Reports
Actions for 2016 - An overview
2016 - An overview
This report focuses on key observations and findings from 2016 audits and highlights key areas of focus for financial and performance audits in 2017. The quality and timeliness of financial reporting continued to improve across the NSW public sector in 2016. Only one qualified audit opinion was issued and most agencies signed their financial statements on time. We found the Government’s cluster governance arrangements were unclear and inconsisten
Actions for Transport 2016
Transport 2016
Financial reporting within the Transport Cluster continues to improve with reported misstatements down 96 per cent since 2011-12 to just three in 2015-16, according to a report released today by the NSW Auditor-General, Margaret Crawford.
Actions for CBD and South East Light Rail Project
CBD and South East Light Rail Project
Transport for NSW did not effectively plan and procure the CBD and South East Light Rail (CSELR) project to achieve best value for money according to a report released today by NSW Auditor-General, Margaret Crawford. Transport for NSW is on track to deliver the project, but it will come at a higher cost with lower benefits than in the approved business case. Parliamentary reference - Report number #278 - released 30 November 2016
Actions for Fraud Survey
Fraud Survey
In a report released today, the NSW Auditor-General, Margaret Crawford provides a snapshot of reported fraud in the NSW public sector and an analysis of NSW Government agencies’ fraud controls based on a survey of 102 agencies.
Actions for Volume Six 2015 Transport
Volume Six 2015 Transport
Public transport revenue decreased by 2.7 per cent despite a fare increase and increased patronage. Twenty-five per cent of all Opal trips (over 74 million) were free, including 47 per cent of trips on ferries, according to a report released today by the New South Wales Acting Auditor-General, Tony Whitfield. These trips were valued at $189 million.
Actions for Albert 'Tibby' Cotter Walkway
Albert 'Tibby' Cotter Walkway
On 17 September 2015, the Acting Auditor-General of New South Wales, Tony Whitfield, released a report on the Albert ‘Tibby’ Cotter Walkway which crosses over Anzac Parade in Moore Park. The Walkway’s primary function is to cater for event patrons in the precinct. Moore Park is listed on the State Heritage Register and is an open space specifically established to cater for public recreation. Roads and Maritime Services (RMS) delivered the Walkway
Actions for Sydney metropolitan bus contracts
Sydney metropolitan bus contracts
On 9 September 2015, the Acting Auditor-General of New South Wales, Tony Whitfield, released a report on Sydney Metropolitan Bus Service Contracts. All scheduled bus services in the Sydney metropolitan area are provided under contracts with the public and private operators. The contracts allow Transport for NSW (TfNSW) to determine what bus services are provided and to whom. This audit assessed the effectiveness of TfNSW’s design and management of
Actions for Identifying productivity in the public sector
Identifying productivity in the public sector
This report examines selected areas of government activity to see if sufficient information was available to identify and assess changes in productivity. The areas examined were primary and secondary school public education, acute inpatient care in NSW public hospitals, CityRail, the NSW Police Force, and the NSW Local Court. Productivity is commonly defined as the amount of output per unit of input. Parliamentary reference - Report number #256
Actions for Implementing performance audit recommendations
Implementing performance audit recommendations
NSW Government agencies have sound processes for implementing performance audit recommendations in Auditor-General’s Reports to Parliament. There are many cases of good practice. For example, some agencies formed a steering committee and developed a detailed plan to implement recommendations. Another incorporated the implementation of recommendations into both its business plan and the work plans of individual officers who were managing projects. Most ag
Actions for Large construction projects
Large construction projects
The independent assurance given to the NSW Government and sponsor agencies on the viability of large capital projects throughout their lifecycle is inadequate. Government policy is regularly not followed and not properly communicated to those responsible for implementing such policy. This audit sought to test the effectiveness of the NSW capital project assurance system - which includes gateway reviews and reporting - but significant levels of non