Reports
Actions for Newcastle Urban Transformation and Transport Program
Newcastle Urban Transformation and Transport Program
The urban renewal projects on former railway land in the Newcastle city centre are well targeted to support the objectives of the Newcastle Urban Transformation and Transport Program (the Program), according to a report released today by the Auditor-General for New South Wales, Margaret Crawford. The planned uses of the former railway land achieve a balance between the economic and social objectives of the Program at a reasonable cost to the government. However, the evidence that the cost of the light rail will be justified by its contribution to the Program is not convincing.
The Newcastle Urban Transformation and Transport Program (the Program) is an urban renewal and transport program in the Newcastle city centre. The Hunter and Central Coast Development Corporation (HCCDC) has led the Program since 2017. UrbanGrowth NSW led the Program from 2014 until 2017. Transport for NSW has been responsible for delivering the transport parts of the Program since the Program commenced. All references to HCCDC in this report relate to both HCCDC and its predecessor, the Hunter Development Corporation. All references to UrbanGrowth NSW in this report relate only to its Newcastle office from 2014 to 2017.
This audit had two objectives:
- To assess the economy of the approach chosen to achieve the objectives of the Program.
- To assess the effectiveness of the consultation and oversight of the Program.
We addressed the audit objectives by answering the following questions:
a) Was the decision to build light rail an economical option for achieving Program objectives?
b) Has the best value been obtained for the use of the former railway land?
c) Was good practice used in consultation on key Program decisions?
d) Did governance arrangements support delivery of the program?
1. The urban renewal projects on the former railway land are well targeted to support the objectives of the Program. However, there is insufficient evidence that the cost of the light rail will be justified by its contribution to Program objectives.
The planned uses of the former railway land achieve a balance between the economic and social objectives of the Program at a reasonable cost to the Government. HCCDC, and previously UrbanGrowth NSW, identified and considered options for land use that would best meet Program objectives. Required probity processes were followed for developments that involved financial transactions. Our audit did not assess the achievement of these objectives because none of the projects have been completed yet.
Analysis presented in the Program business case and other planning documents showed that the light rail would have small transport benefits and was expected to make a modest contribution to broader Program objectives. Analysis in the Program business case argued that despite this, the light rail was justified because it would attract investment and promote economic development around the route. The Program business case referred to several international examples to support this argument, but did not make a convincing case that these examples were comparable to the proposed light rail in Newcastle.
The audited agencies argue that the contribution of light rail cannot be assessed separately because it is a part of a broader Program. The cost of the light rail makes up around 53 per cent of the total Program funding. Given the cost of the light rail, agencies need to be able to demonstrate that this investment provides value for money by making a measurable contribution to the Program objectives.
2. Consultation and oversight were mostly effective during the implementation stages of the Program. There were weaknesses in both areas in the planning stages.
Consultations about the urban renewal activities from around 2015 onward followed good practice standards. These consultations were based on an internationally accepted framework and met their stated objectives. Community consultations on the decision to close the train line were held in 2006 and 2009. However, the final decision in 2012 was made without a specific community consultation. There was no community consultation on the decision to build a light rail.
The governance arrangements that were in place during the planning stages of the Program did not provide effective oversight. This meant there was not a single agreed set of Program objectives until 2016 and roles and responsibilities for the Program were not clear. Leadership and oversight improved during the implementation phase of the Program. Roles and responsibilities were clarified and a multi-agency steering committee was established to resolve issues that needed multi-agency coordination.
Recommendations
For future infrastructure programs, NSW Government agencies should support economical decision-making on infrastructure projects by:
- providing balanced advice to decision makers on the benefits and risks of large infrastructure investments at all stages of the decision-making process
- providing scope and cost estimates that are as accurate and complete as possible when initial funding decisions are being made
- making business cases available to the public.
The planned uses of the former railway land align with the objectives of encouraging people to visit and live in the city centre, creating attractive public spaces, and supporting growth in employment in the city. The transport benefits of the activities are less clear, because the light rail is the major transport project and this will not make significant improvements to transport in Newcastle.
The processes used for selling and leasing parts of the former railway land followed industry standards. Options for the former railway land were identified and assessed systematically. Competitive processes were used for most transactions and the required assessment and approval processes were followed. The sale of land to the University of Newcastle did not use a competitive process, but required processes for direct negotiations were followed.
Recommendation
By March 2019, the Hunter and Central Coast Development Corporation should:
- work with relevant stakeholders to explore options for increasing the focus on the heritage objective of the Program in projects on the former railway land. This could include projects that recognise the cultural and industrial heritage of Newcastle.
Consultations focusing on urban renewal options for the Program included a range of stakeholders and provided opportunities for input into decisions about the use of the former railway land. These consultations received mostly positive feedback from participants. Changes and additions were made to the objectives of the Program and specific projects in response to feedback received.
There had been several decades of debate about the potential closure of the train line, including community consultations in 2006 and 2009. However, the final decision to close the train line was made and announced in 2012 without a specific community consultation. HCCDC states that consultation with industry and business representatives constitutes community consultation because industry representatives are also members of the community. This does not meet good practice standards because it is not a representative sample of the community.
There was no community consultation on the decision to build a light rail. There were subsequent opportunities for members of the community to comment on the implementation options, but the decision to build it had already been made. A community and industry consultation was held on which route the light rail should use, but the results of this were not made public.
Recommendation
For future infrastructure programs, NSW Government agencies should consult with a wide range of stakeholders before major decisions are made and announced, and report publicly on the results and outcomes of consultations.
The governance arrangements that were in place during the planning stages of the Program did not provide effective oversight. Project leadership and oversight improved during the implementation phase of the Program.
Multi-agency coordination and oversight were ineffective during the planning stages of the Program. Examples include: multiple versions of Program objectives being in circulation; unclear reporting lines for project management groups; and poor role definition for the initial advisory board. Program ownership was clarified in mid-2016 with the appointment of a new Program Director with clear accountability for the delivery of the Program. This was supported by the creation of a multi-agency steering committee that was more effective than previous oversight bodies.
The limitations that existed in multi-agency coordination and oversight had some negative consequences in important aspects of project management for the Program. This included whole-of-government benefits management and the coordination of work to mitigate impacts of the Program on small businesses.
Recommendations
For future infrastructure programs, NSW Government agencies should:
- develop and implement a benefits management approach from the beginning of a program to ensure responsibility for defining benefits and measuring their achievement is clear
- establish whole-of-government oversight early in the program to guide major decisions. This should include:
- agreeing on objectives and ensuring all agencies understand these
- clearly defining roles and responsibilities for all agencies
- establishing whole-of-government coordination for the assessment and mitigation of the impact of major construction projects on businesses and the community.
By March 2019, the Hunter and Central Coast Development Corporation should update and implement the Program Benefits Realisation Plan. This should include:
- setting measurable targets for the desired benefits
- clearly allocating ownership for achieving the desired benefits
- monitoring progress toward achieving the desired benefits and reporting publicly on the results.
Appendix one - Response from agencies
Appendix two - About the audit
Appendix three - Performance auditing
Parliamentary reference - Report number #310 - released 12 December 2018
Actions for Managing Antisocial behaviour in public housing
Managing Antisocial behaviour in public housing
The Department of Family and Community Services (FACS) has not adequately supported or resourced its staff to manage antisocial behaviour in public housing according to a report released today by the Deputy Auditor-General for New South Wales, Ian Goodwin.
In recent decades, policy makers and legislators in Australian states and territories have developed and implemented initiatives to manage antisocial behaviour in public housing environments. All jurisdictions now have some form of legislation or policy to encourage public housing tenants to comply with rules and obligations of ‘good neighbourliness’. In November 2015, the NSW Parliament changed legislation to introduce a new approach to manage antisocial behaviour in public housing. This approach is commonly described as the ‘strikes’ approach.
When introduced in the NSW Parliament, the ‘strikes’ approach was described as a means to:
- improve the behaviour of a minority of tenants engaging in antisocial behaviour
- create better, safer communities for law abiding tenants, including those who are ageing and vulnerable.
FACS has a number of tasks as a landlord, including a responsibility to collect rent and organise housing maintenance. FACS also has a role to support tenants with complex needs and manage antisocial behaviour. These roles have some inherent tensions. The FACS antisocial behaviour management policy aims are:
to balance the responsibilities of tenants, the rights of their neighbours in social housing, private residents and the broader community with the need to support tenants to sustain their public housing tenancies.
This audit assessed the efficiency and effectiveness of the ‘strikes’ approach to managing antisocial behaviour in public housing environments.
We examined whether:
- the approach is being implemented as intended and leading to improved safety and security in social housing environments
- FACS and its partner agencies have the capability and capacity to implement the approach
- there are effective mechanisms to monitor, report and progressively improve the approach.
Conclusion
FACS has not adequately supported or resourced its staff to implement the antisocial behaviour policy. FACS antisocial behaviour data is incomplete and unreliable. Accordingly, there is insufficient data to determine the nature and extent of the problem and whether the implementation of the policy is leading to improved safety and security. FACS management of minor and moderate incidents of antisocial behaviour is poor. FACS has not dedicated sufficient training to equip frontline housing staff with the relevant skills to apply the antisocial behaviour management policy. At more than half of the housing offices we visited, staff had not been trained to:
When frontline housing staff are informed about serious and severe illegal antisocial behaviour incidents, they generally refer them to the FACS Legal Division. Staff in the Legal Division are trained and proficient in managing antisocial behaviour in compliance with the policy and therefore, the more serious incidents are managed effectively using HOMES ASB.
|
Parliamentary reference - Report number #306 - released 10 August 2018
Actions for Sydney Road Maintenance Contracts
Sydney Road Maintenance Contracts
In November 2013, Roads and Maritime Services (RMS) outsourced the maintenance of State roads in the Sydney region south and west zones using an innovative contracting approach called the Stewardship Maintenance Contract (SMC). The SMC links risk to reward, and uses a performance framework where outcomes should drive improved performance over time.
WA | VIC | QLD | NSW | |
---|---|---|---|---|
Roads managed (lane kms) | 52,659 | 50,510 | 71,353 | 80,348 |
Estimated spend ($/lane km) | 5,000 | 4,500 | 6,000 | 7,000 |
Road quality measure (%) | 99 | 99 | 94 | 91 |
Parliamentary reference - Report number #288 - released 15 June 2017
Actions for NorthConnex
NorthConnex
The processes used to assess NorthConnex adequately considered value for money for taxpayers.This report also found that the impact of tolling concessions on road users and the motorway network was consistent with policy objectives described in the 2012 NSW Long Term Transport Master Plan.
Parliamentary reference - Report number #287 - released 8 June 2017
Actions for Building the readiness of the non-government sector for the NDIS
Building the readiness of the non-government sector for the NDIS
The Department of Family and Community Services has managed the risks of the transition to the National Disability Insurance Scheme (NDIS) in New South Wales effectively by increasing the overall capacity of the non-government sector and investing in provider capability.
The National Disability Insurance Scheme (NDIS) is a major reform that aims to change the way disability support is provided and received. Responsibility for overseeing the system to support people with disability in New South Wales will transfer from the NSW Government to the National Disability Insurance Agency (NDIA), an independent statutory agency of the Australian Government. Eligible people with disability will receive individual funding from the NDIA and purchase support from their chosen service providers, rather than being referred to services funded or provided by government. The NSW Government will transfer all disability services it currently provides to the non-government sector.
Approximately 78,000 people received NSW Government-funded disability support in 2015–16 at a cost of around $3.3 billion. An estimated 142,000 people will have an individual NDIS support plan in New South Wales, with total funding rising to around $6.8 billion in 2018–19. NDIS trials began in New South Wales in 2013. The full scheme was introduced in July 2016 and is scheduled to be operating across the state by July 2018.
This audit assessed the effectiveness of the NSW Department of Family and Community Services' (the Department's) management of the risks of the NDIS transition in New South Wales. It focused on the Department's work to build the readiness of the non-government sector for the NDIS. To make this assessment, we asked whether:
- the Department supported the non-government sector to build capacity to meet the expected increase in demand under the NDIS
- the Department supported disability service providers in NSW to improve their capability to deliver NDIS services
- the Department's work to prepare for the NDIS has been coordinated with the Australian Government's NDIS readiness work.
In addition to the audit questions above, this audit identified principles governments should consider when building the capacity and capability of the non-government sector to deliver human services.
Conclusion
The Department of Family and Community Services has managed the risks of the transition to the NDIS in New South Wales effectively by increasing the overall capacity of the sector and investing in provider capability building initiatives. More work is needed to build the sector's capacity to provide services to people with more complex support needs and to help existing providers complete the transition to the NDIS successfully.
The Department expanded the capacity of the non-government sector over the past decade in a way that was consistent with NDIS objectives. The development of a national market and workforce for the NDIS is an Australian Government responsibility and the Department has supported the Australian Government's work. More targeted work will be needed to build the capacity of the non-government sector to provide services to people with the most complex support and access needs.
The Department invested in provider capability building by funding programs that were delivered in partnership with sector peak bodies. The larger programs were evaluated and received positive feedback, but many providers will need more support to transition to the NDIS. The overall impact of the programs on provider readiness for the NDIS is not clear because baseline information on provider capability was not collected and targets for improvement were not set.
The Department managed the transition coordination risks by establishing comprehensive governance arrangements, contributing to the Australian Government's sector development work through national policy coordination forums and sharing lessons from New South Wales.
Building the capacity of the non-government sector
The Department supported an increase in the capacity of non-government providers
The Department started building the capacity of the non-government sector before the NDIS was developed. This included moving services provided by government into the non‑government sector, funding early intervention and community-based disability support, and introducing some individual support packages. The Department checks that the business and operational systems of non-government disability providers are adequate. However, its understanding of the outcomes for people using the services is limited.
Service gaps are possible for people with more complex support or access needs
There are risks to the supply of services to people who have more complex support or access needs, including people who need specialist clinical support, people in remote areas, Aboriginal and Torres Strait Islander communities and culturally and linguistically diverse communities. The Department has supported the NDIA's initial market development work and funded some programs to help providers build their capacity to support these groups. However, there is a risk the market will not expand quickly enough to meet the increase in demand for services.
Sector sustainability depends on support from outside the disability services sector
The sustainability of funded disability services provided by the non-government sector depends on support from outside the sector. Most people with disability receive significant unpaid support from family members, so carers will play a key role in the sustainability of the NDIS. There are opportunities for organisations that do not provide specific disability services to contribute to sector sustainability by providing some NDIS services. To do this, many will need help to make their services more accessible and inclusive to people with disability.
Helping non-government providers develop their capability
The Department invested in capability building programs for providers
The Department has spent more than $30 million over six years on programs that aim to improve the capability of disability support providers. This work began before the NDIS was established and was adjusted to focus on NDIS readiness from December 2012. It was guided by an industry development strategy that was developed after consultation with the sector and delivered in partnership with sector peak bodies. This approach gave the sector some responsibility for developing its own capability, which is important because the sector will not receive support from the NSW Government after the transition to the NDIS.
The overall impact of the programs on the capability of providers is not clear
The overall effectiveness of the Department's spending on provider capability is not clear. The Department had some information on the general financial health and organisational capability of providers from previous industry development work. However, baseline information on provider capability was not collected before programs commenced and targets for improvements in provider capability were not set. Without this information, the Department cannot demonstrate clearly that the capability building programs it funded represent good value for money.
Most providers will need more support to transition to the NDIS effectively
In late 2015, the Department assessed the transition progress of providers in New South Wales. This assessment indicates almost one third of providers are highly likely to need additional assistance to transition to the NDIS successfully, with only 14 per cent unlikely to need further assistance. We conducted a survey of 299 providers in New South Wales in August 2016. Most reported that they feel they are on track to transition to the NDIS successfully. Sixty-two per cent said the Department-funded programs and resources they had used had improved their readiness for the NDIS. Fifty-four per cent said the changes made because of using these programs and resources had a lasting impact on their organisation.
Coordinating sector development
Governance systems and planning processes for the NDIS transition were established
The Department developed governance arrangements for the transition in New South Wales. It contributed actively to the development of national policy and strategy documents including a strategy for national market development.
The Department shared sector readiness lessons with the Australian Government
Two NDIS sector readiness programs funded by the NSW Government were later expanded to national programs through funding from the Australian Government. New South Wales only received around five per cent of the total Australian Government funding for NDIS sector readiness initiatives. A report by the Australian National Audit Office in 2016 found there was limited evidence of a strategic approach by the Australian Government when allocating this funding to states and territories.
The Department has monitored transition issues and mitigated these where possible
The Department has monitored administrative issues for providers, which have included the changes in funding arrangements and registering for the NDIS. It has taken action to mitigate these where possible, although some issues, such as the operation of NDIA administrative systems, are beyond its control.
The National Disability Insurance Scheme (NDIS)
The NDIS is a fundamental change to the disability support system
The NDIS is a major reform that aims to make significant changes to the way disability support is provided and received. Under the NDIS, the administration of funding for disability support in New South Wales will transfer from the NSW Government to the National Disability Insurance Agency (NDIA), an independent statutory agency of the Australian Government. The NSW and Australian Governments will both contribute to funding the NDIS. The size of the disability services sector in New South Wales is expected to more than double when the NDIS is fully operational (Exhibit 1).
Measure of sector capacity | Pre-NDIS (2015-16) | NDIS (2018-19) |
---|---|---|
Funding for services | $3.3 billion | $6.8 billion |
People receiving support | 78,000 | 142,000 |
Workforce required | 25,000-30,000 | 48,000-59,000 |
Number of providers | 699 | Determined by the market |
One of the main objectives of the NDIS is to increase the choice and control that people with disability have over the support they receive. Under the NDIS, people with disability receive individual funding packages which they can use to pay their chosen providers for the support they need, instead of being referred to services that are deemed appropriate for their needs. This is a fundamental change to the nature of disability support. Before the NDIS, people with disability were moved around the system according to decisions made by government or other organisations providing disability support. Under the NDIS, the funding will move around the system based on the choices people with disability make. The development of the new market for NDIS disability services is expected to take up to ten years because the changes to the system are so extensive.
In addition to increasing choice and control for participants, the NDIS aims to:
- improve outcomes for people with disability by intervening early to help reduce the need for support later in life
- increase integration by helping people with disability access mainstream government services such as health and education
- increase the involvement of people with disability in the community by making it easier to access community services such as sports clubs and community groups.
The transition to the NDIS is underway
The transition to the NDIS is underway in most Australian states and territories, following trials over the last three years. In New South Wales, a trial site was established in the Hunter area in July 2013. Early roll out of the NDIS began in July 2015 for people aged under 18 in the Nepean Blue Mountains area. On 30 June 2016, about 7,800 people had an NDIS plan in the Hunter trial site and around 1,800 people had a plan in the Nepean Blue Mountains area.
The full roll out of the NDIS began in about half of New South Wales in July 2016. The NDIS will start operating in the rest of the state from July 2017 and the transition is scheduled to be completed by July 2018 (Exhibit 2).
For the rest of the transition, the Department of Family and Community Services should:
- Work with the Australian Government, NDIA and other NSW Government agencies to identify gaps and develop the capacity of specialist clinical services, focusing on regional and rural areas.
- Continue to implement projects to increase the number of organisations that can support Aboriginal and Torres Strait Islander and culturally and linguistically diverse communities.
- Target remaining capability building assistance to less prepared providers, including via one-to-one support and mentoring in identified areas of weakness.
- Continue working with the Australian Government and the NDIA to ensure lessons from sector capability programs are shared.
Principles for developing the non-government sector
- Commence work to increase the capacity of the non-government sector early to allow time for service capacity to be built in a sustainable way.
- Decide whether to increase the capacity of the sector by supporting existing providers to expand their operations, attracting new organisations from outside the existing provider group, or some combination of these.
- Tailor approaches to supporting groups that have additional support or access needs because of cultural or geographic factors.
- Define the desired outcomes for people using services and, where possible, include outcomes in service delivery contracts.
- Invest in the sector by partnering with sector peak bodies to deliver capability programs.
- Include one-to-one support and mentoring in capability building programs where possible to improve the targeting of support to the specific needs of providers.
- Collect baseline information on provider capability before commencing programs and build robust tracking and evaluation into their design.
- Establish whole-of-government governance arrangements to ensure roles, responsibilities and accountability for delivery are clear.
Parliamentary reference - Report number #280 - released 23 February 2017
Actions for Managing Disruptions to Cityrail Passenger Services
Managing Disruptions to Cityrail Passenger Services
About one in every twelve Sydney people travels by train each weekday.
Unplanned disruptions to services are inevitable, even on the best-run railways.
Because of the complexities of Sydney’s rail network, a single event can disrupt many services.
From a passenger’s perspective, three issues are important –
- how quickly the disruption is fixed (“When will my train arrive?”)
- the accuracy of information provided about the disruption (“Should I change my travel/meeting/other arrangements?”)
- how often the disruptions occur (“Should I give up on rail travel?”).
In this audit, we looked at how well RailCorp responds when there are routine disruptions to its CityRail passenger services. We focused on how RailCorp manages passenger journeys and informs passengers.
This report informs Parliament and the community about the limitations of the current system, and what more needs to be done in order to minimise the impact of disruptions on passengers.
It should also help passengers judge the extent to which they can rely on the information they receive, and to better understand some of the obstacles faced by staff.
Parliamentary reference - Report number #139 - released 22 June 2005
Actions for Follow-up of Performance Audit: Bus Maintenance and Bus Contracts
Follow-up of Performance Audit: Bus Maintenance and Bus Contracts
Periodically we review the extent to which agencies have implemented the recommendations they accepted from our earlier audits.
This gives Parliament and the public an update on the extent of progress made.
In this follow-up audit, we examine changes following our May 2002 report on how well the:
- State Transit Authority maintained its buses
- Ministry of Transport administered contracts for the provision of regular passenger bus services.
Parliamentary reference - Report number #138 - released 14 June 2005