Actions for Handback of the M4 Tollway

Handback of the M4 Tollway

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management

This audit focuses on the M4 handback. It looks at whether the road will be in good condition when the State gets it back, and whether it will cope with the extra traffic after the toll is removed. These are critical issues for taxpayers and motorists. Taxpayers don’t want to be responsible for a large repair bill and motorists don’t want to be stuck in traffic jams. To ensure that future private sector partnerships (PPP) deal adequately with handb

Published

Actions for Improving Road Safety: Heavy Vehicles

Improving Road Safety: Heavy Vehicles

Transport
Compliance
Internal controls and governance
Management and administration
Regulation
Risk

The RTA (Roads and Traffic Authority) approach to detecting and enforcing heavy vehicle safety has produced mixed results. There have been overall decreases in the number of crashes and people killed and injured in crashes involving heavy vehicles between 2002 and 2007. However, the number of crashes and the number of people injured have increased between 2006 and 2007. We recognise that the RTA is unable to prevent all crashes. However, we conside

Published

Actions for Condition of State Roads

Condition of State Roads

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Service delivery

The Roads and Traffic Authority (RTA) has improved the overall surface condition of State Roads in the last decade. Country road surfaces are now generally much better. Ride quality has improved and cracking has been reduced. The RTA has also achieved a substantial reduction in the number of structurally deficient bridges over the same period.  Despite a significant increase in the State’s contribution to maintenance since 1999-2000, the RTA h

Published

Actions for The Cross City Tunnel Project

The Cross City Tunnel Project

Transport
Treasury
Premier and Cabinet
Planning
Environment
Infrastructure
Management and administration
Procurement
Project management
Risk

In our opinion the Government’s ‘no net cost to government’ requirement was a legitimate (but not the only possible) basis for the tunnel bid process. The Government was entitled to decide that tunnel users meet the tunnel costs. Structuring the bid process on the basis of an upfront reimbursement of costs incurred (or to be incurred) by the Roads and Traffic Authority (RTA) was therefore appropriate. In our opinion, however, the Government, Treasu

Published

Actions for Dealing with Unlicensed and Unregistered Driving

Dealing with Unlicensed and Unregistered Driving

Justice
Transport
Information technology
Regulation
Shared services and collaboration

In our opinion there are inadequacies in the current arrangements for detecting unauthorised driving. For example better information is needed on the extent of unlicensed driving. This may require giving the NSW Police power to conduct random licence and registration checks. In addition, there are technological and legal constraints to the efficient and effective detection of unauthorised driving.   Parliamentary reference - Report number #115&nbs

Published

Actions for Freedom of Information

Freedom of Information

Transport
Premier and Cabinet
Education
Management and administration
Regulation
Service delivery

Freedom of Information (FOI) Coordinators and their staff were supportive of the legislation. However, the agencies examined can do considerably more to fully achieve the intentions of the Act. On the positive side, all three agencies had processes in place to handle requests and had made a number of changes to improve the effectiveness of the FOI process. Fees and charges had also been kept to a minimum. No processing fees were requested in the majority

Published

Actions for The Millennium Train Project

The Millennium Train Project

Transport
Infrastructure
Procurement
Project management
Service delivery

State Rail has made significant improvements since the purchase of the Tangara. It improved measures necessary for handling contracts dealing with technically complex and innovative projects, although some other problems have been encountered, with new lessons to learn. The design and manufacture of new trains requires a significant investment in both time and cost. The Millennium Train has come at a considerably higher price than originally expected. An

Published

Actions for Review of Eastern Distributor

Review of Eastern Distributor

Transport
Infrastructure
Procurement
Project management

Following a resolution of the Legislative Council, the Audit Office has undertaken a performance audit of the Eastern Distributor. For a number of reasons, The Audit Office is not in the position to determine “whether the proposed toll and concession period represents the best deal”. In part this is the result of time constraints which do not allow a careful analysis of many toll and concession options. Similarly, the audit does not answer “whether