Refine search Expand filter

Reports

Published

Actions for Transport 2016

Transport 2016

Transport
Asset valuation
Compliance
Financial reporting
Fraud
Information technology
Internal controls and governance
Procurement
Project management

Financial reporting within the Transport Cluster continues to improve with reported misstatements down 96 per cent since 2011-12 to just three in 2015-16, according to a report released today by the NSW Auditor-General, Margaret Crawford.

Published

Actions for CBD and South East Light Rail Project

CBD and South East Light Rail Project

Transport
Compliance
Financial reporting
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk

Transport for NSW did not effectively plan and procure the CBD and South East Light Rail (CSELR) project to achieve best value for money according to a report released today by NSW Auditor-General, Margaret Crawford.

Transport for NSW is on track to deliver the project, but it will come at a higher cost with lower benefits than in the approved business case.

 

Parliamentary reference - Report number #278 - released 30 November 2016

Published

Actions for Family and Community Services 2016

Family and Community Services 2016

Community Services
Asset valuation
Compliance
Financial reporting
Fraud
Information technology
Internal controls and governance
Project management
Risk

The Family and Community Services report was released today by the Acting Deputy Auditor-General. Financial reporting within the cluster continues to improve but there are opportunities to improve governance and performance reporting.

Published

Actions for Fraud Survey

Fraud Survey

Education
Community Services
Finance
Health
Industry
Justice
Local Government
Planning
Premier and Cabinet
Transport
Treasury
Universities
Whole of Government
Environment
Fraud
Information technology
Internal controls and governance
Procurement
Risk

In a report released today, the NSW Auditor-General, Margaret Crawford provides a snapshot of reported fraud in the NSW public sector and an analysis of NSW Government agencies’ fraud controls based on a survey of 102 agencies.

Published

Actions for Franchising of Sydney Ferries Network services

Franchising of Sydney Ferries Network services

Transport
Procurement
Service delivery

Franchising services on the Sydney Ferries Network was justified, and Transport for NSW’s management of the franchise has been largely effective according to a report released today by the NSW Acting Auditor-General, Tony Whitfield.

'Franchising has resulted in cost savings, good service performance, and effective risk transfer from government to the private sector operator', said Mr Whitfield.

 

Parliamentary reference - Report number #265 - released 4 February 2016

Published

Actions for Handback of the M4 Tollway

Handback of the M4 Tollway

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management

This audit focuses on the M4 handback. It looks at whether the road will be in good condition when the State gets it back, and whether it will cope with the extra traffic after the toll is removed. These are critical issues for taxpayers and motorists. Taxpayers don’t want to be responsible for a large repair bill and motorists don’t want to be stuck in traffic jams.

To ensure that future private sector partnerships (PPP) deal adequately with handback, we recommend that the Roads and Traffic Authority (RTA):

  • ensure deeds spell out an appropriate inspection and testing program to determine repairs required to bring roads up to a satisfactory condition at handback (p.11)
  • ensure deeds link condition standards and maintenance approaches to changing industry standards and approaches over the life of the PPP (p.11)
  • consider including in deeds a requirement that operators provide a performance bond or similar security over the cost of handback repairs (p.11)
  • review the lessons learnt from the M4 tollway handback and determine whether it should seek to negotiate changes to existing tollway deeds to better deal with handback, by June 2010 (p.11)

 

Parliamentary reference - Report number #193 - released 27 October 2009

Published

Actions for Improving Road Safety: Heavy Vehicles

Improving Road Safety: Heavy Vehicles

Transport
Compliance
Internal controls and governance
Management and administration
Regulation
Risk

The RTA (Roads and Traffic Authority) approach to detecting and enforcing heavy vehicle safety has produced mixed results. There have been overall decreases in the number of crashes and people killed and injured in crashes involving heavy vehicles between 2002 and 2007. However, the number of crashes and the number of people injured have increased between 2006 and 2007.

We recognise that the RTA is unable to prevent all crashes. However, we consider that the RTA could do more to improve its ability to detect and respond to high risk heavy vehicles travelling on our roads.

 

Parliamentary reference - Report number #187 - released 13 May 2009

Published

Actions for Grants Administration

Grants Administration

Premier and Cabinet
Treasury
Health
Community Services
Planning
Compliance
Internal controls and governance
Management and administration
Procurement
Risk

We found no significant difference in the funding of government and opposition electorates. However, more money was given to electorates that were safely held by the major parties. These seats received $1.29 for every dollar given to marginal and independent seats with government marginals getting the least. Electorates also receive different levels of funding according to which region they are in. Such variations may reflect valid agency objectives such as meeting State Plan targets or addressing socio-economic disadvantage.

But while agencies publish who gets what, they do not adequately evaluate or explain what grant programs have achieved. As a result, there is a risk that New South Wales may not get the best value for its spending. We recommend that agencies regularly evaluate their grant programs and publish the results.

 

Parliamentary reference - Report number #186 - released 6 May 2009

Published

Actions for The Millennium Train Project

The Millennium Train Project

Transport
Infrastructure
Procurement
Project management
Service delivery

State Rail has made significant improvements since the purchase of the Tangara. It improved measures necessary for handling contracts dealing with technically complex and innovative projects, although some other problems have been encountered, with new lessons to learn. The design and manufacture of new trains requires a significant investment in both time and cost. The Millennium Train has come at a considerably higher price than originally expected. And it is very late compared to the Government’s original announcements, as the development/design took longer than planned.

 

Parliamentary reference - Report number #112 - released 17 June 2003

Published

Actions for Review of Eastern Distributor

Review of Eastern Distributor

Transport
Infrastructure
Procurement
Project management

Following a resolution of the Legislative Council, the Audit Office has undertaken a performance audit of the Eastern Distributor. For a number of reasons, The Audit Office is not in the position to determine “whether the proposed toll and concession period represents the best deal”. In part this is the result of time constraints which do not allow a careful analysis of many toll and concession options. Similarly, the audit does not answer “whether the current proposal represents the best environmental outcome”. But each of these issues (toll and concession and environmental consequences) is discussed in the audit report.

The Audit Office recommends that the Roads and Traffic Authority (RTA), for any further major project of this type, ensures that it establishes a process which allows all decision makers to have a thorough understanding of the reasonableness of the proponents’ offers and their implications for the State and for the public. The Audit Office also recommends that the RTA should at the outset consult with TCorp in respect of each major project put to tender.

 

Parliamentary reference - Report number #42 - released 31 July 1997