Actions for Transport 2019

Transport 2019

Transport
Asset valuation
Financial reporting
Infrastructure
Internal controls and governance
Management and administration
Service delivery
Workforce and capability

This report details the results of the financial audits of NSW Government's Transport cluster for the financial year ended 30 June 2019. The report focuses on key observations and findings from the most recent financial statement audits of agencies in the Transport cluster.

Unqualified audit opinions were issued for all agencies' financial statements. However, valuations of assets continue to create challenges across the cluster. The Audit Office identified some deficiencies in relation to asset valuations at Transport for NSW, Roads and Maritime Services, Rail Corporation New South Wales and Sydney Metro.

The Audit Office noted an increase in findings on internal controls across the Transport cluster. Key themes related to information technology, asset management and employee leave entitlements. The report also highlights the status of significant infrastructure projects across the Transport cluster.

The report makes several recommendations including:

  • agency finance teams need to be consulted on major business decisions and commercial transactions at the time of their execution to assess the financial reporting impacts
  • the Department of Transport should ensure consistent accounting policies are applied across its controlled entities.

Download the Transport 2019 report (PDF)

This report analyses the results of our audits of financial statements of the Transport cluster for the year ended 30 June 2019. The table below summarises our key observations.

1. Machinery of Government changes
Transport for NSW, as the
lead agency, will absorb the
functions of Roads and
Maritime Services

The NSW Government announced its intention to integrate Roads and Maritime Services (RMS) into Transport for NSW (TfNSW) as part of the Machinery of Government changes.

This change was not included in the Administrative Orders as the Transport Administration Act 1988 No. 109 governs the composition of the Transport cluster. The Transport Administration Amendment (RMS Dissolution) Act 2019 (the Act) received assent on 22 November 2019. The Act dissolves RMS and transfers the assets, rights and liabilities of RMS to TfNSW. As at the date of this Report, the Act is not yet in force.

Transport is considering the impact of the changes on its operating model and financial reporting.

2. Financial reporting
Audit opinions

Unqualified audit opinions were issued on the 2018–19 financial statements of all agencies in the Transport cluster.

TfNSW and Sydney Metro obtained a three-week extension from NSW Treasury to submit their financial statements for audit to resolve accounting issues surrounding the valuation of property, plant and equipment.

The Department of Transport reported total consolidated property, plant and equipment of $158 billion at 30 June 2019. In 2018–19, there were issues with asset valuations at TfNSW, RMS, Sydney Metro and Rail Corporation New South Wales (RailCorp), resulting in adjustments after the submission of financial statements for audit and the correction of a prior period error.

There was also a prior period error resulting from an agreement between TfNSW and the former UrbanGrowth Development Corporation due to a lack of assessment of the financial reporting implications at the time of signing the agreement.

Recommendation: Agency finance teams need to be consulted on major business decisions and commercial transactions to assess their accounting impacts at the time of their execution, rather than at the end of a financial year. Agencies also need to resolve all key accounting issues such as valuations as part of the early close procedures.

This would improve the quality of financial reporting and avoid the need for extensions for agencies to submit their financial statements for audit.

Preparedness for new
accounting standards
Agencies across the cluster are progressing in their implementation of the new accounting standards.

Transport cluster agencies need to improve their contracts registers to ensure they have a complete list of contracts and agreements to assess the impact of the new accounting standards.
Valuation of assets remains
a challenge in the
Transport cluster

Whilst agencies complied with the requirements of the accounting standards and NSW Treasury policies on valuations, the Audit Office identified some deficiencies in relation to asset valuations across the cluster.

TfNSW reported a retrospective correction of a prior period error at 1 July 2017 which resulted in a reduction in the valuation of its Country Rail Network earthworks by $2.1 billion. This was due to survey results which identified the earthworks were flatter and lower than estimated in the valuation at 30 June 2017.

RMS made several adjustments during the year to correct asset values due to changes to valuation assumptions or data improvements. This included:

  • reduction of $318 million in the value of land under roads
  • decrease of $84.9 million to the value of land and buildings
  • changes to the value of traffic control and traffic signal network assets, due to data improvements.

Sydney Metro North West officially opened in May 2019 and reported total assets of $9.1 billion. Sydney Metro derecognised $322 million in assets constructed to facilitate its operation but transferred to councils and utilities.

Inconsistent accounting
policies across the
Transport cluster

There was an inconsistency identified in the cluster relating to the valuation of substratum land. In 2018–19, RailCorp derecognised $109 million of substratum land to ensure consistency in its approach with other Transport agencies.

As the parent entity, the Department of Transport needs to ensure accounting policies are consistently applied across all controlled entities for consolidation purposes. Inconsistencies in the application of accounting standards across agencies will impact comparability of financial reporting and decision making across the Transport cluster.

Recommendation: The Department of Transport should ensure consistent accounting policies are applied across its controlled entities.

Revenue growth

Public transport passenger revenue increased by $89.0 million (5.9 per cent) in 2018–19, and patronage increased by 37.8 million (4.9 per cent) across all modes of transport based on data provided by TfNSW.

The increase in revenue is mainly due to an increase in patronage as well as the annual increase in fares.

Negative Opal cards

Negative balance Opal cards resulted in $2.9 million in revenue not collected in 2018–19 ($10.4 million since the introduction of Opal).

In January 2019, Transport made a change to the Sydney Airport stations to prevent customers with high negative balances exiting the station. In addition, in late 2018, Transport increased the minimum top up values for new cards at the airport stations.

Recommendation (repeat): TfNSW should implement further measures to prevent the loss of revenue from passengers tapping off with negative balance Opal cards.

3. Audit observations
Internal controls There was an increase in findings on internal controls across the Transport cluster. Key themes relate to information technology, employee leave entitlements and asset management.

Twenty-nine per cent of all issues were repeat issues. The majority of the repeat issues related to information technology controls.
Write-off of assets In addition to a $322 million derecognition of assets transferred to councils and utilities by Sydney Metro and a $109 million derecognition of substratum land at RailCorp, the Transport cluster wrote-off $278 million of assets related to roads, bridges, maritime assets, traffic signals and controls network.

These mainly related to roads, bridges, maritime assets, traffic signals and the control network where new infrastructure assets substantially replaced an existing asset as part of construction activities.
Transport Asset Holding
Entity (TAHE)
TAHE was established to be a dedicated asset manager for the delivery of public transport asset management. The Transport Administration Amendment (Transport Entities) Act 2017 will transition RailCorp into TAHE. RailCorp is now expected to transition to TAHE from 1 July 2020 (previously 1 July 2019). Several working groups have been considering various aspects of the TAHE transition including its status as a for profit Public Trading Enterprise, the operating model and the impact of the new accounting standards AASB 16 'Leases' and AASB 1059 'Service Concession Arrangements: Grantors'. The considerations of these aspects identified several challenges in the implementation of TAHE which has led to the revised transition date. Given the delays in implementation, it is important to clarify the intent of the TAHE model.
Excess annual leave

Twenty-six per cent of Transport employees have annual leave balances exceeding 30 days. Of the employees with excess leave balances, 732 (10.3 per cent) did not take any annual leave in 2018–19.

Recommendation (repeat): Transport entities should further review the approach to managing excess annual leave in 2019–20. They should:

  • monitor current and projected leave balances to the end of the financial year each month
  • agree formal leave plans with employees to reduce leave balances over an acceptable timeframe
  • ensure leave plans are actioned appropriately
  • encourage all staff with excess leave balances take a minimum two-week period of leave per year.
Completeness and
accuracy of contracts
registers

There are no centralised processes to record all significant contracts and agreements in a register across the Transport cluster.

Across the Transport cluster, contracts and agreements are maintained by the individual agencies using disparate registers. Agencies must perform detailed assessments of their existing contracts and agreements to quantify the impact of the new accounting standards (AASB 16 ‘Leases’, AASB 15 ‘Revenue from Contracts with Customers’, AASB 1058 ‘Income of Not-for-Profit Entities’ and AASB 1059 'Service Concession Arrangements: Grantors').

In 2018–19, there was also a prior period error resulting from an agreement between TfNSW and another government agency due to a lack of assessment of the financial reporting implications at the time of signing the agreement.

A lack of a complete register of all contracts and agreements increases the risk that agencies may not be able to assess the full impact of the new accounting standards, as well as perform a complete assessment of the financial reporting implications of contracts and agreements.

Recommendation: Transport agencies should implement a process to centrally capture all significant contracts and agreements entered. This will ensure:

  • agencies are fully aware of contractual and other obligations
  • appropriate assessment of financial reporting implications
  • assessment of new accounting standards, in particular AASB 16 ‘Leases’, AASB 15 'Revenue from Contract with Customers', AASB 1058 'Income of Not-for-Profit Entities ' and AASB 1059 'Service Concession Arrangements: Grantors' are accurate and complete.

 

This report provides parliament and other users of the Transport cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

This cluster was impacted by the Machinery of Government changes on 1 July 2019. The NSW Government announced its intention to integrate Roads and Maritime Services (RMS) into Transport for NSW (TfNSW). This report is focused on the Transport cluster prior to these changes. Please refer to the section on Machinery of Government changes for more details.

Machinery of Government refers to how the government organises the structures and functions of the public service. Machinery of Government changes are where the government reorganises these structures and functions, and are given effect by Administrative orders.

The Transport cluster was impacted by recent Machinery of Government changes. These changes were announced by the Department of Premier and Cabinet but were not included in the Administrative Orders as the Transport Administration Act 1988 No. 109 governs the composition of the Transport cluster. It was the intention of government to transfer the functions of the RMS into TfNSW. This requires legislative changes to the Transport Administration Act 1988 No. 109.

Section highlights

Under the Machinery of Government changes, the NSW Government will transfer the functions of RMS into TfNSW.

  • The Transport Administration Amendment (RMS Dissolution) Act 2019 (the Act) received assent on 22 November 2019.
  • The Act will dissolve RMS and transfer its functions, assets, rights and liabilities to TfNSW.
  • As at the date of this report, the Act is not yet in force.
  • There are risks and challenges for asset and liability transfers, governance and retention of knowledge.
  • As of 1 July 2019, administrative arrangements (delegations and reporting line changes) were put in place to enable TfNSW and RMS to operate within a single management structure, while still remaining as separate legal entities.
  • Transport is working on a number of options as to how to implement the changes. 

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Transport cluster for 2019.

Section highlights

  • Unqualified audit opinions were issued on all agencies' financial statements.
  • RMS required an extension from NSW Treasury for their early close procedures.
  • TfNSW and Sydney Metro required extensions to submit their year-end financial statements.
  • Valuation of assets remains a challenge across the cluster.
  • There remains Opal cards with negative balances.
  • Sydney Metro derecognised assets of $322 million in relation to assets constructed for third parties.
  • Inconsistencies in the application of accounting policies across cluster agencies impact comparability of financial reporting across the Transport cluster.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our observations and insights from our financial statement audits of agencies in the Transport cluster.

Section highlights

  • There was an increase in findings on internal controls across the Transport cluster. Twenty-nine per cent of all issues were repeat issues.
  • Transport entities wrote-off over $278 million of assets which were replaced by new assets or technology.
  • Twenty-six per cent of Transport employees have excess annual leave.
  • There are no processes to ensure all significant contracts and agreements are captured by agencies in a centralised register.

Appendix one – Timeliness of financial reporting by agency 

Appendix two – Management letter findings by agency 

Appendix three – List of 2019 recommendations 

Appendix four – Status of 2017 and 2018 recommendations 

Appendix five – Cluster agencies 

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for State Finances 2019

State Finances 2019

Education
Finance
Community Services
Health
Justice
Industry
Planning
Premier and Cabinet
Transport
Treasury
Whole of Government
Financial reporting

The Auditor-General, Margaret Crawford, has released her report on the State Finances for the year ended 30 June 2019.

‘I am pleased to once again report that I issued an unmodified audit opinion on the State’s consolidated financial statements,’ the Auditor-General said.

The report acknowledges NSW Treasury and agency efforts to reduce the number and value of errors compared with the previous year. ‘Strong financial management and transparent reporting are key elements of our system of government. Treasury and agency finance teams need to be consulted on major business decisions at the time of their execution. This will ensure agencies assess the accounting implications earlier and support accurate financial statements being presented for audit on a timely basis,’ said the Auditor-General.

The report summarises the financial audit result of the Total State Sector Accounts. The Total State Sector comprises 304 entities controlled by the NSW Government with total assets of $468 billion and total liabilities of $218 billion.

The General Government sector comprises 212 entities that provide goods and services that are funded centrally by the State. General Government expenditure grew by 5.5 per cent in 2018-19, which was below the long-term revenue growth of 5.6 per cent target established by the Fiscal Responsibility Act 2012.

Download PDF of State Finances 2019 report

Pursuant to the Public Finance and Audit Act 1983, I present my Report on State Finances 2019.

Strong financial management and transparent reporting are key elements of our system of government.

I am pleased to once again report that I issued an unmodified audit opinion on the State’s consolidated financial statements. 

The number of errors in agencies’ 2018–19 financial statements fell to six compared to the 23 recorded in 2017–18. This reflects Treasury’s focus on early close and the resolution of complex accounting matters before submission. Agency finance teams need to be consulted on major business decisions and commercial transactions to assess their accounting impacts at the time of their execution, rather than at the end of a financial year. This would improve the quality of financial reporting and avoid the need for extensions for agencies to submit their financial statements for audit.

To further increase transparency, a Key Audit Matters section was included in my Independent Auditor Report on the Total State Sector Accounts this year. This explains those matters considered most significant to the conduct of the audit and requiring significant management judgement.

Looking forward, certain factors have the potential to impact the accuracy and completeness of the Total State Sector Accounts in coming years. First, three new accounting standards are effective from 1 July 2019 and a fourth from 1 July 2020. Transitioning to new standards requires significant planning and resources to ensure the impacts are appropriately assessed and accounted for. Second, the Government Sector Finance Act 2018 will be implemented in stages over three years to 2020–21. This Act is intended to focus on performance, transparency, accountability, and efficiency of financial management in the government sector. I encourage agencies to build their awareness of this important reform and ensure their alignment with the principles of the Act. 

I want to thank Treasury staff for the way they engaged with my staff in the conduct of the audit. Our partnership is critical to ensuring the quality of financial management and reporting.

Margaret Crawford
Auditor-General, 10 October 2019

Our audit opinion on the State’s 2018–19 financial statements was unmodified. There were fewer reported errors but earlier resolution of accounting matters is still required.

Our audit opinion on the State’s 2018–19 financial statements was unmodified.

This year, six errors exceeding $20 million were found in agencies’ 2018–19 financial statements that make up the State’s consolidated financial statements. The total value of these errors was $927 million compared to $3.8 billion in 2017–18. The errors identified in 2018–19 resulted from:

  • incorrectly applying Australian Accounting Standards and Treasury Policies
  • using inappropriate assumptions and inaccurate data
  • incorrectly assessing the fair value of non-current physical assets.

The introduction of mandatory ‘early close procedures’ in 2011–12, saw the number of errors in agencies’ financial statements fall progressively, to a low of five in 2015–16.

In 2016–17, Treasury narrowed the scope of its mandatory early close procedures to focus on non-current physical asset valuations and pro-forma financial statements. Following this, the number of significant errors increased to 23 in 2017–18, the

highest number in six years and similar to the numbers identified before mandatory early close procedures were introduced.

In 2018–19, Treasury and agencies’ refocused their efforts around early close procedures and other year-end processes resulting in this year’s lower error total of six.

Errors in agency financial statements exceeding $20m (2015–2019)

Correction of prior year’s reported values    

Correction of earthwork assets ($2.1 billion)

Some of the State’s earthworks were first valued in 2016–17. These included earth excavations and embankments for the Country Rail and Metropolitan Network created before the year 2000 and dating back to the early 1900s.

For many years, the State did not account for earthworks because it believed the value could not be reliably measured. In 2016–17, the State engaged an external valuer who identified a methodology showing the earthworks could be valued. That valuer performed a valuation using topography maps for the Country Rail Network (CRN) because information in this earthworks database was of poor quality and incomplete. The valuation resulted in the State recognising $7.5 billion of earthworks for the first time in 2016–17. This was disclosed as a prior period error.

Over the following years, the State improved the quality of the CRN earthworks database by engaging an engineering firm to perform more detailed earthworks surveys. The work involved the use of technology to survey most of the CRN lines.

In 2018–19, the State once again engaged an external valuer to assess the fair value of the CRN earthworks. The valuer determined that incorrect assumptions were used in the 2016–17 valuation. These primarily related to land elevations, which were corrected in the earthworks database and this resulted in a new fair value of $5.4 billion, $2.1 billion less than the previous valuation. The error reported in the 2017–18 value has been corrected in the 2018–2019 financial statements to reflect the revised value.

Previously reported value for earthworks reduced from $7.5 billion to $5.4 billion.

Correction of museum collection assets ($27 million)

The Australian Museum’s collection assets were restated by $27 million to $800 million in 2017–18.

After the 2017–18 financial statements were published, the Australian Museum identified additional collection assets that were not included in the original valuation. This resulted in a $27 million error relating to collection asset values. As last year’s valuation was based on an incomplete listing of collection assets, the 2017-18 value has been corrected in the 2018–19 financial statements to reflect the revised value.

Correction of lease liability ($46.2 million)

On 1 July 1995, the Department of Justice entered into a 25-year lease arrangement with an option to extend for a further 15 years.

The Department accounted for the arrangement as a finance lease by recognising a building asset and a corresponding finance lease liability for the period of 25 years. The Department depreciated the leased asset based on a useful life of 40 years.

As it was reasonably certain the Department would exercise the lease option at inception, it should have recognised a liability that reflected the entire 40 year lease period. To correct the prior year error and properly reflect the extended lease period, the Department of Justice increased the lease liability and decreased retained earnings by $46.2 million as at 1 July 2017.

Abuse Claims remain a significant contingent liability of the State

The State discloses a contingent liability in its financial statements when the possibility of settling the liability in the future is considered less than probable, but more likely than remote, or the amount of the obligation cannot be measured with sufficient reliability.

If the expected settlement subsequently becomes probable and reliably estimable, a provision is recognised.

The State has numerous contingent liabilities. Some are quantifiable while others are not. As contingent liabilities are potentially material future liabilities of the State, every effort should be made to quantify these as accurately as possible. They also need to be monitored closely to ensure that they are recognised and brought on balance sheet as they crystallise.

At 30 June 2019, NSW Self Insurance Corporation (SiCorp) could not reliably measure the claims liability arising from past incidences of abuse that occurred within NSW Government institutions which have not yet been reported. These are referred to as incurred but not reported claims (IBNR).

Since 1 July 2018, victims of child sexual abuse can opt to claim compensation through the National Redress Scheme, or to lodge a civil claim. Civil claims for incidents that occurred within NSW Government institutions may be covered by SiCorp. An estimate of an IBNR for child abuse claims within SiCorp will be impacted by the extent that victims claim compensation through redress as compared to civil claims.

Recent legislative changes have added further uncertainty to estimating the extent of IBNR claims. SiCorp requires more reliable data on the number of IBNR child abuse claims and the expected average size of the related payments. As such, the liabilities presented in the SiCorp and the State financial statements do not include an allowance for IBNR abuse claims.

As more information becomes available it may be possible for SiCorp to reasonably estimate the value of abuse claim liabilities. It is possible that such an estimate may be material to SiCorp and the State’s financial statements. 

TAFE update

In prior years we reported on information system limitations at TAFE NSW, specifically relating to its student administration system. TAFE NSW continues to implement additional processes to verify the accuracy and completeness of revenue from student fees for the 2018–19 financial year.

In 2017–18 TAFE NSW started implementing a new student management system. Significant delays have occurred in implementing this system, mainly due to the complexity of integrating the vendor solution with the requirements of TAFE. TAFE will now bring the final commissioning and operation of the system in house. Final project delivery timeframes and estimated completion costs are being reviewed. Costs incurred to date amount to $67 million. The original budget for this new system is $89.4 million.

Light Rail settlement

The CBD and South East Light Rail is a new twelve kilometre light rail network for Sydney, currently under construction. Passenger trips are set to begin on the light rail by December between Circular Quay and Randwick. The second stage from Randwick to Kingsford is planned to open in March 2020. The original budget for construction work of $1.6 billion was revised to $2.1 billion in 2014.

The State Government has been in dispute with the firm responsible for delivering and operating the CBD and South East light rail project. In May 2019, the parties reached a Settlement Arrangement resulting in the State agreeing to pay a settlement amount of $576 million, which is in addition to the revised budget. Transport has advised a final cost is still to be determined following project completion.

The Audit Office has commenced a follow up audit on the CBD South East Light Rail. This audit will consider whether recommendations of our previous audit have been implemented. We will also review the current status and budget of this project.

Sydney Metro Northwest project commissioning

The Sydney Metro North West officially opened in May 2019.

In constructing the metro, some assets were built to facilitate its operation. These included pavements, roadworks, and electricity
and water connections.

When the project was completed, the assets and the responsibility for maintaining them transferred to third parties, primarily Councils and utility providers. In 2018–19, the State expensed (derecognised) the assets, valued at $306 million, because it no longer controlled them.

Financial Reporting by Crown Land Reserve Trusts

Approximately 700 reserve trusts, managed by Trust Boards, did not prepare the financial statements at 30 June 2019 as required by the
Public Finance and Audit Act 1983.

These Crown reserves contain showgrounds, cemeteries, racecourses, local parks, and other community facilities and public areas. Some of the Crown reserves have independent streams of revenue from user charges.

In 2016–17, Treasury determined that NSW cemetery trusts and a holiday park reserve trust were controlled entities of the State. As such, the Public Finance and Audit Act 1983 requires them to prepare financial statements and have these audited by the Auditor-General.

In 2017–18, three reserve trusts accepted NSW Treasury’s view, prepared financial statements and had them audited by the Auditor-General.

However, three cemetery reserve trusts continue to maintain they are not controlled by the State and therefore their financial statements are not audited by the Audit Office. These cemeteries shared their unaudited financial statements with Treasury so they could be incorporated into the State’s financial statements. At 30 June 2019, the value of their combined assets and liabilities, which are not audited by the Audit Office, was $564 million.

The State included an additional $319 million in assets that relate to Crown land values of approximately 700 reserve trusts that did not prepare or submit financial statements.

We performed additional audit procedures to obtain some assurance over the value of these crown lands. The nature and extent of the limitations to the scope of these procedures was not significant enough to impact our audit opinion. Treasury should ensure these trusts comply with the requirements of the Public Finance and Audit Act.

Derecognition of investment in City West Housing

In 2017–18, the State had an equity investment of $680 million in a community housing provider, City West Housing Pty Limited (CWH).

During 2018–19, CWH amended its constitution to ensure alignment with its charitable status. The unintended impact of this change was that on windup the net assets would not be distributed to the State. The accounting implications to the State’s investment was not considered by Treasury at the time of approving the amended constitution. Consequently, the State wrote off its $680 million investment in CWH in 2018–19.

It is important that accounting impacts of such changes are discussed and agreed upon early. At the time of approving the decision to change the constitution, all accounting implications should be made available and understood. Such information is relevant when approving decisions. The theme of what is relevant
information will be explored further in our Performance Audit of ‘Advice on Major Decisions’.

Machinery of government (MoG) changes refers to how the government reorganises agency structures and functions and realigns ministerial responsibilities.

Cluster changes

On 2 April 2019, the Government reorganised public sector agencies into eight clusters (ten in 2017–18) with effect from 1 July 2019.

Prior to 30 June 2019, two subsequent administrative arrangement orders were made to amend and finalise the MoG changes.

The key MoG changes included:

  • abolishing the following five departments:
    • Finance, Services and Innovation
    • Industry
    • Planning and Environment
    • Family and Communities
    • Justice
  • transferring their functions into three new departments:
    • Department of Customer Service
    • Department of Planning, Industry and Environment
    • Department of Communities and Justice
The State’s consolidated financial statements at 30 June 2019 were not impacted by the changes, as they were effective from 1 July 2019.

The chart below shows the cluster arrangements before and after the MoG changes to the General Government Sector. It compares total budgeted expenses presented in the 2018–19 and 2019–20 Budget Papers (1).

Each cluster’s share of the General Government Sector’s (GGS) total expenditure remains relatively unchanged after the MoG changes. Further details on other functions transferred between clusters are detailed in the 2019–20 Budget Papers.

Of the clusters, Education is affected most by the MoG changes from the perspective of increased expenditure in the 2019–20 budget. This is because the TAFE Commission transferred into this cluster from the former Department of Industry on 1 July 2019, resulting in a corresponding decrease in the new Planning, Industry and Environment cluster’s expenditure.

(1) The 2018–19 Budget Paper 3 (unaudited) and 2019–20 Budget Paper 3 (unaudited).

Cluster expenses

2018-19
Before MoG Changes

2019-20
After MoG Changes

Industry 6% Planning, Industry and Environment 7%
Planning and Environment 4%
Education 18% Education 21%
Premier and Cabinet 1% Premier and Cabinet 2%
Finance, Service and Innovation 4% Customer Service 3%
Family and Community Services 8% Stronger Communities 18%
Justice 10%
Transport 9% Transport 9%
Treasury 14% Treasury 14%
Health 26% Health 26%

 

$1.2 billion surplus, $0.2 billion below 2018–19 budget of $1.4 billion

The Total State Sector comprises 304 entities controlled by the NSW Government.

The General Government Sector, which comprises 212 entities, generally provides goods and services funded centrally by the State.
The non-General Government Sector, which comprises 92 Government businesses, generally provides goods and services, such as water, electricity and financial services that consumers pay for directly.

A principal measure of a Government’s overall performance is its Net Operating Balance (Budget Result). This is the difference
between the cost of General Government service delivery and the revenue earned to fund these sectors.

What changed from 2018 to 2019?

The State maintained its AAA credit rating.

The object of the Fiscal Responsibility Act 2012 is to maintain the State’s AAA credit rating.

The Government manages NSW’s finances in accordance with the Fiscal Responsibility Act 2012 (the Act).

The Act establishes the framework for fiscal responsibility and the strategy to protect the State’s AAA credit rating and service delivery to the people of New South Wales.

The legislation sets out targets and principles for financial management to achieve this.

New South Wales has credit ratings of AAA/Stable from Standard & Poor’s and Aaa/Stable from Moody’s Investors Service.

The fiscal targets for achieving this objective are:

General Government annual expenditure growth is lower than long term average revenue growth.

General Government expenditure grew by 5.5 per cent in 2018–19 (5.1 per cent in 2017–18 based on restated balances). This was slightly below the long-term revenue growth rate of 5.6 per cent.

Eliminating unfunded superannuation liabilities by 2030.

The Act sets a target to eliminate unfunded superannuation liabilities by 2030.

The State’s funding plan is to contribute amounts escalated by five per cent each year so the schemes will be fully funded by 2030. In 2018–19, the State made employer contributions of $1.73 billion ($1.67 billion in 2017–18), an increase of $64 million or 3.8 per cent ($52 million or 3.2 per cent in 2017–18). This was under the five per cent target by $19.5 million.

For fiscal responsibility purposes, the State uses AASB 1056: Superannuation Entities. This accounting standard discounts superannuation liabilities using the expected return from the assets backing the liability.

Using this method, the State’s unfunded superannuation liability was $13.2 billion at 30 June 2019 ($14.0 billion).

Superannuation funding position since inception of the Act - AASB 1056 Valuation

State revenues fell $604 million to $86.1 billion in 2018–19    

In the prior years, revenue growth was underpinned by cyclical increases in land tax, payroll tax and one-off large stamp duty receipts from the lease of the State’s electricity network assets. In 2018–19, the State’s revenue fell by $604 million to $86.1 billion ($86.7 million in 2017–18).

Taxation revenue remained relatively stable

Taxation revenue only grew slightly, mainly due to:

  • a $517 million increase in payroll tax from NSW wages growth
  • a $469 million increase in land tax from growth in land values
  • offset by a $1.2 billion decrease in stamp duty due to lower than expected growth in the property market. This decrease would have been higher had the State not received $555 million in stamp duty from the new 51 per cent owner of WestConnex.

The gap between payroll tax and stamp duty reduced significantly in 2018–19. Stamp duty still remains the largest source of revenue for the State at $9.2 billion, only $42 million above payroll tax.

Australian Government grants and subsidies

The State received $31.8 billion in grants and subsidies from the Australian Government, $158 million less than the previous year. This was due to falls in other grants and subsidies of $98 million and GST revenues of $48 million.

GST revenues fell due to weaker growth in national consumption expenditure and a smaller GST pool. The GST pool represents funds made available by the Commonwealth for transfer to the States as untied financial assistance. The allocation of GST is determined by the Commonwealth, not the State.

A $392 million decrease in National Partnership Payments was offset by a $380 million increase in Specific Purpose Payments.
 
In 2018–19, sales of goods and services fell $395 million mainly due to the sale of WestConnex.

Other dividends and distributions fell by $122 million due to lower distributions from associates. This reflected weaker performance in the electricity sector (Ausgrid and Endeavour) resulting in lower distributions paid to the State following changes in the Electricity Network Service Providers regulatory environment and the sale of Snowy Hydro Pty Ltd in 2017–18.

Fines, regulatory fees and other revenues increased by $242 million largely from mineral royalties. The increase was attributed to strong demand across Asian markets for coal exports, which the State expects will continue to experience steady growth.

Expenses increased $4 billion to $87.9 billion in 2018–19    

Overall, the State’s expenses increased 4.8 per cent in 2018–19 compared to 2017–18. Most of the increase was due to higher employee expenses, operating costs and grants and subsidies.

Employee expenses, including superannuation, increased by 3.9 per cent to $40.3 billion.

Salaries and wages increased to $40.3 billion in 2018–19 from $38.8 billion 2017–18. This was mainly due to salary and wage increases. The Government wages policy aims to limit growth in employee remuneration and other employee related costs to no more than 2.5 per cent per annum.

Operating expenses increased 6.1 per cent from 2017–18.

Within operating expenses, payments for supplies, services and other expenses increased due to:

  • increased operating costs associated with the commencement of the new Sydney Metro
  • higher operating activity levels experienced in the Health sector resulting in higher visiting medical officer costs, surgical supplies and information management costs
  • higher school operating expenses in Education, mainly relating to teaching cloud tools and purchase of computer equipment.
Health costs remain the highest expense of the State.

The following clusters have the highest expenses as a percentage of total government expenses:

  • Health - 25.8 per cent (24.6 per cent in 2017–18)
  • Education - 20 per cent (18.5 per cent)
  • Transport - 14.7 per cent (17.6 per cent).

Other, mainly relates to Economic Affairs, Housing and Community, Recreation and Culture functions of the State.

Transport expenses have decreased in 2018–19 mainly due to the sale of WestConnex. This is partially offset by costs associated with the new Sydney Metro, which commenced operations from 1 July 2018. The graph highlights annual expenditure by function in 2018–19 compared to 2017–18.

Grants and subsidies increased by $782 million to $11.7 billion.

This was mainly due to:

  • the $239 million Emergency Drought Relief Package
  • a $226 million increase in funding to the Human Services sector to deliver key election commitments, including 5,000 more nurses and midwives
  • $123 million in funding for sporting facilities and creating NSW Centre's of Excellence.

Assets grew by $26.7 billion to $468 billion in 2018–19    

Overall, the States total assets increased by $26.7 billion to $468 billion in 2018–19. This is a six per cent increase compared to 2017–18. Most of this was due to increases in carrying value of the State’s physical assets and investments.

Valuing the State's physical assets

The State’s physical assets were valued at $352 billion at 30 June 2019.

The State’s physical assets include land and buildings ($166 billion) and infrastructure ($168 billion). The value of the State’s physical assets at 30 June 2018 was restated from $339 billion to $337 billion. The restatement was required to correct errors in the fair value of earthworks previously reported at $7.5 billion and subsequently corrected to $5.4 billion.

Our audits assess the reasonableness and appropriateness of assumptions used to value physical assets. This includes
obtaining an understanding of the valuation methodologies used and judgements made. We also review the completeness of asset registers and the mathematical accuracy of valuation models.

Net movements between years include additions, disposals, depreciation and valuations. The State’s physical assets increased by $15.2 billion compared with 2017–18.

Movement in the State's physical assets

Liabilities increased $28.6 billion to $217.5 billion in 2018–19    

The State relies on actuarial assessments to value its liabilities

Nearly half of the State’s liabilities relate to its employees. They include unfunded superannuation and employee benefits, such as long service and recreation leave.

Valuing these obligations involves complex estimation techniques and significant judgements. Small changes in assumptions can materially impact balances in the financial statements, such as a lower discount rate.

Superannuation obligations rose by $14.3 billion.

The State’s $70.7 billion unfunded superannuation liability represents obligations to past and present employees less the value of assets set aside to meet those obligations. The unfunded superannuation liability rose by $14.3 billion from $56.4 billion at 30 June 2018 to $70.7 billion at 30 June 2019. This was mainly due to a lower discount rate.

Borrowings totalled $79.9 billion at 30 June 2019.

The State’s borrowings of $79.9 billion at 30 June 2019 were $8.6 billion higher than they were at 30 June 2018.

TCorp issues bonds to raise funds for NSW Government agencies. These are actively traded in financial markets, which provides price transparency and liquidity to public sector borrowers and institutional investors. All TCorp bonds are guaranteed by the NSW Government.

The Government manages its debt liabilities through its balance sheet management strategy. The strategy extends to TCorp, which applies an active risk management strategy to the Government’s debt portfolio.

General Government Sector debt has been restructured by replacing shorter-term debt with longer-term debt. This lengthens the portfolio to match liabilities with the funding requirements for infrastructure assets.

Implementing the requirements of new accounting standards will be challenging

Risks to the quality and timeliness of financial reporting

The State and its agencies will be implementing the requirements of new accounting standards shortly. These are likely to have a major impact on the financial positions and operating results of agencies across the sector.

Accounting standards require agencies to assess and disclose where possible, the impact of the new standards in their 2018–19 financial statements.

Our review found agencies needed to do more work on their impact assessments to minimise the risk of errors in the financial statement disclosures. Some agencies disclosed that the new standards would not have a material impact on their reported financial position and performance, but had little evidence to support this.

Each agency is unique and implementing the new standards is not straight forward as many new principles apply. Management judgement is needed to interpret how the principles apply to each agency. As a result, agencies face the following risks and challenges:

  • having the required technical skills in house
  • having accurate data to assess the impacts
  • correctly and consistently interpreting the new requirements
  • adequately planning and preparing for their application
  • implementing new systems to capture the information needed to meet the new reporting obligations.

To help agencies implement the new standards consistently across the sector, Treasury:

  • issued guidance to agencies
  • prepared position papers on proposed accounting treatments
  • provided briefing sessions to agencies
  • mandated which option in the new standards agencies had to adopt on transition.

Key dates

Section 45 of the Public Finance and Audit Act 1983 requires the Auditor-General to perform audits of the financial statements of entities prescribed for the purposes of that section.
The following were prescribed entities as at 30 June 2019:

Entity/Fund Latest financial statements audited Type of audit opinion issued
Agricultural Scientific Collections Trust 30 June 2019 Unmodified
AustLII Foundation Limited 31 December 2018 Unmodified
Belgenny Farm Agricultural Heritage Centre Trust 30 June 2019 Unmodified
The Brett Whiteley Foundation 30 June 2019 Unmodified
Buroba Pty Ltd 30 June 2018* Unmodified
C. B. Alexander Foundation 30 June 2018 Unmodified
City West Housing Pty Ltd 30 June 2019 Unmodified
The Commissioner for Uniform Legal Services Regulation 30 June 2019 N/A (a)
Cowra Japanese Garden Maintenance Foundation Limited 31 March 2019 Unmodified
Cowra Japanese Garden Trust 31 March 2019 Unmodified
Crown Employees (NSW Fire Brigades Firefighting Staff Death and Disability) Superannuation Fund 30 June 2019 Unmodified
Eif Pty Limited 30 June 2019 Unmodified
Energy Investment Fund 30 June 2019 Unmodified
Central Coast Council Water Supply Authority (formerly Gosford City and Wyong City Council Water Supply Authorities) 30 June 2018 Unmodified
Home Building Compensation Fund 30 June 2019 Unmodified
The funds for the time being under the management of the New South Wales Treasury Corporation, as trustee 30 June 2019 Unmodified
The Illawarra Health and Medical Research Institute Limited 30 June 2019 Unmodified
The Legal Services Council 30 June 2019 Unmodified
Macquarie University Professorial Superannuation Scheme 30 June 2019 Unmodified
Planning Ministerial Corporation 30 June 2019 Unmodified
Corporation Sole 'Minister administering the Heritage Act 1977' (a corporation) 30 June 2019 Unmodified
National Art School 31 December 2018 Unmodified
NSW Fire Brigades Superannuation Pty Limited 30 June 2019 Unmodified
Parliamentary Contributory Superannuation Fund 30 June 2019 Unmodified
Sydney Education Broadcasting Limited 31 December 2018 Unmodified
The superannuation fund amalgamated under the Superannuation Administration Act 1991 and continued to be amalgamated under the Superannuation Administration 30 June 2019 Unmodified
Act 1996 (known as the SAS Trustee Corporation Pooled Fund) 30 June 2019 Unmodified
The trustees for the time being of each superannuation scheme established by a trust deed as referred to in section 127 of the Superannuation Administration Act 1996 30 June 2019 Unmodified
The Art Gallery of New South Wales Foundation 30 June 2019 Unmodified
Trustee of the Home Purchase Assistance Fund 30 June 2019 Unmodified
Trustees of the Farrer Memorial Research Scholarship Fund 31 December 2018 Unmodified
United States Studies Centre 31 December 2018 Unmodified
Universities Admissions Centre (NSW and ACT) Pty Limited 30 June 2018 Unmodified
University of Sydney Professorial Superannuation System 31 December 2018 Unmodified
Valley Commerce Pty Ltd 30 June 2018* Unmodified
     
(a) Included as part of the Legal Services Council.
*Entities exempt from preparing financial statements at 30 June 2019.
aa


 

Published

Actions for Transport Access Program

Transport Access Program

Transport
Infrastructure
Project management
Service delivery

The following report is available in an Easy English version that is intended to meet the needs of some people with lower literacy skills, some people with an intellectual disability and some people from different cultural backgrounds.

View the Easy English version of the Transport Access Program report

Transport for NSW’s process for selecting and prioritising projects for the third stage of its Transport Access Program balanced compliance with national disability standards with broader customer outcomes. Demographics, deliverability and value for money were also considered. However, Transport for NSW does not know the complete scope of work required for full compliance, limiting its ability to demonstrate that its approach is effective, according to a report released today by the Auditor-General for New South Wales, Margaret Crawford.

Access to transport is critical to ensuring that people can engage in all aspects of community life, including education, employment and recreation. People with disability can encounter barriers when accessing public transport services. In 2015, there were 1.37 million people living with disability in New South Wales.

Accessible public transport is about more than physical accessibility. It also means barrier-free access for people who have vision, hearing or cognitive impairments. All users, not just people with disability, benefit from improvements to the accessibility and inclusiveness of transport services. 

Transport for NSW has an obligation under Australian Government legislation to provide accessible services to people with disabilities in a manner which is not discriminatory. Under the Disability Standards for Accessible Public Transport 2002 (the DSAPT - an instrument of the Disability Discrimination Act 1992 (the Act) (Commonwealth)), there is a requirement to modify and develop new infrastructure, means of transport and services to provide access for people with disabilities. All public transport operators are required to ensure that at least 90 per cent of their networks met DSAPT by December 2017 and the networks will need to be 100 per cent compliant with all parts of the standards by 31 December 2022. Trains are not required to be fully compliant with DSAPT until December 2032. 

The Transport Access Program (TAP) is Transport for NSW's largest program with a specific focus on improving access to public transport for people with disability. The TAP is a series of projects to upgrade existing public transport infrastructure across four networks: Sydney Trains, Intercity Trains, Regional Trains and Sydney Ferries. Transport for NSW established the TAP as a rolling program and, to date, it has delivered the first tranche of TAP (TAP 1) and is completing the final projects for the second tranche (TAP 2). NSW budget papers estimate that by 30 June 2018, Transport for NSW had spent $1.2 billion in the TAP since its commencement in 2011-12.

After the completion of TAP 1 and TAP 2 (as well as through other transport infrastructure programs), Transport for NSW estimates that 58.5 per cent of the Sydney Trains, Regional Trains and Intercity Trains networks, and 66 per cent of the Sydney Ferries network, will be accessible. To close the significant gap in compliance with the DSAPT target, the objective for TAP 3 is ‘to contribute to Disability Discrimination Act 1992 related targets through DSAPT compliance upgrades’. 

The audit assessed whether Transport for NSW has an effective process to select and prioritise projects as part of the TAP, with a specific focus on the third tranche of TAP funding.

In August 2018, at the commencement of this audit, Transport for NSW intended to complete the selection of projects for the TAP 3 final business case in December 2018. Transport for NSW advise that it now intends to complete the development stage and final business case in the first quarter of 2019, prior to the final investment decision of the TAP program. This report is based on the TAP 3 strategic business case and information provided by Transport for NSW up to December 2018.

Conclusion
Transport for NSW’s process for selecting and prioritising projects for TAP 3 balanced DSAPT compliance goals with broader customer outcomes. It also considered demographics, deliverability and value for money. However, Transport for NSW does not know the complete scope of work required for full DSAPT compliance, and this limits its ability to demonstrate that its approach is effective. 
Transport for NSW has applied most of the external review recommendations from previous funding rounds to the implementation of the third round of TAP funding (TAP3), with positive results. Changes made include a clear objective for TAP 3 to focus on improving compliance, improved governance arrangements, and better consideration of deliverability and design during project planning. 
Through TAP 3, Transport for NSW is also trying to better address disability access in a way that balances DSAPT compliance with other considerations - such as population demographics, access to services and value for money. Transport for NSW developed an objective prioritisation and selection methodology to assess projects for TAP 3 funding. 
Transport for NSW cannot quantify the work needed to meet DSAPT compliance targets across the rail and ferry networks as it has not completed a comprehensive audit of compliance. This information is needed to ensure the effective targeting of funding, and to measure the contribution of TAP 3 work to meeting the DSAPT compliance targets. Instead, Transport for NSW has undertaken a phased approach to completing a comprehensive audit of compliance across the networks, with a focus on first assessing compliance at locations that are not wheelchair accessible. This creates two problems. First, Transport for NSW does not know the complete scope of work required to achieve DSAPT compliance. Second, not all wheelchair accessible locations fully meet DSAPT standards.
Transport for NSW's proposed communication plan for the schedule of TAP 3 funded works does not align with its Disability Inclusion Action Plan 2018-2022. The Disability Inclusion Action Plan commits Transport for NSW to providing a full list of stations and wharves to be upgraded with their estimated time of construction when the next round of funding, TAP 3, is announced. Given the long timeframes associated with improving transport infrastructure, this information is important as it allows people to make informed decisions about where they live, work or study. Instead, Transport for NSW plans to communicate information to customers on a project by project basis.

In 2015, there were 1.37 million people living with disability in New South Wales. Access to transport is critical to ensuring that people can engage in all aspects of community life, including education, employment and recreation. People with disability can encounter barriers when accessing public transport services. 

The social model of disability, outlined in the United Nations Convention on the Rights of Persons with Disabilities, views people with disability as not disabled by their impairment but by the barriers in the community and environment that restrict their full and effective participation in society on an equal basis with others. 

Accessible public transport is more than the provision of physical access to premises and conveyances, it provides barrier-free access for people who have vision, hearing or cognitive impairments. All users, not just people with disability, benefit from improvements to the accessibility and inclusiveness of transport services.

According to the Australian Bureau of Statistics, the main types of difficulties experienced by people with disability when using public transport relate to steps (39.9 per cent), difficulty getting to stops and stations (25 per cent), fear and anxiety (23.3 per cent) and lack of seating or difficulty standing (20.7 per cent).

Transport for NSW has a Disability Inclusion Action Plan (the Action Plan) 2018-2022 that sets an overall framework for planning, delivering and reporting on initiatives to increase accessibility of the transport network. It covers all elements of the journey experienced when using public transport, including journey planning, staff training, customer services and interaction between the physical environment and modes of transport. Appendix five outlines the guiding principles of the Action Plan.

Transport for NSW's Transport Social Policy branch developed the Action Plan in consultation with internal and external stakeholders. The director of the Transport Social Policy branch is a member of the TAP executive steering committee, which supports alignment between the Action Plan and TAP.

Transport for NSW's Disability Inclusion Action Plan describes a customer focussed approach to accessibility

One of the guiding principles of the Action Plan is ‘intelligent compliance’. Transport for NSW describes this as compliance that prioritises customer-focused outcomes over a narrow focus on legal compliance with accessibility standards. As well as being compliant, infrastructure should be practical, usable, fit for purpose and convenient. 

The TAP prioritisation and selection methodology reflects Transport for NSW’s focus on intelligent compliance. We consider this a reasonable approach as had Transport for NSW focussed exclusively on achieving compliance with the DSAPT targets by upgrading the most affordable infrastructure, some locations, that are used by more customers, would remain inaccessible to people with disability. However, this approach should not be seen as an alternative to Transport for NSW meeting its DSAPT compliance obligations.

TAP program staff consult with the Accessible Transport Advisory Committee

The Accessible Transport Advisory Committee (ATAC) has representatives from disability and ageing organisations, who provide expert guidance to Transport for NSW on access and inclusion. The ATAC provide guidance and feedback on projects and project solutions, including user testing where appropriate. TAP program staff provide regular updates at ATAC meetings, which include briefings on progress. The ATAC also provides feedback and suggestions to TAP program staff, which is considered and sometimes included in current and future projects.For example, in March 2017 the TAP program team briefed the ATAC on the challenges with respect to a number of ferry wharves and sought support for DSAPT exemptions proposed in the TAP 3 strategic business case.

Case study: Feedback on Braille lettering for lift buttons
In June 2018, the Program team sought feedback on a variety of lift button options to improve accessibility on future TAP projects. In September 2018, during the ATAC meeting attended by the Audit Office, the program team sought feedback on the standard designs for TAP 3. Some ATAC members noted that the standard design included Braille lettering on the lift buttons, and that this was not good practice because people can accidently press the button while reading it. As a result, Transport for NSW are incorporating this feedback into design requirements for the lifts for TAP 3, which will consider larger buttons, clearer Braille and Braille signage adjacent to the button.

Transport for NSW has not briefed the Advisory Committee on the outcome of the prioritisation and selection process

TAP program staff briefed the Advisory Committee about the prioritisation and selection methodology, after the Minister approved it in 2016. However, Transport for NSW have not briefed or consulted the Advisory Committee on the outcome of the prioritisation process. Infrastructure NSW noted this issue during its review of the strategic business case. 

Transport for NSW advised us that it established the ATAC as an advisory group, and that Transport for NSW does not disclose sensitive information to it. Transport for NSW intends to share the outcome of the prioritisation process following the completion of the TAP 3 development stage and final investment decision.

The TAP communication plan does not fully meet the requirements of the Disability Inclusion Action Plan

The Disability Inclusion Action Plan includes an action item to ‘provide a listing of stations and wharves to be upgraded with estimated time of construction as each new tranche of the Transport Access Program is announced’ The TAP Communication Plan that we reviewed does not include this provision instead focussing on communication on a per project basis. Given the long timeframes associated with improving transport infrastructure, this information is important as it allows people to make informed decisions about where they live, work or study.

Published

Actions for Newcastle Urban Transformation and Transport Program

Newcastle Urban Transformation and Transport Program

Transport
Planning
Compliance
Infrastructure
Management and administration
Procurement
Project management

The urban renewal projects on former railway land in the Newcastle city centre are well targeted to support the objectives of the Newcastle Urban Transformation and Transport Program (the Program), according to a report released today by the Auditor-General for New South Wales, Margaret Crawford. The planned uses of the former railway land achieve a balance between the economic and social objectives of the Program at a reasonable cost to the government. However, the evidence that the cost of the light rail will be justified by its contribution to the Program is not convincing.

The Newcastle Urban Transformation and Transport Program (the Program) is an urban renewal and transport program in the Newcastle city centre. The Hunter and Central Coast Development Corporation (HCCDC) has led the Program since 2017. UrbanGrowth NSW led the Program from 2014 until 2017. Transport for NSW has been responsible for delivering the transport parts of the Program since the Program commenced. All references to HCCDC in this report relate to both HCCDC and its predecessor, the Hunter Development Corporation. All references to UrbanGrowth NSW in this report relate only to its Newcastle office from 2014 to 2017.

This audit had two objectives:

  1. To assess the economy of the approach chosen to achieve the objectives of the Program.
  2. To assess the effectiveness of the consultation and oversight of the Program.

We addressed the audit objectives by answering the following questions:

a) Was the decision to build light rail an economical option for achieving Program objectives?
b) Has the best value been obtained for the use of the former railway land?
c) Was good practice used in consultation on key Program decisions?
d) Did governance arrangements support delivery of the program?

Conclusion
1. The urban renewal projects on the former railway land are well targeted to support the objectives of the Program. However, there is insufficient evidence that the cost of the light rail will be justified by its contribution to Program objectives.

The planned uses of the former railway land achieve a balance between the economic and social objectives of the Program at a reasonable cost to the Government. HCCDC, and previously UrbanGrowth NSW, identified and considered options for land use that would best meet Program objectives. Required probity processes were followed for developments that involved financial transactions. Our audit did not assess the achievement of these objectives because none of the projects have been completed yet.

Analysis presented in the Program business case and other planning documents showed that the light rail would have small transport benefits and was expected to make a modest contribution to broader Program objectives. Analysis in the Program business case argued that despite this, the light rail was justified because it would attract investment and promote economic development around the route. The Program business case referred to several international examples to support this argument, but did not make a convincing case that these examples were comparable to the proposed light rail in Newcastle.

The audited agencies argue that the contribution of light rail cannot be assessed separately because it is a part of a broader Program. The cost of the light rail makes up around 53 per cent of the total Program funding. Given the cost of the light rail, agencies need to be able to demonstrate that this investment provides value for money by making a measurable contribution to the Program objectives.

2. Consultation and oversight were mostly effective during the implementation stages of the Program. There were weaknesses in both areas in the planning stages.

Consultations about the urban renewal activities from around 2015 onward followed good practice standards. These consultations were based on an internationally accepted framework and met their stated objectives. Community consultations on the decision to close the train line were held in 2006 and 2009. However, the final decision in 2012 was made without a specific community consultation. There was no community consultation on the decision to build a light rail.

The governance arrangements that were in place during the planning stages of the Program did not provide effective oversight. This meant there was not a single agreed set of Program objectives until 2016 and roles and responsibilities for the Program were not clear. Leadership and oversight improved during the implementation phase of the Program. Roles and responsibilities were clarified and a multi-agency steering committee was established to resolve issues that needed multi-agency coordination.
The light rail is not justified by conventional cost-benefit analysis and there is insufficient evidence that the indirect contribution of light rail to achieving the economic development objectives of the Program will justify the cost.
Analysis presented in Program business cases and other planning documents showed that the light rail would have small transport benefits and was expected to make a modest contribution to broader Program objectives. Analysis in the Program business case argued that despite this, the light rail was justified because it would attract investment and promote economic development around the route. The Program business case referred to several international examples to support this argument, but did not make a convincing case that these examples were comparable to the proposed light rail in Newcastle.
The business case analysis of the benefits and costs of light rail was prepared after the decision to build light rail had been made and announced. Our previous reports, and recent reports by others, have emphasised the importance of completing thorough analysis before announcing infrastructure projects. Some advice provided after the initial light rail decision was announced was overly optimistic. It included benefits that cannot reasonably be attributed to light rail and underestimated the scope and cost of the project.
The audited agencies argue that the contribution of light rail cannot be assessed separately because it is part of a broader Program. The cost of the light rail makes up around 53 per cent of the total Program funding. Given the high cost of the light rail, we believe agencies need to be able to demonstrate that this investment provides value for money by making a measurable contribution to the Program objectives.

Recommendations
For future infrastructure programs, NSW Government agencies should support economical decision-making on infrastructure projects by:
  • providing balanced advice to decision makers on the benefits and risks of large infrastructure investments at all stages of the decision-making process
  • providing scope and cost estimates that are as accurate and complete as possible when initial funding decisions are being made
  • making business cases available to the public.​​​​​​
The planned uses of the former railway land achieve a balance between the economic and social objectives of the Program at a reasonable cost to the government.

The planned uses of the former railway land align with the objectives of encouraging people to visit and live in the city centre, creating attractive public spaces, and supporting growth in employment in the city. The transport benefits of the activities are less clear, because the light rail is the major transport project and this will not make significant improvements to transport in Newcastle.

The processes used for selling and leasing parts of the former railway land followed industry standards. Options for the former railway land were identified and assessed systematically. Competitive processes were used for most transactions and the required assessment and approval processes were followed. The sale of land to the University of Newcastle did not use a competitive process, but required processes for direct negotiations were followed.

Recommendation
By March 2019, the Hunter and Central Coast Development Corporation should:
  • work with relevant stakeholders to explore options for increasing the focus on the heritage objective of the Program in projects on the former railway land. This could include projects that recognise the cultural and industrial heritage of Newcastle.
Consultations about the urban renewal activities followed good practice standards, but consultation on transport decisions for the Program did not.

Consultations focusing on urban renewal options for the Program included a range of stakeholders and provided opportunities for input into decisions about the use of the former railway land. These consultations received mostly positive feedback from participants. Changes and additions were made to the objectives of the Program and specific projects in response to feedback received. 

There had been several decades of debate about the potential closure of the train line, including community consultations in 2006 and 2009. However, the final decision to close the train line was made and announced in 2012 without a specific community consultation. HCCDC states that consultation with industry and business representatives constitutes community consultation because industry representatives are also members of the community. This does not meet good practice standards because it is not a representative sample of the community.

There was no community consultation on the decision to build a light rail. There were subsequent opportunities for members of the community to comment on the implementation options, but the decision to build it had already been made. A community and industry consultation was held on which route the light rail should use, but the results of this were not made public. 

Recommendation
For future infrastructure programs, NSW Government agencies should consult with a wide range of stakeholders before major decisions are made and announced, and report publicly on the results and outcomes of consultations. 

The governance arrangements that were in place during the planning stages of the Program did not provide effective oversight. Project leadership and oversight improved during the implementation phase of the Program.

Multi-agency coordination and oversight were ineffective during the planning stages of the Program. Examples include: multiple versions of Program objectives being in circulation; unclear reporting lines for project management groups; and poor role definition for the initial advisory board. Program ownership was clarified in mid-2016 with the appointment of a new Program Director with clear accountability for the delivery of the Program. This was supported by the creation of a multi-agency steering committee that was more effective than previous oversight bodies.

The limitations that existed in multi-agency coordination and oversight had some negative consequences in important aspects of project management for the Program. This included whole-of-government benefits management and the coordination of work to mitigate impacts of the Program on small businesses.

Recommendations
For future infrastructure programs, NSW Government agencies should: 

  • develop and implement a benefits management approach from the beginning of a program to ensure responsibility for defining benefits and measuring their achievement is clear
  • establish whole-of-government oversight early in the program to guide major decisions. This should include:
    • agreeing on objectives and ensuring all agencies understand these
    • clearly defining roles and responsibilities for all agencies
    • establishing whole-of-government coordination for the assessment and mitigation of the impact of major construction projects on businesses and the community.

By March 2019, the Hunter and Central Coast Development Corporation should update and implement the Program Benefits Realisation Plan. This should include:

  • setting measurable targets for the desired benefits
  • clearly allocating ownership for achieving the desired benefits
  • monitoring progress toward achieving the desired benefits and reporting publicly on the results.

Appendix one - Response from agencies    

Appendix two - About the audit

Appendix three - Performance auditing

 

Parliamentary reference - Report number #310 - released 12 December 2018

Published

Actions for Transport 2018

Transport 2018

Transport
Asset valuation
Compliance
Financial reporting
Infrastructure
Management and administration
Procurement
Risk
Service delivery
Workforce and capability

The Auditor-General for New South Wales, Margaret Crawford released her report today on key observations and findings from the 30 June 2018 financial statement audits of agencies in the Transport cluster. Unqualified audit opinions were issued for all agencies' financial statements. However, assessing the fair value of the broad range of transport related assets creates challenges.

This report analyses the results of our audits of financial statements of the Transport cluster for the year ended 30 June 2018. The table below summarises our key observations.

This report provides Parliament and other users of the Transport cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Transport cluster for 2018.

Observation Conclusions and recommendations
2.1 Quality of financial reporting
Unqualified audit opinions were issued for all agencies' financial statements Sufficient audit evidence was obtained to conclude the financial statements were free of material misstatement.
2.2 Key accounting issues
Valuation of assets continues to create challenges. Although agencies complied with the requirements of the accounting standards and Treasury policies on valuations, we identified some opportunities for improvements at RMS.

RMS incorporated data from its asset condition assessments for the first time in the valuation methodology which improved the valuation outcome. Overall, we were satisfied with the valuation methodology and key assumptions, but we noted some deficiencies in the asset data in relation to asset component unit rates and old condition data for some components of assets. 

Also, a bypass and tunnel were incorrectly excluded from RMS records and valuation process since 2013. This resulted in an increase for these assets’ value by $133 million.

The valuation inputs for Wetlands and Moorings were revised this year to better reflect the assets' characteristics resulting in a $98.0 million increase.

2.3 Timeliness of financial reporting
Residual Transport Corporation did not submit its financial statements by the statutory reporting deadline. Residual Transport Corporation remained a dormant entity with no transactions for the year ended 30 June 2018.
With the exception of Residual Transport Corporation, all agencies completed early close procedures and submitted financial statements within statutory timeframes. Early close procedures allow financial reporting issues and risks to be addressed early in the reporting and audit process.
2.4 Financial sustainability
NSW Trains and the Chief Investigator of the Office of Transport Safety Investigations reported negative net assets of $75.7 million and $89,000 respectively at 30 June 2018.  NSW Trains and the Chief Investigator of the Office of Transport Safety Investigations continue to require letters of financial support to confirm their ability to pay liabilities as they fall due. 
2.5 Passenger revenue and patronage
Transport agencies revenue growth increased at a higher rate than patronage. Public transport passenger revenue increased by $114 million (8.3 per cent) in 2017–18, and patronage increased by 37.1 million (5.1 per cent) across all modes of transport based on data provided by TfNSW. 
Negative balance Opal Cards resulted in $3.8 million in revenue not collected in 2017–18 and $7.8 million since the introduction of Opal. A total of 1.1 million Opal cards issued since its introduction have negative balances. Transport for NSW advised it is liaising with the ticketing vendor to implement system changes and are investigating other ways to reduce the occurrences.
2.6 Cost recovery from public transport users
Overall cost recovery from users has decreased. Overall cost recovery from public transport users (on rail and bus services by STA) decreased from 23.2 per cent to 22.4 per cent between 2016–17 and 2017–18. The main reason for the decrease is due to expenditure increasing at a faster rate than revenue in 2017–18.


 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our observations and insights from:

  • our financial statement audits of agencies in the Transport cluster for 2018
  • the areas of focus identified in the Audit Office annual work program.

The Audit Office Annual Work Program provides a summary of all audits to be conducted within the proposed time period as well as detailed information on the areas of focus for each of the NSW Government clusters. 

Observation Conclusions and recommendations
3.1 Internal controls 
There was an increase in findings on internal controls across the Transport cluster. Key themes related to information technology, employee leave entitlements and asset management. Eighteen per cent of all issues were repeat issues.
3.2 Audit Office Annual work program
The Transport cluster wrote-off over $200 million of assets which were replaced by new assets or technology.

Majority of this write-off was recognised by RMS, with $199 million relating to the write-off of existing assets which have been replaced during the year. 

RailCorp is expected to convert to TAHE from 1 July 2019. Several working groups are considering different aspects of the TAHE transition including its status as a for-profit Public Trading Enterprise and which assets to transfer to TAHE. We will continue to monitor developments on TAHE for any impact to the financial statements.
RMS' estimated maintenance backlog at 30 June 2018 of $3.4 billion is lower than last year. Sydney Trains' estimated maintenance backlog at 30 June 2018 increased by 20.6 per cent to $434 million. TfNSW does not quantify its backlog maintenance. TfNSW advised it is liaising with Infrastructure NSW to develop a consistent definition of maintenance backlog across all transport service providers. 
Not all agencies monitor unplanned maintenance across the Transport cluster. Unplanned maintenance can be more expensive than planned maintenance. TfNSW should develop a consistent approach to define, monitor and track unplanned maintenance across the cluster.

This chapter outlines certain service delivery outcomes for 2017–18. The data on activity levels and performance is provided by Cluster agencies. The Audit Office does not have a specific mandate to audit performance information. Accordingly, the information in this chapter is unaudited. 

We report this information on service delivery to provide additional context to understand the operations of the Transport cluster and to collate and present service information for different modes of transport in one report. 

In our recent performance audit, Progress and measurement of Premier's Priorities, we identified 12 limitations of performance measurement and performance data. We recommended that the Department of Premier and Cabinet ensure that processes to check and verify data are in place for all agency data sources.

Published

Actions for Internal Controls and Governance 2018

Internal Controls and Governance 2018

Education
Community Services
Finance
Health
Industry
Justice
Planning
Premier and Cabinet
Transport
Treasury
Whole of Government
Environment
Compliance
Cyber security
Financial reporting
Fraud
Information technology
Internal controls and governance
Management and administration
Procurement
Project management

The Auditor-General for New South Wales Margaret Crawford found that as NSW state government agencies’ digital footprint increases they need to do more to address new and emerging information technology (IT) risks. This is one of the key findings to emerge from the second stand-alone report on internal controls and governance of the 40 largest NSW state government agencies.

This report analyses the internal controls and governance of the 40 largest agencies in the NSW public sector for the year ended 30 June 2018.

This report covers the findings and recommendations from our 2017–18 financial audits that relate to internal controls and governance at the 40 largest agencies (refer to Appendix three) in the NSW public sector.

This report offers insights into internal controls and governance in the NSW public sector

This is our second report dedicated to internal controls and governance at NSW State Government agencies. The report provides insights into the effectiveness of controls and governance processes in the NSW public sector by:

  • highlighting the potential risks posed by weaknesses in controls and governance processes
  • helping agencies benchmark the adequacy of their processes against their peers
  • focusing on new and emerging risks, and the internal controls and governance processes that might address those risks.

Without strong governance systems and internal controls, agencies increase the risks associated with effectively managing their finances and delivering services to citizens. The way agencies deliver services increasingly relies on contracts and partnerships with the private sector. Many of these arrangements deliver front line services, but others provide less visible back office support. For example, an agency may rely on an IT service provider to manage a key system used to provide services to the community. The contract and service level agreements are only truly effective where they are actively managed to reduce risks to continuous quality service delivery, such as interruptions caused by system outages, cyber security attacks and data security breaches.

Our audits do not review all aspects of internal controls and governance every year. We select a range of measures, and report on those that present heightened risks for agencies to mitigate. This report divides these into the following five areas:

  1. Internal control trends
  2. Information technology (IT), including IT vendor management
  3. Transparency and performance reporting
  4. Management of purchasing cards and taxis
  5. Fraud and corruption control.

The findings in this report should not be used to draw conclusions on the effectiveness of individual agency control environments and governance arrangements. Specific financial reporting, controls and service delivery comments are included in the individual 2018 cluster financial audit reports, which will be tabled in Parliament from November to December 2018.

The focus of the report has changed since last year

Last year's report topics included asset management, ethics and conduct, and risk management. We are reporting on new topics this year. We plan to introduce new topics and re-visit our previous topics in subsequent reports on a cyclical basis. This will provide a baseline against which to measure the NSW public sectors’ progress in implementing appropriate internal controls and governance processes to mitigate existing, new and emerging risks in the public sector.

Agencies selected for the volume account for 95 per cent of the state's expenditure

While we have covered only 40 agencies in this report, those selected are a large enough group to identify common issues and insights. They represent about 95 per cent of total expenditure for all NSW public sector agencies.

Internal controls are processes, policies and procedures that help agencies to:

  • operate effectively and efficiently
  • produce reliable financial reports
  • comply with laws and regulations
  • support ethical government.

This chapter outlines the overall trends for agency controls and governance issues, including the number of findings, level of risk and the most common deficiencies we found across agencies. The rest of this volume presents this year’s controls and governance findings in more detail.

Observation Conclusions and recommendations
2.1 High risk findings
We found six high risk findings (seven in 2016–17), one of which was repeated from both last year and 2015–16. Recommendation: Agencies should reduce risk by addressing high risk internal control deficiencies as a priority.
2.2 Common findings
We found several internal controls and governance findings common to multiple agencies. Conclusion: Central agencies or the lead agency in a cluster can play a lead role in helping ensure agency responses to common findings are consistent, timely, efficient and effective.
2.3 New and repeat findings
Although internal control deficiencies decreased over the last four years, this year has seen a 42 per cent increase in internal control deficiencies. The increase in new IT control deficiencies and repeat IT control deficiencies signifies an emerging risk for agencies.
IT control deficiencies feature in this increase, having risen by 63 per cent since last year. The number of repeat IT control deficiencies has doubled and is driven by the increasing digital footprint left by agencies as government prioritises on-line interfaces with citizens, and the number of transactions conducted through digital channels increases

Recommendation: Agencies should reduce IT risks by:

  • assigning ownership of recommendations to address IT control deficiencies, with timeframes and actions plans for implementation
  • ensuring audit and risk committees and agency management regularly monitor the implementation status of recommendations.

 

Government agencies’ financial reporting is now heavily reliant on information technology (IT). IT is also increasingly important to the delivery of agency services. These systems often provide the data to help monitor the efficiency and effectiveness of agency processes and services they deliver. Our audits reviewed whether agencies have effective controls in place to manage both key financial systems and IT service contracts.

Observation Conclusions and recommendations
3.1 Management of IT vendors
Contract management framework 
Although 87 per cent of agencies have a contract management policy to manage IT vendors, one fifth require review.
 

Conclusion: Agencies can more effectively manage IT vendor contracts by developing policies and procedures to ensure vendor management frameworks are kept up to date, plans are in place to manage vendor performance and risk, and compliance with the framework is monitored by:

  • internal audit focusing on key contracting activities
  • experienced officers who are independent of contract administration performing spot checks or peer reviews
  • targeted analysis of data in contract registers.
Contract risk management
Forty-one per cent of agencies are not using contract management plans and do not assess contract risks. Half of the agencies that did assess contract risks, had not updated the risk assessments since the commencement of the contract.
 
Conclusion: Instead of applying a 'set and forget' approach in relation to management of contract risks, agencies should assess risk regularly and develop a plan to actively manage identified risks throughout the contract lifecycle - from negotiation and commencement, to termination.

Performance management
Eighty-six per cent of agencies meet with vendors to discuss performance. 

Only 24 per cent of agencies sought assurance about the accuracy of vendor reporting against KPIs, yet sixty-seven per cent of the IT contracts allow agencies to determine performance based payments and/or penalise underperformance.

Conclusion: Agencies are monitoring IT vendor performance, but could improve outcomes and more effectively manage under-performance by:

  • a more active, rigorous approach to both risk and performance management
  • checking the accuracy of vendor reporting against those KPIs and where appropriate seeking assurance over their accuracy
  • invoking performance based payments clauses in contracts when performance falls below agreed standards.

Transitioning services
Forty-three per cent of the IT vendor contracts did not contain transitioning-out provisions.

Where IT vendor contracts do make provision for transitioning-out, only 28 per cent of agencies have developed a transitioning-out plan with their IT vendor.

Conclusion: Contract transition/phase out clauses and plans can mitigate risks to service disruption, ensure internal controls remain in place, avoid unnecessary costs and reduce the risk of 'vendor lock-in'.
Contract Registers
Eleven out of forty agencies did not have a contract register, or have registers that are not accurate and/or complete.

Conclusion: A contract register helps to manage an agency’s compliance obligations under the Government Information (Public Access) Act 2009 (the GIPA Act). However, it also helps agencies more effectively manage IT vendors by:

  • monitoring contract end dates and contract extensions, and commence new procurements through their central procurement teams in a timely manner
  • managing their contractual commitments, budgeting and cash flow requirements.

Recommendation: Agencies should ensure their contract registers are complete and accurate so they can more effectively govern contracts and manage compliance obligations.

3.2 IT general controls
Governance
Ninety-five per cent of agencies have established policies to manage key IT processes and functions within the agency, with ten per cent of those due for review.
 
Conclusion: Regular review of IT policies ensures risks are considered and appropriate strategies and procedures are implemented to manage these risks on a consistent basis. An absence of policies can lead to ad-hoc responses to risks, and failure to consider emerging IT risks and changes to agency IT environments. 

User access administration
Seventy-two deficiencies were identified related to user access administration, including:

  • thirty issues related to granting user access across 43 per cent of agencies
  • sixteen issues related to removing user access across 30 per cent of agencies
  • twenty-six issues related to periodic reviews of user access across 50 per cent of agencies.
Recommendation: Agencies should strengthen the administration of user access to prevent inappropriate access to key systems.
Privileged access
Forty per cent of agencies do not periodically review logs of the activities of privileged users to identify suspicious or unauthorised activities.

Recommendation: Agencies should:

  • review the number of, and access granted to privileged users, and assess and document the risks associated with their activities
  • monitor user access to address risks from unauthorised activity.
Password controls
Twenty-three per cent of agencies did not comply with their own policy on password parameters.
Recommendation: Agencies should ensure IT password settings comply with their password policies.
Program changes
Fifteen per cent of agencies had deficient IT program change controls mainly related to segregation of duties and authorisation and testing of IT program changes prior to deployment.
Recommendation: Agencies should maintain appropriate segregation of duties in their IT functions and test system changes before they are deployed.

 

This chapter outlines our audit observations, conclusions and recommendations from our review of how agencies reported their performance in their 2016–17 annual reports. The Annual Reports (Statutory Bodies) Regulation 2015 and Annual Reports (Departments) Regulation 2015 (annual reports regulation) currently prescribes the minimum requirements for agency annual reports.

Observation Conclusion or recommendation
4.1 Reporting on performance

Only 57 per cent of agencies linked reporting on performance to their strategic objectives.

The use of targets and reporting performance over time was limited and applied inconsistently.

Conclusion: There is significant disparity in the quality and consistency of how agencies report on their performance in their annual reports. This limits the reliability and transparency of reported performance information.

Agencies could improve performance reporting by clearly linking strategic objectives to reported outcomes, and reporting on performance against targets over time. NSW Treasury may need to provide more guidance to agencies to support consistent and high-quality performance reporting in annual reports.

There is no independent assurance that the performance metrics agencies report in their annual reports are accurate.

Prior performance audits have noted issues related to the collection of performance information. For example, our 2016 Report on Red Tape Reduction highlighted inaccuracies in how the dollar-value of red tape reduction had been reported.

Conclusion: The ability of Parliament and the public to rely on reported information as a relevant and accurate reflection of an agency's performance is limited.

The relevance and accuracy of performance information is enhanced when:

  • policies and guidance support the consistent and accurate collection of data
  • internal review processes and management oversight are effective
  • independent review processes are established to provide effective challenge to the assumptions, judgements and methodology used to collect the reported performance information.
4.2 Reporting on reports

Agency reporting on major projects does not meet the requirements of the annual reports regulation.

Forty-seven per cent of agencies did not report on costs to date and estimated completion dates for major works in progress. Of the 47 per cent of agencies that reported on major works, only one agency reported detail about significant cost overruns, delays, amendments, deferments or cancellations.

NSW Treasury produce an annual report checklist to help agencies comply with their annual report obligations.

Recommendation: Agencies should comply with the annual reports regulation and report on all mandatory fields, including significant cost overruns and delays, for their major works in progress.

The information the annual reports regulation requires agencies to report deals only with major works in progress. There is no requirement to report on completed works.

Sixteen of 30 agencies reported some information on completed major works.

Conclusion: Agencies could improve their transparency if they reported, or were required to report:

  • on both works in progress and projects completed during the year
  • actual costs and completion dates, and forecast completion dates for major works, against original and revised budgets and original expected completion dates
  • explanations for significant cost overruns, delays and key project performance metrics.

 

This chapter outlines our audit observations, conclusions and recommendations, arising from our review of agency preventative and detective controls over purchasing card and taxi use for 2017–18.

Observation Conclusion or recommendation
5.1 Management of purchasing cards
Volume of credit card spend
Purchasing card expenditure has increased by 76 per cent over the last four years in response to a government review into the cost savings possible from using purchasing cards for low value, high volume procurement.
 
Conclusion: The increasing use of purchasing cards highlights the importance of an effective framework for the use and management of purchasing cards.
Policy framework
We found all agencies that held purchasing cards had a policy in place, but 26 per cent of agencies have not reviewed their purchasing card policy by the scheduled date, or do not have a scheduled revision date stated within their policy.
Recommendation: Agencies should mitigate the risks associated with increased purchasing card use by ensuring policies and purchasing card frameworks remain current and compliant with the core requirements of TPP 17–09 'Use and Management of NSW Government Purchasing Cards'.
Preventative controls
We found that:
  • all agencies maintained purchasing card registers
  • seventy-six per cent provided training to cardholders prior to being issued with a card
  • eighty-nine per cent appointed a program administrator, but only half of these had clearly defined roles and responsibilities
  • thirty-two per cent of agencies place merchant blocks on purchasing cards
  • forty-seven per cent of agencies place geographic restrictions on purchasing cards.

Agencies have designed and implemented preventative controls aimed at deterring the potential misuse of purchasing cards.

Conclusion: Further opportunities exist for agencies to better control the use of purchasing cards, such as:

  • updating purchasing card registers to contain all mandatory fields required by TPP17–09
  • appointing a program administrator for the agency's purchasing card framework and defining their role and responsibility for the function
  • strengthening preventive controls to prevent misuse.

Detective controls
Ninety-two per cent of agencies have designed and implemented at least one control to monitor purchasing card activity.

Major reviews, such as data analytics (29 per cent of agencies) and independent spot checks (49 per cent of agencies) are not widely used.

Agencies have designed and implemented detective controls aimed at identifying potential misuse of purchasing cards.

Conclusion: More effective monitoring using purchasing card data can provide better visibility over spending activity and can be used to:

  • detect misuse and investigate exceptions
  • analyse trends to highlight cost saving opportunities.
5.2 Management of taxis
Policy framework
Thirteen per cent of agencies have not developed and implemented a policy to manage taxi use. In addition:
  • a further 41 per cent of agencies have not reviewed their policies by the scheduled revision date, or do not have a scheduled revision date
  • more than half of all agencies’ policies do not offer alternative travel options. For example, only 36 per cent of policies promoted the use of general Opal cards.
Conclusion: Agencies can promote savings and provide more options to staff where their taxi use policies:
  • limit the circumstances where taxi use is appropriate
  • offer alternate, lower cost options to using taxis, such as general Opal cards and rideshare.
Detective controls
All agencies approve taxi expenditure by expense reimbursement, purchasing card and Cabcharge, and have implemented controls around this approval process. However, beyond this there is minimal monitoring and review activity, such as data monitoring, independent spot checks or internal audit reviews.
Conclusion: Taxi spend at agencies is not significant in terms of its dollar value, but it is significant from a probity perspective. Agencies can better address the probity risk by incorporating taxi use into a broader purchasing card or fraud monitoring program.

 

Fraud and corruption control is one of the 17 key elements of our governance lighthouse. Recent reports from ICAC into state agencies and local government councils highlight the need for effective fraud control and ethical frameworks. Effective frameworks can help protect an agency from events that risk serious reputational damage and financial loss.

Our 2016 Fraud Survey found the NSW Government agencies we surveyed reported 1,077 frauds over the three year period to 30 June 2015. For those frauds where an estimate of losses was made, the reported value exceeded $10.0 million. The report also highlighted that the full extent of fraud in the NSW public sector could be higher than reported because:

  • unreported frauds in organisations can be almost three times the number of reported frauds
  • our 2015 survey did not include all NSW public sector agencies, nor did it include any NSW universities or local councils
  • fraud committed by citizens such as fare evasion and fraudulent state tax self-assessments was not within the scope of our 2015 survey
  • agencies did not estimate a value for 599 of the 1,077 (56 per cent) reported frauds.

Commissioning and outsourcing of services to the private sector and the advancement of digital technology are changing the fraud and corruption risks agencies face. Fraud risk assessments should be updated regularly and in particular where there are changes in agency business models. NSW Treasury Circular TC18-02 NSW Fraud and Corruption Control Policy now requires agencies develop, implement and maintain a fraud and corruption control framework, effective from 1 July 2018. 

Our Fraud Control Improvement Kit provides guidance and practical advice to help organisations implement an effective fraud control framework. The kit is divided into ten attributes. Three key attributes have been assessed below; prevention, detection and notification systems.

This chapter outlines our audit observations, conclusions and recommendations, arising from our review of agency fraud and corruption controls for 2017–18.

Observation Conclusion or recommendation
6.1 Prevention systems

Prevention systems
Ninety-two per cent of agencies have a fraud control plan in place, 81 per cent maintain a fraud database and 79 per cent report fraud and corruption matters as a standing item on audit and risk committee agendas.

Only 54 per cent of agencies have an employment screening policy and all agencies have IT security policies, but gaps in IT security controls could undermine their policies.

Conclusion: Most agencies have implemented fraud prevention systems to reduce the risk of fraud. However poor IT security along with other gaps in agency prevention systems, such as employment screening practices heightens the risk of fraud and inappropriate use of data.

Agencies can improve their fraud prevention systems by:

  • completing regular fraud risk assessments, embedding fraud risk assessment into their enterprise risk management process and reporting the results of the assessment to the audit and risk committee
  • maintaining a fraud database and reviewing it regularly for systemic issues and reporting a redacted version of the database on the agency's website to inform corruption prevention networks
  • developing policies and procedures for employee screening and benchmarking their current processes against ICAC's publication ‘Strengthening Employment Screening Practices in the NSW Public Sector’
  • developing and maintaining up to date IT security policies and monitoring compliance with the policy.
Twenty-three per cent of agencies were not performing fraud risk assessments and some agency fraud risk assessments may not be as robust as they could be.  Conclusion: Agencies' systems of internal controls may be less effective where new and emerging fraud risks have been overlooked, or known weaknesses have not been rectified.
6.2 Detection systems
Detection systems
Several agencies reported they were developing a data monitoring program, but only 38 per cent of agencies had already implemented a program.
 

Studies have shown data monitoring, whereby entire populations of transactional data are analysed for indicators of fraudulent activity, is one of the most effective methods of early detection. Early detection decreases the duration a fraud remains undetected thereby limiting the extent of losses.

Conclusion: Data monitoring is an effective tool for early detection of fraud and is more effective when informed by a comprehensive fraud risk assessment.

6.3 Notification systems
Notification system
All agencies have notification systems for reporting actual or suspected fraud and corruption. Most agencies provide multiple reporting lines, provide training and publicise options for staff to report actual or suspected fraud and corruption.
Conclusion: Training staff about their obligations and the use of fraud notification systems promotes a fraud-aware culture

 

Published

Actions for State Finances 2018

State Finances 2018

Education
Finance
Community Services
Health
Justice
Industry
Planning
Premier and Cabinet
Transport
Treasury
Whole of Government
Environment
Financial reporting

Pursuant to the Public Finance and Audit Act 1983, I present my Report on State Finances 2018.

I am pleased to once again report that I issued a clear audit opinion on the State’s consolidated financial statements. This demonstrates the Government’s focus on preparing high quality information on the State’s financial position and performance for use by stakeholders.

However, there are two key areas I would like to see addressed to further support the preparation of the State’s financial statements.
Firstly, some complex accounting matters are not being resolved until late in the financial reporting cycle. This has contributed to an increase in the number of errors in the financial statements key agencies are submitting for audit, particularly around assessing the value of physical assets. Better planning and earlier resolution of these matters would lead to more efficient processes.

Secondly, the State needs to implement five new accounting standards over the next two years. Agencies will need to devote significant resources and effort to collect the necessary information and assess the impact at the whole of government level. I will work with Treasury and relevant agencies to help them improve quality assurance controls over their financial reporting.

Throughout 2017-18 my office worked with Treasury on reforms to improve financial governance, budgeting and reporting arrangements across the sector.

The Government Sector Finance Bill 2018 passed both houses of Parliament in June 2018. However, the Legislative Council returned other proposed changes to the Public Finance and Audit Act 1983 to the Legislative Assembly for further consideration. Most of these changes relate to the Public Accounts Committee. At the time of writing, the cognate Bill had not been debated.

The budget result was a $4.2 billion surplus. The consolidated financial statements at 30 June 2018 do not reflect the sale of 51 per cent of the State’s investment in Sydney Motorway Corporation for which it received $9.3 billion. The sale was announced on 31 August 2018.

Finally, I would like to thank the staff of Treasury for the way they approached the audit. Our partnership is critical to ensuring the quality of financial management and reporting.

Margaret Crawford
Auditor-General
19 October 2018

 

The State's financial statements given a clear audit opinion


Timely and accurate financial reporting enables informed decision making, effective management of public funds and enhances public accountability.

Since the introduction of mandatory ‘early close procedures’ in 2011-12, the number of significant errors in financial statements of agencies had fallen largely due to identifying and resolving complex accounting issues early.

In 2016-17, Treasury narrowed the scope of mandatory procedures to focus on physical asset valuations and pro-forma financial statements. Despite being broadened for 2017-18, we have observed an increase in the number of errors in agency financial statements.

In 2017-18, twenty-three errors exceeding $20 million were found in agencies’ financial statements that make up the State’s consolidated financial statements. This compares to only five in 2015-16.

The errors identified this year were the result of:

  • incorrectly applying Australian Accounting Standards
  • deficiencies in assessing the value of physical assets
  • using inappropriate and inaccurate assumptions when measuring liabilities
  • inaccurately reflecting inter-agency payables and receivables.

Quality financial reporting would be enhanced by responding to key accounting issues as soon as they are identified, and preparing accounting position papers for consideration by Treasury, agency Audit and Risk Committees and the Audit Office.

Key accounting matters addressed by the State in 2017-18.


Restatement of some of the State’s previously reported asset and liability values.

The state corrected the previously reported values of some long-term liabilities ($2 billion).

Accounting standards require the State to measure its long-term liabilities at the best estimate of the expenditures required to settle the obligations. The affected liabilities include claims liabilities of the Lifetime Care and Support Authority of NSW and the NSW Self Insurance Corporation, and scheme liabilities of the Long Service Corporation. The liabilities are adjusted by what is referred to as the ‘discount rate’ to reflect the decreasing value of money over time.

In the past, agencies used a variety of rates to discount these liabilities. Some liabilities were discounted using the estimated long-term fair value of 10-year TCorp bond yields while others were discounted using the expected
return on investments. These discount rates did not comply with the requirements of Australian Accounting Standards and underestimated liabilities by $2.0 billion.

In 2017-18, the State assessed the discount rates previously used in the Sector. It determined the market yield on Commonwealth Bonds best met the Accounting Standard requirements and used this rate to discount similar liabilities in relevant agencies. This resulted in a $2.0 billion increase in the previously reported values of these liabilities and a similar decrease in retained earnings at 1 July 2016.

The State corrected previously reported values of certain Library assets ($1.1 billion).

The value of the Pictorial Collection of the Library Council of NSW (the Library) was reassessed at 31 January 2018. During the valuation process the Library identified three errors in the 2015 valuations which overstated the previously reported asset values. The errors included:

  • inconsistencies in the sampling technique ($583m)
  • double counting of some assets ($376m)
  • errors in population sizes ($164m).

This resulted in a $1.1 billion decrease in previously reported asset values and a corresponding decrease in the asset revaluation reserve at 1 July 2016.

 

Information system limitations continue at TAFE NSW.

TAFE NSW has experienced ongoing issues with its student administration system.

TAFE NSW has again implemented additional processes to verify the accuracy and completeness of revenue from student fees.

TAFE NSW expects to spend up to $89 million on a new information system to address these issues. Modules of the new student enrolment system are planned to be in place by May 2019

Risks to the quality and timeliness of financial reporting.


Challenges associated with valuing the State's physical assets.

When we audit financial statements we focus on areas we consider higher risk. These areas often require the use of estimates and judgements.

The valuation of the State’s physical assets is one such area. Fair value estimates are inherently complex and sensitive to assumptions and judgements. In the public sector, this may be exacerbated by the unique nature of its assets, such as land under roads, preserved plant specimens, cultural collections and other heritage assets.

In 2017-18, valuations of physical assets added $24.5 billion to the value of the State’s balance sheet. These assets are now valued at $339.2 billion. Our audits of these valuations identified:

The Library Council of NSW had three errors in the methodology previously used to value their pictorial assets ($1.1 billion error).
The Royal Botanic Gardens and Domain Trust did not previously recognise a value for their Herbarium assets ($284 million error).
Some revaluations within the Ministry of Health did not meet the requirements of Australian Accounting Standards or Treasury requirements ($159 million error).
The Department of Justice used an incorrect valuation
methodology ($83 million error).

Some important matters agencies should consider when planning/conducting asset valuations include:


STARTING OUT

  • Planning is important
  • Most effective revaluations include early engagement with all stakeholders, including auditors.
  • Determine who needs to be involved and advised of progress with the revaluation – e.g. finance, internal audit, audit and risk committee.
  • Ensure asset registers are complete and there is evidence to demonstrate the agency controls the assets.
  • The effective date of the valuation can be any date after the financial year commences, but well before year end.

MANAGEMENT'S ROLE

  • For large mass valuations consider using a suitable project management methodology to ensure the process remains ‘on track’ with sufficient oversight.
  • Consider engaging an expert to perform the valuation, but maintain responsibility for the outcomes. Ensure the outcomes are reasonable and quality review the results, including the appropriateness of inputs and key assumptions.
  • Compare pre and post valuation results on an individual asset basis. Where changes are significant and/or unexpected, document explanations from the valuer.
  • Start revaluations early so they are completed by early close (around March). The timetable must allow time for a quality review of results and for the results to be recorded in the financial records.
  • Revaluation workpapers must include the revaluation source data provided to the valuer and a reconciliation of the source data to the general ledger.

USING EXPERTS

  • The terms of engagement should be documented in an engagement letter, which clearly details the proposed valuation methodology. It’s important the valuer knows what is required from a policy perspective and clearly understands the accounting framework used to prepare the financial statements.
  • Valuation reports should detail the key assumptions used, explain why the valuation approach was adopted and how the use of relevant observable input was maximised.
  • Valuation reports should clearly differentiate between assets revalued using a cost approach and those using an income or market approach. They should explain why the approach used was the most relevant for the asset type.
  • Consider using representative/statistical sampling for mass valuations and determine the extent of physical inspections that may be required.
  • If a sampling technique is used, it should provide sufficient confidence that the sample is representative of the population.
  • Significant judgements should be supported by relevant benchmark data or other analysis and observations. A common example in the public sector is to discount asset values to reflect restrictions on use.
  • Ensure the valuer has considered the age and condition of the assets, and heritage/cultural aspects and/or other special factors.

WHAT ABOUT INTERVENING YEARS?

  • Perform revaluations with sufficient regularity to ensure asset carrying values in the financial statements reflect fair value.
  • Indexation alone is not normally a substitute for a full revaluation. A full revaluation may be needed to accurately establish fair values if asset values move significantly when indices are applied to them.
  • Where indexation is used between full revaluations, the indices should be appropriate for the type of asset being assessed.
  • Indexing can be unreliable in assessing whether the fair value of assets has moved over time. For example, some assets are valued based on re- collection cost estimates, which may fall over time due to improved re-collection methods and technology.

COMMUNICATION

  • For mass or complex valuations, key stakeholders, including auditors, should be involved at the scoping stage and invited to planning meetings with valuers.
  • Management should meet with the auditors regularly to discuss progress and outcomes.
  • When issues are identified, management should consult with and seek advice from Treasury.

 

The state will need to implement five new accounting standards over the next two years.

The State has started developing processes it considers necessary to effectively implement the requirements of five new accounting standards. The changes are significant and will impact the financial position and results of agencies and the State.

The new requirements increase the risk of errors in the financial statements. To minimise this risk, agencies will need to devote resources and effort to collect the necessary information and assess the impact of the accounting changes at the whole of government level.

Treasury is liaising with and obtaining information from agencies to assess the impact of the new standards at the whole of government level. Treasury is also liaising with other Treasuries throughout Australia on common implementation issues. To help agencies implement the new standards, Treasury is developing guidance, preparing position papers on proposed accounting treatments, and mandating options within the new standards that agencies need to adopt on transition.


 

A $4.2 billion surplus, $1.5 billion more than was budgeted


The Total State Sector comprises 304 entities controlled by NSW Government

The General Government Sector, which comprises 212 entities, generally provides goods and services funded centrally by the State.

The non-General Government Sector, which comprises 92 Government businesses, generally provides goods and services, such as water, electricity and financial services that consumers pay for directly.

A principal measure of a Government’s overall performance is its Net Operating Balance (Budget Result). This is the difference between the cost of General Government service delivery and the revenue earned to fund these sectors.

WHAT CHANGED FROM 2017 TO 2018?

$4.2b

2017-18 General Government Budget Result

Changes in revenues compared to 2016-17

   
Financial_performance_red_10x10cm_0.pngDividends and distributions

 

Due to: 

  • Increases in dividends from Sydney Water ($255 million), Water NSW ($60 million) and the Port Authority of NSW ($195 million).
  • An increase in the dividend from Landcom ($200 million) as profits retained in prior years to fund certain projects were not spent.
  • Returns from investments in managed funds increased by $649 million as the State increased the value of its investment using proceeds from the lease of Ausgrid and Endeavour Energy assets
2016-2017 Change 2017-2018

2.4b

+1.3b

3.7b

 

   
Financial_performance_red_10x10cm_0.pngTaxation

 

Due to: 

  • Increases in land tax ($564 million) driven by land valuations used to calculate land tax assessments.
  • Increases in payroll tax ($553 million) and other taxes ($419 million).
  • Stamp duty receipts were $1.0 billion lower largely due to additional duty in the prior year of $718 million relating to the lease of Ausgrid and Endeavour Energy assets.
2016-2017 Change 2017-2018

30.8b

+537m

31.3b

 

   
Greek pantheon style front of building Grants & Subsidies

 

 Due to:

  • Increase in the receipt of general purpose grants relating to GST collected by the Australian Government ($753 million).
  • Decreases in national partnerships and specific purpose payments received from the Australian Government ($305 million), mainly due to the timing of major road projects.
  • An increase in Commonwealth Health Reform funding ($338 million).
  • An increase in grants associated with the National Education Reform Agreement for Education ($233 million).
2016-2017 Change 2017-2018

31.4b

+509m

31.9b

 

   
red shopping tagsSale of Goods and services

 

Includes: 

  • Increases in education revenue ($133 million).
  • Higher fees for services in transport to produce property plant and equipment ($89 million).
2016-2017 Change 2017-2018

8.2b

+349m

8.5b

5.5b

-185m

5.3b

Other revenues

Changes to expenses compared to 2016-17

   
institution_red_10x10cm_0.pngRecurrent Grants & Subsidies

 

Due to: 

  • A $613 million increase in grants for the delivery of aging, disability (including NDIS), homecare, community and public housing services.
  • Increase in grants paid to local government sector ($342 million).
2016-2017 Change 2017-2018

12.6b

+1.3b

13.9b

 

   
group_red_10x10cm_0.pngEmployee costs

 

Due to: 

  • Wage inflation increases ($701 million).
  • Increased workers' compensation and long service leave costs ($337 million). 
2016-2017 Change 2017-2018

34.9b

+1.2b

36.1b

 

   
red cogs with a dollar sign in the middleOther operating expenses

 

Includes: 

  • Increased expenditure by Transport for NSW ($283 million) for major rail projects and the new rail timetable.
  • Increased expenditure by the Department of Education ($165 million) to address the maintenance backlog, and higher school operating expenses.
2016-2017 Change 2017-2018

18.3b

+1.4b

19.7b

6.8b

+103m

6.9b

Other expenses

 

$5.7b

2016-17 General Government Budget Result

The State maintained its AAA credit rating.


The object of the Fiscal Responsibility Act 2012 is to maintain the State’s AAA credit rating.

The Government manages NSW’s finances in alignment with the Fiscal Responsibility Act 2012 (the Act).

The Act establishes the framework for fiscal responsibility and the strategy to protect the State’s AAA credit rating and service delivery
to the people of NSW.

The legislation sets out targets and principles for financial management to achieve this.

New South Wales has credit ratings of AAA/ Stable from Standard & Poor’s and Aaa/ Stable from Moody’s Investors Service.

THE FISCAL TARGETS FOR ACHIEVING THIS OBJECTIVE ARE:

General Government annual expenditure growth is lower than long term average revenue growth.

General Government expenditure grew by 5.4 per cent in 2017-18. This was lower than the long-term revenue growth rate of 5.6 per cent.

Eliminating unfunded superannuation liabilities by 2030.

The Act sets a target to eliminate unfunded superannuation liabilities by 2030.

The State’s funding plan is to contribute amounts escalated by five per cent each year so the schemes will be fully funded by 2030. In 2017-18, the State made employer contributions of $1.7 billion, which is largely consistent with contributions over the past five years. Treasury expects superannuation liabilities will be fully funded by 2030 based on the funding program at the last triennial review (December 2015).

For fiscal responsibility purposes, the State uses AASB 1056: Superannuation Entities. This standard discounts superannuation liabilities using the expected return on assets backing the liability.

Using this method, the State’s unfunded superannuation liability was $14.0 billion at 30 June 2018 ($15.0 billion at 30 June 2017). The unfunded liability is $3.4 billion less than it was when the Act was introduced.


 

Revenues increased by $3.2 billion to $86.7 billion in 2017-18.


Revenues were underpinned by growth in taxation and Australian Government grant revenues, but stamp duties fell.

Tax revenue for the Total State Sector increased by $746 million, or 2.5 per cent compared to 2016-17, primarily due to a:

  • $582 million increase in land tax from growth in land values
  • $562 million increase in payroll tax from NSW employment and wages growth
  • $1 billion decrease in stamp duty due to lower than expected growth in property market transactions, volumes and prices. In 2016-17, stamp duty included $718 million from the leases of Ausgrid and Endeavour Energy assets.

The State expects total stamp duties will fall to $9.5 billion in 2018-19, a decrease of almost $2.0 billion from 2016-17.

The State received Australian Government grants and subsidies of $30.9 billion in 2017-18.
The State received $444 million more in grants and subsidies from the Australian Government than it did in 2016-17. This was due to increases in GST revenues ($753 million) and special purpose payments ($683 million).
There was a decrease in National Partnership payments ($992 million), mainly due to the timing of major road projects including the Pacific Highway (Woolgoolga to Ballina), WestConnex and Western Sydney Infrastructure Program.

In 2017-18, sales of goods and services were $1.1 billion higher than in 2016-17. This reflected increased transaction revenue at Sydney Water ($139 million), the Department of Education ($133 million), WestConnex ($145 million), Department of Finance, Services and Innovation ($111 million) and Sydney Trains ($83 million).

Other dividends and distributions were $803 million higher than in 2016-17 mainly reflecting higher investment returns on TCorp investments.

$

83.5b

+3.9%

86.7b

Total Revenue

Key revenues include:

  2016-2017 Change% 2017-2018  
red gavel

35.4b

+2.8

36.3b

Taxation, Fees, Fines, and other
institution_red_10x10cm_0.png

31.4b

+1.6

31.9b

Grants & Subsidies
tags_red_10x10_0.png

14.1b

+8.1

15.2b

Sale of Goods and Services

Expenses increased $4.9 billion to $84.2 billion in 2017-18


Overall expenses increased 6.1 per cent compared to 2016-17. Most of the increase was due to higher employee and operating costs.

$

79.3b

+6.1%

84.2b

Total Expenses

Salaries and wages increased by 3.6 per cent compared to 2016-17.

Salaries and wages increased to $31.1 billion from $30 billion. This was due to inflation linked salary and wage increases and a reported increase in front line staff.

The Government wages policy aims to limit growth in employee remuneration and other employee related costs to no more than 2.5 per cent per annum.

Operating expenses increased by 7.8 per cent from 2016-17.

Within operating expenses, payments for supplies, services and other expenses increased, in part, due to:

  • increased costs of major rail projects, WestConnex, B-Line bus program and a new rail timetable
  • addressing the maintenance backlog and higher school operating expenses of the Department of Education.

Key expenses include:

  2016-2017 Change% 2017-2018  
group_red_10x10cm_0.png

32.8b

+3.8

34.1b

Employee Expenses
Financial_controls_red_10x10cm_0.png

21.6b

+7.8

23.3b

Operating Costs
institution_red_10x10cm_0.png

9.7b

+12.7

10.9b

Grants & Subsidies
down arrow red

7.2b

+6.6

7.6b

Depreciation
red briefcase

4.6b

+2.8

4.7b

Superannuation Expense

Health costs remain the highest expense of the State.

The Australian Bureau of Statistics introduced a revised Classification of the Function of Government Australia Framework (COFOG-A) effective 1 July 2017. This resulted in some re-classification of expenditure between purposes and now shows State expenses are highest in:

  • Health (25.5 per cent)
  • General Public Services (25.0 per cent)
  • Education (19.6 per cent).

General Public Services includes the executive and legislative branches, financial affairs, public debt transactions and general public service transactions.

The graph highlights the annual expenditure by function and the value of assets to deliver those services.

Assets grew by $35.6 billion to $443 billion in 2017-18


Valuing the State’s physical assets.

The State had physical assets with a fair value of $339 billion at 30 June 2018. This includes land and buildings ($161.6b) and Infrastructure ($160.2b).

Our audits assess the reasonableness and appropriateness of assumptions used to value physical assets. This includes obtaining an understanding of the valuation methodologies used and judgements made. We also review the completeness of asset registers and the mathematical accuracy of valuation models.

Net movements between years include additions, disposals, depreciation and valuations. This year, revaluations of physical assets added $24.5 billion to the value of the State’s assets. This was mainly attributable to the following agencies:

  • Department of Education - $8.5 billion
  • Roads and Maritime Services - $7.4 billion.

The State’s financial assets increased by $308 million in 2017-18 ($27.5 billion in 2016-17).

In 2016-17, the significant increase in financial assets was primarily from the sale or lease of the following government assets and businesses:

  • In June 2017, the Government leased 50.4 per cent of Endeavour Energy assets, which followed the long-term lease 50.4 per cent of Ausgrid’s assets in December 2016. The Government received proceeds of $24.0 billion from these transactions.
  • A 35-year concession for providing titling and registry services, effective 30 June 2017, was granted to a private sector operator. The Government received $2.6 billion cash for the concession.

The Government implemented reforms relating to the use the State’s financial assets.

In 2017-18, the Asset and Liability Committee, which advises the Government on balance sheet management, recommended the following policy actions and frameworks to help manage the State’s financial risks and opportunities:

  • expanding the scope of cash management reforms to give the State a whole-of-government view on the use of surplus funds. Treasury advises these reforms have centralised funds management of approximately $3.0 billion
  • endorsing a new whole-of-government Foreign Exchange (FX) Risk Policy (effective 1 July 2018) to effectively manage the State’s FX risk
  • expanding management of the State’s debt portfolio to minimise interest rate risks, reduce interest costs where possible, and extend the average weighted life of the General Government’s debt portfolio towards eight years
  • endorsing establishment of a ‘sustainability bond’ program to further diversify and expand the State’s bond investor base and raise awareness of the Government’s social and environmental initiatives.

The State has established the NSW Generations Fund to maintain debt at sustainable levels.

The State established the NSW Generations Funds (NGF) in June 2018 to support debt retirement and to fund community-focused initiatives. The Government has indicated it will initially capitalise the NGF with $3.0 billion from its reserves.

The NSW Generations Funds Act 2018 requires an audit of each NSW Generations Fund by the Auditor- General (including a report by the Auditor-General on whether payments from the Funds have been made in accordance with the Act). The first audit of the fund will be for the period up to 30 June 2019.
 

$

407b

+8.7%

443b

Total Assets

Key assets include: 

  2016-2017 Change% 2017-2018  
Physical Assets      
road_red_10x10_0.png

147.0b

+9.0

160.2b

Infrastructure
factory red

143.4b

+12.7

161.6b

Land and Buildings
Financial Assets      
scales of justice red

27.7b

- 4.6

26.4b

Equity investments
Financial_performance_red_10x10cm_0.png

20.6b

- 5.2

19.5b

Cash and Recievables
red pillar building - partheon

40.5b

+6.5

41.3b

Investments and Placements

Liabilities increased $5.1 billion to $189 billion in 2017-18


Valuing the State’s liabilities relies on actuarial assessments.

Nearly half of the State’s liabilities relate to its employees. They include unfunded superannuation, and employee benefits, such as long service and recreation leave.

Valuing these obligations involves complex estimation techniques and significant judgements. Small changes in assumptions can materially impact the values and the financial statements.

The State’s superannuation obligations fell $2.2 billion in 2017-18.

The State’s $56.4 billion unfunded superannuation liability represents obligations to past and present employees less the value of assets set aside to meet those obligations. The unfunded superannuation liability fell from $58.6 billion to $56.4 billion in 2017-18.

The State’s borrowings at 30 June 2018 were $700 million higher than they were at 30 June 2017.

The State’s borrowings totalled $71.3 billion at 30 June 2018.

TCorp issues bonds to raise funds for NSW Government agencies. These are actively traded in financial markets, which provides price transparency and liquidity to public sector borrowers and institutional investors. All TCorp bonds are guaranteed by the NSW Government.

The Government manages its debt liabilities through its balance sheet management strategy. The strategy extends to TCorp, which applies an active risk management strategy to the Government’s debt portfolio.

General Government Sector debt has been restructured by replacing shorter-term debt with longer-term debt. This lengthens the portfolio to match liabilities with the funding requirements for infrastructure assets.

$

184b

+2.8%

189b

Total Liabilities

Key liabilities include: 

  2016-2017 Change% 2017-2018  
briefcase_red_10x10cm_0.png

58.6b

- 3.7

56.4b

Unfunded Superannuation
group_red_10x10cm_0.png

18.3b

+4.7

19.1b

Other Employee Benefits
institution red - pantheon style building

70.6b

+1.0

71.3b

Borrowings

Published

Actions for Mobile speed cameras

Mobile speed cameras

Transport
Compliance
Financial reporting
Information technology
Internal controls and governance
Management and administration
Regulation
Service delivery

Key aspects of the state’s mobile speed camera program need to be improved to maximise road safety benefits, according to a report released today by the Auditor-General for New South Wales, Margaret Crawford. Mobile speed cameras are deployed in a limited number of locations with a small number of these being used frequently. This, along with decisions to limit the hours that mobile speed cameras operate, and to use multiple warning signs, have reduced the broad deterrence of speeding across the general network - the main policy objective of the mobile speed camera program.

The primary goal of speed cameras is to reduce speeding and make the roads safer. Our 2011 performance audit on speed cameras found that, in general, speed cameras change driver behaviour and have a positive impact on road safety.

Transport for NSW published the NSW Speed Camera Strategy in June 2012 in response to our audit. According to the Strategy, the main purpose of mobile speed cameras is to reduce speeding across the road network by providing a general deterrence through anywhere, anytime enforcement and by creating a perceived risk of detection across the road network. Fixed and red-light speed cameras aim to reduce speeding at specific locations.

Roads and Maritime Services and Transport for NSW deploy mobile speed cameras (MSCs) in consultation with NSW Police. The cameras are operated by contractors authorised by Roads and Maritime Services. MSC locations are stretches of road that can be more than 20 kilometres long. MSC sites are specific places within these locations that meet the requirements for a MSC vehicle to be able to operate there.

This audit assessed whether the mobile speed camera program is effectively managed to maximise road safety benefits across the NSW road network.

Conclusion

The mobile speed camera program requires improvements to key aspects of its management to maximise road safety benefits. While camera locations have been selected based on crash history, the limited number of locations restricts network coverage. It also makes enforcement more predictable, reducing the ability to provide a general deterrence. Implementation of the program has been consistent with government decisions to limit its hours of operation and use multiple warning signs. These factors limit the ability of the mobile speed camera program to effectively deliver a broad general network deterrence from speeding.

Many locations are needed to enable network-wide coverage and ensure MSC sessions are randomised and not predictable. However, there are insufficient locations available to operate MSCs that meet strict criteria for crash history, operator safety, signage and technical requirements. MSC performance would be improved if there were more locations.

A scheduling system is meant to randomise MSC location visits to ensure they are not predictable. However, a relatively small number of locations have been visited many times making their deployment more predictable in these places. The allocation of MSCs across the time of day, day of week and across regions is prioritised based on crash history but the frequency of location visits does not correspond with the crash risk for each location.

There is evidence of a reduction in fatal and serious crashes at the 30 best-performing MSC locations. However, there is limited evidence that the current MSC program in NSW has led to a behavioural change in drivers by creating a general network deterrence. While the overall reduction in serious injuries on roads has continued, fatalities have started to climb again. Compliance with speed limits has improved at the sites and locations that MSCs operate, but the results of overall network speed surveys vary, with recent improvements in some speed zones but not others.
There is no supporting justification for the number of hours of operation for the program. The rate of MSC enforcement (hours per capita) in NSW is less than Queensland and Victoria. The government decision to use multiple warning signs has made it harder to identify and maintain suitable MSC locations, and impeded their use for enforcement in both traffic directions and in school zones. 

Appendix one - Response from agency

Appendix two - About the audit

Appendix three - Performance auditing

 

Parliamentary reference - Report number #308 - released 18 October 2018

Published

Actions for Regional Assistance Programs

Regional Assistance Programs

Premier and Cabinet
Planning
Transport
Compliance
Infrastructure
Management and administration
Project management

Infrastructure NSW effectively manages how grant applications for regional assistance programs are assessed and recommended for funding. Its contract management processes are also effective. However, we are unable to conclude whether the objectives of these programs have been achieved as the relevant agencies have not yet measured their benefits, according to a report released today by the Auditor-General for New South Wales, Margaret Crawford. 

In 2011, the NSW Government established Restart NSW to fund new infrastructure with the proceeds from the sale and lease of government assets. From 2011 to 2017, the NSW Government allocated $1.7 billion from the fund for infrastructure in regional areas, with an additional commitment of $1.3 billion to be allocated by 2021. The NSW Government allocates these funds through regional assistance programs such as Resources for Regions and Fixing Country Roads. NSW councils are the primary recipients of funding provided under these programs.

The NSW Government announced the Resources for Regions program in 2012 with the aim of addressing infrastructure constraints in mining affected communities. Infrastructure NSW administers the program, with support from the Department of Premier and Cabinet.

The NSW Government announced the Fixing Country Roads program in 2014 with the aim of building more efficient road freight networks. Transport for NSW and Infrastructure NSW jointly administer this program, which funds local councils to deliver projects that help connect local and regional roads to state highways and freight hubs.

This audit assessed whether these two programs (Resources for Regions and Fixing Country Roads) were being effectively managed and achieved their objectives. In making this assessment, we answered the following questions:

  • How well are the relevant agencies managing the assessment and recommendation process?
  • How do the relevant agencies ensure that funded projects are being delivered?
  • Do the funded projects meet program and project objectives?

The audit focussed on four rounds of Resources for Regions funding between 2013–14 to 2015–16, as well as the first two rounds of Fixing Country Roads funding in 2014–15 and 2015–16.

Conclusion
Infrastructure NSW effectively manages how grant applications are assessed and recommended for funding. Infrastructure NSW’s contract management processes are also effective. However, we are unable to conclude on whether program objectives are being achieved as Infrastructure NSW has not yet measured program benefits.
While Infrastructure NSW and Transport for NSW managed the assessment processes effectively overall, they have not fully maintained all required documentation, such as conflict of interest registers. Keeping accurate records is important to support transparency and accountability to the public about funding allocation. The relevant agencies have taken steps to address this in the current funding rounds for both programs.
For both programs assessed, the relevant agencies have developed good strategies over time to support councils through the application process. These strategies include workshops, briefings and feedback for unsuccessful applicants. Transport for NSW and the Department of Premier and Cabinet have implemented effective tools to assist applicants in demonstrating the economic impact of their projects.
Infrastructure NSW is effective in identifying projects that are 'at‑risk' and assists in bringing them back on track. Infrastructure NSW has a risk‑based methodology to verify payment claims, which includes elements of good practice in grants administration. For example, it requires grant recipients to provide photos and engages Public Works Advisory to review progress claims and visit project sites.
Infrastructure NSW collects project completion reports for all Resources for Regions and Fixing Country Roads funded projects. Infrastructure NSW intends to assess benefits for both programs once each project in a funding round is completed. To date, no funding round has been completed. As a result, no benefits assessment has been done for any completed project funded in either program.
 

The project selection criteria are consistent with the program objectives set by the NSW Government, and the RIAP applied the criteria consistently. Probity and record keeping practices did not fully comply with the probity plans.

The assessment methodology designed by Infrastructure NSW is consistent with2 the program objectives and criteria. In the rounds that we reviewed, all funded projects met the assessment criteria.

Infrastructure NSW developed probity plans for both programs which provided guidance on the record keeping required to maintain an audit trail, including the use of conflict of interest registers. Infrastructure NSW and Transport for NSW did not fully comply with these requirements. The relevant agencies have taken steps to address this in the current funding rounds for both programs.

NSW Procurement Board Directions require agencies to ensure that they do not engage a probity advisor that is engaged elsewhere in the agency. Infrastructure NSW has not fully complied with this requirement. A conflict of interest arose when Infrastructure NSW engaged the same consultancy to act as its internal auditor and probity advisor.

While these infringements of probity arrangements are unlikely to have had a major impact on the assessment process, they weaken the transparency and accountability of the process.

Some councils have identified resourcing and capability issues which impact on their ability to participate in the application process. For both programs, the relevant agencies conducted briefings and webinars with applicants to provide advice on the objectives of the programs and how to improve the quality of their applications. Additionally, Transport for NSW and the Department of Premier and Cabinet have developed tools to assist councils to demonstrate the economic impact of their applications.

The relevant agencies provided feedback on unsuccessful applications to councils. Councils reported that the quality of this feedback has improved over time.

Recommendations

  1. By June 2018, Infrastructure NSW should:
    • ensure probity reports address whether all elements of the probity plan have been effectively implemented.
  1. By June 2018, Infrastructure NSW and Transport for NSW should:
    • maintain and store all documentation regarding assessment and probity matters according to the State Records Act 1998, the NSW Standard on Records Management and the relevant probity plans

Infrastructure NSW is responsible for overseeing and monitoring projects funded under Resources for Regions and Fixing Country Roads. Infrastructure NSW effectively manages projects to keep them on track, however it could do more to assure itself that all recipients have complied with funding deeds. Benefits and outcomes should also start to be measured and reported as soon as practicable after projects are completed to inform assessment of future projects.

Infrastructure NSW identifies projects experiencing unreasonable delays or higher than expected expenses as 'at‑risk'. After Infrastructure NSW identifies a project as 'at‑risk', it puts in place processes to resolve issues to bring them back on track. Infrastructure NSW, working with Public Works Advisory regional offices, employs a risk‑based approach to validate payment claims, however this process should be strengthened. Infrastructure NSW would get better assurance by also conducting annual audits of compliance with the funding deed for a random sample of projects.

Infrastructure NSW collects project completion reports for all Resources for Regions and Fixing Country Roads funded projects. It applies the Infrastructure Investor Assurance Framework to Resources for Regions and Fixing Country Roads at a program level. This means that each round of funding (under both programs) is treated as a distinct program for the purposes of benefits realisation. It plans to assess whether benefits have been realised once each project in a funding round is completed. As a result, no benefits realisation assessment has been done for any project funded under either Resources for Regions or Fixing Country Roads. Without project‑level benefits realisation, future decisions are not informed by the lessons from previous investments.

Recommendations

  1. By December 2018, Infrastructure NSW should:
    • conduct annual audits of compliance with the funding deed for a random sample of projects funded under Resources for Regions and Fixing Country Roads
    • publish the circumstances under which unspent funds can be allocated to changes in project scope
    • measure benefits delivered by projects that were completed before December 2017
    • implement an annual process to measure benefits for projects completed after December 2017
  1. By December 2018, Transport for NSW and Infrastructure NSW should:
    • incorporate a benefits realisation framework as part of the detailed application.

Published

Actions for Liverpool to Parramatta Bus Transitway

Liverpool to Parramatta Bus Transitway

Transport
Treasury
Infrastructure
Management and administration
Project management
Service delivery

Several of my recent audits have identified a need to improve our public transport system – both for the benefit of travellers and to assist in achieving better air quality.

Bus Transitways can provide a good public transport solution for lower density population areas, potentially at a relatively low capital cost. This audit examines the transitway running between Liverpool and Parramatta, the first of several planned for Sydney. This audit should contribute to a better understanding of the lessons learnt from this first project, and so to future transitways providing better value for money.

But this audit also raises broader issues.

It highlights the importance of accurately projecting the total cost of major infrastructure projects before governments lock in their decisions. It also highlights the need for sound decision-making processes when government agencies compete with the private sector. The principles and recommendations flowing from these issues are ones I would draw to the attention of all agencies, and to the Government.

 

Parliamentary reference - Report number #146 - released 5 December 2005