Actions for CBD and South East Light Rail: follow-up performance audit

CBD and South East Light Rail: follow-up performance audit

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk
Service delivery

The CBD and South East Light Rail is a 12 km light rail network for Sydney. It extends from Circular Quay along George Street to Central Station, through Surry Hills to Moore Park, then to Kensington and Kingsford via Anzac Parade and Randwick via Alison Road and High Street. Transport for NSW (TfNSW) is responsible for planning, procuring and delivering the Central Business District and South East Light Rail (CSELR) project. In December 2014, TfNSW ent

Published

Actions for Train station crowding

Train station crowding

Transport
Management and administration
Risk
Service delivery
Workforce and capability

Sydney Trains patronage has increased by close to 34 per cent over the last five years, and Transport for NSW (TfNSW) expects the growth in patronage to continue over the next 30 years. As patronage increases there are more passengers entering and exiting stations, moving within stations to change services, and waiting on platforms. As a result, some Sydney metropolitan train stations are becoming increasingly crowded. There are three main causes of sta

Published

Actions for Family and Community Services 2018

Family and Community Services 2018

Community Services
Compliance
Financial reporting
Information technology
Management and administration
Project management
Risk
Service delivery
Workforce and capability

The Auditor-General for New South Wales, Margaret Crawford released her report today on the Family and Community Services cluster. The report focuses on key observations and findings from the most recent financial audits of agencies in the cluster. Cluster entities received unqualified audit opinions for their 30 June 2018 financial statements. Opportunities to improve the quality of financial reporting were identified and reported to management.

Published

Actions for Central Agencies 2018

Central Agencies 2018

Treasury
Premier and Cabinet
Finance
Financial reporting
Internal controls and governance
Management and administration
Risk

The Auditor-General for New South Wales, Margaret Crawford, released her report today on the results of the financial audits of NSW Government central agencies. The report focuses on key observations and findings from the most recent financial statement audits of agencies in the Treasury, Premier and Cabinet, and Finance, Services and Innovation clusters. While clear audit opinions were issued on all agency financial statements, the report notes that som

Published

Actions for Transport 2018

Transport 2018

Transport
Asset valuation
Compliance
Financial reporting
Infrastructure
Management and administration
Procurement
Risk
Service delivery
Workforce and capability

The Auditor-General for New South Wales, Margaret Crawford released her report today on key observations and findings from the 30 June 2018 financial statement audits of agencies in the Transport cluster. Unqualified audit opinions were issued for all agencies' financial statements. However, assessing the fair value of the broad range of transport related assets creates challenges. This repor

Published

Actions for Progress and measurement of the Premier's Priorities

Progress and measurement of the Premier's Priorities

Premier and Cabinet
Compliance
Internal controls and governance
Management and administration
Project management
Risk
Service delivery
Shared services and collaboration
Workforce and capability

The Premier’s Implementation Unit uses a systematic approach to measuring and reporting progress towards the Premier’s Priorities performance targets, but public reporting needed to improve, according to a report released today by the Auditor-General of NSW, Margaret Crawford. The Premier of New South Wales has established 12 Premier’s Priorities. These are key performance targets for governm

Published

Actions for Solar Bonus Scheme

Solar Bonus Scheme

Premier and Cabinet
Compliance
Infrastructure
Management and administration
Project management
Regulation
Risk
Service delivery

A NSW Auditor General’s Report has found that the NSW Government and its agencies grossly underestimated the cost and number of people that would install systems under the Solar Bonus Scheme. By October 2010, the estimated cost of the Scheme, if it continued the way it was going, would have reached $3.988 billion. More than ten times the original estimate of $362 million. In response to the increased cost, the gross tariff for new applicants was reduced

Published

Actions for Prequalification Scheme: Performance and Management Services

Prequalification Scheme: Performance and Management Services

Premier and Cabinet
Finance
Compliance
Internal controls and governance
Management and administration
Regulation
Risk
Workforce and capability

There have been tangible improvements in the time it takes NSW Government agencies to engage consultants through the Government’s Prequalification Scheme. The Scheme was introduced in February 2008 to improve agencies’ procurement of consultants. More than 300 service providers have been prequalified and over $300 million worth of consultancy services have been provided. Ideally agencies should know what assignments each consultant has won, for what serv

Published

Actions for Helping older people access a residential aged care facility

Helping older people access a residential aged care facility

Health
Community Services
Compliance
Internal controls and governance
Management and administration
Risk
Service delivery
Shared services and collaboration
Workforce and capability

Assessment processes for older people needing to go to an Residential Aged Care Facility (RACF) vary depending on the processes of the Aged Care Assessement Teams (ACAT) they see and whether or not they are in hospital. The data collected on ACAT performance was significantly revised during 2004 making comparisons with subsequent years problematic. ACATs have more responsibilities than assessing older people for residential care. It is not clear whether

Published

Actions for The Cross City Tunnel Project

The Cross City Tunnel Project

Transport
Treasury
Premier and Cabinet
Planning
Environment
Infrastructure
Management and administration
Procurement
Project management
Risk

In our opinion the Government’s ‘no net cost to government’ requirement was a legitimate (but not the only possible) basis for the tunnel bid process. The Government was entitled to decide that tunnel users meet the tunnel costs. Structuring the bid process on the basis of an upfront reimbursement of costs incurred (or to be incurred) by the Roads and Traffic Authority (RTA) was therefore appropriate. In our opinion, however, the Government, Treasury an