Actions for Government expenditure and transport planning in relation to implementing Barangaroo

Government expenditure and transport planning in relation to implementing Barangaroo

Industry
Treasury
Transport
Compliance
Internal controls and governance
Management and administration
Project management
Service delivery

Barangaroo is an ambitious and significant development on Government-owned Sydney Harbour foreshore. Construction on the 22 hectare CBD site is expected to take 12 years to 2023. Developer contributions to Government of $1 billion are to provide for public domain and other Government development costs, including a six hectare Headland Park. When completed the precinct is to service an anticipated 26,000 workers and residents and up to 33,000 visitors a d

Published

Actions for Volume Nine 2010 focus on Transport, Planning and Industry

Volume Nine 2010 focus on Transport, Planning and Industry

Transport
Planning
Industry
Asset valuation
Compliance
Internal controls and governance
Management and administration
Procurement
Project management
Regulation
Risk
Workforce and capability

The report includes comments on his financial audits of NSW Government transport, planning and industry agencies for 2009-10. A key recommendation from the report is that the New South Wales Government identify lessons learnt from the metro experience and ensure that future decision processes are developed to ensure the State never again expends such a large amount of scarce transport funding dollars and valuable time on a project that does not proceed.

Published

Actions for Volume Five 2010 focus on Public Financing Enterprises

Volume Five 2010 focus on Public Financing Enterprises

Industry
Transport
Finance
Treasury
Planning
Financial reporting
Information technology
Internal controls and governance
Management and administration
Regulation
Risk
Workforce and capability

The report includes comments on NSW Treasury and agencies in the finance and superannuation sectors. The New South Wales public sector superannuation funds’ investments were $42.2 billion at 30 June 2010, up from $38.5 billion in 2009. Investment returns reached 14.5 per cent in 2009-10. This is a significant improvement on the investment returns of up to negative 18.4 per cent at the peak of the global financial crisis in 2008.  

Published

Actions for Improving the Performance of Metropolitan Bus Services

Improving the Performance of Metropolitan Bus Services

Transport
Internal controls and governance
Management and administration
Procurement
Service delivery

The 2004 Review of Bus Services in NSW always envisaged that there would be a transition period as the new bus contracts were introduced. NSWTI has developed and implemented the new arrangements, and pursued a range of new initiatives including the network improvement program, strategic corridors and uniform bus fares and concessions. The new contracts provided for a performance management regime to hold operators accountable. But this is still being dev

Published

Actions for Handback of the M4 Tollway

Handback of the M4 Tollway

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management

This audit focuses on the M4 handback. It looks at whether the road will be in good condition when the State gets it back, and whether it will cope with the extra traffic after the toll is removed. These are critical issues for taxpayers and motorists. Taxpayers don’t want to be responsible for a large repair bill and motorists don’t want to be stuck in traffic jams. To ensure that future private sector partnerships (PPP) deal adequately with handb

Published

Actions for Improving Road Safety: Heavy Vehicles

Improving Road Safety: Heavy Vehicles

Transport
Compliance
Internal controls and governance
Management and administration
Regulation
Risk

The RTA (Roads and Traffic Authority) approach to detecting and enforcing heavy vehicle safety has produced mixed results. There have been overall decreases in the number of crashes and people killed and injured in crashes involving heavy vehicles between 2002 and 2007. However, the number of crashes and the number of people injured have increased between 2006 and 2007. We recognise that the RTA is unable to prevent all crashes. However, we conside

Published

Actions for Signal failures on the metropolitan rail network

Signal failures on the metropolitan rail network

Transport
Information technology
Infrastructure
Internal controls and governance
Project management
Risk
Service delivery

Between 2004 and 2006, the number of signalling failures, signalling downtime and the number of trains delayed as a result of signal failures all fell. RailCorp’s on-time running performance improved over the same period. The fall in failures is a clear indication of improved performance. Changes in the definition of on-time and to the timetable during 2005 and 2006 however make it difficult to determine whether improvements in response downtime and sign

Published

Actions for Connecting with public transport

Connecting with public transport

Transport
Information technology
Infrastructure
Internal controls and governance
Management and administration
Project management
Service delivery
Workforce and capability

We see considerable potential for the Ministry of Transport to plan and manage interchanges more effectively, so as to make better use of our public transport network. We believe that the Ministry now needs to focus more on multi-modal transport planning and interchange performance. It needs to assign responsibility for the coordination and oversight of inter-modal operations to an entity resourced for the purpose. Without this it will continue to b

Published

Actions for Condition of State Roads

Condition of State Roads

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Service delivery

The Roads and Traffic Authority (RTA) has improved the overall surface condition of State Roads in the last decade. Country road surfaces are now generally much better. Ride quality has improved and cracking has been reduced. The RTA has also achieved a substantial reduction in the number of structurally deficient bridges over the same period.  Despite a significant increase in the State’s contribution to maintenance since 1999-2000, the RTA h

Published

Actions for The Cross City Tunnel Project

The Cross City Tunnel Project

Transport
Treasury
Premier and Cabinet
Planning
Environment
Infrastructure
Management and administration
Procurement
Project management
Risk

In our opinion the Government’s ‘no net cost to government’ requirement was a legitimate (but not the only possible) basis for the tunnel bid process. The Government was entitled to decide that tunnel users meet the tunnel costs. Structuring the bid process on the basis of an upfront reimbursement of costs incurred (or to be incurred) by the Roads and Traffic Authority (RTA) was therefore appropriate. In our opinion, however, the Government, Treasu