Refine search Expand filter

Reports

Published

Actions for Planning, Industry and Environment 2019

Planning, Industry and Environment 2019

Planning
Industry
Environment
Asset valuation
Cyber security
Financial reporting
Information technology
Infrastructure
Internal controls and governance
Management and administration
Service delivery
Workforce and capability

This report outlines the results of audits of the financial statements of agencies now grouped in the NSW Planning, Industry and Environment cluster.

Unqualified audit opinions were issued for 56 of the 66 cluster agencies’ 30 June 2019 financial statements. Ten audits remain incomplete. The cluster agencies need to improve the timeliness of financial reporting. 

The Audit Office continued to identify issues regarding unprocessed Aboriginal land claims and the recognition of Crown land. ‘Auditor-General’s reports to parliament have recommended action to reduce the level of unprocessed land claims since 2007. However, the number of unprocessed claims continued to increase’, Margaret Crawford said.

One in five internal control findings were repeat issues. Key themes included information technology, asset management and improvements required to expense and payroll controls.

The report makes several recommendations including:

  • Property NSW should urgently address the deficiencies in the lease data used to calculate the impact of the new leasing standard effective from 1 July 2019
  • the Department of Planning, Industry and Environment should prioritise action to reduce unprocessed Aboriginal land claims
  • the Department of Planning, Industry and Environment should ensure the Crown land database is complete and accurate so state agencies and local government councils are better informed about the Crown land they control.

This report analyses the results of our audits of financial statements of the Planning, Industry and Environment cluster agencies for the year ended 30 June 2019. The table below summarises our key observations.

1. Machinery of Government changes

Creation of the Planning, Industry and Environment cluster

The Machinery of Government (MoG) changes abolished the former Planning and Environment cluster and former Industry cluster, and created the Planning, Industry and Environment cluster on 1 July 2019.

The Department of Planning and Environment (DPE), the Department of Industry (DOI), the Office of Environment and Heritage, and the Office of Local Government were abolished and the majority of their functions were transferred to the new Department of Planning, Industry and Environment (DPIE).

The Department of Planning, Industry and Environment is still in the process of implementing changes

The MoG changes bring risks and challenges to the cluster. A MoG Steering Committee, with the support of various project control groups and working groups, identified and developed responses to key risks arising from the changes.

However, the DPIE will take some time to fully integrate the policies, systems and processes of the abolished Departments and agencies.

2. Financial reporting

Audit opinions Unqualified audit opinions were issued for 56 of the 66 cluster agencies' 30 June 2019 financial statements audits. Ten financial statements audits are still ongoing.
Timeliness of financial reporting

Fifty-five of the 57 agencies subject to statutory deadlines submitted their financial statements on time.

Due to issues identified during the audit, 13 financial statements audits were not completed and audit opinions issued by the statutory deadline.

Agencies prepared and submitted their early close procedures in accordance with the mandatory timeframe set by NSW Treasury. However, 17 of the 49 agencies where we reviewed early close procedures were assessed as either partially addressing or not addressing one or more of the mandatory requirements. The cluster agencies could benefit from an increased focus on early close procedures.

Introduction of AASB 16 'Leases'

We noted errors in the lease data used in Property NSW's AASB 16 impact calculations, which affect both Property NSW and other government agencies. These errors were significant enough to present a risk of material misstatements to the financial statements of Property NSW and other government agencies in future reporting periods.

We had similar findings in our recent performance audit on 'Property Asset Utilisation', which highlighted issues with the quality of Property NSW's records.

Recommendation: Property NSW should urgently address the deficiencies in the lease data used to calculate the impact of the new leasing standard effective from 1 July 2019.

Unprocessed Aboriginal land claims have continued to increase

Despite an increase in the number of claims resolved, the number of unprocessed Aboriginal land claims increased by 7.2 per cent from the prior year to 35,855 at 30 June 2019. Claims can be made over Crown land assets of the DPIE or other government agencies. Until claims are resolved, there is an uncertainty over who is entitled to the land and the uses and activities that can be carried out on the land. We first recommended action to address unprocessed claims in 2007.

Recommendation (repeat issue): The DPIE should prioritise action to reduce unprocessed Aboriginal land claims.

3. Audit observations

Internal controls

One in five internal control issues identified and reported to management in 2018–19 were repeat issues.

The lack of user access review was the most common IT general control issue in the cluster.

Drought relief

The NSW Government announced an emergency drought relief package of $500 million in 2018, in addition to other financial assistance measures already in place.

Limited documentation and written agreements between relevant delivery agencies resulted in a $31.0 million misstatement relating to grant revenue.

Recognition of Crown land

Crown land is an important asset of the state. Management and recognition of Crown land assets is weakened when there is confusion over who is responsible for a particular Crown land parcel. Last year we recommended the DOI should ensure the database of Crown land is complete and accurate. While the DOI has commenced actions to improve the database, this continued to be an issue in 2018–19.

Recommendation (repeat issue): The DPIE should ensure the Crown land database is complete and accurate so state agencies and local government councils are better informed about the Crown land they control.

Developer contributions The former DPE continued to accumulate more developer contributions revenues than it spent on infrastructure projects. Total unspent funds increased to $274 million at 30 June 2019.

 

This report provides parliament and other users of the Planning, Industry and Environment cluster agencies financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

This cluster was created by the Machinery of Government changes on 1 July 2019. This report is focused on agencies in the Planning, Industry and Environment cluster from 1 July 2019. However, these agencies were all in other clusters during 2018–19. Please refer to the section on Machinery of Government changes for more details.

Machinery of Government (MoG) refers to how the government organises the structures and functions of the public service. MoG changes are where the government reorganises these structures and functions that are given effect by Administrative orders.

The MoG changes, announced following the NSW State election on 23 March 2019, created the Planning, Industry and Environment (PIE) cluster. The Administrative Changes Orders issued on 2 April 2019, 1 May 2019 and 28 June 2019 gave effect to these changes. These orders became effective on 1 July 2019.

Section highlights

The 2019 MoG changes significantly impacted the former Planning and Environment, and Industry clusters and agencies.

  • The PIE cluster combines most of the functions and agencies of the former Planning and Environment and Industry clusters from 1 July 2019.
  • The Department of Planning, Industry and Environment is the principal agency in the PIE cluster.
  • The MoG changes bring risks and challenges to the PIE cluster.
  • A MoG Steering Committee was established to oversee the transitional processes.
  • The full integration of the systems and processes will not be completed in the near future.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Planning, Industry and Environment (PIE) cluster for 2019. In this chapter, the Department of Planning, Industry and Environment is referred to as DPIE, the former Department of Planning and Environment as DPE, and the former Department of Industry as DOI.

Section highlights

  • Unqualified audit opinions were issued for all completed 30 June 2019 financial statements audits. However, some cluster agencies can further enhance the quality of financial reporting.
  • Timeliness of financial reporting remains an issue for 13 agencies.
  • Deficiencies were identified in the data used to calculate the impact of AASB 16 ‘Leases’ effective from 1 July 2019. Property NSW should urgently address these deficiencies.
  • Unprocessed Aboriginal land claims continue to increase. DPIE should prioritise action to reduce unprocessed Aboriginal land claims.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our audit observations and insights from our financial statement audits of agencies in the Planning, Industry and Environment (PIE) cluster for 2019. In this chapter, the Department of Planning, Industry and Environment is referred to as DPIE, the former Department of Planning and Environment as DPE, and the former Department of Industry as DOI.

Section highlights

  • One in five issues identified and reported to management in 2018–19 were repeat issues.
  • The lack of user access review was the most common IT general control issue in the PIE cluster.
  • The PIE cluster provided significant financial assistance for drought relief.
  • There continues to be significant deficiencies in Crown land records. The DPIE should ensure the Crown land database is complete and accurate.
  • Unspent developer contributions funds continued to build up in 2018–19. 

Appendix one – List of 2019 recommendations

Appendix two – Status of 2018 recommendations

Appendix three – Cluster agencies

Appendix four – Financial data

Appendix five – Management letter findings

Appendix six – Timeliness of financial reporting

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Stronger Communities 2019

Stronger Communities 2019

Justice
Community Services
Compliance
Financial reporting
Internal controls and governance
Management and administration
Project management
Service delivery
Shared services and collaboration
Workforce and capability

A report has been released on the NSW Stronger Communities cluster.

From 1 July 2019, the functions of the former Department of Justice, the former Department of Family and Community Services and many of the cluster agencies moved to the new Stronger Communities cluster. The Department of Communities and Justice is the principal agency in the new Stronger Communities cluster.

The report focuses on key observations and findings from the most recent financial audits of agencies in the Stronger Communities cluster.

Unqualified audit opinions were issued on the financial statements for all agencies in the cluster.  

There were 157 audit findings on internal controls. Two of these were high risk and 59 were repeat findings from previous financial audits. ‘Cluster agencies should prioritise actions to address internal control weaknesses promptly with particular focus given to issues that are assessed as high risk’, the Auditor-General said.

The report notes that the NSW Government’s new workers' compensation legislation, which gave eligible firefighters presumptive rights to workers' compensation, cost emergency services agencies $180 million in 2018–19, mostly in increased premiums.

Download the PDF version of report

This report analyses the results of our audits of financial statements of the agencies comprising the Stronger Communities cluster for the year ended 30 June 2019. The table below summarises our key observations.

This report provides parliament and other users of the financial statements of agencies in the Stronger Communities cluster with the results of our audits, our observations, analyses, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

This cluster was significantly impacted by the Machinery of Government (MoG) changes on 1 July 2019. This report focuses on the agencies that from 1 July 2019, comprised the Stronger Communities cluster. The MoG changes moved some agencies from the clusters to which they belonged in 2018–19 to the Stronger Communities cluster. Conversely, the MoG also moved some agencies formerly in the Family and Community Services cluster and Justice cluster elsewhere. Please refer to the section on Machinery of Government changes for more details.

The Department of Communities and Justice is the principal agency of the cluster. The newly created department combines functions of the former Department of Justice and the Department of Family and Community Services.

Machinery of Government (MoG) refers to how the government organises the structures and functions of the public service. MoG changes occur when the government reorganises these structures and functions and those changes are given effect by Administrative Orders.

The MoG changes announced following the NSW State election on 23 March 2019 significantly impacted the Stronger Communities cluster through Administrative Changes Orders issued on 2 April 2019 and 1 May 2019. These orders took effect on 1 July 2019.

Section highlights

The 2019 MoG changes significantly impacted the former Justice and Family and Community Services (FACS) departments and clusters.

  • The Stronger Communities cluster combines most of the functions and agencies of the former Justice and FACS clusters from 1 July 2019.
  • The Department of Communities and Justice is now the principal agency in the new cluster.
  • The MoG changes bring new responsibilities, risks and challenges to the cluster.
  • A temporary office has been established by the Department of Communities and Justice to support the cluster in the planning, delivery and reporting associated with implementing the changes.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations relating to the financial reporting of agencies in the Stronger Communities cluster for 2019.

Section highlights
  • Unqualified audit opinions were issued for all agencies' 30 June 2019 financial statements. However, further actions can be taken by some cluster agencies to enhance the quality of their financial reporting.
  • In November 2018, the Department of Justice implemented a new Victims Support Services system called VS Connect. Significant data quality issues arising from the VS Connect system implementation impacted the Department's ability to reliably estimate its Victims Support Scheme claims liabilities at 30 June 2019.
    We recommend the Department of Communities and Justice resolves the data quality issues in the new VS Connect System before 30 June 2020 and capture and apply lessons learned from recent project implementations, including LifeLink, Justice SAP and VS Connect, in any relevant future implementations.
  • Our audits found some cluster agencies needed to do more work on their impact assessments and preparedness to implement the new accounting standards, to minimise the risk of errors in their 2019–20 financial statements.
  • Cluster agencies with annual leave balances exceeding the State's target should further review their approach to managing leave balances.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our observations and insights from our financial statement audits of agencies in the Stronger Communities cluster.

Section highlights

  • Cluster agencies should action recommendations to address internal control weaknesses promptly. Particular focus should be given to prioritising high risk issues. The 2018–19 financial audits of cluster agencies identified 157 internal control issues. Of these, two were high risk and 37.6 per cent were repeat findings from previous audits.
  • Data from the Department of Justice shows the inmate population reached a maximum of 13,798, compared to an operational capacity of 14,626 beds on 31 August 2019. This equates to an operational vacancy rate of 5.7 per cent, which is more than the recommended 5.0 per cent buffer. This is the first time the vacancy rate has exceeded the target over the last five years. Growth in the NSW prison population is being managed through the NSW Government's $3.8 billion Prison Bed Capacity Program.
  • In September 2018, the NSW Government introduced new workers' compensation legislation, which gives eligible firefighters presumptive rights to workers' compensation when diagnosed with one of 12 prescribed cancers. The new legislation cost emergency services agencies $180 million in 2018–19, mainly through additional workers' compensation premiums.

Appendix one – Timeliness of financial reporting by agency

Appendix two – Management letter findings by agency

Appendix three – List of 2019 recommendations 

Appendix four – Status of 2018 recommendations 

Appendix five – Cluster agencies 

Appendix six – Financial data 

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Planning and Environment 2018

Planning and Environment 2018

Planning
Environment
Asset valuation
Financial reporting
Information technology
Infrastructure
Internal controls and governance
Service delivery

The Auditor-General for New South Wales, Margaret Crawford, released her report today on the NSW Planning and Environment cluster. The report focuses on key observations and findings from the most recent financial audits of these agencies. Unqualified audit opinions were issued for all agencies' financial statements. However, some cultural institutions had challenges valuing collection assets in 2017–18. These issues were resolved before the financial statements were finalised.

This report analyses the results of our audits of financial statements of the Planning and Environment cluster for the year ended 30 June 2018. The table below summarises our key observations.

This report provides parliament and other users of the Planning and Environment cluster agencies' financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations
  • service delivery.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making is enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Planning and Environment cluster for 2018.

Observation Conclusions and recommendations
2.1 Quality of financial reporting
Unqualified audit opinions were issued for all agencies' financial statements. The quality of financial reporting remains high across the cluster.
2.2 Key accounting issues
There were errors in some cultural institutions' collection asset valuations. Recommendation: Collection asset valuations could be improved by:
  • early engagement with key stakeholders regarding the valuation method and approach
  • completing revaluations, including quality review processes earlier 
  • improving the quality of asset data by registering all items in an electronic database. 
2.3 Timeliness of financial reporting
Except for two agencies, the audits of cluster agencies’ financial statements were completed within the statutory timeframe.  Issues with asset revaluations delayed the finalisation of two environment and heritage agencies' financial statement audits. 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our observations and insights from:

  • our financial statement audits of agencies in the Planning and Environment cluster for 2018
  • the areas of focus identified in the Audit Office work program.

The Audit Office annual work program provides a summary of all audits to be conducted within the proposed time period as well as detailed information on the areas of focus for each of the NSW Government clusters.

Observation Conclusions and recommendations
3.1 Internal controls
One in five internal control weaknesses reported in 2017–18 were repeat issues. Delays in implementing audit recommendations can prolong the risk of fraud and error.
Recommendation (repeat issue): Management letter recommendations to address internal control weaknesses should be actioned promptly, with a focus on addressing repeat issues.
One extreme risk was identified relating to the National Art School. The School does not have an occupancy agreement for the Darlinghurst campus. Lack of formal agreement creates uncertainty over the School's continued occupancy of the Darlinghurst site.

The School should continue to liaise with stakeholders to formalise the occupancy arrangement. 
 
3.2 Information technology controls
The controls and governance arrangements when migrating payroll data from the Aurion system to SAP HR system were effective. Data migration from the Aurion system to SAP HR system had no significant issues.
The Department can improve controls over user access to SAP system. The Department needs to ensure the SAP user access controls are appropriate, including investigation of excess access rights and resolving segregation of duties issues. 
3.3 Annual work program
Agencies used different benchmarks to monitor their maintenance expenditure. The cluster agencies under review operate in different industries. As a result, they do not use the same benchmarks to assess the adequacy of their maintenance spend. 

This chapter outlines certain service delivery outcomes for 2017–18. The data on activity levels and performance is provided by cluster agencies. The Audit Office does not have a specific mandate to audit performance information. Accordingly, the information in this chapter is unaudited. 

We report this information on service delivery to provide additional context to understand the operations of the Planning and Environment cluster, and to collate and present service information for different segments of the cluster in one report. 

In our recent performance audit, ‘Progress and measurement of Premier's Priorities’, we identified 12 limitations of performance measurement and performance data. We recommended the Department of Premier and Cabinet ensure that processes to check and verify data are in place for all relevant agency data sources.

Published

Actions for Family and Community Services 2018

Family and Community Services 2018

Community Services
Compliance
Financial reporting
Information technology
Management and administration
Project management
Risk
Service delivery
Workforce and capability

The Auditor-General for New South Wales, Margaret Crawford released her report today on the Family and Community Services cluster. The report focuses on key observations and findings from the most recent financial audits of agencies in the cluster. Cluster entities received unqualified audit opinions for their 30 June 2018 financial statements. Opportunities to improve the quality of financial reporting were identified and reported to management.

This report analyses the results of our audits of financial statements of the Family and Community Services cluster for the year ended 30 June 2018. The table below summarises our key observations.

This report provides NSW Parliament and other users of the financial statements of Family and Community Services' agencies with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations
  • service delivery.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Family and Community Services cluster for 2018.

Observation Conclusions and recommendations
2.1 Quality of financial reporting
Unqualified audit opinions were issued for all cluster agencies' financial statements. Conclusion: Sufficient audit evidence was obtained to conclude the financial statements were free of material misstatement.
Agencies complied with NSW Treasury’s mandatory early close requirements.

Completing other early close procedures was inconsistent and not always supported by adequate evidence.
Conclusion: There are opportunities for agencies to improve the quality of financial reporting by:
  • documenting all significant judgements and assumptions used when preparing the financial statements
  • regularly reconciling inter-agency balances and transactions
  • reconciling key account balances on a timely basis
  • quantifying the impact of new and revised accounting standards.
2.2 Timeliness of financial reporting
Agencies completed revaluations of property, plant and equipment and submitted 31 March 2018 financial statements by the due date as required by NSW Treasury.

Agencies submitted year-end financial statements by the statutory deadline.
Conclusion: Early revaluations of property, plant and equipment contributes to agencies meeting the year-end statutory reporting deadline.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our observations and insights from:

  • our financial statement audits of agencies in the Family and Community Services cluster for 2018
  • the areas of focus identified in the Audit Office annual work program.

The Audit Office Annual Work Program provides a summary of all audits to be conducted within the proposed time period as well as detailed information on the areas of focus for each NSW Government cluster.

Observation Conclusions and recommendations
3.1 Internal controls
The 2017–18 audits reported 47 internal control weaknesses. While none were high risk, there were 15 repeat issues.

Conclusion: Management accepted audit findings and advised they are actioning recommendations. Timely action is important to ensure internal controls operate effectively.

Twenty-two of these internal control weaknesses related to information technology processes and control environment. Conclusion: Control weaknesses in information systems may compromise the integrity and security of financial data used for decision making and financial reporting.

Recommendation: Agencies should strengthen user access administration to prevent inappropriate access to key IT systems by:
  • ensuring privileged user access is limited to those requiring access to maintain the IT systems
  • monitoring privileged user access to address risks from unauthorised activity
  • ensuring IT password settings comply with password policies
  • ensuring timely removal of access to business systems for terminated and casual employees.
The Department, NSW Land and Housing Corporation (LAHC) and three other cluster agencies’ contract registers are incomplete and/or inaccurate. Recommendation: Agencies should ensure their contract registers are complete and accurate so they can more effectively govern contracts and manage compliance obligations.
3.2 Audit Office annual work program
Financial impact of the commissioning approach.

The transfer of disability services to the National Disability Insurance Scheme and other commissioning of service delivery has contributed to a 36 per cent decrease in frontline employee numbers since 2015–16. Similarly, corporate services’ employee numbers reduced by 34 per cent.

The Department’s salary costs have reduced by $232 million or 18 per cent from 2016–17.
Conclusion: The ratio of corporate services employee numbers to support frontline and support services has remained at 1:10 since 2015–16, which indicates restructures have been planned to align with the transfer of disability services.
Impact of the new social housing maintenance contract

Maintenance expenses have increased by about 40 per cent since the new maintenance contract commenced in April 2016. LAHC measures the benefits of the new maintenance contract such as improved tenant satisfaction.
Conclusion: The new maintenance contract has contributed to some positive social outcomes such as tenants being employed by the contractors to conduct maintenance, as call centre operators and in administration. However, more can be done to ensure value for money is being achieved.
ChildStory IT Project

Whilst phase one of the ChildStory IT project went 'live' in 2017–18, the planned timetable has not been met and the revised date for full implementation is end of 2018.

According to the 2014–15 NSW Budget, the budget for ChildStory was $100 million over a four-year period. During the design and implementation stage, this amount was revised to $128 million, with approval of the Expenditure Review Committee. The actual cost incurred over the four years until 30 June 2018, is approximately $131 million.

We identified issues with the data migration from the legacy systems to ChildStory.
Conclusion: To inform future IT projects, we understand the Department is capturing our findings, along with the findings from the Department of Finance, Services and Innovation’s ‘Healthchecks’.

This chapter outlines certain service delivery outcomes for 2017–18. The data on activity levels and performance is provided by Cluster agencies. The Audit Office does not have a specific mandate to audit performance information. Accordingly, the information in this chapter is unaudited.

In our recent performance audit, Progress and measurement of Premier's Priorities, we identified 12 limitations of performance measurement and performance data. We recommended that the Department of Premier and Cabinet ensure that processes to check and verify data are in place for all agency data sources.