On 16 September 2015 the NSW Acting Auditor-General, Tony Whitfield, released a report on community housing. The audit examines the Department of Family and Community Services’ transfer of public housing to non-government community housing providers. The Department has worked collaboratively with community housing providers and industry groups to develop the community housing sector. Although there have been some delays, it has managed the transfer of p
Actions for Large construction projects
Large construction projects
The independent assurance given to the NSW Government and sponsor agencies on the viability of large capital projects throughout their lifecycle is inadequate. Government policy is regularly not followed and not properly communicated to those responsible for implementing such policy. This audit sought to test the effectiveness of the NSW capital project assurance system - which includes gateway reviews and reporting - but significant levels of non
Actions for WestConnex: Assurance to the Government
WestConnex: Assurance to the Government
This audit assesses the assurance provided to the NSW Government for the initial stages of the WestConnex project. The audit examined the WestConnex project from concept development to the pre-tender phase for Stage 1A – M4 (Parramatta to Homebush Bay). It did not examine the merit of the project or whether it represented value-for-money. This audit found a number of shortcomings with the governance of the WestConnex project during its early stages and
Actions for Condition of State Roads
Condition of State Roads
The Roads and Traffic Authority (RTA) has improved the overall surface condition of State Roads in the last decade. Country road surfaces are now generally much better. Ride quality has improved and cracking has been reduced. The RTA has also achieved a substantial reduction in the number of structurally deficient bridges over the same period. Despite a significant increase in the State’s contribution to maintenance since 1999-2000, the RTA h
Actions for The Cross City Tunnel Project
The Cross City Tunnel Project
In our opinion the Government’s ‘no net cost to government’ requirement was a legitimate (but not the only possible) basis for the tunnel bid process. The Government was entitled to decide that tunnel users meet the tunnel costs. Structuring the bid process on the basis of an upfront reimbursement of costs incurred (or to be incurred) by the Roads and Traffic Authority (RTA) was therefore appropriate. In our opinion, however, the Government, Treasu