This report analyses the results of our audits of financial statements of the agencies comprising the Stronger Communities cluster for the year ended 30 June 2020. The table below summarises our key observations.

1. Financial reporting

Quality of financial reporting Unqualified audit opinions were issued for all agencies' 30 June 2020 financial statements.
Compliance with financial reporting requirements

The Treasury extended the statutory deadline for the submission of the 2019–20 financial statements. For agencies subject to Treasurer's Directions, Treasury required agencies to submit their 30 June 2020 financial statements by 5 August 2020. For other agencies, the deadline was extended to 31 October 2020. All agencies in the cluster met the revised statutory deadlines.

Cluster agencies substantially completed the mandatory early close procedures set by NSW Treasury. However, nine agencies including the Department of Communities and Justice (the department) did not complete one or more mandatory requirements, such as assessing the impact of new and updated accounting standards.

Financial implications of recent emergencies

Emergency events significantly impacted cluster agencies in 2019–20. Our review of seven cluster agencies most affected highlighted some had incurred additional expenditure because of the bushfires and floods. Others lost revenue due to the COVID-19 pandemic.

During the year these agencies collectively received additional funding of $1.1 billion from the State to respond to:

  • increased demand for homeless people seeking temporary accommodation
  • additional cleaning requirements
  • bushfire recovery efforts
  • emergency support for eligible small businesses.

The Sydney Cricket Ground Trust, Venues NSW and Office of Sport lodged insurance claims of $51.3 million with the Treasury Managed Fund with respect to lost revenues from the pandemic. The losses were mainly due to event cancellations and covered various periods ranging from mid-March to 31 December 2020.

The change in economic conditions caused by the COVID-19 pandemic resulted in the NSW Government cancelling the refurbishment of Stadium Australia it had previously approved in August 2019. Venues NSW wrote off $16.8 million of redevelopment costs during 2019–20.

Restatement of the Sydney Cricket Ground valuation The valuation of the Sydney Cricket Ground (the Stadium) included costs of $28.6 million which were not eligible for capitalisation. The financial statements were restated to reflect the reduction in the value of the Stadium and the asset revaluation reserve.
Unresolved data quality issues in the VS Connect system

The department continues to address significant data quality issues resulting from its implementation of the VS Connect system (the System) in 2019. The issues relate to the completeness and accuracy of the data transferred from the legacy system. The System is used by the department to manage its Victims Support Services (VSS) and for financial reporting purposes.

An independent actuary helps the department estimate its liability for VSS claims. The actuary's valuation at 30 June 2020 was again impacted by the data quality issues. Consequently, the actuary adopted a revised valuation methodology compared to previous years.

Recommendation (repeat issue):

The department should resolve the data quality issues in the VS Connect System before 31 March 2021.

AASB 16 'Leases' resulted in significant changes to agencies' financial position

Cluster agencies implemented three new accounting standards for the first time in 2019–20. Adoption of AASB 16 'Leases' resulted in cluster agencies collectively recognising right-of-use assets and lease liabilities of $1.7 billion and $1.1 billion respectively on 1 July 2019.

Significant misstatements in how lease related balances had been calculated were found in 17 of the 29 cluster agencies. The cluster outsources the management of most of its owned and leased property portfolio to Property NSW, but cluster agencies remain responsible for any deliverables under that arrangement. The misstatements were mainly caused by late revisions of key assumptions and issues with the accuracy and completeness of Property NSW's lease information.

2. Audit observations

Internal control deficiencies

Our 2019–20 financial audits identified 191 internal control issues. Of these, two were high risk and almost one-third were repeat findings from previous audits. While repeat findings reduced by 5.7 percentage points in 2019–20, the number remains high.

Recommendation (repeat issue):

Cluster agencies should action recommendations to address internal control weaknesses promptly. Focus should be given to addressing high risk and repeat issues.

Agencies response to recent emergencies

The severity of the recent bushfires and floods meant natural disaster expenses incurred by emergency services agencies rose from $67.4 million in 2018–19 to $497 million in 2019–20.

The COVID-19 pandemic presented unprecedented challenges for the cluster. Social distancing and other infection control measures disrupted the traditional means of delivering services. Agencies established committees or response teams to respond to these challenges.

The department introduced measures to minimise the risk of the spread of COVID-19 amongst inmates in custodial settings.

Managing excess annual leave

Managing excess annual leave was a challenge for cluster agencies directly involved in the government's response to the emergency events. Employees in frontline cluster agencies deferred leave plans and many have taken little or no annual leave during the reporting period.

Annual leave liabilities rose at the department, NSW Police Force, Fire and Rescue NSW, Office of the NSW Rural Fire Service, the Legal Aid Commission of New South Wales and the Office of the Director of Public Prosecutions. The combined liabilities increased from $620 million to $692 million or 11.6 per cent between 30 June 2019 and 30 June 2020.

Implementation of Machinery of Government (MoG) changes

Administrative Arrangement Orders effective from 1 July 2019, created the department of Communities and Justice and transferred functions and staff, together with associated assets and liabilities into the department from the former departments of Justice and Family and Community Services.

The department continues to establish its governance arrangements following the MoG changes.

Recommendation:

The department should finalise appropriate governance arrangements for its new organisational structure as soon as possible. This includes:

  • harmonising policies and procedures to ensure a unified approach across the department
  • finalising risk management and monitoring processes across the department
  • updating its delegation instruments to reflect the current organisational structure, delegation limits and roles and responsibilities.
Delivery of the Prison Bed Capacity Program

The department continued to expand prison system capacity through the NSW Government's $3.8 billion Prison Bed Capacity Program. The department reported it spent $480 million on the Program in 2019–20. Six prison expansion projects were completed during the year, which added 1,660 new and 395 refurbished beds to the NSW prison system.

Data from the department shows the number of adult inmates in the NSW prison system reached a maximum of 14,165 during the year. Operational capacity was 16,096 beds on 19 August 2020.

 

This report provides parliament and other users of the financial statements of agencies in the Stronger Communities cluster with the results of our audits, our observations, analysis, conclusions and recommendations.

Agencies in the Stronger Communities cluster were significantly impacted by the bushfires, floods and the COVID-19 pandemic in 2019–20. Our 2019–20 financial audits of the seven cluster agencies most significantly impacted by the recent emergency events considered:

  • the financial implications of the emergency events
  • changes to agencies' operating models and control environments
  • delivery of new or expanded projects, programs or services at short notice.

Our findings on these seven agencies' responses to the recent emergencies are included throughout this report. These agencies are:

  • Department of Communities and Justice
  • Fire and Rescue NSW
  • NSW Police Force
  • Office of the NSW Rural Fire Service
  • Office of the NSW State Emergency Service
  • Sydney Cricket and Sports Ground Trust
  • Venues NSW.

The Department of Communities and Justice is the principal agency of the cluster. The names of all agencies in the Stronger Communities cluster are included in Appendix one.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Stronger Communities cluster for 2020, including any financial implications from the recent emergency events.

Section highlights

  • Unqualified audit opinions were issued for all agencies' 30 June 2020 financial statements. All agencies met the revised statutory deadlines for completing early close procedures and submitting their financial statements.
  • Emergency events significantly impacted cluster agencies in 2019–20. Agencies received additional funding of $1.1 billion to respond to the emergencies.
  • Cluster agencies implemented three new accounting standards in 2019–20. Adoption of AASB 16 'Leases' resulted in significant changes to agencies' financial statements.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our:

  • observations and insights from our financial statement audits of agencies in the Stronger Communities cluster
  • assessment of how well cluster agencies adapted their systems, policies and procedures, and governance arrangements in response to recent emergencies
  • review of how the cluster agencies managed the increased risks associated with new programs aimed at stemming the spread of COVID-19 and stimulating the economy.

Section highlights

  • Almost one-third of internal control issues reported were repeat findings. Cluster agencies should address these issues more promptly.
  • The severity of the recent bushfires and floods meant natural disaster expenses incurred by emergency services agencies increased by $430 million in 2019–20.
  • The department continues to establish its governance arrangements following Machinery of Government changes effective 1 July 2019.

 

Appendix one – Timeliness of financial reporting by agency

Appendix two – Management letter findings by agency

Appendix three – List of 2020 recommendations 

Appendix four – Status of 2019 recommendations 

Appendix five – Selected agencies for review of response to emergency events 

Appendix six – Financial data 

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Regional NSW 2020

Regional NSW 2020

Environment
Industry
Compliance
Financial reporting
Information technology
Management and administration
Risk

This report analyses the results of our audits of financial statements of entities within the Regional NSW cluster for the year ended 30 June 2020. The table below summarises our key observations and recommendations.

1. Machinery of Government (MoG) changes

Creation of Regional NSW cluster MoG changes on 2 April 2020 created the Department of Regional NSW (the Department). The Department of Planning, Industry and Environment (DPIE) staff employed in the Regions, Industry, Agriculture and Resources Group, together with associated functions, assets and liabilities were transferred to the new Department. A number of agencies moved from the Planning, Industry and Environment cluster to the new Regional NSW cluster. The Department deals with major issues affecting regional communities, including the coordination of support for people, businesses and farmers who have faced drought, bushfires, flood and the COVID-19 pandemic.
The Department is still in the process of implementing changes The Department continues to receive corporate services support from DPIE. The Department has indicated it will transition to its own policies and procedures by June 2021.

2. Financial reporting

Audit opinions Unqualified audit opinions were issued for all cluster agencies' 30 June 2020 financial statements audits.
Timeliness of financial reporting Nine of the ten cluster agencies subject to statutory reporting deadlines met the revised timeline for submitting the financial statements. The Department and a number of cluster agencies obtained NSW Treasury’s approval to delay submission of their 30 June 2020 financial statements due to delays resulting from accounting and administrative complexities created by the Machinery of Government changes that separated the Department from DPIE. The deadlines were moved from 5 August 2020 to either 10 August 2020 or 12 August 2020. New South Wales Rural Assistance Authority missed the revised deadline by one day. All agencies that were required to perform early close procedures had met the revised timeline. Due to issues identified during audit, four financial statements audit were not completed and audit opinions issued by the statutory deadline.
New accounting standards

Agencies implemented three new accounting standards during the year. Our audit of the Department identified there was a lack of quality assurance over the accuracy of lease information provided by Property NSW.

Recommendation:

The Department should:

  • quality assure and validate the leasing information provided by Property NSW
  • ensure changes made by Property NSW to lease data are supported and that assumptions and judgements applied are appropriate
  • document their review of the data supplied.

3. Audit observations

Internal control deficiencies

We identified 30 internal control issues, including 16 findings that were raised with former agencies in previous years. Two matters from previous years have been elevated to high risk during 2019–20. Both matters related to Local Land Services:

  • not completing all mandatory requirements as part of its early close procedures at 31 March 2020
  • not performing annual fair value assessment of asset improvements on land reserves used for moving livestock.

Recommendation:

Management letter recommendations to address internal control weaknesses should be actioned promptly, with a focus on addressing high-risk and repeat issues.

Agency responses to emergency events The Department's executive leadership committee along with support from DPIE crisis management team managed the recovery from the bushfires and impact of COVID-19. Social distancing and other infection control measures were put in place. The Forestry Corporation of New South Wales accelerated a fire salvage timber program in response to the bushfire emergency. The Department and cluster agencies received additional funding for bushfire recovery and COVID-19 pandemic response.

The Regional NSW cluster aims to respond to regional issues, creating and preserving regional jobs, driving regional economy, growing existing and supporting emerging industries. The key areas of focus across the New South Wales (NSW) State is shown below:

MoG changes impact on Department of Regional NSW

The Department was created as result of the MoG changes during 2019–20. The Administrative Arrangements Order 2020, effective on 2 April 2020 created the Department of Regional NSW. These changes had a significant administrative impact on the cluster agencies. The MoG change resulted in a transfer of net assets ($446 million) and budget ($284 million) from DPIE to the newly created Department of Regional NSW on 2 April 2020. A summary of the MoG impacts on the Regional NSW cluster is shown below.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

The COVID-19 Legislation Amendment (Emergency Measures–Treasurer) Act 2020 amended legislation administered by the Treasurer to implement further emergency measures as a result of the COVID-19 pandemic. These amendments:

  • allowed the Treasurer to authorise payments from the consolidated fund until the enactment of the 2020–21 budget – impacting the going concern assessments of cluster agencies
  • revised budgetary and financial and annual reporting time frames – impacting the timeliness of financial reporting
  • exempted certain statutory bodies and departments from preparing financial statements.

This chapter outlines our audit observations related to the financial reporting of agencies in the Regional NSW cluster for 2020, including any financial implications from the recent emergency events.

Section highlights

  • Unqualified audit opinions were issued for all cluster agencies' 30 June 2020 financial statements audits.
  • Nine of the ten cluster agencies subject to statutory reporting deadlines met the revised timeline for submitting the financial statements. New South Wales Rural Assistance Authority missed the revised deadline by one day.
  • Due to issues identified during audit, four financial statements audit were not completed and audit opinions issued by the statutory deadline.
  • Emergency legislation allowing the Treasurer to continue authorising payments from the consolidated fund under the existing Appropriations Act enabled cluster agencies to prepare financial statements on a going concern basis.

 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our:

  • observations and insights from our financial statement audits of agencies in the Regional NSW cluster
  • assessment of how well cluster agencies adapted their systems, policies and procedures, and governance arrangements in response to recent emergencies.

Section highlights

  • Two high-risk issues were identified during our audits. Both related to Local Land Services for:
    − not completing all mandatory requirements as part of its early close procedures at 31 March 2020
    − not performing annual fair value assessment of asset improvements on land reserves used for moving livestock
  • More than one in two issues identified and reported to management in 2019–20 were raised in the former agencies.

Appendix one - List of 2020 recommendations

Appendix two - Financial data

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Planning, Industry and Environment 2020

Planning, Industry and Environment 2020

Planning
Environment
Industry
Asset valuation
Compliance
Financial reporting
Internal controls and governance
Management and administration

This report analyses the results of our audits of financial statements of the Planning, Industry and Environment cluster agencies for the year ended 30 June 2020. The table below summarises our key observations.

1. Financial reporting

Audit opinions

There are 45 separate entities in the cluster. Unqualified audit opinions were issued for 38 cluster agencies' 30 June 2020 financial statements audits. Four financial statements audits are still ongoing, and three agencies were not subject to audit due to NSW Treasury reporting exemptions.

Timeliness of financial reporting

The majority of cluster agencies subject to statutory reporting deadlines met the revised timeline for submitting financial statements. Twenty‑four of the 26 cluster agencies required to submit early close financial statements met the revised timeframe.

Due to issues identified during the audit, 13 financial statements audits were not completed and audit opinions not issued by the statutory deadline.

Implementation of AASB 16 'Leases'

Significant deficiencies were identified in Property NSW's lease data maintenance and lease calculations.

Recommendation (partially repeat):

Property NSW should:

  • review and document the accounting implications for each lease
  • ensure the accuracy and validity of lease data used for the lease calculations
  • review user access to the leasing system, including privileged users.

Our audits of the cluster agencies identified there was a lack of thorough quality assurance over the accuracy of lease information provided by Property NSW.

Recommendation:

The Department and cluster agencies should:

  • quality assure and validate the information provided by Property NSW
  • ensure changes made by Property NSW on lease data are supported and that assumptions and judgements applied are appropriate
  • document their review of the data supplied.

Unprocessed Aboriginal land claims continued to increase

In 2019–20, the Department resolved an additional 468 Aboriginal land claims compared to the prior year. However, the total number of unprocessed Aboriginal land claims increased by 914 to 36,769 at 30 June 2020. The number of claims remaining unprocessed for more than ten years after lodgement increased by 10.9 per cent from last year. Until claims are resolved, there is an uncertainty over who is entitled to the land and the uses and activities that can be carried out on the land.

Auditor-General's Reports to Parliament since 2007 have recommended action to address the increasing number of unprocessed claims. To date, the Department has not been able to resolve this issue.

During 2020–21, a performance audit will assess the effectiveness and efficiency of the administration of Aboriginal land claims.

Financial reporting of Crown land managers

The Department will need to provide additional support and guidance to help Crown land managers (CLMs) meet their financial reporting obligations.

Recommendation:

The Department should:

  • in consultation with NSW Treasury, develop an appropriate statutory reporting framework for CLMs
  • ensure sufficient resources are available to help CLMs meet their reporting obligations.

During 2019–20, NSW Treasury established the reporting exemption criteria for the CLMs. Based on available information, the Department determined 31 CLMs would not meet the exemption criteria and therefore are required to prepare annual financial statements.

2. Audit observations

Internal controls

Six high‑risk issues were identified across the cluster in 2019–20:

  • 5 of those were related to financial reporting issues identified in Property NSW, Wentworth Park Sporting Complex Land Manager, Lord Howe Island Board, Planning Ministerial Corporation and Hunter and Central Coast Development Corporation
  • 1 issue was related to Lord Howe Island Board's outdated business continuity plan.

One in three internal control issues identified and reported to management in 2019–20 were repeat issues.

Recommendation:

Management letter recommendations to address internal control weaknesses should be actioned promptly, with a focus on addressing high‑risk and repeat issues.

Agencies response to recent emergencies

The unprecedented bushfires and COVID‑19 pandemic presented challenges for the cluster. Agencies established taskforces or response teams to respond to these emergencies.

With more staff working from home, agencies implemented protocols and procedures to manage risks associated with the remote working arrangements, and also needed to address certain technology issues.

The Department is responsible for the new Planning System Acceleration Program, which aims to fast‑track planning assessments, boost the State's economy and keep people in jobs during COVID‑19 pandemic. Between April and October 2020, the Department announced and determined 101 major projects and planning proposals.

Recognition of Crown land

Crown land is an important asset of the State. Management and recognition of Crown land assets is weakened when there is confusion over who is responsible for a particular Crown land parcel.

Auditor-General's Reports to Parliament since 2017 have recommended that the Department should ensure the database of Crown land is complete and accurate. Whilst the Department has commenced actions to improve the database, this remained an issue in 2019–20.

Recommendation (repeat issue):

The Department should prioritise action to ensure the Crown land database is complete and accurate. This allows state agencies and local councils to be better informed about the Crown land they control.

Implementation of Machinery of Government (MoG) changes

Since its creation on 1 July 2019, the Department has largely established its governance arrangements, including setting up the Audit and Risk Committee and internal audit function for the Department and relevant cluster agencies.

The Department still operated three main financial reporting systems in 2019–20, and has commenced the process to consolidate some of the systems.

The recent Regional NSW MoG change led to the transfer of $446 million net assets and $284 million 2019–20 budget from the Department to the newly created Department of Regional NSW on 2 April 2020.

 

This report provides parliament and other users of the Planning, Industry and Environment cluster agencies’ financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations
  • the impact of emergencies and the pandemic.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

The COVID‑19 Legislation Amendment (Emergency Measures–Treasurer) Act 2020 amended legislation administered by the Treasurer to implement further emergency measures as a result of the COVID‑19 pandemic. These amendments:

  • allowed the Treasurer to authorise payments from the Consolidated fund until the enactment of the 2020–21 budget – impacting the going concern assessments of cluster agencies
  • revised budgetary, financial and annual reporting time frames – impacting the timeliness of financial reporting
  • exempted certain statutory bodies and departments from preparing financial statements.

This chapter outlines our audit observations related to the financial reporting of agencies in the Planning, Industry and Environment cluster for 2020, including any financial implications from the recent emergency events.

Section highlights

  • Unqualified audit opinions were issued for all completed 30 June 2020 financial statements audits. Timeliness of financial reporting remains an issue for 13 agencies.
  • Significant deficiencies were identified in Property NSW's lease data maintenance and lease calculations. Cluster agencies can also improve their management of lease information provided by Property NSW.
  • The number of unprocessed Aboriginal land claims continued to increase. During 2020–21, a performance audit will assess the effectiveness and efficiency of the administration of Aboriginal land claims.

The Department has not yet developed a statutory reporting framework for Crown land managers and will need to provide additional resources to help Crown land managers meet their financial reporting obligations.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our:

  • observations and insights from our financial statements audits of agencies in the Planning, Industry and Environment cluster
  • assessment of how well cluster agencies adapted their systems, policies and procedures, and governance arrangements in response to recent emergencies
  • review of how the cluster agencies managed the increased risks associated with new programs aimed at stemming the spread of COVID-19 and stimulating the economy.

Cluster agencies experienced a range of control and governance related issues in recent years. An increased number of high risk issues and greater proportion of repeat issues were identified as part of our audits. It is important for cluster agencies to promptly address these issues.

Section highlights

  • Six high risk issues were identified during 2019–20 audits. One in three issues identified and reported to management in 2019–20 were repeat issues.
  • The Department has fast tracked the assessment and determination of 101 projects as a part of the Planning System Acceleration Program.
  • There continues to be significant deficiencies in Crown land records. The Department should ensure the Crown land database is complete and accurate.

Published

Actions for Internal controls and governance 2020

Internal controls and governance 2020

Education
Environment
Community Services
Finance
Health
Industry
Justice
Premier and Cabinet
Transport
Treasury
Compliance
Cyber security
Information technology
Internal controls and governance
Management and administration
Procurement

The Auditor-General for New South Wales, Margaret Crawford today released her report on the findings and recommendations from the 2019–20 financial audits that relate to internal controls and governance at 40 of the largest agencies in the NSW public sector.

The bushfire and flood emergencies and the COVID‑19 pandemic continue to have a significant impact on the people and public sector of New South Wales. The scale of the government response to these events has been significant. The report focuses on the effectiveness of internal controls and governance processes, including relevant agencies’ response to the emergencies. In particular, the report focuses on:

  • financial and information technology controls
  • business continuity and disaster recovery planning arrangements
  • procurement, including emergency procurement
  • delegations that support timely and effective decision-making.

Due to the ongoing impact of COVID‑19 agencies have not yet returned to a business‑as‑usual environment. ‘Agencies will need to assess their response to the recent emergencies and update their business continuity, disaster recovery and other business resilience frameworks to reflect the lessons learnt from these events’ the Auditor-General said.

The report noted that special procurement provisions were put in place to allow agencies to better respond to the COVID-19 pandemic. The Auditor-General recommended agencies update their procurement policies to reflect the current requirements of the NSW Procurement Framework and the emergency procurement requirements.

Read the PDF report

This report analyses the internal controls and governance of 40 of the largest agencies in the NSW public sector for the year ended 30 June 2020. These 40 agencies constitute an estimated 85 per cent of total expenditure for all NSW public sector agencies.

1. Internal control trends
New, repeat and high risk findings

Internal control deficiencies increased by 13 per cent compared to last year. This is predominately due to a seven per cent increase in new internal control deficiencies and 24 per cent increase in repeat internal control deficiencies. There were ten high risk findings compared to four last year.

The recent emergencies have consumed agency time and resources and may have contributed to the increase in internal control deficiencies, particularly repeat deficiencies.

Agencies should:

  • prioritise addressing high-risk findings
  • address repeat internal control deficiencies by re-setting action plans and timeframes and monitoring the implementation status of recommendations.
Common findings

A number of findings remain common across multiple agencies over the last four years, including:

  • out of date or missing policies to guide appropriate decisions
  • poor record keeping and document retention
  • incomplete or inaccurate centralised registers or gaps in these registers.
2. Information technology controls
IT general controls

We found deficiencies in information security controls over key financial systems including:

  • user access administration deficiencies relating to inadequate oversight of the granting, review and removal of user access at 53 per cent of agencies
  • privileged users were not appropriately monitored at 43 per cent of agencies
  • deficient password controls that did not align to the agency's own password policies at 25 per cent of agencies.

The deficiencies above increase the risk of non-compliance with the NSW Cyber Security Policy, which requires agencies to have processes in place to manage user access, including privileged user access to sensitive information or systems and remove that access once it is not required or employment is terminated.

3. Business continuity and disaster recovery planning
Assessing risks to business continuity and Scenario testing

The response to the recent emergencies and the COVID-19 pandemic has encompassed a wide range of activities, including policy setting, on-going service delivery, safety and availability of staff, availability of IT and other systems and financial management. Agencies were required to activate their business continuity plans in response, and with the continued impact of COVID-19 have not yet returned to a business-as-usual environment.

Our audits focused on the preparedness of agency business continuity and disaster recovery planning arrangements prior to the onset of the COVID-19 pandemic.

We identified deficiencies in agency business continuity and disaster recovery planning arrangements. Twenty-three per cent of agencies had not conducted a business impact analysis (BIA) to identify critical business functions and determine business continuity priorities. Agencies can also improve the content of their BIA. For example, ten per cent of agencies' BIAs did not include recovery time objectives and six per cent of agencies did not identify key IT systems that support critical business functions. Scenario testing improves the effectiveness with which a live crisis is handled, but 40 per cent of agencies had not conducted a business continuity scenario testing exercise in the period from 1 January 2019 to 31 December 2019. There were also opportunities to improve the effectiveness of scenario testing exercises by:

  • involving key dependent or inter-dependent third parties who support or deliver critical business functions
  • testing one or more high impact scenarios identified in their business continuity plan
  • preparing a formalpost-exercise report documenting the outcome of their scenario testing.

Agencies have responded to the recent emergencies but addressing deficiencies will ensure agencies have adequate safeguards in their processes to again respond in the future, if required.

During 2020–21 we plan to conduct a performance audit on 'Business continuity and disaster recovery planning'. This audit will consider the effectiveness of agency business continuity planning arrangements to maintain business continuity through the recent emergencies and/or COVID-19 pandemic and return to a business-as-usual environment. We also plan to conduct a performance audit on whole-of-government 'Coordination of emergency responses'.

Responding to disruptions

We found agencies' governance functions could have been better informed about responses to disruptive incidents that had activated a business continuity or disaster recovery response between 1 January 2019 to 31 December 2019. For instance:

in 89 per cent of instances where a business continuity response was activated, a post-incident review had been performed. In 82 per cent of these instances, the outcomes were reported to a relevant governance or executive management committee

in 95 per cent of instances where a disaster recovery response was activated, a post incident review had been performed. In 86 per cent of these instances, the outcomes were reported to a relevant governance committee or executive management committee.

Examples of recorded incidents included extensive air quality issues and power outages due to bushfires, system and network outages, and infected and hijacked servers.

Agencies should assess their response to the recent emergencies and the COVID-19 pandemic and update business continuity, disaster recovery and other business resilience frameworks to incorporate lessons learned. Agencies should report to those charged with governance on the results and planned actions.

Management review and oversight Eighty-two per cent and 86 per cent of agencies report to their audit and risk committees (ARC) on their business continuity and disaster recovery planning arrangements, respectively. Only 18 per cent and five per cent of ARCs are briefed on the results of respective scenario testing. Briefing ARCs on the results of scenario testing exercises helps inform their decisions about whether sound and effective business continuity and disaster recovery arrangements have been established.
4. Procurement, including emergency procurement
Policy framework

Agency procurement policies did not capture the requirements of several key NSW Procurement Board Directions (the Directions), increasing the risk of non-compliance with the Directions. We noted: 

  • 67 per cent of agencies did specify that procurement above $650,000 must be open to market unless exempt or procured through an existing Whole of Government Scheme or contract
  • 36 per cent of agencies did specify that procurements above $500,000 payable in foreign currencies must be hedged
  • 69 per cent of agencies' policies did specify that the agency head or cluster CFO must authorise the engagement of consultants where the engagement of the supplier does not comply with the standard commercial framework.

Recommendation: Agencies should review their procurement policies and guidelines to ensure they capture the key requirements of the NSW Government Procurement Policy Framework, including NSW Procurement Board Directions.

Managing contracts

Eighty-eight per cent of agencies maintain a central contract register to record all details of contracts above $150,000, which is a requirement of GIPA legislation. Of the agencies that maintained registers, 13 per cent did not capture all contracts and eight per cent did not include all relevant contract details.

Sixteen per cent of agencies did not periodically review their contract register. Timely review increases compliance with GIPA legislation, and enhances the effectiveness with which procurement business units monitor contract end dates, contract extensions and commence new procurement.

Training and support

Ninety-three per cent of agencies provide training to staff involved in procurement processes, and a further 77 per cent of agencies provide this training on an on-going basis. Of the seven per cent of agencies that had not provided training to staff, we noted gaps in aspects of their procurement activity, including:

  • not conducting value for money assessments prior to renewing or extending the contract with their existing supplier
  • not obtaining approval from a delegated authority to commence the procurement process
  • procurement documentation not specifying certain key details such as the conditions for participation including any financial guarantees and dates for the delivery of goods or supply of services.

Training on procurement activities ensures there is effective management of procurement processes to support operational requirements, and compliance with procurement directions.

Procurement activities While agencies had implemented controls for tender activities above $650,000, 43 per cent of unaccredited agencies did not comply with the NSW Procurement Policy Framework because they had not had their procurement endorsed by an accredited agency within the cluster or by NSW Procurement. This endorsement aims to ensure the procurement is properly planned to deliver a value for money outcome before it commences.
Emergency procurement

As at 30 June 2020, agencies within the scope of this report reported conducting 32,239 emergency procurements with a total contract value of $316,908,485. Emergency procurement activities included the purchase of COVID-19 cleaning and hygiene supplies.

The government, through NSW Procurement released the 'COVID-19 Emergency procurement procedure', which relaxed procurement requirements to allow agencies to make COVID-19 emergency procurements. Our review against the emergency procurement measures found most agencies complied with requirements. For example:

  • 95 per cent of agencies documented an assessment of the need for the emergency procurement for the good and/or service
  • 86 per cent of agencies obtained authorisation of the emergency procurement by the agency head or the nominated employee under Public Works and Procurement Regulation 2019
  • 76 per cent of agencies reported the emergency procurement to the NSW Procurement Board.

Complying with the procedure helps to ensure government resources are being efficiently, effectively, economically and in accordance with the law.

Recommendation: Agency procurement frameworks should be reviewed and updated so they can respond effectively to emergency situations that may arise in the future. This includes:

  • updating procurement policies and guidelines to define an emergency situation, specify who can approve emergency procurement and capture other key requirements
  • using standard templates and documentation to prompt users to capture key requirements, such as needs analysis, supplier selection criteria, price assessment criteria, licence and insurance checks
  • having processes for reporting on emergency procurements to those charged with governance and NSW Procurement.
5. Delegations
Instruments of delegation

We found that agencies have established financial and human resources delegations, but some had not revisited their delegation manuals following the legislative and machinery of government changes. For those agencies impacted by machinery of government changes we noted:

  • 16 per cent of agencies had not updated their financial delegations to reflect the changes
  • 16 per cent of agencies did not update their human resources delegations to reflect the changes.

Delegations manuals are not always complete; 16 per cent of agencies had no delegation for writing off bad debts and 26 per cent of agencies had no delegation for writing off capital assets.

Recommendation: Agencies should ensure their financial and human resources delegation manuals contain regular set review dates and are updated to reflect the Government Sector Finance Act 2018, machinery of government changes and their current organisational structure and roles and responsibilities.

Compliance with delegations

Agencies did not understand or correctly apply the requirements of the Government Sector Finance Act 2018 (GSF Act), resulting in non-compliance with the Act. We found that 18 per cent of agencies spent deemed appropriations without obtaining an authorised delegation from the relevant Minister(s), as required by sections 4.6(1) and 5.5(3) of the GSF Act.

Further detail on this issue will be included in our Auditor-General's Reports to Parliament on Central Agencies, Education, Health and Stronger Communities, which will be tabled throughout December 2020.

Recommendation: Agencies should review financial and human resources delegations to ensure they capture all key functions of laws and regulations, and clearly specify the relevant power or function being conferred on the officer.

6. Status of 2019 recommendations
Progress implementing last year's recommendations

Recommendations were made last year to improve transparency over reporting on gifts and benefits and improve the visibility management and those charged with governance had over actions taken to address conflicts of interest that may arise. This year, we continue to note:

  • 38 per cent of agencies have not updated their gifts and benefits register to include all the key fields required under the minimum standards set by the Public Service Commission
  • 56 per cent of agencies have not provided training to staff and 63 per cent of agencies have not implemented an annual attestation process for senior management
  • 97 per cent of agencies have not published their gifts and benefits register on their website and 41 per cent of agencies are not reporting on trends in the gifts and benefits register to those charged with governance.

While we acknowledge the significance of the recent emergencies, which have consumed agency time and resources, we note limited progress has been made implementing these recommendations. Further detail on the status of implementing all recommendations is in Appendix 2.

Recommendation: Agencies should re-visit the recommendations made in last year's report on internal controls and governance and action these recommendations.

Internal controls are processes, policies and procedures that help agencies to:

  • operate effectively and efficiently
  • produce reliable financial reports
  • comply with laws and regulations
  • support ethical government.

This chapter outlines the overall trends for agency controls and governance issues, including the number of audit findings, the degree of risk those deficiencies pose to the agency, and a summary of the most common deficiencies we found across agencies. The rest of this report presents this year’s controls and governance findings in more detail.

Section highlights

We identified ten high risk findings, compared to four last year with two findings repeated from the previous year. There was an overall increase of 13 per cent in the number of internal control deficiencies compared to last year due to a seven per cent increase in new internal control deficiencies, and a 24 per cent increase in repeat internal control deficiencies. The recent emergencies have consumed agency time and resources and may have contributed to the increase in internal control deficiencies, particularly repeat deficiencies.

We identified a number of findings that remain common across multiple agencies over the last four years. Some of these findings related to areas that are fundamental to good internal control environments and effective organisational governance. Examples include:

  • out of date or missing policies to guide appropriate decisions
  • poor record keeping and document retention
  • incomplete or inaccurate centralised registers, or gaps in these registers.

Policies, procedures and internal controls should be properly designed, be appropriate for the current organisational structure and its business activities, and work effectively.

This chapter outlines our audit observations, conclusions and recommendations, arising from our review of agency controls to manage key financial systems.

Section highlights

Government agencies’ financial reporting is heavily reliant on information technology (IT). We continue to see a high number of deficiencies related to IT general controls, particularly those related to user access administration. These controls are key in adequately protecting IT systems from inappropriate access and misuse.

IT is also important to the delivery of agency services. These systems often provide the data to help monitor the efficiency and effectiveness of agency processes and services they deliver. Our financial audits do not review all agency IT systems. For example, IT systems used to support agency service delivery are generally outside the scope of our financial audit. However, agencies should also consider the relevance of our findings to these systems.

Agencies need to continue to focus on assessing the risks of inappropriate access and misuse and the implementation of controls to adequately protect their systems, focussing on the processes in place to grant, remove and monitor user access, particularly privileged user access.

 

This chapter outlines our audit observations, conclusions and recommendations, arising from our review of agency business continuity and disaster recovery planning arrangements.

Section highlights

We identified deficiencies in agency business continuity and disaster recovery planning arrangements and opportunities for agencies to enhance their business continuity management and disaster recovery planning arrangements. This will better prepare them to respond to a disruption to their critical functions, resulting from an emergency or other serious event. Twenty-three per cent of agencies had not conducted a business impact analysis (BIA) to identify critical business functions and determine business continuity priorities and 40 per cent of agencies had not conducted a business continuity scenario testing exercise in the period from 1 January 2019 to 31 December 2019. Scenario testing improves the effectiveness with which a live crisis is handled.

This section focusses on the preparedness of agency business continuity and disaster recovery planning arrangements prior to the onset of the COVID-19 pandemic. While agencies have responded to the recent emergencies, proactively addressing deficiencies will ensure agencies have adequate safeguards in their processes to again respond in the future, if required.

During 2020–21 we plan to conduct a performance audit on 'Business continuity and disaster recovery planning'. This audit will consider the effectiveness of agency business continuity planning arrangements to maintain business continuity through the recent emergencies and/or COVID-19 pandemic and return to a business-as-usual environment. We also plan to conduct a performance audit on whole-of-government 'Coordination of emergency responses'.

 

This chapter outlines our audit observations, conclusions and recommendations, arising from our review of procurement agency procurement policies and procurement activity.

Section highlights

We found agencies have procurement policies in place to manage procurement activity, but the content of these policies was not sufficiently detailed to ensure compliance with NSW Procurement Board Directions (the Directions). The Directions aim to ensure procurement activity achieves value for money and meets the principles of probity and fairness.

Agencies have generally implemented controls over their procurement process. In relation to emergency procurement activity, agencies reported conducting 32,239 emergency procurements with a total contract value of $316,908,485 up to 30 June 2020. Our review of emergency procurement activity conducted during 2019–20 identified areas where some agencies did not fully comply with the 'COVID-19 Emergency procurement procedure'.

We also found not all agencies are maintaining complete and accurate contract registers. This not only increases the risk of non-compliance with GIPA legislation, but also limits the effectiveness of procurement business units to monitor contract end dates, contract extensions and commence new procurement in a timely manner. We noted instances where agencies renewed or extended contracts without going through a competitive tender process during the year.

 

This chapter outlines our audit observations, conclusions and recommendations, arising from our review of agency compliance with financial and human resources delegations.

Section highlights
We found that agencies are not always regularly reviewing and updating their financial and human resources delegations when there are changes to legislation or other organisational changes within the agency or from machinery of government changes. For example, agencies did not understand or correctly apply the requirements of the GSF Act, resulting in non-compliance with the Act. We found that 18 per cent of agencies spent deemed appropriations without obtaining an authorised delegation from the relevant Minister(s), as required by sections 4.6(1) and 5.5(3) of the GSF Act.
In order for agencies to operate efficiently, make necessary expenditure and human resource decisions quickly and lawfully, particularly in emergency situations, it is important that delegations are kept up to date, provide clear authority to decision makers and are widely communicated.

Appendix one – List of 2020 recommendations 

Appendix two – Status of 2019 recommendations

Appendix three – Cluster agencies

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Support for regional town water infrastructure

Support for regional town water infrastructure

Industry
Environment
Local Government
Infrastructure
Management and administration
Regulation
Risk

The Auditor-General for New South Wales, Margaret Crawford, released a report today examining whether the Department of Planning, Industry and Environment has effectively supported the planning for, and funding of, town water infrastructure in regional NSW.

The audit found that the department has not effectively supported or overseen town water infrastructure planning since at least 2014. It does not have a clear regulatory approach and lacks internal procedures and data to guide its support for local water utilities that service around 1.85 million people in regional NSW.

The audit also found that the department has not had a strategy in place to target investments in town water infrastructure to the areas of greatest priority. A state-wide plan is now in development.

The Auditor-General made seven recommendations to the department, aimed at improving the administration and transparency of its oversight, support and funding for town water infrastructure, and at strengthening its sector engagement and interagency coordination on town water planning issues and investments.

According to the Auditor-General, ‘A continued focus on coordinating town water planning, investments and sector engagement is needed for the department to more effectively support, plan for and fund town water infrastructure, and to work with local water utilities to help avoid future shortages of safe water in regional towns and cities.’ 

This report is part of a multi-volume series on the theme of water. Refer to ‘Water conservation in Greater Sydney’ and ‘Water management and regulation – undertaking in 2020-21’.

Read full report (PDF)

Safe and reliable water and sewer services are essential for community health and wellbeing, environmental protection, and economic productivity. In 2019, during intense drought, around ten regional New South Wales (NSW) cities or towns were close to ‘zero’ water and others had six to 12 months of supply. In some towns, water quality was declared unsafe.

Ensuring the right water and sewer infrastructure in regional NSW to deliver these services (known as 'town water infrastructure') involves a strategic, integrated approach to water management. The NSW Government committed to ‘secure long-term potable water supplies for towns and cities’ in 2011. In 2019, it reiterated a commitment to invest in water security by funding town water infrastructure projects.

The New South Wales’ Water Management Act 2000 (WM Act) aims to promote the sustainable, integrated and best practice management of the State’s water resources, and establishes the priority of town water for meeting critical human needs.

The Department of Planning, Industry and Environment (the department) is the lead agency for water resource policy, regulation and planning in NSW. It is also responsible for ensuring water management is consistent with the shared commitments of the Australian, State and Territory Governments under the National Water Initiative. This includes the provision of healthy, safe and reliable water supplies, and reporting on the performance of water utilities.

Ninety-two Local Water Utilities (LWUs) plan for, price and deliver town water services in regional NSW. Eighty-nine are operated by local councils under the New South Wales’ Local Government Act 1993, and other LWUs exercise their functions under the WM Act. The Minister for Water, Property and Housing is the responsible minister for water supply functions under both acts.

The department is the primary regulator of LWUs. NSW Health, the NSW Environment Protection Authority (EPA) and the Natural Access Resource Regulator (NRAR) also regulate aspects of LWUs' operations. The department’s legislative powers with respect to LWUs cover approving infrastructure developments and intervening where there are town water risks, or in emergencies. In this context, the department administers the Best Practice Management of Water Supply and Sewerage Guidelines (BPM Guidelines) to support its regulation and to assist LWUs to strategically plan and price their services, including their planning for town water infrastructure.

Under the BPM Guidelines, the department supports LWU’s town water infrastructure planning with the Integrated Water Cycle Management (IWCM) Checklist. The Checklist outlines steps for LWUs to prepare an IWCM strategy: a long-term planning document that sets out town water priorities, including infrastructure and non-infrastructure investments, water conservation and drought measures. The department's objective is to review and approve (i.e. give ‘concurrence to’) an IWCM strategy before the LWU implements it. In turn, these documents should provide the department with evidence of town water risks, issues and infrastructure priorities.

The department also assesses and co-funds LWU's town water infrastructure projects. In 2017, the department launched the $1 billion Safe and Secure Water Program to ensure town water infrastructure in regional NSW is secure and meets current health and environmental standards. The program was initially established under the Restart NSW Fund.

This audit examined whether the department has effectively supported the planning for and funding of town water infrastructure in regional NSW. It focused on the department’s activities since 2014. This audit follows a previous Audit Office of NSW report which found that the department had helped to promote better management practices in the LWU sector, up to 2012–13.

Conclusion

The Department of Planning, Industry and Environment has not effectively supported or overseen town water infrastructure planning in regional NSW since at least 2014. It has also lacked a strategic, evidence-based approach to target investments in town water infrastructure.

A continued focus on coordinating town water planning, investments and sector engagement is needed for the department to more effectively support, plan for and fund town water infrastructure, and work with Local Water Utilities to help avoid future shortages of safe water in regional towns and cities.

The department has had limited impact on facilitating Local Water Utilities’ (LWU) strategic town water planning. Its lack of internal procedures, records and data mean that the department cannot demonstrate it has effectively engaged, guided or supported the LWU sector in Integrated Water Cycle Management (IWCM) planning over the past six years. Today, less than ten per cent of the 92 LWUs have an IWCM strategy approved by the department.

The department did not design or implement a strategic approach for targeting town water infrastructure investment through its $1 billion Safe and Secure Water Program (SSWP). Most projects in the program were reviewed by a technical panel but there was limited evidence available about regional and local priorities to inform strategic project assessments. About a third of funded SSWP projects were recommended via various alternative processes that were not transparent. The department also lacks systems for integrated project monitoring and program evaluation to determine the contribution of its investments to improved town water outcomes for communities. The department has recently developed a risk-based framework to inform future town water infrastructure funding priorities.

The department does not have strategic water plans in place at state and regional levels: a key objective of these is to improve town water for regional communities. The department started a program of regional water planning in 2018, following the NSW Government’s commitment to this in 2014. It also started developing a state water strategy in 2020, as part of an integrated water planning framework to align local, regional and state priorities. One of 12 regional water strategies has been completed and the remaining strategies are being developed to an accelerated timeframe: this has limited the department’s engagement with some LWUs on town water risks and priorities.

Regional New South Wales (NSW) is home to about a third of the state's population. Infrastructure that provides safe and reliable water and sewer services (also known simply as 'town water infrastructure') is essential for community health and wellbeing, environmental protection, and economic productivity. Planning for and meeting these infrastructure needs, as well as identifying when non-infrastructure options may be a better solution, involves a strategic and integrated approach to water resource management in regional NSW.

We examined whether the department has effectively supported planning for town water infrastructure since 2014. This assessment was made in the context of its current approach to LWU sector regulation. The findings below focus on whether the department has an effective framework including governance arrangements for town water issues to inform state-wide strategic water planning, and whether (at the local level) the department has effectively overseen and facilitated town water infrastructure planning through its Integrated Water Cycle Management (IWCM) planning guidance to LWUs.

We examined whether the department has effectively targeted town water infrastructure funding to policy objectives, with a focus on the design and implementation of the Safe and Secure Water Program (SSWP) since its commencement in 2017. The program’s aim was to fund town water infrastructure projects that would deliver health, social and environmental benefits, and support economic growth and productivity. We also assessed the department’s capacity to demonstrate the outcomes of the SSWP funding and the contributions of its town water infrastructure investments more broadly. Finally, we identified risks to the effectiveness of the department’s work underway since 2018–19, which is intended to enhance its strategic water planning and approach to prioritising investments in reducing town water risks.

Appendix one – Response from agency

Appendix two – Key terms

Appendix three – About the audit

Appendix four – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #341 - released 24 September 2020

Published

Actions for Health capital works

Health capital works

Health
Compliance
Infrastructure
Procurement
Project management

This report examines whether NSW Health effectively planned and delivered major capital works to meet the demand for health services in New South Wales.

The report found that NSW Health has substantially expanded health infrastructure across New South Wales since 2015. However, the program was driven by Local Health District priorities without assessment of the State’s broader and future‑focussed health requirements.

The report found that unclear decision making roles and responsibilities between Health Infrastructure and the Ministry of Health limited the ability of NSW Health to effectively test and analyse investment options.

Project delays and budget overruns on some major projects indicate that Health Infrastructure's project governance, risk assessment and management systems could be improved.

The Auditor‑General recommends that NSW Health ensure its capital projects offer the greatest value to New South Wales by establishing effective policy guidance and enhancing project governance and management systems.

Read full report (PDF)

Since 2011–12, NSW Health has aimed to improve its facilities and build 'future focused' infrastructure. The NSW Government’s 2015–16 election commitments established a four-year $5.0 billion capital program for NSW Health to build and upgrade more than 60 hospitals and health services. The 2019–20 State Budget committed a further $10.1 billion over four years for another 29 projects. This is the largest investment to date on health capital works in New South Wales.

Recent reviews of infrastructure have recognised that population and demographic growth will require a change in the delivery and composition of health infrastructure, including considering greater use of non-traditional, non-capital health service options and assets.

To ensure that expenditure on capital works represents the best value for money, NSW Health's business cases need to be robust and supported by evidence that demonstrates they are worthy investments. The NSW Process of Facility Planning has been the main framework guiding the detailed planning and development of NSW Health's capital works proposals. This framework was developed by the then NSW Department of Health in 2010. Its aim is to ensure investment proposals are supported by rigorous planning processes that address health service needs and provide value for money.

Infrastructure projects of the complexity and scale being delivered by NSW Health carry inherent risks. For example, unplanned cost escalations can potentially impact on the State’s finances. Unforeseen delays can also reduce the intended benefits. The growth in the State’s health capital spend and project profile, means its exposure to such risks has increased over time.

The objective of this audit was to assess the effectiveness of planning and delivery of major capital works to meet demand for health services in New South Wales. To address this objective, the audit examined whether:

  • the Ministry of Health has effective procedures for planning and prioritising investments in major health capital works
  • Health Infrastructure develops robust business cases for initiated major capital works that reliably inform government decision making
  • Health Infrastructure has effective project governance and management systems that support delivering projects on-time, within budget and achievement of intended benefits.

The audit focused on the Ministry of Health and Health Infrastructure – being the lead agencies within NSW Health responsible for prioritising, planning and delivering major health capital works across the State. The audit examined 13 business cases for eight discrete projects over a ten-year period.

Conclusion

NSW Health has substantially expanded health infrastructure across New South Wales since 2015. However, its planning and prioritisation processes were not assessed against a long-term statewide health infrastructure plan and lacked rigorous assessment against non-capital options creating a risk that they do not maximise value for New South Wales.

The scale of NSW Health's capital investment is significant and has grown substantially in recent years. The NSW Government’s election commitments in 2015–16 and 2019–20 collectively set out a $15.0 billion capital program to build and upgrade 89 hospitals and health services. NSW Health developed this infrastructure program in the absence of a statewide health infrastructure strategy and investment framework to focus its planning and decisions on the types of capital investments required to meet the long-term needs of the NSW health system.

Consequently, locally focused priorities of the State’s 17 Local Health Districts have been the primary drivers of NSW Health’s capital investments since 2015–16. Local Health District investment proposals for hospitals were developed without consideration of alternative health options such as community health service models, technology-driven eHealth care, or private sector options. Without rigorous assessment against a range of potential health service options, there is a risk that selected projects do not maximise value for New South Wales.

In recognition of the need for a statewide approach to infrastructure planning, the Ministry of Health recently developed a 20-year Health Infrastructure Strategy and prioritisation framework in 2019. The strategy was approved by the NSW Government in April 2020.

NSW Health's ability to effectively test and analyse its capital investment options has been compromised by unclear decision-making roles and responsibilities between its Health Infrastructure and the Ministry of Health agencies.

While both Health Infrastructure and the Ministry of Health have responsibilities for the assessment of business cases for proposed infrastructure projects, confusion about the roles of each agency at key steps compromised the efficacy of the process. Health Infrastructure and the Ministry of Health have differing views about which agency is responsible for testing business case inputs and conducting comprehensive options appraisals.

As a result of this confusion, Health Infrastructure and the Ministry of Health did not rigorously test Local Health District capital investment proposals against defined statewide health infrastructure investment priorities. The NSW Process of Facility Planning does not clarify the responsibilities of all parties in validating and prioritising Local Health District's Clinical Service Plans and progressing them to business cases.

NSW Health's infrastructure priorities are not sufficiently supported by transparent documentation of selection methodology and the rationale for decisions. Consequently, there is a risk that recommended options, whilst having some economic and health service merit, do not represent the greatest value.

Substantial delays and budget overruns on some major projects indicate that Health Infrastructure's project governance, risk assessment and management systems could be improved.

Health Infrastructure did not fully comply with NSW Government guidelines for developing business cases and making economic appraisals for proposed capital investments. These weaknesses, along with delays and budget overruns on some projects, demonstrate a need for Health Infrastructure to strengthen its project governance, management and quality control systems.

 

Over the period of review, NSW Government policies for business case development and submission have emphasised that effective governance arrangements are critical to a proposal's successful implementation.

NSW Health's Process of Facility Planning similarly highlights the importance of effective governance and project management for achieving good outcomes. It prescribes a general governance structure managed by Health Infrastructure that can be tailored to the planning and delivery of health infrastructure projects greater than $10.0 million.

Project challenges indicate opportunities for strengthening governance and project management

The three major hospital redevelopments examined in metropolitan, regional and rural areas had a combined Estimated Total Cost of more than $1.2 billion and comprised eight discrete projects and 13 separate business cases.

Almost all these projects experienced delivery challenges which impacted achievement of their original objectives and intended benefits. This is expected in complex and large-scale health infrastructure programs. However, in some projects the impacts were significant and resulted in substantial delays, unforeseen costs, and diversion of resources from other priority areas.

Our review of the selected case studies highlighted opportunities for enhancing governance and project management. Specifically, it indicates a need for improving transparency in the management of contingencies, risk management and assessments particularly relating to adverse site conditions and the selection of contractors. There is also a need to strengthen forward planning for options to address unfunded priorities within business cases that risk complicating the delivery of future project stages resulting in unforeseen costs and potentially avoidable budget overruns.

Need for increased transparency and accountability in the management of contingency funds

In February 2017, the Ministry's Capital Strategy Group approved the use of surplus funds of $13.76 million from Stage 1 of the Hornsby Ku-ring-gai Hospital Redevelopment for new works deemed needed to support Stage 2. Following this decision, Health Infrastructure finalised and submitted a business case addendum for Stage 1 to the Ministry in March 2017, addressing the new works comprising a two-storey building for medical imaging and paediatric floors. The business case addendum also addressed options to fit out and procure major medical imaging equipment. The Ministry approved the Stage 1 business case in July 2017, noting the Ministry's Capital Strategy Group had already approved the use of remaining Stage 1 funds to deliver the new works.

Stage 1 was completed in 2015, almost two years before the Stage 1 business case addendum was prepared in February 2017.

The Ministry's decision to approve the new works using $13.76 million of surplus Stage 1 funds did not comply with the NSW Treasury Circular TC 12/20. This policy establishes the Treasurer's approval must be sought and received before a new capital project with an Estimated Total Cost of $5.0 million or more can be approved by NSW Health. The Ministry therefore exceeded its delegated authority in making this decision, as it was not evident it had sought and received the Treasurer's approval prior to doing so.

Consequently, the surplus Stage 1 funds should not have been used by the Ministry to deliver new works in the circumstances. Instead, they should have been released from the Stage 1 project in accordance with established NSW Health procedures, and the Stage 1 Estimated Total Cost revised down accordingly. This did not occur, and NSW Health ultimately directed $11.0 million in surplus Stage 1 funds to the new works.

These circumstances indicate a need to strengthen transparency and accountability within NSW Health for the approval of new projects, and how contingency funds are used in the management of major health capital works. They also demonstrate the impact of weaknesses with options appraisal as the initial Stage 1 business case did not consider alternative options for addressing the initially unfunded works later covered by the Stage 1 business case addendum and ultimately funded from the Stage 1 contingency provision.

Weaknesses in service delivery planning resulted in unaccounted-for costs

In addition to proposing the above-noted new works, the 2017 Stage 1 Business Case Addendum for the Hornsby-Ku-ring-gai development sought to retrospectively address the estimated funding gap of around $14.0 million for the internal fit out, supply of major medical imaging equipment, and cost to operate the medical imaging service at Hornsby Ku-ring-gai Hospital also not addressed in the originally Stage 1 business case.

The Stage 1 business case addendum considered various procurement options to purchase and run the medical imaging services ranging from State operation purchase options to private operation purchase options.

It recommended outsourcing the operation and provision of equipment to the private sector based on estimated savings to the public sector initially of around $650,000 per annum reducing over time to $270,000. The Ministry endorsed this option in June 2017, but it did not ultimately proceed.

A July 2018 report to the Executive Steering Committee on the project shows NSW Health later decided to deliver operation of the medical imaging unit 'traditionally' with an updated estimate of the cost at approximately $16.4 million. The report also shows the Ministry supported the costs now being met by the Northern Sydney Local Health District.

This means the funding gap previously identified in the Stage 1 business case addendum for fitting out the medical imaging building and supply of major medical equipment would need to be met fully by the State, representing a $16.4 million cost overrun for the project.

Examined reports to the Executive Steering Committee show this was largely funded by the Northern Sydney Local Health District via the disposal of land realising approximately $15.0 million in proceeds.

This initially unforeseen cost, along with the additional $11.0 million for the new works approved under the Stage 1 business case addendum, were ultimately merged with the Stage 2 project initially approved in 2017–18 with an Estimated Total Cost of $200 million.

The extent of budget variation on the Hornsby Kur-ring-gai development has not been transparent

The 2019–20 State Budget provided an additional $65.0 million for a further Stage 2A to deliver additional built capacity to support outpatient services, enhanced allied health services, re-housed community health services and the delivery of prioritised clinical services unfunded as part of Stage 2. The funds were approved based on an Investment Decision Template (IDT) that examined two options in addition to the base case representing scoping alternatives to the preferred master planned capital solution.

However, we found the IDT showed around 23 per cent of the $65.0 million sought (i.e. $15.0 million) was to be allocated to fund the deficit in Stage 2, which had arisen as a result of project delays due to adverse site conditions. This was not discussed in the IDT.

The February 2020 report to the Executive Steering Committee shows a combined Stage 2 and 2A final forecast cost of $292.6 million against a potential budget of $290.7 million representing an overall deficit for the project of around 0.6 per cent.

However, this favourable final budget position does not transparently show the funding challenges experienced over the project's implementation to-date. The three major budget issues include:

  • inappropriate use of around $11.0 million in Stage 1 contingency for originally unfunded works contrary to Treasury policy
  • the additional $16.4 million cost unforeseen in the Stage 1 business case for delivering medical imaging services mostly funded through the sale of land
  • an additional $15.0 million from Stage 2A to cover the budget overrun in Stage 2 due to adverse site conditions.

The cumulative impact of these events is that Stages 1 and 2 of the Hornsby project cost approximately $42.4 million than it should have in the circumstances around 14 per cent more than what the revised combined Estimated Total Cost for both stages should have been after releasing the $11.0 million in surplus Stage 1 funds, with Stage 2 delayed by around 14 months.

Opportunity for strengthening risk management for adverse site conditions

Major construction projects often experience adverse site conditions which can be difficult to fully detect in advance. However, we found this was a common occurrence in the projects we examined sometimes with significant time and/or budget impacts indicating scope to enhance related risk and cost assessments. Specifically:

  • Hornsby Ku-ring-gai Hospital Redevelopment Stage 2: adverse site conditions during demolition works resulted in an 11-month delay for delivering the medical imaging unit and 14-month delay completing Stage 2 main works including need for additional $15.0 million in funds to cover the resultant budget deficit for the project.
  • Blacktown Mt Druitt Hospital Redevelopment Stage 2: adverse site conditions combined with project complexity delayed completion of the early works by approximately five months. This contributed to the delay in completing the main construction works which occurred around nine months later than planned in the business case.
  • Dubbo Health Service Redevelopment Stages 3 and 4: Health Infrastructure advised adverse site conditions including asbestos containing materials and ground conditions delayed works for the main building with completion forecast for March 2021, around 21 months later than planned in the final business case. This resulted in the need for additional $13.5 million to cover increased construction costs and risks, increasing the Stage 3 and 4 forecast final cost from $150 million to $163.5 million as at February 2020.

These examples indicate a risk the cumulative impact of adverse site conditions may be substantial when measured across both time and Health Infrastructure's full delivery program. They also point to potential for Health Infrastructure to achieve efficiencies and improved outcomes from strengthening its approach to assessing and mitigating the risks from adverse site conditions.

Limited due diligence with prospective contractors risks avoidable delays and costs

Main construction works on Stage 1 of the Dubbo Health Service Redevelopment were completed in October 2015, approximately 13 months later than planned in the final business case. Delays were mainly due to insolvency of the early works contractor resulting in their departure from the project. The ensuing 11-month delay in completing the early works significantly impacted the overall schedule and delivery of main construction works.

The insolvency event was significant as it affected nine separate Health Infrastructure projects – three of which had yet to reach practical completion. It also affected state-funded projects in other sectors. It resulted in the need for additional funding of $11.5 million that was provided in the 2014–15 State Budget increasing the total Stage 1 and 2 budget from $79.8 million to $91.3 million.

Health Infrastructure’s analysis of lessons learned shows it worked actively to mitigate the impacts of the insolvency event across all affected projects. However, it also indicates a risk the lessons were mainly focused on mitigating the impacts after an insolvency event occurred rather than on prevention.

Although Health Infrastructure initially commissioned a financial assessment of the now insolvent early works contractor before engagement, it did not detect any risks of the impending insolvency and instead concluded the contractor was in a strong financial position. However, the contractor became insolvent shortly after commencement approximately seven months later. This indicates a risk of weaknesses in the assessment performed that was not explicitly addressed by the lessons learned.

Delivery of the main construction works were further impacted by disputes with the main works contractor over the scope of works for the renal unit resulting in Health Infrastructure terminating the contract in November 2016 following lengthy negotiations over several months.

The scope of works relating to the renal unit were ultimately transferred to Stages 3 and 4 and were delivered in December 2019, around five years later than originally planned in the business case.

Health Infrastructure advised the delay was ultimately beneficial to the project because the refurbishment works for the renal unit, initially scheduled for Stages 1 and 2, would have been demolished to accommodate the new Western Cancer Centre proposed after Stages 1 and 2 and currently being delivered in parallel with Stages 3 and 4.

Health Infrastructure advised the actual cost of Stages 1 and 2 was $84.7 million against the budget of $91.3 million. The residual $6.6 million relates to the renal works not delivered during Stage 1 and 2 and transferred to Stage 3 and 4.

Health Infrastructure advised the contractual provisions for mitigating insolvency events 'in-flight' are limited highlighting the importance of proactive and effective due diligence prior to engaging contractors for significant construction projects.

Need for a quality framework linked to staff training and capability development

Health Infrastructure's 2017-20 Corporate Plan identifies the development of a quality framework to support delivery of future-focused outcomes as a key organisational priority. Related initiatives within the Corporate Plan describe a framework underpinned by a Quality Committee providing advice on:

  • records management, to meet the requirements of the State Records Act 1998
  • project assurance, to ensure future focused outcomes and enhance Health Infrastructure's Standards, Policies, Procedures and Guidelines, Templates and Design Guidance Notes
  • knowledge management and library services, to promote and leverage from project learnings.

Although Health Infrastructure has some elements of a quality framework it is not yet fully in place. Health Infrastructure advised it had yet to establish the quality framework and related committee described in its Corporate Plan due in part to its focus on responding to the growth of its capital program.

Health Infrastructure's Development and Innovation team has been active in supporting continuous improvement in knowledge and project management including development of business cases. Although useful, these initiatives have relied heavily on leveraging and disseminating insights from Gateway reviews and have not formed part of a systematic quality and continuous improvement framework.

The limited focus on the quality of business cases is reflected in internal performance monitoring and reporting which focuses mainly on tracking the delivery of projects against internal benchmarks, often revised from the baselines in the business case, and expenditure against cashflow targets. There is no evident internal monitoring and/or reporting to the Chief Executive and Board on defined quality metrics linked to business case development and staff capability.

Performance reporting on balanced scorecard metrics has similarly focused mainly on process rather than quality and has been inconsistent in recent years.

Appendix one – Response from agency

Appendix two – About the audit

Appendix three – Performance auditing

Appendix four – Ministry of Health planning tools and guidelines

Appendix five – Streamlined investment decision process for Health Capital Projects

Appendix six – Timeline of business cases and relevant policy guidelines

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #338 - released 12 August 2020

Published

Actions for Their Futures Matter

Their Futures Matter

Justice
Community Services
Education
Health
Whole of Government
Cross-agency collaboration
Internal controls and governance
Management and administration
Project management

The Auditor-General for New South Wales, Margaret Crawford, released a report today examining whether the Department of Communities and Justice had effective governance and partnership arrangements in place to deliver ‘Their Futures Matter’.

Their Futures Matter was intended to place vulnerable children and families at the heart of services, and direct investment to where funding and programs deliver the greatest social and economic benefits. It was a four-year whole-of-government reform in response to the 2015 Tune Review of out-of-home care.

The Auditor-General found that while important foundations were put in place, and new programs trialled, the key objective to establish an evidence-based whole-of-government early intervention approach for vulnerable children and families in NSW was not achieved.

Governance and cross-agency partnership arrangements to deliver Their Futures Matter were found to be ineffective. 'Their Futures Matter lacked mechanisms to secure cross portfolio buy‑in and did not have authority to drive reprioritisation of government investment', the Auditor-General said.

At the reform’s close, the majority of around $380 million in investment funding remains tied to existing agency programs, with limited evidence of their comparative effectiveness or alignment with Their Futures Matter policy objectives. The reform concluded on 30 June 2020 without a strategy or plan in place to achieve its intent.

The Auditor-General made four recommendations to the Department of Communities and Justice, aimed at improving implementation of outstanding objectives, revising governance arrangements, and utilising the new human services data set to address the intent of the reform. However, these recommendations respond only in part to the findings of the audit.

According to the Auditor-General, ‘Cross-portfolio leadership and action is required to ensure a whole-of-government response to delivering the objectives of Their Futures Matter to improve outcomes for vulnerable children, young people and their families in New South Wales.’

Read full report (PDF)

In 2016, the NSW Government launched 'Their Futures Matter' (TFM) - a whole-of-government reform aimed at delivering improved outcomes for vulnerable children, young people and their families. TFM was the government's key response to the 2015 Independent Review of Out of Home Care in New South Wales (known as 'the Tune Review').

The Tune Review found that, despite previous child protection reforms, the out of home care system was ineffective and unsustainable. It highlighted that the system was not client-centred and was failing to improve the long-term outcomes for vulnerable children and families. The review found that the greatest proportion of relevant expenditure was made in out of home care service delivery rather than in evidence-based early intervention strategies to support children and families when vulnerabilities first become evident to government services (such as missed school days or presentations to health services).

The then Department of Family and Community Services (FACS) designed the TFM reform initiatives, in consultation with central and human services agencies. A cross-agency board, senior officers group, and a new unit in the FACS cluster were established to drive the implementation of TFM. In the 2016–17 Budget, the government allocated $190 million over four years (2016–17 to 2019–20) to the reform. This resourced the design and commissioning of evidence-based pilots, data analytics work, staffing for the implementation unit and secretariat support for the board and cross-agency collaboration.

As part of the TFM reform, the Department of Premier and Cabinet, NSW Treasury and partnering agencies (NSW Health, Department of Education and Department of Justice) identified various existing programs that targeted vulnerable children and families (such as the preceding whole-of-government ‘Keep Them Safe’ reform coming to an end in June 2020). Funding for these programs, totalling $381 million in 2019–20, was combined to form a nominal ‘investment pool’. The government intended that the TFM Implementation Board would use this pool to direct and prioritise resource allocation to evidence-based interventions for vulnerable children and families in NSW.

This audit assessed whether TFM had effective governance and partnership arrangements in place to enable an evidence-based early intervention investment approach for vulnerable children and families in NSW. We addressed the audit objective with the following audit questions:

  • Was the TFM reform driven by effective governance arrangements?
  • Was the TFM reform supported by effective cross-agency collaboration?
  • Has the TFM reform generated an evidence base to inform a cross-agency investment approach in the future?

The audit did not seek to assess the outcomes for children, young people and families achieved by TFM programs and projects.

Conclusion

The governance and cross-agency partnership arrangements used to deliver the Their Futures Matter reform were ineffective. Important foundations were put in place, and new programs trialled over the reform's four years. However, an evidence-based whole-of-government early intervention approach for vulnerable children and families in NSW − the key objective of the reform − was not established. The reform concluded in June 2020 without a strategy or plan in place to achieve its intent.

The governance arrangements established for the Their Futures Matter (TFM) reform did not provide sufficient independence, authority and cross-agency clout to deliver on the reform’s intent. This hindered delivery of the reform's key elements, particularly the redirection of funding to evidence-based earlier intervention supports, and limited the impact that TFM could have on driving system change.

TFM increased focus on the contribution that other agencies outside of the former Family and Community Services portfolio could make in responding to the needs of vulnerable children and families, and in reducing the demand costs of related government service delivery. Despite being a whole-of-government reform, TFM lacked mechanisms to secure cross-portfolio buy-in and lacked the powers to drive reprioritisation of government investment in evidence-based and earlier intervention supports across agencies. At the reform’s close, the majority of the reform's investment pool funding remained tied to existing agency programs, with limited evidence of their comparative effectiveness or alignment with Their Futures Matter policy objectives.

TFM began building an evidence base about ‘what works’, including piloting programs and creating a new dataset to identify risk factors for vulnerability and future costs to government. However, this evidence base does not yet comprehensively map how existing services meet needs, identify system duplications or gaps, nor demonstrate which government funded supports and interventions are most effective to make a difference to life outcomes for vulnerable children and families in NSW.
Despite these issues, the need, intent and vision for Their Futures Matter remains relevant and urgent, as issues identified in the Tune Review remain pertinent.

Their Futures Matter (TFM) is a whole-of-government reform to deliver improved outcomes for vulnerable children, young people and their families.

Supported by a cross-agency TFM Board, and the TFM Unit in the then Department of Family and Community Services (FACS), the reform aimed to develop whole-of-government evidence-based early intervention investment approaches for vulnerable children and families in NSW.

Governance refers to the structures, systems and practices that an organisation has in place to:

  • assign decision-making authorities and establish the organisation's strategic direction
  • oversee the delivery of its services, the implementation of its policies, and the monitoring and mitigation of its key risks
  • report on its performance in achieving intended results, and drive ongoing improvements.

We examined whether the TFM reform was driven by effective governance arrangements and cross-agency collaboration.

The reform agenda and timeframe set down for Their Futures Matter (TFM) were ambitious. This chapter assesses whether the TFM Board and TFM Unit had the capability, capacity and clout within government to deliver the reform agenda.

Creating a robust evidence base was important for Their Futures Matter, in order to:

  • identify effective intervention strategies to improve supports and outcomes for vulnerable children and families
  • make efficient use of taxpayer money to assist the maximum number of vulnerable children and families
  • inform the investment-based approach for future funding allocation.

This chapter assesses whether the TFM reform has developed an evidence base to inform cross-agency investment decisions.

Appendix one – Response from agency

Appendix two – TFM governance entities

Appendix three – TFM Human Services Data Set

Appendix four – TFM pilot programs

Appendix five – About the audit

Appendix six – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #337 - released 24 July 2020

Published

Actions for Water conservation in Greater Sydney

Water conservation in Greater Sydney

Environment
Industry
Infrastructure
Internal controls and governance
Management and administration
Regulation
Risk

This report examines whether the Department of Planning, Industry and Environment, and Sydney Water have effectively progressed water conservation initiatives in Greater Sydney.

The report found that the department and Sydney Water have not effectively investigated, implemented or supported water conservation initiatives in Greater Sydney. The agencies have not met key requirements of the current Metropolitan Water Plan and Sydney Water has not met all its operating licence requirements for water conservation. There has been little policy or regulatory reform, little focus on identifying new options and investments, and limited planning and implementation of water conservation initiatives.

As a result, Greater Sydney's water supply may be less resilient to population growth and climate variability, including drought.

The Metropolitan Water Plan states that water conservation, including recycling water, makes the drinking water supply go further. The plan also states that increasing water conservation efforts may be cheaper than building new large-scale supply options and can delay the timing of investment in new supply infrastructure.

The Auditor-General recommends the department develop a clear policy and regulatory position on water conservation options, improve governance and funding for water conservation, and work with Sydney Water to assess the viability of water conservation initiatives. The report also recommends improvements to Sydney Water’s planning for and reporting on water conservation, including the transparency of this information.

This report is part of a multi-volume series on the theme of water. Refer to ‘Support for regional town water infrastructure’ and ‘Water management and regulation – undertaking in 2020-21’.

Read full report (PDF)

The current, 2017 Metropolitan Water Plan states that water conservation, including recycling water, makes the drinking water supply go further. The plan also states that increasing water conservation efforts may be cheaper than building new large-scale supply options and can delay the timing of investment in new supply infrastructure.

Water conservation refers to water recycling, leakage management and programs to enhance water efficiency. Water recycling refers to both harvesting stormwater for beneficial use and reusing wastewater.

This audit examined whether water conservation initiatives for the Greater Sydney Metropolitan area are effectively investigated, implemented and supported. We audited the Department of Planning, Industry and Environment (the Department) and the Sydney Water Corporation (Sydney Water), with a focus on activities since 2016.

The Department is responsible for the integrated and sustainable management of the state’s water resources under the Water Management Act 2000, which includes encouraging ‘best practice in the management and use of water’ as an objective. The Department is also responsible for strategic water policy and planning for Greater Sydney, including implementing the Metropolitan Water Plan.

Sydney Water is a state-owned corporation and the supplier of water, wastewater, recycled water and some stormwater services to more than five million people in Greater Sydney. It is regulated by an operating licence that is issued by the Governor on the recommendation of the Independent Pricing and Regulatory Tribunal (IPART). The Tribunal determines Sydney Water’s maximum prices, reviews its operating licence and monitors compliance. Sydney Water's operating licence and reporting manual set out requirements for its planning, implementing and reporting of water conservation.

From 2007 to 2012, the Climate Change Fund was a source of funds for water conservation activities to be undertaken by the Department and Sydney Water. The Climate Change Fund was established under the Energy and Utilities Administration Act 1987. Four of its six objectives relate to water savings. Water distributors such as Sydney Water can be issued with orders to contribute funds for water-related programs. The Fund is administered by the Department.

In 2016, Sydney Water developed a method for determining whether and how much to invest in water conservation. Known as the ‘Economic Level of Water Conservation’ (ELWC), the method identifies whether it costs less to implement a water conservation initiative than the value of the water saved, in which case the initiative should be implemented.

Conclusion

The Department and Sydney Water have not effectively investigated, implemented or supported water conservation initiatives in Greater Sydney.

The agencies have not met key requirements of the Metropolitan Water Plan and Sydney Water has not met all its operating licence requirements for water conservation. There has been little policy or regulatory reform, little focus on identifying new options and investments, and limited planning and implementation of water conservation initiatives.

As a result, Greater Sydney's water supply may be less resilient to population growth and climate variability, including drought.

The Department has not undertaken an annual assessment of Sydney Water’s level of investment in water conservation against water security risks and the capacity to respond when drought conditions return, as required by the Metropolitan Water Plan. It did not complete identified research and planning activities to support the plan, such as developing and using a framework for assessing the potential for water conservation initiatives for Greater Sydney, and developing a long-term strategy for water conservation and water recycling. It also did not finalise a monitoring, evaluation, reporting and improvement strategy to support the plan.

Sydney Water has been ineffective in driving water conservation initiatives, delivering detailed planning and resourcing for ongoing initiatives, and in increasing its investment in water conservation during drought. These were requirements of the Metropolitan Water Plan. Sydney Water's reporting on water conservation has not met all its operating licence requirements and lacked transparency with limited information on key aspects such as planning for leakage management, how the viability of potential initiatives were assessed, and how adopted initiatives are tracking.

The Department and Sydney Water did not put in place sufficient governance arrangements, including clarifying and agreeing responsibilities for key water conservation planning, delivery and reporting activities. There has also been limited collaboration, capacity building and community engagement to support water conservation, particularly outside times of drought.

Appendix one – Responses from agencies

Appendix two – About the audit

Appendix three – Glossary

Appendix four – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #336 - released 23 June 2020

Published

Actions for Funding enhancements for police technology

Funding enhancements for police technology

Justice
Community Services
Information technology
Management and administration
Procurement
Project management

This report focuses on how the NSW Police Force managed a $100 million program to acquire new technology. The program invested in technologies intended to make police work safer and quicker. These included body-worn video (BWV) cameras, smart phone devices, mobile fingerprint scanners and hand-held drug testing devices.

The audit found that while the NSW Police Force mostly managed the ‘Policing for Tomorrow’ program effectively, investment decision making could be improved in the future. The NSW Police Force missed an opportunity to take a whole-of-organisation approach to identify capability gaps and target the acquired technologies to plug these.

The NSW Police Force has processes in place to monitor the benefits of some of the larger technology, but it does not do this consistently for all procured technology. It could not demonstrate that smaller projects are improving the efficiency or effectiveness of policing.

The audit also found that the NSW Police Force does not routinely engage with external stakeholders on the use or impacts of new technology that changes how officers interact with the public, noting that this will not always be possible for particularly sensitive procurements that involve covert technologies or methodologies.

The Auditor-General made three recommendations to guide improvement of NSW Police Force ICT procurement, benefits management and stakeholder engagement processes.

Read full report (PDF)

Ahead of the March 2015 election, the NSW Government announced a $100 million Policing for Tomorrow fund for the NSW Police Force to acquire technology intended to make police work safer and quicker. The announcement committed the NSW Police Force to several investment priorities, including body-worn video (BWV) cameras, smart phone devices (MobiPOL), mobile fingerprint scanners and hand-held drug testing devices. Otherwise, the NSW Police Force was allowed flexibility in identifying and resourcing suitable projects.

This audit assessed whether the Policing for Tomorrow fund was effectively managed to improve policing in New South Wales. We addressed the audit objective with the following audit questions:

  • Did the NSW Police Force efficiently and effectively identify, acquire, implement and maintain technology resourced by the fund?
  • Did the NSW Police Force establish effective governance arrangements for administering the fund, and for monitoring expected benefits and unintended consequences?
  • Did technology implemented under the fund improve the efficiency and effectiveness of policing in New South Wales?

Conclusion

The NSW Police Force's management of the Policing for Tomorrow fund was mostly effective. There are measures in place to assess the impact of the technologies on the efficiency and effectiveness of policing in NSW. However, these measures are not in place for all technologies funded by Policing for Tomorrow. A strategic whole-of-organisation approach to identifying and filling technology capability gaps may have assisted in better targeting funds and managing expected benefits.

The NSW Police Force identified, acquired, implemented and maintained a range of technologies resourced by the fund in an efficient and effective way. The election announcement committed the NSW Police Force to four specific projects which made up over three quarters of the fund value. Investment decisions for remaining funds were driven by the availability of funding and individual technology requirements rather than targeting improved policing outcomes and the capability necessary to achieve these.

The NSW Police Force missed an opportunity to take a whole-of-organisation approach to selecting technology projects for the remainder of the funds where it had discretion. This may have included considering less obvious back office technology or making different investment decisions driven by gaps in the agency's technology capabilities.

The NSW Police Force used effective governance arrangements for administering the Policing for Tomorrow fund, including using its existing ICT Executive Board. The NSW Police Force has adequate processes in place to drive benefits and monitor the impact of technology on the efficiency and effectiveness of policing for the larger projects funded by Policing for Tomorrow. Further work is required to ensure this for smaller projects.

The NSW Police Force tends to consider only impacts on the organisation in managing benefits and identifying unintended consequences. It does not routinely engage proactively with stakeholders, including partner criminal justice agencies and members of the community, on new technology that changes how police interact with the public.

We examined how effectively the NSW Police Force governed the Policing for Tomorrow fund, to ensure that key accountability and decision-making arrangements were in place to direct the $100 million spend to appropriate technologies. We also assessed how the NSW Police Force acquired, implemented and maintained technology funded by Policing for Tomorrow to determine the effectiveness of the relevant asset management.

The Policing for Tomorrow election commitment aimed to invest in technology to ‘make police work safer and quicker – meaning more time on the street combatting crime’. We assessed whether the NSW Police Force ensured that funded technologies have improved policing efficiency and effectiveness. We did not seek to independently assure the benefits or outcomes resulting from the technologies.

Appendix one – Response from agency

Appendix two – Policing for Tomorrow projects and expenditure

Appendix three – About the audit

Appendix four – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #334 - released 2 June 2020

Published

Actions for Industry 2018

Industry 2018

Industry
Asset valuation
Cyber security
Financial reporting
Information technology
Internal controls and governance
Service delivery

The Auditor-General for New South Wales, Margaret Crawford, released her report today on the Industry cluster. The report focuses on key observations and findings from the most recent financial audits of agencies in the cluster. Cluster agencies received unqualified audit opinions for 41 out of the 47 financial statements presented for audit for 30 June 2018. Six audits remain incomplete. 'While it is pleasing to note that unqualified audit opinions have been issued, the timeliness of financial reporting needs to be improved through better oversight, prompt resolution of issues, and an increased focus on early close procedures', the Auditor-General said.

This report analyses the results of our audits of financial statements of the Industry cluster for the year ended 30 June 2018. The table below summarises our key observations.

This report provides parliament and other users of the Industry cluster agencies' financial statements with the results of our audits, including our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations
  • service delivery.

The Department of Industry (the Department) is the lead agency in a cluster of 50 agencies. Other significant agencies in the cluster include Local Land Services, New South Wales Rural Assistance Authority, Technical and Further Education Commission (TAFE NSW), various sporting agencies, Forestry Corporation NSW and Water NSW.

The cluster:

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Industry cluster for 2018.
 

Observation Conclusions and recommendations
2.1 Quality of financial reporting
Unqualified audit opinions were issued for 41 out of 47 financial statement audits. Six audits are continuing.

The number of misstatements identified in financial statements submitted for audit increased from 73 in 2016–17 to 92 in 2017–18.
Conclusion: Agencies continue to address financial reporting issues and ensure significant matters that may impact the audit opinion are appropriately dealt with. The increase in the number of misstatements indicates a renewed focus on quality is required.
2.2 Timeliness of financial reporting
Nineteen out of 37 audit opinions were issued within the statutory deadline. Delays occurred due to the time required to resolve issues identified during the audit, or to obtain appropriate evidence to support balances or disclosures in the financial statements. There were also delays in receiving the signed certification from the agency, required before we can issue an audit opinion.

We reviewed the conduct of early close procedures at 17 agencies. Fifteen of these agencies were assessed as not fully addressing mandatory early close procedures.
Recommendation: Timeliness of financial reporting should be improved through better oversight of the preparation of financial statements, prompt resolution of issues, and an increased focus on early close procedures.
2.3 Key financial reporting issues
Information system limitations continue at TAFE NSW. TAFE NSW implemented additional processes to verify the accuracy and completeness of revenue from student fees. Conclusion: Procedures to address system limitations are costly, causing delays in financial reporting and increased resource commitments for staff, contractors and audit.
Misstatements and internal control issues continue to be identified in accounting for Crown land. The information system used to record Crown land was not designed to facilitate efficient financial reporting. These limitations and other control weaknesses impacted the completeness and accuracy of the Department's financial statements.
Recommendation: The Department should address system limitations and control weaknesses to ensure complete and accurate reporting for Crown land.
Unprocessed Aboriginal land claims continue to increase. Recommendation (repeat issue): The Department should reduce unprocessed Aboriginal land claims.
2.4 Financial information and sustainability
Cluster agencies recorded a combined surplus of $58.0 million compared to a combined deficit of $86.0 million in the previous year.

 

We identified five agencies with potential sustainability issues such as low liquidity or negative net assets. Conclusion: Adequate arrangements are in place to mitigate potential sustainability issues. These arrangements include a commitment from the Department to provide financial support if required. 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our observations and insights from:

  • our financial statement audits of agencies in the Industry cluster for 2018
  • the areas of focus identified in the Audit Office work program.

The Audit Office Annual Work Program provides a summary of all audits to be conducted within the proposed time period as well as detailed information on the areas of focus for each of the NSW Government clusters.

Observation Conclusions and recommendations
3.1 Internal control
Almost one in three internal control issues identified in 2017–18 were repeat issues. Recommendation (repeat issue): Recommendations to management to address internal control issues from prior years should be addressed promptly to reduce risks and improve processes.
3.2 Information technology controls
User access administration over financial systems remains an area of weakness. Two high risk and 18 moderate risk issues related to user access administration across nine agencies were identified. Recommendation (repeat issue): Agencies' controls over administration of user access to critical systems should:
  • retain documentation of approvals to create, modify and deactivate user access
  • allocate appropriate access rights
  • perform and document regular user access reviews
  • log and monitor privileged/super user account activity
  • deactivate terminated user access on a timely basis.
3.3 Annual work program
Errors continue to be identified in the Crown land database.

Instances were identified where Crown land was not recognised by the appropriate entity, or was recognised by more than one entity.
Recommendation: The Department should ensure the Crown land database is complete and accurate so state agencies and local government councils are better informed about the Crown land they control.
Approximately 700 managers of Crown land do not submit financial statements required by the Public Finance and Audit Act 1983. NSW Treasury and the Department are continuing work to clarify reporting arrangements for these entities.
3.4 Managing maintenance
Some cluster agencies do not monitor their backlog maintenance. Consequently, the total backlog maintenance in the Industry cluster is unknown. This impacts the reliability and consistency of information about assets and their condition. When backlog maintenance is unknown, it is difficult for agencies to develop an accurate and effective maintenance plan that focuses on areas of highest need. It also means agencies' maintenance plans are reactive rather than preventative.
Effective maintenance planning helps agencies to:
  • quantify and budget asset maintenance costs
  • support service delivery at the lowest possible long-term cost
  • reduce service disruptions and losses due to asset failure
  • identify and respond to risks posed by the age and condition of assets.
Recommendation: Cluster agencies should develop an asset maintenance plan and complete an assessment of the condition of their assets to identify any maintenance backlogs. 
Maintenance budgets in some cluster agencies are not set based on actual maintenance needs. Recommendation: Cluster agencies should set their maintenance budgets based on identified maintenance needs to more accurately budget and prioritise expenditure.

Agencies in the Industry cluster provide services across a wide variety of areas. This chapter outlines certain service delivery outcomes for 2017–18 for the Industry cluster. It provides important contextual information about the cluster's operation, but the data on activity levels and performance is provided by Cluster agencies. The Audit Office does not have a specific mandate to audit performance information. Accordingly, the information in this chapter is unaudited. 

In our recent performance audit, Progress and measurement of Premier's Priorities, we identified 12 limitations of performance measurement and performance data. We recommended that the Department of Premier and Cabinet ensure that processes to check and verify data are in place for all agency data sources.