What the report is about

This audit assessed how effectively the Department of Planning and Environment (Heritage NSW) is overseeing and administering heritage assets of state significance.

Heritage that is rare, exceptional or outstanding to New South Wales may be listed on the State Heritage Register under the Heritage Act 1977. This provides assets with legal recognition and protection. Places, buildings, works, relics, objects and precincts can be listed, whether in public or private ownership.

Heritage NSW has administrative functions and regulatory powers, including under delegation from the Heritage Council of NSW, relevant to the listing, conservation and adaptive re-use of heritage assets of state significance.

In summary, the audit assessed whether Heritage NSW:

  • is effectively administering relevant advice and decisions
  • is effectively supporting and overseeing assets
  • has established clear strategic priorities and can demonstrate preparedness to implement these.

What we found

Heritage NSW does not have adequate oversight of state significant heritage assets, presenting risks to its ability to promote the objects of the Heritage Act.

Information gaps and weaknesses in quality assurance processes limit its capacity to effectively regulate activities affecting assets listed on the State Heritage Register.

Heritage NSW has adopted a focus on customer service and recently improved its timeliness in providing advice and making decisions about activities affecting listed assets. But Heritage NSW has not demonstrated how its customer-focused priorities will address known risks to its core regulatory responsibilities.

Listed assets owned by government entities are often of high heritage value. Heritage NSW could do more to promote effective heritage management among these entities.

What we recommended

The report made eight recommendations to Heritage NSW, focusing on:

  • improving quality assurance over advice and decisions
  • improving staff guidance and training
  • defining and maintaining data in the State Heritage Register
  • clarifying its regulatory intent and approach
  • sector engagement and interagency capability to support heritage outcomes.

The Heritage Act 1977 (the Heritage Act) and accompanying regulation provide the legal framework for the identification, conservation and adaptive re-use of heritage assets in New South Wales.

The Department of Planning and Environment (Heritage NSW) has responsibility for policy, legislative and program functions for state heritage matters, including supporting the Minister for Heritage to administer the Heritage Act.

Heritage assets that are rare, exceptional or outstanding beyond a local area or region may be listed on the State Heritage Register under the Heritage Act. These assets include places, buildings, works, relics, moveable objects and precincts, and assets that have significance to Aboriginal communities in New South Wales. Assets nominated for and listed on the State Heritage Register ('listed assets') may be owned privately or publicly, including by local councils and state government entities.

The Heritage Act establishes the Heritage Council of NSW (the Heritage Council) to undertake a range of functions in line with its objectives. Heritage NSW provides administrative support to the Heritage Council, for example providing advice on assets that have been nominated for listing on the State Heritage Register. Many of Heritage NSW’s core activities also relate to exercising functions and powers under delegation from the Heritage Council. These include making administrative decisions about works affecting listed assets, and exercising powers to regulate asset owners’ compliance with requirements under the Heritage Act.

Heritage NSW states that heritage:

…gives us a sense of our history and provides meaningful insights into how earlier generations lived and developed. It also enriches our lives and helps us to understand who we are.  

According to Heritage NSW, an effective heritage system will facilitate the community in harnessing the cultural and economic value of heritage.

The objective of this audit was to assess how effectively the Department of Planning and Environment (Heritage NSW) is overseeing and administering heritage assets of state significance.

For this audit, ‘heritage assets of state significance’ refers to items (including a place, building, work, relic, moveable object or precinct) listed on the State Heritage Register ('listed assets'), and those which have been nominated for listing.

Conclusion

The Department of Planning and Environment (Heritage NSW) does not have adequate oversight of state significant heritage assets. Information gaps and weaknesses in certain assurance processes limit its capacity to effectively regulate activities affecting assets listed on the State Heritage Register. These factors also constrain its ability to effectively support voluntary compliance and promote the objects of the Heritage Act, which include encouraging conservation and adaptive re-use.
Heritage NSW has adopted a focus on customer service and recently improved the timeliness of its advice and decisions on activities affecting listed assets. But Heritage NSW has not demonstrated how its customer service priorities will address known risks to its regulatory responsibilities. It could also do more to enable and promote effective heritage management among state government entities that own listed assets.

The information that Heritage NSW maintains about assets listed on the State Heritage Register ('listed assets') is insufficient for its regulatory and owner engagement purposes. Data quality and completeness issues have arisen since the register was established in 1999. But Heritage NSW's progress to address important gaps in the register, and its other information systems, has been limited in recent years. These gaps limit Heritage NSW’s capacity to detect compliance breaches early and implement risk-based regulatory responses, and to strategically target its owner engagement activities to promote conservation and re-use.

Heritage NSW makes decisions on applications for works on listed assets, requiring technical skills and professional judgement. But Heritage NSW does not provide its staff with adequate guidance to ensure that consistent approaches are used, and it lacks sufficient quality assurance processes. There are similar weaknesses in Heritage NSW's oversight of decisions on applications that are delegated to other government entities.

Heritage NSW has prioritised the implementation of customer service-focused activities, policies, and programs to reduce regulatory burdens on asset owners since 2017. For example, Heritage NSW has refreshed its website, introduced new information management systems, and implemented new regulation for the self-assessment of exemptions for minor works. However, Heritage NSW has not taken steps to mitigate oversight and quality risks introduced with the reduced regulatory burdens. Heritage NSW has made some, but to date insufficient, progress on a key project to update its publications. These documents (over 150 publications) are intended to play an important role in promoting voluntary compliance and supporting heritage outcomes. Heritage NSW started a new project to update relevant publications in April 2023.

Heritage NSW has recently implemented processes to improve its efficiency, such as screening new nominations for listing on the State Heritage Register. Heritage NSW has also reported improvements in the time it takes to decide on applications for works affecting listed assets. In the third quarter of 2022–23, 87% of decisions were made within the statutory timeframes. This compares to 48% in 2021–22. Heritage NSW has similarly improved how quickly it provides heritage advice on major projects, with 90% of advice reported as delivered on time in the third quarter of 2022–23, compared to 44% in 2020–21.

Assets owned by state government entities comprise a large proportion of State Heritage Register listings. These assets are often of high heritage value or situated within large and complex precincts or portfolios. But Heritage NSW does not implement targeted capability building activities to support good practice heritage management among state government entities and to promote compliance with their obligations under the Heritage Act.

The expected interaction between Heritage NSW's strategic plans and activities, and the priorities of the Heritage Council of NSW, is unclear. Actions to clarify the relevant governance arrangements have also been slow following a review in 2020 but this work re-commenced in late 2022.

Heritage NSW has been progressing work to draft reforms to the Heritage Act. This follows recommendations made in a 2021 Upper House Inquiry into the Heritage Act. To build preparedness for future reforms, Heritage NSW will need to do more to address the risks and opportunities identified in this audit report. In particular, it will need to ensure it has sufficient information and capacity to implement a risk-based regulatory approach; clear and effective governance arrangements with the Heritage Council of NSW; and enhanced engagement with government entities to promote the conservation and adaptive re-use of listed assets in public ownership.

This chapter assesses the effectiveness of Heritage NSW's oversight of state heritage assets, including its visibility of listed assets, and its oversight of regulatory decision-making. It also assesses Heritage NSW's activities to engage with owners to meet their obligations under the Heritage Act and to support heritage outcomes.

This chapter assesses the timeliness of Heritage NSW’s provision of advice, recommendations, and decisions on heritage issues to support heritage management outcomes with respect to listed assets.

This chapter assesses whether the Department of Planning and Environment (Heritage NSW) has established clear strategic priorities to effectively oversee and administer activities related to listed assets, and its preparedness to implement reforms. It also assesses the adequacy of planning activities and governance arrangements to support the achievement of strategic directions.

Appendix one – Response from agency

Appendix two – About the audit

Appendix three – Performance auditing

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #384 - released 27 June 2023

Published

Actions for Regulation of public native forestry

Regulation of public native forestry

Environment
Industry
Compliance
Management and administration
Regulation
Risk

What this report is about

The Forestry Corporation of NSW (FCNSW) is a state-owned corporation that manages over two million hectares of public native forests and plantations supplying timber to sawmills across NSW.

The NSW Environment Protection Authority (EPA) is responsible for regulating the native forestry industry in NSW.

FCNSW must comply with Integrated Forestry Operations Approvals (IFOAs), which set out rules for how timber harvesting may occur.

Most harvesting is undertaken under the Coastal IFOA, which commenced in 2018.

This audit assessed how effectively Forestry Corporation of NSW manages its public native forestry activities to ensure compliance, and how effectively the Environment Protection Authority regulates these activities.

What we found

Forestry Corporation of NSW (FCNSW) clearly articulates its compliance obligations.

While FCNSW undertakes monitoring of its contractors, it does not do so consistently and does not target its monitoring activities on a risk basis.

FCNSW has largely fulfilled mandatory Coastal IFOA training requirements, but has not yet trained other staff who would also benefit from the training.

Contractor compliance appears to be improving, but there are gaps and inconsistencies in FCNSW's documentation of this.

FCNSW is not measuring its overall compliance to determine how it is tracking against its target.

The EPA undertakes proactive inspections of Coastal IFOA harvesting operations on a risk basis. However, it does not assess the risk at harvest sites covered by other IFOAs.

Most EPA compliance staff have received basic training, but few have received more advanced training required to effectively undertake forestry inspections.

Some EPA offices do not have the necessary equipment to undertake forestry inspections.

The EPA and FCNSW are not implementing all elements of a Memorandum of Understanding that aims to promote a cooperative relationship between the agencies.

What we recommended

The report made recommendations to FCNSW which aim to improve:

  • staff training
  • consistency of compliance reviews and data capture
  • targeting of compliance activities
  • measurement of performance.

The report made recommendations to the EPA which aim to improve:

  • risk-assessments
  • staff training
  • staff equipment.

The report also recommended that FCNSW and EPA should fully implement their Memorandum of Understanding.

The Forestry Corporation of NSW (FCNSW) is a state-owned corporation that supplies timber to sawmills in New South Wales, including timber harvested from public native forests. FCNSW is responsible for the management of around two million hectares of public native forests and plantations. Around half the area of native forests is permanently set aside for conservation.

Public native forestry is regulated through the Forestry Act 2012, Biodiversity Conservation Act 2016, Protection of the Environment Operations Act 1997 and associated regulations. Under the Forestry Act 2012, the objectives of FCNSW include, where its activities affect the environment, to conduct its operations in compliance with the principles of ecologically sustainable development contained in section 6(2) of the Protection of the Environment Administration Act 1991. This involves the integration of social, economic and environmental considerations in decision-making processes.

In undertaking its native forestry operations, FCNSW must comply with Integrated Forestry Operations Approvals (IFOA), issued jointly by the Minister for the Environment and the Minister for Agriculture, which set out rules to protect species and ecosystems where timber harvesting is occurring, and aim to ensure forests are managed in an ecologically sustainable way. FCNSW must also ensure that its contractors undertake forestry operations in line with IFOAs. The Coastal IFOA, developed in 2018, consolidated the four IFOAs for the Eden, Southern, Upper and Lower North East coastal regions of New South Wales into a single IFOA. The other three current IFOAs are Brigalow Nandewar, South Western Cypress and Riverina Redgum (the Western IFOAs).

The NSW Environment Protection Authority (EPA) is responsible for regulating native forestry in New South Wales. Under the Protection of the Environment Administration Act 1991, one of the objectives of the EPA is to protect, restore and enhance the quality of the environment in New South Wales, having regard to the need to maintain ecologically sustainable development. This includes monitoring FCNSW’s compliance with IFOA conditions, including by maintaining and enforcing a compliance program.

The Coastal IFOA also introduced a new structure and regulatory approach for IFOAs, establishing outcomes, conditions and protocols. The conditions set mandatory actions and controls intended to protect threatened plants, animals, habitats, soils and water. The protocols, referenced in the conditions, set out additional enforceable actions and controls intended to support the effective implementation of the conditions.

Public native forestry is the largest component of hardwood supply in New South Wales. The 2019–20 bushfires had a major impact on regional communities, and large areas of native forest. This heightened environmental risks and challenges in public native forestry. Five million hectares of New South Wales was impacted, including more than 890,000 hectares of native State Forests. This is over 40% of the coastal and tablelands native State Forests in New South Wales.

In addition to effective compliance activities, the success of the regulatory approach to public native forestry operations depends on how wood supply yields are modelled, and ensuring that harvested volumes do not exceed these yields. This is of particular importance in areas where forests have been severely damaged by fire. This audit did not consider sustainable yields. Recent reviews of this include an independent review of the FCNSW sustainable yield model and a Natural Resources Commission review in 2021.

This audit assessed how effectively Forestry Corporation of NSW manages its public native forestry activities to ensure compliance, and how effectively the Environment Protection Authority regulates these activities.

Conclusion

Forestry Corporation of NSW (FCNSW) clearly articulates its compliance obligations at the corporate level and for each harvest site. However, there are deficiencies in FCNSW’s compliance approach. While FCNSW undertakes monitoring of its contractors in a number of ways, it does not consistently monitor compliance across its contractors and does not target its monitoring activities on a risk basis. This increases the risk that non-compliant practices will not be identified, potentially leading to environmental harm.

FCNSW has a compliance strategy and program that sets out its compliance obligations and how they will be managed. FCNSW’s Compliance Policy outlines compliance requirements, actions to ensure compliance, and responsibilities for staff, supervisors, senior management and board members. FCNSW also has a compliance monitoring system manual that outlines its monitoring program, and its risk-assessment and incident reporting procedures. These corporate documents set out FCNSW’s overall approach to managing compliance.

Harvesting in State Forests is undertaken by contractors or sub-contractors. FCNSW provides training to its staff and contractors and undertakes monitoring to identify contractor compliance with relevant requirements through a variety of means, including its quality assurance assessment (QAA) program. FCNSW also communicates compliance obligations to contractors in harvest plans.

FCNSW is not undertaking its monitoring activities on a risk basis. The frequency of contractor supervision is inconsistent and is not tied to the contractor’s past performance, meaning that monitoring resources are not necessarily being targeted at the areas of highest -risk.

FCNSW also does not target its QAAs on a risk basis. FCNSW does not have procedures for how QAAs should occur outside the North Coast region. QAAs are conducted inconsistently, with some reviews occurring in only part of the harvest site while others cover the whole harvest site. In addition, some QAAs do not meet FCNSW’s minimum standards. FCNSW’s record keeping of QAAs is also inconsistent, making it difficult to determine true levels of compliance and the cause of identified potential non-compliances.

In addition, FCNSW does not collate and analyse the results of its compliance monitoring to target its compliance audits. Undertaking these audits on a risk basis would allow FCNSW to apply its resources to the highest-risk harvest sites and contractors.

The EPA identifies native forestry as a high priority regulatory activity and undertakes proactive inspections of Coastal IFOA harvest sites on a risk basis. However, the EPA does not assess the risk at Western IFOA harvest sites, leaving a significant gap in its inspection regime. This means that the EPA may not be inspecting all high-risk harvest sites to ensure compliance with regulations across those sites. The EPA has started to train more of its staff in conducting forestry inspections, but it currently has a limited number of trained and experienced staff to undertake this work.

The EPA has developed a Regulatory and Compliance Priorities Statement 2022–23 which identifies native forestry as a key risk. This statement identifies that forestry is a priority area for its compliance activities because of the increased environmental risk and sensitivity in forests following the 2019–20 bushfires. A divisional plan for its regulatory operations contains specific actions for forestry, including ensuring that the EPA has a consistent approach to recording regulatory actions undertaken and identifying priority areas for assurance over State Forests.

As part of its compliance activities, the EPA responds to complaints received, or reports of non-compliance, across all four IFOA areas and also carries out proactive inspections in the Coastal IFOA area. To guide these inspections, the EPA determines the level of risk posed by each harvest site in the Coastal IFOA area using information it gathers from FCNSW. The EPA prioritises inspections of sites rated as high and medium-risk, but the EPA has not undertaken risk-assessments for the three Western IFOAs. By not determining the risks in these areas, the EPA does not have assurance that it is checking FCNSW compliance with regulations across all high-risk sites.

Most EPA staff have basic training in forestry matters, but few staff have the more advanced training required to effectively undertake forestry inspections. In addition, not all EPA officers have access to the technology required to undertake forestry inspections, such as internet-enabled tablets and specialised tapes for measuring tree diameter. This limits the EPA’s ability to determine the level of compliance with regulations and respond effectively to instances of environmental harm in relation to public native forestry.

The Coastal IFOA does not contain provisions which allow the EPA to unilaterally restrict forestry activities in the aftermath of a catastrophic event such as the 2019–20 bushfires. Following the bushfires, FCNSW approached the EPA and asked for additional site-specific operating conditions (SSOC) at some locations to assist it in maintaining compliance. The SSOCs were issued by the EPA and FCNSW was required to carry out forestry operations in accordance with the SSOCs at relevant harvest sites. These SSOCs were in place for 12 months. After a year, FCNSW decided not to renew this approach with the EPA, but implemented its own voluntary measures during harvesting operations. Unlike the SSOCs, the EPA was unable to undertake enforcement activities for breaches of voluntary measures.

Appendix one – Responses from agencies
Appendix two – About the audit
Appendix three – Performance auditing

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #382 - released 22 June 2023

Published

Actions for Regulation and monitoring of local government

Regulation and monitoring of local government

Planning
Whole of Government
Environment
Local Government
Compliance
Regulation
Risk

What the report is about

The Office of Local Government (OLG) in the Department of Planning and Environment is responsible for strengthening the local government sector, including through its regulatory functions.

This audit assessed whether the OLG is effectively monitoring and regulating the sector under the Local Government Act 1993. The audit covered:

  • the effectiveness of departmental arrangements for the OLG to undertake its regulatory functions
  • whether the OLG has effective mechanisms to monitor and respond to risks and issues relating to council compliance and performance.

What we found

The OLG does not conduct effective, proactive monitoring to enable timely risk-based responses to council performance and compliance issues.

The OLG has not clearly defined and communicated its regulatory role to ensure that its priorities are well understood.

The OLG does not routinely review the results of its regulatory activities to improve its approaches.

The department lacks an adequate framework to define, measure and report on the OLG's performance, limiting transparency and its accountability.

The OLG's new strategic plan presents an opportunity for the OLG to better define, communicate, and deliver on its regulatory objectives.

What we recommended

The OLG should:

  • publish a tool to support councils to self-assess risks and report on their performance and compliance
  • ensure its council engagement strategy is consistent with its regulatory approach
  • report each year on its regulatory activities and performance
  • publish a calendar of its key sector support and monitoring activities
  • enhance processes for internally tracking operational activities
  • develop and maintain a data management framework
  • review and update frameworks and procedures for regulatory responses.

 

The Local Government Act 1993 (the LG Act) provides the legal framework for the system of local government in New South Wales. The LG Act describes the functions of councils, county councils and joint organisations which should be exercised consistent with the guiding principles and requirements of the LG Act. Councils also have functions and responsibilities under other Acts.

There are 128 local councils, nine county councils and 13 joint organisations of councils in the New South Wales local government sector. Each council is unique in size and location, owns and manages assets, and delivers services for their communities. According to 2021–22 data provided by the Department of Planning and Environment (the department), local councils managed $175.2 billion in infrastructure, property plant and equipment, held $16.8 billion of cash and investments, collected $7.8 billion in rates and charges and entered into $3.7 billion of borrowings. Councils' decision-making responsibilities directly impact the communities they serve, including responsibilities relevant to financial management, economic development, environmental sustainability and community wellbeing.

Under the LG Act, each elected council is accountable to the community they serve. In addition to Auditor-General reports, issues relating to council performance and compliance have been identified in public inquiries commissioned by the Minister for Local Government and investigations by the Independent Commission Against Corruption, NSW Ombudsman and Office of Local Government (OLG). Challenges and opportunities related to the operations and sustainability of the local government sector have also been reported by the sector and identified in reports by NSW government agencies such as the Independent Pricing and Regulatory Tribunal.

The department is the primary state government agency with responsibility for policy, legislative, regulatory and program functions for local government matters. The Office of Local Government (OLG) is a business unit within the department that advises the Minister for Local Government and exercises delegated functions of the Secretary of the Department of Planning and Environment under the LG Act.

Key departmental planning documents state that the OLG is responsible for strengthening the sustainability, performance, integrity, transparency and accountability of the local government sector. As the state regulator of the local government sector, the OLG aims to promote voluntary compliance, build councils' capacity for high performance, and intervene only when 'warranted and appropriate'. Relevant regulatory activities include issuing guidelines, investigating councils and councillors, and supporting the Minister for Local Government's discretionary intervention powers. The OLG's other functions include developing policy, administering grants and programs, supporting local government election processes, and issuing certain approvals.

The objective of this audit was to assess whether the OLG is effectively monitoring and regulating the local government sector under the LG Act. The assessment included:

  • the effectiveness of departmental arrangements for the OLG to undertake its regulatory functions
  • whether the OLG has effective mechanisms to monitor and respond to risks and issues relating to council compliance and performance.

This report focuses on the OLG’s activities relevant to powers under Chapter 13 of the LG Act, and related regulatory activities, such as monitoring risks, issuing guidance and engaging with councils. It also examines strategic and operational planning for these activities in the context of the OLG's other activities, and departmental arrangements to oversee and enable the OLG's regulatory effectiveness.

Other OLG activities were not in scope of the audit but are commented on in this report where contextually relevant. This includes the OLG's responsibilities under the LG Act with respect to councillor misconduct, and the 2022 review of the councillor misconduct framework commissioned by the former Minister for Local Government.

Conclusion

The Office of Local Government (OLG) in the Department of Planning and Environment (the department) does not conduct effective, proactive monitoring to enable timely risk-based responses to council performance and compliance issues. Council performance and compliance varies and a range of issues continue across the local government sector – some significant – that can impact on councils' operations and sustainability.

The department recognises that an effective and efficient sector is 'crucial to the economic and social wellbeing of communities across the State,' but the OLG does not routinely review the results of its regulatory activities to improve its approaches. The OLG has also not clearly defined and communicated its regulatory role to ensure that its priorities are well understood.

Inadequate performance measurement and reporting on its regulatory activities is a significant transparency and accountability issue, and the OLG cannot demonstrate that it is effectively regulating the local government sector.

The department lacks an adequate framework to define, measure and report on the OLG's performance as the state regulator of the sector under the Local Government Act 1993 (the LG Act). The OLG's various council engagement activities are not well structured and coordinated towards delivering on a clearly defined regulatory role and its regulatory priorities are not well understood. In 2022, the OLG identified, in its new strategic plan, that there is a need for it to define its role in the sector. It would be expected that a clearly defined role already underpins its aim to 'strike the right mix of monitoring, intervention, capability improvement and engagement activities'.

The OLG collects various sources of information about council compliance and performance but its systems and processes do not enable structured, proactive sector monitoring to enable timely, risk-based responses. Ineffective sector monitoring is a particular issue in the context of compliance, financial management and governance risks that have been identified in inquiries and reviews by other government agencies including integrity bodies and reported by the sector. Audit Office data for 2021–22 shows that 62 councils did not have or regularly update key corporate governance policies, and 63 do not have basic controls to manage cyber security risks. Further, 31 councils or joint organisations did not meet the statutory requirement to have an audit, risk and improvement committee by 30 June 2022.1

Overall, the OLG has made limited progress on projects that have been identified since 2019 to improve its sector monitoring, such as updating its performance measurement framework for councils. These factors limit its capacity to identify and act on issues early. In early 2023, the OLG started to implement a new council risk assessment tool.

The OLG's two main frameworks to guide its sector improvement and intervention activities were last updated in 2014 and 2017. The OLG considered relevant statutory criteria when advising the Minister on the use of powers to issue performance improvement and suspension orders under the LG Act. But the OLG lacks complete and approved procedures to guide staff when preparing advice and recommendations related to interventions, and other response options. This creates risks to the consistency and transparency of relevant processes.

The department and the OLG have identified that resourcing issues present a risk to the OLG's regulatory functions. Projects since 2021 to review the OLG's budget did not progress. The OLG does not routinely review the costs or evaluate the effectiveness of its regulatory activities.

The OLG's 2022–2026 strategic plan sets out a vision to be, 'A trusted regulator and capability builder enabling councils to better serve their communities'. Implementing the strategic plan presents an opportunity for the OLG to better define, communicate, and deliver on its regulatory objectives towards strengthening the sector. The OLG advises that a delivery plan and performance indicators for its new strategy are being developed, alongside work resulting from the 2022 review of the councillor misconduct framework.

 


1 This data has been sourced through the Audit Office's financial audits of councils. The Local Government 2022 report, which compiles results from the local government sector financial statement audits for the year ended 30 June 2022, will include this and additional data, and related information. This report is expected to be tabled in June 2023.

This chapter considers the effectiveness of departmental arrangements for the OLG to undertake its regulatory functions.

This chapter assesses whether the OLG has effective mechanisms to monitor and respond to risks and issues relating to council compliance and performance.

The OLG’s 2017 Improvement and Intervention Framework is intended to guide appropriate responses to council compliance or performance risks and issues. The publicly available framework states that generally, the OLG will encourage councils to meet their obligations before a more formal intervention will be considered. It also states that any intervention or improvement response will be proportionate to the circumstances.

Appendix one – Response from agency

Appendix two – Statutory powers relevant to council accountability under the Local Government Act

Appendix three – About the audit

Appendix four – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #380 - released 23 May 2023

Published

Actions for Planning and managing bushfire equipment

Planning and managing bushfire equipment

Community Services
Justice
Planning
Environment
Local Government
Asset valuation
Compliance
Financial reporting
Information technology
Infrastructure
Internal controls and governance
Management and administration
Procurement
Regulation
Risk
Shared services and collaboration
Workforce and capability

What the report is about

This audit assessed the effectiveness of the NSW Rural Fire Service (RFS) and local councils in planning and managing equipment for bushfire prevention, mitigation, and suppression.

What we found

The RFS has focused its fleet development activity on modernising and improving the safety of its firefighting fleet, and on the purchase of new firefighting aircraft.

There is limited evidence that the RFS has undertaken strategic fleet planning or assessment of the capability of the firefighting fleet to respond to current bushfire events or emerging fire risks.

The RFS does not have an overarching strategy to guide its planning, procurement, or distribution of the firefighting fleet.

The RFS does not have effective oversight of fleet maintenance activity across the State, and is not ensuring the accuracy of District Service Agreements with local councils, where maintenance responsibilities are described.

What we recommended

  1. Develop a fleet enhancement framework and strategy that is informed by an assessment of current fleet capability, and research into appropriate technologies to respond to emerging fire risks.
  2. Develop performance measures to assess the performance and capabilities of the fleet in each RFS District by recording and publicly reporting on fire response times, fire response outcomes, and completions of fire hazard reduction works.
  3. Report annually on fleet allocations to RFS Districts, and identify the ways in which fleet resources align with district-level fire risks.
  4. Develop a strategy to ensure that local brigade volunteers are adequate in numbers and appropriately trained to operate fleet appliances in RFS Districts where they are required.
  5. Establish a fleet maintenance framework to ensure regular update of District Service Agreements with local councils.
  6. Review and improve processes for timely recording of fleet asset movements, locations, and maintenance status.

This audit assessed how effectively the NSW Rural Fire Service (the RFS) plans and manages the firefighting equipment needed to prevent, mitigate, and suppress bushfires. This audit also examined the role of local councils in managing bushfire equipment fleet assets. Local councils have vested legal ownership of the majority of the land-based firefighting fleet, including a range of legislated responsibilities to carry out fleet maintenance and repairs. The RFS has responsibilities to plan and purchase firefighting fleet assets, and ensure they are ready for use in response to fires and other emergencies.

This report describes the challenges in planning and managing the firefighting fleet, including a confusion of roles and responsibilities between the RFS and local councils in relation to managing certain land-based rural firefighting fleet – a point that has been made in our Local Government financial audits over several years. This role confusion is further demonstrated in the responses of the RFS and local councils to this audit report – included at Appendix one.

The lack of cohesion in roles and responsibilities for managing rural firefighting vehicles increases the risk that these firefighting assets are not properly maintained and managed, and introduces a risk that this could affect their readiness to be mobilised when needed.

While the audit findings and recommendations address some of the operational and organisational inefficiencies in relation to rural firefighting equipment management, they do not question the legislative arrangements that govern them. This is a matter for the NSW Government to consider in ensuring the fleet arrangements are fit for purpose, and are clearly understood by the relevant agencies.

The NSW Rural Fire Service (hereafter the RFS) is the lead combat agency for bushfires in New South Wales, and has the power to take charge of bushfire prevention and response operations anywhere in the State. The RFS has responsibilities to prevent, mitigate and suppress bushfires across 95% of the State, predominantly in the non-metropolitan areas of New South Wales. Fire and Rescue NSW is responsible for fire response activity in the cities and large townships that make up the remaining five per cent of the State.

The RFS bushfire fleet is an integral part of the agency's overall bushfire risk management. The RFS also uses this fleet to respond to other emergencies such as floods and storms, motor vehicle accidents, and structural fires. Fleet planning and management is one of a number of activities that is necessary for fire mitigation and suppression.

The Rural Fires Act 1997 (Rural Fires Act) imposes obligations on all landowners and land managers to prevent the occurrence of bushfires and reduce the risk of bushfires from spreading. Local councils have fire prevention responsibilities within their local government areas, principally to reduce fire hazards near council owned or managed assets, and minor roads.

The RFS is led by a Commissioner and is comprised of both paid employees and volunteer rural firefighters. Its functions are prescribed in the Rural Fires Act and related legislation such as the State Emergency Rescue Management Act 1989. The RFS functions are also described in Bush Fire Risk Management Plans, the State Emergency Management Plan, District Service Agreements, and RFS procedural documents. Some of the core responsibilities of the RFS include:

  • preventing, mitigating, and suppressing fires across New South Wales
  • recruiting and managing volunteer firefighters in rural fire brigades
  • purchasing and allocating firefighting fleet assets to local councils
  • establishing District Service Agreements with local councils to give the RFS permissions to use the fleet assets that are vested with local councils
  • carrying out fleet maintenance and repairs when authorised to do so by local councils
  • inspecting the firefighting fleet
  • supporting land managers and private property owners with fire prevention activity.

In order to carry out its legislated firefighting functions, the RFS relies on land-based vehicles, marine craft, and aircraft. These different firefighting appliance types are referred to in this report as the firefighting fleet or fleet assets.

RFS records show that in 2021 there were 6,345 firefighting fleet assets across NSW. Most of the land-based appliances commonly associated with firefighting, such as water pumpers and water tankers, are purchased by the RFS and vested with local councils under the Rural Fires Act. The vesting of firefighting assets with local councils means that the assets are legally owned by the council for which the asset has been purchased. The RFS is able to use the firefighting assets through District Service Agreements with local councils or groups of councils.

In addition to the land-based firefighting fleet, the RFS owns a fleet of aircraft with capabilities for fire mitigation, suppression, and reconnaissance during fire events. The RFS hires a fleet of different appliances to assist with fire prevention and hazard reduction works. These include aircraft for firefighting and fire reconnaissance, and heavy plant equipment such as graders and bulldozers for hazard reduction. Hazard reduction works include the clearance of bush and grasslands around major roads and protected assets, and the creation and maintenance of fire trails and fire corridors to assist with fire response activity.

The RFS is organised into 44 RFS Districts and seven Area Commands. The RFS relies on volunteer firefighters to assist in carrying out most of its firefighting functions. These functions may include the operation of the fleet during fire response activities and training exercises, and the routine inspection of the fleet to ensure it is maintained according to fleet service standards. Volunteer fleet inspections are supervised by the RFS Fire Control Officer.

In 2021 there were approximately 73,000 volunteers located in 1,993 rural fire brigades across the State, making the RFS the largest volunteer fire emergency service in Australia. In addition to brigade volunteers, the RFS has approximately 1,100 salaried staff who occupy leadership and administrative roles at RFS headquarters and in the 44 RFS Districts.

Local councils have legislative responsibilities relating to bushfire planning and management. Some of the core responsibilities of local councils include:

  • establishing and equipping rural fire brigades
  • contributing to the Rural Fire Fighting Fund
  • vested ownership of land-based rural firefighting equipment
  • carrying out firefighting fleet maintenance and repairs
  • conducting bushfire prevention and hazard reduction activity.

The objective of this audit was to assess the effectiveness of the RFS and local councils in planning and managing equipment for bushfire prevention, mitigation, and suppression. From the period of 2017 to 2022 inclusive, we addressed the audit objective by examining whether the NSW RFS and local councils effectively:

  • plan for current and future bushfire fleet requirements
  • manage and maintain the fleet required to prevent, mitigate, and suppress bushfires in NSW.

This audit did not assess:

  • the operational effectiveness of the RFS bushfire response
  • the effectiveness of personal protective equipment and clothing
  • the process of vesting of rural firefighting equipment with local councils
  • activities of any other statutory authorities responsible for managing bushfires in NSW.

As the lead combat agency for the bushfire response in NSW, the RFS has primary responsibility for bushfire prevention, mitigation, and suppression.

Three local councils were selected as case studies for this audit, Hawkesbury City Council, Wagga Wagga City Council and Uralla Shire Council. These case studies highlight the ways in which the RFS and local councils collaborate and communicate in rural fire districts.

Conclusion

The RFS has focused its fleet development activity on modernising and improving the safety of its land-based firefighting fleet, and on the purchase of new firefighting aircraft

The RFS has reduced the average age of the firefighting fleet from approximately 21 years in 2017, to approximately 16 years in 2022. The RFS has also enhanced the aerial fleet with the addition of six new aircraft to add to the existing three aircraft.

Recommendations from inquiries into the 2019–20 bushfires have driven significant levels of fleet improvement activity, mainly focused on the addition of safety features to existing fleet appliances. The RFS has dedicated most of its efforts to purchasing and refurbishing firefighting appliances of the same type and in the same volumes year on year.

However, the RFS is unable to demonstrate how the composition, size, or the locations of the NSW firefighting fleet is linked to current fire prevention, mitigation, and suppression requirements, or future fire risks.

There is limited evidence that the RFS has undertaken strategic fleet planning or assessment of the capability of the firefighting fleet to respond to current bushfire events or emerging fire risks

The RFS has not established a methodology to assess the composition or volumes of the firefighting fleet against fire activity and fire risks in the 44 NSW Rural Fire Districts. The RFS has not developed performance measures or targets to assess or report on fire response times in each of its districts, nor has it developed measures to assess the effectiveness of responses according to fire sizes and fire types. Similarly, the RFS has limited performance measures to assess fire prevention activity, or to assess fuel load reduction works, so it is not possible to assess whether its fleet capabilities are fit for these purposes.

The RFS does not have an overarching strategy to guide its planning, procurement, or distribution of the firefighting fleet

RFS fleet planning and fleet allocations are based on historical fleet sizes and compositions, and distributed to locations where there are appropriately trained brigade volunteers.

The RFS takes an asset protection approach to bushfire prevention and planning that is based on the Australian and New Zealand Standard for Risk Management. This approach requires that the RFS identify assets at risk of fire, and develop treatment plans to protect these assets. However, fleet requirements are not linked to NSW asset protection plans, meaning that fleet is not allocated according to the identified risks in these plans. Further, the RFS does not develop fire prevention plans for areas where there are no identified assets.

The RFS has not conducted future-focused fleet research or planning into technologies that match fleet capabilities to emerging or future fire risks. Since the significant fire events of 2019–2020, the RFS has not changed its approach to planning for, or assessing, the operational capabilities of the fleet. The RFS advises it is scoping a project to match resources to risk, which it plans to commence in 2023.

The RFS does not have effective oversight of fleet maintenance activity across the State, and is not ensuring the accuracy of District Service Agreements where maintenance responsibilities are described

The RFS does not have a framework to ensure that District Service Agreements with local councils are accurate. Almost two thirds of service agreements have not been reviewed in the last ten years, and some do not reflect actual maintenance practices. There is no formalised process to ensure communication occurs between the RFS and local councils for fleet management and maintenance.

RFS fleet management systems at the central level are not integrated with RFS district-level databases to indicate when fleet assets are in workshops being maintained and serviced. The RFS has a new centralised Computer Aided Dispatch System that relies on accurate fleet locations and fleet condition information in order to dispatch vehicles to incidents and fires. A lack of interface between the district-level fleet systems and the centralised RFS fleet dispatch system, may impact on operational responses to bushfires. 

The RFS has not made significant changes to the size or composition of the firefighting fleet in the past five years and does not have an overarching strategy to drive fleet development

Since 2017, the RFS has made minimal changes to its firefighting fleet volumes or vehicle types. The RFS is taking a fleet renewal approach to fleet planning, with a focus on refurbishing and replacing ageing firefighting assets with newer appliances and vehicles of the same classification and type. While the RFS has adopted a fleet renewal approach, driven by its Appliance Replacement Program Guide, it does not have a strategy or framework to guide its future-focused fleet development. There is no document that identifies and analyses bushfire events and risks in NSW, and matches fleet resources and fleet technologies to meet those risks. The RFS does not have fleet performance measures or targets to assess whether the size and composition of the fleet is meeting current or emerging bushfire climate hazards, or fuel load risks across its 44 NSW Fire Districts.

The RFS fleet currently comprises approximately 4,000 frontline, operational firefighting assets such as tankers, pumpers, and air and marine craft, and approximately 2,300 logistical vehicles, such as personnel transport vehicles and specialist support vehicles. Of the land-based firefighting vehicles, the RFS has maintained a steady number of approximately 3,800 tankers and 65 pumpers, year on year, for the past five years. This appliance type is an essential component of the RFS land-based, firefighting fleet with capabilities to suppress and extinguish fires.

Since 2017, most RFS fleet enhancement activity has been directed to upgrades and the modernisation of older fleet assets with new safety features. There is limited evidence of research into new fleet technologies for modern firefighting. The RFS fleet volumes and fleet types have remained relatively static since 2017, with the exception of the aerial firefighting fleet. Since 2017, the RFS has planned for, and purchased, six additional aircraft to add to the existing three aircraft in its permanent fleet.

While the RFS has made minimal changes to its fleet since 2017, in 2016 it reduced the overall number of smaller transport vehicles, by purchasing larger vehicles with increased capacity for personnel transport. The consolidation of logistical and transport vehicles accounts for an attrition in fleet numbers from 7,058 in 2016, to 6,315 in 2017 as shown in Exhibit 2.

The firefighting fleet management system is not always updated in a timely manner due to insufficient RFS personnel with permissions to make changes in the system

The RFS uses a fleet management system known as SAP EAM to record the location and status of firefighting fleet assets. The system holds information about the condition of the firefighting fleet, the home location of each fleet asset, and the maintenance, servicing, and inspection records of all assets. The RFS uses the system for almost all functions related to the firefighting fleet, including the location of vehicles so that they can be dispatched during operational exercises or fire responses.

Staff at RFS Headquarters are responsible for creating and maintaining asset records in the fleet management system. RFS District staff have limited permissions in relation to SAP EAM. They are able to raise work orders for repairs and maintenance, upload evidence to show that work has been done, and close actions in the system.

RFS District staff are not able to enter or update some fleet information in the system, such as the location of vehicles. When an RFS District receives a fleet appliance, it cannot be allocated to a brigade until the location of the asset is accurately recorded in the system. The location of the asset must be updated in the SAP EAM system by staff at RFS Headquarters. District staff can request system support from staff at RFS Headquarters to enter this information. At the time of writing, the position responsible for updating the fleet management system at RFS Headquarters was vacant, and RFS District personnel reported significant wait times in response to their service requests.

The RFS conducts annual audits of SAP EAM system information to ensure data is accurate and complete. RFS staff are currently doing data cleansing work to ensure that fleet allocations are recorded correctly in the system.

Communication between brigades, local councils and the RFS needs improvement to ensure that fleet information is promptly updated in the fleet management system

RFS brigade volunteers do not have access to the fleet management system. When fleet assets are used or moved, volunteers report information about the location and condition of the fleet to RFS District staff using a paper-based form, or by email or phone. Information such as vehicle mileage, engine hours, and defects are all captured by volunteers in a logbook which is scanned and sent to RFS District staff. RFS District staff then enter the relevant information into the fleet management system, or raise a service ticket with RFS Headquarters to enter the information.

Brigade volunteers move fleet assets for a range of reasons, including for fire practice exercises. If volunteers are unable to report the movement of assets to RFS District staff in a timely manner, this can lead to system inaccuracies. Lapses and backlogs in record keeping can occur when RFS staff at district offices or at Headquarters are not available to update records at the times that volunteers report information. A lack of accurate record keeping can potentially impact on RFS operational activities, including fire response activity.

Brigade volunteers notify RFS District staff when fleet appliances are defective, or if they have not been repaired properly. District staff then enter the information into the fleet management system. The inability of volunteers to enter information into the system means they have no visibility over their requests, including whether they have been approved, actioned, or rejected.

Local councils are responsible for servicing and maintaining the firefighting fleet according to the Rural Fires Act, but this responsibility can be transferred to the RFS through arrangements described in local service agreements. Council staff record all fleet servicing and maintenance information in their local systems. The types of fleet information that is captured in local council records can vary between councils. RFS staff described the level of council reporting, and the effectiveness of this process, as 'mixed'.

Councils use different databases and systems to record fleet assets, and some councils are better resourced for this activity than others

Firefighting fleet information is recorded in different asset management systems across NSW. Each council uses its own asset management system to record details about the vested fleet assets. All three councils that were interviewed for this audit had different systems to record information about the fleet. In addition, the type of information captured by the three councils was varied.

Exhibit 10: Systems used by local councils to manage the firefighting fleet
System Hawkesbury City Council Uralla Shire Council Wagga Wagga City Council
Financial asset management system TechnologyOne Civica Assetic
Asset management system TechnologyOne Manual MEX

Source: Audit Office analysis of information provided by the RFS and local councils.

Local councils have varying levels of resources and capabilities to manage the administrative tasks associated with the firefighting fleet. Some of the factors that impact on the ability of councils to manage administrative tasks include: the size of the council; the capabilities of the information management systems, the size of the staff team, and the levels of staff training in asset management.

Uralla Shire Council is a small rural council in northern NSW. This council uses financial software to record information about the firefighting fleet. While staff record information about the condition of the asset, its replacement value, and its depreciation, staff do not record the age of the asset, or its location. Staff manually enter fleet maintenance information into their systems. Uralla Shire Council would like to purchase asset maintenance software that generates work orders for fleet repairs and maintenance. However, the council does not have trained staff in the use of asset management software, and the small size of the fleet may not make it financially worthwhile.

The Hawkesbury City Council uses a single system to capture financial and asset information associated with the firefighting fleet. Hawkesbury is a large metropolitan council located north-west of Sydney, with a relatively large staff team in comparison with Uralla Shire Council. The Hawkesbury City Council has given RFS District staff access to their fleet information system. RFS District staff can directly raise work orders for fleet repairs and maintenance through the council system, and receive automated notifications when the work is complete.

Two of the three audited councils report that they conduct annual reviews of fleet assets to assess whether the information they hold is accurate and up-to-date.

More than half of the fleet maintenance service agreements between the RFS and local councils have not been reviewed in ten years, and some do not reflect local practices

Local councils have a legislated responsibility to service, repair, and maintain the firefighting fleet to service standards set by the RFS. Councils may transfer this responsibility to the RFS through District Service Agreements. The RFS Districts are responsible for ensuring that the service agreements are current and effective.

The RFS does not have monitoring and quality control processes to ensure that service agreements with local councils are reviewed regularly. The RFS has 73 service agreements with local councils or groups of councils. Sixty-three per cent of service agreements had not been reviewed in the last ten years. Only four service agreements specify an end date and, of those, one agreement expired in 2010 and had not been reviewed at the time of this audit.

The RFS does not have a framework to ensure that service agreements with local councils reflect actual practices. Of the three councils selected for audit, one agreement does not describe the actual arrangements for fleet maintenance practices in RFS Districts. The service agreement with Hawkesbury City Council specifies that the RFS will maintain the firefighting fleet on behalf of council when, in fact, council maintains the firefighting fleet. The current agreement commenced in 2012, and at the time of writing had not been updated to reflect local maintenance practices.

When District Service Agreements are not reviewed periodically, there is a risk that neither local councils nor the RFS have clear oversight of the status of fleet servicing, maintenance, and repairs.

RFS District Service Agreements set out a requirement that RFS and local councils establish a liaison committee. Liaison committees typically include council staff, RFS District staff, and RFS brigade volunteers. While service agreements state that liaison committees must meet periodically to monitor and review the performance of the service agreement, committee members determine when and how often the committee meets.

RFS District staff and staff at the three audited councils are not meeting routinely to review or update their service agreements. At Wagga Wagga City Council, staff meet with RFS District staff each year to report on activity to fulfil service agreement requirements. Uralla Shire Council staff did not meet routinely with RFS District staff before 2021. When liaison committees do not meet regularly, there is a risk that the RFS and local councils have incorrect or outdated information about the location, status, or condition of the firefighting fleet. Given that councils lack systems to track and monitor fleet locations, regular communication between the RFS and local councils is essential.

The RFS has not established processes to ensure that local councils and RFS District personnel meet and exchange information about the fleet. Of the three councils selected for this audit, one council had not received information about the number, type, or status of the fleet for at least five years, and did not receive an updated list of appliances until there was a change in RFS District personnel. This has impacted on the accuracy of council record keeping. Councils do not always receive notification about new assets or information about the location of assets from the RFS, and therefore cannot reflect this information in their accounting and reporting.

RFS area commands audit system records to ensure fleet inspections occur as planned, but central systems are not always updated, creating operational risks

RFS District staff are required by the Rural Fires Act to ensure the firefighting fleet is inspected at least once a year. Regular inspections of the fleet are vital to ensure that vehicles are fit-for-purpose and safe for brigade volunteers. Inspections are also fundamental to the operational readiness and capability of RFS to respond to fire incidents.

RFS Area Command personnel conduct audits of fleet maintenance data to ensure that fleet inspections are occurring as planned. These inspections provide the RFS with assurance that the fleet is being maintained and serviced by local council workshops, or third-party maintenance contractors.

Some RFS Districts run their own fleet management systems outside of the central management system. They do this to manage their fleet inspection activity effectively. Annual fleet inspection dates are programmed by staff at RFS Headquarters. Most of the inspection dates generated by RFS Headquarters are clustered together and RFS Districts need to separate inspection times to manage workloads over the year. Spreading inspection dates is necessary to avoid exceeding the capacity of local council workshops or third party contractors, and to ensure that fleet are available during the bushfire season.

The fleet inspection records at RFS Headquarters are not always updated in a timely manner to reflect actual inspection and service dates of vehicles. District staff are not able to change fleet inspection and service dates in the central management system because they do not have the necessary permissions to access the system. The usual practice is for RFS District staff to notify staff at RFS Headquarters, and ask them to retrospectively update the system. As there is a lag in updating the central database, at a point in time, the actual inspection and service dates of vehicles can be different to the dates entered in the central fleet management system.

Fleet inspection and maintenance records must be accurately recorded in the central RFS management system for operational reasons. RFS Headquarters personnel need to know the location and maintenance status of fleet vehicles at all times in order to dispatch vehicles to incidents and fires. The RFS fleet management system is integrated with a new Computer Aided Dispatch System. The Computer Aided Dispatch System assigns the nearest and most appropriate vehicles to fire incidents. The system relies on accurate fleet locations and fleet condition information in order to dispatch these vehicles.

There is a risk that RFS Headquarters' systems do not contain accurate information about the location and status of vehicles. Some may be in workshops for servicing and repair, while the system may record them as available for dispatch. As there are many thousands of fleet vehicles, all requiring an annual service and inspection, a lack of accurate record keeping has wide implications for State fire operations.

RFS is currently exploring ways to improve the ways in which fleet inspections are programmed into the fleet management system.

RFS provides funds to councils to assist with maintaining the firefighting fleet, but does not receive fleet maintenance cost information from all local councils

Each year the RFS provides local councils with a lump sum to assist with the cost of repairing and maintaining the firefighting fleet. This lump sum funding is also used for meeting the costs of maintaining brigade stations, utilities, and other miscellaneous matters associated with RFS business.

In 2020–21, the RFS provided NSW local councils with approximately $23 million for maintenance and repairs of appliances, buildings, and utilities. Ninety councils were provided with lump sum funding in 2021, receiving on average $257,000. The amounts received by individual councils ranged from $56,200 to $1,029,884.

Some councils provide itemised repairs and maintenance reports to RFS District staff, showing the work completed and the cost of that work. However, not all councils collect this information or provide it to the RFS. Local councils collect fleet maintenance information in their local council systems. In some cases, the responsibility for fleet maintenance is shared across a group of councils, and not all councils have oversight of this process.

The RFS has not taken steps to require local councils to provide itemised maintenance costings for the firefighting fleet. Thus, the RFS does not have a clear understanding of how local councils are spending their annual fleet maintenance funding allocations. The RFS does not know if the funding allocations are keeping pace with the actual cost of repairing and maintaining the fleet.

RFS District staff report that funding shortfalls are impacting on the prioritisation of fleet servicing and maintenance works in some council areas. When fleet servicing and maintenance is not completed routinely or effectively, there is a risk that it can negatively impact the overall condition and lifespan of the vehicle. Poor processes in relation to fleet maintenance and repair risk impacting on the operational capabilities of the fleet during fire events.

The timeliness and effectiveness of fleet servicing and maintenance is affected by resource levels in RFS Districts and local councils

Local councils have a legislated responsibility to service and maintain the firefighting fleet to the service standards set by the RFS. Fleet maintenance is usually done by the entity with the appropriate workshops and resources, and the maintenance arrangements are described in District Service Agreements. RFS District staff conduct annual inspections to ensure that the firefighting fleet has been serviced and maintained appropriately, and is safe for use by brigade volunteers. If the fleet has not been maintained to RFS service standards or timelines, RFS District staff may work with local councils to support or remediate these works.

The effectiveness of this quality control activity is dependent on relationships and communication between the RFS Districts and local councils. While some RFS staff reported having positive relationships with local councils, others said they struggled to get fleet maintenance work done in a timely manner. Some councils reported that funding shortfalls for fleet maintenance activity was impacting on the prioritisation of RFS fleet maintenance works. When fleet maintenance work is not completed routinely or effectively, it can negatively impact on the overall condition and lifespan of the vehicle. It can also reduce the capacity of the RFS to respond to fire events.

Fleet quality control activities are carried out by RFS District staff. In some of the smaller RFS Districts, one person is responsible for liaising with local councils and brigade volunteers about fleet maintenance and repairs. In the regions where resources are limited, there is less ability to maintain ongoing communication. This is impacting on fleet service and maintenance timelines and the timeliness of fleet monitoring activity.

The RFS has mutual support arrangements with agencies in NSW and interstate, though shared fleet levels are yet to be quantified

The RFS has arrangements with state, federal, and international fire authorities to provide mutual support during fire incidents. In NSW, the RFS has agreements with the three statutory authorities – Fire and Rescue NSW, the Forestry Corporation of NSW, and the NSW National Parks and Wildlife Service. The agreement with Fire and Rescue NSW provides a framework for cooperation and joint operations between the agencies. The agreements with the Forestry Corporation of NSW and the NSW National Parks and Wildlife Service describe the control and coordination arrangements for bush and grass fires across NSW. These arrangements are set out in legislation and incorporated into local Bush Fire Risk Management Plans.

The RFS has agreements with fire authorities in three of the four Australian states and territories that share a border with NSW – the Australian Capital Territory, Queensland, and South Australia. Each agreement sets out the arrangements for mutual assistance and joint operations, including arrangements for sharing aircraft. The agreement between the RFS and Victoria had lapsed. The RFS told the NSW Bushfire Inquiry that the agreement with Victoria would be finalised by June 2020. In June 2022, the RFS reported that the agreement was in the process of being finalised.

The arrangements for mutual aid from Western Australia, Northern Territory and Tasmania, are managed by the National Resource Sharing Centre. These agreements set out the arrangements for interstate assistance between Australian fire services, emergency services, and land management agencies in those states and territories.

These mutual support arrangements may assist during state-based fire events. However, when there are competing demands for resources, such as during the bushfires of 2019–2020, there can be limits on fleet availability. During the 2019–2020 fires, resources were stretched in all jurisdictions as these fires affected NSW, Victoria, and Queensland.

There are opportunities for the RFS and other NSW agencies to quantify fleet resources across the State and identify assets that can be mobilised for different fire activities. This form of fleet planning may be used to enhance surge capabilities during times of high fire activity. There are also opportunities for the RFS and other agencies to match the levels of shared assets to projected bushfire risks.

Appendix one – Responses from agencies 

Appendix two – About the audit 

Appendix three – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #376 - released 27 February 2023

 

Published

Actions for Government's acquisition of private property: Sydney Metro project

Government's acquisition of private property: Sydney Metro project

Transport
Planning
Whole of Government
Compliance
Infrastructure
Internal controls and governance
Project management
Risk

What the report is about

Sydney Metro is Australia’s largest public transport project. It requires the acquisition of many private properties, including residential and business properties.

This audit assessed the effectiveness of the acquisition of private properties for the Sydney Metro project. The audited agencies were Sydney Metro, the Department of Planning and Environment (Valuer General NSW) and Transport for NSW (the Centre for Property Acquisition).

The audit assessed agencies against the framework for property acquisitions in New South Wales. It did not re-perform the valuations done for individual properties that were acquired by Sydney Metro.

What we found

Acquisitions of private property for the Sydney Metro project were mostly effective in the sample of acquisitions we assessed. We found Sydney Metro:

  • complied with legislative and policy requirements for compensation and communication with people subject to property acquisitions
  • kept accurate records of its acquisitions and applied probity controls consistently
  • did not complete detailed plans or negotiation strategies for the high-risk and high-value acquisitions we reviewed
  • did not comply with legislative timelines for most compulsory acquisitions because of delays in receiving the required information from the Valuer General in these cases.

The Centre for Property Acquisition has overseen the implementation of reforms to residential acquisition processes, but its assessment of the effectiveness of these reforms has not been comprehensive.

What we recommended

The audit made four recommendations to the audited agencies to improve:

  • plans and strategies for the acquisition of high-risk and high-value properties
  • timeliness of issuing compensation determinations for compulsory acquisitions
  • data quality on the experience of people subject to property acquisitions.

The NSW Government has the power to acquire land that is owned or leased by individuals or businesses, if it is needed for a public purpose. The power arises from the Land Acquisition (Just Terms Compensation) Act 1991 (the Just Terms Act). Government agencies that have the power to compulsorily acquire private property are referred to as ‘acquiring authorities’. People who are subject to acquisitions are referred to as ‘affected parties’ and include property owners (business or residential), businesses with a commercial lease on a property, or individuals with residential tenancy leases. In recent years, the vast majority of acquisitions by the NSW Government have been for public transport or road projects.

Sydney Metro is a NSW Government agency with responsibility for building the Sydney Metro railway project. Sydney Metro is Australia’s largest public transport project. The project requires the acquisition of a large number of private properties. Sydney Metro has been one of the largest acquirers of private property in recent years, completing over 500 acquisitions between 2020 and mid-2022, with a total acquisition value of over $2 billion. Other agencies and statutory officers involved in the acquisition of property for the Sydney Metro project include:

  • the Department of Planning and Environment (DPE), which supports the minister responsible for the Just Terms Act. DPE also provides staff to the Valuer General of NSW
  • the Valuer General of NSW, an independent statutory officer that determines compensation in cases where the acquiring authority and the affected party cannot agree on compensation for property that has been acquired
  • Transport for NSW, which includes the Centre for Property Acquisition (CPA). The CPA does not have a direct role in acquiring properties, but its responsibilities include developing guidance for acquiring agencies and monitoring and reporting on their activities.

About this audit

The objective of this audit was to assess the effectiveness of acquisitions of private properties for Sydney Metro projects. The audit assessed agencies against the legislative and policy requirements in place for government acquisitions of private property in New South Wales. In line with the Audit Office's legislative mandate, the audit does not comment on the merits of the policy objectives reflected in the Just Terms Act.

The audit examined a sample of 20 property acquisitions. This was not a statistically representative sample. While our report provides comments on Sydney Metro’s overall acquisition processes, it does not provide assurance regarding the acquisitions that were not examined for this audit.

The audit did not re-perform the valuations done for individual properties that were acquired by Sydney Metro. Affected parties who disagree with the valuation of their property have the right to seek independent assessment of this via the Valuer General and the Land and Environment Court.

Conclusion

Acquisitions of property for the Sydney Metro project were mostly effective in the sample of acquisitions we assessed. Sydney Metro followed requirements for communication with affected parties. Compensation processes were conducted in compliance with legislative requirements, but compensation determinations for compulsory acquisitions were not completed within legislated time frames due to delays in receiving these from the Valuer General. Governance and probity processes were followed consistently, with some relatively minor exceptions. 

Sydney Metro has detailed guidelines for acquisitions that are based on relevant legislation and government policy. In the 20 acquisitions we assessed for this audit, these procedures were followed consistently. This included adhering to minimum timelines for negotiation periods, engaging independent valuers and other experts when needed, and complying with governance and probity processes.

Sydney Metro staff followed requirements for communication and support for residential acquisitions by assigning ‘personal managers’ and providing additional support to affected parties when needed. The Centre for Property Acquisition (CPA) has overseen reforms to the residential property acquisition process in recent years. These reforms include the introduction of the NSW Property Acquisition Standards and the use of personal managers, in addition to the existing acquisition managers, for residential acquisitions. However, the CPA has not assessed the impact of these changes on the experiences on people affected by property acquisitions.

Sydney Metro did not comply with the legislative requirement to provide a formal compensation notice to the affected party within 45 days of a compulsory acquisition starting in any of the eight relevant acquisitions in our sample. This was because Sydney Metro must wait for the Valuer General to complete a compensation determination before Sydney Metro can send the compensation notice, and the Valuer General did not do this within 45 days. We acknowledge that Sydney Metro does not have full control over this process, and that it has taken steps to mitigate the impact of delays on affected parties. 

This chapter presents our findings on Sydney Metro's acquisition of industrial and commercial properties. Industrial properties include construction businesses and manufacturing facilities. Commercial properties were mostly properties such as shopping centres and office towers. Many of these acquisitions involve businesses and properties that are relatively complex and have high values. This means the valuation process can require multiple experts and can be lengthy and contested. Adherence to governance and probity requirements is important for these acquisitions in order to demonstrate that the acquiring authority has achieved value for money.

This chapter presents our findings on Sydney Metro's acquisition of residential properties, which include apartments and houses, and small business leases, which mostly affected businesses in small shopping centres or arcades. Most of these acquisitions were lower value compared to industrial and commercial property acquisitions and did not require as much expert advice on complex technical issues. However, residential property acquisitions can be personally distressing for the affected parties and require staff from the acquiring authority to provide support and show empathy while ensuring legislative compliance and value for money.

Appendix one – Responses from agencies

Appendix two – About the audit 

Appendix three – Performance auditing 

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #375 - released 9 February 2023

Published

Actions for Bushfire recovery grants

Bushfire recovery grants

Environment
Industry
Compliance
Internal controls and governance
Management and administration
Service delivery

What the report is about

The Bushfire Local Economic Recovery (BLER) program was created after the 2019–20 bushfires, and commits $541.8 million to bushfire affected areas in New South Wales. It is co-funded by the Commonwealth and NSW governments.

This audit assessed how effectively the Department of Regional NSW (the department) and Resilience NSW administered rounds one and two of the BLER program. These rounds were:

  • Round one: early co-funding, split between two streams:
    • ­Fast-Tracked projects 
    • ­Sector Development Grants (SDG)
  • Round two: open round.

What we found

The Department of Regional NSW did not effectively administer the Fast-Tracked stream of the BLER. 

The administration process lacked integrity, given it did not have sufficiently detailed guidelines and the assessment process for projects lacked transparency and consistency. 

At the request of the Deputy Premier's office, a $1 million threshold was applied, below which projects were not approved for funding. The department advises that some of the projects excluded were subsequently funded from other programs. 

This threshold resulted in a number of shortlisted projects in areas highly impacted by the bushfires being excluded, including all shortlisted projects located in Labor Party-held electorates.

The department's administration of the SDG stream had a detailed and transparent assessment process. However, conflicts of interest were not effectively managed. 

The department's administration of the open round included a clearly documented, detailed and transparent assessment framework. Some weaknesses in the approach to conflicts of interest remained.

What we recommended

The Department of Regional NSW should ensure that for all future grant programs it:

  1. establishes and follows guidelines that align with relevant good practice guidance 
  2. ensures a communications plan is in place, including the communication of guidelines to potential applicants
  3. ensures staff declare conflicts of interest prior to the commencement of a grants stream, and that these conflicts of interest are recorded and managed
  4. ensures regular monitoring is in place as part of funding deeds 
  5. documents all key decisions and approvals in line with record keeping obligations.

This audit assessed how effectively the Department of Regional NSW and Resilience NSW administered rounds one and two of the Bushfire Local Economic Recovery (BLER) program.

As noted in this report, Resilience NSW was involved in the set-up and ongoing administration and monitoring of the BLER program. During the audited period, Resilience NSW was tasked with working with the Department of Regional NSW to create program objectives, guidelines and criteria. Their role also involved liaising with the Commonwealth Government, which provided co-funding for the program. Resilience NSW also had an ongoing role in quality assurance and compliance to ensure agencies administering disaster assistance did so in accordance with relevant guidelines. On 16 December 2022, the NSW Government abolished Resilience NSW.

Our work for this performance audit was completed on 3 November 2022, when we issued the final report to the two audited agencies. The audit report does not make specific recommendations to Resilience NSW. On 24 November 2022, the then Commissioner of Resilience NSW provided a response to the final report, which we include as it is the formal response from the audited entity at the time the audit was conducted.

During the 2019–20 bushfire season, New South Wales experienced 11,774 fire incidents, burning 5.5 million hectares of the state. There were 26 fatalities and 2,476 homes destroyed. The agriculture sector was heavily impacted with 601,858 hectares of pasture damaged.

Due to the widespread impacts of these fires on the state, the NSW and Commonwealth governments committed $4.4 billion toward bushfire response, recovery, and preparedness. This included the establishment of the Bushfire Local Economic Recovery (BLER) program, with $541.8 million committed to support job retention and creation in areas impacted by bushfires. The program also aims to strengthen community resilience and reduce the impact of future natural disasters. The BLER program is co-funded, with the Commonwealth and NSW governments funding 50% each.

The BLER program is comprised of three funding rounds:

  • round one early co-funding, split between
    • Fast-Tracked projects
    • Sector Development Grants (SDG)
  • round two: open round
  • round three: final projects and initiatives.

Resilience NSW was involved in setting up the BLER program and the Department of Regional NSW (the department) is responsible for administering it. The Commonwealth National Recovery and Resilience Agency must also endorse any projects proposed by the NSW Government for funding as part of the funding agreement between the State and Commonwealth governments.

Successful projects under the SDG stream were announced in September 2020 and projects funded through the Fast-Tracked stream were announced in October 2020. Round two (the open round) was administered after these two streams and successful projects were announced in June 2021.

The Department of Premier and Cabinet established the 'Good Practice Guide to Grants Administration' (the Good Practice Guide) in 2010 to assist the NSW Government in ensuring grants administration was performed consistently across all NSW Government grants programs. Compliance with the Good Practice Guide was not compulsory, but provided an outline of best practice covering the entire lifecycle of a grants program. This guide was in place at the time these grants were designed and administered.

The design and delivery of round one of the program occurred quickly, as part of the response to the 2019–20 bushfires, and was responding to a request from the Commonwealth Government for rapid project identification.

The objective of this audit was to assess how effectively the Department of Regional NSW and Resilience NSW administered rounds one and two of the BLER program. Round three was excluded from this audit because it had not been announced at the time of the audit.

We addressed this objective by examining whether the audited agencies:

  • effectively planned administration of the BLER program and established appropriate guidelines
  • implemented an effective assessment process for the BLER program
  • are effectively monitoring implementation of projects and program outcomes.

Conclusion

The Department of Regional NSW did not effectively administer the Fast-Tracked stream of the Bushfire Local Economic Recovery program. The administration process lacked integrity, given it did not have sufficiently detailed guidelines, and the assessment process for projects lacked transparency and consistency.

There were significant gaps in the documentation of decision-making throughout this funding stream. At the request of the Deputy Premier's office, a $1 million threshold was applied, below which projects were not approved for funding. This threshold was applied without a documented reason and was not part of the program guidelines. The department advises that some of the projects excluded through application of the threshold were subsequently funded from other programs.

The department's administration of the Sector Development Grants stream had a detailed and transparent assessment process. That said, conflicts of interest were not effectively managed, and the department did not effectively engage with stakeholders during the grants process.

The department's administration of the open round included a clearly documented, detailed and transparent assessment framework that it followed throughout. The department also implemented probity arrangements in the open round, although some weaknesses in the department's approach to conflicts of interest remained.

Fast-Tracked stream

Following requests from the Commonwealth Government in May and June 2020 to identify projects rapidly and as soon as practical, the department used an expedited process to identify relevant projects that had applied for other grants programs but had not received funding or which were identified as local priority projects. The department developed a set of guidelines for the Fast-Tracked stream based on draft Commonwealth funding criteria, but the department's guidelines lacked sufficient detail to ensure transparent and consistent decision-making. The guidelines also did not contain detailed information on how the assessment and approval processes would work. The department did not implement conflict of interest declarations for staff involved in the assessment process.

The assessment process implemented for the Fast-Tracked stream deviated from the guidelines. For example, the guidelines did not set out a role for the then Deputy Premier or his office in the assessment process, but the Deputy Premier's office played a key role in project selection. At the direction of the Deputy Premier's office, a $1 million minimum threshold, not mentioned in the guidelines, was applied to projects, below which, projects would not be funded. This resulted in a number of shortlisted projects in areas highly impacted by the bushfires, including all shortlisted projects located in Labor Party-held electorates, being excluded without a rationale being documented at the time. The department advised that some of these projects were subsequently funded through other funding streams.

The department's assessment process was inconsistent, poorly documented and lacked transparency. The department initially identified 445 potential projects through consultation with councils and through identifying projects that had been unsuccessful for other grant programs. The department only assessed 164 of these 445 projects for funding against the criteria in the guidelines. The department did not document the rationale for not assessing the remaining 281 projects against the criteria. The department also sought advice from Public Works Advisory (PWA) on whether projects could commence within six months, which was an eligibility criterion for the Fast-Tracked stream. PWA were only asked to assess 25 of the 445 projects, of which 19 were funded through the Fast-Tracked stream. The department also did not consistently follow PWA's advice and funded projects which PWA had advised were unable to commence within six months, which was not in line with the guidelines.

The department monitors 21 of the 22 Fast-Tracked projects on a quarterly basis to ensure projects are on track. Resilience NSW is responsible for the remaining project and does not monitor this on a quarterly basis but has established a project control group that performs a similar function. The agencies advised that this project is being transitioned to the department's management.

Sector Development Grants (SDG)

The department designed and published guidelines for the SDG stream. The guidelines largely align with the Department of Premier and Cabinet's 'Good Practice Guide to Grants Administration', although they could have been strengthened by including more detail on the eligibility of projects and the role of cost benefit analyses in the assessment process. The guidelines included a detailed and transparent assessment process which the department largely followed.

There were gaps in the administration of the SDG stream assessment process. The department did not effectively manage conflicts of interest as it did not ensure all required conflict of interest forms were completed and some forms were completed after the assessment process was finalised. The department also advised that the final version of the conflict of interest register, which contained the declarations for the SDG stream, was lost during a record management system change. The department did not develop guidance for communicating with stakeholders for the SDG stream. Feedback was received from industries which had been excluded from the SDG stream, relaying their concerns, and requesting a broader range of agribusiness sectors be considered for eligibility. A communications plan or strategy could have incorporated guidance on engaging agribusiness stakeholders during the planning stages of the stream, ensuring they were aware of the rationale for the eligible industries selected.

The majority of SDG funding went to areas highly impacted by the bushfires, although some highly impacted areas received less funding than lower impacted areas, and there is no clear reason for this.

The department does not monitor SDG projects on a quarterly basis to ensure that they remain on track but it ensures it has sufficient evidence that milestones have been completed before making funding payments.

Open round

The department designed and implemented a clearly documented and detailed assessment process for the open round. There were some areas where the process could have been improved, for example, the published guidelines did not set out the role of the former Deputy Premier or include reference to consultation with members of Parliament (MP) as part of the process, despite the fact that MPs were consulted as part of this round.

The department improved its management of conflicts of interest compared to the Fast-Tracked and SDG streams by maintaining a conflict of interest register, though not all conflict of interest declarations were collected. The department also developed a communications plan which led to improvements in stakeholder engagement.

One of the purposes of the open round was to distribute funding to local government areas (LGA) which did not receive funding through the Fast-Tracked stream. This intention was not outlined in the guidelines for this funding stream. The majority of funding from the open round went to LGAs which had been highly impacted by the bushfires.

The department monitors the open round projects on a quarterly basis to ensure that they are on track.

1. Recommendations

To promote integrity and transparency, the Department of Regional NSW should ensure that for all future grant programs it:

  1. establishes and follows guidelines that align with relevant good practice guidance including accountabilities, key assessment steps and clear assessment criteria
  2. ensures a communications plan is in place, including the communication of guidelines to potential applicants
  3. ensures staff declare conflicts of interest prior to the commencement of a grants stream, and that these conflicts of interest are recorded and managed
  4. ensures regular monitoring is in place as part of funding deeds
  5. documents all key decisions and approvals in line with record keeping obligations.

Stage one of the BLER program consisted of early co-funded projects valued at a total of $180 million. This included 22 Fast-Tracked priority projects valued at a total of $107.8 million. The purpose of these projects was to deliver immediate and significant economic impacts to high and moderate bushfire-impacted areas.

A timeline of key dates may be found at Exhibit 5.

Fifty-two projects worth a total of $73.2 million were funded through the SDG stream. One grantee withdrew their project from the stream in early 2021, leaving a total of 51 projects (of which 49 are co-funded with the Commonwealth Government).

A timeline of key dates may be found at Exhibit 9.

The department distributed $283 million to 195 successful projects as part of the open round of the BLER program.

A timeline of key dates may be found at Exhibit 11.

The department entered into funding deeds with successful applicants

The Good Practice Guide advises that the agency administering a grant should enter into a formal agreement with each grant recipient which sets out the arrangements under which a grant is provided, received, managed and acquitted. Across all three streams, the department sent out a letter of offer to successful project managers to let them know that they had been successful in receiving funding, and then entered into funding deeds with grantees. The one exception was the project that RNSW managed, discussed below.

The reviewed funding deeds were signed by department staff with the appropriate level of delegation. They contained an appropriate level of information and key clauses that would allow the department to monitor the progress of the grant to ensure its completion as agreed with the grantee. The reviewed funding deeds contained key information, including:

  • total value of the grant
  • key deliverables at each milestone
  • expected completion date of both the overall project and each milestone
  • reporting requirements, including provisions to allow the department to request relevant information
  • variation procedures.

The department only makes payments after confirming that milestones have been reached

The department has provided payments to grantees only after they could demonstrate that they had completed the agreed milestone. To ensure each milestone has been completed, the department requires grantees to provide evidence that they have fulfilled the milestone. Types of evidence provided includes photographs and invoices. Where the grantee provides insufficient evidence to the department, the department follows-up with the grantee to ensure that enough information is provided to justify the milestone payment.

The department also plans to undertake site visits of projects at select milestones and at the completion of most projects. The department has undertaken a risk assessment of each SDG and open round project, and uses this risk assessment to determine the number of milestones for the project, as well as the number of site visits that the department will undertake. Fast-Tracked projects all had PWA providing either project management or assurance and as such oversight is being provided through that mechanism. The milestones and site visits at each level of risk can be seen in Exhibit 15 for SDG and Exhibit 16 for open round.

Exhibit 15: Milestones and site visits for each level of risk - SDG
Risk rating Milestones Site visits
Low Two Zero
Medium Three One
High Four Two
Source: Department of Regional NSW.
 
Exhibit 16: Milestones and site visits for each level of risk - open round
Risk rating Milestones Site visits
Low Three One
Medium Four Two
High Five Three
 Source: Department of Regional NSW.

The department does not monitor quarterly progress for SDG grants

As part of the LER framework, the department reports to the Commonwealth every quarter on the status and financials of each project, including whether there are any risks to project delivery and the mitigations in place for those risks. For projects funded through the Fast-Tracked stream and the open round, the department collects quarterly progress reports from the grantees. These progress reports allow the department to determine if there are project risks, which can then be reported to the Commonwealth. The progress reports also allow the department to determine if a milestone is likely to be met within the next quarter or whether a project variation may be needed.

While the department monitors projects funded through the Fast-Tracked stream and the open round on a quarterly basis, there is no quarterly monitoring of progress for projects funded through the SDG stream. The SDG funding deeds do not include a provision to require quarterly reporting to the department. The department only collects progress reports from grantees when the grantee reports that it has completed a milestone. Quarterly monitoring of the SDG stream would allow the department to determine if projects require corrective action.

Resilience NSW is not collecting quarterly reports for the Fast-Tracked grant it is responsible for administering

One of the projects funded through the Fast-Tracked stream was the rebuilding of three local halls across two LGAs, for a total value of $3 million. RNSW is responsible for managing this grant and entered into funding deeds with the relevant councils. It is not documented why RNSW is responsible for these funding deeds rather than the department, which is the signatory for all of the other Fast-Tracked stream funding deeds. RNSW advised it was due to the responsible RNSW Director having a strong working relationship with the relevant councils.

The funding deeds which RNSW signed with the relevant councils set out a requirement that the councils would report on this project to RNSW every quarter. The second milestone of each of these projects involved the submission of a quarterly report. However, RNSW was unable to provide evidence that it carried out this monitoring of the project. At the time of the audit, no second milestone payment had been made. Undertaking quarterly monitoring would provide RNSW with assurance that the money is being expended for the proper purpose and whether the projects will be completed by the target date.

RNSW and the relevant councils developed project control groups for each project, which allows it to monitor the implementation of the projects. PWA is also represented on these project control groups and provides an advisory role in the implementation of the projects.

RNSW and the department advised that responsibility for this project will be transitioned to the department and it will be monitored on a quarterly basis, in line with the other Fast-Tracked projects.

The department has a consistent approach to validating variations

The department's funding deeds with grantees allow for the variation of contracts at the department's discretion after the grantee has written to the department. It is important for the department to consider the impact of any project variation request on the overall program objectives, because a project which costs more than was originally planned or which takes additional time may put at risk the objectives of the BLER program. To ensure that requests for variation are handled consistently and appropriately, the department's Grants Management Office (GMO) has developed a process document which applies to variation requests across the BLER program.

For the grants reviewed as part of this audit, the GMO applied this variation process consistently and has documented the outcomes. Larger variations are reviewed at a higher level of delegation and sign-off. To determine whether a variation is accepted, the GMO considers the following factors:

  • consistency with BLER program objectives
  • delivery within the timeframes of the BLER program
  • eligibility under the BLER program guidelines
  • financial viability to deliver within the requested budget.

The department is preparing multiple evaluations, but it has delayed its process evaluation

When developing round one of the BLER program, the department developed an evaluation plan. A total of $1.1 million has been reserved for conducting process, outcome, and economic evaluations of the BLER program and two other bushfire recovery grant programs.

To assist with evaluating program outcomes and economic impact, the department is planning a post-completion survey in 2023–24. This timeline will allow most projects to be completed and enough time for project outcomes to be realised. The department advised that the data collected through this survey would allow the department to determine whether the BLER program has achieved its objectives, as it includes information such as the number of jobs created through each project.

The process evaluation was initially planned for March to June 2021. This would have aligned with the announcement of the open round funding and would have allowed for the learnings from rounds one and two of the BLER program to be applied to the development of round three. However, the department did not conduct this evaluation in a timely way. The department advised that this was because funding deed negotiations were still ongoing, and the department was waiting for 50% of funding deeds to be signed. Given this, the department was not in a position to commence its process evaluation. In December 2021, the department revised its evaluation plan and advised that it commenced its process evaluation in April 2022. It is unlikely that this will allow time for the department to apply learnings to round three, which is currently underway.

Appendix one – Responses from agencies

Appendix two – BLER program distribution

Appendix three – About the audit

Appendix four – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #373 - released 2 February 2023

Published

Actions for Facilitating and administering Aboriginal land claim processes

Facilitating and administering Aboriginal land claim processes

Planning
Environment
Industry
Local Government
Premier and Cabinet
Whole of Government
Cross-agency collaboration
Compliance
Management and administration

What the report is about

The Aboriginal Land Rights Act 1983 (NSW) (the Act) provides land rights over certain Crown land for Aboriginal Land Councils in NSW.

If a claim is made over Crown land (land owned and managed by government) and meets other criteria under the Act, ownership of that land is to be transferred to the Aboriginal Land Council.

This process is intended to provide compensation for the dispossession of land from Aboriginal people in NSW. It is a different process to the recognition of native title rights under Commonwealth law.

We examined whether relevant agencies are effectively facilitating and administering Aboriginal land claim processes. The relevant agencies are:

  • Department of Premier and Cabinet (DPC)
  • Department of Planning and Environment (DPE)
  • NSW Aboriginal Land Council (NSWALC).

We consulted with Local Aboriginal Land Councils (LALCs) and other Aboriginal community representative groups to hear about their experiences.

What we found

Neither DPC nor DPE have established the resources required for the NSW Government to deliver Aboriginal land claim processes in a coordinated way, and which transparently commits to the requirements and intent of the Act.

Delays in determining land claims result in Aboriginal Land Councils being denied the opportunity to realise their statutory right to certain Crown land. Delays also create risks due to uncertainty around the ownership, use and development of Crown land.

DPC has not established governance arrangements to ensure accountability for outcomes under the Act, and effective risk management.

DPE lacks clear performance measures for the timely and transparent delivery of its claim assessment functions. DPE also lacks a well-defined framework for prioritising assessments.

LALCs have concerns about delays, and lack of transparency in the process.

Reviews since at least 2014 have recommended actions to address numerous issues and improve outcomes, but limited progress has been made.

The database used by DPC (Office of the Registrar) for the statutory register of land claims has not been upgraded or fully validated since the 1990s.

In 2020, DPE identified the transfer of claimable Crown land to LALCs to enable economic and cultural outcomes as a strategic priority. DPE has some activities underway to do this, and to improve how it engages with Aboriginal Land Councils – but DPE still lacks a clear, resourced strategy to process over 38,000 undetermined claims within a reasonable time.

What we recommended

In summary:

  • DPC should lead strategic governance to oversee a resourced, coordinated program that is accountable for delivering Aboriginal land claim processes
  • DPE should implement a resourced, ten-year plan that increases the rate of claim processing, and includes an initial focus on land grants
  • DPE and DPC should jointly establish operational arrangements to deliver a coordinated interagency program for land claim processes
  • DPC should plan an interagency, land claim spatial information system, and the Office of the Registrar should remediate and upgrade the statutory land claims register
  • DPC and NSWALC should implement an education program (for state agencies and the local government sector) about the Act and its operations
  • DPE should implement a five-year workforce development strategy for its land claim assessment function
  • DPE should finalise updates to its land claim assessment procedures
  • DPE should enhance information sharing with Aboriginal Land Councils to inform their claim making
  • NSWALC should enhance information sharing and other supports to LALCs to inform their claim making and build capacity.

Fast facts

  • 53,800 the number of claims lodged since the Act was introduced in 1983
  • 38,200 the number of claims awaiting DPE assessment and determination (about 70 per cent of all claims lodged)
  • 207 the number of claims granted by DPE in six months to December 2021
  • 120 LALCs, and the NSWALC, have the right to make a claim and have it determined
  • +5 years around 60 per cent of claims have been awaiting determination for more than five years
  • 22 years the time it will take DPE to determine existing claims, based on current targets

The return of land under the Aboriginal Land Rights Act 1983 (NSW) (the Act) is intended to provide compensation for the dispossession of land from Aboriginal people in New South Wales. A claim on Crown land1 made by an Aboriginal Land Council that meets criteria under the Act is to be transferred to the claimant council as freehold title. The 2021 statutory review of the Act recognises the spiritual, social, cultural and economic importance of land to Aboriginal people.

The Minister for Aboriginal Affairs administers the Act, with support from Aboriginal Affairs NSW (AANSW) in the Department of Premier and Cabinet (DPC). AANSW also leads the delivery of Opportunity, Choice, Healing, Responsibility and Empowerment (OCHRE), the NSW Government's plan for Aboriginal affairs, and assists the Minister to implement the National Agreement on Closing the Gap – which includes a target for increasing the area of land covered by Aboriginal and Torres Strait Islander people's legal rights or interests.

The Act gives responsibility for registering land claims to an independent statutory officer, the Registrar of the Aboriginal Land Rights Act (the Registrar), whose functions are supported by the Office of the Registrar (ORALRA) which is resourced by AANSW.2

The Land and Environment Court of New South Wales has stated that there is an implied obligation for land claims to be determined within a reasonable time. The Minister administering the Crown Land Management Act 2016 (NSW) is responsible for determining land claims. This function is supported by the Department of Planning and Environment (DPE),3 whose staff assess and recommend claims for determination based on the criteria under section 36(1) of the Act. There is also a mechanism under the Act for land claims to be negotiated in good faith through an Aboriginal Land Agreement.

The NSW Aboriginal Land Council (NSWALC) is a statutory corporation constituted under the Act with a mandate to provide for the development of land rights for Aboriginal people in NSW, in conjunction with the network of 120 Local Aboriginal Land Councils (LALCs). LALCs are constituted over specific areas to represent Aboriginal communities across NSW. Both NSWALC and LALCs can make land claims.

DPC and DPE are responsible for governance and, in partnership with NSWALC, operational and information-sharing activities that are required to coordinate Aboriginal land claim processes. LALCs, statutory officers, government agencies, local councils, and other parties need to be engaged so that these processes are coordinated effectively and managed in a way that is consistent with the intent of the Act, and other legislative requirements.

The first land claim was lodged in 1983. The number of undetermined land claims has increased over time, and at 31 December 2021 DPE data shows 38,257 undetermined claims.

The issue of undetermined land claims has been publicly reported by the Audit Office since 2007. Recommendations to agencies to better facilitate processes and improve how functions are administered have been made in multiple reviews, including two Parliamentary inquiries in 2016.

The objective of this audit was to assess whether relevant agencies are effectively facilitating and administering Aboriginal land claim processes. In making this assessment, we considered whether:

  • agencies (DPE, DPC (AANSW and ORALRA) and NSWALC) coordinate information and activities to effectively facilitate Aboriginal land claim processes
  • agencies (DPE and DPC (ORALRA)) are effectively administering their roles in the Aboriginal land claim process.

We consulted with LALCs to hear about their experiences and priorities with respect to Aboriginal land claim processes and related outcomes. We have aimed to incorporate their insights into our understanding of their expectations of government with respect to delivering requirements, facilitating processes, and identifying opportunities for improved outcomes. 

Conclusion

The Department of Premier and Cabinet (DPC) and the Department of Planning and Environment (DPE) are not effectively facilitating or administering Aboriginal land claim processes. Neither agency has established the resources required for the NSW Government to operate a coordinated program of activities to deliver land claim processes in a way that transparently commits to the requirements and intent of the Aboriginal Land Rights Act 1983 (NSW) (the Act). Arrangements to engage the NSW Aboriginal Land Council (NSWALC) in these activities have not been clearly defined.

There are more than 38,000 undetermined land claims that cover approximately 1.12 million hectares of Crown land. As such, DPE has not been meeting its statutory requirement to determine land claims nor its obligation to do so within a reasonable time. Over 60 per cent of these claims were lodged with the Registrar of the Aboriginal Land Rights Act, for DPE to determine, more than five years ago.

DPE’s Aboriginal Outcomes Strategy 2020–23 identifies transferring claimable Crown land to Local Aboriginal Land Councils (LALCs) as a priority to enable economic and cultural outcomes. Since mid-2020 DPE has largely focused on supporting LALCs to identify priority land claims for assessment and on negotiating Aboriginal Land Agreements. This work may support the compensatory intent of the Act but is in its early stages and is unlikely to increase the pace at which land claims are determined. Based on current targets, it will take DPE around 22 years to process existing undetermined land claims.

Delays in processing land claims result in Aboriginal Land Councils being denied the opportunity to realise their statutory right to certain Crown land in NSW. The intent of the Act to provide compensation to Aboriginal people for the dispossession of land has been significantly constrained over time.

Since 2014, numerous reviews have made recommendations to agencies to address systemic issues, improve processes, and enhance outcomes: but DPC and DPE have made limited progress with implementing these. Awareness of the intent and operations of the Act was often poor among staff from some State government agencies and local government representatives we interviewed for the audit.

DPC has not established culturally informed, interagency governance to effectively oversee Aboriginal land claim processes – and ensure accountability for outcomes consistent with the intent of the Act, informed by the expectations of the NSWALC and LALCs. Such governance has not existed since at least 2017 (the audited period) and we have not seen evidence earlier. DPE still does not have performance indicators for its land claim assessment function that are based on a clear analysis of resources, that demonstrate alignment to defined outcomes, and which are reported routinely to key stakeholders, including NSWALC and LALCs.

LALCs have raised strong concerns during our consultations, describing delays in the land claim process and the number of undetermined land claims as disrespectful. LALCs have also noted a lack of transparency in, and opportunity to engage with, Aboriginal land claim processes. DPE’s role in assessing Aboriginal land claims, and identifying opportunities for Aboriginal Land Agreements, requires specific expertise, evidence gathering and an understanding of the complex interaction between the Act and other legislative frameworks, including the Native Title Act 1993 (Cth) and the Crown Land Management Act 2016 (NSW). In mid-2020, DPE created an Aboriginal Land Strategy Directorate within its Crown lands division, increased staffing in land claim assessment functions, and set a target to increase the number of land claims to be granted in 2021–22. In the six months to December 2021, DPE granted more land claims (207 claims) than in most years prior. DPE has also assisted some LALCs to identify priority land claims for assessment.

But the overall number of claims processed per year remains well below the historical (five-year) average number of claims lodged (2,506 claims). As such, DPE has not yet established an appropriately resourced workforce to assess the large number of undetermined land claims and engage effectively with Aboriginal Land Councils and other parties in the process. There also are notable gaps in DPE’s procedures that impact the transparency of the process, especially with respect to timeframes and the prioritisation of land claims for assessment.

DPC (the Office of the Registrar of the Aboriginal Land Rights Act, ORALRA) has not secured or applied resources that would assist the Registrar to use discretionary powers, introduced in 2015, not to refer certain land claims to DPE for assessment (those not on Crown land). This could have improved the efficiency and coordination of end-to-end land claim processes.

DPC (ORALRA) is also not effectively managing data and ensuring the functionality of the statutory Register of Aboriginal land claims. This contributes to inefficient coordination with DPE and NSWALC, and creates a risk of inconsistent information sharing with LALCs, government agencies, local councils and other parties. More broadly, responsibilities for sharing information about the location and status of land under claim are not well defined across agencies. These factors contribute to risks to Crown land with an undetermined land claim, which case law has found to establish inchoate property rights for the claimant Aboriginal Land Council.4 It can also lead to uncertainty around the ownership, use and development of Crown land, with financial implications for various parties.


1 Crown land is land that is owned and managed by the NSW Government.
 AANSW and ORALRA were previously part of the Department of Education, before the 1 July 2019 Machinery of Government changes.
 Previously, these functions were undertaken by the Department of Industry (2017–June 2019) and the Department of Planning, Industry and Environment (July 2019 to December 2021). 
 The lodgement of a land claim creates an unformed property interest for the claimant Aboriginal Land Council over the claimed land. This interest will be realised if the Crown Lands Minister determines that the land is claimable.

Since 1983, 53,861 Aboriginal land claims have been lodged with the Registrar.25

The Land and Environment Court of New South Wales has stated there is an implied obligation on the Crown Lands Minister to determine land claims within a reasonable time.26

As at 31 December 2021, DPE has processed less than a third (31 per cent) of these land claims: 14,273 were determined by the Crown Lands Minister (that is, granted or refused, in whole or part) and 2,562 were withdrawn. This amounts to 16,835 claims processed, including the negotiated settlement of 15 claims through three Aboriginal Land Agreements. As a result, DPE reports that approximately 163,900 hectares of Crown land has been granted to Aboriginal Land Councils since 1983 up to 31 December 2021.

There are 38,257 land claims awaiting determination, which cover about 1.12 million hectares of Crown land.

The 2017 report on the statutory review of the Act noted that the land claims ‘backlog’ was one of the ‘Top 5’ priorities identified by LALCs during consultations. The importance of this issue is consistent with findings from our consultations with LALCs in 2021 (see Exhibit 7).

Exhibit 7: LALCs report that delays undermine the compensatory intent of the Act

LALCs raised concerns about delays in the Aboriginal land claim process, including waiting decades for claims to be assessed and years for land to be transferred once granted.

The large number of undetermined claims has been described by LALCs as disrespectful, and as reflecting under-resourcing by governments.

LALCs reported that these delays undermine the compensatory intent of the Act, including by creating uncertainty for their plans to support the social and economic aspirations of their communities.

Source: NSW Audit Office consultation with LALCs.

Delays in delivering on the statutory requirement to determine land claims, and limited use of other mechanisms to process claims in consultation or agreement with NSWALC and LALCs, undermines the beneficial and remedial intent of Aboriginal land rights under the Act. It also:

  • impacts negatively on DPE’s ability to comply with the statutory requirement to determine land claims, because often the older a claim becomes the more difficult it can be to gather the evidence required to assess it
  • creates uncertainty around the ownership, use and development of Crown land, which can have financial impacts on Aboriginal Land Councils, government agencies, local councils and developers.

Risks that arise in the context of undetermined claims are discussed further in section 3.3.


25 According to DPC (ORALRA) data in the ALC Register up to 31 December 2021. DPC (ORALRA) data indicates that the Registrar has refused to refer claims to DPE for assessment under section 36(4A) of the Act in a small number of cases – for example, seven times in 2017 and none since that time.
26 Jerrinja Local Aboriginal Land Council v Minister Administering the Crown Lands Act [2007] NSWLEC 577 at 125. The Court stated, ‘While a reasonable time may vary on a case-by-case basis, a delay of 15 to 20 years in determining claims does not accord with any idea of reasonableness’.

NSW Treasury describes public sector governance as providing strategic direction, ensuring objectives are achieved, and managing risks and the use of resources responsibly with accountability.

Consistent with the NSW Treasury’s Risk Management Toolkit (TPP-12-03b), governance arrangements for Aboriginal land claim processes should ensure their effective facilitation and administration. That is, arrangements are expected to contribute to and oversee the performance of administrative processes and service delivery towards outcomes, and ensure that legal and policy compliance obligations are met consistent with community expectations of accountability and transparency.

DPC and DPE are responsible for governance and, in partnership with NSWALC, operational and information-sharing activities required to coordinate Aboriginal land claim processes. LALCs, statutory officers, government agencies, local councils, and other parties (such as native title groups and those with an interest in development on Crown land) need to be engaged so that these processes are coordinated effectively with risks managed – consistent with the intent of the Act, and other legislative requirements.

Policy commitments to Aboriginal people and communities made by the NSW Government in the OCHRE Plan and Closing the Gap priority reforms establish an expectation for culturally informed governance.

Exhibit 12: LALCs want their voices to be heard and responded to by government

LALCs expressed a strong desire to have their voices heard so that outcomes in the Aboriginal land claim process are informed by LALC aspirations and consistent with the intent of the Act. The importance of respect and transparency were consistently raised.

The following quotes are from our consultations with LALCs during this audit which illustrate the inherent cultural value of land being returned, as well as the importance of its social and economic value and potential.

There’s batches of land in and around town. This land is significant…We want to get the land activated to encourage economic development, and promote the community…our job is to step up to create infrastructure, employment, maintenance and services and lead by example.

One of the best things we were able to do is develop a long term 20-year plan and where Crown Land could directly see where land was transferred to us and it was going to things like education, housing, health and other social programs…

There has been a claim lodged on a parcel of land that has long lasting cultural significance, a place that is very special to the Aboriginal community members and holds a lot of history. If the claim lodged was successful this land would be used to strengthen the cultural knowledge of the local youth, through placing signage that depicts stories that have been passed down by the Elders, cultural talks and tours and school group visits. This land, although not large in size, has a significant number of cultural trees and artefacts. Aboriginal families and members of the LALC that have lived in our town are very protective of the site and others surrounding it, respecting the importance of the cultural history of the site. There is one, which is a cultural one. We received a land claim that contained a cultural site. This is the high point: we were given back lands that contained rock engravings, carvings. A real diamond for us, especially as an urban based land council.

At the heart of the ALRA is the ability to claim Crown Land…The slow determination of claims gets in the way of us doing what we want to do, which is focus on our communities and address our real needs which are about health, wellbeing and culture. If we could realise these rights, we can address all sorts of socio-economic needs. We would become an economic benefit to the state…If it was operating well there could be more caring for Country too.

Note: Permission has been granted by LALC interviewees to use these quotes in this context.
Source: Excerpts from NSW Audit Office interviews with LALC representatives, facilitated by Indigenous consultants.

The Crown Lands Minister, supported by DPE, is required to determine whether Aboriginal land claims meet the criteria to be ‘claimable Crown lands’ under section 36(1) of the Act. DPE staff within its Crown Lands division are responsible for assessing land claims and preparing recommendation briefs to the Crown Lands Minister, or their delegate, on determination outcomes. That is, on whether to grant or refuse the claim.38 DPE staff also make decisions about which land claims within the large number of undetermined claims should be processed first.

 

Appendix one – Response from agencies

Appendix two – About the audit

Appendix three – Performance auditing

Banner image used with permission.
Title: Forces of Nature
Artist: Lee Hampton – Koori Kicks Art
Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #365 - released 28 April 2022.

Published

Actions for Fast-tracked Assessment Program

Fast-tracked Assessment Program

Planning
Industry
Environment
Compliance
Internal controls and governance
Management and administration
Service delivery

What the report is about

This report examines the effectiveness of the Fast-tracked Assessment Program, administered by the Department of Planning, Industry and Environment (DPIE) between April 2020 and October 2020. 

The program aimed to support the construction industry during the COVID-19 crisis by accelerating the final assessment stages for planning proposals and development applications. 

DPIE selected projects and planning proposals for fast tracked assessment that demonstrated the potential to:

  • deliver jobs
  • progress to the next stage of development within six months of determination
  • deliver public benefit.

The audit assessed whether the Fast-tracked Assessment Program achieved its objectives while complying with planning controls.

What we found

Through tranches three to six of the program, DPIE successfully accelerated the final stages of 53 assessments. DPIE reported that 89 per cent of these proceeded to the next stage of development within six months.

Assessment of projects and planning proposals was compliant with legislation and other requirements. However, the audit found gaps in DPIE's management of conflicts of interest.

DPIE has not evaluated or costed the program and is not able to demonstrate the extent to which it provided support to the construction industry during COVID-19. 

Aspects of the program have been incorporated into longer term reforms to create a new level of transparency over the progress and status of planning assessments. 

What we recommended

DPIE should:

  • strengthen controls over conflicts of interest 
  • evaluate the Fast-tracked Assessment Program.

Fast facts

Construction industry support 
  • The program aimed at providing immediate support to the construction industry during the COVID-19 crisis
59 fast-tracked projects 
  • 59 projects and 42 planning proposals projects were assessed in six tranches
89% of all fast-tracked assessments in tranches three to six progressed to the next stage of the planning process within six months of determination

In April 2020, the Department of Planning, Industry and Environment (DPIE) introduced programs aimed at providing immediate support to the construction industry during the COVID-19 crisis. One of these was the Fast-tracked Assessment Program. This program identified planning proposals and development applications (DAs), across six tranches, that were partially-assessed and could be accelerated to determination.

In accordance with the program objectives, the planning proposals and DAs selected for fast-tracked assessment had to:

  • deliver jobs – particularly in the construction industry
  • be capable of progressing to the next stage of development within six months of determination
  • deliver public benefit.

At the same time, the Fast-tracked Assessment Program was to lay a foundation for future reform of the planning system by piloting changes in the assessment process that could be adopted in the medium to long term.

This audit assessed whether the Fast-tracked Assessment Program achieved its objectives while complying with planning controls. The audit focused on tranches three to six of the program, which were determined between July 2020 and October 2020. The rationale for focusing on these four tranches was that the program design had been slightly modified after the first two tranches to address identified risks.

Conclusion

Through tranches three to six of the Fast-tracked Assessment Program, DPIE successfully accelerated the final stages of 53 assessments. DPIE’s internal monitoring indicates that 31 DAs and 16 planning proposals selected in these tranches proceeded to the next stage of development within six months of determination. DPIE achieved this while also successfully managing the risk of non-compliance with planning controls arising from the accelerated process. While DPIE has incorporated components of the Fast-tracked Assessment Program into other longer-term reforms, it has not evaluated the program and is not able to demonstrate the extent to which the program provided support to the construction industry during COVID-19.

Between April and October 2020, DPIE adopted a case management approach to accelerate the final stages of assessment for 42 planning proposals and 59 DAs in six tranches. Tranches three to six were the focus of this audit and included 22 planning proposals and 31 DAs. Applicants involved in the program were expected to progress their projects to the next stage of development within six months of determination. While DPIE had no way of compelling applicants to do this and relied on non-binding commitments obtained from applicants, DPIE’s internal monitoring indicates that 47 of the 53 applicants selected in tranches three to six honoured this commitment.

Fast-tracked assessment only applied to the final stages of assessment and required DPIE staff and other stakeholders to work towards a determination deadline. DPIE effectively used a case management approach to manage the risk that the accelerated timeframe could result in planning controls not being fully compliant with legislation. There is some room for improvement in the process, as four of 28 staff assessing planning proposals and DAs had not lodged current conflict of interest declarations.

Based on the results of and learnings from the Fast-tracked Assessment Program, DPIE has incorporated some elements of the program into other longer-term reforms. There is now increased transparency about when applicants can expect to receive a planning determination and DPIE has also introduced a case management approach for strategic and high priority planning applications. Applicants benefiting from case-managed assessment are now required to commit to a formal service charter that specifies the obligations of both DPIE and the applicant.

DPIE has not evaluated the Fast-tracked Assessment Program to understand the costs and benefits of the program, nor which aspects of the program were most effective as a basis for future reform.

Appendix one – Response from agency

Appendix two – Planning determination pathways

Appendix three – About the audit

Appendix four – Performance auditing

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #354 - released (27 July 2021).

Planned

Actions for Water management and regulation

Water management and regulation

Planning
Environment
Compliance
Fraud
Internal controls and governance
Management and administration
Regulation
Service delivery

Water regulation aims to achieve sustainable environmental, economic and social outcomes from the management of water resources, consistent with the Water Management Act 2000. Following recommendations from reviews into water theft, reforms were made to strengthen water regulation, compliance and enforcement – including the establishment of the Natural Resources Access Regulator (NRAR) in 2018. The Department of Planning and Environment shares responsibility for issuing water access licences and approvals with the state-owned corporation, WaterNSW.

This audit could assess how effectively the Department, WaterNSW and NRAR are undertaking relevant planning, licensing and regulatory functions to ensure secure, sustainable and transparent water sharing in New South Wales. This topic could also consider how effectively the Department has implemented reforms to enhance water metering technology and rules, and the efficacy of NRAR’s activities to support this program.

Published

Actions for WestConnex: changes since 2014

WestConnex: changes since 2014

Transport
Compliance
Infrastructure
Internal controls and governance
Management and administration
Project management
Risk

What the report is about

The report examined whether Transport for NSW (TfNSW) and Infrastructure NSW (INSW) effectively assessed and justified major scope changes to the WestConnex project since 2014.

What we found

NSW Government decisions to fund WestConnex-related projects outside WestConnex's $16.812 billion budget have reduced transparency and understate the full cost of WestConnex.

The NSW Government's decision to separate Sydney Gateway from WestConnex has reduced transparency over the cost of the road component of Sydney Gateway. $1.76 billion of the cost to complete Sydney Gateway is funded outside the WestConnex budget.

Network integration costs, currently estimated at $2.3 billion, are also funded outside the WestConnex budget. Many of these costs are directly attributable to WestConnex and ought to be included in the reported budget.

The Parramatta Road Urban Amenity Improvement Program, costing $198 million, should also be included as part of the WestConnex reported budget.

Decisions to exclude or remove these elements from WestConnex without justification have seen $4.26 billion of projects funded outside the $16.8 billion budget.

Positively, robust analysis was used to develop and incorporate design improvements into the 2015 WestConnex Updated Strategic Business Case.

The separate components of WestConnex underwent all required assurance reviews. However, the NSW Government's assurance framework does not require ongoing ‘whole-of-program’ assurance for large and complex projects like WestConnex. The absence of a holistic review of WestConnex allows for some costs and benefits to avoid scrutiny.

What we recommended

TfNSW should:

  • review the impact of scope changes on project objectives, costs and benefits for complex infrastructure projects
  • ensure that estimated costs and benefits of works which are reasonably required to meet consent conditions are included in business cases for complex large infrastructure projects
  • establish centralised and project specific record keeping for major infrastructure projects.

Infrastructure NSW should provide transparent whole of program assurance on total costs and benefits when complex projects are split into sub-projects.

Government should consider enhancing public transparency of existing infrastructure assurance processes by requiring that large complex infrastructure programs undergo periodic review at a whole-of-program level.

Fast facts

  • $16.812b 2015 WestConnex business case budget
  • $2.3b current estimated cost of network integration works to enable WestConnex, funded outside the WestConnex budget
  • $1.76b cost to complete Sydney Gateway to enable WestConnex and also funded outside the WestConnex budget
  • $198m Parramatta Road Urban Amenity Improvement Program, originally part of WestConnex but now funded outside the WestConnex budget

WestConnex

WestConnex is a 33 km motorway network that will link the western and south‑western suburbs with the Sydney CBD and the Airport and Port Botany precinct. It will also connect with proposed future motorway links to the north shore, northern beaches, and southern Sydney. The project is being delivered in three stages, with completion scheduled for 2023.

When first conceived by Infrastructure NSW (INSW) in 2012, WestConnex was described as a single integrated concept. In August 2013, government approved a business case for an integrated concept of WestConnex, with an estimated cost of $14.881 billion (in nominal outturn costs). Transport for NSW (TfNSW) is the government agency (sponsor agency) accountable for the delivery of WestConnex in accordance with the business case. In August 2014, the NSW Government established the Sydney Motorway Corporation to fund, deliver and operate WestConnex.

In November 2015, the NSW Government publicly released an updated WestConnex business case with greater detail and design enhancements, which increased the estimated cost to $16.812 billion.

Subsequent to this update, further changes were made to the design, including realignment of the M4 to M5 Link connection to the Western Harbour Tunnel project, an expanded interchange at Rozelle, the deletion of the Camperdown Intersection, and the addition of the Iron Cove Link. The reported budget for WestConnex was not changed as a result of these design updates.

To fund WestConnex, Sydney Motorway Corporation consolidated a concessional loan of $2 billion from the Australian Government, private sector debt and equity funding from the State. The Australian Government also provided a $1.5 billion contribution to the State to partially fund construction of WestConnex.

In August 2018, the NSW Government sold 51 per cent of its stake in Sydney Motorway Corporation for $9.26 billion. At the time of writing, the NSW Government is in the process of selling its remaining 49 per cent stake of Sydney Motorway Corporation.

About this audit

In the course of delivering a complex major infrastructure project, it is reasonable to expect changes to the original design and scope. Changes may occur as the design moves from a high‑level concept to a detailed design for project delivery, as new risks or issues are identified, as demands change, or as other interdependent projects are approved. Changes can also occur in response to potential cost or delivery overruns which arise as a result of planning deficiencies. Where design and scope changes significantly change the project costs and/or expected benefits, the justification for these changes should be robust and transparent.

Following our 2014 performance audit, 'WestConnex: Assurance to the government', the NSW Government established the Infrastructure Investor Assurance Framework (IIAF) to improve accountability and transparency over major projects that are developed, procured, or delivered by government agencies. Under the framework, TfNSW, as project sponsor, is responsible for ensuring the WestConnex project meets all IIAF requirements. These include ensuring the project remains strategically aligned and viable, and benefits are on track. INSW is responsible for coordinating the assurance review process and reporting directly to NSW Cabinet on project delivery against time, budget and risks to project delivery.

The objective of this performance audit is to assess whether TfNSW and INSW effectively assessed and justified major scope changes to the WestConnex project since 2014.

 

Conclusion

Government decisions to separate WestConnex related projects and deliver them outside WestConnex's 2015 business case budget of $16.812 billion has understated the total cost of WestConnex achieving its objectives. The rationale for separating these elements from the WestConnex project scope has not been transparent. Together, these projects represent costs of $4.26 billion funded outside the $16.812 billion WestConnex budget.

Since 2015, the NSW Government has removed several projects from the scope described in the 2015 WestConnex business case, and funded them separately:
  • In mid‑2017, the Sydney Gateway became a separate project outside WestConnex. This project, estimated in 2015 to cost $800 million, now has an estimated cost of $2.56 billion. The project remains partly funded by an $800 million contribution from the $16.812 billion WestConnex budget, with $1.76 billion funded outside the WestConnex budget.
  • In late 2018, the Parramatta Road Urban Amenity Improvement Program became a separate project outside the 2015 WestConnex budget. This project was part of the 2015 WestConnex Business Case and is intended to create urban renewal opportunities around Paramatta Road. It is estimated to cost $198 million.

Work required to integrate WestConnex with existing roads ('network integration') was funded outside the $16.812 billion budget for the November 2015 WestConnex business case. TfNSW is obliged to deliver network integration works to meet the conditions of planning approval for WestConnex. As such, these costs should be included in the WestConnex budget. The current estimated cost of these network integration works is $2.3 billion.

The rationale to exclude or remove each of these elements from the WestConnex project scope has not been transparent, nor supported by robust analysis and justification. These elements are required for WestConnex to achieve its objectives. The additional project costs will also deliver additional benefits not included in the 2015 WestConnex business case. Removing them understates the total cost of achieving the objectives set out in the 2013 and 2015 WestConnex business cases.

WestConnex's complex financing arrangements further reduce transparency on costs.

Transparency over the total cost of WestConnex – including elements funded from other project budgets – is further limited by the project's complex financing arrangements.

Prior to 2018, the Audit Office provided assurance on costs borne and levied by Sydney Motorway Corporation and its controlled entities. Since the NSW Government sold its majority stake in WestConnex in August 2018, the Auditor‑General no longer has the mandate to provide this assurance. Considering this, and the lack of transparency on the cost of projects removed from the WestConnex project scope, there is no transparent or comprehensive view of the total cost to deliver WestConnex – nor of how these cost would be offset by the sale of the government's remaining stake.

There is no 'whole‑of‑program' assurance over the WestConnex program of works. This limits transparency and confidence that WestConnex will meet intended objectives within its budget.

After INSW conducted a gateway review of a draft of the 2015 WestConnex Business Case under the IIAF, the project was broken up into separate components to support staged delivery. Each of these projects, including the Sydney Gateway, as well as the Network Integration Program, underwent the required assurance reviews under the IIAF. INSW also provided monthly progress updates to government. These individual projects are, in themselves, significant in scale and complexity. Addressing them as discrete components for the purposes of the assurance review process is justified and there is no requirement under the IIAF to holistically review projects which together deliver final benefits of the WestConnex program. However, whole‑of‑program review would improve transparency over total costs and benefits.

In 2016, TfNSW revised the design of the M4‑M5 Link and Rozelle to address traffic and integration issues.

TfNSW identified that the concept designs used for the M4‑M5 Link and Rozelle Interchange in the 2015 WestConnex Business Case would not integrate well with surface roads, including the proposed Bays Precinct, and would result in increased traffic on Victoria Road and the ANZAC Bridge. Following a comprehensive review conducted in mid‑2016, TfNSW refined the design of the M4‑M5 Link and Rozelle Interchange to address these limitations without increasing the cost of delivery. TfNSW documented the rationale for the design changes, including how the changes improved on the original design to increase capacity, improve traffic conditions and create more open space.

1. Key findings

Government decisions to fund WestConnex related projects outside of WestConnex's $16.812 billion reported budget have reduced transparency over costs and understate the full cost of WestConnex

In 2015, the work required to integrate WestConnex with existing roads ('network integration') was funded as a separate project with an estimated cost of $1.534 billion outside the 2015 WestConnex budget of $16.812 billion. TfNSW then created the Network Integration Program to respond to the conditions of planning approval for WestConnex. The current estimated cost to deliver all network integration works is $2.3 billion.

Since the 2015 WestConnex Business Case, the NSW Government has removed several elements from the scope of WestConnex and funded them as separate projects, while keeping the published WestConnex budget at an estimated $16.812 billion. Projects removed include:

  • Sydney Gateway, currently costed at $2.56 billion (with an $800 million contribution from WestConnex)
  • Parramatta Road Urban Amenity Improvement Program, costed at $198 million in late 2018 and funded though new funding to the Greater Sydney Commission.

Together, these projects represent costs of $4.26 billion that are not included in the WestConnex budget, but are required for WestConnex to achieve the objectives of the 2013 and 2015 WestConnex Business Cases. The costs of these elements in supporting the objectives of WestConnex is not tracked centrally, and there is no single point of oversight over them. Exhibit 1 compares total WestConnex forecast costs (including related projects) between November 2015 and April 2021.

 

November 2015
($ million)

April 2021
($ million)
WestConnex
Stage 1
Stage 1A (M4 Widening) 497 517
Stage 1B (M4 East) 3,802 3,782
Total 4,299 4,299
Stage 2
King Georges Road Interchange 131 131
New M5 4,335 4,335
Sydney Gateway Contribution 800 800
Total 5,266 5,266
Stage 3
M4‑M5 Link and Rozelle Interchange 7,049 7,049
Urban renewal (Parramatta Road) 198 ‑‑
Urban renewal (Rozelle) ‑‑ 198
Total 7,247 7,247
Total reportable WestConnex 16,812 16,812

Exhibit 1: WestConnex and related projects forecast costs
  November 2015
($ million)
April 2021
($ million)
Related projects
Network integration 1,534 2,300
Urban renewal (Parramatta Road) ‑‑ 198
Sydney Gateway Road Component ‑‑ 1,760
Total 1,534 4,258

Source: AO research.

Many network integration costs are directly attributable to WestConnex and ought to be included in the reported budget for WestConnex

Prior to 2015, the scope of WestConnex included enabling works needed before or during construction, as well as funding for future works to address any adverse traffic outcomes created by WestConnex which become apparent after its opening. These works are also known as network integration works.

When government approved the 2015 WestConnex Business Case, it noted that the project would require $1.534 billion for network integration works to address the impacts of WestConnex on the road network. However, the WestConnex project budget of $16.812 billion did not include funding for network integration works. Instead, Roads and Maritime Services (RMS, now TfNSW) was to fund network integration through its normal budget allocation.

It is important to recognise these costs as part of the total WestConnex project cost because:

  • TfNSW created the Network Integration Program to respond to network traffic and transport elements of the planning conditions of approval for WestConnex granted by the then NSW Department of Planning and Environment under the Environment, Planning and Assessment Act 1979.
  • NSW Treasury guidelines for business cases note that accurate cost estimates include assessment of the financial impact of meeting the conditions of planning approval.
  • Travel time and vehicle operating cost benefits attributed to the WestConnex project in the 2015 WestConnex Business Case assume that some network integration works, then costed at $373 million, were in place.

Refer to Appendix two for more detail on network integration works.

Some of the projects in the WestConnex Network Integration Program provide community and place benefits, such as parklands and cycleways. These benefits have not been attributed to WestConnex. Additionally, some network integration works are likely to deliver additional traffic related benefits to WestConnex. As the Network Integration Program’s primary purpose is to meet the conditions of planning approval for WestConnex, TfNSW should attribute all the costs and benefits of the program to WestConnex.

To September 2021, the total funded cost of the Network Integration Program is approximately $2.077 billion. TfNSW estimates that it will need a further $222 million to complete all expected network integration works.

The NSW Government's decision to separate Sydney Gateway from WestConnex has reduced transparency and accountability for TfNSW's underestimation of the cost of the road component of Sydney Gateway

Sydney Gateway is a high‑capacity connection between the new St Peters Interchange and the Sydney Airport and Port Botany precinct. It includes a road and rail components. The road component was included in the scope of WestConnex in the 2015 WestConnex Business Case. The November 2015 design, which TfNSW costed at $800 million, involved separate roadways from the St Peters Interchange to the International terminal, and to the domestic terminals and Mascot airport precinct.

By October 2016, TfNSW was aware that the $800 million budget for Sydney Gateway was insufficient and revised the forecast cost for the road component to $1.8 billion. The original cost estimate did not sufficiently consider the cost of:

  • constructing a complex design adjacent to the airport precinct
  • obtaining access to land required for the project
  • managing environmental contamination.

On 9 August 2017, the then Minister for WestConnex announced that the Sydney Gateway project was not part of WestConnex.

The 2015 WestConnex Business Case notes that material changes to the WestConnex budget, funding, scope, or timeframe are subject to Cabinet approval processes. It states that, when seeking approval for material changes, the portfolio Minister will make a submission to the relevant Cabinet Committee. Changes in project scope required the approval of the then Cabinet Committee on Infrastructure and should have been endorsed by the WestConnex Interdepartmental Steering Committee.

TfNSW and the NSW Department of Premier and Cabinet (DPC) assert that there is no documentation to support the government’s decision to separate Sydney Gateway from the WestConnex Program, or the WestConnex Interdepartmental Steering Committee's endorsement of a submission to Cabinet seeking approval for the separation.

The established governance processes for major scope changes were not followed in this instance. The lack of transparency regarding government's decision to separate Sydney Gateway from WestConnex also reduces visibility of TfNSW's underestimation of the cost of delivering the road component of Sydney Gateway.

The November 2018 Final Business Case for Sydney Gateway, which was approved by the government, included an estimate of $2.45 billion (nominal outturn cost) for the road component. This estimate included an $800 million contribution from WestConnex. A more recent estimate (late 2020) for this project is $2.56 billion (nominal outturn cost).

The Parramatta Road Urban Amenity Improvement Program should be included as part of the WestConnex budget

A specific objective of the 2015 WestConnex Business Case was the creation of opportunities for urban renewal along and around Parramatta Road. The business case included an allocation of $198 million in the $16.812 billion WestConnex budget for the Parramatta Road Urban Amenity Improvement program, designed to implement aspects of the objective. In November 2018, the NSW Government removed the Parramatta Road Urban Amenity Improvement Program from the WestConnex program of works and reallocated the $198 million (inside the $16.812 billion WestConnex budget) for urban renewal works around the Rozelle Interchange. As part of this decision, government approved new funding of $198 million to the Greater Sydney Commission for the urban amenity program, outside the $16.812 billion WestConnex budget. This understates the cost of WestConnex meeting its objectives by $198 million.

There is no requirement for ongoing ‘whole‑of‑program’ assurance of the WestConnex program of works, including related projects

In August 2015, INSW conducted its first Gateway Review of WestConnex as a program consisting of composite projects. Following that review, TfNSW registered each of the components of WestConnex with INSW as individual projects, rather than keeping WestConnex registered as a program or mega‑project. This is not inconsistent with the IIAF and all WestConnex related projects, including Sydney Gateway and the Network Integration Program, have undergone independent assurance reviews as individual projects under the IIAF.

Once a program like WestConnex is broken down into its composite parts, there is no requirement for the sponsor agency (TfNSW) or INSW to provide independent assurance on the program as a whole until it is completed. This is then done as part of the Gateway review for benefits realisation, which examines whether project benefits are being measured and meet expectations. These individual projects are, in themselves, significant in scale and complexity. While addressing them as discrete components for the purposes of the assurance review process can be justified, the absence of strategic, holistic reviews of WestConnex allows for total costs and benefits to become opaque and avoid scrutiny. Programs of this scale require greater ongoing transparency on total costs and benefits in order to ensure confidence they will meet intended objectives within budget.

There is a lack of public transparency on the total costs and benefits of the WestConnex project

Prior to 2018, the Audit Office provided assurance on costs borne and levied by Sydney Motorway Corporation and its controlled entities. Since the NSW Government sold 51 per cent of its stake in WestConnex in August 2018, the Auditor‑General no longer has the mandate to provide this assurance. The Audit Office is also unable to provide any assurance regarding the performance of tolling concessions.

This means that the total costs of WestConnex, including those levied on road users through tolling, are not reported alongside the full cost of delivering the project. This information, and independent assurance over that information, would provide transparency and context to the outcome of government's sale of its interest in WestConnex.

To enhance the transparency of existing infrastructure assurance processes, government could consider requiring large and complex infrastructure programs to undergo periodic review at a whole‑of‑program level. This could take the form of annual reports to Parliament on the total costs and benefits of selected large and complex projects by the responsible agency. The reports could include an assessment of the cost to government and cost to the community of funding and financing. Independent assurance of the agency report would provide Parliament with greater confidence that infrastructure is delivered economically and providing value for money for the people of NSW.

The Australian National Audit Office provides similar assurance on selected Department of Defence acquisition projects as part of its annual Major Projects Report.

Design enhancements included in the 2015 WestConnex Updated Strategic Business Case were supported by robust analysis

The 2015 WestConnex Business Case contained more detail than the 2013 WestConnex business case. Design enhancements were made as a result of modelling analysis conducted over the two years since the 2013 business case. Enhancements included a full underground link between Kingsgrove and St Peters as part of the New M5 and re‑alignment of the M4‑M5 link tunnel (Stage 3) to include the Rozelle Interchange. The Rozelle Interchange will provide a direct connection to the Anzac Bridge and Victoria Road, and will enable a connection to the proposed Western Harbour Tunnel and Beaches Link. A map and description of these elements can be found at Exhibits 2 and 3 of this report.

In 2016, TfNSW revised the design of the M4‑M5 Link and Rozelle to address traffic and integration issues

As part of preparing the 2015 WestConnex Business Case, TfNSW prepared a Project Definition and Delivery Report (PDDR) for the M4‑M5 Link. This report describes the scope of the project, including a high‑level concept design. TfNSW identified limitations with the proposed design of the M4‑M5 in the PDDR, which it would need to address as the project moved to a detailed design stage. In particular, these limitations included:

  • poor integration with the Bays Precinct masterplan
  • traffic capacity constraints on Victoria Road and Anzac Bridge
  • construction complexity.

Following a comprehensive review in mid‑2016, TfNSW changed the design of the M4‑M5 Link and Rozelle Interchange to address these limitations. These changes included:

  • deletion of the Camperdown intersection to improve traffic conditions on Parramatta Road
  • a fully underground and larger Rozelle Interchange with 10‑hectare dedicated parklands
  • a toll‑free tunnel link from Iron Cove Bridge to Anzac Bridge
  • increasing the lanes in the dual tunnels from three to four each way.

TfNSW documented, but did not publish, the rationale for the design changes, including how the changes addressed the limitations of the previous design while providing increased community benefit through the creation of open space. TfNSW undertook cost comparison studies which estimated that these changes would have a neutral impact on the estimated project cost while achieving the same or improved benefits.

TfNSW's record‑keeping systems for large infrastructure investments negatively impact accountability and transparency

In response to our formal requests for relevant information, made during the conduct of this audit, TfNSW advised that complete and valid records of key decision‑making processes, analysis and advice were unavailable. Additionally, TfNSW often provided information that was incomplete or unverifiable (for instance, unsigned briefing notes). This is not consistent with accepted governance practices and does not comply with the requirements of the State Records Act 1998.

We also requested that TfNSW provide a list of relevant documents held by the Sydney Motorway Corporation (SMC). While TfNSW acknowledged that SMC may hold material relevant to the audit, TfNSW did not have a list or description of these documents. As SMC is now a majority privately held entity, both the Audit Office and TfNSW have limited power to require SMC to provide documentation.

The delivery timeframe for large and complex infrastructure projects such as WestConnex frequently exceeds five years, and some projects can take over a decade to deliver. These projects represent a significant investment of public resources and government agencies should expect independent review and assurance activities such as performance audits. The establishment of dedicated record keeping facilities for major infrastructure projects, such as data rooms, would improve transparency and accountability. This would ensure that the use of public resources is fully auditable in line with public expectations and the requirements of the Government Sector Finance Act 2018, the State Records Act 1998 and the Public Finance and Audit Act 1983.

2. Recommendations

By December 2021, TfNSW should:

1. review the impact of scope changes on project objectives, costs and benefits for complex infrastructure projects

2. when preparing business cases for complex large infrastructure projects, ensure that the estimated costs and benefits of works which are reasonably expected to meet consent conditions are included in the overall project cost and its benefits (as per Treasury guidelines)

3. establish and maintain centralised and project‑specific record keeping, including through dedicated project data rooms, to ensure major infrastructure projects can readily be subject to external oversight and assurance.

By June 2022, INSW should:

4. provide transparent whole‑of‑program assurance on total costs and benefits throughout the project life‑cycle when complex projects are split into sub‑projects.

By June 2022, NSW Government should:

5. consider enhancing the public transparency of existing infrastructure assurance processes by requiring that large complex infrastructure programs undergo periodic review at a whole‑of‑program level. This could take the form of reports to Parliament on the total costs and benefits on selected large and complex projects by the responsible agency, including cost to government and cost to community of funding and financing, as well as an accompanying independent assessment of the agency report.

Following our 2014 performance audit report 'WestConnex: Assurance to the government', the NSW Government established the Infrastructure Investor Assurance Framework (IIAF). INSW is responsible for the development, implementation and administration of the IIAF. The assurance framework involves gateway reviews, health checks, deep dive reviews, and project monitoring and reporting at various stages in the lifecycle of a project. The main aims of the IIAF are to help ensure major infrastructure projects are delivered on time and on budget, and to ensure that reports are regularly monitored by the Cabinet of the NSW Government. The IIAF gateway review process is compulsory for all significant investments and expenditure under the NSW Treasury Gateway Policy.

In accordance with the IIAF, INSW is responsible for the following:

  • providing a dedicated Assurance Team including Gateway Review Managers to coordinate Reviews
  • determining appropriate expert reviewers, and manages scheduling, commissioning and administration of Assurance Review reports. Infrastructure NSW is independent of the Expert Review Team
  • monitoring Tier 1 – High Profile/High Risk projects, Tier 2 and Tier 3 (if required) project performance through independent Assurance Reviews
  • providing independent analysis and advice on key risks and any corrective actions recommended for Tier 1 – High Profile/High Risk, Tier 2 and Tier 3 projects
  • escalating projects to Infrastructure Investor Assurance Committee (IIAC) and Cabinet where projects present ‘red flag issues’ and where corrective action is needed
  • working with delivery agencies to register all capital projects with an estimated cost greater than $10.0 million and ensures they are risk profiled and assigned a risk‑based project tier with an endorsed IIAF Project Registration report
  • preparing forward looking annual Cluster Assurance Plans
  • maintaining and continuously improves the IIAF process
  • reporting to the IIAC, Cabinet and Infrastructure NSW Board
  • regularly report to NSW Treasury on the performance of the IIAF.

In relation to WestConnex, TfNSW is the sponsor agency responsible for meeting relevant IIAF requirements, including:

  • registering and risk profiling projects
  • IIAF gateway, health check, and deep dive assurance reviews
  • regular reporting.

Under the IIAF, it is mandatory for all capital projects valued over $10.0 million to be registered with INSW. Capital projects can be registered either as a program (comprising of a group of related projects or activities) or as a project (which may or may not be part of a program).

According to the IIAF, programs tend to have a lifespan of several years and aim to deliver outcomes and benefits related to an organisation's strategic objectives. Projects tend to have a shorter lifespan, and deal with outputs. Projects can, however, be grouped under a single program if they are similar in nature or if they are aimed at collectively achieving a strategic objective. Complex projects can be delivered in multiple stages, under different contracts, and across different time periods.

The last assurance review of the entire WestConnex program of works as a whole was in 2015

INSW conducted the first IIAF gateway review of WestConnex in August 2015. TfNSW developed a draft WestConnex Updated Strategic Business Case to consolidate the latest analysis on WestConnex, and to confirm that the project remained fit for purpose, economically viable, and financially deliverable. The review followed a recommendation in our 2014 performance audit report that business cases be thoroughly revisited.

During September 2015, INSW conducted additional informal reviews to identify strategic risks associated with public release of the WestConnex business case. Subsequently, INSW gave the Premier of NSW its views on the draft business case, including the following points:

  • The $398 million budget for Sydney Gateway was insufficient to meet the benefits claimed in the business case for a ‘functional’ connection to Sydney Airport and Port Botany. INSW studies indicate a future‑proof solution would require a minimum spend of $755 million.
  • Enabling works for WestConnex estimated at $1.534 billion were excluded from the cost of WestConnex. Significant work remained for RMS to identify mitigation measures to address planning approvals and network performance issues.
  • Enabling works (a Southern Connector), an access ramp and surface road improvements within St Peters were excluded from the draft 2015 business case despite their inclusion in the WestConnex scope in the 2014–15 State Budget.
  • The overall cost of works not funded within the WestConnex budget ranged from $2.011 billion to $2.196 billion. This included the enabling works, access ramp and surface road improvements and the shortfall for Sydney Gateway.

All WestConnex related projects, including Sydney Gateway have undergone independent assurance reviews under the IIAF

Since INSW submitted the first WestConnex progress update report to Cabinet in June 2015, INSW has been reporting monthly on the different stages of the WestConnex Program, including Sydney Gateway, as the projects were registered with INSW as High‑Profile, High‑Risk projects. Separate reporting enabled INSW to report and review each stage with more detailed scrutiny, compared to the reporting and reviewing at a program level.

WestConnex Stage 2 (New M5) underwent both mandatory and non‑mandatory reviews at key points in the project lifecycle. Three mandatory gateway reviews – at Gate 2 (Final business case), Gate 3 (Readiness for market), and Gate 4 (Tender evaluation) – were conducted by TfNSW before the introduction of IIAF. Four non‑mandatory health check reviews and one non‑mandatory deep dive review were conducted after the introduction of the IIAF managed by INSW.

Similarly, WestConnex Stage 3 projects – M4‑M5 link, M4‑M5 Tunnels, and Rozelle Interchange – also underwent mandatory and non‑mandatory reviews at key points in their lifecycle under IIAF.

The M4‑M5 Link had two mandatory gateway reviews and one non‑mandatory health check review under IIAF. These reviews were conducted before Stage 3 was split into two stages, due to major design changes to the Rozelle Interchange and the M4‑M5 tunnels.

The M4‑M5 tunnels had two mandatory gateway reviews (at Gates 3 and 4), one non‑mandatory health check review, and one non‑mandatory deep dive review under IIAF.

Rozelle Interchange also underwent three mandatory gateway reviews at Gate 3 (part 1), Gate 3 (part 2), and Gate 4, two non‑mandatory health check reviews, and one non‑mandatory deep dive review under IIAF.

Since mid‑2017, the Sydney Gateway project has undergone required independent assurance reviews, as well as a number of optional assurance reviews

In November 2016, INSW conducted a mandatory Gate 1 gateway review on a strategic business case for the Sydney Gateway Project. TfNSW did not proceed with this business case. Following the separation of Sydney Gateway from WestConnex in mid‑2017, TfNSW developed a new business case for Sydney Gateway. It has undergone the required Gate 1, Gate 2, and Gate 3 gateway reviews, as well as two non‑mandatory health check reviews, and three non‑mandatory deep dive reviews under IIAF.

Network integration works have undergone all IIAF required assurance reviews

TfNSW completed a strategic business case for the Network Integration Program in August 2020, and INSW completed a gateway review in November 2020. This is despite network integration projects starting as early as 2015, with $645 million having been spent by June 2020. The strategic business case included a prioritisation process for completing remaining works in the program. Prior to November 2020, TfNSW registered individual network integration projects with INSW, and these projects have undergone gateway reviews where required.

The Network Integration Program strategic business case does not include Rozelle interchange network integration works ($353 million) and additional network integration works to settle a contractor claim adjacent to St Peters Interchange ($190 million). These were excluded from the business case on the basis they had already been approved by government, and as such were not subject to the prioritisation elements of the business case. TfNSW has not developed separate business cases for these works, although the scope of the St Peters Interchange works was developed through a negotiated process.

TfNSW did not prepare business cases for some network integration works which have commenced, including the $323 million Campbell Road/Euston Road works

Prior to its development of the August 2020 strategic business case, TfNSW did not prepare business cases for many network integration works that have commenced, and in some instances were completed, before 2019. Significantly, TfNSW did not prepare a business case for the Campbell Road/Euston Road works, which cost $323 million and have been completed.

In 2016, TfNSW’s Business Case Policy requires the creation of business cases for capital projects costing over $1.0 million. At the time of writing this report, TfNSW’s draft policy requires full business cases for capital projects costing $10.0 million or more.

There is no requirement for ongoing ‘whole‑of‑program’ assurance of the WestConnex program of works, including related projects

INSW conducted its first gateway review of WestConnex (as a program, which consisted of composite projects) in August 2015. Following that review, TfNSW registered each of the components of WestConnex with INSW as individual projects, rather than keeping WestConnex registered as a program or complex project. The IIAF allows this to occur.

Separate registration enabled INSW to report and review each stage with more scrutiny compared to whole‑of‑program level review.

Such an approach has merit, considering the individual stages (and components of these stages) are multi‑million dollar works in their own right. Each project has its own timing for gateway reviews at stages such as 'Readiness for Market' and 'Tender Evaluation'.

Once a program such as WestConnex is broken down into its composite parts, there is no requirement for the sponsor agency (TfNSW) or INSW to conduct independent assurance on the program of works as a whole until the whole program is completed as part of the Benefits Realisation (Gate 6) gateway review. The absence of strategic, holistic reviews of projects of the scale and complexity such as WestConnex during their delivery allows for total costs and benefits to become opaque and avoid scrutiny. Projects of this scale require greater ongoing transparency on total costs and benefits in order to ensure confidence they will meet intended objectives within budget.

INSW has advised us that it has prepared a proposal to expand its assurance function to include whole‑of‑program review of inter‑related infrastructure projects.

Appendix one – Responses from agencies

Appendix two – Network integration works

Appendix three – About the audit

Appendix four – Performance auditing

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.