Reports
Actions for WestConnex: Assurance to the Government
WestConnex: Assurance to the Government
This audit assesses the assurance provided to the NSW Government for the initial stages of the WestConnex project.
The audit examined the WestConnex project from concept development to the pre-tender phase for Stage 1A – M4 (Parramatta to Homebush Bay). It did not examine the merit of the project or whether it represented value-for-money.
This audit found a number of shortcomings with the governance of the WestConnex project during its early stages and makes recommendations on how to better govern the remainder of the project to minimise the risk of failure.
Parliamentary reference - Report number #247 - released 18 December 2014
Actions for Regional Road Funding - Block Grant and REPAIR Programs
Regional Road Funding - Block Grant and REPAIR Programs
In 2013–14, Roads and Maritime Services (RMS) provided over $170 million to local councils through the Block Grant and REPAIR programs to spend on Regional Roads. Regional Roads are the link between State Roads and Local Roads.
Parliamentary reference - Report number #241 - released 8 May 2014
Actions for Connecting with public transport
Connecting with public transport
We see considerable potential for the Ministry of Transport to plan and manage interchanges more effectively, so as to make better use of our public transport network. We believe that the Ministry now needs to focus more on multi-modal transport planning and interchange performance. It needs to assign responsibility for the coordination and oversight of inter-modal operations to an entity resourced for the purpose. Without this it will continue to be very difficult to identify and address unmet needs, seek and secure stakeholder funding, and monitor and evaluate system performance.
Parliamentary reference - Report number #168 - released 6 June 2007
Actions for Freedom of Information
Freedom of Information
Freedom of Information (FOI) Coordinators and their staff were supportive of the legislation. However, the agencies examined can do considerably more to fully achieve the intentions of the Act. On the positive side, all three agencies had processes in place to handle requests and had made a number of changes to improve the effectiveness of the FOI process. Fees and charges had also been kept to a minimum. No processing fees were requested in the majority of cases, and if charged, were not unreasonable.
Parliamentary reference - Report number #114 - released 28 August 2003