Actions for CBD and South East Light Rail Project
CBD and South East Light Rail Project
Transport for NSW did not effectively plan and procure the CBD and South East Light Rail (CSELR) project to achieve best value for money according to a report released today by NSW Auditor-General, Margaret Crawford.
Transport for NSW is on track to deliver the project, but it will come at a higher cost with lower benefits than in the approved business case.
Parliamentary reference - Report number #278 - released 30 November 2016
Actions for Fraud Survey
Fraud Survey
In a report released today, the NSW Auditor-General, Margaret Crawford provides a snapshot of reported fraud in the NSW public sector and an analysis of NSW Government agencies’ fraud controls based on a survey of 102 agencies.
Actions for Volume Six 2015 Transport
Volume Six 2015 Transport
Public transport revenue decreased by 2.7 per cent despite a fare increase and increased patronage. Twenty-five per cent of all Opal trips (over 74 million) were free, including 47 per cent of trips on ferries, according to a report released today by the New South Wales Acting Auditor-General, Tony Whitfield. These trips were valued at $189 million.
Actions for Albert 'Tibby' Cotter Walkway
Albert 'Tibby' Cotter Walkway
On 17 September 2015, the Acting Auditor-General of New South Wales, Tony Whitfield, released a report on the Albert ‘Tibby’ Cotter Walkway which crosses over Anzac Parade in Moore Park. The Walkway’s primary function is to cater for event patrons in the precinct. Moore Park is listed on the State Heritage Register and is an open space specifically established to cater for public recreation.
Roads and Maritime Services (RMS) delivered the Walkway to an extremely tight timeframe. It was operational for the 2015 Cricket World Cup at the Sydney Cricket Ground as promised by the government. However, the World Cup deadline added substantially to the total cost of the Walkway, which is projected to be $38 million.
Transport for NSW and RMS could not provide evidence of a compelling economic or financial argument to support the construction of the Walkway or for the tight deadline. Also, the processes they adopted to provide assurance of the project’s value for money were not adequate.
Parliamentary reference - Report number #260 - released 17 September 2015
Actions for Sydney metropolitan bus contracts
Sydney metropolitan bus contracts
On 9 September 2015, the Acting Auditor-General of New South Wales, Tony Whitfield, released a report on Sydney Metropolitan Bus Service Contracts.
All scheduled bus services in the Sydney metropolitan area are provided under contracts with the public and private operators. The contracts allow Transport for NSW (TfNSW) to determine what bus services are provided and to whom. This audit assessed the effectiveness of TfNSW’s design and management of these contracts.
Bus services provided under the Sydney Metropolitan Bus Service Contracts have largely been effective and efficient. Operators are mostly meeting their key performance indicators. Customer satisfaction is better than under the previous contracts and improving, patronage is increasing, and the unit costs of providing services are now lower than under the previous contracts.
However, punctuality remains a problem. Private operators are mostly starting their trips on time, but rarely meeting their mid and end-of-trip targets. State Transit Authority’s (STA) punctuality is improving but is worse than private operators, and other areas of performance are generally below private operators.
The current situation is a substantial improvement over what we found in our 2010 audit on the previous contracts.
Parliamentary reference - Report number #258 - released 9 September 2015
Actions for Large construction projects
Large construction projects
The independent assurance given to the NSW Government and sponsor agencies on the viability of large capital projects throughout their lifecycle is inadequate. Government policy is regularly not followed and not properly communicated to those responsible for implementing such policy.
This audit sought to test the effectiveness of the NSW capital project assurance system - which includes gateway reviews and reporting - but significant levels of non-compliance identified in our case studies prevented this. The NSW Commission of Audit also identified this issue in 2012. Gateway reviews are conducted by independent reviewers at key stages of a project’s life cycle and provide an independent assessment on a project’s readiness to proceed to the next stage.
Parliamentary reference - Report number #252 - released 7 May 2015
Actions for Areas of focus from 2014
Areas of focus from 2014
Actions for Security of critical IT infrastructure
Security of critical IT infrastructure
Roads and Maritime Services and Transport for NSW have deployed many controls to protect traffic management systems but these would have been only partially effective in detecting and preventing incidents and unlikely to support a timely response. There was a potential for unauthorised access to sensitive information and systems that could have disrupted traffic.
Until Roads and Maritime Services’ IT disaster recovery site is fully commissioned, a disaster involving the main data centre is likely to lead to higher congestion in the short-term as traffic controllers would be operating on a regional basis without the benefit of the Traffic Management Centre.
Parliamentary reference - Report number #248 - released 21 January 2015
Actions for WestConnex: Assurance to the Government
WestConnex: Assurance to the Government
This audit assesses the assurance provided to the NSW Government for the initial stages of the WestConnex project.
The audit examined the WestConnex project from concept development to the pre-tender phase for Stage 1A – M4 (Parramatta to Homebush Bay). It did not examine the merit of the project or whether it represented value-for-money.
This audit found a number of shortcomings with the governance of the WestConnex project during its early stages and makes recommendations on how to better govern the remainder of the project to minimise the risk of failure.
Parliamentary reference - Report number #247 - released 18 December 2014
Actions for Volume Seven 2014 Focusing on Transport
Volume Seven 2014 Focusing on Transport
All agencies in transport cluster received unqualified audit opinions for the year ended 30 June 2014. The quality of financial reporting continues to improve with the number of misstatements identified during audits falling for the fifth year in a row.