Reports

Published

Actions for CBD and South East Light Rail Project

CBD and South East Light Rail Project

Transport
Compliance
Financial reporting
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk

Transport for NSW did not effectively plan and procure the CBD and South East Light Rail (CSELR) project to achieve best value for money according to a report released today by NSW Auditor-General, Margaret Crawford.

Transport for NSW is on track to deliver the project, but it will come at a higher cost with lower benefits than in the approved business case.

 

Parliamentary reference - Report number #278 - released 30 November 2016

Published

Actions for Implementation of the NSW Government’s program evaluation initiative

Implementation of the NSW Government’s program evaluation initiative

Industry
Justice
Planning
Premier and Cabinet
Treasury
Environment
Financial reporting
Internal controls and governance
Management and administration
Risk
Service delivery
Shared services and collaboration
Workforce and capability

The NSW Government’s ‘program evaluation initiative’, introduced to assess whether service delivery programs achieve expected outcomes and value for money, is largely ineffective according to a report released today by NSW Auditor-General, Margaret Crawford.

Government services, in areas such as public order and safety, health and education, are delivered by agencies through a variety of programs. In 2016–17, the NSW Government estimates that it will spend over $73 billion on programs to deliver services.

 

Parliamentary reference - Report number #277 - released 3 November 2016

Published

Actions for Red tape reduction

Red tape reduction

Premier and Cabinet
Finance
Financial reporting
Internal controls and governance
Management and administration
Project management
Regulation
Shared services and collaboration

Overall, NSW Government initiatives and processes to prevent and reduce red tape were not effective, according to a report released today by the NSW Auditor-General.

In 2015, the Government reported that its red tape reduction initiatives, implemented between 2011 and 2015, had resulted in $896 million in savings. While these initiatives resulted in some savings, the total value of savings is unknown because estimates for some initiatives were based on unverified assumptions, cost transfers or unrealised projections.

 

Parliamentary reference - Report number #272 - released 25 August 2016

Published

Actions for Public sector management reforms

Public sector management reforms

Finance
Industry
Premier and Cabinet
Planning
Whole of Government
Environment
Management and administration
Workforce and capability

The Public Service Commission is making good progress with leading the implementation of public sector management reforms, according to a report released today by the Acting New South Wales Auditor-General, Tony Whitfield.

'The Commission developed a sound evidence base for the reforms and gained wide public sector support by engaging with agency heads and using public sector working groups to develop options', said the Acting Auditor-General. 'They developed good guidance for government agencies and have improved the senior executive structure in the NSW public sector', he added.

 

Parliamentary reference - Report number #264 - released 28 January 2016

Published

Actions for WestConnex: Assurance to the Government

WestConnex: Assurance to the Government

Transport
Treasury
Premier and Cabinet
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk

This audit assesses the assurance provided to the NSW Government for the initial stages of the WestConnex project.

The audit examined the WestConnex project from concept development to the pre-tender phase for Stage 1A – M4 (Parramatta to Homebush Bay). It did not examine the merit of the project or whether it represented value-for-money.

This audit found a number of shortcomings with the governance of the WestConnex project during its early stages and makes recommendations on how to better govern the remainder of the project to minimise the risk of failure.

 

Parliamentary reference - Report number #247 - released 18 December 2014

Published

Actions for Managing Contaminated Sites

Managing Contaminated Sites

Planning
Industry
Environment
Compliance
Internal controls and governance
Management and administration
Project management
Regulation
Risk

NSW Government agencies with large landholdings need to better manage their contaminated sites.

When contaminated sites are reported to the Environmental Protection Authority (EPA) there are long delays in assessing the extent of contamination. The EPA also lacks the management controls to ensure that all significantly contaminated sites are actively monitored and key milestones for remediation are met.

 

Parliamentary reference - Report number #245 - released 10 July 2014

Published

Actions for Regional Road Funding - Block Grant and REPAIR Programs

Regional Road Funding - Block Grant and REPAIR Programs

Transport
Internal controls and governance
Management and administration
Project management
Risk

In 2013–14, Roads and Maritime Services (RMS) provided over $170 million to local councils through the Block Grant and REPAIR programs to spend on Regional Roads. Regional Roads are the link between State Roads and Local Roads.

 

Parliamentary reference - Report number #241 - released 8 May 2014

Published

Actions for Managing Overtime: RailCorp and Roads and Maritime Services

Managing Overtime: RailCorp and Roads and Maritime Services

Transport
Management and administration
Workforce and capability

Overtime is a significant cost for RailCorp and Roads and Maritime Services, adding about ten per cent to the cost of regular salaries. RailCorp’s overtime cost was $133.7 million in 2010–11, and at Roads and Maritime Services it cost $49.3 million.

 

Parliamentary reference - Report number #223 - released 20 June 2012

Published

Actions for Settling Humanitarian Entrants in New South Wales -  Services to permanent residents who come to New South Wales through the humanitarian migration scheme

Settling Humanitarian Entrants in New South Wales -  Services to permanent residents who come to New South Wales through the humanitarian migration scheme

Community Services
Premier and Cabinet
Internal controls and governance
Management and administration

Support for humanitarian entrants living in New South Wales is poorly coordinated.  Humanitarian entrants in New South Wales are doing less well than in other states on the key indicators of health, housing and employment. Unlike some States, New South Wales does not have a single point of contact that humanitarian entrants can go to assist them with settling in a new country.

 

Parliamentary reference - Report number #221 - released 23 May 2012

Published

Actions for Managing IT Services Contracts

Managing IT Services Contracts

Finance
Health
Justice
Compliance
Information technology
Internal controls and governance
Procurement
Project management
Risk

Neither agency (NSW Ministry of Health and NSW Police Force) demonstrated that they continued to get value for money over the life of these long term contracts or that they had effectively managed all critical elements of the three contracts we reviewed post award. This is because both agencies treated contract extensions or renewals as simply continuing previous contractual arrangements, rather than as establishing a new contract and financial commitment. Consequently, there was not a robust analysis of the continuing need for the mix and quantity of services being provided or an assessment of value for money in terms of the prices being paid.

 

Parliamentary reference - Report number #220 - released 1 February 2012