Actions for CBD South East Sydney Light Rail: follow-up performance audit

CBD South East Sydney Light Rail: follow-up performance audit

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk
Service delivery

This is a follow-up to the Auditor-General's November 2016 report on the CBD South East Sydney Light Rail project. This follow-up report assessed whether Transport for NSW has updated and consolidated information about project costs and benefits.

The audit found that Transport for NSW has not consistently and accurately updated project costs, limiting the transparency of reporting to the public.

The Auditor-General reports that the total cost of the project will exceed $3.1 billion, which is above the revised cost of $2.9 billion published in November 2019. $153.84 million of additional costs are due to omitted costs for early enabling works, the small business assistance package and financing costs attributable to project delays.

The report makes four recommendations to Transport for NSW to publicly report on the final project cost, the updated expected project benefits, the benefits achieved in the first year of operations and the average weekly journey times.

Read full report (PDF)

The CBD and South East Light Rail is a 12 km light rail network for Sydney. It extends from Circular Quay along George Street to Central Station, through Surry Hills to Moore Park, then to Kensington and Kingsford via Anzac Parade and Randwick via Alison Road and High Street.

Transport for NSW (TfNSW) is responsible for planning, procuring and delivering the Central Business District and South East Light Rail (CSELR) project. In December 2014, TfNSW entered into a public private partnership with ALTRAC Light Rail as the operating company (OpCo) responsible for delivering, operating and maintaining the CSELR. OpCo engaged Alstom and Acciona, who together form its Design and Construct Contractor (D&C).

On 14 December 2019, passenger services started on the line between Circular Quay and Randwick. Passenger services on the line between Circular Quay and Kingsford commenced on 3 April 2020.

In November 2016, the Auditor-General published a performance audit report on the CSELR project. The audit found that TfNSW would deliver the CSELR at a higher cost with lower benefits than in the approved business case, and recommended that TfNSW update and consolidate information about project costs and benefits and ensure the information is readily accessible to the public.

In November 2018, the Public Accounts Committee (PAC) examined TfNSW's actions taken in response to our 2016 performance audit report on the CSELR project. The PAC recommended that the Auditor-General consider undertaking a follow-up audit on the CSELR project. The purpose of this follow-up performance audit is to assess whether TfNSW has effectively updated and consolidated information about project costs and benefits for the CSELR project.

Conclusion

Transport for NSW has not consistently and accurately updated CSLER project costs, limiting the transparency of reporting to the public. In line with the NSW Government Benefits Realisation Management Framework, TfNSW intends to measure benefits after the project is completed and has not updated the expected project benefits since April 2015.

Between February 2015 and December 2019, Transport for NSW (TfNSW) regularly updated capital expenditure costs for the CSELR in internal monthly financial performance and risk reports. These reports did not include all the costs incurred by TfNSW to manage and commission the CSELR project.

Omitted costs of $153.84 million for early enabling works, the small business assistance package and financing costs attributable to project delays will bring the current estimated total cost of the CSELR project to $3.147 billion.

From February 2015, TfNSW did not regularly provide the financial performance and risk reports to key CSELR project governance bodies. TfNSW publishes information on project costs and benefits on the Sydney Light Rail website. However, the information on project costs has not always been accurate or current.

TfNSW is working with OpCo partners to deliver the expected journey time benefits. A key benefit defined in the business plan was that bus services would be reduced owing to transfer of demand to the light rail - entailing a saving. However, TfNSW reports that the full expected benefit of changes to bus services will not be realised due to bus patronage increasing above forecasted levels.

Appendix one – Response from agency

Appendix two – Governance and reporting arrangements for the CSELR

Appendix three – 2018 CSELR governance changes

Appendix four – About the audit

Appendix five – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #335 - released 11 June 2020

Published

Actions for Train station crowding

Train station crowding

Transport
Management and administration
Risk
Service delivery
Workforce and capability

This report focuses on how Transport for NSW and Sydney Trains manage crowding at selected metropolitan train stations.

The audit found that while Sydney Trains has identified platform crowding as a key strategic risk, it does not have an overarching strategy to manage crowding in the short to medium term. Sydney Trains 'do not have sufficient oversight to know if crowding is being effectively managed’, the Auditor-General said.

Sydney Trains' operational response to crowding involves restricting customer access to platforms or station entries before crowding reaches unsafe levels or when it impacts on-time running. Assuming rail patronage increases, it is likely that Sydney Trains will restrict more customers from accessing platforms or station entries, causing customer delay. ‘Restricting customer access to platforms or station entries is not a sustainable approach to manage station crowding’, said the Auditor-General.

The Auditor-General made seven recommendations to improve Transport for NSW and Sydney Trains' management of station crowding. Transport for NSW have accepted these recommendations on behalf of the Transport cluster.

Public transport patronage has been impacted by COVID-19. This audit was conducted before these impacts occurred.

Read full report (PDF)

Sydney Trains patronage has increased by close to 34 per cent over the last five years, and Transport for NSW (TfNSW) expects the growth in patronage to continue over the next 30 years. As patronage increases there are more passengers entering and exiting stations, moving within stations to change services, and waiting on platforms. As a result, some Sydney metropolitan train stations are becoming increasingly crowded.

There are three main causes of station crowding:

  • patronage growth exceeding the current capacity limits of the rail network
  • service disruptions
  • special events.

Crowds can inhibit movement, cause discomfort and can lead to increased health and safety risks to customers. In the context of a train service, unmanaged crowds can affect service operation as trains spend longer at platforms waiting for customers to alight and board services which can cause service delays. Crowding can also prevent customers from accessing services.

Our 2017 performance audit, ‘Passenger Rail Punctuality’, found that rail agencies would find it hard to maintain train punctuality after 2019 unless they significantly increased the capacity of the network to carry trains and people. TfNSW and Sydney Trains have plans to improve the network to move more passengers. These plans are set out in strategies such as More Trains, More Services and in the continued implementation of new infrastructure such as the Sydney Metro. Since 2017, TfNSW and Sydney Trains have introduced 1,500 more weekly services to increase capacity. Additional network capacity improvements are in progress for delivery from 2022 onwards.

In the meantime, TfNSW and Sydney Trains need to use other ways of managing crowding at train stations until increased capacity comes on line.

This audit examined how effectively TfNSW and Sydney Trains are managing crowding at selected metropolitan train stations in the short and medium term. In doing so, the audit examined how TfNSW and Sydney Trains know whether there is a crowding problem at stations and how they manage that crowding.

TfNSW is the lead agency for transport in NSW. TfNSW is responsible for setting the standard working timetable that Sydney Trains must implement. Sydney Trains is responsible for operating and maintaining the Sydney metropolitan heavy rail passenger service. This includes operating, staffing and maintaining most metropolitan stations. Sydney Trains’ overall responsibility is to run a safe rail network to timetable.

Conclusion

Sydney Trains has identified platform crowding as a key strategic risk, but does not have an overarching strategy to manage crowding in the short to medium term. TfNSW and Sydney Trains devolve responsibility for managing crowding at stations to Customer Area Managers, but do not have sufficient oversight to know if crowding is being effectively managed. TfNSW is delivering a program to influence demand for transport in key precincts but the effectiveness of this program and its impact on station crowding is unclear as Transport for NSW has not evaluated the outcomes of the program.

TfNSW and Sydney Trains do not directly measure or collect data on station crowding. Data and observation on dwell time, which is the time a train waits at a platform for customers to get on and off trains, inform the development of operational approaches to manage crowding at stations. Sydney Trains has KPIs on reliability, punctuality and customer experience and use these to indirectly assess the impact of station crowding. TfNSW and Sydney Trains only formally assess station crowding as part of planning for major projects, developments or events.

Sydney Trains devolve responsibility for crowd management to Customer Area Managers, who rely on frontline Sydney Trains staff to understand how crowding affects individual stations. Station staff at identified key metropolitan train stations have developed customer management plans (also known as crowd management plans). However, Sydney Trains does not have policies to support the creation, monitoring and evaluation of these plans and does not systematically collect data on when station staff activate crowding interventions under these plans.

Sydney Trains stated focus is on providing a safe and reliable rail service. As such, management of station crowding is a by-product of its strategies to manage customer safety and ensure on-time running of services. Sydney Trains' operational response to crowding involves restricting customer access to platforms or stations before crowding reaches unsafe levels, or when it impacts on-time running. As rail patronage increases, it is likely that Sydney Trains will need to increase its use of interventions to manage crowding. As Sydney Trains restrict more customers from accessing platforms or station entries, it is likely these customers will experience delays caused by these interventions.

Since 2015, TfNSW has been delivering the 'Travel Choices' program which aims to influence customer behaviour and to manage the demand for public transport services in key precincts. TfNSW is unable to provide data demonstrating the overall effectiveness of this program and the impact the program has on distributing public transport usage out of peak AM and PM times. TfNSW and Sydney Trains continue to explore initiatives to specifically address crowd management.

Conclusion

TfNSW and Sydney Trains do not directly measure or collect data on station crowding. There are no key performance indicators directly related to station crowding. Sydney Trains uses performance indicators on reliability, punctuality and customer experience to indirectly assess the impact of station crowding. Sydney Trains does not have a routine process for identifying whether crowding contributed to minor safety incidents. TfNSW and Sydney Trains formally assess station crowding as part of planning for major projects, developments or events.

 

Conclusion

Sydney Trains has identified platform crowding as a strategic risk but does not have an overarching strategy to manage station crowding. Sydney Trains' stated focus is on providing a safe and reliable rail service. As such, management of station crowding is a by-product of its strategies to manage customer safety and ensure on-time running of services.

Sydney Trains devolve responsibility for managing crowding at stations to Customer Area Managers but does not have sufficient oversight to know that station crowding is effectively managed. Sydney Trains does not have policies to support the creation, monitoring or evaluation of crowd management plans at key metropolitan train stations. The use of crowding interventions is likely to increase due to increasing patronage, causing more customers to experience delays directly caused by these activities.

TfNSW and Sydney Trains have developed interventions to influence customer behaviour and to manage the demand for public transport services but are yet to evaluate these interventions. As such, their impact on managing station crowding is unclear.

Appendix one – Response from agency

Appendix two – Sydney rail network

Appendix three – Rail services contract

Appendix four – Crowding pedestrian modelling

Appendix five – Airport Link stations case study

Appendix six – About the audit

Appendix seven – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #333 - released 30 April 2020

 

Published

Actions for Transport Access Program

Transport Access Program

Transport
Infrastructure
Project management
Service delivery

The following report is available in an Easy English version that is intended to meet the needs of some people with lower literacy skills, some people with an intellectual disability and some people from different cultural backgrounds.

View the Easy English version of the Transport Access Program report

Transport for NSW’s process for selecting and prioritising projects for the third stage of its Transport Access Program balanced compliance with national disability standards with broader customer outcomes. Demographics, deliverability and value for money were also considered. However, Transport for NSW does not know the complete scope of work required for full compliance, limiting its ability to demonstrate that its approach is effective, according to a report released today by the Auditor-General for New South Wales, Margaret Crawford.

Access to transport is critical to ensuring that people can engage in all aspects of community life, including education, employment and recreation. People with disability can encounter barriers when accessing public transport services. In 2015, there were 1.37 million people living with disability in New South Wales.

Accessible public transport is about more than physical accessibility. It also means barrier-free access for people who have vision, hearing or cognitive impairments. All users, not just people with disability, benefit from improvements to the accessibility and inclusiveness of transport services. 

Transport for NSW has an obligation under Australian Government legislation to provide accessible services to people with disabilities in a manner which is not discriminatory. Under the Disability Standards for Accessible Public Transport 2002 (the DSAPT - an instrument of the Disability Discrimination Act 1992 (the Act) (Commonwealth)), there is a requirement to modify and develop new infrastructure, means of transport and services to provide access for people with disabilities. All public transport operators are required to ensure that at least 90 per cent of their networks met DSAPT by December 2017 and the networks will need to be 100 per cent compliant with all parts of the standards by 31 December 2022. Trains are not required to be fully compliant with DSAPT until December 2032. 

The Transport Access Program (TAP) is Transport for NSW's largest program with a specific focus on improving access to public transport for people with disability. The TAP is a series of projects to upgrade existing public transport infrastructure across four networks: Sydney Trains, Intercity Trains, Regional Trains and Sydney Ferries. Transport for NSW established the TAP as a rolling program and, to date, it has delivered the first tranche of TAP (TAP 1) and is completing the final projects for the second tranche (TAP 2). NSW budget papers estimate that by 30 June 2018, Transport for NSW had spent $1.2 billion in the TAP since its commencement in 2011-12.

After the completion of TAP 1 and TAP 2 (as well as through other transport infrastructure programs), Transport for NSW estimates that 58.5 per cent of the Sydney Trains, Regional Trains and Intercity Trains networks, and 66 per cent of the Sydney Ferries network, will be accessible. To close the significant gap in compliance with the DSAPT target, the objective for TAP 3 is ‘to contribute to Disability Discrimination Act 1992 related targets through DSAPT compliance upgrades’. 

The audit assessed whether Transport for NSW has an effective process to select and prioritise projects as part of the TAP, with a specific focus on the third tranche of TAP funding.

In August 2018, at the commencement of this audit, Transport for NSW intended to complete the selection of projects for the TAP 3 final business case in December 2018. Transport for NSW advise that it now intends to complete the development stage and final business case in the first quarter of 2019, prior to the final investment decision of the TAP program. This report is based on the TAP 3 strategic business case and information provided by Transport for NSW up to December 2018.

Conclusion
Transport for NSW’s process for selecting and prioritising projects for TAP 3 balanced DSAPT compliance goals with broader customer outcomes. It also considered demographics, deliverability and value for money. However, Transport for NSW does not know the complete scope of work required for full DSAPT compliance, and this limits its ability to demonstrate that its approach is effective. 
Transport for NSW has applied most of the external review recommendations from previous funding rounds to the implementation of the third round of TAP funding (TAP3), with positive results. Changes made include a clear objective for TAP 3 to focus on improving compliance, improved governance arrangements, and better consideration of deliverability and design during project planning. 
Through TAP 3, Transport for NSW is also trying to better address disability access in a way that balances DSAPT compliance with other considerations - such as population demographics, access to services and value for money. Transport for NSW developed an objective prioritisation and selection methodology to assess projects for TAP 3 funding. 
Transport for NSW cannot quantify the work needed to meet DSAPT compliance targets across the rail and ferry networks as it has not completed a comprehensive audit of compliance. This information is needed to ensure the effective targeting of funding, and to measure the contribution of TAP 3 work to meeting the DSAPT compliance targets. Instead, Transport for NSW has undertaken a phased approach to completing a comprehensive audit of compliance across the networks, with a focus on first assessing compliance at locations that are not wheelchair accessible. This creates two problems. First, Transport for NSW does not know the complete scope of work required to achieve DSAPT compliance. Second, not all wheelchair accessible locations fully meet DSAPT standards.
Transport for NSW's proposed communication plan for the schedule of TAP 3 funded works does not align with its Disability Inclusion Action Plan 2018-2022. The Disability Inclusion Action Plan commits Transport for NSW to providing a full list of stations and wharves to be upgraded with their estimated time of construction when the next round of funding, TAP 3, is announced. Given the long timeframes associated with improving transport infrastructure, this information is important as it allows people to make informed decisions about where they live, work or study. Instead, Transport for NSW plans to communicate information to customers on a project by project basis.

In 2015, there were 1.37 million people living with disability in New South Wales. Access to transport is critical to ensuring that people can engage in all aspects of community life, including education, employment and recreation. People with disability can encounter barriers when accessing public transport services. 

The social model of disability, outlined in the United Nations Convention on the Rights of Persons with Disabilities, views people with disability as not disabled by their impairment but by the barriers in the community and environment that restrict their full and effective participation in society on an equal basis with others. 

Accessible public transport is more than the provision of physical access to premises and conveyances, it provides barrier-free access for people who have vision, hearing or cognitive impairments. All users, not just people with disability, benefit from improvements to the accessibility and inclusiveness of transport services.

According to the Australian Bureau of Statistics, the main types of difficulties experienced by people with disability when using public transport relate to steps (39.9 per cent), difficulty getting to stops and stations (25 per cent), fear and anxiety (23.3 per cent) and lack of seating or difficulty standing (20.7 per cent).

Transport for NSW has a Disability Inclusion Action Plan (the Action Plan) 2018-2022 that sets an overall framework for planning, delivering and reporting on initiatives to increase accessibility of the transport network. It covers all elements of the journey experienced when using public transport, including journey planning, staff training, customer services and interaction between the physical environment and modes of transport. Appendix five outlines the guiding principles of the Action Plan.

Transport for NSW's Transport Social Policy branch developed the Action Plan in consultation with internal and external stakeholders. The director of the Transport Social Policy branch is a member of the TAP executive steering committee, which supports alignment between the Action Plan and TAP.

Transport for NSW's Disability Inclusion Action Plan describes a customer focussed approach to accessibility

One of the guiding principles of the Action Plan is ‘intelligent compliance’. Transport for NSW describes this as compliance that prioritises customer-focused outcomes over a narrow focus on legal compliance with accessibility standards. As well as being compliant, infrastructure should be practical, usable, fit for purpose and convenient. 

The TAP prioritisation and selection methodology reflects Transport for NSW’s focus on intelligent compliance. We consider this a reasonable approach as had Transport for NSW focussed exclusively on achieving compliance with the DSAPT targets by upgrading the most affordable infrastructure, some locations, that are used by more customers, would remain inaccessible to people with disability. However, this approach should not be seen as an alternative to Transport for NSW meeting its DSAPT compliance obligations.

TAP program staff consult with the Accessible Transport Advisory Committee

The Accessible Transport Advisory Committee (ATAC) has representatives from disability and ageing organisations, who provide expert guidance to Transport for NSW on access and inclusion. The ATAC provide guidance and feedback on projects and project solutions, including user testing where appropriate. TAP program staff provide regular updates at ATAC meetings, which include briefings on progress. The ATAC also provides feedback and suggestions to TAP program staff, which is considered and sometimes included in current and future projects.For example, in March 2017 the TAP program team briefed the ATAC on the challenges with respect to a number of ferry wharves and sought support for DSAPT exemptions proposed in the TAP 3 strategic business case.

Case study: Feedback on Braille lettering for lift buttons
In June 2018, the Program team sought feedback on a variety of lift button options to improve accessibility on future TAP projects. In September 2018, during the ATAC meeting attended by the Audit Office, the program team sought feedback on the standard designs for TAP 3. Some ATAC members noted that the standard design included Braille lettering on the lift buttons, and that this was not good practice because people can accidently press the button while reading it. As a result, Transport for NSW are incorporating this feedback into design requirements for the lifts for TAP 3, which will consider larger buttons, clearer Braille and Braille signage adjacent to the button.

Transport for NSW has not briefed the Advisory Committee on the outcome of the prioritisation and selection process

TAP program staff briefed the Advisory Committee about the prioritisation and selection methodology, after the Minister approved it in 2016. However, Transport for NSW have not briefed or consulted the Advisory Committee on the outcome of the prioritisation process. Infrastructure NSW noted this issue during its review of the strategic business case. 

Transport for NSW advised us that it established the ATAC as an advisory group, and that Transport for NSW does not disclose sensitive information to it. Transport for NSW intends to share the outcome of the prioritisation process following the completion of the TAP 3 development stage and final investment decision.

The TAP communication plan does not fully meet the requirements of the Disability Inclusion Action Plan

The Disability Inclusion Action Plan includes an action item to ‘provide a listing of stations and wharves to be upgraded with estimated time of construction as each new tranche of the Transport Access Program is announced’ The TAP Communication Plan that we reviewed does not include this provision instead focussing on communication on a per project basis. Given the long timeframes associated with improving transport infrastructure, this information is important as it allows people to make informed decisions about where they live, work or study.

Published

Actions for Mobile speed cameras

Mobile speed cameras

Transport
Compliance
Financial reporting
Information technology
Internal controls and governance
Management and administration
Regulation
Service delivery

Key aspects of the state’s mobile speed camera program need to be improved to maximise road safety benefits, according to a report released today by the Auditor-General for New South Wales, Margaret Crawford. Mobile speed cameras are deployed in a limited number of locations with a small number of these being used frequently. This, along with decisions to limit the hours that mobile speed cameras operate, and to use multiple warning signs, have reduced the broad deterrence of speeding across the general network - the main policy objective of the mobile speed camera program.

The primary goal of speed cameras is to reduce speeding and make the roads safer. Our 2011 performance audit on speed cameras found that, in general, speed cameras change driver behaviour and have a positive impact on road safety.

Transport for NSW published the NSW Speed Camera Strategy in June 2012 in response to our audit. According to the Strategy, the main purpose of mobile speed cameras is to reduce speeding across the road network by providing a general deterrence through anywhere, anytime enforcement and by creating a perceived risk of detection across the road network. Fixed and red-light speed cameras aim to reduce speeding at specific locations.

Roads and Maritime Services and Transport for NSW deploy mobile speed cameras (MSCs) in consultation with NSW Police. The cameras are operated by contractors authorised by Roads and Maritime Services. MSC locations are stretches of road that can be more than 20 kilometres long. MSC sites are specific places within these locations that meet the requirements for a MSC vehicle to be able to operate there.

This audit assessed whether the mobile speed camera program is effectively managed to maximise road safety benefits across the NSW road network.

Conclusion

The mobile speed camera program requires improvements to key aspects of its management to maximise road safety benefits. While camera locations have been selected based on crash history, the limited number of locations restricts network coverage. It also makes enforcement more predictable, reducing the ability to provide a general deterrence. Implementation of the program has been consistent with government decisions to limit its hours of operation and use multiple warning signs. These factors limit the ability of the mobile speed camera program to effectively deliver a broad general network deterrence from speeding.

Many locations are needed to enable network-wide coverage and ensure MSC sessions are randomised and not predictable. However, there are insufficient locations available to operate MSCs that meet strict criteria for crash history, operator safety, signage and technical requirements. MSC performance would be improved if there were more locations.

A scheduling system is meant to randomise MSC location visits to ensure they are not predictable. However, a relatively small number of locations have been visited many times making their deployment more predictable in these places. The allocation of MSCs across the time of day, day of week and across regions is prioritised based on crash history but the frequency of location visits does not correspond with the crash risk for each location.

There is evidence of a reduction in fatal and serious crashes at the 30 best-performing MSC locations. However, there is limited evidence that the current MSC program in NSW has led to a behavioural change in drivers by creating a general network deterrence. While the overall reduction in serious injuries on roads has continued, fatalities have started to climb again. Compliance with speed limits has improved at the sites and locations that MSCs operate, but the results of overall network speed surveys vary, with recent improvements in some speed zones but not others.
There is no supporting justification for the number of hours of operation for the program. The rate of MSC enforcement (hours per capita) in NSW is less than Queensland and Victoria. The government decision to use multiple warning signs has made it harder to identify and maintain suitable MSC locations, and impeded their use for enforcement in both traffic directions and in school zones. 

Appendix one - Response from agency

Appendix two - About the audit

Appendix three - Performance auditing

 

Parliamentary reference - Report number #308 - released 18 October 2018

Published

Actions for Administering Domestic Waterfront Tenancies

Administering Domestic Waterfront Tenancies

Planning
Transport
Management and administration
Service delivery
Shared services and collaboration

The audit’s overall conclusion is that Lands and Maritime are broadly achieving outcomes consistent with the IPART report on administering domestic waterfront tenancies. But a lack of collaboration between the agencies is contributing to poor customer service. Inconsistencies with the IPART report recommendations and operational differences between the two agencies result in different rents and conditions for tenants in the two agencies. The differences are having a significant impact on customer service.

 

Parliamentary reference - Report number #191 - released 23 September 2009

Published

Actions for Improving Road Safety: Heavy Vehicles

Improving Road Safety: Heavy Vehicles

Transport
Compliance
Internal controls and governance
Management and administration
Regulation
Risk

The RTA (Roads and Traffic Authority) approach to detecting and enforcing heavy vehicle safety has produced mixed results. There have been overall decreases in the number of crashes and people killed and injured in crashes involving heavy vehicles between 2002 and 2007. However, the number of crashes and the number of people injured have increased between 2006 and 2007.

We recognise that the RTA is unable to prevent all crashes. However, we consider that the RTA could do more to improve its ability to detect and respond to high risk heavy vehicles travelling on our roads.

 

Parliamentary reference - Report number #187 - released 13 May 2009

Published

Actions for Liverpool to Parramatta Bus Transitway

Liverpool to Parramatta Bus Transitway

Transport
Treasury
Infrastructure
Management and administration
Project management
Service delivery

Several of my recent audits have identified a need to improve our public transport system – both for the benefit of travellers and to assist in achieving better air quality.

Bus Transitways can provide a good public transport solution for lower density population areas, potentially at a relatively low capital cost. This audit examines the transitway running between Liverpool and Parramatta, the first of several planned for Sydney. This audit should contribute to a better understanding of the lessons learnt from this first project, and so to future transitways providing better value for money.

But this audit also raises broader issues.

It highlights the importance of accurately projecting the total cost of major infrastructure projects before governments lock in their decisions. It also highlights the need for sound decision-making processes when government agencies compete with the private sector. The principles and recommendations flowing from these issues are ones I would draw to the attention of all agencies, and to the Government.

 

Parliamentary reference - Report number #146 - released 5 December 2005

Published

Actions for Managing Disruptions to Cityrail Passenger Services

Managing Disruptions to Cityrail Passenger Services

Transport
Management and administration
Service delivery
Workforce and capability

About one in every twelve Sydney people travels by train each weekday.

Unplanned disruptions to services are inevitable, even on the best-run railways.

Because of the complexities of Sydney’s rail network, a single event can disrupt many services.

From a passenger’s perspective, three issues are important –

  • how quickly the disruption is fixed (“When will my train arrive?”)
  • the accuracy of information provided about the disruption (“Should I change my travel/meeting/other arrangements?”)
  • how often the disruptions occur (“Should I give up on rail travel?”).

In this audit, we looked at how well RailCorp responds when there are routine disruptions to its CityRail passenger services. We focused on how RailCorp manages passenger journeys and informs passengers.

This report informs Parliament and the community about the limitations of the current system, and what more needs to be done in order to minimise the impact of disruptions on passengers.

It should also help passengers judge the extent to which they can rely on the information they receive, and to better understand some of the obstacles faced by staff.

 

Parliamentary reference - Report number #139 - released 22 June 2005

Published

Actions for Follow-up of Performance Audit: Bus Maintenance and Bus Contracts

Follow-up of Performance Audit: Bus Maintenance and Bus Contracts

Transport
Asset valuation
Compliance
Financial reporting
Infrastructure
Management and administration
Procurement
Project management
Service delivery
Workforce and capability

Periodically we review the extent to which agencies have implemented the recommendations they accepted from our earlier audits.

This gives Parliament and the public an update on the extent of progress made.

In this follow-up audit, we examine changes following our May 2002 report on how well the:

  • State Transit Authority maintained its buses
  • Ministry of Transport administered contracts for the provision of regular passenger bus services.

 

Parliamentary reference - Report number #138 - released 14 June 2005