including as described in the business case as incorporating asset decommissioning, asset re-use, and site make-good) is an inherent part of the program management for an enhanced PSN
  • costs incurred in decommissioning are entirely a consequence of the CCEP program.

The estimated minimum cost of building an enhanced PSN consistent with the original proposal is over $2 billion

We have derived two estimated minimum whole-of-government costs for delivering an enhanced PSN. These are:

  • $2.04 billion when calculated from NSW Telco Authority data – shown as estimate A in Exhibit 9 below.
  • $2.26 billion when calculated from ESO supplied data – shown as estimate B in Exhibit 9.

Both totals include:

  • budgeted amounts for both CCEP capital expenditure ($1,292.8 million) and operating expenditure ($139 million)
  • the NSW Telco Authority's 2020 estimated cost for decommissioning ($201 million)
  • the NSW Telco Authority's approved funding for paging refresh ($60.3 million).

The two estimated totals primarily vary around the capital expenditure of ESOs (particularly SSKO funding). To determine these costs, we used ESO provided actual SSKO costs to date, as well as their estimates for maintaining their legacy radio networks through to 2027.

The equivalent cost estimates from the NSW Telco Authority were sourced from the November 2017 internal review and the October 2020 business case for CCEP. It should be noted that the amounts for both estimates are not audited, or verified, but do provide an indication of how whole-of-government costs have grown over the course of the program.

The increase in and reasons for the increase in total CCEP costs (capital and one-off operating) incurred or forecast by the NSW Telco Authority (from $437.3 million in 2016 to $1,431.8 million in 2022) have been provided to the NSW Government through various business cases and reviews prepared by the NSW Telco Authority, as well as by reviews conducted by Infrastructure NSW as part of its project assurance responsibilities.

However, the growth in ESO costs and other consequential costs, such as paging and decommissioning, from around $263 million in the 2016 CCEP business case to between $600 million and $800 million, has to a large degree remained invisible and unexplained to the NSW Government and other stakeholders

Exhibit 9: Estimated whole-of-government costs of the enhanced PSN
  Estimated whole-of-government cost, over time
Cost type 20161 20172 20203 2023–Estimate A4 2023–Estimate B5
$ million $ million $ million $ million $ million
CCEP capital expenditure 400a 476.7b 1,263.1c 1,292.8d 1,292.8d
CCEP operating expenditure 37.3a 41.7b 41.5e 139d 139d
CCEP total 437.3 518.4 1,304.6 1,431.8 1,431.8
ESO capital expenditure 75.2a,f 183b,e 75.4e 258.4g 292.5
ESO one-off operating expenditure 93a n.a.l 86.5e 86.5h 273
ESO total 168.2 183 161.9 344.9 565.5
Paging n.a.i n.a.i n.a.j 60.3k 60.3k
Decommissioning 93 n.a.l 201.0 201h 201
Paging and decommissioning total 93 n.a. 201 261.3 261.3
Whole-of-government total 698.5 701.4 1,667.5 2,038 2,258.6

Notes:
  1. Financial year 2016 to Financial year 2020.
  2. Financial year 2016 to Financial year 2021.
  3. Financial year 2016 to Financial year 2025.
  4. Financial year 2016 to Financial year 2026.
  5. Financial year 2022 to Financial year 2025.
  6. Stay Safe and Keep Operational (SSKO) costs plus terminals costs.
  7. November 2017 internal review and October 2020 Business case.
  8. October 2020 Business case.
  9. Included in CCEP capital expenditure at that time.
  10. By 2020, a refresh of the paging network had been removed from the CCEP scope.
  11. A separate business case for a refresh of the paging network was approved by government in 2022.
  12. Figure not included in the source document.
Sources:
  1. March 2016 CCEP business case.
  2. November 2017 Internal Review conducted by the NSW Telco Authority.
  3. October 2020 CCEP business case.
  4. Derived from business cases, with ESO costs drawn from NSW Telco Authority data.
  5. Derived from business cases, with ESO costs based on data provided to the Audit Office of New South Wales by each of the five ESOs.

Appendix one – Response from agency

Appendix two – Trunked public safety radio networks

Appendix three – About the audit

Appendix four – Performance auditing

 

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #383 - released 23 June 2023

 

Published

Actions for Government's acquisition of private property: Sydney Metro project

Government's acquisition of private property: Sydney Metro project

Transport
Planning
Whole of Government
Compliance
Infrastructure
Internal controls and governance
Project management
Risk

What the report is about

Sydney Metro is Australia’s largest public transport project. It requires the acquisition of many private properties, including residential and business properties.

This audit assessed the effectiveness of the acquisition of private properties for the Sydney Metro project. The audited agencies were Sydney Metro, the Department of Planning and Environment (Valuer General NSW) and Transport for NSW (the Centre for Property Acquisition).

The audit assessed agencies against the framework for property acquisitions in New South Wales. It did not re-perform the valuations done for individual properties that were acquired by Sydney Metro.

What we found

Acquisitions of private property for the Sydney Metro project were mostly effective in the sample of acquisitions we assessed. We found Sydney Metro:

  • complied with legislative and policy requirements for compensation and communication with people subject to property acquisitions
  • kept accurate records of its acquisitions and applied probity controls consistently
  • did not complete detailed plans or negotiation strategies for the high-risk and high-value acquisitions we reviewed
  • did not comply with legislative timelines for most compulsory acquisitions because of delays in receiving the required information from the Valuer General in these cases.

The Centre for Property Acquisition has overseen the implementation of reforms to residential acquisition processes, but its assessment of the effectiveness of these reforms has not been comprehensive.

What we recommended

The audit made four recommendations to the audited agencies to improve:

  • plans and strategies for the acquisition of high-risk and high-value properties
  • timeliness of issuing compensation determinations for compulsory acquisitions
  • data quality on the experience of people subject to property acquisitions.

The NSW Government has the power to acquire land that is owned or leased by individuals or businesses, if it is needed for a public purpose. The power arises from the Land Acquisition (Just Terms Compensation) Act 1991 (the Just Terms Act). Government agencies that have the power to compulsorily acquire private property are referred to as ‘acquiring authorities’. People who are subject to acquisitions are referred to as ‘affected parties’ and include property owners (business or residential), businesses with a commercial lease on a property, or individuals with residential tenancy leases. In recent years, the vast majority of acquisitions by the NSW Government have been for public transport or road projects.

Sydney Metro is a NSW Government agency with responsibility for building the Sydney Metro railway project. Sydney Metro is Australia’s largest public transport project. The project requires the acquisition of a large number of private properties. Sydney Metro has been one of the largest acquirers of private property in recent years, completing over 500 acquisitions between 2020 and mid-2022, with a total acquisition value of over $2 billion. Other agencies and statutory officers involved in the acquisition of property for the Sydney Metro project include:

  • the Department of Planning and Environment (DPE), which supports the minister responsible for the Just Terms Act. DPE also provides staff to the Valuer General of NSW
  • the Valuer General of NSW, an independent statutory officer that determines compensation in cases where the acquiring authority and the affected party cannot agree on compensation for property that has been acquired
  • Transport for NSW, which includes the Centre for Property Acquisition (CPA). The CPA does not have a direct role in acquiring properties, but its responsibilities include developing guidance for acquiring agencies and monitoring and reporting on their activities.

About this audit

The objective of this audit was to assess the effectiveness of acquisitions of private properties for Sydney Metro projects. The audit assessed agencies against the legislative and policy requirements in place for government acquisitions of private property in New South Wales. In line with the Audit Office's legislative mandate, the audit does not comment on the merits of the policy objectives reflected in the Just Terms Act.

The audit examined a sample of 20 property acquisitions. This was not a statistically representative sample. While our report provides comments on Sydney Metro’s overall acquisition processes, it does not provide assurance regarding the acquisitions that were not examined for this audit.

The audit did not re-perform the valuations done for individual properties that were acquired by Sydney Metro. Affected parties who disagree with the valuation of their property have the right to seek independent assessment of this via the Valuer General and the Land and Environment Court.

Conclusion

Acquisitions of property for the Sydney Metro project were mostly effective in the sample of acquisitions we assessed. Sydney Metro followed requirements for communication with affected parties. Compensation processes were conducted in compliance with legislative requirements, but compensation determinations for compulsory acquisitions were not completed within legislated time frames due to delays in receiving these from the Valuer General. Governance and probity processes were followed consistently, with some relatively minor exceptions. 

Sydney Metro has detailed guidelines for acquisitions that are based on relevant legislation and government policy. In the 20 acquisitions we assessed for this audit, these procedures were followed consistently. This included adhering to minimum timelines for negotiation periods, engaging independent valuers and other experts when needed, and complying with governance and probity processes.

Sydney Metro staff followed requirements for communication and support for residential acquisitions by assigning ‘personal managers’ and providing additional support to affected parties when needed. The Centre for Property Acquisition (CPA) has overseen reforms to the residential property acquisition process in recent years. These reforms include the introduction of the NSW Property Acquisition Standards and the use of personal managers, in addition to the existing acquisition managers, for residential acquisitions. However, the CPA has not assessed the impact of these changes on the experiences on people affected by property acquisitions.

Sydney Metro did not comply with the legislative requirement to provide a formal compensation notice to the affected party within 45 days of a compulsory acquisition starting in any of the eight relevant acquisitions in our sample. This was because Sydney Metro must wait for the Valuer General to complete a compensation determination before Sydney Metro can send the compensation notice, and the Valuer General did not do this within 45 days. We acknowledge that Sydney Metro does not have full control over this process, and that it has taken steps to mitigate the impact of delays on affected parties. 

This chapter presents our findings on Sydney Metro's acquisition of industrial and commercial properties. Industrial properties include construction businesses and manufacturing facilities. Commercial properties were mostly properties such as shopping centres and office towers. Many of these acquisitions involve businesses and properties that are relatively complex and have high values. This means the valuation process can require multiple experts and can be lengthy and contested. Adherence to governance and probity requirements is important for these acquisitions in order to demonstrate that the acquiring authority has achieved value for money.

This chapter presents our findings on Sydney Metro's acquisition of residential properties, which include apartments and houses, and small business leases, which mostly affected businesses in small shopping centres or arcades. Most of these acquisitions were lower value compared to industrial and commercial property acquisitions and did not require as much expert advice on complex technical issues. However, residential property acquisitions can be personally distressing for the affected parties and require staff from the acquiring authority to provide support and show empathy while ensuring legislative compliance and value for money.

Appendix one – Responses from agencies

Appendix two – About the audit 

Appendix three – Performance auditing 

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #375 - released 9 February 2023

Published

Actions for Design and implementation of the Transport Asset Holding Entity

Design and implementation of the Transport Asset Holding Entity

Transport
Treasury
Asset valuation
Financial reporting
Infrastructure
Procurement
Risk
Service delivery

What the report is about

The Transport Asset Holding Entity (TAHE) is the State's custodian of rail assets. It is a state owned corporation and commenced operating on 1 July 2020.

This audit assessed the effectiveness of NSW Government agencies' design and implementation of TAHE. We audited TAHE, Transport for NSW (TfNSW) and NSW Treasury.

Separate and related audits on TAHE are reported in 'State Finances 2022', 'State Finances 2021' and 'Transport and Infrastructure 2022' reports.

What we found

The design and implementation of TAHE, which spanned seven years, was not effective.

The process was not cohesive or transparent. It delivered an outcome that is unnecessarily complex in order to support an accounting treatment to meet the NSW Government's short-term Budget objectives, while creating an obligation for future governments.

The benefits of TAHE were claimed in the 2015–16 NSW Budget before the enabling legislation was passed by Parliament in 2017. This committed the agencies to implement a solution that justified the 2015–16 Budget impacts, regardless of any challenges that arose.

Rail safety arrangements were a priority throughout TAHE's design and implementation, and risks were raised and addressed.

Agencies relied heavily on consultants on matters related to the creation of TAHE, but failed to effectively manage these engagements. Agencies failed to ensure that consultancies delivered independent advice as an input to decision-making. A small number of firms were used repeatedly to provide advice on the same topic. The final cost of TAHE-related consultancies was $22.6 million compared to the initial estimated cost of $12.9 million.

What we recommended

We recommended that the audited agencies should:

  • improve accountability and transparency for major new fiscal transformation initiatives
  • ensure entities do not reflect the financial impact of significant initiatives in the Budget when there is uncertainty, or it creates perverse incentives
  • review record keeping practices, systems and policies to ensure compliance with the State Records Act 1998, and the NSW Government Information Classification, Labelling and Handling Guidelines
  • review procurement policies to ensure that consultant use complies with all NSW Government policy requirements.

The NSW Government established the Transport Asset Holding Entity (TAHE), a statutory State Owned Corporation (SOC), on 1 July 2020 to replace the former rail infrastructure owner – RailCorp. It is the State's custodian of rail network assets, including rail tracks and other infrastructure, rolling stock, land, train stations and facilities, retail space, and signal and power systems, within metropolitan and regional New South Wales. It is responsible for $2.8 billion of major capital projects in 2022–23.

TAHE was established under Part 2 of the Transport Administration Act 1988 and is governed by a decision-making board. The Treasurer and the Minister for Finance and Employee Relations are the Shareholding Ministers of TAHE, and they annually agree performance expectations articulated in a Statement of Corporate Intent.

Whereas TAHE is the custodian of rail assets, Sydney Trains and NSW Trains operate public rail services. TAHE does not have responsibility for the operation of the heavy rail network or train services, nor does it have network control functions. TAHE, Sydney Trains and NSW Trains are in the Transport and Infrastructure cluster in the public sector (formerly the Transport cluster and renamed in April 2022), which also includes Sydney Metro and Transport for NSW (TfNSW).

TfNSW leads the Transport and Infrastructure cluster. Its role is to set the strategic direction for transport across the State. This involves the shaping of planning, policy, strategy, regulation, resource allocation and other service and non-service delivery functions for all modes of transport.

TAHE's Operating Licence is granted by the Portfolio Minister and authorises the entity to perform the functions required to acquire, develop, finance, divest and hold assets, pursuant to the Transport Administration Act 1988. The Portfolio Minister also issues a Statement of Expectations which outlines the government’s expectation for the business for the next three to five years.

TAHE's original Portfolio Minister was the Minister for Transport who approved, on 30 June 2020, the issuing of an interim 12-month Operating Licence to enable TAHE to commence operating on 1 July 2020. The Portfolio Minister then granted TAHE's current Operating Licence in 2021. After TAHE requested a 12-month extension to its current Operating Licence, its next Operating Licence is due on 1 July 2024. The current Portfolio Minister is the Minister for Infrastructure, Cities and Active Transport.

About this audit

This audit assessed the effectiveness of NSW Government agencies' design and implementation of TAHE. In making this assessment, we considered whether: 

  • the process of designing and implementing TAHE was cohesive and transparent, and delivered an effective outcome
  • agencies' roles and responsibilities were clear in the planning of TAHE
  • agencies effectively identified and managed certain risks.

Conclusion

The design and implementation of TAHE was not effective. The process was not cohesive or transparent. It delivered an outcome that is unnecessarily complex in order to meet the NSW Government's short-term Budget objectives, while creating an obligation for future governments to sustain TAHE through continuing investment, and funding of the state owned rail operators. The ineffective process to design TAHE delivered a model that entails significant uncertainty as to whether the anticipated longer-term financial improvements to the Budget position can be achieved or sustained.

NSW Treasury and TfNSW had different objectives for TAHE

Up to June 2013, RailCorp had been the owner and operator of rail services and maintainer of the metropolitan rail network for almost a decade. It had been operating as a not-for-profit Public Non-Financial Corporation (PNFC).

In 2012, NSW Treasury (hereafter Treasury) decided there was a risk that the Australian Bureau of Statistics (ABS) would reclassify RailCorp to the General Government Sector (GGS), meaning depreciation expenses of approximately $870 million would be reflected in the GGS Budget. Treasury wanted to avoid this impact on the GGS Budget, and considered the establishment of a transport asset holding entity as a means to do so. Capital grants to RailCorp were being treated as an expense to the GGS Budget.

TfNSW also wanted an asset holding entity – but one that would be a non-trading ‘shell’ company with no staff that would hold and manage all public transport assets. TfNSW's concept envisaged the entity would have a structure that would enable future public transport reforms and strategic directions while ensuring vertical integration of operations between asset owners and the rail operators to maintain rail safety.

However, Treasury pursued its objective to improve the GGS Budget result, and sought to expand on TfNSW's 'shell' asset holding entity concept. Treasury wanted an entity that could generate a return on investment, as this meant that government investment in transport assets could be treated as equity investments, rather than a Budget expense, and in turn improve the GGS Budget position. As an example of the potential impact of creating this new entity, capital grants of $2.3 billion were paid to RailCorp in 2013–14. If Treasury's objective was met, grants of this significance would then be treated as an equity investment, rather than an expense in the GGS Budget.

In 2017, Treasury's preferred option was progressed through legislation, but both agencies' central objectives for the proposed asset holding entity would continue to prove difficult to reconcile. To achieve Treasury's objective to improve the Budget result, the entity would need to generate a return on investment (this is further discussed below). However, TfNSW expressed concerns that the prioritisation of rail safety, and the effective management of governance, regulation and operations would be more complex in an entity with commercial imperatives.

Asset holding entities are a common approach to the management of transport assets in Australia and internationally, and there are a range of approaches to how they are structured and used. Such structures should be driven by the goal of improved asset management. Ultimately, TfNSW's objectives could have been delivered through a simpler entity structure. However, reconciling TfNSW's objectives with Treasury's imperative to deliver and justify a Budget improvement in the short-term resulted in an overly lengthy process and an unnecessarily complex outcome that places an obligation on future governments to sustain. There is still significant uncertainty as to whether the short-term improvements to the Budget can continue to be realised in the longer-term.

The Budget benefits of TAHE were claimed before the entity was legislated, committing the agencies to deliver, regardless of the complexities that subsequently arose

The 2015–16 GGS Budget treated the government's investment in TAHE (still known at this time as RailCorp) as an equity contribution. This had the immediate impact of improving the Budget result by $1.8 billion per annum. However, the legislation to enable the establishment of TAHE had not yet been passed by Parliament, key elements of the operating model were still under development, and imminent changes in accounting standards had the potential to impact TAHE's financial model. The decision to book the benefits in the Budget early committed the involved agencies to implement a solution that justified the 2015–16 Budget impacts, irrespective of the challenges that arose. 

TAHE's financial structure requires circular government investment to work

For the NSW Government to continue to treat its investment in TAHE as an equity contribution, rather than an expense to the Budget, there must be a reasonable expectation that TAHE will generate a sufficient rate of return as required by the Government Finance Statistics (GFS) framework. In doing so, it needs to recover a revaluation loss created by a $20.3 billion reduction in the value of its assets which was incurred in its first full year of operation. This loss occurred as a result of a revaluation of TAHE's assets when RailCorp (a not-for profit entity) became TAHE (a for-profit commercial entity) – and is discussed further in the 'Key findings' below.

TAHE generates a small portion of its income from transactions with the private sector but, as noted in our report 'State Finances 2021', TAHE receives the majority of its revenue (more than 80%) from access and licence fee agreements with Sydney Trains and NSW Trains. Both of these entities are funded by grants (a Budget expense) to TfNSW from the GGS Budget.

Based on Treasury’s correspondence with the ABS in 2015, TAHE was initially expected to pay a return on equity of 7% in 2016–17. The assumption of a 7% return persisted through to 2018, after the legislation enabling the establishment of TAHE was passed by Parliament. However, when the initial access and licence fees were agreed on 1 July 2020, this figure had been revised to an expected rate of return of 1.5% excluding the revaluation loss. This was below the long-term inflation target and did not include the recovery of the revaluation loss – risking the government's ability to treat its investment in TAHE as an equity contribution. Importantly, as TAHE is primarily reliant on fees paid by the state owned rail operators that, in turn, are funded by the GGS Budget (as an expense), the decision to change the returns model from 7% to 1.5% would in its own right have had a positive impact on the GGS Budget. However, the decision to use a 1.5% return would ultimately be problematic as it made it difficult to treat the government's contributions to TAHE as an equity investment, as discussed below.

On 14 December 2021, to avoid a qualified audit opinion, the NSW Government made the decision to increase TAHE's expected rate of return to 2.5%, equal to the Reserve Bank’s long-term inflation target.

In 2021-22, TAHE needed to start charging rail operators higher access and licence fees in order to generate a return of 2.5%, so as to support the government's treatment of its investment in TAHE as an equity contribution in the GGS Budget. This meant the government needed to provide additional grant (expense) funding to the state owned rail operators so they could pay the increased access and licence fees to TAHE. Based on current projections, TAHE is not expected to recover the revaluation loss until 2046.

There remains a risk that TAHE will not be able to generate a sufficient return on the NSW Government's investment without relying on increased funding to state owned rail operators so that they can in turn pay the higher access and licence fees. TAHE's ability to generate returns on government investment from other sources are uncertain and may not be achievable or sustainable. Current modelling highlights that TAHE remains largely reliant, through to 2046, on increasing fees (which are assumed to increase at 2.5% per annum from 2031 onwards when the current 10 year contracts with rail operators expire) paid by the state owned rail operators that remain principally reliant on GGS Budget grants.

The process of designing and implementing TAHE was not transparent to independent scrutiny

Our report 'State Finances 2021' commented that Treasury did not always provide this Office with information relating to TAHE on a timely basis. Similarly, during this performance audit, there were also multiple instances where auditees were unable to provide documentation regarding key activities in the process to deliver TAHE. Agencies also applied higher sensitivity classifications to large tranches of documents than was justified or required by policy. Of particular concern is the incorrect classification of documents as Cabinet sensitive information. The incorrect or over-classification of documentation as Cabinet sensitive delayed this Office's ability to provide scrutiny or independent assurance.

There was a lack of clarity around the roles and responsibilities of governance structures set up to oversee the design and implementation of TAHE

From 2014, multiple workstreams and advisory committees were established to progress the design and implementation of TAHE. For some of these committees and workstreams, there is limited information on what they were tasked to do and what they achieved. Most had ceased meeting by 2018, before significant work needed to deliver TAHE was completed.

The lack of clarity around the roles and responsibilities of these governance structures reduced opportunities for TfNSW and Treasury to reconcile their differing objectives for TAHE, and resolve key questions earlier in the process.

There was a heavy reliance on consulting firms throughout the process to establish TAHE, and the management of consultant engagements failed to ensure that agencies received independent advice to support objective decision-making

In 2020, Treasury and TfNSW failed to prevent, identify, or adequately manage a conflict of interest when they engaged the same 'Big 4' consulting firm to work on separate TAHE-related projects. Both agencies used the firm's work to further their respective views with regard to the financial implications of TAHE's operating model. At this time those views were still unreconciled.

Treasury engaged the firm to provide a fiscal risk management strategy and advice on the impact of changes to accounting standards. TfNSW engaged the same firm to develop operating and financial models for TAHE, which raised concerns regarding the viability of TAHE. Disputes arose around the findings of these reports. Treasury disagreed with some of the outcomes of the work commissioned by TfNSW, relating to accounting treatment and fiscal advice.

The management of this conflict (real or perceived) was left to the 'Big 4' consulting firm when it was more appropriate for it to be managed by Treasury and TfNSW. If these agencies had communicated more effectively, used available governance structures consistently, and shared information openly about their use of the firm and the nature of their respective engagements, these disputes might have been avoided. This issue, coupled with deficiencies in procurement by both agencies, reflected and further perpetuated the lack of cohesion in the design and implementation of TAHE.

More broadly, over the period 2014 – 2021, 16 separate consulting firms were employed to work on 36 contracts, valued at over $22.56 million, relating to TAHE ranging from accounting and legal advice, project management, and the provision of administrative support and secretariat services.

Consultants are legitimately used by agencies to provide advice on how to achieve the outcomes determined by government, including advising agencies on the risks and challenges in achieving those outcomes. Similarly, consultants can provide expert knowledge in the service of achieving those outcomes and managing the risks. However, the heavy reliance on consulting firms during the design and implementation of TAHE heightened the risk that agencies were not receiving value for money, were outsourcing tasks that should be performed by the public service, and did not mitigate the risk that the advice received was not objective and impartial. The risk that the role of consultants could have been blurred between providing independent advice to government on options and facilitating a pre-determined outcome was not effectively treated or mitigated. This risk was amplified because a small number of firms were used repeatedly to provide advice on one topic. The effective procurement and management of consultants is an obligation of government agencies.

Appendix one – Responses from audited agencies, and Audit Office clarification of matters raised in the TAHE formal response 

Appendix two – Classification of government entities 

Appendix three – About the audit 

Appendix four – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #372 - released 24 January 2023

 

Published

Actions for Rail freight and Greater Sydney

Rail freight and Greater Sydney

Transport
Information technology
Infrastructure
Management and administration
Project management
Service delivery

What the report is about

The movement of freight contributes $66 billion annually to the NSW economy. Two thirds of all freight in NSW moves through Greater Sydney, and the volume of freight moving through Greater Sydney is expected to increase by 48 per cent by 2036.

This audit assessed the effectiveness of transport agencies in improving the use of rail freight capacity in Greater Sydney, and to meet current and future freight demand.

What we found

Transport agencies do not have strategies or targets in place to improve the efficiency or capacity of the metropolitan shared rail network for freight.

The transport agencies acknowledge that they do not have sufficient information to achieve the most efficient freight outcomes and they do not know how to use the shared rail network to maximise freight capacity without compromising passenger rail services.

The Freight and Ports Plan 2018-2023 contains one target for rail freight - to increase the use of rail at Port Botany to 28 per cent by 2021. However, Transport for NSW (TfNSW)'s data indicates this target will not be met.

Sydney Trains records data on train movements and collects some data on delays and incidents. TfNSW collects data for the construction of the Standard Working Timetable and third-party contracts.

However, a lack of clarity around what data is gathered and who has ownership of the data makes data sharing difficult and limits its analysis and reporting.

The Freight and Ports Plan 2018-2023 includes the goal of 'Reducing avoidable rail freight delays', but the transport agencies do not have any definition for an avoidable delay and, as a result, do not measure or report them.

TfNSW and Sydney Trains are appointed to manage and deliver the Transport Asset Holding Entity of New South Wales (TAHE)'s obligations to allow rail freight operators to use the shared rail network. There are no performance measures in rail freight operator contracts or inter-agency agreements. This limits transport agencies' ability to improve performance.

TfNSW’s Freight Branch is working on four freight-specific strategies; a review of the Plan, a freight rail strategy, a port efficiency strategy and a freight data strategy.

TfNSW has not yet determined the timeframes or intended outcomes of these strategies.

What we recommended

Transport agencies should:

  • commit, as part of the review of Future Transport 2056, to delivering the freight-specific strategies currently in development and develop whole-of-cluster accountability for this work including timeframes, specific targets and clear roles and responsibilities 
  • improve the collection and sharing of freight data
  • develop a plan to reduce avoidable freight delays
  • systematically collect data on the management of all delays involving and/or impacting rail-freight
  • develop and implement key performance indicators for the agreements between the transport agencies.

Fast facts    

  • 288 million tonnes of freight volume predicted to pass through Greater Sydney in 2036, up from 194 million in 2016 (an increase of 48%)

  • 54 trucks that can be replaced by one 600 m long port shuttle freight train    

  • 26,671 freight trains that passed through the metropolitan shared rail network between 1 July 2020 and 30 June 2021

The movement of freight contributes $66.0 billion annually to the New South Wales economy — or 13 per cent of the Gross State Product. Two thirds of all freight in New South Wales moves through Greater Sydney, and the volume of freight moving through Greater Sydney is expected to increase by 48 per cent by 2036. This increasing demand is driven by increasing population and economic growth.

The sequence of activities required to move goods from their point of origin to the eventual consumer (the supply chain) is what matters most to shippers and consumers. Road can provide a single-mode door-to-door service, whereas conveying goods by rail typically involves moving freight onto road at some point. In Greater Sydney, 80 per cent of all freight is moved on road. Freight often passes through intermodal terminals (IMTs) as it transitions from one mode of transport to the next.

In 2016, Transport for NSW (TfNSW) released Future Transport 2056 - the NSW Government's 40-year vision for transport in New South Wales, which is intended to guide investment over the longer term. In Future Transport 2056, TfNSW noted that New South Wales will struggle to meet increasing demand for freight movements unless rail plays a larger role in the movement of freight.

Sydney Trains manages the metropolitan shared rail network, which is made up of rail lines that are used by both passenger and freight trains. The Transport Administration Act 1988 requires that, for the purposes of network control and timetabling, NSW Government transport agencies give ‘reasonable priority’ to passenger trains on shared lines. As the Greater Sydney population and rail patronage continue to grow, so too will competition for access to the shared rail network. See Appendix two for details of the area encompassed by Greater Sydney.

Freight operators can also use dedicated rail freight lines operated by the Australian Rail Track Corporation (ARTC - an Australian Government statutory-owned corporation). As the metropolitan shared rail network connects with dedicated freight lines, freight operators often use both to complete a journey.

TfNSW, Sydney Trains and the Transport Asset Holding Entity (TAHE) work in conjunction with other rail infrastructure owners and private sector entities, including port operators, privately operated IMTs and freight-shipping companies. TfNSW and Sydney Trains are responsible for managing the movement of freight across the metropolitan shared rail network. TAHE is the owner of the rail infrastructure that makes up the metropolitan shared rail network. The NSW Government established TAHE, a NSW Government state-owned corporation, on 1 July 2020 to replace the former rail infrastructure owner - RailCorp. The Auditor-General for New South Wales has commenced a performance audit on TAHE which is expected to table in 2022.

On 1 July 2021, TAHE entered into new agreements with TfNSW and Sydney Trains to operate, manage and maintain the metropolitan shared rail network. Until 30 June 2021, and in accordance with TAHE's Implementation Deed, TAHE operated under the terms of RailCorp's existing arrangements and agreements.

This audit assessed the effectiveness of TfNSW, Sydney Trains and TAHE in improving the use of rail freight capacity in Greater Sydney, and to meet current and future freight demand.

The audit focused on:

  • the monitoring of access to shared rail lines
  • the management of avoidable delays of rail freight movements
  • steps to increase the use of rail freight capacity in Greater Sydney.

Conclusion

Transport agencies do not have clear strategies or targets in place to improve the freight efficiency or capacity of the metropolitan shared rail network. They also do not know how to make best use the rail network to achieve the efficient use of its rail freight capacity. These factors expose the risk that rail freight capacity will not meet anticipated increases in freight demand.

Future Transport 2056 notes that opportunities exist to shift more freight onto rail, and that making this change remains an important priority for the NSW Government. However, the transport agencies acknowledge that they do not have sufficient information to achieve the most efficient freight outcomes. In particular, transport agencies do not know how to use the shared rail network in a way that maximises freight capacity without compromising passenger rail services.

Neither Future Transport 2056 nor the Freight and Ports Plan 2018–2023 give any guidance on how transport agencies will improve the efficiency or capacity of the shared rail network. Other than a target for rail freight movements to and from Port Botany, which TfNSW's data indicates will not be met, there are no targets for improving rail freight capacity across the shared network. The lack of specific strategies, objectives and targets reduces accountability and makes it difficult for transport agencies to effectively improve the use of rail freight capacity in line with their commitment to do so.

Sydney Trains and Transport for NSW do not effectively use data to improve rail freight performance and capacity.

To drive performance improvement when planning for the future, transport agencies need good quality data on freight management and movements. Sydney Trains records data on train movements in real-time and collects some data on delays and incidents. TfNSW collects data for the construction of the Standard Working Timetable (SWTT) and third-party contracts. However, the different types of data gathered and the separation between the teams responsible mean that there is a lack of clarity around what data is gathered and who has ownership it. This lack of coordination prevents best use of the data to develop a single picture of how well the network is operating or how performance could be improved.

Sydney Trains' ability to evaluate the effectiveness of its incident and delay mitigation strategies is also limited by a lack of information on its management of rail-freight related delays or incidents. While Sydney Trains collects data on major incidents, it can only use this to conduct event-specific analysis on the causes of an incident, and to review the operational and management response. The use of complete and accurate incident data would assist to define, identify and reduce avoidable delays. Reducing avoidable delays is a goal of the Freight and Ports Plan 2018–2023. More complete data on all incidents would help TfNSW to have more effective performance discussions with rail freight operators to help improve performance.

TfNSW has started developing strategies to identify how it can use rail freight capacity to achieve efficient freight outcomes, but it has not committed to implementation timeframes for this work.

TfNSW’s Freight Branch has started work on four freight-specific strategies to improve freight efficiency: a review of the Plan, a freight rail strategy, a port efficiency strategy and a freight data strategy. However, none of these strategies will be fully developed before the end of 2022. TfNSW has not yet determined the implementation timeframes or intended outcomes of these strategies, although TfNSW reports that it is taking an iterative approach and some recommendations and initiatives will be developed during 2022. 

Appendix one - Response from agencies

Appendix two - The Greater Sydney region

Appendix three - TfNSW strategic projects 

Appendix four - Sydney Trains path priority principles 

Appendix five - Sydney Trains delay management

Appendix six - About the audit 

Appendix seven - Performance auditing
 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #357 - released (19 October 2021).

Published

Actions for Grants administration for disaster relief

Grants administration for disaster relief

Treasury
Finance
Compliance
Fraud
Management and administration
Project management

What the report is about

The report examined whether NSW Treasury, Service NSW and the Department of Customer Service effectively administered grants programs funded under the $750 million Small Business Support Fund, including:

  • $10,000 Small Business Support Grant
  • $3,000 Small Business Recovery Grant.

What we found

The agencies effectively implemented the grants within required timeframes, reflecting the NSW Government’s decision to deliver urgent financial support to small businesses impacted by the COVID-19 pandemic.

NSW Treasury met urgent timeframes to design the grants and Service NSW made timely payments in line with the grants' objectives and eligibility criteria.

Service NSW and the Department of Customer Service strengthened processes to detect and minimise fraud in response to identified external fraud risks, and to investigate suspected fraudulent applications.

Fraud security checks and investigations are ongoing, and the agencies will not know the full extent of fraud across the grants until these processes have been completed.

The agencies regularly monitored and reported on the timeliness of payments to small business applicants but have not yet measured all benefits of the grants programs.

The $10,000 Support Grant and the $3,000 Recovery Grant have provided around $630 million in one off grant payments to eligible small businesses.

What we recommended

NSW Treasury should finalise and implement an evaluation of both grants programs, including obtaining feedback from businesses.

Service NSW should develop a framework that documents expected controls for how it administers grants, including business processes, fraud control and governance and probity requirements.

Service NSW should publish information on all grants programs, including grants distribution and uptake.

The Department of Customer Service should ensure its processes for managing conflicts of interest meets its policy requirements.

Upcoming performance audit

The Audit Office is conducting a further performance audit into grants administration for disaster relief focussing on bushfire grants. This is planned to complete in 2021-22.

Fast facts

Small Business Support Fund
  • $630m Grant payments made to small businesses under two grants administered
  • Over 52,500 Applications received a $10,000 Grant payment
  • Over 23,000 Businesses paid both $10,000 Support Grant and $3,000 Recovery Grant
  • 36,700 Applications received a $3,000 grant payment
Grant program administration
  • 11 Days taken to deliver the $10,000 Small Business Support Grant application website
  • 26 Days taken to deliver the $3,000 Small Business Recovery Grant application website

Further information

Please contact Ian Goodwin, Deputy Auditor-General on 9275 7347 or by email.

The NSW Government responded to the partial shutdown of the NSW economy caused by the COVID-19 pandemic in 2020 by, among other measures, announcing on 3 April 2020 that it would place $750 million into the Small Business Support Fund (the Fund).

Under the Fund, the NSW Government would pay one-off grants of up to $10,000 to small business impacted by the shutdown. The objectives of the $10,000 Small Business Support Grant ($10,000 Support Grant) were to:

  • ease the pressure on small businesses that have been affected by the COVID-19 pandemic
  • support the ongoing operations of small businesses highly impacted by the COVID-19 restrictions
  • deliver cash-flow into small businesses as soon as possible so that small businesses could meet pressing financial needs.

Grant applications were assessed against eligibility criteria that were determined by the NSW Government. The eligibility criteria for the $10,000 Support Grant required an employing small business to demonstrate it was significantly impacted by the COVID-19 pandemic by self-declaring or demonstrating a significant decline of 75 per cent or more in turnover compared to 2019. Documentation requirements were relaxed for small businesses within highly impacted industries.

In June 2020, the NSW Government announced a second round of one-off grants of up to $3,000 to small businesses that were highly impacted by the COVID-19 pandemic ($3,000 Recovery Grant). The objective of the $3,000 Recovery Grant was to help small businesses in 'highly impacted industries' — those directly impacted by the restrictions and closures put in place under the Public Health Orders — to meet the costs of safely reopening or scaling up operations.

The eligibility criteria for the $3,000 Recovery Grant required that a small business be in a highly impacted industry, demonstrate that it was significantly impacted by the COVID-19 pandemic by declaring a significant decline in turnover, and had costs associated with reopening under the 'COVID-Safe' requirements.

NSW Treasury and Service NSW implemented both grants on behalf of the NSW Government. The process of applying for a grant was intended to be quick and easy, with Service NSW using automated assessments and simple online application forms to process applications. Applicants applied for the $10,000 Support Grant through the Service NSW website between 14 April 2020 to 30 June 2020 and applied for the $3,000 Small Business Recovery Grant between 1 July 2020 and 31 August 2020.

At May 2021, around $520 million has been paid to over 52,500 grant applicants under the $10,000 Support Grant and around $109 million had been paid to around 36,700 grant applicants under the $3,000 Recovery Grant.

The Audit Office plans to undertake a performance audit into grants administration for disaster relief focussing on bushfire grants in 2021–22.

This audit assessed whether the grants funded under the $750 million Small Business Support Fund were effectively administered and implemented to provide disaster relief. It addressed the following questions:

  • Were funded grants programs planned, designed and targeted effectively?
  • Were funded grants programs implemented in line with the objectives and criteria and delivery requirements?
  • Have agencies established measures to monitor intended benefits and outcomes?

This audit did not seek to assess the effectiveness of any other grant programs or stimulus measures. It also did not seek to assess the impact of the funding on applicants, or the future prospects of small businesses that received support.

Conclusion

NSW Treasury and Service NSW effectively implemented two grants within required timeframes reflecting the NSW Government's decision to deliver urgent financial support to small businesses impacted by the COVID-19 pandemic in 2020. The $10,000 Support Grant and the $3,000 Recovery Grant have provided around $630 million in one-off grant payments to eligible small businesses.
NSW Treasury met urgent timeframes to design the grants and Service NSW made timely payments in line with the grants' objectives and eligibility criteria.

NSW Treasury met urgent timeframes to provide advice to the NSW Government on the grant design, proposed delivery partner, expected numbers of eligible businesses and the suitability of the proposed grant payment amount within the required timeframes. This was achieved within one day for the $10,000 Support Grant and within four days for the $3,000 Support Grant. In the context of the complex and changing pandemic and economic conditions between March and July 2020, NSW Treasury's advice to government outlined the risk, feasibility, expected demand estimates and assumptions for the grants.

NSW Treasury's demand projections were limited by uncertainty as to the pandemic's economic impact. Estimated demand for the grants was not met, resulting in around $120 million from the Small Business Support Fund remaining unspent.

Service NSW met urgent timeframes to stand-up both grants: 11 days for the $10,000 Support Grant and 26 days for the $3,000 Recovery Grant. It met agreed delivery requirements and made timely payments to small businesses in line with the grants' objectives and eligibility criteria. Over 65,000 businesses have received a payment under either grant, and over 23,000 businesses received both grants.

Gaps in project and risk management processes were expected given the tight timeframe to implement the grants.

The tight timeframe in which the agencies had to implement the grants contributed to gaps in project and risk management. The agencies advised that compromises were understood by both parties and were a necessary trade-off to ensure payments were made quickly.

Service NSW and the Department of Customer Service have acted to strengthen their processes to detect and minimise fraud in response to identified external fraud risks and to investigate suspected fraudulent applications since the grants commenced. Service NSW intends to further enhance fraud controls for grants applications and payments for future grants by implementing a fraud control framework by December 2021.

The agencies regularly monitored and reported on the timeliness of payments to small business applicants but have not yet measured all benefits of the grants programs.

Service NSW and NSW Treasury established processes to monitor and report on the timeliness of payments to grant applicants.

NSW Treasury has not yet measured all intended impacts of the grants, nor undertaken processes to obtain detailed feedback from grant recipients. Without these measures, there is limited insight into the extent to which the grants helped to support small businesses or ability to capture lessons which could be applied in future grants programs. NSW Treasury advises that an evaluation will commence from mid-2021.

1. Key findings

Around $630 million in timely one-off grant payments have been made to small businesses

Service NSW and NSW Treasury have paid around $630 million in one-off grant payments to small businesses via two grants administered under the $750 million Small Business Support Fund. At May 2021:

  • around $520 million has been paid to over 52,500 grant applications received for the $10,000 Small Business Support Grant ($10,000 Support Grant)
  • around $109 million has been paid to 36,700 grant applications received for the $3,000 Small Business Recovery Grant ($3,000 Recovery Grant).

Across both grants, over 65,000 small businesses received a payment across either grant, and over 23,000 businesses received payments under both grants.

NSW Treasury advise that, while no data was collected on the time to pay applicants for the $10,000 Support Grant, from its monitoring of the grants' outputs it was satisfied that payment timeframes met its expectations. Service NSW met its targeted time to pay applicants with payments made within ten days for the $3,000 Recovery Grant.

Funds for both grants were not fully spent due to limitations in data and uncertainty of the COVID-19 pandemic's impact. At May 2021, the final demand for the $10,000 Support Grant was around 30 per cent less than initially anticipated and the final demand for the $3,000 Recovery Grant was around 40 per cent less than initially anticipated.

NSW Treasury developed proposals establishing high level design and delivery expectations within rapid timeframes

NSW Treasury put forward proposals to the NSW Government for the two grants administered under the $750 million Small Business Support Fund. It met rapid timeframes for producing this advice: within one day for the $10,000 Support Grant and within four days for the $3,000 Recovery Grant. NSW Treasury's advice to the NSW Government on how to best target the total funding, eligibility criteria and the feasibility of delivering the grants through Service NSW was based on comparable grants programs – including the $10,000 Small Business Bushfire Support Grant – which at that time were ongoing.

The proposals established, at a high-level, the rationale for the grants, expected financial costs, risks and analysis on budget impacts, and confirmation that Service NSW could deliver the grants applications platform. NSW Treasury's demand projections were uncertain due to limited data in the early stages of the pandemic regarding potential economic impact.

Given the tight timeframes, the proposals did not fully consider all planning and design aspects for both grants. For example, there was minimal identification of the costs and benefits of the programs, and a lack of detailed design and delivery requirements. The proposals outlined that arrangements to finalise the risk management, controls, and auditing plan would be agreed by Service NSW and NSW Treasury before implementation.

In future circumstances where urgent advice on program design is required, NSW Treasury could set clearer expectations for the delivery agency, including fully considering costs, benefits and delivery requirements that could be carried through to project governance and implementation.

Service NSW implemented both grants in line with delivery expectations

Service NSW met urgent timeframes to stand-up both grants: 11 days for the $10,000 Support Grant and 26 days for the $3,000 Recovery Grant. Delivery expectations for each grant were established under a grant project agreement (grant agreement). Service NSW delivered the online application platform, assessment of applications, payments and reporting of the grants' uptake as per the grant agreements.

The urgent timeframes to deliver the grants contributed to gaps in Service NSW's project and risk management processes throughout the lifecycle of both grants. For example, the requirement to meet pressing timeframes for the $10,000 Support Grant launch meant agencies had reduced time to achieve sign-off on key documentation. As a result, important documents and processes – including the grant agreement, risk documentation and key business process and quality assurance processes – were not finalised ahead of launch.

Quality assurance and compliance processes for detecting fraud were not settled until after the conclusion of the applications for the $10,000 Support Grant, and were not completed until late 2020. Some project documents, including risk registers, communication plans and project briefs are still not finalised.

The longer timeframe to develop the $3,000 Recovery Grant meant that agencies were able to build on their understanding of the implementation requirements from the $10,000 Support Grant, and better document these expectations and understanding while ensuring that key documents and sign-offs were in place prior to launch.

Service NSW tightened its risk management and controls in response to evidence of fraudulent applications

In May 2020, Service NSW and the Department of Customer Service (DCS) were alerted to suspected fraudulent activity within grants administered by Service NSW. Initially, Service NSW anticipated that up to $8.8 million of the $10,000 Support Grant was at risk of exposure to fraudulent applications. However, Service NSW reported that, at April 2021, $1.9 million for the $10,000 Support Grant and $254,000 for the $3,000 Recovery Grant from paid applications were at risk of fraud exposure.

Following an internal review of the potential exposure to fraudulent or ineligible applications, Service NSW implemented additional automated security checks on applications, increased manual assessments of grant applications, established a dedicated taskforce for grants administration and engaged a unit within DCS to manage high-risk investigations.

Service NSW and DCS's increased governance and oversight has resulted in an established case management function, increased referrals to law enforcement, prioritised investigations of suspicious applications and the development of a 'Fraud Control Framework' aimed at addressing external fraud risks. Given Service NSW had limited experience in these processes in context of administering grant payments, such actions were an appropriate response.

Security checks and investigations of suspicious applications are ongoing. Service NSW will not know the full extent of fraud across the grants until these processes have been fully completed.

Service NSW and Department of Customer Service can improve how conflicts of interest are managed for future programs

Compliance with agency policies and processes to manage conflicts of interest and financial subdelegations demonstrates that investment decisions are being made by appropriately skilled and experienced staff, allowing agencies to operate efficiently, and reducing the risk of internal fraud.

DCS was unable to produce employee conflicts of interest declarations for the $10,000 Support Grant. Therefore, it is not known how many employees had completed conflicts of interest declarations for this round.

DCS provided information on conflicts of interest declarations for the $3,000 Recovery Grant. Twenty-nine per cent of declarations provided for employees undertaking grant assessments for the $3,000 Recovery Grant were incomplete at March 2021, and a further nine per cent were not finalised even though they indicated a real, potential or perceived conflict.

For future grants programs, ensuring compliance with conflicts of interest policies would help DCS and Service NSW to have greater confidence that conflicts of interest are appropriately identified and managed.

NSW Treasury has not yet measured all benefits or outcomes of the grants

In April 2021, NSW Treasury updated its evaluation plan for the $10,000 Support Grant and $3,000 Recovery Grant in support of an economic evaluation to commence from mid-2021. The updated evaluation plan outlines inputs, activities, and outputs as well as immediate, short term and medium term outcomes for both grants.

The evaluation will consider the extent to which both grants achieved their intended outcomes, and whether the economic benefits exceeded the costs to help inform decisions about the nature and design of any future small business support programs. This will complement, and feed into a broader review of all NSW Government COVID-19 stimulus measures.

Service NSW rapidly developed an approach to administer the grants

Over recent disasters, such as the 2019–20 bushfires and the COVID-19 pandemic, Service NSW has been responsible for administering grant programs on behalf of other government agencies.

Service NSW implemented both grants under its Project Management Framework and under each grant agreement with NSW Treasury as it does not have its own grants administration framework. To address the risks that emerged during delivery, Service NSW developed an approach to standardise and monitor the administration of the grants while they were being implemented.

Service NSW now has an opportunity to establish a grants administration framework, based on the processes, lessons and outcomes captured under the grants administration taskforce and in developing its fraud control framework. Embedding these processes into business as usual for grants administration will enable Service NSW to have a consistent set of expectations for controls, business processes and governance and probity requirements for future grants it implements.

2. Recommendations

By December 2021, NSW Treasury should:

1. finalise and implement an evaluation of the $10,000 Support Grant and $3,000 Recovery Grant, including obtaining direct feedback from businesses on how grant funds achieved the grant objectives.

By December 2021, Service NSW should:

2. develop a grants administration framework, which documents expected controls – including fraud controls – business processes and governance and probity requirements

3. publish information on all grants programs, including grants distribution and uptake.

By December 2021, the Department of Customer Service should:

4. ensure its process for managing conflicts of interest meets policy requirements by:

  • ensuring employees promptly declare any real, potential or perceived conflicts of interest
  • annually producing a list of conflicts of interest for records retention purposes
  • requiring a separate register of conflicts of interest declarations where a grant program is deemed as high risk.

3. Lessons for grants administered within urgent timeframes

The two grants this audit examined were administered within a context of urgent timeframes, and increased complexity and uncertainty about the impact of the COVID-19 pandemic. The following lessons are shared to assist sponsor and delivery agencies in administering future grants where rapid implementation is required.

Sponsor agencies should consider the following lessons:

1. develop an approach to define and measure benefits for rapidly developed programs and projects where a full business case and cost-benefit analysis is not feasible

2. establish common processes and expectations for co-administered grants:

  • periodically assure agencies' capability to deliver grants programs
  • agree and establish risk appetite statements with administering agencies
  • clearly establish expected performance levels and targets under any agreement

3. review the processes and outcomes of rapidly developed programs, capture lessons learned, and apply these in planning and delivering future programs.

Delivery agencies should consider the following lessons:

1. risk management and risk appetite:

  • perform robust assessment procedures to ensure risks associated with delivery of the project are identified
  • ensure the controls implemented adequately address identified risks
  • agree and document the acceptable risk appetite at the outset
  • review risk management processes after the grants are issued when unable to finalise risk management processes ahead of launch

2. grant agreements between NSW public sector agencies:

  • ensure agreements are finalised in a timely manner
  • ensure agreements clearly outline:
    • roles and responsibilities of both parties,
    • changes in scope of services provided
    • fees and charges applicable

3. frameworks for grants administration:

  • ensure that there is a common set of expectations in place to guide grants administration including standard controls and processes for managing risk, capturing lessons learned and reporting on outcomes.

Appendix one – Response from agencies

Appendix two – Summary of other COVID‑19 Stimulus and Support for small businesses in NSW in April 2020

Appendix three – Public Health Orders

Appendix four – Highly impacted industries

Appendix five – About the audit

Appendix six – Performance auditing

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #352 - released (24 June 2021).

 

Published

Actions for WestConnex: changes since 2014

WestConnex: changes since 2014

Transport
Compliance
Infrastructure
Internal controls and governance
Management and administration
Project management
Risk

What the report is about

The report examined whether Transport for NSW (TfNSW) and Infrastructure NSW (INSW) effectively assessed and justified major scope changes to the WestConnex project since 2014.

What we found

NSW Government decisions to fund WestConnex-related projects outside WestConnex's $16.812 billion budget have reduced transparency and understate the full cost of WestConnex.

The NSW Government's decision to separate Sydney Gateway from WestConnex has reduced transparency over the cost of the road component of Sydney Gateway. $1.76 billion of the cost to complete Sydney Gateway is funded outside the WestConnex budget.

Network integration costs, currently estimated at $2.3 billion, are also funded outside the WestConnex budget. Many of these costs are directly attributable to WestConnex and ought to be included in the reported budget.

The Parramatta Road Urban Amenity Improvement Program, costing $198 million, should also be included as part of the WestConnex reported budget.

Decisions to exclude or remove these elements from WestConnex without justification have seen $4.26 billion of projects funded outside the $16.8 billion budget.

Positively, robust analysis was used to develop and incorporate design improvements into the 2015 WestConnex Updated Strategic Business Case.

The separate components of WestConnex underwent all required assurance reviews. However, the NSW Government's assurance framework does not require ongoing ‘whole-of-program’ assurance for large and complex projects like WestConnex. The absence of a holistic review of WestConnex allows for some costs and benefits to avoid scrutiny.

What we recommended

TfNSW should:

  • review the impact of scope changes on project objectives, costs and benefits for complex infrastructure projects
  • ensure that estimated costs and benefits of works which are reasonably required to meet consent conditions are included in business cases for complex large infrastructure projects
  • establish centralised and project specific record keeping for major infrastructure projects.

Infrastructure NSW should provide transparent whole of program assurance on total costs and benefits when complex projects are split into sub-projects.

Government should consider enhancing public transparency of existing infrastructure assurance processes by requiring that large complex infrastructure programs undergo periodic review at a whole-of-program level.

Fast facts

  • $16.812b 2015 WestConnex business case budget
  • $2.3b current estimated cost of network integration works to enable WestConnex, funded outside the WestConnex budget
  • $1.76b cost to complete Sydney Gateway to enable WestConnex and also funded outside the WestConnex budget
  • $198m Parramatta Road Urban Amenity Improvement Program, originally part of WestConnex but now funded outside the WestConnex budget

WestConnex

WestConnex is a 33 km motorway network that will link the western and south‑western suburbs with the Sydney CBD and the Airport and Port Botany precinct. It will also connect with proposed future motorway links to the north shore, northern beaches, and southern Sydney. The project is being delivered in three stages, with completion scheduled for 2023.

When first conceived by Infrastructure NSW (INSW) in 2012, WestConnex was described as a single integrated concept. In August 2013, government approved a business case for an integrated concept of WestConnex, with an estimated cost of $14.881 billion (in nominal outturn costs). Transport for NSW (TfNSW) is the government agency (sponsor agency) accountable for the delivery of WestConnex in accordance with the business case. In August 2014, the NSW Government established the Sydney Motorway Corporation to fund, deliver and operate WestConnex.

In November 2015, the NSW Government publicly released an updated WestConnex business case with greater detail and design enhancements, which increased the estimated cost to $16.812 billion.

Subsequent to this update, further changes were made to the design, including realignment of the M4 to M5 Link connection to the Western Harbour Tunnel project, an expanded interchange at Rozelle, the deletion of the Camperdown Intersection, and the addition of the Iron Cove Link. The reported budget for WestConnex was not changed as a result of these design updates.

To fund WestConnex, Sydney Motorway Corporation consolidated a concessional loan of $2 billion from the Australian Government, private sector debt and equity funding from the State. The Australian Government also provided a $1.5 billion contribution to the State to partially fund construction of WestConnex.

In August 2018, the NSW Government sold 51 per cent of its stake in Sydney Motorway Corporation for $9.26 billion. At the time of writing, the NSW Government is in the process of selling its remaining 49 per cent stake of Sydney Motorway Corporation.

About this audit

In the course of delivering a complex major infrastructure project, it is reasonable to expect changes to the original design and scope. Changes may occur as the design moves from a high‑level concept to a detailed design for project delivery, as new risks or issues are identified, as demands change, or as other interdependent projects are approved. Changes can also occur in response to potential cost or delivery overruns which arise as a result of planning deficiencies. Where design and scope changes significantly change the project costs and/or expected benefits, the justification for these changes should be robust and transparent.

Following our 2014 performance audit, 'WestConnex: Assurance to the government', the NSW Government established the Infrastructure Investor Assurance Framework (IIAF) to improve accountability and transparency over major projects that are developed, procured, or delivered by government agencies. Under the framework, TfNSW, as project sponsor, is responsible for ensuring the WestConnex project meets all IIAF requirements. These include ensuring the project remains strategically aligned and viable, and benefits are on track. INSW is responsible for coordinating the assurance review process and reporting directly to NSW Cabinet on project delivery against time, budget and risks to project delivery.

The objective of this performance audit is to assess whether TfNSW and INSW effectively assessed and justified major scope changes to the WestConnex project since 2014.

 

Conclusion

Government decisions to separate WestConnex related projects and deliver them outside WestConnex's 2015 business case budget of $16.812 billion has understated the total cost of WestConnex achieving its objectives. The rationale for separating these elements from the WestConnex project scope has not been transparent. Together, these projects represent costs of $4.26 billion funded outside the $16.812 billion WestConnex budget.

Since 2015, the NSW Government has removed several projects from the scope described in the 2015 WestConnex business case, and funded them separately:
  • In mid‑2017, the Sydney Gateway became a separate project outside WestConnex. This project, estimated in 2015 to cost $800 million, now has an estimated cost of $2.56 billion. The project remains partly funded by an $800 million contribution from the $16.812 billion WestConnex budget, with $1.76 billion funded outside the WestConnex budget.
  • In late 2018, the Parramatta Road Urban Amenity Improvement Program became a separate project outside the 2015 WestConnex budget. This project was part of the 2015 WestConnex Business Case and is intended to create urban renewal opportunities around Paramatta Road. It is estimated to cost $198 million.

Work required to integrate WestConnex with existing roads ('network integration') was funded outside the $16.812 billion budget for the November 2015 WestConnex business case. TfNSW is obliged to deliver network integration works to meet the conditions of planning approval for WestConnex. As such, these costs should be included in the WestConnex budget. The current estimated cost of these network integration works is $2.3 billion.

The rationale to exclude or remove each of these elements from the WestConnex project scope has not been transparent, nor supported by robust analysis and justification. These elements are required for WestConnex to achieve its objectives. The additional project costs will also deliver additional benefits not included in the 2015 WestConnex business case. Removing them understates the total cost of achieving the objectives set out in the 2013 and 2015 WestConnex business cases.

WestConnex's complex financing arrangements further reduce transparency on costs.

Transparency over the total cost of WestConnex – including elements funded from other project budgets – is further limited by the project's complex financing arrangements.

Prior to 2018, the Audit Office provided assurance on costs borne and levied by Sydney Motorway Corporation and its controlled entities. Since the NSW Government sold its majority stake in WestConnex in August 2018, the Auditor‑General no longer has the mandate to provide this assurance. Considering this, and the lack of transparency on the cost of projects removed from the WestConnex project scope, there is no transparent or comprehensive view of the total cost to deliver WestConnex – nor of how these cost would be offset by the sale of the government's remaining stake.

There is no 'whole‑of‑program' assurance over the WestConnex program of works. This limits transparency and confidence that WestConnex will meet intended objectives within its budget.

After INSW conducted a gateway review of a draft of the 2015 WestConnex Business Case under the IIAF, the project was broken up into separate components to support staged delivery. Each of these projects, including the Sydney Gateway, as well as the Network Integration Program, underwent the required assurance reviews under the IIAF. INSW also provided monthly progress updates to government. These individual projects are, in themselves, significant in scale and complexity. Addressing them as discrete components for the purposes of the assurance review process is justified and there is no requirement under the IIAF to holistically review projects which together deliver final benefits of the WestConnex program. However, whole‑of‑program review would improve transparency over total costs and benefits.

In 2016, TfNSW revised the design of the M4‑M5 Link and Rozelle to address traffic and integration issues.

TfNSW identified that the concept designs used for the M4‑M5 Link and Rozelle Interchange in the 2015 WestConnex Business Case would not integrate well with surface roads, including the proposed Bays Precinct, and would result in increased traffic on Victoria Road and the ANZAC Bridge. Following a comprehensive review conducted in mid‑2016, TfNSW refined the design of the M4‑M5 Link and Rozelle Interchange to address these limitations without increasing the cost of delivery. TfNSW documented the rationale for the design changes, including how the changes improved on the original design to increase capacity, improve traffic conditions and create more open space.

1. Key findings

Government decisions to fund WestConnex related projects outside of WestConnex's $16.812 billion reported budget have reduced transparency over costs and understate the full cost of WestConnex

In 2015, the work required to integrate WestConnex with existing roads ('network integration') was funded as a separate project with an estimated cost of $1.534 billion outside the 2015 WestConnex budget of $16.812 billion. TfNSW then created the Network Integration Program to respond to the conditions of planning approval for WestConnex. The current estimated cost to deliver all network integration works is $2.3 billion.

Since the 2015 WestConnex Business Case, the NSW Government has removed several elements from the scope of WestConnex and funded them as separate projects, while keeping the published WestConnex budget at an estimated $16.812 billion. Projects removed include:

  • Sydney Gateway, currently costed at $2.56 billion (with an $800 million contribution from WestConnex)
  • Parramatta Road Urban Amenity Improvement Program, costed at $198 million in late 2018 and funded though new funding to the Greater Sydney Commission.

Together, these projects represent costs of $4.26 billion that are not included in the WestConnex budget, but are required for WestConnex to achieve the objectives of the 2013 and 2015 WestConnex Business Cases. The costs of these elements in supporting the objectives of WestConnex is not tracked centrally, and there is no single point of oversight over them. Exhibit 1 compares total WestConnex forecast costs (including related projects) between November 2015 and April 2021.

 

November 2015
($ million)

April 2021
($ million)
WestConnex
Stage 1
Stage 1A (M4 Widening) 497 517
Stage 1B (M4 East) 3,802 3,782
Total 4,299 4,299
Stage 2
King Georges Road Interchange 131 131
New M5 4,335 4,335
Sydney Gateway Contribution 800 800
Total 5,266 5,266
Stage 3
M4‑M5 Link and Rozelle Interchange 7,049 7,049
Urban renewal (Parramatta Road) 198 ‑‑
Urban renewal (Rozelle) ‑‑ 198
Total 7,247 7,247
Total reportable WestConnex 16,812 16,812

Exhibit 1: WestConnex and related projects forecast costs
  November 2015
($ million)
April 2021
($ million)
Related projects
Network integration 1,534 2,300
Urban renewal (Parramatta Road) ‑‑ 198
Sydney Gateway Road Component ‑‑ 1,760
Total 1,534 4,258

Source: AO research.

Many network integration costs are directly attributable to WestConnex and ought to be included in the reported budget for WestConnex

Prior to 2015, the scope of WestConnex included enabling works needed before or during construction, as well as funding for future works to address any adverse traffic outcomes created by WestConnex which become apparent after its opening. These works are also known as network integration works.

When government approved the 2015 WestConnex Business Case, it noted that the project would require $1.534 billion for network integration works to address the impacts of WestConnex on the road network. However, the WestConnex project budget of $16.812 billion did not include funding for network integration works. Instead, Roads and Maritime Services (RMS, now TfNSW) was to fund network integration through its normal budget allocation.

It is important to recognise these costs as part of the total WestConnex project cost because:

  • TfNSW created the Network Integration Program to respond to network traffic and transport elements of the planning conditions of approval for WestConnex granted by the then NSW Department of Planning and Environment under the Environment, Planning and Assessment Act 1979.
  • NSW Treasury guidelines for business cases note that accurate cost estimates include assessment of the financial impact of meeting the conditions of planning approval.
  • Travel time and vehicle operating cost benefits attributed to the WestConnex project in the 2015 WestConnex Business Case assume that some network integration works, then costed at $373 million, were in place.

Refer to Appendix two for more detail on network integration works.

Some of the projects in the WestConnex Network Integration Program provide community and place benefits, such as parklands and cycleways. These benefits have not been attributed to WestConnex. Additionally, some network integration works are likely to deliver additional traffic related benefits to WestConnex. As the Network Integration Program’s primary purpose is to meet the conditions of planning approval for WestConnex, TfNSW should attribute all the costs and benefits of the program to WestConnex.

To September 2021, the total funded cost of the Network Integration Program is approximately $2.077 billion. TfNSW estimates that it will need a further $222 million to complete all expected network integration works.

The NSW Government's decision to separate Sydney Gateway from WestConnex has reduced transparency and accountability for TfNSW's underestimation of the cost of the road component of Sydney Gateway

Sydney Gateway is a high‑capacity connection between the new St Peters Interchange and the Sydney Airport and Port Botany precinct. It includes a road and rail components. The road component was included in the scope of WestConnex in the 2015 WestConnex Business Case. The November 2015 design, which TfNSW costed at $800 million, involved separate roadways from the St Peters Interchange to the International terminal, and to the domestic terminals and Mascot airport precinct.

By October 2016, TfNSW was aware that the $800 million budget for Sydney Gateway was insufficient and revised the forecast cost for the road component to $1.8 billion. The original cost estimate did not sufficiently consider the cost of:

  • constructing a complex design adjacent to the airport precinct
  • obtaining access to land required for the project
  • managing environmental contamination.

On 9 August 2017, the then Minister for WestConnex announced that the Sydney Gateway project was not part of WestConnex.

The 2015 WestConnex Business Case notes that material changes to the WestConnex budget, funding, scope, or timeframe are subject to Cabinet approval processes. It states that, when seeking approval for material changes, the portfolio Minister will make a submission to the relevant Cabinet Committee. Changes in project scope required the approval of the then Cabinet Committee on Infrastructure and should have been endorsed by the WestConnex Interdepartmental Steering Committee.

TfNSW and the NSW Department of Premier and Cabinet (DPC) assert that there is no documentation to support the government’s decision to separate Sydney Gateway from the WestConnex Program, or the WestConnex Interdepartmental Steering Committee's endorsement of a submission to Cabinet seeking approval for the separation.

The established governance processes for major scope changes were not followed in this instance. The lack of transparency regarding government's decision to separate Sydney Gateway from WestConnex also reduces visibility of TfNSW's underestimation of the cost of delivering the road component of Sydney Gateway.

The November 2018 Final Business Case for Sydney Gateway, which was approved by the government, included an estimate of $2.45 billion (nominal outturn cost) for the road component. This estimate included an $800 million contribution from WestConnex. A more recent estimate (late 2020) for this project is $2.56 billion (nominal outturn cost).

The Parramatta Road Urban Amenity Improvement Program should be included as part of the WestConnex budget

A specific objective of the 2015 WestConnex Business Case was the creation of opportunities for urban renewal along and around Parramatta Road. The business case included an allocation of $198 million in the $16.812 billion WestConnex budget for the Parramatta Road Urban Amenity Improvement program, designed to implement aspects of the objective. In November 2018, the NSW Government removed the Parramatta Road Urban Amenity Improvement Program from the WestConnex program of works and reallocated the $198 million (inside the $16.812 billion WestConnex budget) for urban renewal works around the Rozelle Interchange. As part of this decision, government approved new funding of $198 million to the Greater Sydney Commission for the urban amenity program, outside the $16.812 billion WestConnex budget. This understates the cost of WestConnex meeting its objectives by $198 million.

There is no requirement for ongoing ‘whole‑of‑program’ assurance of the WestConnex program of works, including related projects

In August 2015, INSW conducted its first Gateway Review of WestConnex as a program consisting of composite projects. Following that review, TfNSW registered each of the components of WestConnex with INSW as individual projects, rather than keeping WestConnex registered as a program or mega‑project. This is not inconsistent with the IIAF and all WestConnex related projects, including Sydney Gateway and the Network Integration Program, have undergone independent assurance reviews as individual projects under the IIAF.

Once a program like WestConnex is broken down into its composite parts, there is no requirement for the sponsor agency (TfNSW) or INSW to provide independent assurance on the program as a whole until it is completed. This is then done as part of the Gateway review for benefits realisation, which examines whether project benefits are being measured and meet expectations. These individual projects are, in themselves, significant in scale and complexity. While addressing them as discrete components for the purposes of the assurance review process can be justified, the absence of strategic, holistic reviews of WestConnex allows for total costs and benefits to become opaque and avoid scrutiny. Programs of this scale require greater ongoing transparency on total costs and benefits in order to ensure confidence they will meet intended objectives within budget.

There is a lack of public transparency on the total costs and benefits of the WestConnex project

Prior to 2018, the Audit Office provided assurance on costs borne and levied by Sydney Motorway Corporation and its controlled entities. Since the NSW Government sold 51 per cent of its stake in WestConnex in August 2018, the Auditor‑General no longer has the mandate to provide this assurance. The Audit Office is also unable to provide any assurance regarding the performance of tolling concessions.

This means that the total costs of WestConnex, including those levied on road users through tolling, are not reported alongside the full cost of delivering the project. This information, and independent assurance over that information, would provide transparency and context to the outcome of government's sale of its interest in WestConnex.

To enhance the transparency of existing infrastructure assurance processes, government could consider requiring large and complex infrastructure programs to undergo periodic review at a whole‑of‑program level. This could take the form of annual reports to Parliament on the total costs and benefits of selected large and complex projects by the responsible agency. The reports could include an assessment of the cost to government and cost to the community of funding and financing. Independent assurance of the agency report would provide Parliament with greater confidence that infrastructure is delivered economically and providing value for money for the people of NSW.

The Australian National Audit Office provides similar assurance on selected Department of Defence acquisition projects as part of its annual Major Projects Report.

Design enhancements included in the 2015 WestConnex Updated Strategic Business Case were supported by robust analysis

The 2015 WestConnex Business Case contained more detail than the 2013 WestConnex business case. Design enhancements were made as a result of modelling analysis conducted over the two years since the 2013 business case. Enhancements included a full underground link between Kingsgrove and St Peters as part of the New M5 and re‑alignment of the M4‑M5 link tunnel (Stage 3) to include the Rozelle Interchange. The Rozelle Interchange will provide a direct connection to the Anzac Bridge and Victoria Road, and will enable a connection to the proposed Western Harbour Tunnel and Beaches Link. A map and description of these elements can be found at Exhibits 2 and 3 of this report.

In 2016, TfNSW revised the design of the M4‑M5 Link and Rozelle to address traffic and integration issues

As part of preparing the 2015 WestConnex Business Case, TfNSW prepared a Project Definition and Delivery Report (PDDR) for the M4‑M5 Link. This report describes the scope of the project, including a high‑level concept design. TfNSW identified limitations with the proposed design of the M4‑M5 in the PDDR, which it would need to address as the project moved to a detailed design stage. In particular, these limitations included:

  • poor integration with the Bays Precinct masterplan
  • traffic capacity constraints on Victoria Road and Anzac Bridge
  • construction complexity.

Following a comprehensive review in mid‑2016, TfNSW changed the design of the M4‑M5 Link and Rozelle Interchange to address these limitations. These changes included:

  • deletion of the Camperdown intersection to improve traffic conditions on Parramatta Road
  • a fully underground and larger Rozelle Interchange with 10‑hectare dedicated parklands
  • a toll‑free tunnel link from Iron Cove Bridge to Anzac Bridge
  • increasing the lanes in the dual tunnels from three to four each way.

TfNSW documented, but did not publish, the rationale for the design changes, including how the changes addressed the limitations of the previous design while providing increased community benefit through the creation of open space. TfNSW undertook cost comparison studies which estimated that these changes would have a neutral impact on the estimated project cost while achieving the same or improved benefits.

TfNSW's record‑keeping systems for large infrastructure investments negatively impact accountability and transparency

In response to our formal requests for relevant information, made during the conduct of this audit, TfNSW advised that complete and valid records of key decision‑making processes, analysis and advice were unavailable. Additionally, TfNSW often provided information that was incomplete or unverifiable (for instance, unsigned briefing notes). This is not consistent with accepted governance practices and does not comply with the requirements of the State Records Act 1998.

We also requested that TfNSW provide a list of relevant documents held by the Sydney Motorway Corporation (SMC). While TfNSW acknowledged that SMC may hold material relevant to the audit, TfNSW did not have a list or description of these documents. As SMC is now a majority privately held entity, both the Audit Office and TfNSW have limited power to require SMC to provide documentation.

The delivery timeframe for large and complex infrastructure projects such as WestConnex frequently exceeds five years, and some projects can take over a decade to deliver. These projects represent a significant investment of public resources and government agencies should expect independent review and assurance activities such as performance audits. The establishment of dedicated record keeping facilities for major infrastructure projects, such as data rooms, would improve transparency and accountability. This would ensure that the use of public resources is fully auditable in line with public expectations and the requirements of the Government Sector Finance Act 2018, the State Records Act 1998 and the Public Finance and Audit Act 1983.

2. Recommendations

By December 2021, TfNSW should:

1. review the impact of scope changes on project objectives, costs and benefits for complex infrastructure projects

2. when preparing business cases for complex large infrastructure projects, ensure that the estimated costs and benefits of works which are reasonably expected to meet consent conditions are included in the overall project cost and its benefits (as per Treasury guidelines)

3. establish and maintain centralised and project‑specific record keeping, including through dedicated project data rooms, to ensure major infrastructure projects can readily be subject to external oversight and assurance.

By June 2022, INSW should:

4. provide transparent whole‑of‑program assurance on total costs and benefits throughout the project life‑cycle when complex projects are split into sub‑projects.

By June 2022, NSW Government should:

5. consider enhancing the public transparency of existing infrastructure assurance processes by requiring that large complex infrastructure programs undergo periodic review at a whole‑of‑program level. This could take the form of reports to Parliament on the total costs and benefits on selected large and complex projects by the responsible agency, including cost to government and cost to community of funding and financing, as well as an accompanying independent assessment of the agency report.

Following our 2014 performance audit report 'WestConnex: Assurance to the government', the NSW Government established the Infrastructure Investor Assurance Framework (IIAF). INSW is responsible for the development, implementation and administration of the IIAF. The assurance framework involves gateway reviews, health checks, deep dive reviews, and project monitoring and reporting at various stages in the lifecycle of a project. The main aims of the IIAF are to help ensure major infrastructure projects are delivered on time and on budget, and to ensure that reports are regularly monitored by the Cabinet of the NSW Government. The IIAF gateway review process is compulsory for all significant investments and expenditure under the NSW Treasury Gateway Policy.

In accordance with the IIAF, INSW is responsible for the following:

  • providing a dedicated Assurance Team including Gateway Review Managers to coordinate Reviews
  • determining appropriate expert reviewers, and manages scheduling, commissioning and administration of Assurance Review reports. Infrastructure NSW is independent of the Expert Review Team
  • monitoring Tier 1 – High Profile/High Risk projects, Tier 2 and Tier 3 (if required) project performance through independent Assurance Reviews
  • providing independent analysis and advice on key risks and any corrective actions recommended for Tier 1 – High Profile/High Risk, Tier 2 and Tier 3 projects
  • escalating projects to Infrastructure Investor Assurance Committee (IIAC) and Cabinet where projects present ‘red flag issues’ and where corrective action is needed
  • working with delivery agencies to register all capital projects with an estimated cost greater than $10.0 million and ensures they are risk profiled and assigned a risk‑based project tier with an endorsed IIAF Project Registration report
  • preparing forward looking annual Cluster Assurance Plans
  • maintaining and continuously improves the IIAF process
  • reporting to the IIAC, Cabinet and Infrastructure NSW Board
  • regularly report to NSW Treasury on the performance of the IIAF.

In relation to WestConnex, TfNSW is the sponsor agency responsible for meeting relevant IIAF requirements, including:

  • registering and risk profiling projects
  • IIAF gateway, health check, and deep dive assurance reviews
  • regular reporting.

Under the IIAF, it is mandatory for all capital projects valued over $10.0 million to be registered with INSW. Capital projects can be registered either as a program (comprising of a group of related projects or activities) or as a project (which may or may not be part of a program).

According to the IIAF, programs tend to have a lifespan of several years and aim to deliver outcomes and benefits related to an organisation's strategic objectives. Projects tend to have a shorter lifespan, and deal with outputs. Projects can, however, be grouped under a single program if they are similar in nature or if they are aimed at collectively achieving a strategic objective. Complex projects can be delivered in multiple stages, under different contracts, and across different time periods.

The last assurance review of the entire WestConnex program of works as a whole was in 2015

INSW conducted the first IIAF gateway review of WestConnex in August 2015. TfNSW developed a draft WestConnex Updated Strategic Business Case to consolidate the latest analysis on WestConnex, and to confirm that the project remained fit for purpose, economically viable, and financially deliverable. The review followed a recommendation in our 2014 performance audit report that business cases be thoroughly revisited.

During September 2015, INSW conducted additional informal reviews to identify strategic risks associated with public release of the WestConnex business case. Subsequently, INSW gave the Premier of NSW its views on the draft business case, including the following points:

  • The $398 million budget for Sydney Gateway was insufficient to meet the benefits claimed in the business case for a ‘functional’ connection to Sydney Airport and Port Botany. INSW studies indicate a future‑proof solution would require a minimum spend of $755 million.
  • Enabling works for WestConnex estimated at $1.534 billion were excluded from the cost of WestConnex. Significant work remained for RMS to identify mitigation measures to address planning approvals and network performance issues.
  • Enabling works (a Southern Connector), an access ramp and surface road improvements within St Peters were excluded from the draft 2015 business case despite their inclusion in the WestConnex scope in the 2014–15 State Budget.
  • The overall cost of works not funded within the WestConnex budget ranged from $2.011 billion to $2.196 billion. This included the enabling works, access ramp and surface road improvements and the shortfall for Sydney Gateway.

All WestConnex related projects, including Sydney Gateway have undergone independent assurance reviews under the IIAF

Since INSW submitted the first WestConnex progress update report to Cabinet in June 2015, INSW has been reporting monthly on the different stages of the WestConnex Program, including Sydney Gateway, as the projects were registered with INSW as High‑Profile, High‑Risk projects. Separate reporting enabled INSW to report and review each stage with more detailed scrutiny, compared to the reporting and reviewing at a program level.

WestConnex Stage 2 (New M5) underwent both mandatory and non‑mandatory reviews at key points in the project lifecycle. Three mandatory gateway reviews – at Gate 2 (Final business case), Gate 3 (Readiness for market), and Gate 4 (Tender evaluation) – were conducted by TfNSW before the introduction of IIAF. Four non‑mandatory health check reviews and one non‑mandatory deep dive review were conducted after the introduction of the IIAF managed by INSW.

Similarly, WestConnex Stage 3 projects – M4‑M5 link, M4‑M5 Tunnels, and Rozelle Interchange – also underwent mandatory and non‑mandatory reviews at key points in their lifecycle under IIAF.

The M4‑M5 Link had two mandatory gateway reviews and one non‑mandatory health check review under IIAF. These reviews were conducted before Stage 3 was split into two stages, due to major design changes to the Rozelle Interchange and the M4‑M5 tunnels.

The M4‑M5 tunnels had two mandatory gateway reviews (at Gates 3 and 4), one non‑mandatory health check review, and one non‑mandatory deep dive review under IIAF.

Rozelle Interchange also underwent three mandatory gateway reviews at Gate 3 (part 1), Gate 3 (part 2), and Gate 4, two non‑mandatory health check reviews, and one non‑mandatory deep dive review under IIAF.

Since mid‑2017, the Sydney Gateway project has undergone required independent assurance reviews, as well as a number of optional assurance reviews

In November 2016, INSW conducted a mandatory Gate 1 gateway review on a strategic business case for the Sydney Gateway Project. TfNSW did not proceed with this business case. Following the separation of Sydney Gateway from WestConnex in mid‑2017, TfNSW developed a new business case for Sydney Gateway. It has undergone the required Gate 1, Gate 2, and Gate 3 gateway reviews, as well as two non‑mandatory health check reviews, and three non‑mandatory deep dive reviews under IIAF.

Network integration works have undergone all IIAF required assurance reviews

TfNSW completed a strategic business case for the Network Integration Program in August 2020, and INSW completed a gateway review in November 2020. This is despite network integration projects starting as early as 2015, with $645 million having been spent by June 2020. The strategic business case included a prioritisation process for completing remaining works in the program. Prior to November 2020, TfNSW registered individual network integration projects with INSW, and these projects have undergone gateway reviews where required.

The Network Integration Program strategic business case does not include Rozelle interchange network integration works ($353 million) and additional network integration works to settle a contractor claim adjacent to St Peters Interchange ($190 million). These were excluded from the business case on the basis they had already been approved by government, and as such were not subject to the prioritisation elements of the business case. TfNSW has not developed separate business cases for these works, although the scope of the St Peters Interchange works was developed through a negotiated process.

TfNSW did not prepare business cases for some network integration works which have commenced, including the $323 million Campbell Road/Euston Road works

Prior to its development of the August 2020 strategic business case, TfNSW did not prepare business cases for many network integration works that have commenced, and in some instances were completed, before 2019. Significantly, TfNSW did not prepare a business case for the Campbell Road/Euston Road works, which cost $323 million and have been completed.

In 2016, TfNSW’s Business Case Policy requires the creation of business cases for capital projects costing over $1.0 million. At the time of writing this report, TfNSW’s draft policy requires full business cases for capital projects costing $10.0 million or more.

There is no requirement for ongoing ‘whole‑of‑program’ assurance of the WestConnex program of works, including related projects

INSW conducted its first gateway review of WestConnex (as a program, which consisted of composite projects) in August 2015. Following that review, TfNSW registered each of the components of WestConnex with INSW as individual projects, rather than keeping WestConnex registered as a program or complex project. The IIAF allows this to occur.

Separate registration enabled INSW to report and review each stage with more scrutiny compared to whole‑of‑program level review.

Such an approach has merit, considering the individual stages (and components of these stages) are multi‑million dollar works in their own right. Each project has its own timing for gateway reviews at stages such as 'Readiness for Market' and 'Tender Evaluation'.

Once a program such as WestConnex is broken down into its composite parts, there is no requirement for the sponsor agency (TfNSW) or INSW to conduct independent assurance on the program of works as a whole until the whole program is completed as part of the Benefits Realisation (Gate 6) gateway review. The absence of strategic, holistic reviews of projects of the scale and complexity such as WestConnex during their delivery allows for total costs and benefits to become opaque and avoid scrutiny. Projects of this scale require greater ongoing transparency on total costs and benefits in order to ensure confidence they will meet intended objectives within budget.

INSW has advised us that it has prepared a proposal to expand its assurance function to include whole‑of‑program review of inter‑related infrastructure projects.

Appendix one – Responses from agencies

Appendix two – Network integration works

Appendix three – About the audit

Appendix four – Performance auditing

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #351 - released (17 June 2021).