Actions for Volume Five 2012 focusing on superannuation, compensation and housing

Volume Five 2012 focusing on superannuation, compensation and housing

Finance
Treasury
Premier and Cabinet
Community Services
Asset valuation
Compliance
Financial reporting
Information technology
Internal controls and governance
Procurement
Regulation

The NSW Government’s defined benefit superannuation funds have had positive returns for the last three years. However, the returns fell significantly in 2011-12. Global economic conditions led to substantial volatility and uncertainty in markets creating challenges for superannuation funds’ trustees.

Published

Actions for Volume Three 2012 focusing on New South Wales State Finances

Volume Three 2012 focusing on New South Wales State Finances

Whole of Government
Asset valuation
Compliance
Financial reporting
Internal controls and governance
Management and administration
Project management

A qualified audit opinion was issued on the Total State Sector Accounts for the year ended 30 June 2012. Qualified opinions have been issued every year for the past decade. The key issue contributing to past qualifications has been partially resolved, but new issues have arisen that impact the ability to confirm property, plant and equipment balances in 2011-12.

Published

Actions for Volume Five 2011 focus on Superannuation, Compensation and Housing

Volume Five 2011 focus on Superannuation, Compensation and Housing

Finance
Treasury
Asset valuation
Compliance
Financial reporting
Internal controls and governance
Management and administration
Procurement
Project management
Regulation
Shared services and collaboration

The audits of the New South Wales Government controlled superannuation entities financial statements for the year ended 30 June 2011 resulted in unmodified audit opinions within the Independent Auditor’s Reports. Findings show that Treasury should review the structure and number of public sector superannuation funds and consider whether efficiencies and cost savings could be achieved through consolidation.

Published

Actions for Volume Three 2011

Volume Three 2011

Whole of Government
Asset valuation
Compliance
Financial reporting
Internal controls and governance
Management and administration
Project management

On 31 October 2011, the Auditor-General, Mr Peter Achterstraat, released Volume Three Report to Parliament on the 2010-11 NSW Total State Sector Accounts. The audited budget surplus was $1,340 million. The Auditor-General issued a qualified independent auditor’s opinion as the State could not identify the full extent and value of its land and infrastructure holdings for the eighth year in a row. The government needs to address its processes for identifying, valuing and recording land and related assets it controls as a matter of priority so it can effectively manage the full extent of its land and infrastructure holdings.

Published

Actions for Volume Two 2011 focusing on Universities

Volume Two 2011 focusing on Universities

Universities
Compliance
Financial reporting
Fraud
Internal controls and governance
Management and administration
Workforce and capability

New South Wales’ ten universities recorded a combined operating surplus of $582  million in 2010, similar to last year’s surplus of $494 million.Capital works expenditure increased by 16 per cent from $874 million in 2009 to $1,015 million in 2010. Despite this, financial and reputational issues continue for universities.

Published

Actions for Government expenditure and transport planning in relation to implementing Barangaroo

Government expenditure and transport planning in relation to implementing Barangaroo

Industry
Treasury
Transport
Compliance
Internal controls and governance
Management and administration
Project management
Service delivery

Barangaroo is an ambitious and significant development on Government-owned Sydney Harbour foreshore. Construction on the 22 hectare CBD site is expected to take 12 years to 2023. Developer contributions to Government of $1 billion are to provide for public domain and other Government development costs, including a six hectare Headland Park. When completed the precinct is to service an anticipated 26,000 workers and residents and up to 33,000 visitors a day. The Auditor-General concluded that while there was extensive transport planning and extensive documentation supporting Government financial forecasts, considerable risks remain for the implementation of the Barangaroo project. 

 

Parliamentary reference - Report number #214 - released 15 June 2011